    KOREKSI RSUD BENGKULU

    # WAHYU1. ruang irna diganti ac 1hp type wall mounted2. ac ceiling diberi arah semburan3. RUANG IRNA MEMAKAI SAKLAR HOTEL4. LAMPU LANTAI ATAP TL 1X365. LAMPU RUANG MESIN LIFT6. LAMPU RAMP DIGANTI BARRET 27. LAMPU SITE8. DETAIL LAMPU9. DETAIL PEMASANGAN AC10. KABEL TOEVOER DAN LETAK PANEL# NORMAN1. STYLE TABLE EQUIPMENT SISTEM HYDRANT DIGANTI2. KOTAK KONTAK DI LANTAI ATAP TAMBAH 2 (PIT LIFT & DUMB WAITER)3. MATV UNTUK LANTAI 4 TIDAK MENGGUNAKAN SPLITER4. POWER SUPLY SYSTEM MATV DIHILANGKAN5. TABLE SPESIFIKASI BED LIFT6. LIFT SESUAIKAN RAB

    #FAJRAN

    INSTALASI DATA1. SKALA 1502. PATCH PANEL DIGANDI SWICTH PORT3. FO GANTI CAT 64. SH JADI SW

    SISTEM SKEMATIK DATA1. TAMBAH KOLOM MENYESUAIKAN JENIS SWITCH2. KELUARAN DARI SWITCH HUB 1 KABEL3. PEMPOSISIAN SERVER

    SISTEM TELEPON1. PABX JADI 24 EXT

    2. MDF-TP 30

    INSTALASI TELEPON1. KETERANGAN KABEL TELEPON KELUARAN DARI SHAFT LT.12. OUTLET TELEPON LT. 1 KE MDF MELALUI TBT3. OUTLET TELEPON LT.2.3.4 LANGSUNG KE MDF

    INSTALASI PENYALUR PETIR1. PENGHANTAR TURUN SATU TARIKAN, GROUNDING 22. RADIUS PROTEKSI ATAS 50m DIGANTI 120m3. *DETAIL PEMASANGAN (DIGANTI 70mm)4. TURUN MELALUI LIFT

    5. BAK KONTROL ARDE POJOK KANAN ATAS/BAWAH

    #ISTUPL ABK1. SHAFT LANTAI 3 DIBUAT 30CM2. ARAH PIPA + UKURAN3. PIPA UTAMA LT.3 DITAMBAH SLOPE 1%4. SISTEM > KELUARAN LANGSUNG MENUJU EXISTING

    DRAIN

  • 7/26/2019 rsud bengkulu 18 mei.txt

    2/2

    1. RESAPAN DIGAMBAR SEMUA2. SISTEM > BAK KONTROL DIKECILIN

    TS1. EMERGENCY DITAMBAH2. SISTEM > FONT DISAMAKAN3. SISTEM > PAGGING DICABANG

    #AANFA1. KET KABEL NYA DARI FS DAN TBFA2. TAMBAH NOTASI ZONA3. LT.3 TAMBAH DETEKTOR DI RUANG KOSONG4. SIS FA > DARI MCFA KET SEMI ADRESEBLE DIGANTI CONVENSIONAL 10 ZONE5. KELUARAN MCFA DI KASIH KET KE SOUND SISTEM

    AB1. TANGKI AIR PANAS KAP.500L2. RISER JADI 2 OUT3. PRINT GAMBAR EXISTING + PROGRESS4. MENYESUAIKAN SISTEM EXISTING

    #JANUCCTV

    1. PERBAIKAN MAIN CONTROL2. HAPUS KAMERA YANG TIDAK DIGUNAKAN3. SERTAKAN CTB(CAMERA TERMINAL BOX) + MDB (MAIN DISTRIBUTION BOX) DALAM TABEL4. WIRING KABEL DIBEDAKAN LINETYPE NYA (DATA=DASHDOT2 ) NYA=DASHED25. WIRING SISTEM = WIRING LAYOUT6. TAMBAH KAMERA OUTDOOR DI PINTU RAMP (ALL FLOOR) + RUANG TINDAKAN7. TAMBAHKAN CTB TIAP LANTAI8. SEBELUM DVR DIKASIH MDB9. SKALA 1:150

    TRAY1. SKALA 1:1502. ARUS KUAT 30 + ARUS LEMAH 20

    3.NURSECALL1.LEGEND DISESUIKAN DGN RAB2. TAMBAH CEILING SPEAKER AMBIL DI TS3. NYADUR AN NUR4. SIMBOL GANTI SEMUA