Upload
anonymous-jjnhtxa3m
View
9
Download
0
Embed Size (px)
DESCRIPTION
RSA JAMBI
Citation preview
iRepublic of IndonesiaMinistry of Public WorksDirectorate General of Highways
Strategic Roads Infrastructure Project(SRIP)
Technical assistance for Core Team Consultant (CTC)To Support the Management Unit
Under IBRD Loan No. 4834-IND
PALMERAH RING ROAD JAMBIROAD SAFETY AUDIT REPORT
FINAL DESIGN & CONSTRUCTION
FEBRUARY 2012
iTable of Contents
1. Summary in Bahasa................................................................................................. ii2. Introduction
2.1. Audit Process ............................................................................................ 12.2. SRIP ....................................................................................................... 12.3. Objectives of the Road Safety Audit Report ................................................ 22.4. Project Location ......................................................................................... 22.5. Project Information ................................................................................. 22.6. Plans and Documents ...................................................................... 52.7. Traffic Volumes ................................................................................. 52.8. Members of the Audit Team ...................................................................... 52.9. Site Visit ...................................................................................................... 52.10. Completed Sections..................................................................................... 7
3. Problems and Recommendations3.1. Existing Pavement Conditions...................................................................... 93.2. Pavement Materials ................................................................................. 143.3. Completed Section Safety Issues................................................................ 163.4. Bends........................................................................................................... 203.5. Junctions...................................................................................................... 243.6. Road-Side Activity........................................................................................ 423.7. Narrow Road ........................................................................................... 443.8. Guard rail ............................................................................................. 44
4. Road Safety Audit of Construction4.1. Inadequate Safety Culture ........................................................................ 48
Appendix A. References ............................................................................................. 50Appendix B. Safety Concerns at Roadworks - English .......................................... 51Appendix C. Safety Concerns at Roadworks Bahasa........................................... 52Appendix D. Maintenance of Traffic Flow .. 53Appendix F. High specification of traffic lights and Equipment from DGLT........... 54
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
ii
Kesimpulan Permasalahan dan rekomendasi dalam BahasaIndonesia
Kondisi Perkerasan yang ada saat iniPermasalahanPerkerasan yang ada saat dalam kondisi sangat memprihatinkan di banyak lokasi danbanyak yang rusak di berbagai tempat. Hal ini menyebabkan kondisi yang sangat kacaupada saat ini dan menimbulkan banyak masalah, terutama menyulitkan untuk kendaraanbesar seperti truk sehingga menimbulkan kemacetan.
Semua masalah ini memiliki akibat terhadap keselamatan dijalan karena merekamenyebabkan kelelahan kepada pengemudi kendaraan dan kemungkinan terjadikecelakaan antara truk-truk besar dan sepeda motor maupun pengendara ataupunpengguna jalan lainnya.
Kondisi tersebut juga tidak dapat ditoleransi untuk pejalan kaki di banyak lokasi, tapiuntungnya pada saat survey dilapangan hanya terlihat beberapa pejalan kaki.
Rekomendasi Kontraktor sekarang memiliki tugas untuk menjaga jalan yang ada dalam kondisi
aman dan perlu menjadi prioritas utama untuk staf dan peralatan. Prioritas terhadap kondisi jalan yang terburuk dan ditangani dengan cepat. Hubungan dengan polisi lalulintas setempat sangat diperlukan untuk memastikan
keputusan yang terbaik dalam pengaturan lalulintas karena mereka aktif beradadilapangan.
Masalah terhadap hasil galian lubang harus diselesaikan secepatnya.
Bahan PerkerasanPermasalahan.
Selama pertemuan dengan Engineer Pengawasan dan Kontraktor, ada banyakdiskusi tentang kesulitan menentukan bahan perkerasan yang benar untukmemperbaiki atau membangun kembali jalan.
Bahan untuk rekonstruksi adalah AC-WC, AC-BC, AC-Base, Base Class Agregat A,Base Kelas B dan timbunan pilihan.
Pengawas Lapangan menunjukkan bahwa material timbunan pilihan harus diubahdengan menggunakan kerikil yang berpasir.
Drainase yang buruk sangat berkontribusi pada masalah kerusakan perkerasan dilokasi.
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
iii
Rekomendasi Spesifikasi untuk bahan yang paling efektif dan metode kerja perlu disepakati
secepatnya oleh pihak yang terkait, dan dimungkinkan dalam justifikasi teknis padasaat ini.
Keamanan dijalan pada Bagian jalan yang Sudah DiperbaikiPermasalahan.Ada kekhawatiran tentang masalah keselamatan di jalan pada bagian jalan yang sudahdikerjakan oleh proyek APBN 2011 yang dilontarkan oleh Bank Dunia, pengamatandilapangan dengan desain yang ada perlu dikembangkan lebih lanjut karean sangatberkesinambungan dengan jalan yang akan diperbaiki melalui proyek SRIP.
Isu-isu keselamatan meliputi: Pemasangan zona sekolah, (lihat juga 2.10 di atas) Penyelesaian persimpangan pada STA 16+415 Pedestrian fasilitas Konstruksi Bahu jalan
Pulau-pulau yang sudah didesain dan penyeberangan banyak yang tidak dikerjakan padaloksai persimpangan. Site engineer menyatakan bahwa persimpangan ini tidak akanmemperbaiki persimpangan tersebut di bawah proyek SRIP saat ini. Dan juga menunjukpada Surat Bank Dunia tanggal 1 Juni 2011 khusus meminta untuk memproteksi pipaPertamina di lokasi ini.Kemungkinan persimpangan tersebut tidak dikerjakan sesuai dengan desain aslinya.
Fasilitas pejalan kaki.Permasalahan.Masyarakat setempat sudah mencoba untuk meningkatkan rambu rambu peringatanpada lokasi yang banyak pejalan kaki agar terjadi perlambatan kendaraan yang berlalulintas dengan berbagai macam cara. Ini seharusnya dilakukan dengan benar olehdesainer
Konstruksi bahu jalan.Permasalahan.beberapa tipikal bahu jalan sudah banyak yang rusak yang disebabkan kendaraan berat.Konstruksi bahu jalan tersebut (APBN proyek), terdiri atas Agregat Kelas B yang ditutupdengan lapisan laburan Satu lapis (Burtu).
Bahan yang diusulkan untuk bahu di BOQ SRIP adalah Agregat kelas S dan terbuka, jadibahu jalan yang ada dalam SRIP lebih buruk daripada konstruksi bahu jalan yang sudah
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
iv
selesai yang didanai dengan anggaran APBN. Meskipun proyek APBN baru selesai padaDesember 2011, namun banyak bahu jalan yang sudah rusak. Ini bukan pertanda baikuntuk desain bahu yang diusulkan.
RekomendasiDiskusi perlu dilakukan antara instansi terkait untuk menyepakati pekerjaan tambahan dilokasi yang sudah dikerjakan dengan anggaran APBN, pekerjaan tersebut adalahsebagai berikut:
Zona Sekolah perlu diaplikasikan pada STA.17 +000 dan STA.3+300. Rambu lalulintas perlu di tambah serta rumble strip perlu dipasang pada tempat
penyeberangan dan menuju lokasi yang padat penduduk untuk menggantikanrambu buatan sementara.
Simpang pada STA 16+415 perlu dikerjakan sesuai desain jalan pada gambarkontrak SRIP.
Kegagalan konstruksi bahu jalan pada proyek APBN dapat dijadikan bahanpertimbangan pada proyek SRIP sebagai berikut:
Tikungan pada proyek SRIP perlu didesain kembali , ini merupakan penerapanterbaik yang sudah dilakukan oleh proyek APBN dengan menggunakan marka danpatok pengarah.
Desain Bahu jalan perlu ditinjau untuk menghindari kegagalan yang telah terjadipada proyek APBN.
TikunganPermasalahan.Ada banyak tikungan di ruas jalan ini dengan berbagai macam Rambu-rambu yangbermacam-macam namun indikasi tersebut tidak didetailkan dalam pemasangan guardrail.
Beberapa tikungan tajam tidak ada rambu peringatan yang sesuai hanya rambutikungan saja yang diletakan sebelum tikungan (Tidak ada rambu penunjanglainnya)
Jarak Antar patok pengarah tidak didetailkan dalam gambar untuk diterapkan padalokasi yang membutuhkan.
Ada beberapa rambu arah namun tidak dilengkapi dengan patok pengarah. 250 unit patok pengarah di BOQ tanpa informasi di mana patok tersebut akan
diletakan. Ada banyak tikungan yang membutuhkan delineasi baik seperti rambu-rambu
peringatan namun tidak memberikan informasi yang cukup bila berdiri sendiri. Ada juga beberapa daerah timbunan dan lokasi gorong-gorong yang perlu
dilengkapi patok pengarah.
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
v
Rekomendasi Jarak patok pengarah perlu disusun dan digambar untuk menentukan banyaknya
patok pengarah yang dibutuhkan pada tikungan, timbunan ataupun gorong-gorongsehingga jumlah total kebutuhan tersebut dapat dipastikani dalam BOQ.
Persimpangan Secara UmumPermasalahan.Desain persimpangan dan konstruksi di Indonesia biasanya memiliki kelemahan yangmenyebabkan masalah keselamatan, terutama untuk pejalan kaki. Hal ini dapat diamatidengan melihat persimpangan yang ada di Jambi dan desain yang diusulkan untukpersimpangan.
Lansekap adalah manfaat besar bagi lingkungan dan memiliki efek "menenangkan" padapengendara yang baik untuk keselamatan tetapi juga menyebabkan banyakpermasalahan. Seperti halnya menghambat pergerakan pejalan kaki serta membuatrambu-rambu jalan tidak terlihat.
Rekomendasi Perawatan tanaman harus dilakukan di setiap persimpangan untuk memastikan
tidak menhambat gerakan pejalan kaki yang aman terutama pada pulau-pulauyang indah dipersimpangan.
Pertamanan dan penanaman jangan sampai menghalangi rambu-rambu jalanatau pejalan kaki pada saat penanaman atau di masa depan.
Penanaman harus direncanakan dengan kesadaran akan pemeliharaan dimasamendatang untuk meminimalkan masalah keamanan kepada pengguna jalandan pekerja pemeliharaan tanaman.
Pertamanan selalu membutuhkan pekerjaan pemeliharaan yang rutin. Perlupelatihan khusus terhadap para pekerja pemeliharaan tanaman ditengah tengahkesibukan lalulintas yang sangat tinggi agar dapat bekerja secara aman danuntuk mengenakan pakaian yang mudah dilihat.
Persimpangan STA 0+000Permasalahan.
Leher sempit yang diusulkan di awal jalan lingkar akan menyebabkan konflik serius. Pulau-pulau indah yang diusulkan akan menimbulkan masalah serius bagi
pergerakan pejalan kaki. Fase Sinyalisasi menunjukkan konflik antara pejalan kaki dan kendaraan. Tidak ada detil gambar lampu lalulintas cukup untuk memastikan lokasi yang tepat
serta standard lampu yang berspesifikasi tinggi. Lihat lampiran F Tidak ada jalur atau halte bus.. Ada median kaki Jambi tidak jauh dari persimpangan yang tampaknya tidak
digambarkan dalam desain.
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
vi
Rekomendasi Pulau-pulau indah yang diusulkan dan penyeberangan harus didesain ulang untuk
memastikan pergerakan pejalan kaki mudah dan aman dan pendekatan yang lebihluas untuk bypass.
Fase Sinyalisasi harus direvisi kembali masih adanya konflik antara pejalan kakidan kendaraan
Lokasi lampu lalulintas serta spesifikasinya berikut ukuran lampu harus ditentukandengan standar yang tinggi serta penambahan lampu lalulintas kedua (secondaryTraffic light) , Digital penghitung waktu dan lampu harus mempunyai pencahayaanyang sangat baik (LED Lamps). Lihat lampiran F
Tambahkan halte bis. Desain dari pulau pulau harus ditinjau kembali dan digambarkan sesuai kondisi
kondisi existing. Digital penghitung waktu sangat diperlukan karena baik untuk visibilitas Terutama
di malam hari.
Persimpangan Sta. 8+450Permasalahan
Pulau-pulau indah yang diusulkan akan menimbulkan masalah serius bagipergerakan pejalan kaki.
Fase Sinyalisasi menunjukkan konflik antara pejalan kaki dan kendaraan. Tidak ada detil gambar lampu lalulintas cukup untuk memastikan lokasi yang tepat
serta standard lampu yang berspesifikasi tinggi. Lihat lampiran F Tidak ada jalur atau halte bus..
Rekomendasi Pulau-pulau indah yang diusulkan dan penyeberangan harus didesain ulang untuk
memastikan pergerakan pejalan kaki mudah dan aman. Fase sinyalisasi harus direvisi untuk menunjukan semua pergerakan dan fase. Lokasi lampu lalulintas serta spesifikasinya berikut ukuran lampu harus ditentukan
dengan standar yang tinggi serta penambahan lampu lalulintas kedua (secondaryTraffic light) , Digital penghitung waktu dan lampu harus mempunyai pencahayaanyang sangat baik (LED Lamps). Lihat lampiran F
Persimpangan Sta. 16+415Permasalahan.
Persimpangan dengan pulau-pulau belum dibangun pada proyek APBN dan BankDunia meminta untuk memproteksi pipa pertamina.
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
vii
Rekomendasi Diskusi harus diadakan antara pihak yang berkepentingan untuk memastikan
persimpangan selesai dalam satu proyek atau lain. Pulau-pulau indah yang diusulkan dan penyeberangan harus didesain ulang untuk
memastikan pergerakan pejalan kaki mudah dan aman. Memastikan perlindungan pipa Pertamina segera dilaksanakan
Persimpangan Sta. 18+ 440Permasalahan.
Desain untuk penyeberangan bagi Pejalan kaki, pulau dan pertamanan sangatburuk.
Penyeberangan yang diusulkan dan pulau-pulau indah yang sangat buruk dalamgambar dan tidak memungkinkan untuk gerakan pejalan kaki yang sebenarnyadiharapkan.
Fase sinyalisasi tidak cukup untuk menunjukkan semua gerakan pejalan kaki. Detail Lampu lalulintas tidak mengggambarkan penempatan lampu yang optimal
dan spesifikasi tinggi.
Rekomendasi Pulau-pulau indah yang diusulkan dan penyeberangan harus didesain ulang untuk
memastikan pergerakan pejalan kaki mudah dan aman Fase sinyalisasi harus direvisi untuk menunjukan semua pergerakan dan fase. Lokasi lampu lalulintas serta spesifikasinya berikut ukuran lampu harus ditentukan
dengan standar yang tinggi serta penambahan lampu lalulintas kedua (secondaryTraffic light) , Digital penghitung waktu dan lampu harus mempunyai pencahayaanyang sangat baik (LED Lamps). Lihat lampiran F
Persimpangan Sta. 22 +550Permasalahan
Penyeberangan diusulkan dan pulau yang indah tidak memungkinkan untukgerakan pejalan kaki yang sebenarnya diharapkan
Rekomendasi Pulau-pulau indah yang diusulkan dan penyeberangan harus didesain ulang untuk
memastikan pergerakan pejalan kaki mudah dan aman.
Kegiatan Disekitar Ruas JalanPermasalahan.Truk membentuk persentase yang sangat tinggi dari pergerakan lalu lintas tetapi merekajuga sering berhenti di bahu atau di luar bahu di berbagai lokasi depot peralatan beratdan lapangan. Banyak truk yang kelebihan muatan yang diijinkan. Hal ini menyebabkan
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
viii
kerusakan ekstrim pada jalan lama dan telah menyebabkan kerusakan pad bahu jalanyang baru.
Desain yang diusulkan dan metode konstruksi tidak memperhitungkan kebutuhan sopirtruk untuk berhenti dan mereka tampaknya mengabaikan potensi kerusakan yang sangatserius.
Rekomendasi Struktur jalan harus harus dirancang untuk dengan berdasarkan kendaraan berat
yang melalui jalan tersebut dan ini harus mencakup desain sebagai berikut; Bahu jalan yang diperkeras agar dapat dilewati oleh truk biasa, termasuk akses ke
depot. Desain dan konstruksi area istirahat dan jalur bis. Jembatan timbang harus dimasukan ke proyek atau direncanakan pada proyek
berikutnya.
Badan Jalan yang MenyempitPermasalahan.
Tidak ada Detail desain pada lokasi jalan yang menyempit. Kondisi ini sangatberbahaya bagi pengguna jalan dimana kecepatan kendaraan harus diperlambat(Dari arah utara ke selatan), meletakan awal atau akhir median jalan harusdiperhitungkan karena akan sangat berbahaya bila awal median hampir dekatdengan tikungan (dari selatan ke utara).
Rekomendasi Marka arsir pada jalan yang menyempit harus ditambahkan. Median harus diperpanjang atau dikurangi sampai tikungan awal (dari selatan ke
utara).
Guard RailPermasalahan
Banyak sisi jalan yang terjal dengan bahu sempit serta tersembunyi di banyaktempat dan juga tidak bisa dilihat pada gambar kontrak.
Rekomendasi Tim lapangan harus mensurvey kembali untuk mengetahui lokasi dimana tempat
tempat yang terjal ada ruas jalan tersebut. Apabila beda tingginya melebihi dari 2meter maka harus di desain dengan detail yang baik dengan menggunakan guardrail.
Guard rail harus dipasang untuk melindungi pengguna jalan. Ada peningkatan pada proyek APBN di link jalan yang sama, tapi masih tidak
memadai karena hanya menggunakan patok pengarah.
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
ix
Budaya Keselamatan jalan yang Tidak MemadaiPermasalahan
Hanya sedikit atau tidak ada peringatan pad zona konstruksi baik di awal proyekatau di mana pekerjaan konstruksi dilakukan.
Hanya Site Engineer & Survei staf dari konsultan yang memakai pakaian denganvisibilitas keselamatan yang tinggi.
Rekomendasi Manajemen lalu lintas harus ditingkatkan khususnya pada awal dan akhir proyek,
seperti ; Memasang papan proyek, Rambu Peringatan, pemasangan barier(kerucut) serta memoperbanyak jumlah kerucut yang digunakan.
Harus ada upaya langsung untuk meningkatkan jumlah pekerja yang mengenakanpakaian keselamatan jaket safety.
Staf pengawas Kontraktor harus menerapkan contoh yang baik dengan selalumengenakan pakaian keselamatan di lapangan.
Ikuti instruksi dalam spesifikasi kontrak dan saran yang diberikan dalam LampiranB & C
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
1
1. Introduction2.1. Audit ProcessRoad Safety Audit (RSA) can be defined as a formal examination of a highway ortraffic project in which an independent qualified auditor or team of auditors reports onthe road safety problems associated with the designs or construction of the project andmakes recommendations on improvements.
It started in the UK some twenty years ago and is now common practice around theworld. There are several Road Safety Audit Guidelines that are used as standardpractice for Audits around the World; an adaption of the Australian Guidelines arecurrently used in Indonesia
Audits can be carried out at various stages and arguably the earlier the better: Feasibility Preliminary Design Final Design Construction Pre-Opening Existing Road
2.2. SRIPThe Strategic Roads Infrastructure Project (SRIP) was developed to meet theincreasing traffic demand and institutional requirements following easing of the 1997financial crisis in 2001. SRIP, which is supported by the World Bank under IBRD Loan4834-IND, is being implemented by the Directorate General of Highways within theMinistry of Public Works over the five-year Loan period following its effectiveness dateof 01 November 2007. Project implementation was initially scheduled to be complete bythe end of 2011 but has now been extended to the end of June 2013.
SRIP originally included twenty two (22) Civil Works packages of road betterment,capacity expansion and new roads & bridges, encompassing urban and inter - urbanNational Roads in 7 provinces (4 provinces on Java and 3 provinces on Sumatra) andincluded a trial Performance Based Contract (PBC). The scope of civil works howeverhas now been reduced to nineteen (19) packages after dropping two civil workspackages and PBC. Details for these packages are given in Appendix A. TheImplementation Support Component includes two (2) road safety components: theIntegrated Road Safety Management System (IRSMS-1) for the Directorate General ofLand Transport (DGLT) and IRSMS-2 for the Indonesian National Traffic Police Corp.
SRIP project implementation was initially supported by four key consulting assignments:(i) Core Team Consultants (CTC); (ii) Construction Supervision Consultants for non-Metropolitan roads (CSC-1); (iii) Construction Supervision Consultants for Metropolitanroads (CSC-2); and (iv) Procurement Advisor, which has now been demobilised. The
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
2
original Core Team Consultants responsibilities included a pilot road safety audit onSemarang Demak and following the successful completion of this audit, the scope ofworks was modified to include road safety audits on all SRIP packages.
2.3. Objectives of the Road Safety Audit ReportThe objectives of this Road Safety Audit report are to summarise the systematicreview/checking of the safety aspects of the completed road plans (DED plans), trafficschemes and list the Problems and make feasible Recommendations forimprovements to the designs and construction process.
2.4. Project Location PlanThe proposed bypass project is shown below
Project Map Showing Partial Completion & SRIP Sections
2.5. Project InformationApproximately half the original SRIP project has already been completed with localfunding, see Project Location Map above and transition between uncompleted andcompleted in photo below.
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
3
Typical completed section shown above and typical cross-sections of proposed SRIPproject are shown below:
Start ofcompleted
section STA6+400
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
4
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
5
2.6. Plans and DocumentsThe documents used in this audit were the contract drawings dated April 2011, but onlyDecember 2007 documents were in site office. The project has changed dramaticallysince original designs and aproximately half is already completed with local funding.
Contract Drawings Used for Audit (2011) & On Site (2007)
2.7. Traffic VolumesThe existing road section has a high volume of traffic, mainly heavy trucks carrying coaland palm oil, or empty, and a small but important number of vulnerable road users;motorcyclists and pedestrians.
The high volume of traffic in the area reinforces the need to provide a safe road.
2.8. Members of the Audit TeamThe road safety audit team members are from the Core Team Consultants of SRIP:
Mike Goodge - Senior Road Safety Audit EngineerAgus Herudianto - Road Safety Audit Engineer
2.9. Site VisitThe site was visited on 18th January, during daylight hours and darkness and travelledin both directions. The weather was fine.
The contractors only mobilised a few weeks back and only a few graders and truckswere in evidence, forming drainage channels at a few locations
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
6
Meetings were held with on the project and in the site office with the following:Mr Idwan Rozanova, Supervision EngineerMr Suyadi, Quality EngineerMr Edi Sunaryo, Chief InspectorMr Edi Susanto, ContractorMr Ariansyah, Contractor
Start of Site Visit near End Junction STA 22+550
Office Meeting: Reviewing Junctions & Pavement Material Tests
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
7
Reviewing Junction 8+450 & Pavement Material Test Site
2.10 Completed Sections
In a letter dated June 1, 2011, to Mr Harris Batubara, (Director of Planning, DirectorateGeneral of Highways), Mr Mitsuyoshi Asada, (World Bank Task Team Leader SRIP)suggested several measures still need to be carried out on the completed sectionincluding: that the project provide school safety zones for two schools, (sekolah DasarNegeri 211/IV in Kota Baru and Sekolah Dasar Negeri 207/IV in Kecematan JambiSelatan) that have direct access to the road to provide safe access for school children.The locations of these two schools are shown in the photos below.
School at STA.3+300
Night-timeVisit
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
8
School at STA.17+000
The World Bank letter also requested protection of the Pertamina pipe at Kenaliintersection STA 16+415, see below.
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
9
2. Problems and Recommendations
3.1 Existing Pavement Conditions
Problem
The existing pavement is in very poor condition at many locations and extremelydamaged in others. This is causing very chaotic conditions at times and many problems,mainly to trucks, involving congestion, getting stuck, breaking down and over-turning.
Congestion & Extremely Bad Road Condition near End of Project
Queue Approaching End of Project
The congestion was caused by very poor road condition and trucks trying to avoid deepholes but most could not. This problem lead to grid-lock at times.
One truck did get stuck during the night visit and had to be hauled out by another
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
10
Road Condition near End of Project
Other very poor sections of road are shown below:
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
11
The bad road condition had consequences related to safety. Several vehicles wereobserved being repaired, on or at the side of the road, see below:
Three vehicles were seen to be completely stuck, one at night. The truck below had tobe pushed out of the deep hole by a contactors grader. The grader then repaired thehole.
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
12
Grader Repairing Hole After Removing Stuck Truck
Truck Fell in Ditch in Middle of Daytime 18th January
Truck completelystuck a few metres
from signal junction atSTA 8+450
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
13
All these problems have safety implications as they lead to frustrated drivers, damagedvehicles and severe conflicts between heavy trucks and motorcycles.
Conditions are also intolerable for pedestrians at many locations, but luckily there arevery few pedestrians even at the junctions, (see photos throughout this report).
Typical Shoulder Conditions at Many Sections of Project
Section 1.8 of Contract Specifications, Maintenance of Traffic Flow, see APPENDIX D,states the following:
It is the intent of the Article in this Section to ensure that during the performanceof the Works al existing roads are kept open for traffic and are maintained in asafe and usable condition ----
The word traffic in this section often connoted as any kind of vehicles shallmean all vehicles and pedestrians
There is little evidence on site of this duty being carried out. While one grader did helpat truck near STA 8+450, and repair the deep hole, there was no staff and no equipmentapparent near the worst problem near STA 22+000
Recommendations
The contractor now has a duty to maintain the existing road in a safecondition and it needs to be a top priority for his staff and equipment.
A priority list of worst locations should be agreed and tackled as a matterof urgency
Liaison is needed with local police to decide best traffic management. Theyare active on the road, see below:
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
14
Problems over materials used needs to be resolved immediately, seebelow:
3.2 Pavement MaterialsProblemDuring meetings with the Supervision Engineer and Contractors, there was muchdiscussion on the difficulties of specifying the correct pavement material to repair orrebuild the road
The material for reconstruction is AC-WC, AC-BC, AC-Base, Aggregate Base Class A,Aggregate Base Class B and Selected Embankment
Efforts to use these materials for repairs had recently been carried out, but veryunsuccessfully, see photos below.
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
15
The materials used had not been effective as the surface deteriorated almost straightaway, see below:
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
16
The Supervision Engineer suggests that the Selected Embankment should be changedto Sandy gravel.
Poor drainage and other works issues probably contributed to continuing problems atthe above location and other sections along the road
Recommendations
The specifications for the most effective materials and methods need to beagreed as soon as possible by the relevant authorities, possibly in thecurrent Design Review
3.3 Completed Section Safety Issues
Problems
There are safety concerns on the completed sections of road that were raised by theWorld Bank, observed on site or in the contract documents that need addressing. Theyare relevant to the continuity of the ring road and thus the SRIP sections.The safety issues include the following:
Installation of school zones, (see also 2.10 above) Completion of junction at STA 16+415 Pedestrian facilities Shoulder construction
Photos illustrating all these items are shown below:
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
17
Junction STA 16+415
Approach to Junction. Tee Junction Sign but Operates as Fast Bend
Centre of Junction
Exposed Pertamina pipe
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
18
The proposed islands and crossings are missing from this junction and there is atemporary wooden pole holding up wires.
The Supervision Engineer stated that this junction will not be carried out under thecurrent SRIP project.
The World Bank letter of June 1, 2011 specifically requested protection of the Pertaminapipe at this location and it is understood that this is currently being addressed within thelocally funded project but with no intention of completing the junction to the originaldesign, shown below
Design for Junction at STA 16+415
Pedestrian Facilities
Homemade Safety Feature at Pedestrian Crossing
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
19
The local communities shown above have tried to increase the warning of pedestriansand slow traffic by the home-made features shown above. This should have be donecorrectly by the designer
Shoulder Construction
Typical Shoulder Failure Caused by Heavy TrucksThe completed shoulders, (APBN project), comprise Aggregate Base Class Bcovered with SST (Burtu).
The proposed material for the shoulders in the SRIP BOQ is Aggregate based class Sand open graded and thus weaker than the completed sections
Even though the APBN project was only finished in December 2011, there are manydamaged sections already. This does not bode well for the proposed shoulder design.
Recommendations Discussions need to take place between relevant agencies to agree how
additional works can be carried out on the completed sections, including thefollowing;
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
20
School zones need to be installed at STA.17+000 and STA.3+300 oncompleted sections of road
Additional signing and rumble strips should be installed at the busiestcrossings to replace home-made features on the completed sections of road
Junction at STA 16+415 needs completion, see 3.5 below Lessons learned from the completed sections need to be applied to the SRIP
construction as follows: Bends on the new project need to be designed to best practice on the
completed section, see 3.4 below Shoulder design in new sections needs to be reviewed to avoid early failure,
see 3.6
3.4 Bends
Problem
There are many bends on the new project with a variety of different signs but no clearindication of the proposed delineation using guard rails. See contract drawings below:
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
21
Sharp Bend Above Has No Adjacent Warning SignsOnly Series of Bends Signs Some Way in Distance
Three of the 4 standard types of bend warning signs are used but most need guideposts too to be effective, particularly the Series of Bends signs 1g or 1f, see below
Guidepost Spacing but No Schedule of Locations
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
22
The photos below illustrate the benefit of having well located guide posts to give muchmore information to motorists than the warning signs
Series of Bends Sign on Completed Road but No Guide Posts
Bend That is Very Well Defined by Guide Posts
Guide Posts Work Well at Night Too
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
23
Bend on Unimproved Road Without Guide Posts Note Skid Mark
Guide Posts Also Used at Embankments & Culverts
Problem
There are 250 guide posts in the BOQ but without any information as to where they areto located
There are many bends that need good delineation as the warning signs are notadequate when used alone. There are also some embankments and culverts requiringguideposts
Recommendation
A schedule of guideposts needs to be drawn up to determine numbersat each bend, embankment and culverts to ensure there is an adequatenumber within the BOQ
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
24
3.5 Junctions
Problems
Junctions design and construction in Indonesia typically has weaknesses that causesafety problems, particularly for pedestrians. This can be observed by looking atexisting junctions in Jambi and the proposed designs for the junctions, see below:
Crossing in Jambi Leading to Drain & Raised Island Unsuitable for Pedestrians
Close-up of Drain Above Footpath at Existing Junction STA 0+000
Landscaping is a great benefit to the environment and has a calming effect onmotorists that is good for safety but it also leads to many problems too. It often blockspedestrian movements as shown above and often hides signs, see below:
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
25
U Turn Sign Hidden by Palm Tree U Turn Sign in Front of Palm Tree
Best Practice is to Only Allow Low Level Planting Near Junctions or Gaps
Recommendations
Care needs to be taken at all junctions to ensure safe movement ofpedestrians particularly at the landscaped islands
Landscaping maintenance isusually very good in cities
but often very poor ormissing in rural locations
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
26
Landscaping and planting should not obscure any signs or shortpedestrians at planting or any time in the future
Planting should be planned with an awareness of the level ofmaintenance that will occur to minimise safety problems to road usersand maintenance workers
Landscaping always requires maintenance workers to be exposed totraffic thus they need to be trained in working safely and to wear highvisibility clothing
Junction STA 0+000
The proposed signalised junction designs are shown below together with photos ofexisting conditions
Proposed Junction Layout & Signal Phasing. Note Proposed Pedestrian PhasesConflicting with Green Signals
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
27
Proposed Landscaping of Islands Note Location of Crossings
Proposed design of islands
Not pedestrian friendly
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
28
Conflicts in Centre of Junction
Approach from Jambi Broken Pedestrian Signals
Existing Ring Roadapproach to
junction at STA0+000
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
29
Many Mini-busses Near Junction
Median on Leg to Jambi as Seen from Junction
Median on Leg to Jambi
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
30
Proposed Junction Median Ends Prior to existing Median (Not Shown)
Unacceptable Narrowing at Start of Bypass
Problems
The proposed narrow neck at the start of the ring road will lead to serious conflicts
The proposed landscaped islands will cause serious problems for pedestrianmovements
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
31
The signal phasing shows conflicts between pedestrians and vehicles
Signal head details are insufficient to ensure optimum locations and high specifications
There are no provisions for busses
There is a median on Jambi leg a short distance from junction that appears to beignored in the design
Recommendations
The proposed landscaped islands and crossings should be redesigned toensure easy and safe pedestrian movements and a much wider approachto the bypass
The signal phasing should be revised to remove conflicts betweenpedestrians and vehicles
Signal head locations and specifications should be determined to includefar side signals, countdown timers and high luminosity, See appendix F
Add bus lay-bys to match existing or expected usage The design of the central island on Jambi leg needs reviewing to be
compatible with median a short distance away
Countdown Timers Add Greatly to Visibility Especially at Night
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
32
Junction STA 8+450
The proposed signalised junction designs are shown below together with photos ofexisting conditions
Proposed Layout & Signal Phasing
Proposed Signal Locations are Inadequate Note no Far Side Signals & SomeHeads Behind Stop Line, Circled
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
33
Pedestrian Phases are Unclear as Four Crossings on Each Approach
Proposed Landscaping Will Block Pedestrian Movements
Approach Travelling Westward
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
34
Defective Countdown & Signal Heads
Current conditions are poor and many signals are very difficult to see due to poorlocation and broken equipment.
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
35
The bright sun makes the problems worse when travelling easterly, see below:
Problems
The proposed landscaped islands will cause serious problems for pedestrianmovements
The signal phasing is insufficient to show all pedestrian movements
Signal head details are insufficient to ensure optimum locations and high specifications
Recommendations
The proposed landscaped islands and crossings should be redesigned toensure easy and safe pedestrian movements
The signal phasing should be revised to show all pedestrian movementsand phases
Signal head locations and specifications should be determined to includefar side signals, countdown timers and high luminosity, See appendix F
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
36
Junction STA 16+415
The proposed junction design is shown below together with photos of existingconditions. It is within one of the road sections already completed but as mentionedabove in 3.3, the junction with islands has not been built and the World Bank requestedprotection of a Pertamina pipeline
Proposed Junction Layout
Existing Conditions, Note No Islands
Recommendations
Discussions should be held between interested parties to ensure junctionis completed within one project or another
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
37
The proposed landscaped islands and crossings should be redesigned toensure easy and safe pedestrian movements
Ensure protection of Pertamina pipeline
Junction STA 18+440
The proposed signalised junction designs are shown below together with photos ofexisting conditions
Proposed Layout & Signal Phasing, Note Conflict Between Pedestrian & Vehicle Phases
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
38
Very Poor Design for Pedestrians of Crossings, Islands & Landscaping
Approach Travelling Westerly
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
39
Travelling Easterly
Problems
The proposed crossings and landscaped islands are very poorly drawn and do not allowfor the actual expected pedestrian movements
The signal phasing is insufficient to show all pedestrian movements
Signal head details are insufficient to ensure optimum locations and high specifications
Recommendations
The proposed landscaped islands and crossings should be redesigned toensure easy and safe pedestrian movements
The signal phasing should be revised to show all pedestrian movementsand phases
Signal head locations and specifications should be determined to includefar side signals, countdown timers and high luminosity, See appendix F
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
40
Junction STA 22+550
The proposed junction design at the end of the project is shown below together withphotos of existing conditions
Proposed Junction Layout
Poor design forpedestrians of
crossings,islands &
landscaping
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
41
Existing Landscaped Island
Existing Landscaping Appears Well Maintained but Not Designed for Pedestrians
Problems
The proposed crossings and landscaped island do not allow for the actual expectedpedestrian movements
Recommendations
The proposed landscaped islands and crossings should be redesigned toensure easy and safe pedestrian movements
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
42
3.6 Road side Activity
Problems
Trucks form a very high percentage of the moving traffic but they are also frequentlystopped on the shoulders or in an out of various heavy goods depots and yards. Manyare stated as being overloaded. This causes extreme damage to the old road and isalready causing new shoulders to fail.
The proposed designs and construction methods do not take into account the needs ofthe truckers to stop and they appear to ignore potential for serious damage
Typical of 100s of trucks stopped at Side of Road
Typical Road Side Commercial Activity. Note Shoulder Damage
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
43
Roadside Depot with Heavy Vehicles but Well Designed & Constructed Shoulders& Access
Recommendations The road cross-sections should be designed for the expected heavy truck
use and this should particularly include the following Stronger sealed shoulders where there is regular truck use, including
accesses to depots Design and construction of resting areas and lay-bys A weighbridge should be added to the project or planned
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
44
3.7 Narrow Road
Problems
No Detailed design at approaching the narrow road also, this condition is hazard forroad user where the speed need to be reduced. (From north to south)
The nose of road median is a dangerous moreover the nose is very nearly with the bend(from south to north). In many country the median always get hit by the vehicles werenot designed carefully
Recommendation
Hatch markings on the road where the road becomes narrow. The median should be extended or decreased until the starting
bend(from the south to north)
3.8 Guardrail
Problems
Many of steeps road side with narrow shoulders are hidden in many placesand also could not be seen at contract drawing, as shown in photographbellows;
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
45
Steep side at the junction
Steep side at the junction
Steep side with narrow shoulder
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
46
Steep side with narrow shoulder
Recommendations
The Site Team should be resurveying the condition on sitewhere the steeps road side is more than 2 meter and the detaileddesign for guard rail location should be proposed.
Guard rail must be installed to protect the road users. There is a improvement at the APBN project at the same road
link, but still inadequate, As shown bellows;
The same link road , additional shoulder and noticed with guide post at steep side.(work by APBN 2011)
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
47
Guard rail at narrow shoulders at Ngawi Bypass Project (SRIP Project)
Guide post are installed where the steep is between 1 up to 2 meters height (at NgawiRR Project)
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
48
4 Road Safety Audit of Construction
4.1 Inadequate Safety Culture
Problems
There was little or no warning of construction zones either at start of project or wheremachinery was working
Only the Supervision Engineers & Surveying staff was observed to wear any highvisibility safety clothing
Good Safety Culture
Inadequate Safety Culture
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
49
Recommendations
Carry out an immediate upgrade of traffic management of constructionareas particularly at start and end of project sections, installed projectboards, warning sgns, erection of barriers and increasing the numbers ofcones used
There should be an immediate effort to increase numbers of workerswearing safety clothing
Contractors supervisory staff should set good example by always wearingsafety clothing on site
Follow instruction in contract specifications and advice given inAppendices B & C
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
50
APPENDIX A References Pedoman Audit Keselamatan Jalan (PD T-17-2005-B), PU Prasarana Transportasi (Road
Safety Guidelines (PDT -17 2005 B). Public Works, Transportation) Pedoman Audit Keselamatan di jalan raya (Austroads Standard) edisi ke 2, 2002
(Road safety Audit Guidelines (Austroads Standards) Second edition 2002) Pedoman Teknis Penanaman Pohon Pada Sistem Jaringan jalan 2010
(Technical Guidelines for Planting trees at Road Network System 2010) Pedoman teknis Fasilitas Pejalan Kaki di Perkotaan SK.43/AJ 007/DRJD/1997 Direktorat
Jenderal Perhubungan Darat)(Technical Guidelines for Pedestrian facilities at Cities region, SK.43/AJ007/DRJD/1997, Directorate General land & transportation)
Mewujudkan Jalan Berkeselamatan di Indonesia, Australia Indonesia bekerjasama dalamteknis keselamatan di Jalan. Direktorat Jenderal Bina Marga, INDIE 2010(Making Indonesias Roads Safer, Australia- Indonesia Partnership in Road SafetyEngineering, Directorate General of Bina Marga, INDI 2010)See extracts on construction zone safety below.
Petunjuk Praktis , Keselamatan Jalan Pada Zona Kerja di Jalan, mendukung ProyekEINRIP, Direktorat Jenderal Bina Marga(Practical Guidelines, Road Safety of Construction Zone) to Support EINRIP Projects,Directorate General of Bina Marga
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
51
Appendix B Safety Concerns at Roadworks - English
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
52
Appendix C Safety Concerns at Roadworks Bahasa
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
IBRD Loan No. 4834-IND/7786-ID Palmerah Ring Road Jambi
53
APPENDIX D MAINTENANCE OF TRAFFIC FLOW
Strategic Roads Infrastructure Project (SRIP)
IBRD Loan No. 4834-IND/7786-ID
Appendix F
In specifications chapter XII. Specifications for Traffic Light; explain that the head of traffic lampshould use the LED lamp with diameter head is 30 cm the requirements from DLLAJR under theDepartement of Transportation could be read as shown below;
Bab XII. SpesifikasNo. 1 Goods/Items
LED Traffic Light Colour of LEDConnecting StructureNumber of LEDLED TypeWave LengthPower LampLens Diffuse
Lumination intensityLife timeVoltageFrequencyPower FactorPower ConsumptionOperating Temperature
Humidity
Spesification/features/OtherFacilities
Strategic Roads Infrastructure Project (SRIP) Road Safety Audit
ID Palmerah Ring Road Jambi
54
chapter XII. Specifications for Traffic Light; explain that the head of traffic lampshould use the LED lamp with diameter head is 30 cm the requirements from DLLAJR under theDepartement of Transportation could be read as shown below;
Bab XII. Spesifikasi TeknisSpecifications
Colour of LED : Red Yellow - GreenConnecting Structure : CircleNumber of LED : 200 400 units per Head lamps with Dia. 300 mmLED Type : Super Bright Water Clear 5 mm/10 mmWave Length : M:615-650mm/K:585-597mm/H:500Power Lamp : 18 - 25 wattLens Diffuse : UV Resistant Polycarbonate Dia.30 cm with spots
for reflection of lightLumination intensity : 400 cdLife time : 40.000 50.000 hoursVoltage : 90-125 volt and/or 170-240 volt with 50HzFrequency : 50 HzPower Factor >. 0.9Power Consumption : Red 9.4W/ Yellow 7.8W/ Green 8.6WOperating Temperature : 5 70C
Humidity
Spesification/features/OtherFacilities
Aspects of the light device must be in newcondition, no defects and should bematerials / components as requiredspesification
Road Safety Audit
Palmerah Ring Road Jambi
chapter XII. Specifications for Traffic Light; explain that the head of traffic lampshould use the LED lamp with diameter head is 30 cm the requirements from DLLAJR under the
400 units per Head lamps with Dia. 300 mm: Super Bright Water Clear 5 mm/10 mm
597mm/H:500-509 mm
: UV Resistant Polycarbonate Dia.30 cm with spots
240 volt with 50Hz
: Red 9.4W/ Yellow 7.8W/ Green 8.6W
Aspects of the light device must be in newshould be made of
required in technical