8 叶轮吊装 Rotor lifting 8.1 叶轮吊装过程示意图 Simple diagrammatic drawing of rotor lifting process Place the blade vertically (tailing edge upwards) Ground motor- driven pitch changing; pitch bearing changes to -90° Screw all the bolts in blade -90°assembly of blade Install the tooth belt(6552mm)in stead of 5130mm Pitch bearing changes to ,for there are about 11 bolts near the pitch motor bracket we can’t put the spanner on these bolts Change the 2#,3# blade to 90°and the 1# blade to -90° Lock the 2#,3#blade,and replace their tooth belts to 5130mm Install rain blocking ring; install front end cover of dome hoisting of rotor(2 blades 90° ,1 blade - 90°) Disassembly lifting tools 1# blade:change to 90° ,lock the blade,and exchange the tooth belt to 5130mm,then unlock all the blades Unlock the blade block Check the belt frequency 34 叶轮吊装过程示意图 Pic34 Diagrammatic Drawing of rotor installation Process of Rotor 8.2 地面组装叶片 Ground assembly of blade 8.2.1 准备工作(安装需用标准件见表 18,吊具见表 19,工具及耗品见表 20Preparationsstandard component refer to table18,lifting spreader refer to table19,tools list refer to table2018 组装叶片所需标准件 Table18 Standard Parts Needed in Assembling Blade 序号 No. 名称 name 型号 specification 数量 quantity 备注 Remark 1 Stud bolt M36×625-10.9 276pcs For 3 blades 2 Hex nut M36-10(GB/T 6170-2000) 276pcs 3 Washer 36-300HV (GB/T 97.1-2002) 276pcs

Rotor Assembly and Lift

Embed Size (px)

DESCRIPTION

wind turbine

Citation preview

  • 8 Rotor lifting

    8.1 Simple diagrammatic drawing of rotor lifting process

    Place the blade

    vertically (tailing

    edge upwards)

    Ground motor-

    driven pitch

    changing; pitch

    bearing changes

    to -90

    Screw all the

    bolts in blade

    -90 assembly

    of blade

    Install the tooth

    belt(6552mm)in

    stead of

    5130mm

    Pitch bearing

    changes to

    0,for there are

    about 11 bolts

    near the pitch

    motor bracket

    we cant put the spanner on

    these bolts

    Change the

    2#,3# blade to

    90 and the 1#

    blade to -90

    Lock the

    2#,3#blade,and

    replace their

    tooth belts to

    5130mm

    Install rain

    blocking ring;

    install front end

    cover of dome

    hoisting of

    rotor(2 blades

    90,1 blade -

    90 )

    Disassembly

    lifting tools

    1# blade:change to 90,lock the

    blade,and exchange the tooth belt to

    5130mm,then unlock all the blades

    Unlock

    the

    blade

    block

    Check the belt

    frequency

    34

    Pic34 Diagrammatic Drawing of rotor installation Process of Rotor

    8.2 Ground assembly of blade

    8.2.1 18 19 20

    Preparationsstandard component refer to table18,lifting spreader refer to table19,tools

    list refer to table20

    18

    Table18 Standard Parts Needed in Assembling Blade

    No.

    name

    specification

    quantity

    Remark

    1 Stud bolt M36625-10.9 276pcs

    For 3 blades 2 Hex nut M36-10(GB/T 6170-2000) 276pcs

    3 Washer 36-300HV (GB/T 97.1-2002) 276pcs

  • 19

    Table19 Lifting tools Needed in Assembling Blade

    No.

    name

    specification

    quantity

    Remark

    1

    Round sling 18t10m 1pcs For 1# blade

    2

    Protector of

    edge of the

    blade

    4pcs

    3

    Protector of

    blade tip

    3pcs

    4

    Guide rope

    Guide rope(50m)

    Short guide rope(100m)

    Long guide rope(300m)

    2 rolls

    2 rolls

    2 rolls

    5

    Hoisting

    beam of blade

    15T*10m 1pcs

    6

    eye & eye

    webbing sling

    8t10m 2pcs

    7

    Bow shackle G209-S-BW12t-1 1/4'' 5pcs

    8

    Rotating

    ring

    VLBG 8t M36 2pcs

    20

    Table20 tools Needed in Assembling Blade

    No.

    name

    specification

    quantity

    Remark

    1

    spanner 55mm 2pcs

    2

    Adjustable

    spanner

    45055mm 2pcs

    3

    hairbrush 2 pcs

    4

    socket 55mm (long) 1 pcs

    5

    Hydraulic

    wrench

    4514N.m

    Maximum value 4514Nm 1set

  • 6

    sleeper p.s.

    7

    Solid

    lubrication

    grease

    MOLYKOTE G-Rapid Plus p.s.

    8

    Washing

    liquid

    p.s.

    9

    Lashing belt 3pcs

    10 Manual chain

    block 5t3m 2pcs

    8.2.2 Blade assembly (or named fitting up)

    8.2.2.1 Preparation hub

    1 90

    Determine the area for assembling blade and hub according to site conditions, then

    place 90 hub support of rotor to corresponding position with crane and the ground for

    placing bracket is required to be compacted and smooth.

    1#

    Note:for easy to install the slip ring support,the 1# blade must be use as the

    trail blade,so when fixing the hub on the assembly support,pay attention to this

    point.

    1#1#

    How to recognise which pitch box is 1#?As the pic below shown,there is a cable

    bridge(in red block) on the left side of the cabinet,so its 1# pitch box,and the

    blade is 1# blade.

  • 2904M30100-8.8

    300N.m

    3435

    Place the pitch system of hub and transportation tools onto 90 hub support of rotor

    with crane and connect them firmly with four bolts M30100-8.8, with the tightening torque

    value of 300N.M. Pitch system and bracket can be lifted off the ground by crane and the

    orientation of pitch bearing can be adjusted by rotating the hub, thus preventing the blade

    from interfering with other objects during fitting up. (refer to Pic34,35).

    3

    Disassemble lifting tools in pitch system of hub.

    4-90

    000

    Operation pitch system of hub. Change the position of pitch bearing near to -90

    (There is a red line scale 0on the pitch bearing flange. The 0 red line is on the horizontal

    direction. We need to pitch to change the red 0line near to support of pitch motor.)

    a)

    Supporting area of hub is required to be solid and smooth.

    b)

    According to position and yard conditions, adjust the orientation of blade

    installation opening of hub dome when the pitch system of hub is lifted off

    ground, which will be convenient for assembly of blade and prevent

    interference with other objects during assembling blade, meanwhile, make

    the orientation of one blade opening fit main wind direction to the greatest

    extent and ensure that no barrier is in blade assembly area.

    c)

    Pay attention to the protection of components when assembling and

    disassembling them, avoiding knocking against interior components in pitch

    system of hub.

  • 34 90 35

    Pic 34 90hub assembly support Pic 35 hub position

    8.2.2.2 Blade preparation

    1)

    First, check whether the thunder record card and variable pitch limit stop are

    installed; if not, they should be installed before the fitting up of blade.

    2) 36

    Install the sensor block.refer to pic36.

    3) 280mm1mm

    37

    38

    Screw stud bolt into blade flange which reveals a length of 280mm1mm. The stud

    is required to be screwed into manually when it is implanted into blade, strictly

    forbidding clamping stud head by motor-driven and hydraulic wrench or pipe

    wrench. (refer to Pic37,38)

    (MOLYKOTE G-Rapid Plus

    Note: the thread of flange part which is screwed into blade is not coated with

    solid lubricating grease (MOLYKOTE G-Rapid Plus).

    4) 39

    Paint the stud bolt with solid lubricating grease (refer to Pic39) and put the required

    bolts, washers and nuts near hub for use.

    5) 2#3# 300m

    1# 100m

    Sleeve in the protective belt for rip of blade from rip of blade and tie two guidance

    rope.(1#blade:100m;2# and 3#blade:300m).

    36 37

    Pic36 install the sensor block Pic37 Screwing into Stud Bolt

  • 38 39

    Pic38 Measuring the Extending Length of Stud Pic39 Painting Solid Lubricating Grease

    8.2.2.3 Blade fitting up

    1) 8T*10m

    Hoist with 2 cranes, which use two 8T*10m eye&eye slings at lifting position of

    blade,direct the crane and maintain lifting tonnage of crane just when the lifting

    power can lift the blade.unloading the blade on the ground,then use the beam

    to lift the blade to disassemble transport holder of blade, tie a guiding rope to

    root parts of blade to coordinate with guiding rope at the rip of blade and

    allocate specially-assigned person to pull guiding rope to control the direction of

    blade. Direct the stable hoisting of crane to reach pitch flange face of hub.

    Note: decide which blade should be connect to the hub based on site

    condition,keep the blade same direction with the wind,prevent the blade

    from the more stress.

    2) 00

    40 41

    Make the 0 calibration tail at the top of blade align at 0 calibration tail of pitch

    bearing by adjusting the rotation of pitch bearing manually. Adjust the crane and

    control the direction of blade at the same time to make connecting bolt of blade

    pass through flange hole of pitch bearing, thus realizing butt joint. Distinguish

    direction when installing spacer and nut, with the flat side facing pitch

    bearing.(refer to Pic40,41)

  • 40 41

    Pic40 blade fitting up Pic41 align mark

    5130mm,

    -90 6544mm

    Note: Before the pitch operation, the factory hub with a configuration such as a short

    tooth belt (tooth belt with a length of only 5130mm, It can not make the blade pitch

    to -90 position) you need to replace the tooth belt (tooth belt length about 6544mm).

    Long tooth belt replacement when the short tooth belt removed, the tooth belt

    tensioners mounted on the long trip on the pitch plate position. Install long tooth belt

    and tensioners refer to 8.3.2. Restore the factory configuration toothed belt after the

    blade fitting up operations is completed.

    3) -90

    Remove the blade lock block,pitch to -90position.

    4)

    50%75%100%

    Use hydraulic wrench (lengthened sleeve) to adjust the torque of hydraulic wrench

    and fasten flange bolt at the diagonal. Hit the bolt torque by three times with the value

    being 50%, 75% and 100% of the required torque value respectively.

    -90 11

    0

    Attention: when torque the bolts near the -90, there are about 11 bolts near the

    pitch motor bracket we cant put the spanner on these bolts. We can

    pre-tighten them by open spanner,then torque the bolts by pitch the blade

    to 0 degree later.

    5)

    42 2t

    Use sleeper to support the fitted-up blade, using soft materials between blade

    and vertical bracing to protect the blade.Or use a crane to lift the blade,maintain

  • 2T.refer to Pic42.

    6)

    Follow the above steps to fit up the second and third blades.

    7)

    , 43

    If the rotor is not hoisted right after being fit up and needs to be put on site,

    reliable support must be provided for blade to ensure that the rotor will not be

    damaged during placement.(refer to Pic43)

    42 43

    Pic42 blade support Pic43 the rotor position

    8) 90 44 45

    Before lifting, change the 2#,3# blades to the position of 90. Lock the locking device

    of blade and perform 90 hoisting.refer to Pic44,45.

    44 -90 45 90

    Pic44 blade -90fitting up Pic45 rotor 90 lock state

    Considerations:

    Clear up the blade flange and pitch bearing flange and keep the hub inside clean

    when operating in it; protect anticorrosive coating with leather or rubber to avoid

    damage when hitting moment.

  • 8.3 Assembly installation of blade collar

    8.3.1 preparation work

    21 22

    Table 21

    Table21 assembly components and parts

    No.

    name

    specification

    quantity

    remark

    1

    blade collar

    assembly

    3 set

    2

    Core rivet 18pcs

    22

    No.

    name

    specification

    quantity

    remark

    1 lashing belt TMLS058m 3set

    2 glue gun

    structural adhesive 1pcs

    3 hand riveter 1pcs

    4 sealant gun

    sealant 1pcs

    5 angle grinder 1pcs

    6 drill M5 1pcs

    7 mark pen 1pcs

    8 structural

    adhesive Plexus MA310 4group

    9 sealant SM7108 or MS939 3bottle

    10 cutting disk 2disk

    8.3.2 Steps forinstallation

    1)

    Cut open the blade collar, and chamfer and polish the edges with polishing

    machine to prevent abrading sling when hoisting.

    2

    46

    Marking-off: clean blade root and bonding face of blade sealing assembly, keep

    the bonding face clean and install blade sealing assembly at the blade root,

    move blade sealing assembly to make it be close to hairbrush, and then mark on

    the blade along the outer edge of blade sealing assembly with marking

    pen.(refer to Pic46)

  • 3) Plexus MA310

    Install Plexus structural adhesive MA310 into glue gun and install mixing nozzle

    according to instructions. The glue solution outgoing first cannot be used; glue

    on blade formally till the color of outgoing glue is uniform.

    4) 25mm

    8mm10mm 47

    Gluing: at the position 25mm away from the marking line on blade (middle

    position of bonding width), glue continuously to form a closed ring, with the

    diameter of adhesive tape being around 8mm~10mm.refer to Pic47.

    46 47

    Pic46 marking-off Pic47 gluing

    1) ()

    48 49

    1

    Pull open blade collar assembly and move it to installation position (above

    gluing), cling to hairbrush and press it down tightly; fix and clamp blade collar

    assembly with tightener to solidify the glue.Fill any gaps with structural

    adhesive.remove the lashing belt after completing the collar installation.

    Note:the lashing belt cant be removed in less than 1 hour.

    48 49

    Pic48 fix the collar with lashing belt Pic49 gluing

  • 6)

    50 51

    Paint sealant between blade collar assembly and blade (marking-off part); use

    fingers stained with cleanser essence water to sleek and press tightly the

    sealant.(refer to Pic50 51)

    50 51

    Pic50 paint sealant Pic51 press tightly the sealant

    7 6(525)

    52

    Connect junction plate at the opening of blade collar assembly with six rebites (525),

    with the edges and rivets painted with sealant.refer to Pic52.

    52

    Pic52 Installing Junction Plate at the Opening of Rain Blocking Rain

    8.3.3 technical requirements

    a)

    The gaps between the collar and the blade should be full of blue.

    b) ,

    This product belongs to flammable items, please keep it away from flame and spark.

    a

  • Do not tread the sealing assembly of blade collar when painting sealant,

    to prevent misplacement and moving of blade collar when bonding glue is not

    solidified.

    b

    When using the drill and angle grinder,avoiding damage the surfae of the

    blade or the hub.

    c 1518min

    The installation should be completed in 15-18min after gluing.

    8.4 spinner cap installation

    8.4.1 Preparation

    23

    Table23 installation components and parts

    No.

    name

    specification

    quantity

    remark

    1

    Spinner cap 1pcs

    2

    bolt M10100GB/T 5783-2000 A4-70 15pcs

    3

    washer 10GB/T 96-2002 A140 30pcs

    4

    Self-lock

    nut

    M10 15pcs

    24

    Table24 installation tools list

    No.

    Name

    specification

    quantity

    remark

    1

    sealant gun for sealant 1pcs

    2

    Open spanner 17mm 2pcs

    3

    Adjustable

    spanner

    20024mm 2ps

    4 U

    U type shacle 1t 2ps

    5

    Sling belt 1t-3m 1pcs

  • 6

    ladder 4m 1pcs

    7

    sealant SM7108 or MS939 2bottle

    8.4.2

    1 1t-3m

    15 M10

    100 40N.m SM7108

    MS939 53

    Hoist spinner cap with a 1t-3m sling and install it onto the dome; connect nose

    cone and the dome with fifteen bolts M10100 with the fastening torque value of

    40N.m, then paint the circumference and bolt head with SM7108 or Loctite MS939

    sealant.

    53

    Pic install the spinner cap

    a)

    b)

    Considerations:

    a) Do not tread the sealing assembly of blade collar when painting sealant, to prevent

    misplacement and moving of blade collar when bonding glue is not solidified. Pay

    attention to personal safety as well.

    b) Use properly in accordance with the instructions on bottle of locking glue, do not

    waste.

    8.5 Rotor lifting

    8.5.1 Preparation

    25

    Table25 Standard Parts for Rotor Installation

  • No. Name Specification Quantity Remark

    1 Bolt M36240-10.9 (GB/T 5782-2000) 54

    2 Washer 36-300HV (GB/T 1230-2006) 54

    26

    Table26 Spreader for Rotor Installation

    No. Name Specification Quantity Remark

    No. Name Specification Quantity Remark

    1

    Protective

    belt 1 for rip of

    blade

    JF2500.85.027 1

    2

    Protective

    belt 2 for rip of

    blade

    JF2500.85.026 2

    3 Hawser cable 20300m 3

    4 round sling 8t-10m 1

    5

    Protective

    clothing at tailing

    edge of blade

    JF2500.85.020 1

    6 Flat sling W04-30t20m (width: 250mm) 2

    27

    Table27 install tools list

    No. Name Specification Quantity Remark

    1

    Chain block 5t*3m 2pcs

    2

    Hairbrush 2pcs

    3

    Electric wrench 800N.m 1set

    4

    Hydraulic wrench

    4514N.m

    1set

    5 55mm 1pcs

  • socket

    6

    Solid lubrication

    grease

    MOLYKOTE G-Rapid Plus p.s.

    8.5.2 Steps for- 90 hoisting of rotor

    -90()

    Method One: - 90 hoisting of rotor(recommend)

    1 23

    -90290

    According to the location selected two blades installed crane main spreader.

    According to the location selected two blades installed crane main spreader, The

    blade which Install auxiliary spreader to maintain -90 pitch position, The other

    two blades pitch to 90 pitch position, with the pitch locking pin lock.

    2 21

    20300m54

    Install a short protective belt on the rip of blade of the two blades respectively and

    fix two guiding ropes of 20 and 300m by protective belt of rip of blade

    respectively.refer to Pic54

    54

    Pic54 Install the protective belt

  • 55 -90

    Pic55 auxiliary spreader installation

    3 318t*10m

    50

    55

    Install the protective clothing at tailing edge of blade on the third blade and one

    sling of 18t-10m on the third blade. Play buckle at end of the sling which in the top

    of the protective clothing at tailing edge of blade, the other end hanging on the

    crane's hook. Tie a 50m rope at the part of sling buckle.refer to Pic55

    4 2W04-3030t-20m)250mm

    ,500mm

    56

    Install flat sling W04-30 (30t*20m) at the root of the two blades with the width of

    250mm. Notice that the sling should bear at least a space of 500mm from blade

    collar for fear of abrading the sling when hoisting. The sling should keep dry in

    winter.refer to Pic56.

  • 56

    Pic56 install the flat sling

    5

    80

    5758

    Cranes are hoisted simultaneously; the main crane goes up slowly while auxiliary

    crane cooperates to lean the rotor from level slowly and ensure that the rip of

    blade do not contact the ground. After the vertically downward rip of blade is off

    ground completely and when the vertically downward blade forms an angle of

    about 80, tension the guiding rope of vertically downward blade manually, then

    loose the sling of auxiliary crane and unhook the auxiliary crane; hoist the rotor to

    the height of hub by main crane.

    57 58

    Pic57 turn over of the rotor Pic58 rotor fitting up

    6

    (MOLYKOTE G-Rapid Plus

  • Make the rotor approach generator slowly, and pull haulage rope to cooperate

    with the crane to make flange face of pitch system of hub parallel to cooperating

    flange face of generator; paint the bolt with solid lubricating grease (MOLYKOTE

    G-Rapid Plus) and screw it in.After finishing the butt joint of rotor, fix the

    connecting bolt used in installation pedestal of gap bridge onto flange face of

    generator rotor which is just against 1# pitch cabinet when installing connecting

    bolt, with the elbow pointing at generator.

    7

    50%75%100%B1

    Screw all bolts into bolt holes with open spanner firstly and then fasten the

    moment with hydraulic torque wrench by three times with the value of 50%, 75%,

    100% of the required torque value respectively.

    Table for Tighten Force of Bolt

    No. Location

    Quantit

    y(inspected

    number)

    Type and strength grade

    of bolt

    Wre

    nch

    (m

    m)

    Torq

    ue value

    (N.m

    )

    Rotor

    1 Hub-rotation shaft 54 (6) GB/T 5782-2000

    M36240-10.9 55

    240

    0*

    8

    After the bolt moment is fastened according to requirements, the crane can be

    unhooked and spreaders can be disassembled.

    9

    Q/JF 2FW2500.4-20102.5MW

    When disassembling protective belt for rip of blade, unlock the locking device of

    generator rotor firstly and then rotate the blade manually. Refer to document Q/JF

    2FW2500.4-2010 Work Standards for Rotor Locking of Goldwind 2.5MW Series

    Wind Turbine Generator System for specific steps of unlocking locking device of

    generator rotor.

    1

    2

    3

  • 4

    5

    6

    Considerations:

    1) The surface of sling should be kept clean and tidy to prevent damage to blade

    surface caused by particles on sling surface; strictly forbid twining, folding,

    twisting and knotting wide sling. In winter, wide sling should be kept dry to prevent

    freezing and slipping; paint with rosin to increase friction if it is slippy.

    2) When installing rotor, guiding bar can be chosen to install as required;

    the process of hoisting rotor should maintain the hoisting speed of crane constant

    and slow, preventing rotor rocking.

    3) The bolt can be threaded in manually only after hub flange and rotor flange

    are fit tightly and bolt holes are aligned as well. Besides, the thread part of bolt

    is required to be painted with solid lubricating grease which is also used between

    bolt root and spacer.

    4) Operators must wear full body safety clothing and safety rope, safety rope

    and reliable fixed.

    5) Remove auxiliary spreader, note the speed and demolition demolition, so as

    not to damage the leaves.

    6) Parts in contact with the spreader of blades to make full protection to

    avoid damage to blades in the lifting process.

    Operational requirement: during rotor installation, body-safety-belt must be

    worn while the safety rope should be fixed at reliable position of nacelle.