Project Number Project Number and Name YEAR location Work Type Project Description 7842 7842-ANDREWS AFB-AMBULATORY CARE 2015 MD Pile Driving, Shoring, Tiebacks, Rakers Worked for Manhattan Construction (used rakers as heel blocks) - installed piles and lagging and rakers 7852 7852-SWATARA BRIDGE 2014-2015-2016 Middletown, PA Micropiles Ongoing installation of micropiles (178 approximately remaining to do), approximately 35 feet deep, challenging drilling through existing concrete abutments 7873 7873-YORK HOSP EARTH RETN UNDERPIN 2015 York, PA Shoring, Tiebacks Expansion for the hospital, shoring to facilitate the building of emergency department and helipad overhead 7890 7890-JHU 33RD ST PAUL 2015 Baltimore, MD Shoring, Tiebacks, Tiedowns, Rakers Armada hoffler was the GC, Mixed use building, we utilized the daily utility ticket on this project sucessfully 7891 7891 - JHU Pedestrian Bridge 2016 Baltimore, MD Micropiles Installation of 76 micropiles for a pedestrian bridge at JHU 7894 7894-MERRIWEATHER POST PAVILION 2015 Columbia, MD Shoring Cantilever shoring 7897 7897-VILLAGE AT ORCHARD-EARTH RET 2015 Winchester, VA Shoring, Raker Raker and shoring for addition to the charles village retirement community 7898 7898-JHU CHARLES VILLAGE 2015 Baltimore, MD Tiedowns Part of Armada hoffler project, 3 tiedowns were installed (100 Kips capacity) drilled 40 feet into rock (per engineer they would not ease up on this, we tried) 7901 7901-ARLINGTON NATL CEMETARY 2015 Arlington, VA Shoring, Tiebacks Tiebacks for columbarium - addition to the cemetery. Tiered wall system, 2 walls were built and piling crew drove all piling 7903 7903-SR 180 (129) 2015-2016 Williamsport, PA Soil Nails Soil nails through gabion baskets for hawbaker construction. Challenging project, nails were 23 feet drilled into fill and clay soils 7904 7904-BRETHREN VILLAGE SHORT TERM 2015 Lancaster, PA Underpinning Underpinning design and management for WCI (norm adams and Jeremiah) - matt beihl project manager. We designed and oversaw the construction 7909 7909 - VA 688 Martins Construction 2016 Markham, VA Shoring, Tiebacks Phased shoring for Martins construction. Tiebacks, shoring and attachment to abutments PROJECT Project Manager – Ryan Smith

RRS Project Photos 10-23-16

Embed Size (px)

Citation preview

Page 1: RRS Project Photos 10-23-16

Project Number Project Number and Name YEAR location Work Type Project Description

7842 7842-ANDREWS AFB-AMBULATORY CARE 2015 MD Pile Driving, Shoring, Tiebacks, RakersWorked for Manhattan Construction (used rakers as heel blocks) - installed

piles and lagging and rakers

7852 7852-SWATARA BRIDGE 2014-2015-2016 Middletown, PA Micropiles

Ongoing installation of micropiles (178 approximately remaining to do),

approximately 35 feet deep, challenging drilling through existing concrete

abutments

7873 7873-YORK HOSP EARTH RETN UNDERPIN 2015 York, PA Shoring, TiebacksExpansion for the hospital, shoring to facilitate the building of emergency

department and helipad overhead

7890 7890-JHU 33RD ST PAUL 2015 Baltimore, MD Shoring, Tiebacks, Tiedowns, RakersArmada hoffler was the GC, Mixed use building, we utilized the daily utility

ticket on this project sucessfully

7891 7891 - JHU Pedestrian Bridge 2016 Baltimore, MD Micropiles Installation of 76 micropiles for a pedestrian bridge at JHU

7894 7894-MERRIWEATHER POST PAVILION 2015 Columbia, MD Shoring Cantilever shoring

7897 7897-VILLAGE AT ORCHARD-EARTH RET 2015 Winchester, VA Shoring, Raker Raker and shoring for addition to the charles village retirement community

7898 7898-JHU CHARLES VILLAGE 2015 Baltimore, MD TiedownsPart of Armada hoffler project, 3 tiedowns were installed (100 Kips capacity)

drilled 40 feet into rock (per engineer they would not ease up on this, we tried)

7901 7901-ARLINGTON NATL CEMETARY 2015 Arlington, VA Shoring, TiebacksTiebacks for columbarium - addition to the cemetery. Tiered wall system, 2

walls were built and piling crew drove all piling

7903 7903-SR 180 (129) 2015-2016 Williamsport, PA Soil NailsSoil nails through gabion baskets for hawbaker construction. Challenging

project, nails were 23 feet drilled into fill and clay soils

7904 7904-BRETHREN VILLAGE SHORT TERM 2015 Lancaster, PA UnderpinningUnderpinning design and management for WCI (norm adams and Jeremiah) -

matt beihl project manager. We designed and oversaw the construction

7909 7909 - VA 688 Martins Construction 2016 Markham, VA Shoring, TiebacksPhased shoring for Martins construction. Tiebacks, shoring and attachment to

abutments

PROJECT Project Manager – Ryan Smith

Page 2: RRS Project Photos 10-23-16

7842 – Andrews Airforce Base (2015 Andrews AFB, MD)Project Manager – Ryan Smith

Pile Driving, Rakers, Tiebacks, H-Pile Heel Blocks, Timber Lagging

Page 3: RRS Project Photos 10-23-16

7852 – Swatara Creek Bridge (2014-2016 Middletown, PA) Project Manager – Ryan Smith

Micropiles (#14 Bar) – Mostly battered working for Turnpike

Page 4: RRS Project Photos 10-23-16

7873 – York Hospital (2015 York, PA)Project Manager – Ryan Smith

Cantilever Shoring, Tiebacks, Bracing

Page 5: RRS Project Photos 10-23-16

7890 – JHU 33rd & St. Paul Street (2015 Baltimore, MD) Project Manager – Ryan Smith

Tiebacks, Cantilever Shoring, Rakers, Wales, Heel Blocks

Page 6: RRS Project Photos 10-23-16

7894 – Merriweather Post Pavilion (2015 Columbia, MD)Project Manager – Ryan Smith

Cantilever Shoring, Tiebacks, Bracing – Worked for Whiting Turner

Page 7: RRS Project Photos 10-23-16

7898 – JHU Charles Village (2015 Baltimore, MD)Project Manager – Ryan Smith

(3) Permanent Tiedowns –

Worked for Atlantic Caisson

for the work 40 feet deep

completely in compotent Rock

Page 8: RRS Project Photos 10-23-16

7901 – Arlington National Cemetery (2015-2016 Arlington, VA)Project Manager – Ryan Smith

Pile Driving (Team did great!), Tiebacks in Potomac clay, tiered wall

System in soft soils for new columbarium

Page 9: RRS Project Photos 10-23-16

7903 – SR180 Soil Nails 2015-2016 Williamsport, PAProject Manager – Ryan Smith

Very challenging job – 90% complete

Soil Nailing being installed through existing

Gabion Baskets (Bob Horst – Superintendant)

Page 10: RRS Project Photos 10-23-16

Bob and crew enjoying Sticky Bunns during morning safety

Review onsite

Soil nail headed shear studs

With 10”x10” bearing plates

7903 – SR180 Soil Nails 2015-2016 Williamsport, PAProject Manager – Ryan Smith

Page 11: RRS Project Photos 10-23-16

7909 – VA 688 Martins Construction (2016 Markham VA)Project Manager – Ryan Smith

Phased Shoring of 2 Bridge culvert replacements for

Martins Construction in Markham VA