RSRDC. UNIT- II, AJMER. ORGANISATION CHART OF RSRDC UNIT-II, AJMER. P.K.Arora. Vacant (Addl. Charge to Sh. Sunil jain. ARE. Sh. Lokesh Gupte Sh. Lalit Sharma. 3. Sh. Ashish Sharma 4. Sh. Harsh Rai. Financial Work Load in Unit. Rs. In Lacs. - PowerPoint PPT Presentation

Citation preview

Page 1: RSRDC

RSRDC

UNIT- II, AJMER

Page 2: RSRDC

ORGANISATION CHART OF RSRDC UNIT-II, AJMER

P.K.Arora

ARE1. Sh. Lokesh Gupte

2. Sh. Lalit Sharma

3. Sh. Ashish Sharma

4. Sh. Harsh Rai

Vacant(Addl. Charge to Sh. Sunil jain

Page 3: RSRDC

Financial Work Load in UnitS.

No. Name of Work Client Deptt. A& F Sanction Expenditure till date

Balance Work

ARE – I Sh. Lokesh Gupta

1 Construction of ROB with approaches (Excluding railway portion) on Dholpur-Rajakhera road Km-3 on SH-2

PWD 1000.00 579.43 420.57

2 Construction of ROB with approaches at LC No. 472 (1305/6-8 Mania-Marena road) Jhansi-Agra Section.

PWD 1000.00 0.03 999.97

ARE – II Sh. Lalit Sharma

1 Construction of 2 lane ROB with approaches (excluding Railway portion) at MDR 37-A on Nagour-Basni Road in lieu of LC No. 63-C (On NH-89)

PWD 1300.00

ARE – II 600.00 191.45 408.55

ARE - IV 700.00 197.41 502.59

Rs. In Lacs

Page 4: RSRDC

S. No. Name of Work Client

Deptt.A& F

SanctionExpenditure

till dateBalance

Work

ARE – III Sh. Ashish Sharma

1 Construction of ROB & approaches on Bhilwara -Chittorgarh BG Track at Bhilwara. (UIT Work)

UIT Bhilwara

2086.00 1327.31+

385.00(Rly.)

373.69

ARE – IV Sh. Harsh Rai

1 Construction of ROB & approaches on Phalodi-Mandal-Bhilwara road in lieu of LC No. 63-C

PWD 1000.00 870.32 129.68

2 Construction of ROB on Manglana - Makrana road in lieu of LC No. 36 Kuchaman city Makrana section SH-2B

PWD 1000.00 305.16 694.84

ARE – V Sh. Brijesh Mathur of Unit-I,Ajmer

1 Construction of ROB in Km. 70 of Kishangarh -Roopangarh road SH-07 in lieu of LC No. 28 NWR.

PWD 1000.00 843.67 156.33

2 Construction of ROB (excluding Railway portion) and approaches on Ajmer-Beawer road in lieu of LC No. 5A/2E

PWD 1000.00 783.28 216.72

Page 5: RSRDC

Regional Pollution Control Board office, Bhilwara

Completion Cost – Rs. 23.97 lacs

Important Works Completed during last 5 years

Page 6: RSRDC

Construction of ROB at Kishangarh, Ajmer

Total Cost : Rs. 10.00 Crores

Location : Kishangarh, Ajmer

Date of Start : 18.03.2007

Stipulated Date of Completion : 17.01.2008

Expenditure till Date : Rs. 843.96 Lacs

Likely Completion date : 30.6.2010 (Depends on Railway work)

Bottlenecks if any : Two nos span and finishing dependant on railway work

Status of railway work : Sub structure work completed. Idle since last six months due to finalisation of drawing & design of super structure.

Page 7: RSRDC

Construction of ROB at Saradhna, Ajmer

Total Cost : Rs. 10.00 Crores

Location : Beawar road, Ajmer

Date of Start : 17.07.2007

Stipulated Date of Completion : 16.06.2008

Expenditure till Date : Rs. 783.56 Lacs

Likely Completion date : 31.12.2010 (Depends on Railway work)

Bottlenecks if any : Gap slab connecting rly. portion and finishing dependant on railway work

Status of railway work : Lay out & shifting of cable work in progress.

Page 8: RSRDC

Construction of ROB at Bhilwara(UIT Work)

Total Cost : Rs. 20.86 Crores

Location : Bhilwara

Date of Start : 18.03.2007

Stipulated Date of Completion : 17.11.2007Expenditure till Date : Rs. 1327.31 lacs + Rs385.00 lacs (Rly.)Likely Completion date : 31.05.2010 (Depends on Railway work)

Bottlenecks if any : Two nos span and finishing dependant on railway work

Status of railway work : Sub structure work completed.

Super structure work in progress.

Page 9: RSRDC

Construction of ROB at Mandal (Bhilwara)

Total Cost : Rs. 10.00 Crores

Location : Mandal, Bhilwara

Date of Start : 19.07.2007

Stipulated Date of Completion : 18.06.2008Expenditure till Date : Rs. 870.46 LacsLikely Completion date : 30.06.2010 (Depends on Railway work)

Bottlenecks if any : Two nos span and finishing dependant on railway work

Status of railway work : Sub structure work in progress.

Page 10: RSRDC

Construction of ROB at Makrana Distt. - Nagour)

Total Cost : Rs. 10.00 Crores

Location : Makrana, (Distt.-Nagour)

Date of Start : 23.08.2008

Stipulated Date of Completion : 22.07.2009Expenditure till Date : Rs. 390.67 lacs.Likely Completion date : 30.09.2010 (Depends on Railway work)

Bottlenecks if any : Shifting of electric lines & encroachments.

Status of railway work : Work order placed. Work yet not started.

Page 11: RSRDC

Construction of ROB at Nagour

Total Cost : Rs. 13.00 Crores

Location : Nagour

Date of Start : 21.08.2008

Stipulated Date of Completion : 20.07.2009Expenditure till Date : Rs. 405.45 lacs.Likely Completion date : 30.09.2010 (Depends on Railway work)

Bottlenecks if any : -

Status of railway work : Work order issued. Work yet not started.

Page 12: RSRDC

Construction of ROB at Dholpur

Total Cost : Rs. 10.00 Crores

Location : Dholpur

Date of Start : 17.11.2007

Stipulated Date of Completion : 16.10.2008Expenditure till Date : Rs. 609.36 lacs.Likely Completion date : 30.09.2010 (Depends on Railway work)

Bottlenecks if any : -

Status of railway work : Work order issued. Work yet not started.

Page 13: RSRDC

Construction of ROB at Mania-Marena Road

Total Cost : Rs. 10.00 Crores

Location : Mania, Dholpur

Date of Start : -

Stipulated Date of Completion : -Expenditure till Date : Rs. 0.03 lacs.Likely Completion date :

Bottlenecks if any : The present LC No. 472 is a part of Bye pass for ROB at LC No. 463. Hence traffic is to be bye passed at LC No. 473 which requires interlocking. Railway has agreed for interlocking & up gradation. Which shall be completed by Feb-2010. Revised A&F required amounting to Rs. 16.15 Crore Estimate Submitted to CE PWD through ACE Zone Bharatpur

Status of railway work : Revised GAD pending at Railway part for approval, likely to be received in Dec. 2009’

Page 14: RSRDC

Proposed New WorksS. No. Name of Work Client Deptt. Mode Estimated Cost

1 Construction of Academic block at MLV Textile & Engineering College, Bhilwara

MLVT, Bhilwara Actual plus Rs. 350.00 lacs

2 Construction of Urban Co Operative bank at Shastri Nagar Bhilwara

BUCB Bhilwara Actual plus Rs. 50.00 Lacs