Upload
marina-slaton
View
219
Download
0
Embed Size (px)
Citation preview
Rüdiger Schmidt - Wuppertal Januar 2004
1
Der LHC Beschleuniger Der LHC Beschleuniger Rüdiger Schmidt - CERN
Universität Wuppertal
Januar 2004
Herausforderungen
LHC Beschleunigerphysik
LHC Technologie
Operation und Maschinenschutz
Rüdiger Schmidt - Wuppertal Januar 2004 2
Energy and Luminosity Energy and Luminosity Particle physics requires an accelerator colliding beams with a centre-of-mass energy substantially exceeding 1TeV
In order to observe rare events, the luminosity should be in the order of 1034 [cm-1s-2] (challenge for the LHC
accelerator)
Event rate:
Assuming a total cross section of about 100 mbarn for pp collisions, the event rate for this luminosity is in the order
of 109 events/second (challenge for the LHC experiments)
Nuclear and particle physics require heavy ion collisions in the LHC (quark-gluon plasma .... )
][][ 212 cmscmLtN
CERN is the leading European institute for particle physics
It is close to Geneva across the French Swiss border
There are 20 CERN member states, 5 observer states, and many other states participating in research
LHC
CMS
ATLAS
LEP: e+e-
104 GeV/c (1989-2000)
Circumference26.8 km
LHCproton-protonCollider7 TeV/c in theLEP tunnel2 rings
Injectionfrom SPS at450 GeV/c
ATLAS
CMS
Rüdiger Schmidt - Wuppertal Januar 2004 7
LHC: From first ideas to realisationLHC: From first ideas to realisation
1982 : First studies for the LHC project
1983 : Z0 detected at SPS proton antiproton collider
1985 : Nobel Price for S. van der Meer and C. Rubbia
1989 : Start of LEP operation (Z-factory)
1994 : Approval of the LHC by the CERN Council
1996 : Final decision to start the LHC construction
1996 : LEP operation at 100 GeV (W-factory)
2000 : End of LEP operation
2002 : LEP equipment removed
2003 : Start of the LHC installation
2005 : Start of hardware commissioning
2007 : Commissioning with beam planned
Rüdiger Schmidt - Wuppertal Januar 2004 8
To make the LHC accelerator a reality: To make the LHC accelerator a reality: Accelerators physics and ....Accelerators physics and ....
Electromagnetism und Relativity Thermodynamics Mechanics Quantum mechanics Physics of nonlinear systems Solid state physics und surface physics Particle physics and radiation physics Vacuum physics
+ Engineering
Mechanical, Civil, Cryogenics, Electrical, Automation, Computing
Accelerator Physics: An Introduction• Why protons? Why in the LEP tunnel? Why superconducting magnets? Why “two”
accelerators in one tunnel?
LHC Layout The quest for high luminosity and the consequences Beam-Beam interaction Crossing angle and insertion layout LHC Parameters The CERN accelerator complex: injectors and transfer
LHC technology LHC Operation and machine protection Conclusions
OutlineOutline
Accelerator Physics: An Introduction• Why protons? Why in the LEP tunnel? Why superconducting magnets? Why “two”
accelerators in one tunnel?
LHC Layout The quest for high luminosity and the consequences Beam-Beam interaction Crossing angle and insertion layout Wrapping up: LHC Parameters The CERN accelerator complex: injectors and transfer
LHC technology LHC Operation and machine protection Conclusions
OutlineOutline
Rüdiger Schmidt - Wuppertal Januar 2004 11
Particle accelerationParticle acceleration
2
1
s
s
U sdE
Acceleration of a charged particle by an electrical potential
Energy gain given by the potential
UqqEs
s
s
s
2
1
2
1
sdEsdF
For an acceleration to 7 TeV a voltage of 7 TV is required The maximum electrical field in an accelerator is in the
order of some 10 MV/m (superconducting RF cavities) To accelerate to 7 TeV would require a linear accelerator
with a length of about 350 km (assuming 20 MV/m)
12Rüdiger Schmidt - Wuppertal Januar 2004
Acceleration in a cavityAcceleration in a cavity
)(tE
U = 1000000 Vd = 1 mq = e0
E = 1 MeV
-+
beambunchedeConsequenc
mMVaboutfieldMaximum
)t(E(t)Ez
:
/
cos
20
field varying Time
0
13Rüdiger Schmidt - Wuppertal Januar 2004
How to get to 7 TeV: Synchrotron – circular How to get to 7 TeV: Synchrotron – circular accelerator and many passages in RF cavitiesaccelerator and many passages in RF cavities
LINAC (planned for several hundred GeV - but not above 1 TeV)
LHC circular machine with energy gain per turn some MeV
Rüdiger Schmidt - Wuppertal Januar 2004 14
RF systemsRF systems: 400 MHz: 400 MHz
400 MHz system:
all 16 sc cavities (copper sputtered with niobium) for 16 MV/beam were built and assembled in four modules
Power test of the first module
Rüdiger Schmidt - Wuppertal Januar 2004 15
Particle deflection: Lorentz ForceParticle deflection: Lorentz Force
The force on a charged particle is proportional to the charge, and to the vector product of velocity and magnetic field:
)( BvEF
q
• Maximaler Impuls 7000 GeV/c
• Radius 2805 m
• Ablenkfeld B = 8.33 Tesla
• Magnetfeld mit Eisenmagneten maximal 2 tesla, daher werden supraleitende Magnete benötigt
Rep
B
0
z
x
s
v
B
F
Radius
Lorenz Force = accelerating force
Particle trajectory
Radiation field
charged particle
Figure from K.Wille
Energy loss for charged particles by synchrotron radiation
Power emitted for one particle: Ps=e0
2 c
6 0 m0 c2 4
E4
2
with E = energy, m0 = rest mass, e0 = charge, and = radius
Rüdiger Schmidt - Wuppertal Januar 2004 17
Energy loss for charged particles Energy loss for charged particles electrons / protons in LEP tunnelelectrons / protons in LEP tunnel
Elep 100GeV Elhc 7000GeV
Energy loss for one particle per turn:
Ulep 3.844 109 eV Ulhc 8.121 103 eV
Total power of synchrotronradiation:
Number of electrons in LEP: Nlep 1012 Number of protons in LHC Nlhc 1014
Ptotal_lep Nlep Plep Ptotal_lhc Nlhc Plhc
Ptotal_lep 1.278 107 W Ptotal_lhc 2.699 103 W
The power of the synchrotronradiation emitted at the LHC is very small, but the radiation goes into the supraconducting magnets at 1.9 K ... 20 K
Rüdiger Schmidt - Wuppertal Januar 2004 18
assuming LEP with electrons at 7 TeV: lep7 1012
me c2eV
Ulep e02
lep4
3 0
Ulep 9.23 1016 eV
...just assuming to accelerate electrons ...just assuming to accelerate electrons to 7 TeV to 7 TeV
...better to accelerate protons...better to accelerate protons
Accelerator Physics: An Introduction• Why protons? Why in the LEP tunnel? Why superconducting magnets? Why “two”
accelerators in one tunnel?
LHC Layout The quest for high luminosity and the consequences Beam-Beam interaction Crossing angle and insertion layout The CERN accelerator complex: injectors and transfer Wrapping up: LHC Parameters
LHC technology LHC operation and machine protection Conclusions
OutlineOutline
LHC: eight arcs (approximatley circular) and eight long straight section (about 700 m long)
Momentum Cleaning
Betatron Cleaning
Beam dump system
RF + Beam instrumentation
CMS
ATLAS
LHC-BALICE
Rüdiger Schmidt - Wuppertal Januar 2004 22
Beam transportBeam transport
Need for keeping protons on a circle: dipole magnets
Need for focusing the beams:
Particles with different injection parameters (angle, position) separate with time• Assuming an angle difference of 10-6 rad, two particles would separate by
1 m after 106 m. At the LHC, with a length of 26860 m, this would be the case after 50 turns (5 ms !)
The beam size must be well controlled • At the collision point the beam size must be tiny
Particles with (slightly) different energies should stay together
Particles would „drop“ due to gravitation
Rüdiger Schmidt - Wuppertal Januar 2004 23
The LHC arcs: FODO cellsThe LHC arcs: FODO cells
Dipole- und Quadrupol magnets– Particle trajectory stable for particles with nominal momentum
Sextupole magnets– To correct the trajectories for off momentum particles
– Particle trajectories stable for small amplitudes (about 10 mm)
Multipole-corrector magnets– Sextupole - and decapole corrector magnets at end of dipoles
– Particle trajectories can become instable after many turns (even after, say, 106 turns)
QF QD QFdipolemagnets
small sextupolecorrector magnets
decapolemagnets
LHC Cell - Length about 110 m (schematic layout)
sextupolemagnets
Rüdiger Schmidt - Wuppertal Januar 2004 24
Particle stability and supraconducting magnets - Particle stability and supraconducting magnets - Quadrupolar- and multipolar fieldsQuadrupolar- and multipolar fields
LHC
Teilchenschwingungim Quadrupolfeld(kleine Amplitude)
Harmonische Schwingung(Koordinatentransformation)
Kreisbewegung im Phasenraum
z
y
y
y'
LHC
Teilchenschwingungbei nichlinearen Feldernund grosser Amplitude
Amplitude wächst bis zumTeilchenverlust
Keine Kreisbewegung im Phasenraum
z
y
y
y'
Particle oscillations in quadrupole field (small amplitude)
Harmonic oscillation after coordinate transformation
Circular movement in phase space
Particle oscillation assuming non-linear fields, large amplitude
Amplitude grows until particle is lost (touches aperture)
No circular movement in phasespace
Rüdiger Schmidt - Wuppertal Januar 2004 25
Dynamic aperture and magnet imperfectionsDynamic aperture and magnet imperfections
Particles with small amplitudes are in general stable Particles with large amplitudes are not stable The dynamic aperture is the limit of the stability region The dynamic aperture depends on field error - without any field
errors, the dynamic aperture would be large
The magnets should be made such as the dynamic aperture is not too small (say, 10 the amplitude of a one sigma particle, assuming Gaussian distribution)
The dynamic aperture depends also on the working point and on the sextupole magnets for correction of chromatic effects
Accelerator Physics: An Introduction• Why protons? Why in the LEP tunnel? Why superconducting magnets? Why “two”
accelerators in one tunnel?
LHC Layout The quest for high luminosity and the consequences Beam-Beam interaction Crossing angle and insertion layout Wrapping up: LHC Parameters The CERN accelerator complex: injectors and transfer
LHC technology LHC operation and machine protection Conclusions
OutlineOutline
Rüdiger Schmidt - Wuppertal Januar 2004 27
High luminosity by High luminosity by colliding trains of bunchescolliding trains of bunches
Number of „New Particles“
per unit of time:
The objective for the LHC as proton – proton collider is a luminosity of about 1034 [cm-1s-2]
• LEP (e+e-) : 3-4 1031 [cm-1s-2]
• Tevatron (p-pbar) : 3 1031 [cm-1s-2]
• B-Factories: 1034 [cm-1s-2]
212 cmscmLT
N
Rüdiger Schmidt - Wuppertal Januar 2004 28
Luminosity parametersLuminosity parameters
point ninteractio at dimensions beam
beamperbunchesofnumbern
frequency revolution f
bunch per protons of Number N
: with
4
nfNL
yx
b
yx
b
2
What happens with one particle experiencing the force of the em-fields or 1011 protons in the other beam during the collision ?
Accelerator Physics: An Introduction• Why protons? Why in the LEP tunnel? Why superconducting magnets? Why “two”
accelerators in one tunnel?
LHC Layout The quest for high luminosity and the consequences Beam-Beam interaction Crossing angle and insertion layout Wrapping up: LHC Parameters The CERN accelerator complex: injectors and transfer
LHC technology LHC operation and machine protection Conclusions
OutlineOutline
Rüdiger Schmidt - Wuppertal Januar 2004 30
Limitation: beam-beam interactionLimitation: beam-beam interaction
Quadrupole Lense
Beam - Beam Lense
Force
Force
Y
Y
Bunch intensity limited due to this strong non-linearity to about N = 1011
Rüdiger Schmidt - Wuppertal Januar 2004 31
Beam beam interaction determines parametersBeam beam interaction determines parameters
Beam size 16 m, for = 0.5 m
f = 11246 Hz
Beam size given by injectors and by space in vacuum chamber
Number of protons per bunch limited to about 1011
L = N2 f n b / 4 xy
= 3.5 1030 [cm-2 s-1]
with one bunch
with 2808 bunches (every 25 ns one bunch) L = 1034 [cm-2s-1]
Accelerator Physics: An Introduction• Why protons? Why in the LEP tunnel? Why superconducting magnets? Why “two”
accelerators in one tunnel?
LHC Layout The quest for high luminosity and the consequences Beam-Beam interaction Crossing angle and insertion layout Wrapping up: LHC Parameters The CERN accelerator complex: injectors and transfer
LHC technology LHC operation and machine protection Conclusions
OutlineOutline
Rüdiger Schmidt - Wuppertal Januar 2004 33
Large number of bunchesLarge number of bunches
IP
Crossing angle to avoid long range beam beam interaction
Rüdiger Schmidt - Wuppertal Januar 2004 34
Large number of bunchesLarge number of bunches
IP
Crossing angle to avoid long range beam beam interaction
Rüdiger Schmidt - Wuppertal Januar 2004 35
Large number of bunchesLarge number of bunches
IP
Crossing angle to avoid long range beam beam interaction
Rüdiger Schmidt - Wuppertal Januar 2004 36
distance about 100 m
Interaction point
QD QD QF QD QF QD
Experiment
Focusing quadrupole for beam 1, defocusing for beam 2 High gradient quadrupole magnets with large aperture (US-JAPAN) Total crossing angle of 300 rad Beam size at IP 16 m, in arcs about 1 mm
Crossing angle for multibunch operationCrossing angle for multibunch operation
Rüdiger Schmidt - Wuppertal Januar 2004 37
Layout of insertion for ATLAS and CMS Layout of insertion for ATLAS and CMS
200 m
inner quadrupoletriplet
separationdipole (warm)
recombinationdipole
quadrupoleQ4
quadrupoleQ5
ATLAS or CMS
inner quadrupoletriplet
separationdipole
recombinationdipole
quadrupoleQ4
quadrupoleQ5
collision point
beam I
Example for an LHC insertion with ATLAS or CMS
24 m
beamdistance194 mm
beam II
Accelerator Physics: An Introduction• Why protons? Why in the LEP tunnel? Why superconducting magnets? Why “two”
accelerators in one tunnel?
LHC Layout The quest for high luminosity and the consequences Beam-Beam interaction Crossing angle and insertion layout The CERN accelerator complex: injectors and transfer LHC Parameters
LHC technology LHC operation and machine protection Conclusions
OutlineOutline
Rüdiger Schmidt - Wuppertal Januar 2004 39
summarising constraints and summarising constraints and consequences….consequences….
Centre-of-mass energy must well exceed 1 TeV, LHC installed into LEP tunnel
Colliding protons, and also heavy ions Magnetic field of 8.3 T with superconducting magnets Large amount of energy stored in magnets
Luminosity of 1034
Need for “two accelerators” in one tunnel with beam parameters pushed to the extreme – with opposite magnetic dipole field
Large amount of energy stored in beams
Economical constraints and limited space Two-in-one superconducting magnets
Rüdiger Schmidt - Wuppertal Januar 2004 40
Very high beam currentVery high beam current
Many bunches and high energy -
Energy in one beam about 330 MJ
Beam stability and magnet field quality Synchrotron radiation - power to cryogenic system
Dumping the beam in a safe way Beam induced quenches (when 10-7 of beam hits magnet at 7 TeV) Beam cleaning (Betatron and momentum cleaning)
Radiation, in particular in experimental areas from beam collisions (beam lifetime is dominated by this effect)
Photo electrons - accelerated by the following bunches
Rüdiger Schmidt - Wuppertal Januar 2004 41
Challenges:Challenges: Energy stored in the beam Energy stored in the beam
courtesy R.Assmann Momentum [GeV/c]
Ene
rgy
stor
ed in
the
bea
m [
MJ]
Transverse energy density: even a factor of 1000 larger
x 200
x 10000
One beam, nominal intensity(corresponds to an energy that melts 500 kg of copper)
Rüdiger Schmidt - Wuppertal Januar 2004 42
Accelerator Physics: An Introduction• Why protons? Why in the LEP tunnel? Why superconducting magnets? Why
“two” accelerators in one tunnel?
LHC Layout The quest for high luminosity and the consequences Beam-Beam interaction Crossing angle and insertion layout Wrapping up: LHC Parameters The CERN accelerator complex: injectors and transfer LHC technology LHC operation and machine protection Conclusions
OutlineOutline
Rüdiger Schmidt - Wuppertal Januar 2004 43
Getting beam into the LHCGetting beam into the LHC
Beam size of protons decreases with energy: 2 = 1 / E Beam size large at injection Beam fills vacuum chamber at 450 GeV
If the energy would be lower ... larger vacuum chamber and larger magnets – increased cost magnets and power converter limitations (dynamic effects,
stability, …) issues of beam stability
Injection from the SPS at 450 GeV, via two transfer lines, into the LHC
Rüdiger Schmidt - Wuppertal Januar 2004 44
Autumn 2004
Injector complex Injector complex
High intensity beam from the SPS into LHCat 450 GeV via TI2 and TI8
LHC accelerates to 7 TeV
LEIR
CPS
SPS
Booster
LINACS
LHC
3
45
6
7
8
1
2TI8
TI2
Ions
protons
Extraction
Beam 1Beam 2
Summer 2003
Spring 2006
Rüdiger Schmidt - Wuppertal Januar 2004 45
Injector ComplexInjector Complex
Already today, beams are available close to the nominal beam parameters required for the LHC
Fast extraction from the SPS with a new system into a new line successfully done in summer 2003
B.Goddard
Rüdiger Schmidt - Wuppertal Januar 2004 46
Accelerator Physics: An Introduction• Why protons? Why in the LEP tunnel? Why superconducting magnets? Why
“two” accelerators in one tunnel?
LHC Layout The quest for high luminosity and the consequences Beam-Beam interaction Crossing angle and insertion layout Wrapping up: LHC Parameters The CERN accelerator complex: injectors and transfer LHC technology LHC operation and machine protection Conclusions
OutlineOutline
Rüdiger Schmidt - Wuppertal Januar 2004 47
LHC accelerator in the tunnelLHC accelerator in the tunnel
LHC Main Systems
Superconducting magnetsCryogenicsVacuum systemPowering (industrial use of High Temperature Superconducting material)
Rüdiger Schmidt - Wuppertal Januar 2004 48
1232 main dipoles +
3700 multipole corrector magnets
392 main quadrupoles +
2500 corrector magnets
Regular arc:
Magnets
Rüdiger Schmidt - Wuppertal Januar 2004 49
Regular arc:
Cryogenics
Supply and recovery of helium with 26 km long cryogenic distribution line
Static bath of superfluid helium at 1.9 K in cooling loops of 110 m length
Connection via service module and jumper
Rüdiger Schmidt - Wuppertal Januar 2004 50
Insulation vacuum for the cryogenic distribution line
Regular arc:
Vacuum
Insulation vacuum for the magnet cryostats
Beam vacuum for
Beam 1 + Beam 2
Rüdiger Schmidt - Wuppertal Januar 2004 51
Regular arc:
Electronics
Along the arc about several thousand electronic crates (radiation tolerant) for:
quench protection, power converters for orbit correctors and instrumentation (beam, vacuum + cryogenics)
Rüdiger Schmidt - Wuppertal Januar 2004 52
Installation of cryogenic distribution Installation of cryogenic distribution line in the LHC tunnel – started line in the LHC tunnel – started during summer 2003during summer 2003
Rüdiger Schmidt - Wuppertal Januar 2004 53
1232 DipolmagnetsLength about 15 mMagnetic Field 8.3 TTwo beam tubes with an opening of 56 mm
Dipole magnets for the LHCDipole magnets for the LHC
Rüdiger Schmidt - Wuppertal Januar 2004 55
Superconducting cable for 12 kA
15 mm / 2 mm
Temperature 1.9 K cooled with Helium
Force on the cable:
F = B * I0 * L
with
B = 8.33 T
I0 = 12000 Ampere
L = 15 m
F = 165 tons
56 mm
Rüdiger Schmidt - Wuppertal Januar 2004 56
Beam tubes
Supraconducting coil
Nonmagetic collars
Ferromagnetic iron
Steelcylinder for Helium
Insulationvacuum
Supports
Vacuumtank
Rüdiger Schmidt - Wuppertal Januar 2004 57
Magnetic field - current density - temperatureMagnetic field - current density - temperature
Superconducting
material determines:
Tc critical temperature
Bc critical field
Production process:
Jc critical current density
Temperature [K]A
pplie
d fie
ld [
T]
Superconductingstate
Normal state
Bc
TcLower temperature
increased current density
Typical for NbTi:
2000 A/mm2
@ 4.2K, 6TFür 10 T, Operation less than 1.9 K required
Copyright A.Verweij
Rüdiger Schmidt - Wuppertal Januar 2004 58
Supraconducting wireSupraconducting wire
1 mm6 m
Typical value for operation at 8 T and 1.9 K: 800 A
Copyright A.Verweij
Rutherford cableRutherford cable
width 15 mm
Rüdiger Schmidt - Wuppertal Januar 2004 59
Dipole magnet production: Snapshot at industryDipole magnet production: Snapshot at industry
L.Rossi
Rüdiger Schmidt - Wuppertal Januar 2004 60
Storage of dipole cold masses Storage of dipole cold masses waiting for cryostating waiting for cryostating
Rüdiger Schmidt - Wuppertal Januar 2004 61
Histogram of the number of quenches to reach 8.33 Tesla for the f irst 53 LHC preseries dipoles
0
2
46
8
10
1214
16
18
2022
24
26
0 1 2 3 4 5 6 7 notreached
Number of quenches to reach 8.33T
Nu
mb
er o
f m
agn
ets
01 02 03
Performance of LHC dipole magnetsPerformance of LHC dipole magnets
Rüdiger Schmidt - Wuppertal Januar 2004 62
Challenges for dipole productionChallenges for dipole production
The magnets must reach without quenching a field of at least 8.3 Tesla, and possibly 9 Tesla
The field quality must be excellent (relative field errors much less than 0.1 %, positioning of collars to some 10 m)
The geometry must be respected – and the magnet must be correctly bent
All magnets must be produced in time, delivered to CERN, installed in the cryostats, cold tested, and finally installed into the LHC tunnel
Rüdiger Schmidt - Wuppertal Januar 2004 63
Operation and machine Operation and machine protectionprotection
Rüdiger Schmidt - Wuppertal Januar 2004 64
OutlineOutline
Energy stored in the LHC magnets and beams Charging the energy LHC dipole magnets - discharging the energy
• irregular discharge - magnet quenches
LHC Beams - discharging the energy• regular and irregular discharge
Magnets facing Beams
Rüdiger Schmidt - Wuppertal Januar 2004 65
Energy stored in dipole magnetsEnergy stored in dipole magnets
10 GJoule……
corresponds to the energy of 1900 kg TNT corresponds to the energy of 400 kg Chocolate corresponds to the energy for heating and melting 12000 kg of copper
Could this damage equipment: How fast can this energy be released?
E dipole = 0.5 L dipole I 2dipole
Energy stored in one dipole is 7.6 MJoule
For all 1232 dipoles in the LHC: 9.4 GJ
Rüdiger Schmidt - Wuppertal Januar 2004 66
OutlineOutline
Energy stored in the LHC magnets and beams Charging the energy LHC dipole magnets - discharging the energy
• irregular discharge - magnet quenches
LHC Beams - discharging the energy• regular and irregular discharge
Magnets facing Beams
Rüdiger Schmidt - Wuppertal Januar 2004 67
0
2000
4000
6000
8000
10000
12000
-4000 -2000 0 2000 4000
time from start of injection (s)
dip
ole
cu
rre
nt (A
)
energy
ramp
preparation and access
injection phase
coast
coast
LHC magnetic cycleLHC magnetic cycle
L.Bottura
450 GeV
7 TeV
start of the
ramp
Rüdiger Schmidt - Wuppertal Januar 2004 68
0
2000
4000
6000
8000
10000
12000
-4000 -2000 0 2000 4000
time from start of injection (s)
dip
ole
cu
rre
nt (A
)
injection phase12 batches from the SPS (every 20 sec)
one batch 216 / 288 bunches
LHC magnetic cycle - Beam injectionLHC magnetic cycle - Beam injection
L.Bottura
450 GeV
7 TeV
beam dump
Rüdiger Schmidt - Wuppertal Januar 2004 69
OutlineOutline
Energy stored in the LHC magnets and beams Charging the energy LHC dipole magnets - discharging the energy
• irregular discharge - magnet quenches
LHC Beams - discharging the energy• regular and irregular discharge
Magnets facing Beams
Rüdiger Schmidt - Wuppertal Januar 2004 70
Operational margin of a superconducting magnetOperational margin of a superconducting magnet
Temperature [K]
App
lied
field
[T]
Superconductingstate
Normal state
Bc
Tc
9 K
Applied Magnetic Field [T]
Bc critical field
1.9 K
quench with fast loss of
~5 · 109 protons
quench with fast loss of ~5 · 106 protons
8.3 T
0.54 T
QUENCH
Tc critical
temperature
Rüdiger Schmidt - Wuppertal Januar 2004 71
Quench - transition from superconducting Quench - transition from superconducting state to normalconducting statestate to normalconducting state
Quenches are initiated by an energy in the order of mJ (corresponds to the energy of 1000 protons at 7 TeV)
Movement of the superconductor by several m (friction and heat dissipation)
Beam losses
Failure in cooling
To limit the temperature increase after a quench (in 1s to 5000 K)
The quench has to be detected
The energy is distributed in the magnet by force-quenching the coils using quench heaters
The magnet current has to be switched off within << 1 second
Rüdiger Schmidt - Wuppertal Januar 2004 72
OutlineOutline
Energy stored in the LHC magnets and beams Charging the energy LHC dipole magnets - discharging the energy
• irregular discharge - magnet quenches
LHC Beams - discharging the energy• regular and irregular discharge
Magnets facing Beams
Rüdiger Schmidt - Wuppertal Januar 2004 73
Regular (very healthy) operationRegular (very healthy) operation
Assuming that the beams are colliding at 7 TeV
Single beam lifetime larger than 100 hours…..• corresponds to a loss of about 1 kW / beam
• far below the cooling power of the cryogenic system, even if all particles would be lost at 1.9 K
• losses should be either distributed across the machine or captured in the warm cleaning insertions
Collision of beams with a luminosity of 1034 cm-2s-1 • lifetime of the beam can be be dominated by collisions
• 109 protons / second lost per beam / per experiment (in IR 1 and IR 5 - high luminosity insertions) - this is about 1.2 kW
• large heat load to close-by superconducting quadrupoles
• heavy shielding around the high luminosity IPs
Rüdiger Schmidt - Wuppertal Januar 2004 74
End of data taking in normal operationEnd of data taking in normal operation
Luminosity lifetime estimated to be approximately 10 h (after 10 hours only 1/3 of initial luminosity)
Beam current somewhat reduced - but not much Energy per beam still about 200-300 MJ Beams are extracted in beam dump blocks
The only component that can stand a fast loss of the full beam at top energy is the beam dump block - all other components would be damaged
At 7 TeV, fast beam losses with an intensity of about 5% of a “nominal bunch” could damage superconducting coils
Rüdiger Schmidt - Wuppertal Januar 2004 75
LHC ringLHC ring: 3 insertions for machine : 3 insertions for machine protection systems protection systems
Beam Cleaning IR3 (Momentum)
Beam Cleaning IR7 (Betatron)
Beam dump system IR6
RF+ Beam monitors IR4
Rüdiger Schmidt - Wuppertal Januar 2004 76
Beam losses into materialBeam losses into material
Proton losses lead to particle cascades in materials The energy deposition leads to a temperature increase For the maximum energy deposition as a function of material there is no straightforward expression Programs such as FLUKA are being used for the calculation of the energy deposition
Magnets could quench…..• beam lost - re-establish condition will take hours
The material could be damaged…..• melting
• losing their performance (mechanical strength)
Repair could take several weeks
Rüdiger Schmidt - Wuppertal Januar 2004 77
Damage of material for impact of a pencil beamDamage of material for impact of a pencil beam
Maximum energy deposition in the proton cascade (one proton): Emax_C 2.0 106
J
kg
Specific heat of graphite is cC_spec 710.60001
kg
J
K
To heat 1 kg graphite by, say, by T 1500K , one needs: cC_spec T 1 kg 1.07 106 J
Number of protons to deposit this energy is: cC_spec T
Emax_C5.33 10
11
Maximum energy deposition in the proton cascade (one proton): Emax_Cu 1.5 105
J
kg
Specific heat of copper is cCu_spec 384.56001
kg
J
K
To heat 1 kg copper by, say, by T 500K , one needs: cCu_spec T 1 kg 1.92 105 J
Number of protons to deposit this energy is: cCu_spec T
Emax_Cu1.28 10
10 copper
graphite
Rüdiger Schmidt - Wuppertal Januar 2004 78
Schematic layout of beam dump system in IR6Schematic layout of beam dump system in IR6
Q5R
Q4R
Q4L
Q5L
Beam 2
Beam 1
Beam Dump Block
Septum magnet deflecting the extracted beam H-V kicker
for painting the beam
about 700 m
about 500 m
Fast kicker magnet
Rüdiger Schmidt - Wuppertal Januar 2004 79
Beam Dump Block - LayoutBeam Dump Block - Layout
about 8 m
L.Bruno
concrete shielding
beam absorber (graphite)
Rüdiger Schmidt - Wuppertal Januar 2004 80
Beam on Beam Dump BlockBeam on Beam Dump Block
about 35 cm
M.Gyr
initial transverse beam dimension in the LHC about 1 mm
beam is blown up due to long distance to beam dump block
additional blow up due to fast dilution kickers: painting of beam on beam dump block
beam impact within less than 0.1 ms
Rüdiger Schmidt - Wuppertal Januar 2004 81
L.Bruno: Thermo-Mechanical Analysis with ANSYS
Temperature of beam dump block at 80 cm insideTemperature of beam dump block at 80 cm inside
up to 800 0C
Rüdiger Schmidt - Wuppertal Januar 2004 82
OutlineOutline
Energy stored in the LHC magnets and beams Charging the energy LHC dipole magnets - discharging the energy
• irregular discharge - magnet quenches
LHC Beams - discharging the energy• regular and irregular discharge
Magnets facing Beams
Rüdiger Schmidt - Wuppertal Januar 2004 83
Beam lifetime with nominal intensity at 7 TeVBeam lifetime with nominal intensity at 7 TeV
Beam lifetime
Beam power into equipment (1 beam)
Comments
100 h 1 kW Healthy operation
10 h 10 kW Operation acceptable, collimation must absorb large fraction of beam energy
(approximately beam losses = cryogenic cooling power at 1.9 K)
0.2 h 500 kW Operation only possibly for short time, collimators must be very efficient
1 min 6 MW Equipment or operation failure - operation not possible - beam must be dumped
<< 1 min > 6 MW Beam must be dumped VERY FAST
Failures will be a part of the regular operation and MUST be
anticipated
Rüdiger Schmidt - Wuppertal Januar 2004 84
+- 3 ~5 mm
Beam +/- 3 sigma
56.0 mm
Beam in vacuum chamber with beam screen at 450 GeVBeam in vacuum chamber with beam screen at 450 GeV
Rüdiger Schmidt - Wuppertal Januar 2004 85
+- 3 ~1.3 mm
Beam +/- 3 sigma
56.0 mm
Beam in vacuum chamber with beam screen at 7 TeVBeam in vacuum chamber with beam screen at 7 TeV
Rüdiger Schmidt - Wuppertal Januar 2004 86
Beam +/- 3 sigma
56.0 mm
1 mm
+/- 8 sigma = 4.0 mm
Example: Setting of collimators at 7 TeV - with luminosity opticsExample: Setting of collimators at 7 TeV - with luminosity optics Beam must always touch collimators first !Beam must always touch collimators first !
R.Assmanns EURO
Collimators at Collimators at 7 TeV, squeezed7 TeV, squeezedopticsoptics
Rüdiger Schmidt - Wuppertal Januar 2004 87
Jaws (blocks of solid materials such as copper, graphite, ….) very close to the beam to absorb more than 99.9 % of protons that would be lost
Primary collimators: Intercept primary haloImpact parameter: ~ 1 Impact parameter: ~ 1 mmScatter protons of primary haloConvert primary halo to secondary off-momentum halo
Secondary collimators: Intercept secondary haloImpact parameter: ~ 200 Impact parameter: ~ 200 mmAbsorb most protonsLeak a small tertiary halo
Particles
Beam axis
Impactparameter
Collimator jaw
Basic concept of Basic concept of two stage two stage collimationcollimation
R.Assmann / J.B.Jeanneret
Rüdiger Schmidt - Wuppertal Januar 2004 88
Accidental kick by the beam dump kicker at 7 TeVAccidental kick by the beam dump kicker at 7 TeV part of beam touches collimators (about 20 bunches from 2800)part of beam touches collimators (about 20 bunches from 2800)
P.Sievers / A.Ferrari / V.Vlachoudis
circulating beam
Rüdiger Schmidt - Wuppertal Januar 2004 89
Accidental kick by the beam dump kicker at 7 TeVAccidental kick by the beam dump kicker at 7 TeV part of beam touches collimators (about 20 bunches from 2800)part of beam touches collimators (about 20 bunches from 2800)
P.Sievers / A.Ferrari / V. Vlachoudis
Beryllium
Rüdiger Schmidt - Wuppertal Januar 2004 90
Optimisation of Cleaning systemOptimisation of Cleaning system
Requirements for collimation system take into account failure scenarios and imperfect operation
• Worst case is the impact of about 20 bunches on the collimator due to pre-firing of one dump kicker module
Material for collimator is being reconsidered - low Z material is favoured Impedance to be considered - conducting material is favoured More exotic materials are considered: copper loaded graphite,
beryllium, partially plated copper ….
Rüdiger Schmidt - Wuppertal Januar 2004 92
Recalling LHC challenges
Enormous amount of equipment Complexity of the LHC accelerator New challenges in accelerator physics with LHC beam
parameters
20052004
1 2 3 4 5 6 7 8 9 10 11 12
2006 2007
1 2 3 4 5 6 7 8 9 10 11 121 2 3 4 5 6 7 8 9 10 11 121 2 3 4 5 6 7 8 9 10 11 12
Fabrication of equipment
Installation
Beam in one sectorLHC Beam commissioning
LHC “hardware” commissioning
Rüdiger Schmidt - Wuppertal Januar 2004 93
ConclusionsConclusions
The LHC is installed and commissioned in eight (rather)independent sectors - that allows for activities to be performed in parallel
…….... to avoid a lengthy and painful start-up when LHC hardware ready for two beam
The LHC is a global project with the world-wide high-energy physics community devoted to its progress and results
As a project, it is much more complex and diversified than the SPS or LEP or any other large accelerator project constructed to date Machine Advisory Committee, chaired by
Prof. M. Tigner, March 2002
Rüdiger Schmidt - Wuppertal Januar 2004 94
citing Lyn Evansciting Lyn Evans
No one has any doubt that it will be a great challenge for both machine to reach design luminosity and for the detectors to swallow it.
However, we have a competent and experienced team, and 30 years of accumulated knowledge from previous CERN projects has been put into the LHC design
Rüdiger Schmidt - Wuppertal Januar 2004 95
Acknowledgement Acknowledgement
The LHC accelerator is being realised by CERN in collaboration with The LHC accelerator is being realised by CERN in collaboration with institutes from many countries over a period of more than 20 yearsinstitutes from many countries over a period of more than 20 years
Main contribution come from the USA, Russia, India, Canada, special Main contribution come from the USA, Russia, India, Canada, special contributions from France and Switzerland contributions from France and Switzerland
Industry plays a major role in the construction of the LHCIndustry plays a major role in the construction of the LHC
Thanks for the material from:
R.Assmann, L.Bottura, L.Bruno, R.Denz, A.Ferrari, B.Goddard, M.Gyr, D.Hagedorn, J.B.Jeanneret, P.Proudlock, B.Puccio, F.Rodriguez-Mateos, F.Ruggiero, L.Rossi, S.Russenschuck, P.Sievers, G.Stevenson, A.Verweij, V.Vlachoudis, L.Vos
Rüdiger Schmidt - Wuppertal Januar 2004 96
Some referencesSome referencesAccelerator physics Proceedings of CERN ACCELERATOR SCHOOL (CAS),
http://schools.web.cern.ch/Schools/CAS/CAS_Proceedings.html• In particular: 5th General CERN Accelerator School, CERN 94-01, 26
January 1994, 2 Volumes, edited by S.TurnerSuperconducting magnets / cryogenics Superconducting Accelerator Magnets, K.H.Mess, P.Schmüser, S.Wolff, World
Scientific 1996 Superconducting Magnets, M.Wilson, Oxford Press Superconducting Magnets for Accelerators and Detectors, L.Rossi, CERN-AT-
2003-002-MAS (2003)LHC Technological challenges for the LHC, CERN Academic Training, 5 Lectures,
March 2003 (CERN WEB site) Beam Physics at LHC, L.Evans, CERN-LHC Project Report 635, 2003 Status of LHC, R.Schmidt, CERN-LHC Project Report 569, 2003 ...collimation system.., R.Assmann et al., CERN-LHC Project Report 640, 2003 LHC Design Report 1995 LHC Design Report 2003 - in preparation
Rüdiger Schmidt - Wuppertal Januar 2004 97
Power into superconductingPower into superconductingcable after a quenchcable after a quench
Cross section : Asc 10 mm2
Current : Isc 10000 A
Length of superconductor : Lsc 1 m
Copper resistance at 300 C: cu 1.76 10 6 ohm cm
Psc cu Isc2
Lsc
Asc Psc 1.76 105 watt
Specific temperature of copper at 300 C : cvcu 3.244joule
K cm3
Temperature increase of copper TPsc
Asc Lsc cvcu
Temperature increase within one second: T 5.425 103K
s