Upload
sterea-marian
View
230
Download
10
Embed Size (px)
DESCRIPTION
wind turbine
Citation preview
8 Rotor lifting
8.1 Simple diagrammatic drawing of rotor lifting process
Place the blade
vertically (tailing
edge upwards)
Ground motor-
driven pitch
changing; pitch
bearing changes
to -90
Screw all the
bolts in blade
-90 assembly
of blade
Install the tooth
belt(6552mm)in
stead of
5130mm
Pitch bearing
changes to
0,for there are
about 11 bolts
near the pitch
motor bracket
we cant put the spanner on
these bolts
Change the
2#,3# blade to
90 and the 1#
blade to -90
Lock the
2#,3#blade,and
replace their
tooth belts to
5130mm
Install rain
blocking ring;
install front end
cover of dome
hoisting of
rotor(2 blades
90,1 blade -
90 )
Disassembly
lifting tools
1# blade:change to 90,lock the
blade,and exchange the tooth belt to
5130mm,then unlock all the blades
Unlock
the
blade
block
Check the belt
frequency
34
Pic34 Diagrammatic Drawing of rotor installation Process of Rotor
8.2 Ground assembly of blade
8.2.1 18 19 20
Preparationsstandard component refer to table18,lifting spreader refer to table19,tools
list refer to table20
18
Table18 Standard Parts Needed in Assembling Blade
No.
name
specification
quantity
Remark
1 Stud bolt M36625-10.9 276pcs
For 3 blades 2 Hex nut M36-10(GB/T 6170-2000) 276pcs
3 Washer 36-300HV (GB/T 97.1-2002) 276pcs
19
Table19 Lifting tools Needed in Assembling Blade
No.
name
specification
quantity
Remark
1
Round sling 18t10m 1pcs For 1# blade
2
Protector of
edge of the
blade
4pcs
3
Protector of
blade tip
3pcs
4
Guide rope
Guide rope(50m)
Short guide rope(100m)
Long guide rope(300m)
2 rolls
2 rolls
2 rolls
5
Hoisting
beam of blade
15T*10m 1pcs
6
eye & eye
webbing sling
8t10m 2pcs
7
Bow shackle G209-S-BW12t-1 1/4'' 5pcs
8
Rotating
ring
VLBG 8t M36 2pcs
20
Table20 tools Needed in Assembling Blade
No.
name
specification
quantity
Remark
1
spanner 55mm 2pcs
2
Adjustable
spanner
45055mm 2pcs
3
hairbrush 2 pcs
4
socket 55mm (long) 1 pcs
5
Hydraulic
wrench
4514N.m
Maximum value 4514Nm 1set
6
sleeper p.s.
7
Solid
lubrication
grease
MOLYKOTE G-Rapid Plus p.s.
8
Washing
liquid
p.s.
9
Lashing belt 3pcs
10 Manual chain
block 5t3m 2pcs
8.2.2 Blade assembly (or named fitting up)
8.2.2.1 Preparation hub
1 90
Determine the area for assembling blade and hub according to site conditions, then
place 90 hub support of rotor to corresponding position with crane and the ground for
placing bracket is required to be compacted and smooth.
1#
Note:for easy to install the slip ring support,the 1# blade must be use as the
trail blade,so when fixing the hub on the assembly support,pay attention to this
point.
1#1#
How to recognise which pitch box is 1#?As the pic below shown,there is a cable
bridge(in red block) on the left side of the cabinet,so its 1# pitch box,and the
blade is 1# blade.
2904M30100-8.8
300N.m
3435
Place the pitch system of hub and transportation tools onto 90 hub support of rotor
with crane and connect them firmly with four bolts M30100-8.8, with the tightening torque
value of 300N.M. Pitch system and bracket can be lifted off the ground by crane and the
orientation of pitch bearing can be adjusted by rotating the hub, thus preventing the blade
from interfering with other objects during fitting up. (refer to Pic34,35).
3
Disassemble lifting tools in pitch system of hub.
4-90
000
Operation pitch system of hub. Change the position of pitch bearing near to -90
(There is a red line scale 0on the pitch bearing flange. The 0 red line is on the horizontal
direction. We need to pitch to change the red 0line near to support of pitch motor.)
a)
Supporting area of hub is required to be solid and smooth.
b)
According to position and yard conditions, adjust the orientation of blade
installation opening of hub dome when the pitch system of hub is lifted off
ground, which will be convenient for assembly of blade and prevent
interference with other objects during assembling blade, meanwhile, make
the orientation of one blade opening fit main wind direction to the greatest
extent and ensure that no barrier is in blade assembly area.
c)
Pay attention to the protection of components when assembling and
disassembling them, avoiding knocking against interior components in pitch
system of hub.
34 90 35
Pic 34 90hub assembly support Pic 35 hub position
8.2.2.2 Blade preparation
1)
First, check whether the thunder record card and variable pitch limit stop are
installed; if not, they should be installed before the fitting up of blade.
2) 36
Install the sensor block.refer to pic36.
3) 280mm1mm
37
38
Screw stud bolt into blade flange which reveals a length of 280mm1mm. The stud
is required to be screwed into manually when it is implanted into blade, strictly
forbidding clamping stud head by motor-driven and hydraulic wrench or pipe
wrench. (refer to Pic37,38)
(MOLYKOTE G-Rapid Plus
Note: the thread of flange part which is screwed into blade is not coated with
solid lubricating grease (MOLYKOTE G-Rapid Plus).
4) 39
Paint the stud bolt with solid lubricating grease (refer to Pic39) and put the required
bolts, washers and nuts near hub for use.
5) 2#3# 300m
1# 100m
Sleeve in the protective belt for rip of blade from rip of blade and tie two guidance
rope.(1#blade:100m;2# and 3#blade:300m).
36 37
Pic36 install the sensor block Pic37 Screwing into Stud Bolt
38 39
Pic38 Measuring the Extending Length of Stud Pic39 Painting Solid Lubricating Grease
8.2.2.3 Blade fitting up
1) 8T*10m
Hoist with 2 cranes, which use two 8T*10m eye&eye slings at lifting position of
blade,direct the crane and maintain lifting tonnage of crane just when the lifting
power can lift the blade.unloading the blade on the ground,then use the beam
to lift the blade to disassemble transport holder of blade, tie a guiding rope to
root parts of blade to coordinate with guiding rope at the rip of blade and
allocate specially-assigned person to pull guiding rope to control the direction of
blade. Direct the stable hoisting of crane to reach pitch flange face of hub.
Note: decide which blade should be connect to the hub based on site
condition,keep the blade same direction with the wind,prevent the blade
from the more stress.
2) 00
40 41
Make the 0 calibration tail at the top of blade align at 0 calibration tail of pitch
bearing by adjusting the rotation of pitch bearing manually. Adjust the crane and
control the direction of blade at the same time to make connecting bolt of blade
pass through flange hole of pitch bearing, thus realizing butt joint. Distinguish
direction when installing spacer and nut, with the flat side facing pitch
bearing.(refer to Pic40,41)
40 41
Pic40 blade fitting up Pic41 align mark
5130mm,
-90 6544mm
Note: Before the pitch operation, the factory hub with a configuration such as a short
tooth belt (tooth belt with a length of only 5130mm, It can not make the blade pitch
to -90 position) you need to replace the tooth belt (tooth belt length about 6544mm).
Long tooth belt replacement when the short tooth belt removed, the tooth belt
tensioners mounted on the long trip on the pitch plate position. Install long tooth belt
and tensioners refer to 8.3.2. Restore the factory configuration toothed belt after the
blade fitting up operations is completed.
3) -90
Remove the blade lock block,pitch to -90position.
4)
50%75%100%
Use hydraulic wrench (lengthened sleeve) to adjust the torque of hydraulic wrench
and fasten flange bolt at the diagonal. Hit the bolt torque by three times with the value
being 50%, 75% and 100% of the required torque value respectively.
-90 11
0
Attention: when torque the bolts near the -90, there are about 11 bolts near the
pitch motor bracket we cant put the spanner on these bolts. We can
pre-tighten them by open spanner,then torque the bolts by pitch the blade
to 0 degree later.
5)
42 2t
Use sleeper to support the fitted-up blade, using soft materials between blade
and vertical bracing to protect the blade.Or use a crane to lift the blade,maintain
2T.refer to Pic42.
6)
Follow the above steps to fit up the second and third blades.
7)
, 43
If the rotor is not hoisted right after being fit up and needs to be put on site,
reliable support must be provided for blade to ensure that the rotor will not be
damaged during placement.(refer to Pic43)
42 43
Pic42 blade support Pic43 the rotor position
8) 90 44 45
Before lifting, change the 2#,3# blades to the position of 90. Lock the locking device
of blade and perform 90 hoisting.refer to Pic44,45.
44 -90 45 90
Pic44 blade -90fitting up Pic45 rotor 90 lock state
Considerations:
Clear up the blade flange and pitch bearing flange and keep the hub inside clean
when operating in it; protect anticorrosive coating with leather or rubber to avoid
damage when hitting moment.
8.3 Assembly installation of blade collar
8.3.1 preparation work
21 22
Table 21
Table21 assembly components and parts
No.
name
specification
quantity
remark
1
blade collar
assembly
3 set
2
Core rivet 18pcs
22
No.
name
specification
quantity
remark
1 lashing belt TMLS058m 3set
2 glue gun
structural adhesive 1pcs
3 hand riveter 1pcs
4 sealant gun
sealant 1pcs
5 angle grinder 1pcs
6 drill M5 1pcs
7 mark pen 1pcs
8 structural
adhesive Plexus MA310 4group
9 sealant SM7108 or MS939 3bottle
10 cutting disk 2disk
8.3.2 Steps forinstallation
1)
Cut open the blade collar, and chamfer and polish the edges with polishing
machine to prevent abrading sling when hoisting.
2
46
Marking-off: clean blade root and bonding face of blade sealing assembly, keep
the bonding face clean and install blade sealing assembly at the blade root,
move blade sealing assembly to make it be close to hairbrush, and then mark on
the blade along the outer edge of blade sealing assembly with marking
pen.(refer to Pic46)
3) Plexus MA310
Install Plexus structural adhesive MA310 into glue gun and install mixing nozzle
according to instructions. The glue solution outgoing first cannot be used; glue
on blade formally till the color of outgoing glue is uniform.
4) 25mm
8mm10mm 47
Gluing: at the position 25mm away from the marking line on blade (middle
position of bonding width), glue continuously to form a closed ring, with the
diameter of adhesive tape being around 8mm~10mm.refer to Pic47.
46 47
Pic46 marking-off Pic47 gluing
1) ()
48 49
1
Pull open blade collar assembly and move it to installation position (above
gluing), cling to hairbrush and press it down tightly; fix and clamp blade collar
assembly with tightener to solidify the glue.Fill any gaps with structural
adhesive.remove the lashing belt after completing the collar installation.
Note:the lashing belt cant be removed in less than 1 hour.
48 49
Pic48 fix the collar with lashing belt Pic49 gluing
6)
50 51
Paint sealant between blade collar assembly and blade (marking-off part); use
fingers stained with cleanser essence water to sleek and press tightly the
sealant.(refer to Pic50 51)
50 51
Pic50 paint sealant Pic51 press tightly the sealant
7 6(525)
52
Connect junction plate at the opening of blade collar assembly with six rebites (525),
with the edges and rivets painted with sealant.refer to Pic52.
52
Pic52 Installing Junction Plate at the Opening of Rain Blocking Rain
8.3.3 technical requirements
a)
The gaps between the collar and the blade should be full of blue.
b) ,
This product belongs to flammable items, please keep it away from flame and spark.
a
Do not tread the sealing assembly of blade collar when painting sealant,
to prevent misplacement and moving of blade collar when bonding glue is not
solidified.
b
When using the drill and angle grinder,avoiding damage the surfae of the
blade or the hub.
c 1518min
The installation should be completed in 15-18min after gluing.
8.4 spinner cap installation
8.4.1 Preparation
23
Table23 installation components and parts
No.
name
specification
quantity
remark
1
Spinner cap 1pcs
2
bolt M10100GB/T 5783-2000 A4-70 15pcs
3
washer 10GB/T 96-2002 A140 30pcs
4
Self-lock
nut
M10 15pcs
24
Table24 installation tools list
No.
Name
specification
quantity
remark
1
sealant gun for sealant 1pcs
2
Open spanner 17mm 2pcs
3
Adjustable
spanner
20024mm 2ps
4 U
U type shacle 1t 2ps
5
Sling belt 1t-3m 1pcs
6
ladder 4m 1pcs
7
sealant SM7108 or MS939 2bottle
8.4.2
1 1t-3m
15 M10
100 40N.m SM7108
MS939 53
Hoist spinner cap with a 1t-3m sling and install it onto the dome; connect nose
cone and the dome with fifteen bolts M10100 with the fastening torque value of
40N.m, then paint the circumference and bolt head with SM7108 or Loctite MS939
sealant.
53
Pic install the spinner cap
a)
b)
Considerations:
a) Do not tread the sealing assembly of blade collar when painting sealant, to prevent
misplacement and moving of blade collar when bonding glue is not solidified. Pay
attention to personal safety as well.
b) Use properly in accordance with the instructions on bottle of locking glue, do not
waste.
8.5 Rotor lifting
8.5.1 Preparation
25
Table25 Standard Parts for Rotor Installation
No. Name Specification Quantity Remark
1 Bolt M36240-10.9 (GB/T 5782-2000) 54
2 Washer 36-300HV (GB/T 1230-2006) 54
26
Table26 Spreader for Rotor Installation
No. Name Specification Quantity Remark
No. Name Specification Quantity Remark
1
Protective
belt 1 for rip of
blade
JF2500.85.027 1
2
Protective
belt 2 for rip of
blade
JF2500.85.026 2
3 Hawser cable 20300m 3
4 round sling 8t-10m 1
5
Protective
clothing at tailing
edge of blade
JF2500.85.020 1
6 Flat sling W04-30t20m (width: 250mm) 2
27
Table27 install tools list
No. Name Specification Quantity Remark
1
Chain block 5t*3m 2pcs
2
Hairbrush 2pcs
3
Electric wrench 800N.m 1set
4
Hydraulic wrench
4514N.m
1set
5 55mm 1pcs
socket
6
Solid lubrication
grease
MOLYKOTE G-Rapid Plus p.s.
8.5.2 Steps for- 90 hoisting of rotor
-90()
Method One: - 90 hoisting of rotor(recommend)
1 23
-90290
According to the location selected two blades installed crane main spreader.
According to the location selected two blades installed crane main spreader, The
blade which Install auxiliary spreader to maintain -90 pitch position, The other
two blades pitch to 90 pitch position, with the pitch locking pin lock.
2 21
20300m54
Install a short protective belt on the rip of blade of the two blades respectively and
fix two guiding ropes of 20 and 300m by protective belt of rip of blade
respectively.refer to Pic54
54
Pic54 Install the protective belt
55 -90
Pic55 auxiliary spreader installation
3 318t*10m
50
55
Install the protective clothing at tailing edge of blade on the third blade and one
sling of 18t-10m on the third blade. Play buckle at end of the sling which in the top
of the protective clothing at tailing edge of blade, the other end hanging on the
crane's hook. Tie a 50m rope at the part of sling buckle.refer to Pic55
4 2W04-3030t-20m)250mm
,500mm
56
Install flat sling W04-30 (30t*20m) at the root of the two blades with the width of
250mm. Notice that the sling should bear at least a space of 500mm from blade
collar for fear of abrading the sling when hoisting. The sling should keep dry in
winter.refer to Pic56.
56
Pic56 install the flat sling
5
80
5758
Cranes are hoisted simultaneously; the main crane goes up slowly while auxiliary
crane cooperates to lean the rotor from level slowly and ensure that the rip of
blade do not contact the ground. After the vertically downward rip of blade is off
ground completely and when the vertically downward blade forms an angle of
about 80, tension the guiding rope of vertically downward blade manually, then
loose the sling of auxiliary crane and unhook the auxiliary crane; hoist the rotor to
the height of hub by main crane.
57 58
Pic57 turn over of the rotor Pic58 rotor fitting up
6
(MOLYKOTE G-Rapid Plus
Make the rotor approach generator slowly, and pull haulage rope to cooperate
with the crane to make flange face of pitch system of hub parallel to cooperating
flange face of generator; paint the bolt with solid lubricating grease (MOLYKOTE
G-Rapid Plus) and screw it in.After finishing the butt joint of rotor, fix the
connecting bolt used in installation pedestal of gap bridge onto flange face of
generator rotor which is just against 1# pitch cabinet when installing connecting
bolt, with the elbow pointing at generator.
7
50%75%100%B1
Screw all bolts into bolt holes with open spanner firstly and then fasten the
moment with hydraulic torque wrench by three times with the value of 50%, 75%,
100% of the required torque value respectively.
Table for Tighten Force of Bolt
No. Location
Quantit
y(inspected
number)
Type and strength grade
of bolt
Wre
nch
(m
m)
Torq
ue value
(N.m
)
Rotor
1 Hub-rotation shaft 54 (6) GB/T 5782-2000
M36240-10.9 55
240
0*
8
After the bolt moment is fastened according to requirements, the crane can be
unhooked and spreaders can be disassembled.
9
Q/JF 2FW2500.4-20102.5MW
When disassembling protective belt for rip of blade, unlock the locking device of
generator rotor firstly and then rotate the blade manually. Refer to document Q/JF
2FW2500.4-2010 Work Standards for Rotor Locking of Goldwind 2.5MW Series
Wind Turbine Generator System for specific steps of unlocking locking device of
generator rotor.
1
2
3
4
5
6
Considerations:
1) The surface of sling should be kept clean and tidy to prevent damage to blade
surface caused by particles on sling surface; strictly forbid twining, folding,
twisting and knotting wide sling. In winter, wide sling should be kept dry to prevent
freezing and slipping; paint with rosin to increase friction if it is slippy.
2) When installing rotor, guiding bar can be chosen to install as required;
the process of hoisting rotor should maintain the hoisting speed of crane constant
and slow, preventing rotor rocking.
3) The bolt can be threaded in manually only after hub flange and rotor flange
are fit tightly and bolt holes are aligned as well. Besides, the thread part of bolt
is required to be painted with solid lubricating grease which is also used between
bolt root and spacer.
4) Operators must wear full body safety clothing and safety rope, safety rope
and reliable fixed.
5) Remove auxiliary spreader, note the speed and demolition demolition, so as
not to damage the leaves.
6) Parts in contact with the spreader of blades to make full protection to
avoid damage to blades in the lifting process.
Operational requirement: during rotor installation, body-safety-belt must be
worn while the safety rope should be fixed at reliable position of nacelle.