THE UNITED REPUBLIC OF TANZANIA PRESIDENT’S OFFICE, REGIONAL ADMINISTRATION
AND LOCAL GOVERNMENT (PO‐RALG)
RURAL ROAD MAINTENANCE SYSTEM
DEVELOPMENT PROJECT
COMPLETION REPORT
MARCH 2016
JAPAN INTERNATIONAL COOPERATION AGENCY (JICA)
EIGHT‐JAPAN ENGINEERING CONSULTANTS INC. INFRASTRUCTURE DEVELOPMENT INSTITUTE
Acronyms and Abbreviations
ADRICS Annual District Roads Inventory and Condition Survey
AMTC Annual Monitoring and Training Cycle
AFCAP Africa Community Access Programme
ATTI Appropriate Technology Training Institute
BSD Bidding Security Declaration
CRB Contractors Registration Board
CTB Council Tender Board
DC District Council
DE District Engineer
DED District Executive Director
DROMAS District Roads Management System
DRDP District Road Development Programme
EBT Equipment Based Technology
EC Evaluation Committee
JICA Japan International Cooperation Agency
LBT Labour Based Technology
LGTP Local Government Transport Programme
MC Municipality Council
MD Municipal Director
MP Member of Parliament
PMO-RALG Prime Minister’s Office Regional Administration and Local Government
PO-RALG President’s Office, Regional Administration and Local Government
PMU Procurement Management Unit
PPRA Public Procurement Regulation Authority
RFB Road Fund Board
RSE Regional Secretariat Engineer
RSPS Road Sector Programme Support
TANROADS Tanzania National Roads Agency
TASAF Tanzania Social Action Funds
Table of Contents
1. General Outline of the Project ·············································· 1
1.1 Background of the Project ······························································· 1
1.2 Framework of the Project ································································ 1
1.3 Outputs ····················································································· 2
1.4 Target Groups ············································································· 2
1.5 Project Design Matrix (PDM) ··························································· 3
1.6 Project Activities ·········································································· 3
1.7 RMSD Experts Assignment ····························································· 4
2. Progress and Achievement 2012-2016 ····································· 5 2.1 Results of Project Activities based on the APO ······································· 5
2.2 Progress and Achievement for Output-1 ··············································· 8
2.3 Progress and Achievement for Output-2 ·············································· 11
2.4 Progress and Achievement for Output-3 ·············································· 26
2.5 Progress and Achievement for Output-4 ·············································· 33
2.6 LBT Equipment Management ·························································· 37
3. Project Monitoring and Achievement of Outputs ····················· 51 3.1 Monitoring of Project Activities ······················································· 51
3.2 Achievements based on Indicators ····················································· 52
4. Terminal Evaluation ························································ 74 4.1 Results of the Terminal Evaluation ···················································· 74
4.2 Recommendations from the Terminal Evaluation Team ···························· 85
4.3 Lessons Learned ········································································· 88
5. Other Important Activities ················································ 89 5.1 Joint Coordinating Committee ························································· 89
5.2 Provision of Equipment ································································· 89
5.3 Conducting the Baseline Surveys ······················································ 90
5.4. Modification of the PDM ······························································ 91
5.5. Training in Japan ········································································ 91
5.6 Public Relations ·········································································· 92
6. Issues, Contrivance, and Lessons Learned ····························· 93
6.1 Lessons Learned from the Project Operation ········································ 93
6.2 Lessons Learned from the Capacity Development ·································· 94
6.3 Lessons Learned from the Dissemination of the Output ···························· 95
7. Recommendations for Further Action ·································· 96
(Table and Figures)
Table1-1 RMSD Expert Team ·································································· 4
Table2-1 Summary of the Results of the Project Activities ································· 5
Table2-2 Outline of Regular Meetings on Operational Guidelines
(2012-2016 February) ······························································ 8
Table2-3 Outlines of Meetings for LBT Specification ······································ 9
Table2-4 Working groups and contents of the guidelines ·································· 10
Table2-5 Annual Schedule of DE in the Model District ···································· 13
Table2-6 RMSD Technical Training Courses ················································ 13
Table2-7 River level change according to bridge lengths ·································· 18
Table2-8 Utilization of GIS/GPS and Issues ················································· 19
Table2-9 Training Topics ······································································· 19
Table2-10 Mid-and Long Term Plan FY 2015/2016 Chamwino DC ····················· 22
Table2-11 Items Proposed for the Annual Rural Road Maintenance Plan ··············· 23
Table2-12 The Procedure of the Road Works in the Model Districts ····················· 24
Table2-13 Outline of the work plan of the Pilot Projects ·································· 28
Table2-14 Before and After, Challenges of the Operational Guidelines
in practice ··········································································· 31
Table2-15 AMTC Operation in the Project ·················································· 33
Table2-16 The Procedure of the Road Works in the Disseminated Districts ············ 36
Table2-17 Chamwino DC Annual Leasing Budget Plan ··································· 37
Table2-18 Iringa DC Annual Leasing Budget Plan ········································· 37
Table2-19 Leasing Price Transition (Chamwino DC) ······································ 38
Table2-20 Leasing Price Transition (Iringa DC) ············································ 38
Table2-21 Result &Target Comparison in Chamwino DC ································· 39
Table2-22 Result &Target Comparison in Chamwino DC ································· 39
Table2-23 2 Years Income Comparison (Chamwino DC) ·································· 39
Table2-24 2 Years Comparison (Iringa DC) ················································· 39
Table2-25 Leasing Period/Days (Chamwino DC) ·········································· 40
Table2-26 Leasing Period/Days (Iringa DC) ················································ 40
Table2-27 Maintenance Cost (Chamwino DC) ·············································· 40
Table2-28 Maintenance Cost (Iringa DC) ···················································· 40
Table2-29 Expense for depreciation including initial cost (Chamwino DC) ············ 40
Table2-30 Expense for depreciation excluding initial cost (Chamwino DC) ············ 41
Table2-31 Expense for depreciation including initial cost (Iringa DC) ·················· 41
Table2-32 Expense for depreciation excluding initial cost (Iringa DC) ·················· 41
Table2-33 Revenue prediction for next 3 years (average, Chamwino DC) ·············· 42
Table2-34 Revenue prediction for next 3 years (average, Iringa DC) ···················· 42
Table2-35 Mid/Long-Term Prediction without equipment renewal
(Chamwino DC) ··································································· 42
Table2-36 Mid/Long-Term Prediction without equipment renewal
(Iringa DC) ········································································· 42
Table2-37 Mid/Long-Term Prediction with equipment renewal
(Chamwino DC) ··································································· 43
Table2-38 Mid/Long-Term Prediction with equipment renewal (Iringa DC) ··········· 43
Table2-39 Satisfaction of Contractors on their own service
and district services ································································ 44
Table3-1 The maintenance status of rural roads in model and
disseminated districts (FY2011/12 – 2014/15) ·································· 53
Table3-2 Satisfaction ratings of contractors who executed the pilot projects
in Chamwino and Iringa DC ······················································· 54
Table3-3 Satisfaction ratings of community people working for the pilot
projects in Chamwino and Iringa DCs ············································ 55
Table3-4 The percentage of the rollover funds (RF) for rural road maintenance
in the model districts (FY 2011/12 – 2014/15) ·································· 57
Table3-5 The percentage of RS/Council Engineers utilizing the Operational
Guidelines and their satisfaction ratings ··········································· 59
Table3-6 Items necessary for the Annual Rural Road Maintenance Plan ················ 61
Table3-7 The percentage of the road maintenance completion in the model
and disseminated districts (FY 2011/12 – 2014/15) ···························· 63
Table3-8 The rating results of Council Engineers and Technicians in Chamwino
DC on their practical skills and knowledge ······································ 64
Table3-9 The rating results of Council Engineers and Technicians in Iringa DC
on their practical skills and knowledge ··········································· 65
Table3-10 The number of consultations provided by the Council Engineers/
Technicians in the model and disseminated districts
(FY 2013/14 – FY 2014/15) ···················································· 69
Table3-11 The ratio of LBT works to all the maintenance works in the model
Districts (FY 2011/12 – 2014/15) ·············································· 69
Table3-12 (1) Agenda of Monitoring W/S in Dodoma Region ···························· 71
Table3-12 (2) Agenda of Monitoring W/S in Iringa Region ······························· 71
Table3-13 (1) Participant List in Dodoma Region ·········································· 72
Table3-13 (2) Participant List in Iringa Region ············································· 72
Table3-14 Persons in charge of each Form in Model and Disseminated DCs ··········· 73
Table4-1 Rating of Achievement of Project Purpose ······································· 74
Table4-2 Maintenance status of rural roads in model and
disseminated districts ······························································· 75
Table4-3 Satisfaction ratings of contractors in Chamwino DC and Iringa DC ·········· 76
Table4-4 Satisfaction ratings of community people in Chamwino DC and
Iringa DC ············································································· 76
Table4-5 The percentage of the rollover funds for rural road maintenance
in the model and disseminated districts ·········································· 76
Table4-6 Rating of Achievement of Outputs ················································ 77
Table4-7 Items necessary for the Annual Rural Road Maintenance Plan ················ 79
Table4-8 Percentages of the road maintenance works Completed in the
model districts ······································································· 80
Table4-9 The total rating on average results of engineers and technicians in
Chamwino and Iringa DC on their practical skills and knowledge ··········· 80
Table4-10 The number of consultations provided by the district engineers/
technicians in model districts ······················································ 81
Table4-11 Statistics and comments at consultations in the model districts ·············· 81
Table4-12 The ratio of LBT works to all the road maintenance works in the
model districts ······································································· 82
Table4-13 Percentages of the road maintenance works Completed in the
disseminated districts ······························································ 83
Table4-14 Rating of Achievement of Overall Goal ········································· 84
Table5-1 RMSD Joint Coordinating Committee 2012-2016 ······························ 89
Table5-2 Equipment Procured by the Project ················································ 89
Table5-3 Contents of Baseline Survey (TOR) ··············································· 90
Table5-4 Member of the Study Tour in Japan ··············································· 92
Table7-1 Indicators and the means of verifications for the Overall Goal ················ 97
*****
Figure2-1 Photos of the Regular Meeting for the Operational Guidelines ················ 9
Figure2-2 Operational Guidelines, Members of Launching Ceremony ·················· 10
Figure2-3 Photos of Stakeholders’ Meeting 2015 ··········································· 11
Figure2-4 Iringa District Bridges ····························································· 15
Figure2-5 Chamwino District Box Culverts ················································· 15
Figure2-6 Photos of Training on Site ························································· 16
Figure2-7 Photos of Indoor training in Iringa DC ·········································· 16
Figure2-8 Confirmation of the Attribute Table ·············································· 20
Figure2-9 Confirmation the property ························································· 20
Figure2-10 Integration the OSM and the GPS data ········································· 20
Figure2-11 Setting the Print View ····························································· 20
Figure2-12 GIS Training onsite in Kondoa DC ············································· 20
Figure2-13 GIS Training in Mufindi DC ····················································· 21
Figure2-14 Training for Vehicle Calibration Odometer in Chamwino DC ·············· 22
Figure2-15 Proposed Value Added Prioritization ··········································· 23
Figure2-16 Annual Plan of the Model Districts ············································· 24
Figure2-17 Kitayawa-Wangama Road (Iringa DC, LBT pilot site) ······················· 25
Figure2-18 Location of the Pilot Project in FY 2013/2014 ································ 26
Figure2-19 Location of the Pilot Project in Chamwino DC FY2014/2015 ·············· 27
Figure2-20 Location of the Pilot Project in Iringa DC FY2014/2015 ···················· 27
Figure2-21 Before and After the rehabilitation of bridge in Iringa DC ·················· 28
Figure2-22 Before and After of the PP in Iringa DC ······································· 30
Figure2-23 Topic and cycle of AMTC ························································ 33
Figure2-24 Photos of AMTC in Mufindi DC and Kondoa DC ···························· 34
Figure2-25 Unkuku-Loo-Kalamba Road, Pilot Site in Kondoa DC ······················ 36
Figure2-26 Contract Form Contractor to District ··········································· 46
Figure2-27 Contract Form District to Contractor ··········································· 46
Figure2-28 Income Management Form ······················································ 47
Figure2-29 Maintenance management Form ················································ 47
Figure2-30 Proposed New Hiring System ··················································· 49
Figure3-1 Comparison between “Satisfaction” and “Improvement”
in each Chapter ····································································· 60
Figure3-2 Results of Checklist in Model Districts
(Form 4 in Monitoring System) ················································ 62
Figure3-3 Results of Checklist in Disseminated Districts
(Form 4 in Monitoring System) ·················································· 63
Figure3-4 Change in the rating results on the practical skills and knowledge of
Council Engineers/Technicians by RS Engineer (evaluation by another
person) in Dodoma Region and Council Engineers/Technicians
(self-evaluation) in Chamwino DC (from 3rd to 5th Questionnaire
Surveys) ············································································· 67
Figure3-5 Change in the rating results on the practical skills and knowledge of
Council Engineers/Technicians by RS Engineer in Iringa Region and
Council Engineers/Technicians in Iringa DC (from 3rd to 5th
Questionnaire Surveys) ·························································· 67
Figure3-6 Comparison of the rating results between Council Engineers and
Technicians (self-evaluation) in Chamwino DC and RS Engineer
(evaluation by another person) in Dodoma Region (4th and 5th
Questionnaire Surveys) ·························································· 68
Figure3-7 Comparison of the rating results between Council Engineers and
Technicians in Iringa DC and RS Engineer in Iringa Region (4th and 5th
Questionnaire Surveys) ·························································· 68
Figure5-1 Photos of ILO International Seminar in Benin 2015 ··························· 92
Annex Annex-1: PDM-1, PDM-2, PDM-3
Annex-2: PO (2012-2016)
Annex-3: RMSD Expert Team Assignment
Annex-4: Monitoring System, Monitoring Manual
Annex-5: Equipment
Annex-6: JCC
Annex-7:Counterpart Designation
Annex-8: Summary of Project Input
1
1. General Outline of the Project 1.1 Background of the Project
Tanzania's mid-term plan for national development, Tanzania Development Vision 2025 (enacted in
1999), states "Improvement of an appropriate amount of infrastructure will contribute to the
development of all sectors." Roads” in particular, are important tools for regional development.
Improvement of rural roads is emphasized as having a direct bearing on the promotion of agricultural
development and the improvement of the lives of the poor, which are important issues in Tanzania's
national development. Their improvement in terms of both quality and quantity is necessary.
In these circumstances, the Project for “Rural Road Maintenance System Development” was launched
aimed at improving the administrative and practical capacity of rural road maintenance and
management.
1.2 Framework of the Project
1.2.1 Term of the Project
From February 2012 to March 2014 for the first operational period
From May 2014 to March 2016 for the second operational period
1.2.2 Tanzanian Counterpart and Administrative Personnel
• Implementing agency: PMO-RALG, reformed as PO-RALG as of January 2016
• Supporting agency: MOW (ATTI as the LBT training institute)
• Project Director: Permanent Secretary, PMO-RALG
• Project Manager: Director of Infrastructure Development Unit (IDU), PMO-RALG
• Counterparts: IDU officials/ PMO-RALG
Officials of Regional Roads Department/ MOW
RS Engineers and District Engineers in the target area
1.2.3 Target area
• Target Regions: Dodoma Region, Iringa Region
• Model Districts: Chamwino District, Iringa District
• Disseminated Districts: Kondoa Districts, Mufindi District.
1.2.4 Super Goal
District roads in whole Tanzania are properly maintained through application of appropriate
technology and methodology.
2
1.2.5 Overall Goal
The district road maintenance procedure and services of LGAs in Dodoma and Iringa regions are
improved.
【Indicators】
1) Annual Rural Road Maintenance Plans prepared by the LGAs of the respective regions contain
necessary items based on the checklist.
2) The percentage of the road maintenance works completed by contractors (including defect liability
period) for all the maintenance works in the Plan is increased within the fiscal year in the
respective regions.
3) The maintenance status (Good, Fair, and Poor) of rural roads is improved in the respective regions.
1.2.6 Project Purpose
Administrative services of rural road maintenance provided by LGAs are improved in the target areas,
and its nationwide expansion approach is developed.
【Indicators】
1) The maintenance status (Good, Fair, and Poor) of rural roads is improved in the model and
disseminated districts of the respective regions.
2) The satisfaction ratings of the contractors/community people in the model and disseminated
districts of the respective regions exceed 75/75% (Chamwino and Iringa) on average with
reference to rural road maintenance works or status.
3) The percentage of the rollover funds for rural road maintenance is decreased in the model and
disseminated districts of the respective regions.
1.3 Outputs
(1) The capacity of PMO-RALG for coordinating and supporting LGAs in collaboration with MOW
on district road maintenance is strengthened.
(2) The district road maintenance procedure of the LGAs is strengthened in the model districts.
(3) The practical skills and knowledge of responsible organizations (concerned departments of the
LGAs, contractors, etc.) on district road maintenance are improved through the LBT application
in the model districts.
(4) The dissemination mechanism for district road maintenance approach within the respective
regions is established.
1.4 Target Groups
RS and District Engineers, District Technicians, contractors, and community people living around the
pilot project sites
3
1.5 Project Design Matrixes (PDM)
The outline of the Project is summarized in the Project Design Matrix (PDM) as shown in Annex 1.
The PDM is subject to modifications through further discussions with the project stakeholders in
accordance with the progress and achievements of the Project.
1.6 Project Activities
(1) Activities for [Output 1]
1-1 Convene regular meetings on operational guidelines development for rural road maintenance
with PMO-RALG and MOW.
1-2 Prepare and revise operational guidelines of rural road maintenance with PMO-RALG and
MOW.
1-3 Share the contents of the guidelines and the lessons learned from LGAs in the model districts
during the Annual Meeting between PMO-RALG and RS and District Engineers.
1-4 Assist RS engineers to monitor rural road maintenance in LGAs based on the guidelines.
(2) Activities for [Output 2]
2-1 Select model districts based on the criteria established.
2-2 Review the current activities done by technical staff in the model districts.
2-3 Provide training on rural road maintenance for the district engineers and technicians in the
model districts.
2-4 Prepare and update the rural road inventories in the model districts.
2-5 Prepare and revise a mid- and long-term rural road maintenance plan.
2-6 Confirm the needs of rural road maintenance in the model districts and prioritize the needs.
2-7 Prepare the annual rural road maintenance plans, including procurement, construction method,
etc., in consideration of gender aspects in the model districts.
(3) Activities for [Output 3]
3-1 Select pilot projects in the model districts from the annual rural road maintenance plan.
3-2 Formulate work plans of the pilot projects.
3-3 Assist district engineers and technicians in the model districts to procure contractors and
supervise the pilot projects based on the work plans.
3-4 Provide consultations on the operation of the pilot projects for the district engineers and
technicians, contractors, etc. through ATTI.
3-5 Promote PR activities on rural road maintenance through the pilot projects.
3-6 Document the process, experiences, outcomes, and lessons learned of the pilot projects.
(4) Activities for [Output 4]
4-1 Organize sensitization workshops on rural road maintenance for the other LGAs in the respective
4
regions in collaboration with the RS engineers.
4-2 Select a LGA to be disseminated in the respective regions.
4-3 Assist the LGAs selected in the respective regions to promote rural road maintenance based on
the guidelines with the full commitments of RS engineers.
4-4 Monitor the rural road maintenance promoted by the LGAs in the respective regions.
4-5 Feedback the monitoring results into the guidelines.
1.7 RMSD Expert Assignment
The Expert Team members of the RMSD Project are listed below:
Table 1-1 RMSD Experts Team
Expertise Name of Experts Organization
Team Leader/Road Maintenance Tatsumi TOKUNAGA
Motoki OGAWA
EJEC
Sub Leader/Rural Road Planning Motoki OGAWA
Tatsumi TOKUNAGA
EJEC
LBT(Design/Structure) Hirokazu MIYAMOTO EJEC
LBT(Maintenance/Quality Control) Noboru SHIMIZU
Masahiko NISHIDA
EJEC
Road Design Ikumasa KAWASAKI EJEC
Construction/Contract Management Kenko OKAMURA IDI
Light Equipment Management Masanori TAKEISHI CDCI
Capacity Building Kazunobu KAMIMURA PACET
Monitoring Takaaki HIRAKAWA INTEM
Coordinating/Training Planning Yumiko TAKEDA CDCI
Coordinating/Public Relations Go EBISU EJEC
5
2. Progress and Achievement February 2012-February2016
In the second operational period of the Project’s implementation, 22 activities out of the 23 identified
in the PDM were realized by the middle of February 2016.
2.1 Results of Project Activities based on the APO
The progress and attainment of the Project’s activities as of February 2016 are summarized as follows:
Table 2-1 Summary of the Results of the Project Activities
Project Activities Progress Situation of Each Activity
Other Activities
Joint Coordinating Committee (JCC) The fourth JCC meeting was held on 20 August, 2015. Past achievements and results as well as the roadmap for nationwide expansion after termination of the Project were discussed and confirmed. Also, the fifth JCC meeting was held on 23 February, 2016. Final outcomes and continued operations after the end of the Project were reported and discussed during the final JCC meeting.
Mid‐term Review and Terminal Evaluation
The Terminal Evaluation Study was conducted on 21 August 2015, and the evaluation results, recommendations, and lessons learned were extracted by the Study Team. As the Project terminates earlier before the end of financial year, the Team emphasizes that C/P shall aggregate the data extracted after the end of the financial year and confirm the changes in target values.
Documentation and submission of the Work Plan
N/A
Documentation of (Mid‐term) Progress Report
The Final Progress Report was prepared and submitted as scheduled in March, 2016.
Procedure of provision of equipment N/A
Output 1: The capacity of PMO‐RALG for coordinating and supporting LGAs in collaboration with MOW on rural road maintenance is strengthened.
1‐1 Convene regular meetings on operational guidelines development for rural road maintenance with PMO‐RALG and MOW.
Accordingly the recommendation from the mid‐term review team, the Project incorporated the production of the LBT specification into the project activities 1‐1. Regular meetings of the Operational Guidelines, and the meeting for LBT Specification were held as follows. 7th Regular meeting (in July 2014) 8th Regular meeting (in August 2015) 9th Regular meeting (March 2015) 10th Regular meeting (LBT Specification Meeting 1 convened in August
2015) 11th Regular meeting (LBT Specification Meeting 2 convened in
December 2015) 12th Regular meeting (LBT Specification Meeting 3 convened in January
2016)
1‐2 Prepare and revise operational guidelines of rural road maintenance with PMO‐RALG and MOW.
Regarding the Operational Guidelines, it has been approved by MoW in December 2014. The Project had a ceremony for the launching the Operational Guidelines in March 2015. After the completion of the Operational Guidelines, the need of LBT technical specification was discussed. As the maintenance work methods are different between EBT and LBT, the quality of LBT works is not secured by referring to the current
6
specification of EBT. Thus, the same member of the Operational Guidelines came to develop the Guidelines for LBT technical specification. The schedule is shown in the Activity 1‐1.
1‐3 Share the contents of the guidelines and the lessons learned from LGAs in the model districts during the Annual Meeting between PMO‐RALG, RS Engineers and District Engineers.
The Annual Engineers Meeting was convened in Arusha from 24th to 28th August, and the presentation on the project outcomes was carried out by the model district (Iringa DC). The questionnaire survey for the utilization of the Operational Guidelines was conducted for RSEs and Council Engineers during the meeting, and the Engineers in other LGAs were encouraged to use the Operational Guidelines.
1‐4 Assist RS engineers to monitor rural road maintenance in LGAs based on the guidelines.
The budget for rural road maintenance was reduced and delayed in this financial year, and only 50% of the original budget was approved. The delay of the disbursement of the budget caused the delay of series of road work procedure in LGAs. It is supposed the quarterly monitoring by RSEs was difficult in this year due to the late disbursement of the budget to the LGAs.
Output 2: The rural road maintenance procedure of the LGAs is strengthened in the model districts.
2‐1 Select model districts based on the criteria established.
N/A
2‐2 Review the current activities done by technical staff in the model districts.
N/A
2‐3 Provide training on rural road maintenance for the district engineers and technicians in the model districts.
In preparation for the termination of the Project in March 2016, themonitoring W/S was convened in Dodoma and Iringa Regions (26 January 2016 in Dodoma and 29th January in Iringa). Because the Project is terminated before the end of the financial year of Tanzania, C/P shall collect the data and information that will be extracted and fixed after the end of financial year. Thus, the Monitoring Expert provided the instructions on the overall picture of M/S, the method for data entry of each form, etc. for the C/P during the W/S. Also, the indicators and various forms necessary for the monitoring were summarized and confirmed. In this way, it is required for the C/P to carry out the monitoring activities on their own initiatives. GIS training was conducted twice in the disseminated districts in August 2015 and January 2016. The contents of training were the collaboration between the annual plan and road information management system, the update of the system before and after the road maintenance works, etc.
2‐4 Prepare and update rural road inventories in the model districts.
Since the budget disbursement has delayed of FY 2015/16, the inventory survey in Iringa DC was partly completed for aiming the prioritization. By the end of January 2016, the inventory in Iringa DC has not been completed. The survey in Chamwino DC has already been completed.
2‐5 Prepare and revise a mid‐ and long‐term rural road maintenance plan.
Iringa District has revised the mid‐ and long‐term rural road maintenance plans based on the inventory data partly done in November. Chamwino District is revising the mid‐and–long term plan and expected to complete by the end of February 2016. Also, they provided the instructions of the mid‐ and long‐term plan in AMTC for the disseminated districts.
2‐6 Confirm the needs of rural road maintenance in the model districts and prioritize the needs.
In the mid‐ and long‐term rural road maintenance plans, the priorities are defined from; (1) road class, (2) road network, (3) population, (4) economic condition, and (5) others. The needs of rural road maintenance are fairly and technically summarized, and the road maintenance works are prioritized. Regarding the prioritization in FY 2016/17, Chamwino DC has already completed whereas Iringa DC has been ongoing.
2‐7 Prepare annual rural road maintenance plans, including procurement, construction method,
Model DCs plan to formulate the Annual Plan from March 2016 based on the mid‐ and long‐term plan. The Annual Plans, which are required for budgeting formatted for DROMAS‐2 have submitted to the Dodoma and
7
etc., in consideration of gender aspects in the model districts.
Iringa Regions respectively.
2‐8 Monitor the rural road maintenance in the model districts.
Due to the delay of budget disbursement from RFB in October 2015, the bidding procedure, the contract, and the commencement of road works were delayed. The implementation of the pilot project in Chamwino DC has started in January. The implementation in Iringa DC will be after April 2016.
Output 3: The practical skills and knowledge of responsible organizations (concerned departments of the LGAs, contractors, etc.) on rural road maintenance are improved through the LBT application in the model districts.
3‐1 Select pilot projects in the model districts from the annual rural road maintenance plan.
N/A
3‐2 Formulate the work plans of the pilot projects.
N/A
3‐3 Assist district engineers and technicians in the model districts to procure contractors and supervise the pilot projects based on the work plans.
N/A
3‐4 Provide consultations on the operation of the pilot projects for the district engineers and technicians, contractors, etc. through ATTI.
N/A
3‐5 Promote PR activities on rural road maintenance through the pilot projects.
The PR video, “The Project for Improvement of District Road,” on the pilot projects was broadcasted on Star TV on 21 and 22 July, 2015. Also, the DVD was distributed to engineers during the Engineers’ Meeting at Arusha as material for sharing the lessons learned from the model districts.
3‐6 Document the process, experiences, outcomes, and lessons learned of the pilot projects.
The Project summarized the results, impacts, lessons learned, etc., extracted from the experiences of pilot projects in the model districts. In terms of the project outcomes and experiences on the capacity development for rural road maintenance, furthermore, the W/S was convened on 12th August in Iringa DC, and the participants exchanged opinions.
Output 4: The dissemination mechanism for rural road maintenance approach within the respective regions is established.
4‐1 Organize sensitization workshops on rural road maintenance for the other LGAs in the respective regions in collaboration with the RS engineers.
The 1st AMTC in FY 2015/16 on the inventory course was convened in the disseminated districts under the initiatives of engineers and technicians in the model districts and RS engineers (on 1st and 9th September 2015 in Kondoa and Mufindi DCs respectively). The 2nd AMTC on the planning & budgeting course was convened with the instructions of mid‐ and long‐term plan, annual plan, and budget preparation by the model districts (on 27th November and 4th December 2015 in Kondoa and Mufindi DCs respectively). The 3rd AMTC on the procurement course was convened with the instructions of bidding procedure and contract document by the model districts (on 18th and 15th January 2016 in Kondoa and Mufindi DCs respectively).
4‐2 Select a LGA to be disseminated in the respective regions.
N/A
4‐3 Assist the LGAs selected in the respective regions to promote rural road maintenance based on the guidelines with the full commitments of RS engineers.
<Inventories in the disseminated districts> Mufindi DC has already completed the inventory, while Kondoa DC has partly done for the budgeting. <Mid‐ and long‐term plan in the disseminated districts> Although Kondoa and Mufindi DCs undertook the formulation of mid‐ and
8
long‐term plans after the 2nd AMTC on the planning course, both districts have on going to revise the mid‐long term plans. <Prioritization in the disseminated districts> Regarding the prioritization of FY2016/17, both districts have completed by the end of January, 2016. The prioritization is aiming for the budgeting based on the inventory partly done.
4‐4 Monitor the rural road maintenance promoted by the LGAs in the respective regions.
In the same way as the model districts, the implementation of the pilot projects in the disseminated districts will be delayed after April. The monitoring workshops were convened in Dodoma and Iringa Regions. In preparation for the end of FY2015/16, the Monitoring Expert instructed the C/P to summarize the information and data of rural road maintenance works for the financial year according to the forms of the Monitoring System (M/S).
4‐5 Feedback the monitoring results into the guidelines.
Due to the delay of the road work procedure in LGAs caused by the late budget disbursement, it is difficult for RSEs to monitor the progress quarterly basis as usual. After the project completion, PMO‐RALG is required to instruct to feedback the monitoring results to the Guidelines.
2.2 Progress and Achievement for Output-1
The capacity of PMO-RALG for coordinating and supporting LGAs in collaboration with
MOW on rural road maintenance is strengthened.
【Activity 1-1】Convene regular meetings on operational guidelines development for rural road
maintenance with PMO-RALG and MOW.
【Meeting for Operational Guidelines】
RMSD convened regular meetings to develop the Operational Guidelines. The contents of the
Guidelines were discussed during the meetings.
Table2-2 Outline of Regular Meetings on Operational Guidelines(2012-2016 February) Items Date Place Agenda Participants
1st
7/February/2013 PMO‐RALG
・ Background for the Operational Guidelines ・ Contents ・ Discussion ・ Working Group ・ Schedule
27
2nd
21/May/2013 PMO‐RALG ・ Draft of Guidelines ・ Schedule
12
3rd
3/June/2013
PMO‐RALG
・ Report of Study Tour ・ Details of Contents ・ Schedule ・ Dissemination and Utilization of Guidelines
17
- 24/July/2013 Arusha
Sharing the draft of Guidelines in Engineers Meeting
Discussion and comments from Engineers in LGAs
600
4th 18‐20/September/2013
Iringa DC
Modification of Guidelines reflected the comments raised in Engineers meeting
Contents of Annex Lessons learnt from the Pilot Project
34
9
5th
20/November/ 2013
Iringa DC Pilot Site
Site Visit for the Pilot Project Summarization of lessons learnt from Pilot
Project
37
6th
13/February/2014 Dar es Salaam
Summarization of lessons learnt from Pilot Project
Utilization of GPS to ADRICS
33
7th
24/July/2014 PMO‐RALG Progress of the Draft of Operational Guidelines Discussion on the comments from MoW
32
8th
6/August/2014 PMO‐RALG Discussion on the comments from MoW 15
‐ 10/March/2015 PMO‐RALG Dar es Salaam
Official Launch of Operational Guidelines The merit of the utilization of Operational
Guidelines The future expectation for the Rural Road
Management
19
【Meeting for LBT Specification】 Figure 2-1 Photos of the Regular Meeting for the Operational Guidelines
The need to produce LBT specification was recognized during the regular meeting. The JICA
Mid-Term Evaluation Team recommended incorporating the activities focusing on LBT Specification
within the Project period. PMO-RALG and the RMSD Team convened the meeting for LBT
specification as follows.
Table 2-3 Outlines of Meetings for LBT Specification
Items Date Place Agenda
‐
11/March/2015
PMO‐RALG
Dar es Salaam
・ Presentation of the existing LBT Manuals
・ Discussions on the Contents of LBT Specifications
・ Discussion on the Procedure for Approval
1st
13/August/2015 Iringa
・ Needs of LGAs and RAS for Practical Specification of LBT
・ Purpose of Producing the Practical LBT Specifications
・ Review of the Existing LBT Manuals
2nd
26/August/2015
Arusha
Reviewing of current existing LBT Manuals / Documents
Assessing the items required to be upgraded, revised
Drafting the Table of Contents
3rd
7/December/2015 Iringa DC
Presentation by the Working Group for the LBT
Specification, Draft of LBT Specification
4th
13‐14/January/2016 Iringa DC
Compiling the Draft, Checking the procedure of the approval
from MoW
10
【Activity1-2】Prepare and revise operational guidelines of rural road maintenance with
PMO-RALG and MOW
The working groups produced the draft of the Operational Guidelines by the end of August 2014. The
lessons learned from the pilot projects in Chamwino and Iringa DC, new knowledge from the Study
Tour to Uganda and Kenya, and training in Japan were all reflected in the draft. PMO-RALG
submitted the draft to MoW and it was approved by MoW in December 2014. In March 2015,
PMO-RALG and the Project conducted the official launching for the Operational Guidelines in Dar es
Salaam. Mr. Jumanne Sagini, Permanent Secretary of PMO-RALG, expressed appreciation for the
continuous support from JICA, and committed to practical utilization of the Guidelines in all the
LGAs. The Guidelines shall be revised annually, with the feedback from the pilot projects in the
model districts and disseminated districts.
Table 2-4 Working groups and contents of the guidelines
Working group Contents Responsible organization
Policy, abstract and outline of
the Guidelines
Policy for making the guidelines will
also be part of the item
PMO‐RALG
Planning
Road condition survey Chamwino DC,
Chaired by Eng. Mpinzile Medium‐long term planning
Annual planning
Implementation and
Procurement
Tender/contract document Iringa DC,
Chaired by Eng. Runji Contract management and
administration
Evaluation of contractor
Monitoring & Post
Evaluation
Monitoring and Evaluation of
maintenance works
RSE of Dodoma and Iringa
Eng. Mkwata & Eng. Mwakalalile
Figure2-2 Operational Guidelines, Members of Launching Ceremony
【Activity1-3】Share the contents of the guidelines and the lessons learned from LGAs in the
model districts during the Annual Meeting between PMO-RALG and RS and District
Engineers.
The contents of the Operational Guidelines and the lessons learned from the model districts were
shared in the Engineers Meeting on behalf of PMO-RALG, RFB & Stakeholders Meeting. The
11
meeting was convened in Arusha from 24 to 28 August 2015. Eng. Mpinzile, District Engineer in
Chamwino DC presented the contents of the Guidelines, and the lessons learned from the application
of the Guidelines. Eng. Runji, District Engineer in Iringa DC also had an opportunity to talk about his
experience in the Iringa district.
Figure2-3 Photos of Stakeholders’ Meeting 2015
【Activity1-4】Assist RS engineers to monitor rural road maintenance in LGAs based on the
guidelines.
Monitoring is one of the key factors in sustaining the project activity even after project completion.
The project supported to the creation of the monitoring system and monitoring manuals for the RSEs
and the District Engineers. Seven (7) types of new monitoring forms were introduced in the
monitoring system. The monitoring system gives engineers the capability to monitor the activities of
the road works, the progress and the issues, and the achievement. As a result of using the monitoring
forms, the maintenance works in FY2014/2015 were properly monitored by RSEs.
The issues of monitoring are caused by the insufficient personnel of RSEs, rather than the quality of
monitoring. In each of the model regions of the Project, Dodoma and Iringa, the role of RSE is
assigned to only one engineer. The numbers of councils in the regions covered by each RSE are; 8
councils in Dodoma region (Dodoma MC, Chamwino DC, Bahi DC, Mpwapwa DC, Chemba DC,
Kongwa DC, Kondoa DC and Kondoa TC) and 5 in Iringa regions (Iringa MC, Iringa DC, Mufindi
DC, Mufindi TC, Kilolo DC). Along with the increase in number of councils due to decentralization,
the volume of monitoring work increased for the RSEs.
Regarding the results of monitoring, around 86% of the FY2014/2015 budget including rollover has
been disbursed. In FY2015/2016, however, the delay of budget disbursement caused the delay of the
procedure for the road works in the LGAs. It affected monitoring works by RSEs.
2.3 Progress and Achievement for Output-2
The rural road maintenance procedure of the LGAs is strengthened in the model districts.
12
【Activity2-1】The establishment of criteria and selection of the model districts
The Model Councils were selected as follows.
-Chamwino District (Dodoma Region)
-Iringa District (Iringa Region)
PMO-RALG and the Project established the criteria for the selection. The candidate councils were
examined by the criteria. Then, the comparative evaluation has been done during the selection.
(1) Basic Concept of the Criteria for Selection of Model Councils
The Project set two indicators to assess the candidate councils.
1) The Preconditions and criteria were to confirm the effectiveness and efficiency.
2) The Comparative Evaluation was done by the criteria.
(2) Precondition Assessments
Precondition was assessed by the following four (4) factors.
- Elimination of the Municipality Councils (MC)
- Location near to the Regional Capital Cities/Municipalities
- Relationship with JICA financial assistance for Road Construction Projects
- Requirement of LBT Training at ATTI
(3) The Comparative Evaluation
Through the comparative evaluation, the Model Councils were selected with the mutual consensus of
PMO-RALG, RS Engineers and the JICA Experts. The availability of the technical support from the
Development Partners were also factored into the consideration.
【Activity2-2】Review the current activities done by technical staff in the model districts.
The Project reviewed the current activities in the model districts. The findings from the review are as
follows.
(1) Regional Engineers (RSE)
The regional engineers conduct three major activities; technical inspection at the site, administrative
inspection at the office, and monitoring the budget disbursement in LGAs. For every quarter, RSEs
produce quarterly reports based on their monitoring results. The format for the quarterly reports is not
standardized. The requirement from PMO-RALG is only to attach the budget disbursement data. This
causes gaps in the contents of the reports between regions. Regarding the number of RSEs assigned,
only one engineer is assigned in most regions. The assignment of sufficient numbers of qualified
personnel is required.
13
(2) Districts Engineer (DE)
The District Engineers commit all the road work stages. As shown in the table below, DEs supervise
and instruct the engineers and technicians throughout the year in the districts.
Table2-5 Annual Schedule of DE in the Model District
【Activity2-3】Provide training on rural road maintenance for the district Engineers and
Technicians in the model districts
The Project provided technical training as listed below. More than 180 engineers and technicians
participated in the training. The technical training contributed to enhancing their capacity for
supervising, monitoring, and meeting the requirement of the technical audit.
Table2-6 RMSD Technical Training Courses Date Topic Place Participants
18‐Sep‐12 Workshop Training on Road Maintenance for District Engineers and Technicians
Iringa DC 10
26‐Sep‐12 Workshop Training on Road Maintenance for District Engineers and Technicians
PMO‐RALG 7
1‐Mar‐13 Planning and design for the Structure Iringa DC 1026‐Mar‐13 Planning and design for the Structure PMO‐RALG 10
18‐June‐13 27‐June‐13
Operation and Management of LBT Equipment (OJT) Chamwino DC 8
20‐June‐13 24‐June‐13
Operation and Management of LBT Equipment (OJT) Iringa DC 5
4‐Nov‐13 15‐Nov‐13
Operation and Management of LBT Equipment (OJT) Chamwino DC Iringa DC
3
19‐Sep‐13 Workshop‐1: Training on Data Processing in ADRICS Workshop‐2: Training on Quarterly Management
Iringa DC 13
18‐Nov‐13 29‐Nov‐13
Mid‐Long term Plan Iringa DC Chamwino DC
4
3‐Feb‐14 20‐Feb‐14
Mid‐Long Term Plan Iringa DC Chamwino DC
2
5‐Feb‐14 Carrying out the Inventory Survey Chamwino DC 9 24‐June‐14 17‐July‐14
GPS/GIS Training ‐OJT for Digital Map Creation and Utilization
Chamwino DC 8
Year: 2012‐2013 No. 1
Name: G.S.Mpinzile
Organization: Chamwino DE
Work Item/Action Document Name Prepared by Submitted ToAction or
Submission
Date
Preparation Approval by Council Approval by MoF Approval by MP
JCC Guideline MTG
Donors MTG (TASAF) TASAF
CMT*
Tendering; Advertising Chamwino DC
Tendering; Preparation Chamwino DC
Technical Auditor Reportregulated to be
submitted every 1/4
Road Fund
MOF
Road Inspection PMO‐RALG
Road Inventory Survey
RF Quarterly ReportRoad Fund
Quarterly ReportChamwino DC
Dodoma Region
PMO‐RALG
DC Internal AuditorDC Internal
Auditor ReportChamwino DC
Chamwino
DC
Donors MTG (JICA) JICA
Local Government
Engineer MTGRAS/DC
Weekly Progress ReportWeekly Progress
ReportChamwino DC
Implementation of
ProjectsChamwino DC
Tendering; Evaluation Chamwino DC
Budgeting Chamwino DCMinistry of
Finance
Annual Schedule
Monthly Management DC
MTG
Monthly
Progress ReportChamwino DC DED
1 2 3 4 5 67 8 9 10 11 12
All Councils Meeting PMO‐RALG
Regional Road Board
MeetingRAS
Year: 2012‐2013 No. 1
Name: Leopold Runji
Organization: Iringa DE
Work Item/Action Document Name Prepared by Submitted To
Action or
Submission
Date
approved by Min. Finapproved by MP
Technical Auditor Reportregulated to be
submitted every 1/4
Road Fund
CAG*
CMT*
Tendering; Advertising Iringa DC
DC Internal Auditor ReportDC Internal
Auditor ReportIringa DC Iringa DC
Donors MTG (AFCAP) AFCAP
RF Quarterly ReportRoad Fund
Quarterly ReportIringa DC
Iringa Region
PMO‐RALG
Local Government
Engineer MTGRAS/DC
Donors MTG (JICA) JICA
Tendering; Evaluation Iringa DC
Implementation of
ProjectsIringa DC
9 10
Tendering; Preparation Iringa DC
Budgeting Iringa DCMinistry of
Finance
Weekly Progress ReportWeekly Progress
ReportIringa DC
11 12
Annual Schedule
Monthly DC MTGMonthly
Progress ReportIringa DC DED
1 2 3 4 5 67 8
14
22‐July‐14 GPS/GIS Training ‐OJT for GIS, GIS Basic Skills and Digital Map Utilization
Iringa DC 15
9‐July‐14 11‐July‐14 1‐Aug‐14
River Survey on Site Iringa DC 16
25‐July‐14 River Survey on Site Chamwino DC 4 18‐July‐14 19‐July‐14 2‐Aug‐14
Structure Planning ‐River Flow Forecasting and Structure Planning ‐River Flow Analysis Software ‐River Flow Calculation and Bridge Planning
Iringa DC 24
22‐July‐14 7‐Aug‐14 8‐Aug‐14
Structure Planning ‐River Flow Forecasting and Structure Planning ‐River Flow Analysis Software ‐Box Culvert Planning
Chamwino DC 12
1‐Sep‐15 GIS Training Chamwino DC Kondoa DC
9‐Sep‐15 GIS Training Iringa DC Mufindi DC
15‐Jan‐16 GIS Training Iringa DC Mufindi DC
10
18‐Jan‐16 GIA Training Chamwino DC Kondoa DC
13
2.3.1. Structure Design Training
【Overview】
The structure of local roads is planned on the basis of the common national standard structural
diagram compilation. If the structure is planned based on local circumstances or site conditions, it is
clear that it is a practical and more economical development. With a plan to suit local conditions, it is
possible to reduce the cost of maintenance. Structures in the model district are those relating to the
river. Therefore, the training focused on the training plan outline and RC design calculation method.
Training was carried out while using a slide and specific calculation example.
The figure below is an example how the Iringa DE repaired a bridge with his own design based on the
structure training in the first phase. The example shows that the DE fully understands the training and
applies the skills.
Before After
Subsidence of the piers and girders The bridge girders were heightened.
15
RC digit is narrow. Rebar placement and concrete filling are difficult.
By reducing the number of bridge girders, workability was improved
Figure 2-4 Iringa District Bridges
Rebar placement and concrete filling are difficult. By reducing the number of bridge girders,
workability was improved. The next figure shows box culverts in Chamwino that were damaged by
flooding in 2014. As the flooding occurred before the completion of construction, the mounting part
was scoured. Therefore, the wings were extended and the mounting part was strengthened after the
flooding. It is hard to predict river channel changes during a flood because the lands around
Chamwino is flat. This point is important to the design and maintenance of structures. In Chamwino
district, Causeway (=Drift) and Vented Causeway structures have been used. However, since the
Vented Causeway structure is often clogged by driftwood, box culverts are constructed to avoid
clogging. It would appear that cutting trees causes clogging to occur.
The wings are extended to strengthen the mounting part.
Vented Causeway. The structure does not work well due to clogging.
Figure 2-5 Chamwino District Box Culverts
(1) Survey on Site
Student interns also attended the training. District technicians know how to survey well and learn
about survey planning, and survey instruments, and how to use them for three days.
16
Training on Site in Iringa DC Intern students also attended the training
Training on Site in Chamwino DC The river direction and the box culvert direction are not the same. The expert suggests they change road alignments or slant the box culvert.
Figure 2-6 Photos of training on site
(2) Indoor training
Trainees learned how to estimate river flow and how to calculate river level change. Exclusive analysis
software is necessary for calculating the river level for bridge construction. Free software (HEC-RAS)
was used for the training. Table shows river level changes according to bridge lengths; trainees
understood the importance of appropriate river cross-section securement. An engineer and a technician
in charge of bridge design also learned how to use the software at a later date.
Figure 2-7 Photos of Indoor training in Iringa DC
(3) Summary of the Training
The training covered river side view creation, river flow calculation, and water level change.
The districts usually designed bridge or culvert based on experience, without any calculation, due to
personnel and budget limitations. The training taught them the need for hydrological surveys or
17
planning. The trainees intend to use their knowledge. In Iringa district, a bridge being planned is being
reviewed based on the training results.
However, it is difficult to estimate precise river flow in a river situation with a large river basin area.
Therefore, the training emphasized the following:
Estimate OFL (Ordinary Flood Level) and HFL (Highest Flood Level) by river erosion condition.
Set DFL (Design Flood Level) considering water level and structure level.
Strengthen mounting parts for more severe flooding than planned.
For the future training plan, the following issues shall be considered.
a. Necessary training
Precise understanding of river levels, riverbank reinforcement and scouring measures,
and maintenance plans are necessary.
b. Utilization on site
In addition to training handouts, the expert prepared the following calculation examples.
With the examples, structure planning and design will be carried out for further
understanding.
RC girder design (bridge span=8m,10m,12.5m,15m)
Box culverts design loading condition, analysis model figure
Actual design calculations are usually conducted by consultants. The calculations are simple
with Excel.
Data input and analysis calculation for hydraulic analysis software
c. Dissemination to other districts
Engineers in the model districts are mainly in charge of dissemination activities
in the dissemination districts. With the dissemination activities, a nationwide
dissemination method will be reviewed.
18
Table 2-7 River level change according to bridge lengths
Single-span bridge (10m span)
Original form
Two-span bridge (10m span)
Change example
(River side view) (River side view)
Over flow at the upper side
(River side view) (River side view)
Bridge plan water level: OFL
Simulating the water level for annual flooding
19
2.3.2. GIS Training
(1) Issues of GIS/GPS utilization in Tanzania
The government of Tanzania has initiated DROMAS-2 which accumulates the entire data of the rural
road in LGAs. The pilot trial launched in Dodoma and Morogoro region. The GIS software that links
to DROMAS-2 is free-soft, namely “QGIS”. The Project conducted interviews the utilization of
GIS/GPS. The findings from the interviews are as follows.
Table2-8 Utilization of GIS/GPS and Issues DC Utilization and Issues
Chamwino DC <Utilization> All the districts roads have been tracked Software: QGIS Training on GIS has been delivered by PMO‐RALG The GPS data have been saved in QGIS Staffs members are assigned for QGIS, DROMAS‐2, and on site <Issues> QGIS only shows the route and no additional information DROMAS‐2 depends on internet accessibility Lack of user‐friendliness in rural road management Difficult to identify the road class (coloring by road class depends on the staffs) GIS data have been plotted, but have had no practical usage
Iringa DC <Utilization> No training for GIS delivered by PMO‐RALG All the districts roads have been tracked The GPS data have been transferred to Excel. Additional information such as Bridge
or Culvert is commented on in Excel <Issues> No idea for the basic information and usage of QGIS Never seen DROMAS‐2
Kondoa DC All the districts roads have been tracked Difficult to use GIS due to unstable electricity
Mufindi DC Partly utilized GPS No utilization of GIS
(2) GIS Training
Table 2-9 Training Topics
i. About DROMAS ii. DROMAS and QGIS iii. What’s QGIS iv. Digital Map (Open Street Map)(referred to “OSMN”) v. What’s a Shape File (SHP File) ? vi. How to make the Base‐Map?
【Open the Shape File】 Open the QGIS and Shape file Check the Layer Confirm the Attribute Table (Source of the OSM) Confirm the property Style Display the OSM Data‐Base
20
Figure2-8 Confirmation of the Attribute Table Figure2-9 Confirmation of the property
Figure2-10 Integration of the OSM and the GPS data Figure2-11 Setting the Print View
Chamwino DC
The district technician in Chamwino DC instructed on-site the training in Kondoa DC. Tracked the
sample data at the Kondoa site, and then presented the manipulation.
Figure2-12 GIS Training onsite in Kondoa DC
Iringa DC
The district engineer and technician in Iringa DC instructed the training.
【Integration of the OSM and the GPS Data】 Add GPS Data Zoom the GPS Data Save as the SHP File Revise the attribute table Display the GPS Data
Set the print view
21
Figure2-13 GIS Training in Mufindi DC
(3) Summary of GIS Training
The GIS training contributed to developing the capacities of engineers and technicians as follows.
Data Management
The significant gain from the training is in data management. At the beginning of the Project, the
engineers managed the rural road data manually on paper. Currently, after the end of Project, the road
data are managed digitally using PCs, by utilizing the GPS. The training introduced new technical
tools, such as a drive recorder, which attracted the engineers.
Utilization of GIS software
The engineers and technicians mastered the utilization of GIS software through the technical training.
Although the GIS software shall be updated in the future, the procedure of the road works and the
manipulation of GPS shall remain the same. The ability to use GIS/GPS promotes efficiency. Due to
the limited numbers of engineers and technicians covering the whole network in the districts, the
difficulty of full usage of GIS is of concern. To accelerate the utilization of GIS, continuous training is
required.
Capacity Development as a GIS Specialist in the Model District
The training contributed to the enhanced technical capacities of the engineers and technicians in the
model and disseminated districts. In particular, the engineers and technicians in the model districts
acquired proficiency in using GIS software. After the Project’s completion, the engineers and
technicians in the model districts are expected to transfer their technical skills to others.
Transferring Technical Skills to the Disseminated Districts
Regarding the engineers and technicians in the disseminated districts, the provision of additional
training opportunity is required. The engineers and technicians in the disseminated districts have
acquired the ability to use GIS, but the continuous training is required for GIS manipulation. Technical
transfer from the engineers and technicians in the model districts to the disseminated districts
contributes to enhanced the technical capacity.
22
【Activity2-4】Prepare and update the rural road inventories in the model districts.
The inventory survey is usually conducted from October to December. The survey conducted of
collecting actual data for road length by using GPS, and road conditions by visual inspection. Up to
FY2013/2014, the inventory survey had been done by vehicle calibration odometer. The introduction
of GPS for the inventory survey accelerated the accumulation of inventory data. The Project
contributed to improving the efficiency of the inventory survey for data collection and accumulation
through the technical trainings.
Figure2-14 Training for Vehicle Calibration Odometer in Chamwino DC
【Activity2-5】Prepare and revise a medium and long-term rural road maintenance plan.
The Project encouraged the preparation of medium and long term plan in the model districts. The aim
is to improve the planning capacity of the model districts with the limited resources. The medium and
long term plan contributes to enabling (1) prioritization of maintenance needs, (2) production of
multi-year budgetary plans, and (3) full utilization of budget.
Table2-10 Mid-and Long Term Plan FY 2015/2016 Chamwino DC (Proposed)
【Activity2-6】
Confirm the needs of rural road maintenance in the model districts and prioritize the needs.
15% 20% 20% 30% 15%
RoadClass
NetworkPopulati
onEconomyActivity
Others R S P B/C R S P B/C R S P B/C
1Nagulo Mwitikira-Huzi-Manda-Ilangali
63.5 5.0 5.0 4.5 5.0 4.0 4.8 1
District road, conect to trunkroad,and three districtBahi,Manyoni and Dodomamunicidal
Fair 20.0 7.0 0.0 0.0 40.0 0.0 0.0 1 0.0 12.0 0.0 0
2 Chalinze-Chinangali I-Chilonwa 15.0 5.0 4.0 3.0 3.0 0.0 3.1 11Conect to trunk road and Regionroad
Good 15.0 0.0 0.0 0.0 0.0 10.0 0.0 0 5.0 5.0 0.0 1
4Huzi-Mpwayunga-khambaku-Ndogoe-Mlazo
61.7 3.0 4.0 4.5 5.0 0.0 3.7 8 conect to Mtera dam Fair 0.0 0.0 6.4 1.0 50.0 0.0 0.0 0 0.0 10.0 5.0 0
5
Nagulo – Mwitikira – Mpwayungu- Chinugulu 57.0 3.0 4.0 5.0 5.0 3.0 4.2 4
conect three villagesmpwayungu, chinugulu & farmarea
Fair 20.0 0.0 0.0 0.0 57.0 0.0 0.0 0 25.0 5.0 0.0 0
6
Haneti – Humekwa
18 3.0 2.0 3.0 3.0 2.0 2.7 16Connecting trunk road twodistrict chamwino & Kondoa
Poor 18.0 0.0 0.0 0.0 0.0 12.0 0.0 0 15.0 0.0 0.0 1
7Haneti – Kwahemu – Gwandi -Zajilwa – Umoja - Izava
67.3 3.0 5.0 4.5 5.0 3.0 4.3 3conecting Farm area & regionalroads
Fair 0.0 20.0 0.0 0.0 0.0 10.0 10.0 1 50.0 0.0 0.0 0
8 Dabalo – Manyemba - Malecela30.0 3.0 4.0 3.0 4.0 2.0 3.4 10
Feeder coneting wards and farmarea
Fair 20.0 0.0 0.0 0.0 0.0 10.0 0.0 0 20.0 5.0 0.0 1
9 Dabalo – Igamba - Chiwondo20.0 3.0 4.5 3.0 2.0 3.0 3.0 12
Feeder coneting wards and farmarea
Good 15.0 0.0 0.0 0.0 10.0 0.0 4.0 0 20.0 0.0 0.0 0
10Chalinze - Majeleko
8.0 3.0 3.0 2.0 2.0 0.0 2.1 18Feeder coneting wards and farmarea
Poor 6.0 0.0 0.0 0.0 0.0 0.0 8.0 0 6.0 0.0 0.0 0.0
priorityEvaluation/Comments
Condition/Deterioration/
Inventory
Prioritization
S/NRoad No./
NameLength
(km)
Value Index
Value
2015/16 2016/17 2017/18
23
The Project proposed to address the prioritization in the mid and long term plan. The indicators to
measure the prioritization are; (1) road class, (2) population, (3) road network, (4) economic activities,
and (5) others. The indicators shall be value added depends on DE’s experience or local situation.
Through the training in the Project, the model districts and disseminate districts have capacitated to
develop the mid-long term plan with the prioritization.
Figure 2-15 Proposed Value added prioritization
【Activity2-7】Prepare the annual rural road maintenance plans, including procurement,
construction method, etc., in consideration of gender aspects in the model districts.
The Project trialed to produce the annual plan with covering 23 items listed below. With the
experience of trials in the model districts, the Project proposes the contents of the annual plan shall to
be compatible to DROMAS-2.
Table 2-11 Items proposed for the Annual Rural Road Maintenance Plan
(1) Mid‐ and long‐term objectives (Vision)
(8) Coverage of road network (15) Surface type
(2) Annual objectives (9) Preliminary schedule (16) Distance (km)
(3) Strategies and specific activities for the annual objectives
(10) Procurement procedures (17) Time frame of rural road
maintenance works
(4) Information of classified roads (11) Work type (18) Supervision expenses
(5) Information of rural road inventories
(12) Type of structures (19) Establishment of unit costs for
road maintenance works
(6) Needs and priority ranking (13) Road name (20) Total cost (TSH)
(7) Selection of rural road maintenance works
(14) Application of LBT and/or EBT (21) Environment aspect
(22) Gender aspect (23) HIV/AIDS aspect
Source: Form 4, MS
24
Figure2-16 Annual Plan of the Model Districts
Through discussion with PMO-RALG, the annual plan that the Project trialed still seems difficult to be
standardized in LGAs. That is because RF only requires data on the type of road works, the road name,
the road length and the budget as the “Annual Plan” to be accumulated into DROMAS-2. The Project
proposed to PMO-RALG to verify the compatibility between the annual plan for DROMAS-2 and the
one the Project trialed.
【Activity2-8】Monitor the rural road maintenance in the model districts.
The Project monitored the progress and the procedure of the rural road maintenance work in the model
districts according to the Operational Guidelines. The progress of the road works in the model districts
is summarized as follows.
Table 2-12 The Procedure of the Road Works in the Model Districts
2014 2015 2016
7-9 10-12 1-3 4-6 7-9 10-12 1-3 4-6 7-9
Chamwino
Iringa
GPN: General Procurement Notice (Tender Advertisement) Rev: Review AG: Attorney General C: Contract
Chamwino DC
In FY2015/2016, 8 contracts were selected. After a budget review, this was decreased to 6 contracts,
including 2 contracts for LBT works. Since each of the contract amounts for the LBT works is less
than 50,000,000 Tsh, the district can start implementation without AG approval. The LBT works had
ADRICS2014 GPN AG C Rev.
ADRICS2015 GPN
ADRICS2014 GPN AG C
ADRICS2015 GPN
50% Cut Order
50% Cut Order
25
been contracted by the end of January 2016; implementation has started one site, while the other is in
preparation due to rain fall. 4 contracts for EBT works are still in waiting for AG approval.
Iringa DC
In December 2015, Iringa DC conducted tendering. At the end of January 2016, evaluation was carried
out. Iringa DC also decreased the numbers of selected works after budget review. Currently, all the
selected work is for EBT. LBT works will take place in the second phase of the procurement. LBT
pilot projects in the second phase will be estimated at 150,000,000 Tsh, which is required to get AG
approval. The implementation of LBT works in Iringa will start by May 2016.
Starting point for LBT in Iringa DC 2 Pipe culverts are planned to set
Road surface flushed away due to lack of ditch Road condition is good where a ditch is designed
LBT works will be started after the cultivation Tender advertizament of Iringa DC
Figure2-17 Kitayawa-Wangama Road (Iringa DC, LBT pilot site)
26
2.4 Progress and Achievement for Output-3
The practical skills and knowledge of responsible organizations on rural road maintenance are
improved through the LBT application in the model districts.
【Activity3-1】Select pilot projects in the model districts from the annual rural road
maintenance plan.
The Pilot Projects (hereafter referred to as PP) were selected after the inventory survey conducted in
FY 2013/2014 and 2014/2015. The criteria for the selection are as follows:
Criteria for the selection of PP
(1) Maintenance works by LBT.
(2) Periodic maintenance works is preferable, rather than routine maintenance works or spot
improvement works.
(3) Approved maintenance work projects by budget of Road Fund Board.
(4) Road section within needs of variety of maintenance activities including road formation, drainage
and concrete works.
Selection of Pilot Site FY2013/2014
(1) Chamwino DC:
Based on the above criteria, pilot site was selected at the eastern side of Chamwino district in
Dodoma Region along Handali – Chanhumba – Igandu Road with a total length of 26.8 km.
The maintained stretch was 7km in length.
(2) Iringa DC:
Based on the selection criteria, the location of a pilot site was selected at the south-west side
of Iringa district in Iringa Region along Wenda-Mgama Road with a total length of 20 km.
9km by LBT and the remainder by EBT.
Figure2-18 Location of the Pilot Project in FY 2013/2014 (Right: Chamwino DC, Left: Iringa DC)
27
Selection of Pilot Site FY2014/2015
(1) Chamwino DC:
Project-1:Nkwenda – Nhinhi – Wiliko – Mlowa bwawani – Mlodaa 34km
Maintained length 2.5km by LBT
Project-2: Haneti – Humekwa 18.2 Km
Maintained length 2.5km by LBT
Figure2-19 Location of the Pilot Project in Chamwino DC FY2014/2015
(2) Iringa DC:
Makombe-Magunga LBT 10km, LOT-II, LOT-III, LOT-IV, LOT-V 2.5km each Rehabilitation
Figure2-20 Location of the Pilot Project in Iringa DC FY2014/2015
【Activity3-2】Formulate work plans of the pilot projects.
The Project assisted the engineers and technicians in the model districts during in the Pilot Projects
accordingly to the Operational Guidelines. The outlines of the selected Pilot Projects are shown below.
28
Table 2-13 Outline of the work plan of the Pilot Projects Chamwino DC Iringa DC
FY 2013/2014 FY 2014/2015 FY2015/2016 FY 2013/2014 FY 2014/2015
Name of roads
Handali‐Chanhumba ‐Igandu‐Ngahelezi
Nhihi‐NkwendaHaneti‐ Humekwa
Nagulomwitika‐Hazi‐
Manda‐Ilangali Chinangali
II‐Mlebe‐Mnase‐Mgunga
Wenda‐Mgama Magunga ‐Makombe
Road Class Feeder Road Feeder Road District Road
Feeder Road District Road District Road
Maintenance type
Routine Routine Routine/Spot Periodic Rehabilitation
Length EBT/LBT
7km 2.5km LBT 2.5km LBT
2km LBT
1.5km LBT
Lot‐1: 10km EBT Lot‐2: 3km LBT Lot‐3: 3km LBT Lot‐4: 3km LBT
Lot‐1: 9.2km EBT Lot‐2: 2.5km LBT Lot‐3: 2.5km LBT Lot‐4: 2.5km LBT Lot‐5: 2.5km LBT
Cost
167,280,000 Tsh 42,545,000 Tsh 39,368,260 Tsh41,093,500 Tsh
LOT‐2: 44,937,500Tsh
LOT‐3:45,059,000Tsh LOT‐4: 42,377,000Tsh
Lot‐2: 49,600,000TshLot‐3: 50,012,500Tsh Lot‐4: 50,200,000Tsh Lot‐5: 53,506,500Tsh
【Activity3-3】Assist district engineers and technicians in the model districts to procure
contractors and supervise the pilot projects based on the work plans.
RMSD provided technical assistance on site. The Expert supported the soil test and the structural
design for the rehabilitation of the bridge which was damaged by the flood in Iringa DC. It was
planned to strengthen the river-bed to prevent flushing away, and the repair of the pier and
superstructure were implemented. The district engineer contributed his efforts to the rehabilitation, and
the DE himself conducted the designing of the superstructure, the soil test and the stability of the
sub-structure of the bridge. The rehabilitation work was started in July 2013 and completed in
December 2013.
Figure2-21 Before and After the rehabilitation of bridge in Iringa DC
29
The findings from the pilot project are as follows.
(1) LBT project costs were deliberately high for the pilot project in Chamwino while the cost of
road construction by LBT in Iringa DC was less compared with EBT. LGAs are recommended
to select the appropriate method to deploy.
(2) Some emergency works was necessary for the pilot project after the rain season.
(3) More culverts are still required for the pilot project.
(4) Needs to capacitate the engineers and technicians for the drawing and design of the structure.
(5) Needs to develop contract documents specified for the LBT works.
(6) Needs to shift the financial year for the Road Fund
(7) Needs to implement LBT works in the appropriate time. LBT road works should be
implemented soon after the rain season.
(8) LBT works contribute to increased employment in the community. LBT works also generate
ownership in the community.
(9) The quality of LBT works should be equal to that of EBT works, if the monitoring and
supervision are appropriate.
(10) LBT works are more environmentally friendly than EBT works.
(11) LBT works should be used in areas with lack of heavy equipment.
(12) LBT works are less dependent on fuel fluctuation.
(13) The use of LBT works in the periodic maintenance should be considered.
EBT‐Site 1: Before EBT‐Site 1: After
EBT Site‐2: Before EBT Site‐2: After
30
LBT Site‐1: Before LBT Site‐1: After
Figure 2-22 Before and After of the PP in Iringa DC
【Activity3-4】Provide consultations on the operation of the pilot projects for the district
engineers and technicians, contractors, etc. through ATTI.
ATTI acquires full of experience in LBT works as a training institution. The Project proposed to
PMO-RALG to utilize the techniques of ATTI in practice in the model districts. ATTI provided the
technical supervision in the Pilot Projects in Chamwino DC from November 2014 to January 2015,
and in Iringa DC in March 2015. As a result, it was difficult to realize the technical inputs from ATTI
for the model districts. That is because; 1) the assignment period has been too short, and 2) local
contractors depended on their own experience rather than the consultation by ATTI.
【Activity3-5】Promote PR activities on rural road maintenance through the pilot projects.
【PR Brochure】
A PR brochure on the pilot project was developed and distributed occasionally such as at the JCC-3,
stakeholder meeting in Arusha.
【LBT PR Video】
A documentary video of the pilot project in Chamwino DC was produced in 2015. The video lasting
15 minutes, consisted an interview with the district engineer in Chamwino DC and the community, the
implementation, the supervision etc. The video was aired on TV nationally and also provided at the
stakeholders’ meeting in Arusha in August 2015.
LBT PR Video Airing on TV
Title: The Project for Improvement of District Road
Air Time: 21-July-2015 from 19:00 pm to 19:15 pm
22-July-2015 from 9:00 am to 9:15 am
Broadcast Media: Star TV
31
【PR at the Regional Road Board Meeting】
The Project had an opportunity to promote PR activities in the regional Road
Board Meeting in Dodoma. The Project presented the activities of AMTC to
all the districts directors, engineers, councilors, and the Regional
Administrative Secretaries, engineers and MPs within the Dodoma Region on
17 February 2015.
【Activity3-6】Document the process, experiences, outcomes, and lessons learned of the pilot
projects.
The Project summarized the feedback from the pilot projects in the model districts in August 2015.
DEs in the model districts presented the good practice and challenges, while RSEs presented the
lessons learned from the monitoring activities. The findings on using the Operational Guidelines are
summarized as “Before and After, Challenges”.
Table 2-14 Before and After, Challenges of the Operational Guidelines in practice
Wok Stage In Charge Before After Challenge
PLANNING
1. Annual District Inventory and Condition Survey (ADRICS)
LGAs Data was Processed Manually Vehicle Odometer Calibration was not applied
Start utilizing GPS for the actual Distance Data was processed in Excel Format Vehicle Odometer Calibration was applied
A cost effective way of assessing traffic volume with limited resources. Category of Low Volume Traffic Date per Day shall be reconsidered A road network map or diagram shall be available in all the districts.
RSE No guidelines to assist monitoring
Standardized Guidelines for Monitoring
PMO‐RALG Lack of reflection to Mapping, appropriate Network
2. Processing inventory data
LGAs Data was Processed Manually
Data was processed in Excel Format, attached in Annex
A system of transferring data from the inventory data to DROMAS.
3. Annual Plan LGAs Annual Plan was not accurate due to possible errors in ADRICS and budgeting forms.
Compile annual data to Annual Plan Efficiency has been improved for the preparation
More simplified format.
4. Mid‐Long Term Plan
LGAs There was no mid‐long Term Plan in LGAs
Detailed category evaluation data are included in the mid‐to‐long term plan.
Implementation of the mid‐to‐long term plan. Technical difficulties of planning because the types of surface.
5. Prioritization of maintenance works
LGAs There was a Prioritization Concept in DROMAS; however it did not function well.
Prioritization became more rational with the mid‐to long term plan
Convincing politician on prioritization. Consensus building mechanism
32
6. Specific Policy Issues
LGAs Issue of Gender, HIV/AIDS, Environment were not Addressed Enough
Specific Policy Issues are emphasized in the Guidelines
Need More Commitment for the Specific Policy
PROCUREMENT
1. Procurement plan/procedure
RFB Procedures were available in the Public Procurement Act and its amendment and its regulations. Not complied to the Act.
The OG emphasizes compliance with the Act and regulations.
Contract vetting to attorney general delays the procurement cycle. The process requires more resources. Registration of power of attorney.
2. Specifications MoW The specifications cannot be attached to the contract. Technical manuals are available.
No LBT specifications. EBT spec cannot be transformed o LBT. Preparation of simplified specifications that can be attached to the contract and tender documents.
3. Tender Document PMU/DE Office
no change No LBT specifications. EBT spec cannot be transformed o LBT. Preparation of simplified specifications that can be attached to the contract and tender documents.
4. Contract Document
PMU/DE Office
PPRA PPRA document was specified.
No LBT specifications. EBT spec cannot be transformed o LBT. Preparation of simplified specifications that can be attached to the contract and tender documents.
IMPLEMENTATION
1. Quality Assurance LGAs Not standardized. Form 17 is included. There may some more forms to be prepared. Use of the forms need to be explained.
2. Supervising the Work Progress
LGAs Not standardized. Form 16 is included. A contractor management system or procedure needs to be developed.
3 Monitoring LGAs No form. No form. Monitoring Form 7 needs to shall be included.
MONITORING
Monitoring and Evaluation
RSE Not systematic, ad hoc No guideline; no procedure. No training in the process of monitoring.
A monitoring plan is developed. A guideline and procedure were developed. Training is included in the process of monitoring.
Evaluation shall be conducted at the end of the financial year separately.
33
2.5 Progress and Achievement for Output-4
The dissemination mechanism for rural road maintenance approach within the respective
regions is established.
【Activity4-1】Organize sensitization workshops on rural road maintenance for the other LGAs
in the respective regions in collaboration with the RS engineers.
The Project convened the workshops to select dissemination districts in 2014. The dissemination
districts are selected with the criteria mentioned in Activity 4-2 as Kondoa DC in Dodoma region, and
Mufindi DC in Iringa region. In the workshops, RSEs and DEs in the model districts explained the
project outlines and the mechanism of the dissemination. By November 2014, Annual Monitoring and
Training Cycle (referred to as “AMTC”) were developed as the technical transfer tools to disseminate
the project outputs.
Figure 2-23 Topic and cycle of AMTC
Table 2-15 AMTC Operation in the Project
Date Topic Person in Charge Place
AMTC in Dodoma Region
14‐Nov‐2014 AMTC as dissemination system
Mid‐Long Term Plan
Dodoma RSE/RMSD
Chamwino DE
Kondoa
DC
4‐Feb‐2015 Budgeting/Annual Plan
Quarterly Progress report
Operational Guidelines Chapter 1&2
Chamwino engineer/technician
Dodoma RSE/Chamwino technician
Dodoma RSE
Kondoa
DC
1‐Sep‐2015 Procurement, Bidding & Contract document
Guidelines; Planning & Implementation
Implementation
Inventory, Practical use of GPS for inventory,
Processing GPS data, Mapping
Kondoa DE
Dodoma RSE
Chamwino DE
Chamwino engineer/technician
Chamwio engineer/technician
Kondoa
DC
27‐Nov‐2015 Inventory, GPS use for Inventory, Data
Processing, Mapping
Guidelines; Planning
Planning and Budgeting
Annual, mid‐‐Long Term Plan, Prioritization
Kondoa DE
Kondoa DE
Dodoma RSE assistant
Chamwino DE
Chamwino engineer/technician
Kondoa
DC
18‐Jan‐2016 Planning and Budgeting
Annual, mid‐‐Long Term Plan, Prioritization
Guidelines; Procurement
Procurement, Tendering, Contract Document
Kondoa DE
Kondoa DE
Dodoma RSE assistant
Chamwino DE
Kondoa
DC
PresentationDisseminated
District
Workshop
Model District
First Quarter(July ‐ Sep)
Second Quarter(Oct ‐ Dec)
Third Quarter(Jan ‐Mar)
Fourth Quarter(Apr ‐ June)
Bidding DocumentationSupervision/Quality
Management
ADRICSInventory SurveyMapping (GPS)
ADRICSInventory SurveyMapping (GPS)
Mid and Long term plan Annual plan, Prioritization
Mid and Long term plan Annual plan, Prioritization
Contract ManagementLBT Application
Contract ManagementLBT Application
Bidding DocumentationSupervision/Quality
Management
34
AMTC in Iringa Region
4‐Dec‐2014 AMTC as dissemination system
Mid‐Long Term Plan
Iringa RSE/RMSD
Iringa DE
Mufindi
DC
4‐Mar‐2015 Budgeting/Annual Plan
Quarterly Progress report
Guidelines Chapter 1&2
Iringa engineer/technician
Iringa RSE/Iringa engineer
Iringa RSE
Mufindi
DC
9‐Sep‐2015 Procurement, Bidding & Contract document
Guidelines; Planning & Implementation
Implementation
Inventory, Practical use of GPS for inventory,
Processing the GPS data, Mapping
Mufindi DE
Iringa RSE
Iringa DE
Iringa engineer/technician
Iringa engineer/technician
Mufindi
DC
4‐Dec‐2015 Inventory, GPS use for Inventory, Data
Processing, Mapping
Guidelines; Planning
Planning and Budgeting
Annual, mid‐‐Long Term Plan, Prioritization
Mufindi DE
Mufindi DE
Iringa RSE assistant
Iringa DE
Iringa engineer/technician
Mufindi
DC
15‐Jan‐2016 Planning and Budgeting
Annual, Mid‐‐Long Term Plan, Prioritization
Guidelines; Procurement
Procurement, Tendering, Contract Document
Mufindi DE
Mufindi DE
Iringa RSE assistant
Iringa engineer
Mufindi
DC
Figure2-24 Photos of AMTC in Mufindi DC and Kondoa DC
Lessons Learned from the AMTC
The lessons learned from the operation of AMTC are as follows.
1) Need to strengthen the organizational structure of RSEs
AMTC is designed to operate within the scope of the RSEs monitoring cycle, i.e. quarterly basis. It is
because a commitment from the RSEs is essential to the AMTC. However, most of the RSEs are too
busy as they cover the whole area of rural road activities in the regions. They are normally overworked
due to insufficient number of personnel. In order to operate AMTC in a sustainable way, strengthening
of the organizational structure of RSEs is required.
2) Need to ensure the appropriate time for the operation
AMTC aims to monitor and confirm the current work procedure, and to prepare for the coming work
stage in the districts. In the project trial, RSEs could not arrange their time for AMTC on some
occasion. It is required to operate AMTC at the appropriate time to adjust the practical work procedure
in the LGAs.
35
3) Need to secure sufficient budget for the model districts
Within the project period, the Project had a responsibility for the operation of AMTC, i.e. allowance
and transport costs for the model districts. For the continuous operation of AMTC, PMO-RALG is
required to secure sufficient budget for the model districts.
4) Need to produce the practical materials for AMTC
The materials used for AMTC is the Operational Guidelines. The experts of the Project also produced
the technical manuals for the model districts that are used in the instruction. The model districts are
expected to transfer their lessons learned to the disseminated districts. PMO-RALG is required to
encourage the model districts to produce the practical materials based on their experience for AMTC.
【Activity4-2】Select a LGA to be disseminated in the respective regions.
The Project defined indicators to select the disseminated districts as follows.
a. Availability of local-based Contractors, sufficient number of qualified staff with LBT
training
b. Lack of heavy equipment, difficulty to hire or lease
c. Lack of support from the Development Partners
d. Willingness to work in the Project, experience of rural participatory approach
e. Relationship with JICA (Japan Overseas Cooperation Volunteers)
Dodoma region
Dodoma region has 7 Councils (as of May 2014); Dodoma MC, Chamwino DC, Kondoa DC,
Mpwapwa DC, Kongwa DC, Chemba DC and Bahi DC. According to the criteria for the disseminated
district, Kondoa DC is selected.
Iringa region
Iringa region has 4 Councils (as of May 2014); Iringa MC, Iringa DC, Kilolo DC and Mufindi DC.
Mufindi DC is selected for the disseminated district, according to the criteria.
【Activity4-3】Assist the LGAs selected in the respective regions to promote rural road
maintenance based on the guidelines with the full commitments of RS engineers
The Project supports operation of AMTC as mentioned in Activity4-1.
【Activity4-4】Monitor the rural road maintenance promoted by the LGAs in the respective
regions.
36
The Project monitored the progress of the road works in the disseminated districts as follows.
Table 2-16 The Procedure of the Road Works in the Disseminated Districts
2014 2015 2016
7-9 10-12 1-3 4-6 7-9 10-12 1-3 4-6 7-9
Kondoa
Mufindi
GPN: General Procurement Notice (Tender Advertisement) Rev: Review, AG: Attorney General, C: Contract
Kondoa DC
ADRICS-2014 was conducted from September to December 2014. In 2015, the Project provided
technical training for GPS/GIS utilization for the inventory survey. It contributed to Kondoa DC ‘s
execution of ADRICS-2015 by utilizing GIS.
Starting point for LBT in Kondoa DC Intervew by the expert
The first river with drift structire Second river, inpassable in rainy season
Figure2-25 Unkuku-Loo-Kalamba Road, Pilot Site in Kondoa DC
ADRICS2014
GPN AG C
GPN
ADRICS2015
ADRICS2014
ADRICS2015 GPN
GIS Training2 GIS
GIS Training2 GIS
(Previous Method)
(Previous Method)
50% Cut Order GPN
AG
C
50% Cut Order
37
Mufindi DC
Mufindi DC has been divided into Mufindi Town Council (TC) and Mufindi District in 2016. The
disseminated district remains as Mufindi DC. The engineers and technicians were also divided into
two. Both Mufindi TC and Mufindi DC have insufficient numbers of engineers. This caused further
delay in the submission of the district budget request to PMO-RALG. If at the end of January 2016,
the district budget is not yet approved by PMO-RALG, then the tendering procedure will be delayed to
July 2016.
【Activity4-5】Feedback the monitoring results into the guidelines.
The late disbursement of the budget caused the delay of the road work procedure in the disseminated
districts. RSEs continuously monitor the progress of road works in the disseminated districts, but it
shall be impossible to reflect lessons learned from the pilot site in the disseminated districts by the
completion of the Project. PMO-RALG is required to reflect the feedback to the Operational
Guidelines after the project period.
2.6 LBT Equipment Management
【LBT Equipment Leasing System】
2.6.1. Outline of Equipment Leasing Plan
(1) Leasing Estimation (Outline of Annual Leasing Budget Plan)
The equipment leasing system, which is in its second year, is reviewed in terms of its achievement
against its plan, as there are some differences between the original plan and the results. The outline of
the original leasing plan (made in 2012/13) is as follows.
Table2-17 Chamwino DC Annual Leasing Budget Plan
Table2-18 Iringa DC Annual Leasing Budget Plan
abc
de
Tractor + Tow GraderTractor +WaterBowser+Pump
Pedistrian Roller Plate Compactor Water Pump Total
Yealy Income a*b 9,000,000 7,500,000 7,500,000 2,000,000 900,000 26,900,000
Hiring Rate Tsh. 300,000 250,000 150,000 50,000 30,000Yealy Hir. Days days 30 30 50 40 30 180
1.715,811 4,506,787884,189 22,393,213
Average Mait. Ratio % 2.7 2.7+1.7Maintenance Cost Tsh. 1,672,380
2.8 1.71,771,810 832,278 214,508
Fiscal Income c-d 7,327,620 5,728,190 6,667,722 1,785,492
The yearly leasing days was estimated based on the premises that the construction estimates (BOQ),
abc
de
Average Mait. Ratio % 2.7 * 2.7 1.7 1.7Maintenance Cost Tsh. 3,344,760 4,500,000 832,278 214,508 15,811 8,907,357
9,692,643Fiscal Income c-d 2,655,240 2,300,000 3,167,722 785,492 784,189
Hiring Rate Tsh. 200,000 170,000 100,000 25,000 20,000Yealy Hir. Days days 30 40 40 40 40 190
4,000,000 1,000,000 800,000 18,600,000Yealy Income a*b 6,000,000 6,800,000
Tractor + Tow Grader Water Bowser+Pump Pedistrian Roller Plate Compactor Water Pump Total
38
the equipment cost (about 20 to 30% in the LBT annual budget) regarding construction budget, and the
hiring from private finance are zero.
The equipment leasing price was determined using the prices of private leasing companies and
experiences of LBT construction contractors(the estimated prices in Iringa district were high because
the quotation of private leasing companies were higher than in Chamwino district due to equipment
shortage in Iringa district).
The estimated revenue was calculated based on the equipment leasing cost in consideration of the
maintenance and administration cost.
For the water tank cars in Chamwino district, the maintenance and administration cost was estimated
to be higher as existing equipment was used. For the equipment maintenance, a guideline (details of
equipment, own spare parts, management form, routine inspection form, contract, etc.) was prepared
for the administration (see details of the report of 2012/13)
(2) Leasing Prices
The leasing price transition was as follows. The prices in each district have been changed and
amended as appropriate by considering the prices of private leasing companies and the current
situation (difficulty of procurement, transportation cost, etc.) of construction contractors. For Iringa
district, whose prices have been pointed out to be higher than those of private companies, the prices
were amended as of 07/2015.
Table 2-19 Leasing Price Transition (Chamwino DC) Table 2-20 Leasing Price Transition (Iringa DC)
2.6.2. Comparison of Achievement with Plan in 2013/14, 14/15
(1) Leasing Achievement (Degree of Attainment in Leasing Revenues)
The leasing revenues were largely lower than the estimates in each district due to the delay of
equipment delivery and inexperience in LBT construction management (Chamwino district 25.7%,
Iringa district 38.5%). However, the leasing revenues dramatically increased in each district because in
the second year the use of equipment in construction was more strictly required, the equipment leasing
service had become more popular among the construction contractors, and leasing by
Equipment-based Technology (EBT) contractors has started (Chamwino district 126.6% compared
with estimation. 492.8% compared with previous year, Iringa district 46% and 124.7%, respectively).
Plate Compactor 25,000 30,000 25,000 30,000Water Pump 20,000 25,000
Planned 14/7~ 15/7~LBT Private LBT Private LBT Private
Tractor 150,000 17,000 120,000 120,000Pedestrian Roller 150,000 17,000 100,000 120,000
Same as 14
20,000 25,000
Water Tank 110,000 150,000 150,000 170,000Towed Grader 60,000 100,000
50,000Water Pump 20,000 25,000 20,000 25,000 30,000 40,000Plate Compactor 25,000 30,000 25,000 30,000 30,000
120,000Pedestrian Roller 150,000 17,000 100,000 120,000 100,000 120,000Tractor 150,000 17,000 120,000 120,000 120,000
150,000Towed Grader 60,000 100,000 60,000Water Tank 110,000 150,000 150,000 170,000 130,000
Planned 14/7~ 15/7~LBT Private LBT Private LBT Private
39
Table 2-21 Result &Target Comparison in Chamwino DC Table2-22 Result &Target Comparison in Chamwino DC.
The total achievements in the two years, with the maintenance and administration cost deducted, was
68% in Chamwino district and 43% in Iringa district compared with the estimated amount in the plan,
because there was not much use of tow graders for levelling off the final road surface, which affects
the finishing of constructions, and the use frequency of the equipment was low in terms of
construction scales.
Table 2-23 2 Years Income Comparison
(Chamwino DC)
Table2-24 2 Years Comparison (Iringa DC)
For future improvement, the on-site management by the district technical staff and the equipment use
instruction of BOQ should be reinforced. The degrees of attainment for vibrating rollers and water
tank cars, which are equipment necessary for the road bed construction that accounts for the main part
of the constructions, are 70% or higher.
(2) Degree of Attainment in Leasing Period (Days)
The achievements in both districts were 38% against target leasing periods. At first, the estimation was
worked out on the premise that the equipment would be leased to individual contractors. However, the
contract was such that a plurality of contractors was assigned to the construction of the same road.
Therefore, the equipment could be shared among the plurality of contractors. Due to mishandling by
BOQ (the usage of the necessary equipment, especially tow graders, was not limited), the achievement
was greatly smaller than the plan, but the achievement as to the water tank cars was slightly less than
70% or more in both districts due to the large capacities of the cars and low prices compared with
market prices, while about 40% of the achievement in Chamwino district were those by EBT
(Equipment based technology) contractors.
(Tsh.)
Plate Compactor 330,000 0 330,000Water Pump 60,000 140,000 200,000
14,760,000CPY(%)
Total 2,490,000 12,270,000492.8
CT(%) 25.7 126.6
Water Bowser 1,020,000 8,840,000 9,860,000
Tractor/Towed Grader 0 0 0Pedestrian Roller 1,080,000 3,290,000 4,370,000
2013/14 2014/15(May) Total
(Tsh.)2013/14 2014/15(May) 計
50,000 600,000Water Pump
Tractor/Towed Grader 300,000 0 300,000Pedestrian Roller 5,520,000 2,700,000 8,220,000Tractor/water Bowser 2,250,000 8,000,000 10,250,000Plate Compactor 550,000
Total 8,620,000 10,750,000 19,370,000CPY(%)CT(%) 38.5 48.0
124.7
(Tsh.)
4,370,000 69.0W/Tank ・Pump 6,168,378 8,972,000 145.5Plate Compactor 1,570,858 330,000 21.0
5,310,480 0 0.0Ped. Roller 6,335,444
Others 0 -480,000Total 19,385,160 13,192,000 68.1
Target(2yer.)Hire Amount(excl.maintenance cost)
Acmp.(%)
Tractor/ Towed Grader
(Tsh.)
Tractor/ Towed Grader
74.8Plate Compactor 3,570,984 600,000 16.8
Total 43,018,048 18,504,200
14,655,240 300,000 2.0Ped. Roller 11,456,380 7,630,200 66.6
43.0
13,335,444 9,974,000W ・Tank /Pump/Tractor
Target(2yer.)Hire Amount(excl.maintenance cost)
Acmp.(%)
40
Table2-25 Leasing Period/Days (Chamwino DC) Table2-26 Leasing Period/Days (Iringa DC)
(3) Achievements in Equipment Maintenance
The increase in expense in Chamwino district was the result of non-use of the tow graders (causing no
maintenance and administration cost), the use of existing water bowser, while, for the other equipment,
the initial spare parts was utilized and the periods they were used were short. For the achievement in
Iringa district, it is deduced that, as described above, the use frequencies for tractors (for towing water
bowser) and vibrating rollers were high.
Table2-27 Maintenance Cost (Chamwino DC) Table2-28 Maintenance Cost (Iringa DC)
(4) Expense for Depreciation
The depreciation rate for the purchase values in Chamwino district was 7.4% including the initial
expenses (spare parts, transportation, training cost etc.), and 8.2 % excluding the initial expenses. The
depreciation period is 13 to 14 years if it is simply based on the depreciation rate. This is substantially
reasonable compared with the statutory depreciation period of 12 year for machinery. For Iringa
district, the depreciation rates are 8.6% and 9.4%, respectively, which are similar to the statutory
depreciation period as well (11 to 12 years). Note that these figures are simple comparisons of the
figures in last 2 years and the later mid/long-term prediction shows different results.
Table2-29 Expense for depreciation including initial cost (Chamwino DC)
Targeted Days(2yr.)
2014/15 (~May) 0 26 59 0 85Total 0 35 68 11 114
Accomp.(%) 0.0 43.8 85.0 13.8 38.0
Equipment Tractor/TowedGrader
Ped. RollerW・Tank/(Pump)
PlateCompactor
TotalYear
60 80 80 80 3002013/14 0 9 9 11 29
Targeted Days(2yr.)2013/14
2014/15 (~May)
Equipment
Year
Tractor/TowedGrader
Ped. RollerW・Tank
/Pump/Tractor
PlateCompactor
Total
TotalAccomp.(8%)
2
100421860
60.0
609
3241
68.3
6020
15.0
3006451
11538.3
112
8011
3.3
(Tsh.)
2014/15Total 480,0000
200,000280,000
00
Total
650,000918,000
1,568,000
Tractor
000
TowedGrader
WaterBowser/Pump
Ped. RollerPlate
CompactorOthers
000
450,000638,000
1,088,000
000
2013/14
(Tsh.)
2013/14 12,000 0 120,000 0 132,000
TowedGrader
Ped. RollerPlate
CompactorTotal
2014/15 264,000 0 469,800 0 743,800
W・Tank/Pump/Tractor
Total 276,000 0 589,800 0 865,800
EquipmetCost
Equipmet Cost①
ResidualValue②
DepreciationValue3
(①-②)Income④
Maintenance&Other Cost⑤
Net Income⑥(④-⑤)
DepreciationRatio(⑥/
③)Unit US$ Tsh Tsh Tsh Tsh Tsh Tsh %
Tractor 76,000 138,320,000 13,832,000 124,488,000Towed Grader 0*1 0 0 0Pedestrain Roller 18,500 33,670,000 3,367,000 30,303,000 4,370,000 0 4,370,000 14.4Water Bowser 0 0 0 0Water Pump 500 910,000 91,000 819,000Plate Compactor 6,900 12,558,000 1,255,800 11,302,200 330,000 0 330,000 2.9Others(Initial parts, transit cost 10,800 19,656,000 1,965,600 17,690,400 480,000
Total 112,700 205,114,000 20,511,400 184,602,600 14,760,000 1,568,000 13,672,000 7.4
*
7.2
0
10,060,000
0
1,088,000
0
8,972,000
41
Table2-30 Expense for depreciation excluding initial cost (Chamwino DC)
EquipmentCost
EquipmentCost①
Residualvalue②
DepreciationValue③(①-②)
Income④Maintenance& Other cost
⑤
Net Income⑥(④-⑤)
Depreciation Ratio
(⑥/③)
Unit US$ Tsh.*2 Tsh. Tsh. Tsh. Tsh. Tsh. %Tractor 76,000 138,320,000 13,832,000 124,488,000
0 0 0 *Towed Grader 0*1 0 0 0Pedestrian Roller 18,500 33,670,000 3,367,000 30,303,000 4,370,000 0 4,370,000 14.4Water Bowser 0 0 0
10,060,000 1,088,000 8,972,000 7.2Water Pump 500 910,000 91,000 819,000Plate Compactor 6,900 12,558,000 1,255,800 11,302,200 330,000 0 330,000 2.9Othehs(Intial part ,transp 10,800 0 480,000
Total 112,700 185,458,000 18,545,800 166,912,200 14,760,000 1,568,000 13,672,000 8.2
Table2-31 Expense for depreciation including initial cost (Iringa DC)
Table2-32 Expense for depreciation excluding initial cost (Iringa DC)
Tractor 76,000 138,320,000 13,832,000 124,488,000300,000 0 300,000 *
Towed Grader 0*1 0 0 0
EquipmentCost
EquipmentCost
Residual valueDepreciation
ValueIncome
Maintenance& Other cost
Net IncomeDepreciation Ratio
Unit US$ Tsh.*2 Tsh. Tsh. Tsh. Tsh. Tsh. %
Total 130,700 237,874,000 23,787,400 196,396,200 19,370,000 865,800 18,504,200 9.4
Pedestrian Roller 18,500 33,670,000 3,367,000 30,303,000 8,220,000 589,800 7,630,200 25.229,484,000
10,250,000 276,000 9,974,000 6.6Water Pump 500 910,000 91,000 819,000Water Bowser 18,000 32,760,000 3,276,000
Plate Compactor 6,900 12,558,000 1,255,800 11,302,200 600,000 0 600,000 5.3Othehs(Intial part ,transp 10,800 19,656,000 1,965,600 0
It was instructed to prepare mid/long-term plans without considering the initial expenses, in order to
give priority to the depreciation cost (rate) in these government-funded organizations in which the
concepts of project leasing equipment and depreciation etc. are not highly regarded.
(5) Revenue prediction for next 3 years (average)
The annual leasing period was amended based on the achievements and the experiences of the past
projects (constructions), amending the annual target amounts for the next 3 years. The figures below
are targets for each district, in which the leasing amount for Chamwino district is increased by 31%
from the initial target amount, and the leasing amount for Iringa district is decreased by 44% from the
initial target amount, because the use of tractors is expected in Chamwino district while the LBT
constructions have progressed substantially according to the plan in Iringa district, expecting an
increase in the maintenance and administration cost surpassing the expected increases in leasing prices
EquipmentCost
EquipmentCost
Residual valueDepreciation
ValueIncome
Maintenance& Other cost
Net IncomeDepreciation Ratio
Unit US$ Tsh.*2 Tsh. Tsh. Tsh. Tsh. Tsh. %Tractor 76,000 138,320,000 13,832,000 124,488,000
300,000 0 300,000 *Towed Grader 0*1 0 0 0Pedestrian Roller 18,500 33,670,000 3,367,000 30,303,000 8,220,000 589,800 7,630,200 25.2Water Bowser 18,000 32,760,000 3,276,000 29,484,000
10,250,000 276,000 9,974,000 6.6Water Pump 500 910,000 91,000 819,000Plate Compactor 6,900 12,558,000 1,255,800 11,302,200 600,000 0 600,000 5.3Othehs(Intial part ,transp 10,800 19,656,000 1,965,600 17,690,400
Total 130,700 237,874,000 23,787,400 214,086,600 19,370,000 865,800 18,504,200 8.6
42
etc. Note that these figures are expected values (averages) on a single-year basis, thereby having a
margin of error from the mid/long-term prediction.
Table2-33 Revenue prediction for next 3 years (average, Chamwino DC)
Table2-34 Revenue prediction for next 3 years (average, Iringa DC)
2.6.3. Mid/Long-Term Prediction
Prediction is carried out based on the current equipment for a period of 12 years, which is the useful
life of the equipment. The prediction shows that the maintenance and administration cost rate will
sharply increase compared with the leasing revenue increase rate after 7 years from installation, so that
no dramatic increase in revenue can be expected from then. Moreover, the depreciation rate will be
98.1%, which is slightly closer to the amortized value. The prediction shows that the depreciation rate
in Iringa district after 12 years is similarly 77%, which is far different from amortization, due to
similar reasons as for Chamwino district and the high initial depreciation price (about 30 million
schilling in comparison with Chamino district, for purchase of water bowser).
Table2-35 Mid/Long-Term Prediction without equipment renewal (Chamwino DC)
Table2-36 Mid/Long-Term Prediction without equipment renewal (Iringa DC)
abc
de
Tractor + Tow Grader Water Bowser Pedistrian Roller Plate Compactor Water Pump Total
Hiring Rate Tsh. 220,000 150,000-170,000 100,000-120,000 25,000-30,000 20,000-25,000Yealy Hir. Days Days 15 50 40 10 20 135Yealy Income(AV) a*b 3,300,000 8,000,000 4,400,000 275,000 450,000 16,425,000Average Mait. Ratio % 1.0 * 2.0 1.7 1.7Maintenance Cost Tsh. 1,244,880 1,500,000 818,181 192,137 9,828 3,765,026Fiscal Income c-d 2,055,120 6,500,000 3,581,819 82,863 440,172 12,659,974
abc
de
Water Pump
30,00010
300,0001.7
9,828290,172
Total
13017,000,000
4,499,25812,500,742
Tractor + Tow GraderTractor +WaterBowser+Pump
Pedistrian Roller
Hiring Rate Tsh. 180,000 250,000 100,000Days 20 30 50
Plate Compactor
30,00020
Average Mait. Ratio % 2.7 2.7+1.7 2.7Yealy Income a*b 3,600,000 7,500,000 5,000,000 600,000
1.7Maintenance Cost Tsh. 1,680,588 1,798,524 818,181
Yealy Hir. Days
Fiscal Income c-d 1,919,412 5,701,476 4,181,819192,137407,863
1 (2013/14) 2 (2014/15) 3 (2015/16) 4 (2016/17) 5 (2017/18) 6 (2018/19) 7 (2019/20) 8(2020/21) 9 (2021/22) 10 (2022/23) 11 (2023/24) 12 (2024/25)166,912,200 166,912,200 166,912,200 166,912,200 166,912,200 166,912,200 166,912,200 166,912,200 166,912,200 166,912,200 166,912,200 166,912,200
2,490,000 12,270,000 14,724,000 18,405,000 22,086,000 25,398,900 27,938,790 29,894,505 31,389,231 32,958,692 33,947,453 34,965,876
492.8 20.0 25.0 20.0 15.0 10.0 7.0 5.0 5.0 3.0 3.0
650,000 918,000 2,503,683 5,007,366 8,345,610 11,683,854 11,683,854 13,352,976 16,691,220 16,691,220 16,691,220 20,029,464
0.4 0.5 1.5 3.0 5.0 7.0 7.0 8.0 10.0 10.0 10.0 12.0
2,490,000 12,270,000 12,220,317 13,397,634 13,740,390 13,715,046 16,254,936 16,541,529 14,698,011 16,267,472 17,256,233 14,936,412
14,760,000 26,980,317 40,377,951 54,118,341 67,833,387 84,088,323 100,629,852 115,327,863 131,595,335 148,851,568 163,787,980
13,909,350 13,909,350 13,909,350 13,909,350 13,909,350 13,909,350 13,909,350 13,909,350 13,909,350 13,909,350 13,909,350 13,909,350
13,909,350 27,818,700 41,728,050 55,637,400 69,546,750 83,456,100 97,365,450 111,274,800 125,184,150 139,093,500 153,002,850 166,912,200-11,419,350 -13,058,700 -14,747,733 -15,259,449 -15,428,409 -15,622,713 -13,277,127 -10,644,948 -9,856,287 -7,498,165 -4,151,282 -3,124,220
1.5 7.4 7.3 8.0 8.2 8.2 9.7 9.9 8.8 9.7 10.3 8.98.8 16.2 24.2 32.4 40.6 50.4 60.3 69.1 78.8 89.2 98.1
Total Depreciation cost(Tsh.)Lease Income(Tsh.)Lease Income Increasing Ratio( %,comparison to previous year)Yearly Maintenance Cost(Tsh.)Maintenance Cost ratio to Depreciationcost(%)
Yearly depreciation ratio(%)Total Depreciation ratio(%)
Balance(Tsh. Income - Maintenancecost)Income Accumulation(Tsh.)Yearly Depreciation Cost (Tsh.12 yearequal depreciation)Total depreciation cost(Tsh.)Total balance(Tsh.)
1 (2013/14) 2 (2014/15) 3 (2015/16) 4 (2016/17) 5 (2017/18) 6 (2018/19) 7 (2019/20) 8(2020/21) 9 (2021/22) 10 (2022/23) 11 (2023/24) 12 (2024/25)196,396,200 196,396,200 196,396,200 196,396,200 196,396,200 196,396,200 196,396,200 196,396,200 196,396,200 196,396,200 196,396,200 196,396,200
8,620,000 10,750,000 12,900,000 16,125,000 19,350,000 22,252,500 24,477,750 26,191,193 27,500,752 28,875,790 29,742,063 30,634,325
24.7 20.0 25.0 20.0 15.0 10.0 7.0 5.0 5.0 3.0 3.0
132,000 743,800 1,963,962 2,945,943 3,927,924 4,909,905 5,891,886 9,819,810 13,747,734 17,675,658 19,639,620 23,567,544
0.1 0.4 1.0 1.5 2.0 2.5 3.0 5.0 7.0 9.0 10.0 12.0
8,488,000 10,006,200 10,936,038 13,179,057 15,422,076 17,342,595 18,585,864 16,371,383 13,753,018 11,200,132 10,102,443 7,066,78118,494,200 29,430,238 42,609,295 58,031,371 75,373,966 93,959,830 110,331,213 124,084,231 135,284,362 145,386,806 152,453,587
16,366,350 16,366,350 16,366,350 16,366,350 16,366,350 16,366,350 16,366,350 16,366,350 16,366,350 16,366,350 16,366,350 16,366,350
16,366,350 32,732,700 49,099,050 65,465,400 81,831,750 98,198,100 114,564,450 130,930,800 147,297,150 163,663,500 180,029,850 196,396,200-7,878,350 -14,238,500 -19,668,812 -22,856,105 -23,800,379 -22,824,134 -20,604,620 -20,599,588 -23,212,919 -28,379,138 -34,643,044 -43,942,613
4.3 5.1 5.6 6.7 7.9 8.8 9.5 8.3 7.0 5.7 5.1 3.69.4 15.0 21.7 29.5 38.4 47.8 56.2 63.2 68.9 74.0 77.6
Total Depreciation cost(Tsh.)Lease Income(Tsh.)
Lease Income Increasing Ratio( %,comparison to previous year)
Yearly Maintenance Cost(Tsh.)Maintenance Cost ratio to Depreciationcost(%)Balance(Income - Maintenance cost,Tsh.)Income Accumulation
Yearly Depreciation Cost (Tsh.12 yearequal depreciation)
Total depreciation cost(Tsh.)Total balance(Tsh.)Yearly depreciation ratio(%)Total Depreciation ratio(%)
43
In the case that the renewal of equipment is carried out while the depreciation is in effect, it is
predicted that both the districts will be able to purchase, in the 5th year and the 8th year, respectively,
small-size vibration rollers that are expected to be high in demand. In this case, the increase in the
leasing revenue after the purchase will make it possible to sell the equipment to LBT small contractors,
which is what is tried in this system and leads to the goal of stabilization of business. Similarly, the
district office will become able to reduce the maintenance and administration cost and to stabilize the
supply by equipment renewal. Moreover, the completion of the depreciation of the purchased
equipment (including renewal equipment) in 12 years is a large benefit obtained as result of the
renewal.
Table2-37 Mid/Long-Term Prediction with equipment renewal (Chamwino DC)
Table2-38 Mid/Long-Term Prediction with equipment renewal (Iringa DC)
1 (2013/14) 2 (2014/15) 3 (2015/16) 4 (2016/17) 5 (2017/18) 6 (2018/19) 7 (2019/20) 8(2020/21) 9 (2021/22) 10 (2022/23) 11 (2023/24) 12 (2024/25)196,396,200 196,396,200 196,396,200 196,396,200 196,396,200 193,029,200 193,029,200 193,029,200 193,029,200 193,029,200 193,029,200 193,029,200
42,180,910 42,180,910 42,180,910 42,180,910 42,180,910 42,180,910
49,078,247 49,078,247 49,078,247 49,078,247 49,078,247
196,396,200 196,396,200 196,396,200 196,396,200 238,577,110 235,210,110 235,210,110 284,288,357 284,288,357 284,288,357 242,107,447 242,107,447
3,367,000 5,453,139
2,490,000 12,270,000 14,724,000 18,405,000 23,006,250 27,607,500 31,748,625 39,685,781 47,622,938 54,766,378 60,243,016 64,460,027
492.8 20.0 25.0 25.0 20.0 15.0 25.0 20.0 15.0 10.0 7.0
132,000 743,800 2,945,943 5,891,886 9,819,810 13,512,044 13,512,044 15,442,336 19,302,920 19,302,920 19,302,920 23,163,504
0.1 0.4 1.5 3.0 5.0 7.0 7.0 8.0 10.0 10.0 10.0 12.0
210,905 421,809 632,714 1,265,427 1,265,427 2,109,046
0.5 1.0 1.5 3.0 3.0 5.0
245,391 490,782 736,174 1,472,347 2,453,912
0.5 1.0 1.5 3.0 5.0132,000 743,800 2,945,943 5,891,886 10,030,715 13,933,853 14,144,758 16,953,155 21,059,130 22,148,139 20,775,267 25,617,416
5.3 6.1 20.0 32.0 43.6 50.5 44.6 42.7 44.2 40.4 34.5 39.7
2,358,000 11,526,200 11,778,057 12,513,114 12,975,535 17,040,647 17,603,867 22,732,627 26,563,808 38,071,378 39,467,749 38,842,611
13,884,200 25,662,257 38,175,371 51,150,906 71,558,553 89,162,421 111,895,047 138,458,855 176,530,233 215,997,982 254,840,592
16,366,350 16,366,350 16,366,350 16,366,350 16,366,350 16,085,767 16,085,767 16,085,767 16,085,767 16,085,767 16,085,767 16,085,767
3,515,076 3,515,076 3,515,076 3,515,076 3,515,076 3,515,076 0 0
4,089,854 4,089,854 4,089,854 4,089,854 4,089,854
16,366,350 16,366,350 16,366,350 16,366,350 19,881,426 19,600,843 19,600,843 23,690,696 23,690,696 23,690,696 20,175,621 20,175,62116,366,350 32,732,700 49,099,050 65,465,400 85,346,826 104,947,668 124,548,511 144,149,353 163,750,196 183,351,038 199,436,805 215,522,572
-14,008,350 -18,848,500 -23,436,793 -27,290,029 -81,063,597 -80,256,793 -82,253,768 -79,121,984 -72,159,019 -53,688,483 -30,306,501 -7,549,6571.2 5.9 6.0 6.4 5.4 7.2 7.5 8.0 9.3 13.4 16.3 16.0
7.1 13.1 19.4 24.9 32.1 39.6 47.6 56.9 70.3 86.6 102.71,580 1,990 2,150 2,215 2,303 2,372 2,467 2,541 2,643 2,722 2,831 2,916
25.9 4.0 3.0 4.0 3.0 4.0 3.0 4.0 3.0 4.0 3.0
2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0
Prediction of Exchange Rate(Tsh./US$)
Currency Changing ratio(%)
Prediction of Equipment Price changingRatio(%)
Total depreciation cost(Tsh.)Accumulation of Depreciation cost(Tsh.)
Balance after depreciation (Tsh.)
Yearly Depreciation ratio(%)
Total Depreciation Ratio(%)
Balance(Tsh. Lease income + disposedincome - Maintenance cost)
Income Accumulation(Tsh.)
Yearly Depreciation Cost (Tsh.12 yearequal depreciation)Depreciation Cost for own procuredequipment 1(Tsh.)
Depreciation Cost for own procuredequipment 2(Tsh.)
Maintenance Cost ratio to DepreciationMaintenance Cost for own procuredequipment 1(Tsh.)
Maintenance Cost ratio to DepreciationTotal Maintenance Cost(Tsh.)
Maintenance Cost ratio to Income(%)
Lease Income(Tsh.)Lease Income Increasing Ratio( %,comparison to previous year)Maintenance Cost (tsh. Initial Equipment)
Maintenance Cost ratio to Depreciationcost(%)Maintenance Cost for own procuredequipment 1(Tsh.)
Total Depreciation cost(Tsh.)Depreciation Cost for own procuredequipment ( Tsh. Vibrating Roller 1)
Depreciation Cost for own procuredequipment ( Tsh. Vibrating Roller 2)
Total Depreciation cost(Tsh.)
Diposed equipment Income(tsh. VibratingRoller, remaining value)
1 (2013/14) 2 (2014/15) 3 (2015/16) 4 (2016/17) 5 (2017/18) 6 (2018/19) 7 (2019/20) 8(2020/21) 9 (2021/22) 10 (2022/23) 11 (2023/24) 12 (2024/25)196,396,200 196,396,200 196,396,200 196,396,200 196,396,200 166,093,200 166,093,200 166,093,200 166,093,200 166,093,200 166,093,200 166,093,200
42,180,910 42,180,910 42,180,910 42,180,910 42,180,910 42,180,910
49,078,247 49,078,247 49,078,247 49,078,247 49,078,247
196,396,200 196,396,200 196,396,200 196,396,200 238,577,110 208,274,110 208,274,110 257,352,357 257,352,357 257,352,357 215,171,447 215,171,447
3,367,100 5,453,139
8,620,000 10,750,000 12,900,000 16,125,000 19,350,000 23,220,000 26,703,000 32,043,600 36,850,140 40,535,154 44,588,669 47,709,876
24.7 20.0 25.0 20.0 20.0 15.0 20.0 15.0 10.0 10.0 7.0
132,000 743,800 1,963,962 2,945,943 3,927,924 4,152,330 4,982,796 8,304,660 11,626,524 14,948,388 16,609,320 19,931,184
0.1 0.4 1.0 1.5 2.0 2.5 3.0 5.0 7.0 9.0 10.0 12.0
210,905 421,809 632,714 1,265,427 1,265,427 2,109,046
0.5 1.0 1.5 3.0 3.0 5.0
245,391 490,782 736,174 1,472,347 2,453,912
0.5 1.0 1.5 3.0 5.0
132,000 743,800 1,963,962 2,945,943 4,138,829 4,574,139 5,615,510 9,815,479 13,382,734 17,793,607 18,081,667 22,385,0961.5 6.9 15.2 18.3 21.4 19.7 21.0 30.6 36.3 43.9 40.6 46.9
8,488,000 10,006,200 10,936,038 13,179,057 15,211,171 22,012,961 21,087,490 22,228,121 23,467,406 22,741,547 31,960,141 25,324,780
18,494,200 29,430,238 42,609,295 57,820,466 79,833,427 100,920,918 123,149,039 146,616,445 169,357,992 201,318,133 226,642,913
16,366,350 16,366,350 16,366,350 16,366,350 16,366,350 13,841,100 13,841,100 13,841,100 13,841,100 13,841,100 13,841,100 13,841,100
3,515,076 3,515,076 3,515,076 3,515,076 3,515,076 3,515,076 0 0
4,089,854 4,089,854 4,089,854 4,089,854 4,089,854
16,366,350 16,366,350 16,366,350 16,366,350 19,881,426 17,356,176 17,356,176 21,446,030 21,446,030 21,446,030 17,930,954 17,930,95416,366,350 32,732,700 49,099,050 65,465,400 85,346,826 102,703,002 120,059,178 137,415,353 154,771,529 172,127,705 185,968,805 199,809,905-7,878,350 -14,238,500 -19,668,812 -22,856,105 -27,526,359 -22,869,574 -19,138,260 -14,266,314 -8,155,084 -2,769,713 15,349,328 26,833,008
4.3 5.1 5.6 6.7 6.4 10.6 10.1 8.6 9.1 8.8 14.9 11.89.4 15.0 21.7 28.1 38.6 48.8 57.4 66.5 75.4 90.2 102.0
1,580 1,990 2,150 2,215 2,303 2,372 2,467 2,541 2,643 2,722 2,831 2,91625.9 4.0 3.0 4.0 3.0 4.0 3.0 4.0 3.0 4.0 3.0
2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0 2.0
Total Depreciation cost(Tsh.)Depreciation Cost for own procured equipment( Tsh. Vibrating Roller 1)
Depreciation Cost for own procured equipment( Tsh. Vibrating Roller 2)
Total Depreciation cost(Tsh.)
Diposed equipment Income(tsh. VibratingRoller, remaining value)
Lease Income(Tsh.)Lease Income Increasing Ratio( %,comparison to previous year)Maintenance Cost (tsh. Initial Equipment)
Maintenance Cost ratio to Depreciationcost(%)Maintenance Cost for own procured equipment1(Tsh.)
Maintenance Cost ratio to Depreciationcost(%)Maintenance Cost for own procured equipment1(Tsh.)
Maintenance Cost ratio to Depreciationcost(%)Total Maintenance Cost(Tsh.)
Maintenance Cost ratio to Income(%)
Balance(Tsh. Lease income + disposedincome - Maintenance cost)
Income Accumulation(Tsh.)
Yearly Depreciation Cost (Tsh.12 yearequal depreciation)Depreciation Cost for own procured equipment1(Tsh.)
Depreciation Cost for own procured equipment2(Tsh.)
Prediction of Exchange Rate(Tsh./US$)
Currency Changing ratio(%)
Prediction of Equipment Price changingRatio(%)
Total depreciation cost(Tsh.)Accumulation of Depreciation cost(Tsh.)
Balance after depreciation (Tsh.)
Yearly Depreciation ratio(%)
Total Depreciation Ratio(%)
44
2.6.4. Current Situations of Contractor Equipment and Problems
(1) Model Site Contractors
The interviewing of LBT contractors has been carried out sequentially on the current situation since
the start of the project. The results of the investigation are as follows, showing that satisfaction has
been increasing and the project has been contributing to the stabilization of business. In order to
further improve these points, the following should be kept in mind as much as possible (even though
there would be difficulties such as the district budget and personnel distribution based thereon).
Table2-39 Satisfaction of Contractors on their own service and district services.
Reviewing of leasing price.
For small-size contractors such as LBTs, the equipment cost accounts for a large portion (30 to 40%)
of the contract amount when they get a road work construction contract.
For this problem, the equipment owners (district office) should provide the equipment at prices as low
as possible with due consideration of the maintenance and administration cost and equipment
replacement cost.
For the Iringa district equipment price, it will be set lower than the prices of private leasing companies
by 5 to 10% from the next fiscal year (15/16) because it is high in demand in Iringa district and the
leasing prices for small-size vibrating roller of private leasing companies are cheaper than those of the
district equipment by about 15%. For Chamwino district, the price, which has been set to be relatively
cheaper, will not be changed.
Eval.
Satisfaction(five-grade eval.)
4 4 4.0
District ownedEqupment
・It is hoped that the equipment ispossessed preferentially by thedistrict to lease the equipment tosmall-size contractors such asLBT.・The prices are interested.
・It is convenient but it is sometimesdifficult to obtain the equipment atthe right time along the progress ofconstruction as the number of theequipment is not large.・As to vibrating rollers, ones withlittle bit larger capacity (weight)would be better in cost-effectiveness.
・Small-size vibrating rollers: the price is highercompared with the others (district 150,000Tsh.,private companies 120,000Tsh.) with the difficultyin accessing to the equipment from privatecompanies. The quantity of this equipment is toosmall compared with the need. The cost-effectiveness is satisfactory (the price isadequate) but the quantity is in short.・Water tank cars: similarly to the cases of rollers,the price is higher than the private leasing but thelarge capacity (10000lt compared with 6-8,000ltfor private leasing) is satisfactory.There is noproblem but the quantity is not enough.・Tow graders: Used as necessary, but theequipment available from private leasingcompanies are hydraulic and cheaper.What waspossessed by the district services was notknown, so a large-size equipment was leasedfrom a private leasing company.・Plate compactors: There is a possibility to usethis equipment for building constructions but thiswork is carried out manually with satisfaction.Therefore, frequency of using this equipment isnot high.
Eval.Satisfaction(five-
grade eval.)1 2 4 2.3
・Possession of small-sizeconstruction equipment by privatecompanies for LBT is limited, so thecases the equipment is procured fromdistant locations are frequent and it isdisadvantageous in terms of cost.
2012/13 2013/14 2014/15 2015/16
Equipment Status・Almost all the LBT contractorsown no equipment but operationaltools.
No change in current situations. No change in current situations.
BussinessManagement
・No obvious changes have beenobserved but they are interested inthe possession of equipment by theprefectural governments, willing toutilize it in the future.
・For LBT contractors with low initial capitals, theleasing service by the prefectural governments isconvenient because of future payment (paymentby results).・The LBT constructions, which are publicallynoticed every year, facilitate the possibility ofstabilizing businesses.
45
Stable Constructions Tender
It has been announced as a policy that 20% of the current roadwork budget is allocated to LBT
construction orders. It is necessary to keep this policy to encourage the contractors.
Ordering with appropriate quotation (BOQ) by Districts.
The quotation and ordering should be carried out with consideration of the current economic situation
as much as possible, in order to reduce effects on labor cost (employment of cheap labors to save labor
cost) and on finish quality (the quality varies among contractors because equipment is not used).
(2) Pilot Site Contractors
Kondoa District - The contractors in the last fiscal year possess minimally required equipment
(vibrating rollers, dump trucks) and water tank cars are also leasable near the construction sites. As
their own equipment is too old, they wish to use equipment of good condition, if available. The
problems they are facing are how to secure good earth filling and water. They said they have no
problem in terms of equipment.
Mufindi District - For the technical transfer effect in Iringa district, the constructions were carried out
in such a manner that a plurality of contractors was allocated to a single construction site for the sake
of easy management. Because 3 areas out of the 4 areas were dealt with by the LBT construction
contractors of Iringa district in the last fiscal year, the situation of equipment was difficult, and the
equipment owned by Iringa district was also used.
The above reports show that access to good equipment is difficult in both the districts, which makes it
important to possess equipment in the model district (neighboring district).
2.6.5. District Equipment Operation Management Situation
The equipment management and maintenance have been instructed according to an initially prepared
guideline, but now have some problems as listed below.
(1) Equipment Utilization Situation
Chamwino District - All the equipment is available for leasing and in good conditions. For
tractors that are not frequently used, it will attempt to increase their utilization rate by an effort
such that the use of graders will be obligated via BOQ, etc. Leasing to agricultural operations
would be possible during the slack period for construction work if appropriate consideration is
given to the leasing period. Negotiation with the agricultural sections of the district office was
considered.
Iringa District - A vibrating roller is being repaired to address trouble in its hydraulic system (It
is still usable for light-load work). As the vibrating roller’s usage is expected to increase from
the next fiscal year, it will contact the supplier for servicing. The other equipment is in good
conditions.
46
(2) Contract (Leasing Application)
The format prepared according to the guideline is too complicated. Therefore, the leasing is basically
done under such contract management that a reply is issued to an application from a contractor.
Figure2-26 Contract Form Contractor to District Figure2-27 Contract Form District to Contractor
(3) Account Management
The account management in Iringa district is carried out through an account of the civil engineering
department in general accounts, and that in Chamwino district is managed through an account of the
civil engineering department. The account management is carried out relatively according to the plan
and the maintenance and administration cost is paid through the accounts. In Chamwino district, a part
of leasing fees is remitted to another account of the district account. They said the amount of money
can be transferred to the right account.
(4) Management Form for Maintenance and Administration
The importance of maintenance and administration for the equipment was not well regarded, maybe
because the equipment is small-sized. About 60% of the book-keeping of the management form on
maintenance and repair is done. This figure is considered as relatively good. The spending on
administration is all kept in record, which makes it possible to trace the administration history. The
reason why the recording rate of the recording book is so low is that the civil engineers in the
department are also assigned to the administration of the equipment, and they do not have enough time
to maintain the recording and have no enough expertise (knowledge regarding the equipment).
(5) Operation Staff Administration
Basically the operation staff administration is carried out based on contract, calculating their working
hours by multiplying the number of wording days on the contracts by 8 hours per day.
(6) Material (parts) Management
The materials have been consumed as per the regular (fast-moving parts) plan, and appropriately
managed in the material management stock house (revenue management record).
As a whole, the management, which has some minor differences from the plan, is carried out
47
appropriately through simplified and flexible management by the locals. As it was confirmed that the
fund has been accumulated and the operation rates have been stabilized, Project and the locals agreed
that the management should be carried on in the same manner. In terms of tractors, it was noted in
both the district that, in order to earn from the investment, tractors will be flexibly utilized in
agriculture, for which tractors are also usable and needed seasonally (needed only in the rainy season
while LBT constructions are concentrated in the dry season), with due consideration to the
maintenance and administration and the effects on constructions.
Figure2-28 Income Management Form Figure2-29 Maintenance management Form
2.6.6. Proposals
(1) Facilitation of equipment renewal
In view of the maintenance and administration cost in the next fiscal year, equipment renewal may be
considered if the renewal cost + the expected maintenance and administration cost in the next fiscal
year (+110 – 120 %) is secured, so as to sell the existing equipment within 1 to 2 years at the
depreciation prices to private contractors who have participated in constructions so far.
(2) Perfection of regular maintenance and administration
In order to prolong the lives of equipment, regular maintenance (oil change and various lubrications) is
important and should be carried out as appropriate. Moreover, cooperation with the suppliers is
necessary for general repairs, especially, hydraulic-related services.
(3) Stricter fund management
At the moment, fund management is appropriately carried out according to the objectives. However
there is a concern that if there are excess funds, the excess would be used for other purposes as a result
of budgeting. It is necessary to make appropriate explanations to the district office in order to secure
the funds.
(4) Clear notification of equipment use and availability in tender documents
A contractor proposed to clearly notify in tender documents about the equipment possessed by the
district office. If possible, tender documents may be amended to have such notification.
48
(5) Appropriate Ordering of LBT constructions.
As mentioned in Item 4, it is important to surely allocate about 20% of the annual roadwork
maintenance budge to LBT constructions for specialized contractors (Class 7 LBT specialist 3). It is
also important to carry out the LBT constructions under suitable conditions, or the equipment would
be exposed to excess load under poor working conditions, thereby shortening their lives. It is
necessary to select appropriate construction sites according to the construction guideline prepared in
the project.
2.6.7. Review on LBT equipment leasing (written in the progress report of the 2nd contracted
year)
For further development of equipment leasing, the district-based leasing, which is currently in
progress, requires at least 5 years to renew the equipment as predicted in the mid/long-term prediction.
It is reasonably probable that some equipment is lost due to accident or breakdown by chance in such a
period. Thus, it is the best scenario that the equipment is ideally renewed in about 3 years.
To achieve this, the following premises are necessary: (1) there are at least two sets of each type of
equipment, (2) the fund management is unified, (3) fund management is run by regional offices (to
facilitate the accumulation of funds), and actual operation is carried out by the district office. The
following is a revised version of the outline view and report prepared in the last fiscal year:
(Revised Report of the last fiscal year)
One problem associated with the LBT contractors is the difficulty in accessing the necessary
equipment. Therefore, equipment leasing under this project is highly expected. However, there is not
enough equipment (only one set), and it is difficult to supply the equipment to all contractors when
they need it. Moreover, under the district-based operation, it takes five to six years to renew the
equipment and an increase in the number of equipment cannot be expected in a short time. However,
the sum of the contracts (revenues) in both the districts in these two years reached about 31 million.
Therefore, it is expected that in the next year (the fourth year of the project) the revenues will increase
to a level at which small-size vibrating rollers can be pursed, even if the maintenance and
administration cost in the next fiscal year is taken into consideration. Unified revenues (leasing fees)
management by the regional office will be a solution of this problem. The following is an outline view
of the management (draft). As shown in the above view, the equipment leasing and administration will
be carried out by the district offices, and only the leasing fees will be paid to an account of a regional
office. The regional office will purchase new equipment and allocate it to each district, taking into
consideration the equipment maintenance and administration cost and the operation cost in the next
fiscal year. This will speed up the renewal of the equipment. Moreover, selling of the equipment of
about five years old to LBT contractors will be considered as per the initial plan. This will solve the
difficulty for small-size contractors in procuring equipment, survival of businesses, and facilitation of
motivation for starting business. And for the regional office, this will improve their ability of operation
and administration by building up their management ability.
49
However, to achieve these, the following are necessary:
An account that the regional office can carry over (and to which the funds accumulated in the district
accounts can be transferred) is opened
Special staff for administration (about one person) can be allocated in the regional office.
The regional office is able to pay the maintenance and administration cost and the operation cost to the
district office in a timely manner.
Each district has LBT constructions on a constant basis.
The BOQ at bidding in the district is written to show that the equipment should be used appropriately.
In each district, construction sites (location, distance, and environment) should be selected taking into
consideration the operation of equipment.
The equipment maintenance and administration is allowed to be carried out by private companies
Figure2-30 Proposed New Hiring System
As to the variety of equipment, the equipment expected to be necessary would be as follows after the
confirmation of the result of the pilot project.
・ Tractors (70 – 80 HP): spec downgrading by about 20% from the equipment procured for this
project.
・ Water Tank Cars (6000-8000 Lit.): spec downgrading by about 20% from the equipment
procured for this project.
・ Small-Size Vibrating Rollers (1 ton): need to be 1 ton or greater.
・ (Plate Compactors)
・ Water Pumps
・ Tow Graders
Where 1 set of equipment includes one of each of these types of equipment, the number of sets of
equipment to be stationed in a state is determined to be the half of the number of districts in state (in
case of a state consisting of 4 to 5 districts, 2 sets will be provided). The investment amount is
expected to be about 100,000 to 130,000 dollars (including transportation, spare parts, and training
cost). The initial investment should be supported by fully grant assistance or the like, considering the
Regional
Office
District
Office
District
Office
District
Office
Contractor Contractor ContractorContractor ContractorContractor
Equipment Equipment Equipment
Equipment Maintenance/Management
Equipment Renewal
Contract Sum
Equipment Hiring
Contract Sum
Contract Sum
Equipment Maintenance/Management Equipment Maintenance/Management
Equipment HiringEquipment Hiring
Equipment Renewal
Hiring Fee
Hiring Fee
50
financial capacity etc. of the area.
The tow grader, whose use frequency is low, may be provided in such a way that only one tow grader
is provided in the project-participating state, or no tow grader is provided in the project-participating
state where the situation (the use frequency of tow graders and the number of existing tow graders that
should have been checked) allows. If a tow grader is to be procured, a hydraulic tow grader is
preferable (the existing tow graders are mechanical).
Plate compactors are low in use frequency, suggesting that most of the constructions were built with
manual compaction. We would like to leave it to the local staff’s judgement whether they still need
this equipment.
A pilot program may be carried out initially in 2 to 3 states, considering the introduction of a
nation-wide program through financial planning in the future. The states for the program may be
selected by considering the following.
・ The region has good experiences of LBT constructions.
・ The environment is suitable for LTB constructions in terms of soil quality, community
participation, weather, etc.
・ The traveling distance (range) for the equipment from its station to the site is in the range of
50 to 80 km (maximum of 120 km).
51
3. Project Monitoring and Achievement of Outputs 3.1. Monitoring of Project Activities
Monitoring is routine work that is project-internal. After the commencement of the Project, monitoring
activities were conducted to check whether project activities were implemented and project outputs
were produced as planned. If necessary, modification of the Project was considered and carried out.
Monitoring is a pillar of project management because the Project manages the objectives initially
established in the Project Design Matrix (PDM) based on the indicators and revises the Project
Activities and Outputs in response to the various changes during the implementation period.
Monitoring activities shall be conducted mainly by the counterparts (C/P) in consideration of project
sustainability after the termination of the Project. In these circumstances, the Monitoring System (MS)
was consensually established in collaboration with C/P and Japanese experts.
3.1.1. Monitoring System (MS)
In order to confirm the progress of the Outputs and Project Purpose achieved by the project activities,
C/P and Japanese experts monitor their progress based on the Monitoring System (MS). The specific
contents of the MS are as follows:
(1) Components of PDM (narrative summary, indicators, means of verification);
(2) Monitoring Plan (persons/organizations in charge, frequency, remarks); and
(3) Baseline Value and Final Target Value (baseline value, final target value).
The project activities were monitored according to the above factors, and the achievements/target
values were filled out in the MS on the basis of their progress. Also, individual forms (questionnaire,
data entry sheet, etc.) necessary for data collection were designed and prepared, and the forms (Form 1
to 7) were organized and attached to the MS (refer to Annex 4-1). Also, the procedure of specific
monitoring activities was summarized in the “Instruction Manual for the Monitoring System (Version
2-2)” (refer to Annex 4-2).
The MS, including each form, was modified accordingly if difficulties were found in the forms during
the data collection along the MS. Ultimately, the Project contributed to the sustainability of monitoring
activities performed by C/P through the establishment of user-friendly and simplified MS and forms.
3.1.2. Monitoring of the Important Assumptions
It is crucial for the project stakeholders to have consciousness of the Important Assumptions so as to
react to them promptly, as needed, by checking the current conditions annually. Further, persons in
charge were assigned to each of the assumptions. The following points were confirmed in each
assumption (refer to Annex 4-1):
(1) With or without the occurrence of the assumptions;
52
(2) Causes (if they occur);
(3) Influences on the Project; and
(4) Measures and undertakings by the Project.
3.1.3. Progress of the Plan of Operations (PO)
The Annual Plan of Operations (APO: (i) March 2012 – June 2013, (ii) July 2013 – June 2014, (iii)
July 2014 – June 2015, (iv) July 2015 – February 2016) extracted from the PO of the entire
cooperation period was produced over the financial year in Tanzania, and progress management was
conducted according to the APO. The progress of the project activities is summarized in Table 2-1
based on the APO.
Also, an enlarged depiction of the APO was posted on the wall at the project office and C/P offices,
and the monthly progress was confirmed. The Japanese expert team and C/P were able to confirm the
progress and comprehend the entire flow because the APO posted on the wall was visualized.
Moreover, the progress was confirmed in the weekly meetings of the expert team.
3.2. Achievements based on Indicators
Through the monitoring activities, the following indicators were confirmed: (1) the maintenance status
of rural roads (Form 1); (2) the satisfaction ratings of contractors and community people (Forms 2-1 &
2-2); (3) the percentage of rollover funds (Form RALG-1 of PMO-RALG); (4) the authorization of the
Operational Guidelines by MOW; (5) the percentage of RS/council engineers utilizing the Operational
Guidelines (Form 3); (6) the progress of Annual Rural Road Maintenance Plan (Form 4); (7) the
percentage of the road maintenance works completed by contractors (Form 5); (8) the ratings of
district engineers and technicians of their practical skills and knowledge (Forms 6-1 & 6-2); (9) the
consultations on rural road maintenance between contractors and district engineers/technicians (Form
7); and (10) the ratio of LBT works to all maintenance works (Form 5). The details are as follows:
3.2.1. Achievements of the Project Purpose
(1) Indicator 1: Maintenance status of rural roads
The maintenance status of rural roads (in combination with “Good” and “Fair”) in Chamwino DC
(target value 80%) and Kondoa DC (target value 70%) in Dodoma Region as well as in Iringa DC
(target value 70%) and Mufindi DC (target value 70%) are described in Table 3-1. However, the road
network in Chamwino DC was extended around 1.6 times in FY 2014/15. Although the indicator did
not attain the target value (80%) in the financial year, the percentage of road status exceeds 90% if
calculated with the previous road network. Moreover, as Mufindi DC did not attain the target value, it
is anticipated that the indicator shall be accomplished in FY 2015/16.
With reference to the road maintenance status in other district councils, including municipal councils,
in the Dodoma and Iringa regions, the achievements are listed in the table below:
53
Table 3-1 The maintenance status of rural roads in model and disseminated districts
(FY2011/12 – 2014/15)
FY 2011/12 FY 2012/13 FY 2013/14 FY 2014/15
Model Districts Chamwino
District
74.71%
(Good:40.67%、
Fair:34.04%)
79.04%
(Good:42.41%、
Fair:36.63%)
81.50%
(Good:47.30%、
Fair:34.20%)
73.70%1
(Good:50.31%、
Fair:23.39%)
Iringa District
60.16%
(Good:44.52%、
Fair:15.64%)
66.36%
(Good:51.96%、
Fair:14.40%)
71.29%
(Good:58.40%、
Fair:12.89%)
92.49%
(Good:72.86%、
Fair:19.63%)
Disseminated
Districts
Kondoa
District ― ―
63.34%
(Good:43.40%、
Fair:19.94%)
77.35%
(Good:61.87%、
Fair:15.48%)
Mufindi
District ― ―
63.09%
(Good:34.77%、
Fair:28.32%)
57.08%
(Good:18.13%、
Fair:38.95%)
Dodoma Region
Kongwa
District ― ―
49.77%
(Good:13.89%、
Fair:35.88%)
52.35%
(Good:17.87%、
Fair:34.48%)
Chemba
District ― ―
46.51%
(Good:43.08%、
Fair:3.43%)
69.28%
(Good:41.62%、
Fair:27.66%)
Mpwapwa
District ― ―
45.54%
(Good:30.62%、
Fair:14.91%)
45.53%
(Good:28.69%、
Fair:16.84%)
Bahi District ― ―
67.81%
(Good:43.60%、
Fair:24.21%)
68.80%
(Good:45.73%、
Fair:23.08%)
Dodoma
Municipality ― ―
56.48%
(Good:38.97%、
Fair:17.51%)
56.56%
(Good:39.16%、
Fair:17.40%)
Iringa Region
Kilolo District ― ―
60.75%
(Good:12.18%、
Fair:48.57%)
59.87%
(Good:11.81%、
Fair:48.06%)
Iringa
Municipality ― ―
46.51%
(Good:8.54%、
Fair:37.98%)
48.55%
(Good:10.76%、
Fair:37.79%)
Source: Form 1 of Monitoring System
(2) Indicator 2: Satisfaction ratings of contractors and community people
The Project aims at achieving over 75% in the satisfaction ratings on average with reference to rural
road maintenance works or status for contractors (refer to Table 3-2) and community people (refer to
1 It seems that the road status has gradually been improved from the perspective of consecutive years in the past from FY 2011/12 to FY 2013/14. However, the road network in Chamwino DC was extended around 1.6 times (total road length = 1,040 km) in FY 2014/15. Importantly, the percentage of road status exceeds 90% if calculated with the previous road network (approximately 600 km).
54
Table 3-3), respectively, in the model and disseminated districts. Questionnaire surveys were
conducted twice in the model districts, and the results are shown below. In the disseminated districts,
the questionnaire survey will be carried out following the completion of pilot projects after the end of
June 2016.
Table 3-2 Satisfaction ratings of contractors who executed the pilot projects in
Chamwino and Iringa DC
1st Questionnaire Survey (February 2014)
2nd Questionnaire Survey (June 2015)
Chamwino DC (5 respondents)
Iringa DC (14
respondents)
Chamwino DC (11
respondents)
Iringa DC (11
respondents)
Q1. Payment of construction costs from the district council in a timely manner
56.00%(2.80)
90.00% (4.50)
72.73% (3.64)
52.73%(2.64)
Q2. Scale or size of road maintenance works
76.00%(3.80)
92.86%(4.64)
80.00% (4.00)
67.27%(3.36)
Q3. Number of road maintenance works
76.00%(3.80)
90.00%(4.50)
76.36% (3.82)
65.45%(3.27)
Q4. Instructions and directions on road maintenance works by district engineer and technicians
80.00%(4.00)
95.71%(4.79)
74.55% (3.73)
83.64%(4.18)
Q5. Prompt and concrete responses to the inquiries about road maintenance works
80.00%(4.00)
84.29%(4.21)
78.18% (3.91)
69.09%(3.45)
Q6. Contents of bill of quantities (BOQ) for road maintenance works
76.00%(3.80)
90.00%(4.50)
69.09% (3.45)
78.18%(3.91)
Q7. Public notices of road maintenance works in a timely manner
68.00%(3.40)
84.29%(4.21)
72.73% (3.64)
80.00%(4.00)
Q8. Process from the tender award to the signing of a contract according to official schedule
84.00%(4.20)
85.71%(4.29)
72.73% (3.64)
83.64%(4.18)
Q9. Lend‐lease condition of light equipment for LBT works
76.00%(3.80)
65.71% (3.29)
60.00% (3.00)
65.45%(3.27)
Q10. Inspection tasks executed by the district engineer and technician
88.00%(4.40)
94.29%(4.71)
72.73% (3.64)
78.18%(3.91)
Total Rating on Average (Q1 – Q10)
76.0% (3.80)
87.3%(4.36)
72.9% (3.65)
72.4%(3.62)
Q11. Overall satisfaction rating of the rural road maintenance works
80.00%(4.00)
97.14% (4.86)
80.00% (4.00)
90.91%(4.55)
Source: Questionnaire survey through Form 2-1 of Monitoring System
In Chamwino DC, the pilot projects were favorably completed in the first half of FY 2014/15. The
target value of the indicator was over 75% of average rating point, and it was almost achieved. The
item that was 10% or more from the target value was the “lend-lease condition of light equipment for
LBT works (Q9).” As one of contractors executing pilot projects did not know that LBT equipment
55
could be rented in Chamwino DC, such as a vibration roller (provided by JICA), tow grader (from
VETA), and water bowser (from the district water department), the contractor used EBT equipment
with payment of higher cost. It might have affected the assessment result.
In Iringa DC, the target value of the indicator was almost achieved. In particular in Iringa DC, the
delay of budget disbursement severely affected the maintenance works, and the contractors criticized it
during the interviews. The delay continued for several months, so that the payment to the community
people participating in the LBT works fell into arrears. Also, they commented that the supervision by
district engineers and technicians was not enough in the financial year. As they did not show up at the
sites for a month, contractors must have redone the road maintenance with the advice of district
engineers/technicians during their site visit after a month. This is also considered as the result of a lack
of governmental budget. District engineers and technicians were not able to supervise the road works
properly because the transportation costs for site visits were not secured.
Also, the issue for LBT is to assemble community people living around project sites to provide labor
for road maintenance works. Furthermore, as the soil is quite hard in Chamwino DC, the LBT works
may not be appropriate in the dry season. On the other hand, although the soil is soft during the rainy
season, this is the farming season. Thus, it might be appropriate to execute LBT works at the end of
the rainy season, i.e., in April.
Previously, as Chamwino DC defined the qualification for LBT works as “Class 7,” the contractors
classified as “LBT Specialist” could not participate in the bidding (in September 2012). However,
these small-scale contractors classified as “LBT Specialist” presently came to be able to participate in
the bidding for LBT works.
Table 3-3 Satisfaction ratings of community people working for the pilot projects
in Chamwino and Iringa DCs
1st Questionnaire Survey (February 2014)
2nd Questionnaire Survey (June 2015)
Chamwino DC (36 respondents)
Iringa DC (43 respondents)
Chamwino DC (103 respondents)
Iringa DC (80 respondents)
Q1. Traffic time for passing through the road
35.56%(1.78)
75.81%(3.79)
73.73% (3.69)
84.75%(4.24)
Q2. Convenience of the transportation
35.56%(1.78)
76.74%(3.84)
68.82% (3.44)
83.00%(4.15)
Q3. Passable throughout the year 33.33%(1.67)
71.16% (3.56)
72.82% (3.64)
86.08%(4.30)
Q4. Drained conditions of the road
36.11%(1.81)
74.88%(3.74)
54.56% (2.73)
85.57%(4.28)
Q5. Road dust 47.78%(2.39)
78.14%(3.91)
60.39% (3.02)
71.90%(3.59)
Q6. Accidents on the road 60.00%(3.00)
80.47%(4.02)
72.35% (3.62)
84.00%(4.20)
56
Q7. To carry agricultural crops to the market
46.11%(2.31)
82.33%(4.12)
77.28% (3.86)
93.25%(4.66)
Q8. Number of customers of local shops around the road
57.78%(2.89)
74.88% (3.74)
69.71% (3.49)
63.26%(3.16)
Q9. Change in incomes 62.22%(3.11)
74.42%(3.72)
61.37% (3.07)
80.00%(4.00)
Q10. Continuous participation in LBT works
86.11%(4.31)
88.37% (4.42)
82.35% (4.12)
90.00%(4.50)
Total Rating on Average (Q1 – Q10)
50.1%(2.50)
77.7% (3.89)
69.3%2 (3.47)
83.3%3
(4.16)
Q11. Overall satisfaction rating of the status of rural roads
51.11%(2.56)
74.42% (3.72)
64.47% (3.22)
85.25%(4.26)
Source: Questionnaire survey through Form 2-2 of Monitoring System
In the model districts, it was confirmed that the ratings of Chamwino and Iringa DC had increased
more than 19% (50.1% ⇒ 69.3%) and 5% (77.7% ⇒ 83.3%), respectively, between the 1st and 2nd
questionnaire surveys (February 2014 and June 2015). In particular, although the rating of Chamwino
DC did not attain the target value, it had been improved dramatically.
Regarding the questionnaire survey of community people in Iringa DC, the average satisfaction rating
exceeded the target value of 75%, and good result was generally extracted. In Chamwino DC, whose
rating did not reach the target value, on the other hand, three (3) items were more than 10% below the
target value, i.e., “drained conditions of the road (Q4),” “road dust (Q5)”, and “change in incomes
(Q9).” Regarding the drainage conditions, as functional drainage ditches were not laid down at the
appropriate places, the ditches were stopped up in the rainy season so that rainwater overflowed onto
roads and the peripheries. Also, since the rainwater flowed into housing areas through the miter drain,
the miter drain was blocked up by the community people as a measure for flood prevention. Water
accumulated on roads, and the roads were seriously damaged. Thus, it is crucial to explain the
installation sites of drainage ditches to the community people so as to avoid such situations. Moreover,
the causes of the road damage may be considered as a problem of drainage design by district
engineers/technicians, lack of contractors’ capacity and working skill of community people, lack of
explanation to community people by district engineers/technicians and contractors, etc. For the future,
therefore, it is necessary to scrutinize the installation sites of drainage ditches properly.
With reference to road dust after passing the roads, as the grounds of Chamwino DC are dry and
harder than the ones of Iringa DC, it seems that the road dust was easily dispersed.
In terms of the income changes, the community people talked about the low wages (around 5,000 TSH
per day). They emphasized minimum wages from 8,000 to 10,000 TSH per day. Because labor costs
2 The total rating for the pilot projects executed in FY 2013/14 was 62.2% in Chamwino and 81.9% in Iringa on average through questionnaire surveys conducted once again at the same sites. It is apparent that the percentages were increased by around 12% in Chamwino and 4% in Iringa compared with the previous year. 3 Refer to the above description.
57
are decided by the contractors, it is considered that the minimum wage should be described in the
tender documents prepared by the LGAs.
As positive effects of LBT works, the following comments were made by the community people:
・ While it took three days to go to Iringa City from Makombe Village before the completion of the
road maintenance works between Magunga and Makombe, it now takes only one day to go to the
City. Furthermore, the transportation cost from Makombe Village to Ifunda located along a trunk
road dropped to 18,000 – 20,000 TSH from 30,000 TSH after the road maintenance works.
・ Community people became able to sell agricultural products at higher prices than before. This is
because the transportation condition has been improved to send the products to a market. For
instance, whereas the selling price of maize (20 kg) in the village was 3,000 TSH, the market
price in Iringa City was 8,000 – 10,000 TSH. Thus, they could increase their profits.
・ As mentioned by the contractors in Iringa DC, it is possible to execute road maintenance works
with appropriate quality through LBT, even compared with EBT, if engineers or technicians
supervise the works on a regular basis.
・ Community people were able to acquire the knowledge and skills of excavation of drainage
ditches, installation of drainpipes, gravelling method, etc., for LBT works.
(3) Indicator 3: The percentage of rollover funds for rural road maintenance
The Project aims to retain the percentage of rollover funds (RF) below 15%4 for rural road
maintenance in the model districts. The percentages of RF in the past four years, i.e., from FY 2011/12
to FY 2014/15, are shown in Table 3-4.
Chamwino DC stably retained the percentage of RF below 15% after FY 2011/12. Iringa DC has also
retained the percentage of RF at almost 15% in the past four years. Thus, it could be said that the
target values were achieved.
In the disseminated districts, moreover, the percentage of RF greatly fell below 15% in FY 2014/15
although the percentage exceeded more than 15% in FY 2013/14. However, because around 30% of
approved budget were only disbursed in FY2014/15, it seems that they could spend almost all the
budget. Therefore, it could be said that the percentages in FY2013/14 are more realistic.
Table 3-4 Percentage of rollover funds (RF) for rural road maintenance in the model districts
(FY 2011/12 – 2014/15)
FY 2011/12 FY 2012/13 FY 2013/14 FY 2014/15
Mod
el
Distri Chamwino
District 60.59% 1.23% 10.03% 1.23%
4 This target value was determined by reference to the target of Annual Performance Agreement concluded between PO‐RALG and each LGA.
58
Iringa
District 12.03% 15.10% 4.60% 0.00%5
Disseminated
Districts
Kondoa
District ― ― 21.48% 3.64%6
Mufindi
District ― ― 32.13% 0.51%7
Source: Form RALG-1 “Summary of Committed and Uncommitted Action Plan” by PMO-RALG
3.2.2. Achievements of Output 1
(1) Indicator 1: Operational Guidelines authorized by MOW
The Rural Road Maintenance Operational Guidelines was finally authorized by MOW on 10th
December, 2014, with the requirement of several modifications pointed out by MOW.
(2) Indicator 2: Percentage of RS/council engineers utilizing the Operational Guidelines
In this indicator, the Project aims at achieving over 80% of RS/council engineers across the country
utilizing the Operational Guidelines distributed by PMO-RALG and MOW. During the annual
engineers’ meeting held at Arusha in August 2014, a questionnaire survey on the Draft Operational
Guidelines was conducted. Although the usage rate was 68.2% (44 respondents), the sample number
was not enough from the aspect of nationwide level (25 regions and 181 LGAs). Afterwards, the
Operational Guidelines with final approval was bound in and distributed with an official letter from
the Director of IDD (19th June, 2015). In the annual engineers’ meeting at Arusha in August 2015, the
2nd questionnaire survey on the Guidelines was conducted, and the usage rate was 65.2% (192
respondents). Although the result was a decrease from the previous year, more than 60% of RS and
Council Engineers across the country came to use the Guidelines in just a month (if it took several
weeks to deliver the Guidelines to their offices). It could be said that the significant result was
achieved within the framework of the Project, which only targeted four district councils in two regions,
and the Guidelines developed in the target areas was utilized on a nationwide level. If the 3rd
questionnaire survey is carried out at the annual meeting in August 2016, the usage rate would exceed
the 80% set as the target value.
Moreover, the Project confirmed the status of guidelines usage according to the following items
through the questionnaire survey. The aggregated results are as follows:
5 Although Iringa DC received 60.6% (1.1 billion TSH) of the total approved budget, actual spending for road maintenance works was approximately 1.3 billion TSH. Thus, the amount of difference was covered by the project budget (1.47 billion TSH in total) for Removal of Bottleneck supported by DFID with approximately 0.2 billion TSH. 6 Due to the delay of the budget disbursement, Kondoa DC received only 33.5% of the total approved budget by the end of FY 2014/15. In other words, the DC might have spent almost all the budget because it received only 30% of the approved budget. There is a prospect that the percentage of RF will be much higher if the DC received the entire approved budget 7 This is also the same as above. Mufindi DC received only 34.0% of the total approved budget by the end of FY 2014/15.
59
Table 3-5 Percentages of RS/Council Engineers using the Operational Guidelines and their satisfaction ratings
1st Questionnaire August 2014
44 respondents
2nd Questionnaire August 2015
192 respondents
Q0. Utilization (% answering “Yes”) 68.18% 65.24%
I. GENERAL INFORMATION
Q1. Frequency of usage
More than several times
per month:90% Less than once per
month:10%
More than several
times per month:65%Less than once per
month:35%
Q2. Ease of understanding8 78.67% 80.33%
Q3. User‐friendliness 77.33% 80.49%
Q4. Applicability to various types of rural road maintenance works
76.00% 79.67%
Q5. Reference to the Operational Guidelines when encountering issues/problems
74.67% 74.10%
II. TARGETS AND POLICY DIRECTIVES OF THE OPERATIONAL GUIDELINES
Q6. Satisfaction with the Targets and Policy Directives 74.67% 76.39%
Q7. Ease of understanding of the Targets and Policy Directives
78.00% 78.03%
III. PLANNING SECTION OF THE OPERATIONAL GUIDELINES
Q8. Satisfaction with the Planning Section 72.00% 77.38%
Q9. Improvement in the Annual Rural Road Maintenance Plan
64.67% 69.09%
Q10. Improvement in the prioritization procedure for rural road maintenance works based on the Medium‐ and Long‐term Rural Road Maintenance Plan
62.67% 64.17%
IV. PROCUREMENT AND IMPLEMENTATION SECTIONS OF THE OPERATIONAL GUIDELINES
Q11. Satisfaction with the Procurement and Implementation Sections
74.00% 74.67%
Q12. Improvement in the procurement and implementation of rural road maintenance works
68.67% 69.50%
V. Monitoring and Evaluation (M&E) Section of the Operational Guidelines
Q13. Satisfaction with the M&E Section 73.33% 75.97%
Q14. Improvement in the M&E activities 66.67% 68.07%
8 Regarding the questions from Q2 to Q16, the respondents marked the grading points on a scale from “1” to “5” – with “5” representing the highest possible rating – and the grading points were converted to percentages (%) with averaged values.
60
VI. ANNEXES OF THE OPERATIONAL GUIDELINES
Q15. Satisfaction with the Annexes 72.67% 77.31%
Q16. Operational improvement in rural road maintenance works by reference to the Annexes
66.00% 70.76%
VII. OVERALL EVALUATION OF THE OPERATIONAL GUIDELINES AND ANNEXES
Q17. Overall evaluation of the Operational Guidelines 66.00% 71.97%
Q18. Overall evaluation of the Annexes 66.00% 70.82%
Source: Questionnaire survey through Form 3 of Monitoring System
Figure 3-1 graphically presents the results of the 2nd questionnaire survey conducted in August 2015.
As the satisfaction ratings exceeded 75% for each chapter except for the chapter of “Procurement and
Implementation” (the chapter almost attained 75%, though), it seems that the RS and Council
Engineers are generally satisfied with the contents. While the chapter of “Planning” was assessed with
the highest rating, the chapter of “Procurement and Implementation” was assessed with the lowest
rating. Thus, it would be desirable to improve the latter chapter.
On the other hand, there are large gaps between the ratings for satisfaction (“Satisfaction”) and for
improvements with the guidelines usage (“Improvement”). In particular, as the gap between
“Satisfaction” and “Improvement” in the chapter of “Planning9” had widened by around 11%, it is
necessary to scrutinize the measures for increasing the actual “Improvement” in the chapter and to
feed them back into the Guidelines as a future challenge. For instance, it is considered that the chapter
should include specific explanations of the planning as well as pictures and graphic illustrations as one
of the suggestions.
Figure 3-1 Comparison between “Satisfaction” and “Improvement” in each Chapter
9 Because there are two questions (Q9 and Q10) on the improvements of “Planning,” they are calculated as an averaged value.
76.39%
77.38%
74.67%
75.97%
77.31%
78.03%
66.63%
69.50%68.07%
70.76%
64.00%
66.00%
68.00%
70.00%
72.00%
74.00%
76.00%
78.00%
80.00%
Targets and PolicyDirectives
Planning Procurement andImplementation
M & E Annexes
Satisfaction
Improvement
10.75% 5.17% 7.90%
6.55%
1.64%
61
3.2.3 Achievements of Output 2
(1) Indicator 1: Preparation of Annual Rural Road Maintenance Plan based on the checklist
(including Indicator 1 of Output 4)
Annual Rural Road Maintenance Plans were prepared on the basis of the medium- and long-term rural
road maintenance plan, the prioritization of rural road maintenance, etc. Also, the Annual Plan
contains necessary items10 based on the checklist (Form 4) as required in indicator 2-1 of the PDM.
The specific items are shown below:
Table 3-6 Items necessary for the Annual Rural Road Maintenance Plan
(1) Medium‐ and long‐term objectives (Vision)
(8) Coverage of road network (15) Surface type
(2) Annual objectives (9) Preliminary schedule (16) Distance (km)
(3) Strategies and specific activities for the annual objectives
(10) Procurement procedures (17) Time frame of rural road
maintenance works
(4) Information of classified roads (11) Work type (18) Supervision expenses
(5) Information of rural road inventories
(12) Type of structures (19) Establishment of unit costs for
road maintenance works
(6) Needs and priority ranking (13) Road name (20) Total cost (TSH)
(7) Selection of rural road maintenance works
(14) Application of LBT and/or EBT (21) Environment aspect
(22) Gender aspect (23) HIV/AIDS aspect
Source: Form 4 of Monitoring System
Indicators 2-1 and 4-1 have been achieved in the model and disseminated districts because the Annual
Plans were formulated with all the necessary items mentioned above (refer to Figures 3-2 and 3-3).
10 The items necessary for the Annual Plan were decided during the Monitoring W/S held in September 2013.
62
Checklist of Chamwino DC (Form 4) Checklist of Iringa DC (Form 4)
Figure 3-2: Results of Checklist in Model Districts (Form 4 in Monitoring System)
63
Checklist of Kondoa DC (Form 4) Checklist of Mufindi DC (Form 4)
Figure 3-3: Results of Checklist in Disseminated Districts (Form 4 in Monitoring System)
(2) Indicator 2: The percentage of road maintenance works completed within the fiscal year
(including indicator 2 of Output 4)
With reference to the percentage of road work completion (including defect liability period), both
model and disseminated districts aimed at exceeding 85%11. Table 3-7 shows the achievements in the
past four years. Chamwino DC has been exceeding the target value since 2012/13, and the indicator
has been achieved. However, Iringa, Kondoa, and Mufindi DCs are aiming at achieving 85% of road
work completion within the financial year. Thus, it is expected that those DCs shall attain the target
value by formulating effective plans and promoting smooth scheduling management.
Table 3-7 The percentage of road maintenance completion in the model and disseminated districts (FY 2011/12 – 2014/15)
FY 2011/12 FY 2012/13 FY 2013/14 FY 2014/15
Model
Districts
Chamwino
District 45.5% 95.2% 91.67% 92.86%
Iringa
District 76.2% 76.9% 75.00% 70.59%
Disseminated
Districts
Kondoa
District ― ― ― 78.13%12
Mufindi
District ― ― ― 70.00%13
Source: Form 5 of Monitoring System
11 This target value was determined by reference to the target of Annual Performance Agreement concluded between PO-RALG and each LGA. 12 Although Kondoa DC received only 33.5% of the total approved budget by the end of FY 2014/15, the percentage of road maintenance completion was 78.13%. Since the financial resources for contractors were not sufficient in the DC, the payments to contractors fell into arrears. 13 The situation in Mufindi DC (received only 34.0% of the total approved budget) was the same as in Kondoa.
64
3.2.4. Achievements of Output 3
(1) Indicator 1: The ratings of district engineers and technicians of their practical skills and
knowledge
The Project aims at achieving over 3.75 (the same as 75%) for the ratings (scales of 1 to 5) of district
engineers and technicians of their practical skills and knowledge in the model districts. The ratings (10
question items with “5” in full points) were extracted from both RS Engineers (evaluation by another
person) and Council Engineers/Technicians (self-evaluation) from the perspective of fairness (refer to
Table 3-8 and Table 3-9).
Since the ratings of Council Engineers and Technicians of their practical skills and knowledge were
calculated as an indicator to show the current status objectively, the trends would be easily grasped.
The questionnaire survey on Council Engineers and Technicians was conducted by themselves
(“self-evaluation”) and RS Engineers (“evaluation by another person”), and the results were compared
so as to avoid subjective evaluation.
Table 3-8 The results of the ratings of Council Engineers and Technicians in Chamwino DC
of their practical skills and knowledge
3rd Questionnaire (February 2014)
4th Questionnaire (June 2015)
5th Questionnaire (January 2016)
RSE CE/CT RSE CE/CT RSE CE/CT
Q1. Planning skills and knowledge
3.00 (60.00%)
3.33(66.67%)
4.14(82.86%)
3.86(77.14%)
4.71 (94.29%)
4.29 (85.71%)
Q2. Preparation of road inventories
3.17 (63.33%)
4.00(80.00%)
4.29(85.71%)
3.71(74.29%)
4.43 (88.57%)
4.57 (91.43%)
Q3. Road structure design and/or drawing
2.33 (46.67%)
2.83(56.67%)
3.57(71.43%)
3.86(77.14%)
4.00 (80.00%)
3.86 (77.14%)
Q4. Procedures of budget request for road maintenance works
2.33 (46.67%)
3.67(73.33%)
4.00(80.00%)
3.57(71.43%)
4.57 (91.43%)
4.43 (88.57%)
Q5. Contents of Bill of Quantities (BOQ)
3.00 (60.00%)
3.83(76.67%)
4.14(82.86%)
4.14(82.86%)
5.00 (100.0%)
4.43 (88.57%)
Q6. Inspection tasks 2.50
(50.00%) 3.67
(73.33%)3.86
(77.14%)4.14
(82.86%)4.00
(80.00%) 4.71
(94.29%)
Q7. Technical advice and support for a contractor
2.33 (46.67%)
3.67(73.33%)
4.00(80.00%)
4.00(80.00%)
4.57 (91.43%)
4.29 (85.71%)
Q8. Time management of road maintenance works during execution periods
2.17 (43.33%)
3.17(63.33%)
3.86(77.14%)
3.71(74.29%)
4.00 (80.00%)
4.29 (85.71%)
Q9. Communication between district engineer/technicians and a contractor
2.17 (43.33%)
4.00(80.00%)
4.00(80.00%)
4.00(80.00%)
4.71 (94.29%)
4.86 (97.14%)
Q10. Record‐keeping skills 2.67
(53.33%) 3.00
(60.00%)3.86
(77.14%)3.86
(77.14%)4.29
(85.71%) 4.00
(80.00%)
Total Rating on Average (Q1 – Q10)
2.57 (51.3%)
3.52(70.3%)
3.97(79.4%)
3.89(77.7%)
4.43 (88.6%)
4.37 (87.4%)
65
Q11. Overall rating of practical skills and knowledge
2.83 (56.67%)
3.83(76.67%)
4.00(80.00%)
4.00(80.00%)
4.00 (80.00%)
4.00 (80.00%)
Note 1) RSE: RS Engineer, CE: Council Engineer, CT: Council Technician
Note 2) The 1st and 2nd Questionnaire Surveys were carried out in September 2012 and September 2013,
respectively.
Source: Questionnaire Survey through Forms 6-1 and 6-2 of Monitoring System
Table 3-9 The results of the ratings of Council Engineers and Technicians in Iringa DC
of their practical skills and knowledge
3rd Questionnaire (February 2014)
4th Questionnaire (June 2015)
5th Questionnaire (January 2016)
RSE CE/CT RSE CE/CT RSE CE/CT
Q1. Planning skills and knowledge
3.38 (67.50%)
3.25(65.00%)
4.20(84.00%)
3.40(68.00%)
4.90 (98.00%)
3.75 (75.00%)
Q2. Preparation of road inventories
3.75 (75.00%)
3.75(75.00%)
4.00(80.00%)
3.60(72.00%)
4.70 (94.00%)
3.92 (78.33%)
Q3. Road structure design and/or drawing
2.50 (50.00%)
2.88(57.50%)
3.60(72.00%)
2.90(58.00%)
4.30 (86.00%)
3.33 (66.67%)
Q4. Procedures of budget request for road maintenance works
3.38 (67.50%)
3.38(67.50%)
4.00(80.00%)
3.70(74.00%)
4.40 (88.00%)
3.92 (78.33%)
Q5. Contents of Bill of Quantities (BOQ)
3.63 (72.50%)
3.50(70.00%)
4.10(82.00%)
4.00(80.00%)
4.80 (96.00%)
4.00 (80.00%)
Q6. Inspection tasks 3.38
(67.50%) 3.13
(62.50%)4.40
(88.00%)3.60
(72.00%)4.80
(96.00%) 4.25
(85.00%)
Q7. Technical advice and support for a contractor
3.13 (62.50%)
3.38(67.50%)
4.50(90.00%)
4.00(80.00%)
4.80 (96.00%)
4.00 (80.00%)
Q8. Time management of road maintenance works during execution periods
3.00 (60.00%)
3.13(62.50%)
3.90(78.00%)
3.50(70.00%)
4.50 (90.00%)
3.42 (68.33%)
Q9. Communication between district engineer/technicians and a contractor
3.13 (62.50%)
3.38(67.50%)
3.90(78.00%)
4.00(80.00%)
4.60 (92.00%)
4.25 (85.00%)
Q10. Record‐keeping skills 3.50
(70.00%) 2.88
(57.50%)4.00
(80.00%)3.30
(66.00%)4.30
(86.00%) 3.42
(68.33%)
Total Rating on Average (Q1 – Q10)
3.28 (65.5%)
3.26(65.3%)
4.06(81.2%)
3.60(72.0%)
4.61 (92.2%)
3.83 (76.5%)
Q11. Overall rating of practical skills and knowledge
3.38 (67.50%)
3.25(65.00%)
3.90(78.00%)
3.40(68.00%)
4.50 (90.00%)
3.83 (76.67%)
Source: Questionnaire Survey through Forms 6-1 and 6-2 of Monitoring System
In the 5th Questionnaire Survey (January 2016), since the total ratings of Q1 to Q10 on average in the
model districts/regions exceeded 3.75, the target value, this indicator has ultimately been achieved.
Also, all the rating items assessed by both RS Engineers (evaluation by another person) exceeded 3.75,
the target value. On the other hand, for the self-evaluation by Council Engineers/Technicians in the
model districts, the rating items below 3.75, the target value, were “road structure design and drawing
66
(Q3)”, “time management (Q8),” and “record-keeping skills (Q10)” in Iringa DC only. Regarding the
design and drawing of Q3, the greater enhancement of these technical skills is required through the
dispatch of an expert who can instruct the topic and provide the training opportunity. With reference to
the time management of Q8, the reduction and delay of the road maintenance budget made it difficult
to execute and manage the works. For the record-keeping skills of Q10, the Council
Engineers/Technicians in Iringa DC perceived the need for recording the progress and completion of
road maintenance works and sharing the information within the office. It seems that the C/Ps try to
enhance and promote their own skills and knowledge. For the purpose of nationwide expansion in the
future, it is necessary for the Council Engineers/Technicians to cultivate their abilities and improve
their skills and knowledge in each item (Q1 - Q10) through the continuation of their own efforts as
resource persons in Tanzania.
Also, an upward trend is generally observed in the comparison of the last three questionnaire surveys
(refer to Figures 3-4 and 3-5). In particular, the ratings of all items, except for the above-mentioned
three items assessed by the Council Engineers/Technicians in Iringa DC, exceeded 3.75, the target
value, in the 5th Questionnaire Survey.
Comparing the spider charts of the results of the 4th and 5th Questionnaire Surveys, shown in Figure
3-6 (Chamwino DC) and Figure 3-7 (Iringa DC), it is sure that the areas in the charts have gradually
increased. In particular, in Chamwino DC, the rating results of the RS Engineers and Council
Engineers/Technicians closely overlapped, and the results have come close to a round shape, balanced
among each item. In Iringa DC, the rating results have gradually become balanced (rating results of
RS Engineers), although there remain some differences between them. Ideally, it is desirable to come
to a “round shape,” balanced among each item, rather than a “polygonal shape,” unbalanced among
them. Ultimately, it is crucial to expand the area of round shape and overlap the rating results of RS
Engineers and Council Engineers/Technicians.
67
2.00
2.50
3.00
3.50
4.00
4.50
5.00
January, 2016
June, 2015
February, 2014
Target Value = 3.75
2.50
3.00
3.50
4.00
4.50
5.00
January, 2016
June, 2015
February, 2014
Target Value = 3.75
Change in the rating results by RS Engineers in Dodoma Region
Change in the rating results by Council Engineers/Technicians in Chamwino DC
Figure 3-4 Change in the rating results of the practical skills and knowledge of Council Engineers/Technicians by RS Engineers (evaluation by another person) in Dodoma Region and
Council Engineers/Technicians (self-evaluation) in Chamwino DC (from 3rd to 5th Questionnaire Surveys)
2.00
2.50
3.00
3.50
4.00
4.50
5.00
January, 2016
June, 2015
February, 2014
Target Value = 3.75
2.00
2.50
3.00
3.50
4.00
4.50
5.00
January, 2016
June, 2015
February, 2014
Target Value = 3.75
Change in the rating results by RS Engineers in Iringa Region
Change in the rating results by Council Engineers/Technicians in Iringa DC
Figure 3-5 Change in the rating results of the practical skills and knowledge of Council Engineers/Technicians by RS Engineers in Iringa Region and Council Engineers/
Technicians in Iringa DC (from 3rd to 5th Questionnaire Surveys)
68
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
5.00
Q1. Planning capacity
Q2. Road inventories
Q3. Design and/ordrawing
Q4. Budget request
Q5. Contents of BOQ
Q6. Inspection tasks
Q7. Technical advices
Q8. Timemanagement
Q9. Communication
Q10. Record keeping
RS Eng.
District Eng. and Tech.0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
5.00
Q1. Planning capacity
Q2. Road inventories
Q3. Design and/ordrawing
Q4. Budget request
Q5. Contents of BOQ
Q6. Inspection tasks
Q7. Technical advices
Q8. Timemanagement
Q9. Communication
Q10. Record keeping
RS Eng.
District Eng. and Tech.
TARGET VALUE
Results of 4th Questionnaire survey (June 2015) Results of 5th Questionnaire survey (January 2016)
Figure 3-6 Comparison of the rating results between Council Engineers and Technicians (self-evaluation) in Chamwino DC and RS Engineers (evaluation by another person) in Dodoma
Region (4th and 5th Questionnaire Surveys)
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
Q1. Planning capacity
Q2. Road inventories
Q3. Design and/ordrawing
Q4. Budget request
Q5. Contents of BOQ
Q6. Inspection tasks
Q7. Technical advices
Q8. Time management
Q9. Communication
Q10. Record keeping
RS Eng.
District Eng. and Tech.
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
5.00
Q1. Planning capacity
Q2. Road inventories
Q3. Design and/ordrawing
Q4. Budget request
Q5. Contents of BOQ
Q6. Inspection tasks
Q7. Technical advices
Q8. Time management
Q9. Communication
Q10. Record keeping
RS Eng.
District Eng. and Tech.
Target Value
Results of 4th Questionnaire survey (June 2015) Results of 5th Questionnaire survey (January 2016)
Figure 3-7 Comparison of the rating results between Council Engineers and Technicians in Iringa DC and RS Engineers in Iringa Region (4th and 5th Questionnaire Surveys)
(2) Indicator 2: Number of consultations by council engineers/technicians (including indicator 3
of Output 4)
Chamwino and Iringa DCs aim at increasing the opportunities for consultations on rural road
maintenance between contractors and Council Engineers/Technicians. The numbers of consultations
by district engineers/technicians in FY 2013/2014 are shown in the table below. In particular, as direct
consultations on sites greatly influence the perfection level of roads, it is crucial to provide proper
instructions for contractors on sites. That is why the gradual increase in the numbers of consultations
in the past two years is highly meaningful.
In addition, the numbers of consultations in the disseminated districts in FY 2014/15 are shown in
Table 3-10. It is expected that the numbers of consultations in FY 2015/16 will exceed those in FY
69
2014/15.
Table 3-10 The numbers of consultations provided by Council Engineers/ Technicians in the
model and disseminated districts (FY 2013/14 – FY 2014/15)
FY 2013/14 FY 2014/15
Model
Districts Chamwino District
30 times
(including 12 pilot projects)
36 times
(including 9 pilot projects)
Iringa District 56 times
(including 10 pilot projects)
62 times
(including 15 pilot projects)
Disseminated
Districts Kondoa District ― 31 times
Mufindi District ― 20 times
Source: Form 7 of Monitoring System
(3) Indicator 3: The ratio of LBT works to all the maintenance works
With reference to the ratio of LBT works to all the maintenance works, Chamwino and Iringa DCs aim
at attaining 20%, and they exceeded the target value in FY 2014/15. The achievements in the past four
years are shown in Table 3-11 below.
Table 3-11 The ratio of LBT works to all the maintenance works in the model districts
(FY 2011/12 – 2014/15)
FY 2011/12 FY 2012/13 FY 2013/14 FY 2014/15
Model
Districts
Chamwino
District 0.0% 4.8% 16.67% 35.71%14
Iringa
District 23.8% 15.4% 56.25% 23.53%
Source: Form 5 of Monitoring System
3.2.5. Important Assumptions
(1) Important Assumptions for the Achievement of the Outputs
1) Institutional arrangement for rural road maintenance is not changed from the PMO-RALG to
another governmental institute.
Since PMO-RALG operates and manages rural road maintenance works at this time, this assumption
is fulfilled.
2) During the cooperation period, the RS engineers capacitated by the Project continue working
in their respective positions at the RS offices in the respective regions.
14 This percentage includes the number of road maintenance works in combination with EBT and LBT.
70
Since the RS Engineers capacitated by the Project are continuing to work in their respective positions
in Dodoma and Iringa Regions at this time, this assumption is fulfilled.
3) Budget disbursement for rural road maintenance is not severely delayed in the model and
disseminated districts of the respective regions.
The budget disbursement from the Ministry of Finance to Road Funds was delayed in FY 2014/1515,
and it affected the budget for rural road maintenance. For example, Iringa DC had received 60.6% of
the total approved budget as of the end of June 2015. Kondoa and Mufindi DCs received only 33.5%
and 34.0% of the total approved budget, respectively.
The project activities and the indicators are not largely influenced by this condition. However,
supervision by Council Engineers and Technicians was not carried out properly because the budget
necessary for transportation to sites was not disbursed sufficiently. Furthermore, payments to some
contractors were left unpaid for a while because of the delay of budget disbursement. Accordingly, the
contractors fell into arrears of wages to the community people participating in LBT works.
(2) Important Assumption for the Achievement of the Project Purpose
1) During the cooperation period, the district engineers capacitated by the Project continue
working in their respective positions in the model and disseminated districts.
Model Districts
Since the District Engineers (DEs) capacitated by the Project are continuing to work in their respective
positions in Chamwino and Iringa DCs at this time, this assumption is fulfilled.
Disseminated Districts
Although the former DE in Kondoa had been working at his office as of the end of FY 2014/15, a
newly appointed DE came to the office at the beginning of FY 2015/16. Afterwards, as he has been
participating in the AMTC, LBT specifications meeting, etc., there is the prospect that the DE will be
able to perform the project activities properly.
The former DE in Mufindi transferred in August 2014, and a newly appointed DE came to the office
three months after the beginning of FY 2014/15. It is considered that this condition does not severely
affect the achievement of the Project Purpose.
3.2.6. Technical Transfer for Continuous Monitoring Operations (Activity 2-3)
In preparation for the termination of the Project in March 2016, a monitoring W/S was held in the
Dodoma and Iringa Regions (on 26 January 2016 in Dodoma and 29 January in Iringa: the W/S
agenda is shown in Table 3-12 (1) (2) and the participant list in Table 3-13 (1) (2)). Because the 15 Although the road maintenance budget in FY 2015/16 is likely to be cut down by 50%, the precise percentages in each district council will be revealed after the end of FY 2015/16.
71
Project will be terminated before the end of the financial year of Tanzania, C/P shall collect the data
and information that will be extracted and settled after the end of the financial year. Thus, the
Monitoring Expert provided instructions on the overall picture of M/S, the indicators necessary for the
monitoring operations, the method of data entry for each form, etc., for the C/P during the W/S. Also,
the persons in charge of the collection and aggregation of monitoring results were decided as shown in
Table 3-14, i.e., “Who does what and how.” In any way, the Council Engineers/Technicians collect the
data and information in each district after the end of FY 2015/16, and PO-RALG aggregates and
summarizes them. Ultimately, PO-RALG needs to submit the achievements of the Project with the
indicators to the JICA Tanzania Office.
Table 3-12 (1) Agenda of Monitoring W/S in Dodoma Region (26 January, 2016)
Time Contents
9:30 – 10:10 1. Briefing of the Project Concept (PDM and PO/APO)
2. Explanation of Monitoring System (M/S)
10:10 – 11:10 (1) Monitoring mechanism with the conceptual diagram
11:10 – 11:40 Tea Break
11:40 – 14:00 (2) Discussions on each Form (Form 1‐7) by the facilitators as follows: Form 1: Makandi Form 2: Shama Form RALG‐1: Makandi Form 3: Expert Form 4: Makandi Form 5: Makandi Form 6: Mkwata Form 7: Mpinzile
14:00 – 15:10 Lunch Break
15:10 – 15:25 (3) Presentation on the project indicators extracted from the M/S
15:25 – 15:55 (4) How to read and use the data and information of Form 1‐7 with the files saved in your PC
15:55 – 16:20 (5) Data that shall be collected after the end of FY 2015/16 in the model and disseminated districts
Table 3-12 (2) Agenda of Monitoring W/S in Iringa Region (29 January, 2016)
Time Contents
9:35 – 10:25 1. Briefing of the Project Concept (PDM and PO/APO)
2. Explanation of Monitoring System (M/S)
10:25 – 11:30 (1) Monitoring mechanism with the conceptual diagram
11:30 – 12:00 Tea Break
12:00 – 14:10 (2) Discussions on each Form (Form 1‐7) by the facilitators as follows:
Form 1: Munissi
Form 2: Mwagogo
Form RALG‐1: Munissi
Form 3: Expert
Form 4: Munissi
Form 5: Munissi
72
Form 6: David
Form 7: Kasongo
14:10 – 15:25 Lunch Break
15:25 – 16:05 (3) Presentation on the project indicators extracted from the M/S
16:05 – 16:40 (4) How to read and use the data and information of Form 1‐7 with the files saved in
your PC
16:40 – 17:10 (5) Data that shall be collected after the end of FY 2015/16 in the model and
disseminated districts
Table 3-13 (1) Participant List in Dodoma Region (26 January, 2016)
Name Position Organization
Eng. Nanai Nyariri Executive Engineer PO‐RALG
Eng. Mkwata M. M. RS Engineer RAS Dodoma
Eng. Godwin S. Mpinzile District Engineer Chamwino DC
Qs. James M. Lukindo Quantity Surveyor (District) Chamwino DC
Mr. Makandi Mange Head of Road Technician Chamwino DC
Mr. Shama Amanzi Road District Technician Chamwino DC
Eng. Msafiri Seleman Road District Engineer Chamwino DC
Eng. Albert Maswaga Building Engineer Chamwino DC
Ms. Evelin Malilo Technician Chamwino DC
Eng. Meddah Donasian Engineer Kondoa DC
Mr. Ibrahim A. Ntomola Technician Kondoa DC
Mr. Magola Elias Lungwecha Technician Kondoa DC
Ms. Mayura Tsukamoto JOCV Kondoa DC
Table 3-13 (2) Participant List in Iringa Region (29 January, 2016)
Name Position Organization
Eng. David Mwakalalile RS Engineer RAS Iringa
Eng. Leopold Runji District Engineer Iringa DC
Eng. Anyitike Kasongo Engineer Iringa DC
Eng. Fidelis Shirima Engineer Iringa DC
Mr. Nestory Chacha Quantity Surveyor Iringa DC
Mr. Baraka Munissi Technician Iringa DC
Mr. Subira Munissi Technician Iringa DC
Mr. Ncholaus Mwagogo Technician Iringa DC
Mr. Alan Mhauka Technician Iringa DC
Ms. Elvira Wilbard Technician Iringa DC
Eng. Peter Johnson District Engineer Mufindi DC
Eng. Dickson Mkokota Engineer Mufindi DC
Mr. Aidani Maliva Engineer Mufindi DC
Mr. Haji Shabani Technician Mufindi DC
Mr. Naoya Kaneko JOCV Mufindi DC
73
Table 3-14 Persons in charge of each Form in Model and Disseminated DCs
Forms Chamwino Iringa Kondoa Mufindi
Form 1 Makandi Munissi Maombi Maliva
Form RALG‐1 Makandi Munissi Maombi Mpaglke
Form 2‐1 & 2 Msafiri (Shama)
Mwagogo Kibegenza
Meddah Ntomolah (Supported by Msafiri and Shama)
Maliva Mpaglke (Supported by Mwagogo and Kibegenza)
Form 3 ― ― ― ―
Form 4 Makandi (Signed by Mpinzile and Mkwata)
Munissi Kajange (Signed by Runji and David)
Magola (Signed by Myaule and Mkwata)
Peter Mkokota (Signed by Peter and David)
Form 5 Shama Munissi Shirima
Maombi Mkokota
Form 6‐1 & 2 ― ― ― ―
Form 7 Mpinzile Runji Kasongo
Myaule Peter Maliva
74
4. Terminal Evaluation JICA dispatched the Terminal Evaluation Team to the United Republic of Tanzania from 7th to 25th
August 2015, with the project period remained of approximately 7 months. The Terminal Evaluation
has been undertaken by the Team and Tanzania authorities concerned.
Objective of the Terminal Evaluation
Objectives of the Terminal Evaluation are as follows:
a. To review the achievements and assess the major outcome of the Project according to the Project
Design Matrix (PDM)
b. To clarify problems and issues to be addressed for the successful implementation of the Project for
the remaining periods
c. To evaluate the project according to the five evaluation criteria(See details in 3.1), i.e. relevance,
effectiveness, efficiency, impact and sustainability
d. To review and revise the PDM if necessary
Members of the Team
Mr. Hiroshi TAKEUCHI Leader Director, Transportation and ICT Group, Infrastructure and Peacebuilding Department, Japan International Cooperation Agency (JICA)
Mr. Kiyohito SHIMADA Project Coordinator
Transportation and ICT Division 2, Infrastructure and Peacebuilding Department, Japan International Cooperation Agency (JICA)
Mr. Masaya OMAE Evaluation Analyst
General ManagerSuccess Project Management Office Co., Ltd.
4.1 Results of the Terminal Evaluation
(1) Achievement of the Project Purpose
Table4-1 Rating of Achievement of Project Purpose
Rating of Achievement A: It will be satisfactory achieved by the end of the Project B: It will be almost but not fully achieved by the end of the Project C: It will be difficult to be achieved by the end of the Project
Indicator 1 Indicator 2 Indicator 3
A B A
Project
Purpose:
Administrative services of rural road maintenance provided by LGAs are
improved in the target areas, and its nationwide expansion approach is developed.
Overall
Achievement
The Project Purpose will be fulfilled until the end of the Project because the
maintenance status of rural roads in model and disseminated districts have been
developing at a certain levels respectively although there are some up and down
according to the results of surveys conducted for the community people who were
75
involved in the pilot projects in the model and disseminated districts showing the
positive status, such as “Good” and “Fair”.
Also the satisfaction ratings of contractors showed almost at the target level of
75% satisfaction according to the results of surveys.
Furthermore, the percentage of the rollover funds for rural road maintenance
showed properly low enough values comparing to the target values.
The approach for the nationwide expansion has been securing developing both on
technically and administratively as clearly observed in the achievement of
Outputs, especially Output 4; however it is necessary to take necessary measures
to secure the budgets and to increase human resources in proportion to the huge
burden for its nationwide expansion.
Verifiable Indicators Achievement Level
1 The maintenance
status (Good, Fair,
and Poor) of rural
roads is improved in
the model and
disseminated districts
of the respective
regions.
The results of Maintenance status of rural roads in Model Districts such
as, Chamwino and Iringa DC from 2012 to 2015 and Disseminated
Districts, such as Kondoa and Mufindi DC are as follows. Total values of
Good and Fair indicate steady-going development over the target values
of 80% in Chamwino and 70% of Iringa until FY 2013/14 but just
downturned in Chamwino in FY 2014/15. This is because the total
length of road network in Chamwino was extended from around 600 to
1,040km. However, the percentage exceeds 90% if the road network is
retained as it was. In Disseminated Districts, these values show good
results in an early stage.
Table 4-2 Maintenance status of rural roads
in model and disseminated districts FY 2011/12 FY2012/13 FY2013/14 FY2014/15
Chamwino 74.71% 79.04% 81.5% 73.70%
Iringa 60.16% 66.36% 71.29% 92.49%
Kondoa Nil. Nil. 63.34% 77.35%
Mufindi Nil. Nil. 63.09% 57.08%
(Source: Form 1 of Monitoring System)
2 The satisfaction
ratings of the
contractors/
community people in
the model and
disseminated districts
of the respective
According to the result of the questionnaire survey conducted in
February 2014 and June 20151, “Satisfaction ratings of contractors in
Chamwino and Iringa DC” shows that they were exceeded at 1st survey
but downturned at 2nd survey as shown in the table below; however they
are still almost same level of target values.
1 This survey is targeted for the contractors and community people who were involved in the pilot projects implemented after the commencement of the Project
76
regions exceed
75/75% (Chamwino
and Iringa) on
average with
reference to rural
road maintenance
works or status.
Table 4-3 Satisfaction ratings of contractors in Chamwino DC and Iringa DC
1st Survey (February 2014)
2nd Survey (June 2015)
Chamwino
Iringa Chamwino Iringa
Number of responders
5 14 11 11
Total Rating on Average (Q1 – Q10)
76.0% (3.80)
87.3%(4.36)
72.9% (3.65)
72.4% (3.62)
(Source: Questionnaire survey through the Form 2-1 of Monitoring System)
On the other hand, the result of the questionnaire survey conducted in
parallel with the above mentioned survey such as “Satisfaction ratings of
community people in Chamwino and Iringa DC” shows that a
steady-going development to almost reach the target value in Chamwino
DC and already achieved in Iringa DC. The satisfaction rating by
community people in Chamwino is lower than Iringa because they may
feel such uneasiness due to the unexpected drainage flows to their own
areas. It is necessary to take a preliminary survey on community needs
precisely.
Table 4-4 Satisfaction ratings of community people
in Chamwino DC and Iringa DC 1st Survey
(February 2014) 2nd Survey (June 2015)
Chamwino Iringa Chamwino Iringa
Number of responders
36 43 171 148
Total Rating on Average (Q1 – Q10)
50.1%(2.50)
77.7% (3.89)
66.5% (3.32)
82.7% (4.13)
(Source: Questionnaire survey through the Form 2-2 of Monitoring System)
3 The percentage of the
rollover funds for
rural road
maintenance is
decreased in the
model and
disseminated districts
of the respective
regions.
With reference to the percentage of the rollover funds for rural road
maintenance, all districts, such as the model districts and disseminated
districts attained the level below 15% as follows.
Table 4-5 The percentage of the rollover funds for rural road maintenance in the model and disseminated districts
FYName
2011/12 2012/13 2013/14 2014/15
Chamwino 60.59% 1.23% 10.03% 1.23%
Iringa 12.03% 15.10% 4.60% 0.00 %
Kondoa Nil. Nil. 21.48% 3.64%
Mufindi Nil. Nil. 32.13% 0.51%(Source: Form RALG-1
“Summary of Committed and Uncommitted Action Plan” by PMO-RALG)
77
(2) Achievement of the Outputs
Table 4-6 Rating of Achievement of Outputs
Rating of Achievement A: It will be satisfactory achieved by the end of the Project B: It will be almost but not fully achieved by the end of the Project C: It will be difficult to be achieved by the end of the Project
Indicator 1-1 Indicator 1-2
A B
Output 1 : The capacity of PMO-RALG for coordinating and supporting LGAs in
collaboration with MOW on rural road maintenance is strengthened.
Overall
Achievement:
The Output 1 will be secured until the end of the Project.
Activities for strengthening the capacity of PMO-RALG for coordinating and
supporting LGA are conducted, the Rural Road Maintenance Operational
Guidelines was authorized by MOW in 10th December, 2014 and printed and
bounded on February 2015 which are waiting for reaching towards the target value
of utilizing rates by the RSE and DE to exceed 80% from the latest value of
68.18% in August 2014.
On the other hand, even though the following Verifiable Indicators from 1-1 and
1-2 are to be fulfilled, the most important effort should be paid for further
development, such as 1) to collect information and data from the model districts,
2) to analyze and 3) to share among all the stakeholders. Such information sharing
will contribute to the further effective planning by PMO-RALG and the
self-reliant efforts for continuous development at site for each district.
Verifiable Indicators Achievement Level
1-1 The Rural Road
Maintenance
Operational
Guidelines are
authorized by MOW.
Secured
The operational guidelines were provided by the strong initiative of
the Tanzanian side and finally approved by MOW. The guidelines
were formally printed and bound on February 2015 and the guidelines
launch ceremony was held in Dar es Salaam on 10th March, 2015.
Therefore the indicator 1-1 was successfully secured; however this is
not completed perfectly but continued to revise periodically to meet
with the actual situation in the future.
1-2 The percentage of
the RS and district
engineers utilizing
the operational
guideline distributed
by PMO-RALG and
Partially Secured
The result of 1st questionnaire survey responded by forty-four (44)
in August 2014 shows the percentage of RS/council engineers utilizing
the Operational Guidelines 68.18% and reaching towards the target
value to exceed 80% (Source: Questionnaire survey through the Form
3 of Monitoring System). The latest result will be confirmed soon at
78
MOW exceeds 80%
across the mainland
of Tanzania.
the Engineers Day at the end of August, 2015.
RSEs play a major role in dissemination and promotion and are in
charge of coordination for technical transfer to dissemination
districts. RSEs are also in charge of similar tasks for dissemination
working groups in the regions. In working groups, the Project
provides training on GIS, medium/long-term plan and support RSEs to
manage the working groups. In addition, the Project explained
AMTC (Annual Monitoring and Training Cycle), which is a
monitoring and training plan for sustainable technical transfer, to
RSEs and DEs.
Indicator 2-1 Indicator 2-2
A B
Output 2 : The rural road maintenance procedure of the LGAs is strengthened in the model
districts.
Overall
Achievement:
The Output 2 will be secured until the end of the Project.
Activities for strengthening the rural road maintenance procedure of the LGAs
have been conducted as planned. Output 2 is likely to be achieved based on the
achievement of activities at the Terminal Evaluation because the Annual Rural
Road Maintenance Plan covered necessary items based on the checklist.
On the other hand, the target values of road maintenance completion in the
model districts (over 85%), it was reached 92.86% in Chamwino but 70.59% with
a sideways movement since 2011/2012 in Iringa.
Although these series of works may let the persons in charge impose a heavy
burden every year, all the related persons should increase awareness about the
importance of proper planning in advance to acquire necessary budget for
necessary works timely and logically.
Verifiable Indicators Achievement Level
2-1 Annual Rural Road
Maintenance Plan
prepared by the
LGAs in the model
districts contains
necessary items
based on the
checklist.
Secured
The Annual Rural Road Maintenance Plan was prepared on the
basis of the medium- and long-term rural road maintenance plan, the
prioritization of rural road maintenance, etc. Also, the Plan contains
necessary items based on the checklist as required in the indicator 2-1
of the PDM. The specific items are shown below. Therefore the
indicator 2-1 was successfully secured. However, it is necessary to pay
attention to the assessment at the end of the year and comments from
the contractors engaged in the maintenance and the benefitted
communities in order to develop the level of the plan in the
79
succeeding year.
Table 4-7 Items necessary for the Annual Rural Road
Maintenance Plan (1) Mid‐ and long‐term objectives (Vision)
(2) Annual objectives
(3) Strategies and specific activities for the annual objectives
(4) Information of classified roads
(5) Information of rural road inventories
(6) Needs and priority ranking
(7) Selection of rural road maintenance works
(8) Coverage of road network
(9) Preliminary schedule
(10) Procurement procedures
(11) Work type
(12) Type of structures
(13) Road name
(14) Application of LBT and/or EBT
(15) Surface type
(16) Distance (km)
(17) Time frame of rural road maintenance works
(18) Supervision by qualified person(s)
(19) Establishment of unit costs for road maintenance works
(20) Total cost (TSH)
(21) Cross‐cutting issues (environment, gender)
(Source: Mid-term Progress Report by Consultant (2nd Year) in June 2015)
2-2 The percentage of the
road maintenance
works completed by
contractors
(including defect
liability period) for
all the maintenance
works in the Plan
exceeds 85%
Chamwino and
Iringa) within the
financial year.
Partially secured
Related to the achievement of target values of road maintenance
completion in the model districts (over 85%), it was reached in
Chamwino but in Iringa. Four (4) years’ progress are as follows. The
reason of low rate Iringa came from the geographical difficulty
comparing to Chamwino, such as bumpy and rocky surface, longer
distance, blockage by river and so on.
The achievement values in the disseminated districts, Kondoa and
Mufindi, were surveyed newly as 78.13% and 70.00% respectively
which show a good results in an early stage.
The standard rate of 85% for completion works is better to be revised
based on the characteristics of each district from the perspectives, such
as technical or financial difficulty, immediacy and others. Such a
decision making process should be resulted taking findings of
stakeholders into consideration and reflected into the Operational
Guidelines.
80
Table 4-8 Percentages of the road maintenance works Completed in the model districts
FYName
2011/12 2012/13 2013/14 2014/15
Chamwino 45.5% 95.2% 91.67% 92.86%Iringa 76.2% 76.9% 75.00% 70.59%
(Source: Form 5 of Monitoring System)
Indicator 3-1 Indicator 3-2 Indicator 3-3
B A A
Output 3 :
The practical skills and knowledge of responsible organizations (concerned
departments of the LGAs, contractors, etc.) on rural road maintenance are
improved through the LBT application in the model districts.
Overall
Achievement:
The Output 3 will be secured until the end of the Project.
The practical skills and knowledge of responsible organizations (concerned
departments of the LGAs, contractors, etc.) on rural road maintenance are
improved through the LBT application in the model districts. However it is
expected to reach the target value of DE/DT in Iringa DC from slightly below
of 3.60 to 3.75.
Apart from the statistics, it is obvious that the skills and knowledge have
been improving because of the completed rural roads constructed by LBT
comparing to such roads by EBT
For the further improvement of the LBT application to the rural road
maintenance, PMO-RALG decided to secure at least 20% of the maintenance
works in all of the districts even though the latest rate is low. This policy will
assist to promote the LBT nation widely.
Verifiable Indicators Achievement Level
3-1 The rating of district
engineers and
technicians on their
practical skills and
knowledge exceeds
3.75 (1 to 5 scales)
Chamwino and
Iringa) on average in
the model districts.
Partially secured
The result of the questionnaires survey from September 2013 to
June 2015 related to the “Overall rating on practical skills and
knowledge” is as follows. Such ratings are over 3.75 except DE
(District Engineer) in Iringa DC; however improving steadily year by
year. (RSE: Regional Secretary Engineer, DE: District Engineer, DT:
District Technician)
Table 4-9 The total rating on average results of engineers and
technicians in Chamwino and Iringa DC on their practical skills and knowledge
September, 2013 February, 2014 June, 2015
81
RSE DE/DT RSE DE/DT RSE DE/DT
Chamwino2.64
(52.9%)3.46
(69.1%)2.57
(51.3%)3.52
(70.3%) 3.97
(79.4%) 3.89
(77.7%)
Iringa 3.04
(60.8%)2.89
(57.8%)3.28
(65.5%)3.26
(65.3%) 4.06
(81.2%) 3.60
(72.0%)
(Source: Questionnaire survey through the Form 6-1 and 6-2 of Monitoring System)
3-2 The number of
consultations on
rural road
maintenance
between
contractors and
district engineers
and technicians is
increased in the
model districts.
Secured
Chamwino DC and Iringa DC have been aiming at increasing the
opportunities for consultations on rural road maintenance between
contractors and district engineers/technicians. The number of
consultations by district engineers/technicians in FY 2013/2014 and
FY 2014/2015 are shown in the table below with good values.
Table 4-10 The number of consultations provided by the district
engineers/technicians in model districts FYName
2013/14 2014/2015
Chamwino District, Dodoma Region
30 times
(incl. 12 pilot projects)
36 times
(incl. 9 pilot projects)
Iringa District, Iringa Region
56 times
(incl. 10 pilot projects)
62 times
(incl. 15 pilot projects)
Kondoa District,Kondoa Region
Nil. 31 times
Mufindi District,Mufindi Region
Nil. 20 times
(Source: Form 7 of Monitoring System)
The following comments were given at the consultations in the
model districts.
Table 4-11 Statistics and comments at consultations in the model districts
Chamwion Iringa Mufindi Kondoa Total Rate
Construction work control
14 37 7 14 72 43%
Sample of Consultation Comments: Equipment utilization: Construction was made to the contractor to hire the equipment, such as towed grader, water bozzer, and pedestrian roller, during compaction.
Quality Control
11 26 4 8 49 30%
Sample of Consultation Comments: Concreate works: At the first contractor proposed to use the aggregates from the locally made stones, but the office instructed him to bring the aggregates from Mswiswi in Mbeya which is approved by our office.
Schedule Management
4 8 8 5 25 15%
Sample of Consultation Comments: Watering and compaction: The contractor was advised to share water bowser with other LBT contractor to fasten the
82
speed of camber formation.
Safety Management
4 8 1 4 17 10%
Sample of Consultation Comments: Drainage works: Insuring the contractor on excavation of cathwater and mitre drains.
Others 3 0 0 0 3 2%
Sample of Consultation Comments: Gravelling works: Inculeds excavate garavel removal boudders, stock piles, load, houl up 5km, off load, spread, watering and compacting to average 150mm thick.
Total number of comments: 166
(Source: Form 7 of Monitoring System)
3-3 The ratio of LBT
works to all the
maintenance works is
increased in the
model districts.
Secured
The ratio of LBT works to all the maintenance work in the past three
(3) years in Chamwino has been improving steadily as shown in the
table below. However, it has been showing a seesaw tendency
because of the same geographical difficulties mentioned in the
indicator 2-2 above.
Table 4-12 The ratio of LBT works to all the road maintenance works in the model districts
FYName
2011/12 2012/13 2013/14 2014/15
Chamwino District, Dodoma Region
0.0% 4.8% 16.67% 35.71%
Iringa District, Iringa Region
23.8% 15.4% 56.25% 23.53%
(Source: Form 5 of Monitoring System)
Indicator 4-1 Indicator 4-2 Indicator 4-3
A B B
Output 4 : The dissemination mechanism for rural road maintenance approach within the
respective regions is established.
Overall
Achievement:
The Output 4 will be secured until the end of the Project but some indicators,
such as the completion rate and numbers of consultation on rural road
maintenance, will be confirmed from the beginning of a new fiscal year, 1st of
July 2015 and summarized for three (3) quarters at the end of the Project in
March 2016. And the annual statistics will be analyzed in June 2016 after the
completion of the project.
The Annual Rural Road Maintenance Plan contains necessary items based on
the checklist as required in the disseminated districts.
83
Furthermore, necessary equipment and materials were provided for the Project
implementation, such as tractor, water pump, spare parts and others. Such
equipment and materials were contributed for LBT application promotion and let
save the renewal expense within 5 (five) years according to the result of
monitoring. This leasing mechanism was confirmed as a feasible system. And
also the combination of necessary equipment as a set was discussed and
illustrated by some examples.
Verifiable Indicators Achievement Level
4-1 Annual Rural Road
Maintenance Plan
prepared by the
LGAs in the
disseminated
districts contains
necessary items
based on the
checklist.
Secured
As stated at the Output 2, Indicator 2-1 above.
4-2 The percentage of
the road maintenance
works completed by
contractors
(including defect
liability period) for
all the maintenance
works in the Plan is
increased within the
financial year.
Partially secured
The Annual Rural Road Maintenance Plan was prepared. The
technical instruction has been conducting in the disseminated district.
This indicator will be fulfilled in the end of June, 2016 after the
completion of the Project towards 85%.
Table 4-13 Percentages of the road maintenance works
Completed in the disseminated districts
FYName
2014/15
Kondoa 78.13% Mufindi 70.00%
(Source: Form 5 of Monitoring System) 4-3 The number of
consultations on
rural road
maintenance between
contractors and
district engineers and
technicians is
increased in the
disseminated
districts.
Partially secured
The data will be commenced confirming from the beginning of a
new fiscal year, 1st of July 2015 and summarized for three (3) quarters
at the end of the Project in March 2016. And the annual statistics will
be analyzed in June 2016 after the completion of the project.
84
(3) Possible Achievement of the Overall Goal
Table 4-14 Rating of Achievement of Overall Goal
Rating of Achievement
A: It will be satisfactory achieved by the end of the ProjectB: It will be achieved within five (5) years after the end of the Project C: It will be difficult to be achieved within five (5) years after the end of the Project
Indicator 1 Indicator 2 Indicator 3
B B B
Overall Goal: The rural road maintenance procedure and services of LGAs in Dodoma and Iringa
Regions are improved.
Overall
Achievement
:
To achieve the Overall Goal is also expected to be fulfilled same as the Project
Purpose if the Tanzanian side takes necessary measures to secure the budgets and
to increase human resources. Also the LGAs should work to simplify and promote
the efficiency in order to reduce burden on each staff member.
In addition, the Operational Guidelines of Rural Maintenance should be always
utilized and be treated as the primary guideline for the rural road maintenance
cycle duties, such as planning, execution and assessment to feedback necessary
information for planning in the succeeding year.
Verifiable Indicators Achievement Level
1 Annual Rural Road Maintenance
Plans prepared by the LGAs of the
respective regions contain
necessary items based on the
checklist.
Will be fulfilled with a specific condition
As this kind of indicator was fulfilled for the
(Indicator 2-1) of the Output 2 in the model district, it
may be fulfilled in the other districts, if the necessary
human resources and budget are secured.
2 The percentage of the road
maintenance works completed by
contractors (including defect
liability period) for all the
maintenance works in the Plan is
increased within the financial year
in the respective regions.
Will be fulfilled with a specific condition
As this kind of indicator was fulfilled for the
(Indicator 2-2) of the Output 2 in Chamwino DC, it may
be fulfilled in the other districts, if the necessary human
resources and budget are secured.
3 The maintenance status (Good,
Fair, and Poor) of rural roads is
improved in the respective regions.
Will be fulfilled with a specific condition
As this kind of indicator was fulfilled for the
(Indicator 1) of the Project Purpose, it may be fulfilled,
in the other districts, if the necessary human resources
and budget are secured.
85
(3) Conclusion
In conclusion, the Team appreciated an enormous effort to achieve the Project Purpose by Tanzanian
side through a series of activities together with the Japanese expert team. Both sides confirmed
sufficient achievements and impacts were produced in principal as the result of the project activities.
As both sides observed, if the following conditions are sincerely secured autonomously by the
Tanzanian side, the tangible results will be created continuously to develop the rural traffic
environment for the better, healthy and convenient community life in rural areas in future.
First of all, it is expected to monitor the activities and indicators for FY2015/16, which were not
confirmed at the Terminal Evaluation because of the works waiting for the confirmation timing, end of
June 2016, although the project would be terminated at that time. Those indicators related to the
Output 4 (The dissemination mechanism for rural road maintenance approach within the respective
regions is established.), which shows the percentage of the completed maintenance works and the
number of consultations on rural road maintenance are necessary to measure the deepness of
establishing the sustainable technical transfer mechanism as well as the possibility for the nationwide
dissemination of the Project fruits.
Secondly, it is obvious to secure sufficient “Man, Machine and Money” are the key factors to proceed
to develop and promote so that super goal and overall goal will be attained.. In order to secure such
core conditions, PMO-RALG has a heavy duty to take a strong leadership.
As PMO-RALG has been trying to reinforce its capacity by the organizational reform since 1st July,
2015, the Team is willing to welcome for the further capacity development. Because it was observed
that human resource management such as so busy situation of RSEs and transfer of counterpart
engineers may hamper technical transfers in the Project progress process, some intervention or effort
might be necessary to promote the technical transfer in further large scale.
The Project activity proved that necessary LBT equipment promotes construction progress and even to
be replaced by self-absorbed leasing revenues. As per financial aspect, expenses for these kinds of
development are expected to be provided, mainly from the Road Fund continuously and increasingly
so as to match the current needs; however for the further dissemination of the result of the Project, the
Tanzanian side is recommended to make an attempt on securing the new sources of funding.
As reference, the Overall Goal is “The rural road maintenance procedure and services of LGAs in
Dodoma and Iringa regions are improved”, and the Super Goal is “Rural roads in whole Tanzania are
properly maintained through application of appropriate technology and methodology.”
4.2. Recommendations from the Terminal Evaluation Team
(1) Contribution to establish technical specifications for the LBT
The developing operational guideline is focused on improvement of the local government
86
administration services, and as for the present PDM, the technical issues for the targeted
regions/districts officers (e.g. RSE, DE) are not the major activities in the Project activity. However,
technical specifications for the LBT implementation are required for conducting appropriate order,
contract for LBT works and explanation to the auditor’s technical questionnaire.
<Within the project period>
Considering the situation mentioned above, the Team recommends again turning to look at the
recommendation at the Mid-term Review that the Project shall continuously challenge to help drafting
specification for the Pilot Projects by conducting the additional workshop, seminar and arrangement
for the meeting inviting the persons concerned as arranging now. LBT Specification meetings are
planed 3 times by the end of the project period, so this meeting should be surely conducted and it is
desirable that the drafted specification will be utilized for the next pilot projects. It is also important to
collect the needs for specification in model district and disseminated districts which Japanese expert
team have already started.
<After the project period>
The LBT specification needs to be finalized by PMO-RALG and then approved by MOW. Besides, the
team expects that stakeholders should improve above LBT specification in the process of
dissemination to other districts in the targeted regions and nationwide. This activity shall be crucial to
achieve the purpose of the Project by considering an additional input to encourage the dissemination
approach which is the super goal to be achieved.
(2) Comprehensive capacity of PMO-RALG to manage development and maintenance of rural
road
For the development of the capacity of PMO-RALG, it is necessary that PMO-RALG needs to be able
to organize information and data collecting, filing, analysing and releasing into the stakeholders. Such
proper information and data management will contribute to secure the management cycle based on the
planning, execution and assessment. This kind of approach will contribute to manage the nationwide
expansion of LBT.
For this organizational enhancement, the following measures are recommended by the Team.
<Within the project period>
The Japanese Project Team is required to give instructions to PMO-RALG related to the above
mentioned necessary know-how, on such as information and data collecting, filing, analysing and
releasing into the stakeholders in order to offer the higher level of capacity-building assistance to
PMO-RALG.
<After the project period>
Through such management mentioned above, PMO-RALG is required to grasp good practices and
87
challenge for the future, especially as the forefront, the Annual Rural Road Maintenance Plans should
be prepared based on such information and data properly.
(3) Effective direction for use of the operational guidelines of rural road maintenance
The Operational Guidelines for District Roads Maintenance is accepted as the first official guidelines
for the rural road maintenance in Tanzania. However, it further needs to be revised for the purpose to
be used conveniently and serve as fitted guidelines for the latest situation in Tanzania.
For this purpose, it is recommended PMO-RALG to pay attention for necessary timing to review and
revise the Guideline such as monitoring activities are conducted. When the guideline needs to be
revised, PMO-RALG should convene the meetings and revise with the stakeholders who has
participated the regular meetings on operational guideline, as it is described on the guideline article 2.8.
This meeting should be convened on Tanzanian sides’ initiative, which means PMO-RALG calls the
stakeholders, leads meeting and submits the revised draft guideline to MOW to get approval timely.
(4) Necessity of monitoring for indicators in end of June, 2016
The next annual monitoring will be conduct after the end of June, 2016 - after the project period. This
monitoring is quite important because the results show the situation and outcome of AMTC in
disseminated districts. For this reason, PMO-RALG needs to conduct the monitoring by itself around
July, 2016. The result of monitoring is expected to be shared with JICA Tanzania Office, before end of
July 2016.
(5) Necessary budget and qualified staff allocation
To secure the sustainability of the Project, needless to say, one of the most important challenges is to
reduce the budget shortfall and delay of disbursement and proper human resource management such as
attach more manpower to RSE offices for the smooth implementation of continuous development and
dissemination of fruits of the Project nation widely. The Team recommends strongly to take proper
measures for such important factors continuously within and after the Project period.
(6) Harmonization and collaboration with BEJDPO and other DPs activities
The Team pointed out the importance of collaboration with other DP financed projects such as
Tanzania First Business Environment for Jobs Development Policy Operation (BEJDPO1) supported
by World Bank and JICA, other technical assistance and financial support in rural road sector by
Europe Union, USAID, DFID, AFCAP and so forth, so that the each project can contribute for
generating synergy effect and complementing one another. Dissemination process such as holding
workshop together, support of human resource management of PMO-RALG and LGAs, procurement
of LBT equipment could be candidates of collaborative activities.
88
4.3. Lessons Learned
The history of technical assistance on LBT in Tanzania by JICA dates to the implementation of the
Project for Capacity Strengthening on Labor Based Technology (LBT) Training at ATTI in May, 2006.
The counterpart personnel and Japanese experts have been working towards to develop the poor
situation of rural road in Tanzania since the previous Project. As a result, the stakeholders related to
the rural road maintenance have accumulated a certain level of experience, skill and knowledge.
The following findings are said as referable to the further ODA project implementation not only in
Tanzania but also world widely.
(1) Initiative by C/P
Primary output from this Project is that the C/Ps prepared the Rural Road Maintenance Operational
Guidelines on their own initiative. The Project has been assisting to realize its autonomous
management of dissemination and stabilization of the Guidelines targeting until the end of Project
period. The approach of the Project may give recommendations to the other Project as the way to
respect activities by C/Ps their own initiative and to spread outputs from the district/region, zone and
to all the country.
(2) Communication in native language
The Japanese experts have been trying to communicate in the national language in Tanzania, Swahili.
This efforts have made communications with the C/P personnel smoothly and friendly.
(3) Monitoring in the Project
The Project has been conducting monitoring the process and achievement, and collecting necessary
information and data for the smooth implementation of the Project and the periodical evaluation
initiate by the specified expert cooperated with stakeholders. In addition, the counterpart personnel
have been working with the said expert based on the project management tool, PDM; therefore the
counterpart personnel understand the process well. At the same time, the format of questionnaires
provided by the said expert is under discussion to be added in the Operational Guidelines together with
the other management and assessment systems for the purpose to enhance both on internal and
external assessment systems.
(4) Depreciable Equipment Management
The set of equipment for LBT provided by JICA was used for the demonstration experiment for the
depreciable equipment management. As a result, it was confirmed to be depreciable within five (5)
years to be renew for keeping such equipment.
89
5. Other Important Activities
5.1 Joint Coordinating Committee (JCC)
PMO-RALG and the Project convened the Joint Coordinating Committee (JCC) meetings as follows.
Table 5-1 RMSD Joint Coordinating Committee 2012-2016
Round Date Agenda Participants
JCC‐1 4/Oct/2012 ・ Presentation of Plan of Operation and Annual Plan, Outline
of the Project,
・ Baseline Survey, Establishment of Model District, Direction
of Capacity Development
20
JCC‐2 3/June/2013 ・ Presentation of Annual Plan, Progress Report 17
JCC‐3 24/July/2014 ・ Progress of the Project, Achievement of the indicators
・ Plan of the Operational
・ PDM modification
・ Disseminated District Selection
・ Mid‐term Review
32
JCC‐4 20/Aug/2015 ・ Progress of the Project, Achievement of the indicators
・ Terminal Evaluation
・ Draft of the Road Map
13
JCC‐5 23/Feb/2016 ・ Achievement of the Project
・ Summary of the Project Activities
・ Proposal from the RMSD
・ Road Map
21
5.2 Provision of Equipment
The Project procured the equipment for the project activities as follows. By the end of the project
period, those were officially provided to the Tanzanian side.
Table 5-2 Equipment Procured by the Project
Iringa DC Chamwino DC
1.Tractor 1. Tractor
2.Towed Type water Bowser 2.Vibrating Roller
3.Vibrating Roller 3. Plate Compactor
4.Plate Compactor 4. Engine Pump
5.Engine Pump
Operation Manegement Direct Direct
Maintenance Management Contract(TEMESA) Contract (TEMESA/Private)
Leasing Management Direct Direct
Fund Management Road Fund Account Road Fund Account
Equipment Procured by JICA
90
5.3 Conducting the Baseline Surveys
A Baseline survey was conducted in 2013 with the implementation sub-contracted to NIMETA
Consult Ltd. The terms of reference for the baseline survey are shown below.
Table 5-3 Contents of Baseline Survey (TOR)
Items TOR
A: Road Inventory Survey (1) The Consultant shall reviews the Road Inventory survey of Dodoma and
Iringa regions. Both regions have 6 and 4 councils respectively.
(2) Review works will be done through the road inventory record analysis (indicated road conditions as Good, Fair, Poor).
(3) Above mentioned records can get available at each Regional Secretariat
Engineer (RSE) office or PMORALG head quarter office at Dodoma.
Supplemental data, such as “Local Government Road Inventory and
Condition Survey (LGRICS)” and “the Annual District Roads Inventory and
Condition Survey (ADRICS)” were available by JICA Team.
(4) The Consultants shall compile inventory’s data on the Windows Excel
Sheet.
(5) To complement data accuracy, the consultant will visit at least two (2)
district roads per region for site surveying.
B: Investigations of Local
Government Authorities
(LGA’s) Capability
(1) The Consultant shall reviews the District Capability of Dodoma and Iringa
regions. Both regions have 6 and 4 councils respectively.
(2) Items of review of the assignment are following;
Personnel (name, affiliation, employee code, date of birth, etc.)
Organization (address, chart, number, name and positions of staff,
etc.)
Position (position name, description, responsibility, salary level, etc.)
Annual budget (financial statements, balance sheets, annual/last five
year, breakdown of components), depends upon the availability of
the respective data.
Project (project name, description, date from, date to, site, length,
surface type, etc.)
Construction Method (type of works‐planning, required equipment;
etc.)
Training (name of training; objective, affiliation of participants, etc.)
Registered contractors (CRB registration firms, registration record)
Plants and equipment for road works (name, number, managed by,
date of purchase, condition) (if any)
(3) Review works will be done through the district’s annual report and other
documents. Those reports can get available at the each Regional
Secretariat Engineer (RSE) office or PMORALG head quarter office at
Dodoma.
(4) The Consultants shall compile reviewed data on the Windows Excel Sheet.
(5) To complement data accuracy, the consultant will visit and interview at
least two districts offices per region for Surveying.
C: Investigations of
Districts Local Contractors
Capability
(1) The Consultant shall reviews the Council’s Local Contractor Capability of Dodoma and Iringa regions. Both regions have 6 and 4 councils
respectively.
(2) Items of review of the assignment are as follows;
Personnel (name, affiliation, employee code, date of birth, etc.)
Organization (address, chart, number, name and positions of staff,
etc.)
91
Position (position name, description, responsibility, salary level, etc.)
Annual income (financial statements, balance sheets, annual/last five
year, breakdown of components), depends upon the availability of
the respective data.
Machinery and equipment owned (name, number, date purchased,
condition)
Project (project name, description, date from, date to, site, length,
surface type, etc.)
(3) Review works will be done through the district’s annual report and other documents. Those reports can get available at the each Regional
Secretariat Engineer (RSE) office or PMORALG head quarter office at
Dodoma.
(4) The Consultants shall compile the reviewed data on the Windows Excel
sheets.
(5) To complement data accuracy, the consultant will visit and interview at
least 2 district offices in two Regions.
D: Reporting (1) The Consultants shall submit survey report based on compile review’s
data. The report shall contain “Introduction of the Project”, “Methodology
of the Survey”, “The summary of the collected data”, “Conclusion and
remarks”, and Appendix with references.
(2) The report should be submitted one week after the completion of the
survey.
(3) The report requires three (3) hard copies with compellation and one (1)
soft copy for data file.
5.4. Modification of the PDM
As the need to modify PDM1 was agreed on the RD, PDM2 was developed through the confirmation
of the following points during the 1st JCC meeting (JCC-1) in the first year (refer to Annex 1 for the
differences between PDM1 and PDM2). The indicators were set up based on the results of the baseline
survey, targets of the Annual Performance Agreement, etc. In July 2014, PDM3 was also developed
during JCC-3; the identified target indicators were set up for the disseminated districts. In addition,
through the experiences of the project monitoring activities, the Project recognized that it is possible to
obtain all the indicators through the monitoring system without an impact survey.
5.5. Training in Japan
The Project conducted training in Japan from 23/August to 10/September 2014. The purposes of the
training are as follows;
Understand the mechanism of rural road maintenance administration
Understand rural road maintenance works in local government (inventory survey, mid-long term
plan, prioritization, annual plan, monitoring, etc.)
Acquire rural road evaluation system in local government
Understand the process of participatory road maintenance works (procurement and construction
control process)
Understand the trial of “Local Rules” (1.5 lane etc.) which adjusts for local needs, low traffic
92
volume
Acquire effective maintenance technology relating to rural roads (Do-nou technology etc.)
Table 5-4 Member of the Study Tour in Japan
5.6. Public Relations
The Project occasionally published “News Letters” on the JICA homepage website. The Project News
Letters highlighted the activities and progress of the Project. PMO-RALG and the Project also had the
opportunities to present the Project’s activities at the ILO international seminar in Cameroon in 2014,
and in Benin in 2015. The ILO international seminar is regarding the LBT participants. In October
2015, the executive engineer of PMO-RALG had a presentation at the seminar, and it attracted the
participants.
Participants for the ILO seminar in Benin Eng.Nanai/PMO‐RALG presented in the seminar
Figure5-1 Photos of ILO International Seminar in Benin 2015
No Name Title Organization
1 Hassan Swalehe MatimbeAssistant Director of
Urban RoadMOW (Ministry of Works)
2 Ezron Charles Kilamhama Principal EngineerInfrastructure Development Unit
PMO‐RALG
3 Justin Mathew Lyatuu EconomistInfrastructure Development Unit
PMO‐RALG
4 Daudi Sweke Lucas Principal EngineerInfrastructure Development Unit
PMO‐RALG
5 David Michael Mwakalalile RSE Iringa Region
6 Mohamed Musa Mkwata RSE Dodoma Region
7 Asel Yesaya Kajange Engineer Iringa DC
8 Baraka Sururu Munissi Technician Iringa DC
9 Mpinzile Godwin Samwel DE Chamwino DC
10 Shama Saidi Amanzi Technician Chamwino DC
93
6. Issues, Contrivance, and Lessons Learned
The issues, contrivance, and lessons learned from the project operation are summarized as follows.
6.1. Lessons Learned from the Project Operation
(1) Ownership of the Tanzanian Counterpart
All the costs of operating the Project were absorbed by the Tanzanian side accordingly, as specified in
the Record of Discussion. PMO-RALG, the Regional Administrative Secretary and the model districts
were all cooperative and showed full ownership to operate the Project. In particular, which is
remarkable to note, the Operational Guidelines were produced by the initiative of the Tanzanian
counterpart, and the model districts covered all the costs of the pilot projects by utilizing the limited
resources of the Road fund. PMO-RALG also had the responsibility to secure the personnel required
by the Project. The ownership of the Tanzanian counterpart will be contributed to sustain the outputs
from the Project.
(2) Attract Engineers and Technicians through New Technologies
Through the operation of the technical training, the Project found that engineers and technicians were
attracted by the introduction of new technologies and new techniques. The new technologies or
techniques, such as GPS/GIS, Mapping, Hydrological Survey, and Structure Planning empowered the
participants. Mostly the technical training was designed with two parts: one for training in the office
through a series of lectures, and the other on site. Both contributed to the training being more practical.
The engineers and technicians are sincere and willing to acquire the new technologies. Some of the
engineers stayed late in the office to solve their issues by utilizing the new technologies, and others
visited the Experts during the weekends for additional training. The tools such as GPS receiver or
drive recorder introduced in the training course, also contributed to improving their efficiency.
(3) Insufficient Number of Equipment
1) GPS
GPS is an effective tool for inventory surveys. It remarkably improves the efficiency of measuring
road length. Although the Project provided GPS units to the model and disseminated districts, the
number of GPS was insufficient, i.e., only one respectively. Due to the insufficient number of GPS
units, the inventory survey took a long time to complete. It is recommended to secure at least two GPS
units for the districts to enhance the practical utilization of GPS.
2) PCs for Data Accumulation
The districts engineers and technicians normally use their own PCs for their work. There is no main
server to accumulate all the data of each district. Due to the risk of damage to one PC, or personnel
leaving after being assigned to another position, data accumulation in the districts is not secured. The
Project proposed securing of one main PC in each district to ensure safe data accumulation.
94
3) LBT Equipment
The Project procured a set of LBT equipment for each of the two model districts. As mentioned in the
lessons learned from the model districts, one set of LBT equipment is insufficient to encourage LBT
works for up to 20 % of all annual road works in the districts, as defined in APA (Annual Performance
Agreement). In addition, the LBT leasing system that the Project trialed, founded to share the LBT
equipment among the LBT contractors was not practical. This is because all the LBT contractors had
to implement the road works more or less at the same time, as contracted. Delay in LBT works due to
leasing LBT equipment at one site caused delays in LBT works at another site.
As mentioned in Chapter-1, it is recommended to clarify that the LBT leasing system shall be
managed by the districts while the accounting shall be the responsibility of the regions. Transferring
the accounting management to the regions will enable acceleration of financial income as funds from
the leasing system, thus making it possible to procure new equipment using the funds. The ideal
number of LBT equipment in each region is assumed to be half of the total number of districts in the
region, i.e., two sets of LBT equipment required for a region with four councils. In order to realize this,
a cost of around 100,000 to 130,000 USD per one set of LBT equipment is estimated, including
transport, spare parts and initial training. In view of the current budget in Tanzania for regional
administration, it is preferable that the Japanese side provides the equipment.
6.2. Lessons Learned from the Capacity Development
(1) Development of AMTC
The Project has developed the dissemination system of the project outputs as AMTC. It aims to
improve the administrative capacity of the disseminated districts by sharing the lessons learned from
the application of the Operational Guidelines, by transferring the technical skills from the model
districts. AMTC enables RSEs to monitor and instruct the practical procedure of the LGAs on a
quarterly basis, according to the Operational Guidelines. This regular monitoring by RSEs shall
contribute to improving the administrative capacity of LGAs, thus AMTC is developed as the
approach to attain the project purpose.
(2)Technical Training
As described in Chapter-3, there remains a serious need for technical training, in particular, on road
structure design and drawings. These technical skills, using software and tools, contribute to
significantly improving the effectiveness of the rural road works in the districts. PMO-RALG
requested the provision of further technical training by the Project, when the mid-term review team
evaluated the progress. It shows the high level of motivation of the engineers and technicians for the
acquisition of the technical skills. With respect for this request from the Tanzanian side, the Project
could not reach the level of their satisfaction due to the limited assignment of technical experts.
Providing further technical training to meet the requirement of Tanzania should have been
incorporated in the Project activities.
95
(3) Integration of Data, Standardize Operation System
As mentioned above, road data and information are managed individually in the districts. The Project
proposed to PMO-RALG the integration of road data, but it is still inactive due to the current
Government regulation for document numbering and the filing system.
Regarding the PC operation system, it varies from personnel to personnel. In the technical training of
QGIS, which requires downloading free software, some engineers succeeded in downloading the latest
version of January 2016 in Windows 7, while others were unable to download in Windows 8 or 10.
Moreover, DROMAS-2 has the aim to integrate the accumulation of rural road data and information in
all LGAs. To realize this, it is recommended to standardize the PC operation system in the districts.
(4) Assignment of Monitoring Expert
The Project assigned an expert for the monitoring. This assignment enabled regular monitoring of the
progress and achievement of the project. The results of the monitoring were shared among all the
counterparts during the regular meetings or JCC meetings. The introduction of monitoring forms and
the monitoring system contributed to visualizing the impacts of the pilot project on the community.
The results of the questionnaire to the contractors were also analyzed and shown in terms of the
percentages of their capacity of supervision. It seems that all of the experience is impressive for the
districts, as monitoring used to be only by the percentage of budget utilized, the quality of the works,
and the number of road works completed.
6.3. Lessons Learned from the Dissemination of the Output
(1) Collaboration to JOCV (Japan Overseas Cooperation Volunteers)
The Project collaborated with JOCV in the dissemination process. JOCV in the sector of public
administration was assigned in the disseminated districts, in Kondoa DC and in Mufindi DC. The
disseminated districts are in charge of transferring outputs from the model districts through AMTC. As
the experts normally stayed in the model districts, in Dodoma and in Iringa, the progress of the
dissemination has been mainly monitored by JOCV. As the assignment of JOCV was in the works
department of the disseminated districts, it was sometimes required to monitor the progress technically.
It seems difficult for JOCV to monitor the progress and issues technically. The collaboration with
JOCV shall be reviewed to assign those with appropriate experience and knowledge.
(2) Improvement of AMTC
It is essential for PMO-RALG to stabilize the outputs of the Project in the two model regions through
AMTC. The dissemination and stabilization of the contents of the Operational Guidelines shall be
approached to the overall goal of the Project. The lessons learned from the RSEs include some
proposals to improve AMTC regarding topic and timing.
As of the middle of February 2016, the sustainable securement of the budget for operating AMTC is
96
undefined. PMO-RALG is required to improve the AMTC with the consideration mentioned by the
RSEs, and secure the budget for operating AMTC.
(3) Institutional Enhancement of RSEs
It is crucial to secure the appropriate number of qualified RSEs. This point was mentioned in the
mid-term review and the terminal evaluation. In most of the region, the RSE is the only personnel
assigned. PMO-RALG, in this regard, requested the human resource department to increase the
number of qualified RSEs. By January 2016, additional assignment of RSEs had been conducted in
several regions out of the 28 in total. The further progress of the institutional enhancement of RSEs
shall be expected.
PMO-RALG was transferred from the “Prime Minister’s Office” to the “President’s Office (referred to
as PO-RALG)” in January 2016. The Infrastructure unit was reformed in PO-RALG to three divisions:
Urban, Rural, and Research Centre. The total number of engineers in the Infrastructure division has
exceeded 20 so far. This institutional enhancement reflects the importance of infrastructure
development in Tanzania. The Project team has the privilege of operating the project for rural road
development in these circumstances.
97
7. Recommendation for Further Action
The overall goal, project purpose and outputs are listed as follows.
Overall Goal: The rural road maintenance procedure and services of LGAs in Dodoma and Iringa
regions are improved
Project Purpose: Administrative services of rural road maintenance provided by LGAs are
improved in the target areas, and its nationwide expansion approach is developed
Output-1: The capacity of PMO-RALG for coordinating and supporting LGAs in
collaboration with MOW on rural road maintenance is strengthened.
Output-2: The rural road maintenance procedure of the LGAs is strengthened in the
model districts.
Output-3: The practical skills and knowledge of responsible organizations (concerned
departments of the LGAs, contractors, etc.) on rural road maintenance are
improved through the LBT application in the model districts
Output-4: The dissemination mechanism for rural road maintenance approach within
the respective regions is established
The Road Map after the Project completion was presented by PMO-RALG in JCC-5. The Project
recommends the following as the conclusion of the Project, to encourage the steady progress of the
Road Map by the Tanzanian side.
7.1. Implementation of the Road Works to achieve the target value of the Overall Goal
The following three indicators are confirmed for the overall goal in Dodoma and Iringa regions.
Regarding the indicator for the annual plan of the districts (as described in indicator-1 below),
PMO-RALG is required to identify whether it is ng the annual plan proposed by the Project, or the one
for DROMAS-2 by August 2016, when PMO-RALG will reports the summary of the achievements of
outputs in FY 2015/2016 to the JICA Tanzania Office.
Table 7-1 Indicators and the means of verifications for the Overall Goal
Indicator-1: Annual Rural Road Maintenance Plans prepared by the LGAs of the respective
regions containing necessary items based on the checklist (means of verification from Form-4 in
the monitoring system)
Indicator-2: The percentage of the road maintenance works completed by contractors (including
defect liability period) for all the maintenance works in the Plan is increased within the fiscal year
in the respective regions. (means of verification from Form-5 in the monitoring system)
Indicator-3: The maintenance status (Good, Fair, and Poor) of rural roads is improved in the
respective regions. (means of verification from Form-1 in the monitoring system)
98
In order to measure the achievements based on the indicators, it is necessary to utilize the monitoring
forms mentioned above. The Project has conducted the monitoring workshop occasionally, thus all the
C/P have mastered the utilization of the monitoring forms. PMO-RALG and RSEs are required to have
the responsibility to instruct the model and disseminated districts to measure the achievement based on
the indicators in FY 2015/2016.
7.2. Standardization of AMTC
AMTC has been designed in accordance with the quarterly monitoring cycle of RSEs. It aims to
monitor and instruct the administrative procedure of each work stages in the model and disseminated
districts. Through the standardization of AMTC, the monitoring activities of RSEs shall be enhanced.
In addition, it is expected not only for the model and disseminated districts, but also the rest of the
districts in the model regions, to improve the administrative procedure of the road works through
AMTC. Thus, PMO-RALG and RSEs are required to operate AMTC continuously to achieve the
overall goal even after the project‘s completion.
To realize the sustainable operation of AMTC, PMO-RALG is required; (1) to utilize the Operational
Guidelines, (2) to produce and improve the practical materials through the lessons learned from RSEs
and the model districts, (3) to secure sufficient budget and assignment for RSEs to enable quarterly
monitoring, and (4) to ensure funds for the model districts, i.e., to cover allowance and transport costs.
The Project expects PMO-RALG to encourage RFB to secure the necessary funds to operate AMTC.
7.3. Utilization of the Operational Guidelines, LBT Specification Guidelines
The Operational Guidelines, which are produced in the Project, are essential to check the appropriate
procedures and to meet audit requirements. Ensuring the utilization of the Operational Guidelines shall
contribute to improving the administrative capacity of rural road works. Therefore, the Operational
Guidelines are required to be sustainably fruitful through updating or revising when necessary.
LBT technical specification guidelines, which are also produced in the Project and named “Guidelines
for Labour Based Road Work in LGAs,” are expected to promote LBT construction in the LGAs.
Applying these technical guidelines will enable the LGAs to meet the requirements of the technical
audit. The Project recommends that PMO-RALG encourages the utilization of the LBT technical
specification guidelines in the LGAs through an announcement from time to time, such as on
Engineers Day.
7.4. Promoting Effective Use of the Monitoring Forms
As described in Section 7-1 above, the Project has been carried out to monitor the achievements based
on the indicators. The monitoring system that the Project trialed is the feasible tool to manage any
project in the road works. The engineers, both in the regions and the model and disseminated districts,
are capable of doing data analysis with Excel spreadsheets. The Project proposes to promote the
effective use of monitoring forms even after the Project is completed.
99
7.5. Providing Technical Training Sustainably
The road classification of “Good,” “Fair” and “Poor” in the Operational Guidelines is defined as
referring to the definition of TANROAD. It is, however, not always applicable to rural roads. It was
modified to apply the IRI (International Roughness Index) as described in ADRICS. In practice during
the inventory survey, the Project found that how the roughness was defined depended on how one
inspects subjectively. It is one of the critical examples in rural road administration in Tanzania.
Currently, there are a number of issues, such as insufficient reliability of the road data, lack of data
accumulation, inadequate criteria to classify, technical gaps between engineers, and inadequate funds
for supervision.
To overcome those challenges, the Project recommends that PMO-RALG effectively uses the limited
resources, as well as invite Development Partners to support their challenges. JICA has long history
and experience to contribute to capacity development of the infrastructure sector through technical
cooperation in Tanzania. It is supposed that JICA is the most appropriate to provide continuous
support in order to overcome the challenges as one of the pioneer partners for rural road maintenance
in Tanzania.
7.6. Continuous Trial of LBT Equipment Leasing System
During the Project implementation, leasing system of LBT equipment in the model districts was
developed. The system was aimed to support LBT contractors due to limited number of construction
equipment in the market. The system shall contribute to increase LBT works in LGAs. The Project
request PMO-RALG and RSEs to monitor the achievement of the leasing system for future benefit of
rural road maintenance especially LBT method.
0
ANNEXES
Annex‐1
Annex‐1
: PDM‐1 (1
1‐Dec‐2
011)
Annex‐2
Annex‐3
Annex‐1
: PDM‐2 (4
‐Oct‐2
013)
Annex‐4
Annex‐5
Annex‐1
: PDM‐3 (2
4‐Ju
ly‐2014)
Annex‐6
Annex‐1
: PDM‐3 (2
4‐Ju
ly‐2014)
Annex‐7
Annex‐2
: PO fo
r the P
roject (20
12 ‐ 2
016)
Note:The schedules described in this chart are subject to modifications through further discussions in future.: To complete project activities within the solid line.: To continuously conduct project activities during the dotted line.: To conduct workshops, documentation, etc.
OUTPUT 4. The dissemination mechanism for rural road maintenance approach within the respective regions is established.
4-1 Organize sensitization workshops on rural road maintenance for the other LGAs in the respective regions in collaboration with the RSengineers.
・ RS and District Engineers
・ Team Leader, Capacity Building, Training Planning (JICA)
4-5 Feed back the monitoring results into the guidelines.・ Director of TID, PM O-RALG
・ RS Engineers
・ Team Leader, Construction/Contract M anagement (JICA)
4-2 Select a LGA to be disseminated in the respective regions.・ Director of TID, PM O-RALG
・ RS and District Engineers
・ Team Leader, Capacity Building, Monitoring (JICA)
4-3 Assist the LGAs selected in the respective regions to promote rural road maintenance based on the guidelines with the full commitments ofRS engineers.
・ RS Engineers
・ Team Leader, LBT, Construction/Contract M anagement (JICA)
4-4 Monitor the rural road maintenance promoted by the LGAs in the respective regions.・ Director of TID, PM O-RALG
・ RS Engineers
・ Team Leader, Construction/Contract M anagement (JICA)
3-2 Formulate work plans of the pilot projects.・ District Engineers
・ Team Leader, LBT, Light Equipment M anagement (JICA)
3-3 Assist district engineers and technicians in the model districts to procure contractors and supervise the pilot projects based on the workplans.
・ District Engineers
・ Team Leader, LBT, Light Equipment M anagement (JICA)
3-4 Provide consultations on the operation of the pilot projects for the district engineers and technicians, contractors, etc. through ATTI.・ District Engineers
・ Team Leader, LBT, Light Equipment M anagement (JICA)
3-5 Promote PR activities on rural road maintenance through the pilot projects.・ RS and District Engineers
・ Team Leader, Capacity Building, Training Planning (JICA)
3-6 Document the process, experiences, outcomes, and lessons learned of the pilot projects.・ Director of TID, PM O-RALG
・ District Engineers
・ Team Leader, LBT, Capacity Building (JICA)
2-6 Confirm the needs of rural road maintenance in the model districts and prioritize the needs.・ District Engineers
・ Team Leader, Construction/Contract M anagement (JICA)
2-7 Prepare the annual rural road maintenance plans, including procurement, construction method, etc., in consideration of gender aspects in themodel districts.
・ District Engineers
・ Team Leader, Construction/Contract M anagement (JICA)
2-8 Monitor the rural road maintenance in the model districts.・ Director of TID, PM O-RALG
・ District Engineers
・ Team Leader, Construction/Contract M anagement (JICA)
OUTPUT 3. The practical skills and knowledge of responsible organizations (concerned departments of the LGAs, contractors, etc.) on rural road maintenance are improved through the LBT application in the model districts.
3-1 Select pilot projects in the model districts from the annual rural road maintenance plan.・ Director of TID, PM O-RALG
・ RS and District Engineers
・ Team Leader, Construction/Contract M anagement, LBT (JICA)
2-1 Select model districts based on the criteria established.・ Director of TID, PM O-RALG
・ RS Engineers
・ Team Leader, Capacity Building, Monitoring (JICA)
2-2 Review the current activities done by technical staff in the model districts.・ RS Engineers / District Engineers
・ Team Leader, Construction/Contract M anagement, Light Equipment Management, Capacity Building (JICA)
2-3 Provide training on rural road maintenance for the district engineers and technicians in the model districts.・ RS Engineers
・ Team Leader, Capacity Building, Training Planning (JICA)
2-4 Prepare and update the rural road inventories in the model districts.・ District Engineers
・ Team Leader, Construction/Contract M anagement (JICA)
2-5 Prepare and revise a mid- and long-term rural road maintenance plan.・ District Engineers
・ Team Leader, Construction/Contract M anagement (JICA)
1-1 Convene regular meetings on operational guidelines development for rural road maintenance with PMO-RALG and MOW.・ Director of TID, PM O-RALG
・ Director of RR, MOW
・ Construction/Contract Management (JICA)
1-2 Prepare and revise operational guidelines of rural road maintenance with PMO-RALG and MOW.・ Director of TID, PM O-RALG
・ Director of RR, MOW
・ Construction/Contract Management (JICA)
1-3 Share the contents of the guidelines and the lessons learned from LGAs in the model districts during the Annual Meeting between PMO-RALG and RS and District Engineers.
・ Director of TID, PM O-RALG
・ Construction/Contract Management (JICA)
1-4 Assist RS engineers to monitor rural road maintenance in LGAs based on the guidelines.・ Director of TID, PM O-RALG
・ Construction/Contract Management (JICA)
OUTPUT 2. The rural road maintenance procedure of the LGAs is strengthened in the model districts.
Documentation and submit the Work Plan・Director of TID, PMO-RALG
・Team Leader, Sub-Leader (JICA)
Documentation of Mid-term Progress Report・Director of TID, PMO-RALG
・Team Leader, Sub-Leader (JICA)
Procedure of Provision of Equipment・Director of TID, PMO-RALG
・Team Leader, Light Equipment Management (JICA)
Conduct the baseline survey・ Director of TID, PM O-RALG
・ Team Leader, Capacity Building, Monitoring (JICA)
OUTPUT 1. The capacity of PMO-RALG for coordinating and supporting LGAs in collaboration with MOW on rural road maintenance is strengthened.
Joint Coordinating Committee(JCC)・ Director of Transport Infrastructure Development (TID), PM O-RALG
・ Director of Rural Roads (RR), M OW
・ Team Leader (JICA)
Mid-term Review and Terminal Evaluation
・ Director of TID, PM O-RALG
・ Director of RR, MOW
・ Team Leader, Monitoring (JICA)
44 45 46 47 48 4935 36 37 38 39 40 41 42 4326 27 28 29 30 31 32 33 3417 18 19 20 21 22 23 24 25Total month 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
9 10 11 12 1 2 312 1 2 3 4 5 6 7 83 4 5 6 7 8 9 10 116 7 8 9 10 11 12 1 2Year Y2012 Y2013 Y2014 Y2015 Y2016
Responsible persons/organizationsMonth 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5
Mid-term Review Terminal Evaluation
Annex‐8
Annex‐3
: RMSD
Expert Team
Assign
ment
Japanese Exp
ert Assign
ment (M
arch 2012 – M
arch 2016)
MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR Tanzania Japan
Plan
Actual14 44 77 75 89 63 32 46 68 30 30
18.47 1.45
Plan
Actual
Plan
Actual75 47 94 66 33 66 23 8 27 45 12
16.53 0.00
Plan
Actual
Plan
Actual60 50 45
5.17 0.00
Plan
Actual60 34 44
4.60 0.00
Plan
Actual48 50
3.27 0.00
Plan
Actual54 46 15
3.83
Plan
Actual48 43 45 44 45 30
8.50 0.50
Plan
Actual60 55 75 45 45
9.50 0.00
Plan
Actual60 60 34 61
7.17 0.00
Plan
Actual45 20 45 45 33 36 38 36
10.17 0.00
Plan
Actual30 60 45 45 45 58 40 40 42
13.50 0.00
Plan
Actual72 30 30
4.40
105.10 1.95
Total Plan
Actual
The 2nd Contract Year
2015 2016
MonitoringTakaaki
HIRAKAWA
Coordinating/Training
Planning
Yumiko
TAKEDA
Coordinating/PRGo
EBISU
Construction/Contract
Management
Kenko
OKAMURA
Light Equipment
Management
Masanori
TAKEISHI
Capacity BuildingKazunobu
KAMIMURA
LBT
(Design/Structure)
Hirokazu
MIYAMOTO
LBT
(Maintenance/Qualit
y Control)
Noboru
SHIMIZU
Road DesignIkumasa
KAWASAKI
LBT
(Maintenance/Qualit
y Control)
Masahiko
NISHIDA
Team Leader/Road
Maintenance
Tatsumi
TOKUNAGA
by March
2015Motoki
OGAWA
from April
2015
Sub Leader/Rural
Road
Planning
Motoki
OGAWA
by March
2015Tatsumi
TOKUNAGA
from April
2015
MM
The 1st Contract Year Total
Achievement of Inputs (HumanResource Allocation/ Japanese side)
Name of Title Name
2012 2013 2014
Annex‐9
Annex‐4: Monitoring System(Annex:4‐1), Monitoring Manual(Annex:4‐2)
Annex‐10
Annex‐1
1
Annex‐1
2
Annex‐1
3
Annex‐1
4
Annex‐1
5
Annex‐16
Annex‐17
Annex‐1
8
Annex‐1
9
Annex‐2
0
Annex‐2
1
Annex‐22
Annex‐2
3
Annex‐2
4
Annex‐2
5
Annex‐26
Annex‐27
Annex‐2
8
Annex‐2
9
Annex‐30
Annex‐3
1
Annex‐3
2
Annex‐3
3
Annex‐34
Annex‐35
Annex‐36
Annex‐37
Annex‐38
Annex‐39
Annex‐40
Annex‐41
Annex‐42
Annex‐43
Annex‐44
Annex‐45
Annex‐46
Annex‐47
Annex‐48
Annex‐49
Annex‐5: Equipment
1 7‐Sep‐12 Printer HP Laser Jet M1212nf MFP 1 730,000 TshRAL Computer
StoreExpert
Means of
Documentation
Iringa DC
OfficeExpert
2 5‐Mar‐13 Scanner HP M1536mfp 1 980,000 TshRAL Computer
StoreExpert
Means of
Documentation
Chamwino
DC OfficeExpert
3 28‐Mar‐13Camera
Memory
Sony DSC‐Hxbr
Fuji Firm Memory 2GB1 840,000 Tsh ANISUMA C/P
Recording Project
Activities
Iringa DC
OfficeIringa DE
4 21‐Jun‐13Camera
Memory
PENTAX Optio WG‐2GPS
Transcend SDHC 16GB1 22,997 JPN Amazon C/P
Recording Project
Activities
Chamwino
DC Office
Chamwino
DE
5 17‐Jun‐13 TractorNew Holland 8030
ZCCA03067 CW 66581 76,000 USD
General Motors
Investment (GMI)C/P
For Project
Activities
Chamwino
DC Garage
Chamwino
DE
6 17‐Jun‐13Pedistrian
Vivratory Roller
Sakai
HV801 18,508 USD
Panafrican
EquipmentC/P
For Project
Activities
Chamwino
DC
Chamwino
DE
7 17‐Jun‐13 Plate CompactorSakai
PC8001 6,905 USD
Panafrican
EquipmentC/P
For Project
Activities
Chamwino
DC
Chamwino
DE
6 17‐Jun‐13Engine Suction
Water PumpWP 30X 1 500 USD GMI C/P
For Project
Activities
Chamwino
DC Garage
Chamwino
DE
8 18‐Jun‐13Tractor
Maintenance Parts7,600 USD GMI C/P
For Project
Activities
Chamwino
DC Garage
Chamwino
DE
9 18‐Jun‐13Water Pump
Maintenance Parts50 USD GMI C/P
For Project
Activities
Chamwino
DC Garage
Chamwino
DE
10 18‐Jun‐13Transport Cost to
Site in Chamwino2,850 USD GMI C/P
For Project
ActivitiesChamwino
Chamwino
DE
11 18‐Jun‐13Training Cost at
Site in Chamwino300 USD GMI C/P
For Project
ActivitiesChamwino
Chamwino
DE
12 20‐Jun‐13 TractorNew Holland 8030
ZCCA02721 CW 66571 76,000 USD GMI C/P
For Project
ActivitiesIringa DC Iringa DE
13 17‐Jun‐13Pedistrian
Vivratory Roller
Sakai
HV801 18,508 USD
Panafrican
EquipmentC/P
For Project
ActivitiesIringa DC Iringa DE
14 17‐Jun‐13 Plate CompactorSakai
PC8001 6,905 USD
Panafrican
EquipmentC/P
For Project
ActivitiesIringa Iringa DE
15 20‐Jun‐13Engine Suction
Water PumpWP 30X 1 500 USD GMI C/P
For Project
Activities
Iringa DC
GarageIringa DE
16 20‐Jun‐13Tractor
Maintenance Parts1 7,600 USD GMI C/P
For Project
Activities
Iringa DC
GarageIringa DE
17 20‐Jun‐13Water Pump
Maintenance Parts1 50 USD GMI C/P
For Project
Activities
Iringa DC
GarageIringa DE
18 20‐Jun‐13Transport Cost to
Site in Iringa1 2,850 USD GMI C/P
For Project
ActivitiesIringa Iringa DE
19 20‐Jun‐13Training Cost at
Site in Iringa1 300 USD GMI C/P
For Project
ActivitiesIringa Iringa DE
20 20‐Jun‐13 Water BowserGMI/WB/00001
CW 66591 18,000 USD GMI C/P
For Project
Activities
Iringa DC
GarageIringa DE
21 20‐Jun‐14 GPS eTrex 30 1 28,483 JPN IDA/Japan C/PFor Project
ActivitiesIringa DC Iringa DE
22 20‐Jun‐14 GPS eTrex 30 1 28,483 JPN IDA/Japan C/PFor Project
ActivitiesIringa RS Iringa RSE
23 20‐Jun‐14 GPS eTrex 30 1 28,483 JPN IDA/Japan C/PFor Project
Activities
Chamwino
DC
Chamwino
DE
24 20‐Jun‐14 GPS eTrex 30 1 28,483 JPN IDA/Japan C/PFor Project
ActivitiesDodoma RS Dodoma RSE
25 20‐Jun‐14 GPS eTrex 30 1 28,483 JPN IDA/Japan C/PFor Project
ActivitiesKondoa DC Kondoa DE
26 20‐Jun‐14 GPS eTrex 30 1 28,483 JPN IDA/Japan C/PFor Project
ActivitiesMufindi DC Mufindi DE
27 20‐Jun‐14 GPS CameraRicoh WG‐4 GPS
Toshiba SDHC 16GB1 35,890 JPN Yodobashi/Japan C/P
For Project
ActivitiesIringa RS Iringa RSE
28 20‐Jun‐14 GPS CameraRicoh WG‐4 GPS
Toshiba SDHC 16GB1 35,890 JPN Yodobashi/Japan C/P
For Project
ActivitiesDodoma RS Dodma RSE
29 20‐Jun‐14 GPS CameraRicoh WG‐4 GPS
Toshiba SDHC 16GB1 35,890 JPN Yodobashi/Japan C/P
For Project
ActivitiesKondoa DC Kondoa DE
30 20‐Jun‐14 GPS CameraRicoh WG‐4 GPS
Toshiba SDHC 16GB1 35,890 JPN Yodobashi/Japan C/P
For Project
ActivitiesMufindi DC Mufindi DE
31 20‐Jan‐15 Projector Epson EB‐S18 1 850,000 TshCLOUD
COMPUTERSC/P
For Project
ActivitiesDodoma RS Dodoma RSE
32 20‐Jan‐15 Projector Epson EB‐S18 1 850,000 TshCLOUD
COMPUTERSC/P
For Project
ActivitiesIringa RS Iringa RSE
Provider User Purpose of Use Place of UseResponsible
PersonNumber
Date of
registration
Description/Name of
equipment / GoodsSpecification ・Standard QTY Price unit
Annex‐50
Annex‐6: JCC
JCC‐4 Agenda
Rural roads Maintenance System Development Project (RMSD) PRIME MINISTER’S OFFICE REGIONAL ADMINISTRATION AND LOCAL
GOVERNMENT (PMO-RALG) JAPAN INTERNATINAL COOPERATION AGENCY (JICA)
4rdJoint Coordination Committee on 20th August 2015 Conference Room, PMO-RALG Agenda: 4rd JCC Meeting Part 1: Progress and Achivement of the Project
Time Agenda Responsible Remarks
09:00 - 09:10 Opening
Chairperson/PS
PMORALG 5 min
JICA Chief
Representative 5 min
09:10 - 10:00 Presentation of the Progress and
Achievement of the RMSD Project
Eng Nanai/
Eng. Mpinzile, Eng.
Runji
50 min
10:00-10:45 The wayforward to Disseminate the
Progress
Eng. Nanai/
Eng. Mkwata/
Eng. David
45 min
10:45 - 12:00 Discussions All 75 min
12:00-12:05 Closing remarks PMO-RALG 5 min
12:05-13:00 Lunch
Annex‐51
Rural roads Maintenance System Development Project (RMSD)
PRIME MINISTER’S OFFICE REGIONAL ADMINISTRATION AND LOCAL GOVERNMENT (PMO-RALG)
JAPAN INTERNATINAL COOPERATION AGENCY (JICA) RMSD Terminal Evaluation Meeting on 21th August 2015 Conference Room, PMO-RALG Agenda: RMSD Terminal Evaluation Meeting and JCC-4 Part 2 on 21th August 2015
Time Agenda Responsible Remarks
09:00 - 09:10 Opening
Chairperson/PS
PMORALG 5 min
JICA Chief
Representative HQ 5 min
9:10- 10:00 Terminal Evaluation Report
Joint Evaluation Team
(JICA Evaluation
Team / PMORALG)
50 min
10:00 – 10:30 Break All
10:30 -12:00 Discussions All 90 min
12:00-12:15 Sign on M/M JICA
PMO-RALG 15 min
12:15 Closing remarks PMO-RALG
Annex 52
JCC 4 Participants
Annex‐53
JCC‐5 Agenda
Rural roads Maintenance System Development Project (RMSD) PRESIDENT’S OFFICE REGIONAL ADMINISTRATION AND LOCAL
GOVERNMENT (PO-RALG) JAPAN INTERNATINAL COOPERATION AGENCY (JICA)
5th Joint Coordination Committee on 23th February 2016 Conference Room, Protea Court Yard Hotel, Dar es Salaam Agenda: 5th JCC Meeting and RMSD Terminal Seminar
JCC-5 Final Time Agenda Responsible Remarks
09:00 - 09:10 Opening Chairperson/PS PORALG 5 min
JICA Chief Representative 5 min
09:10 - 09:40 Achievement of the RMSD Project Eng Nanai/PO-RALG 30 min
09:40 - 10:10
Achievement of the RMSD Project
and Lessons Learnt from the
Model Districts
Eng. Mpinzile/DE Chamwino
Eng. Runji/DE Iringa 30 min
10:10- 10:40 Lessons Learnt from AMTC in the
Disseminated Districts
Eng. Myaule /DE Kondoa
Eng. Johnson / DE Mufindi 30 min
Tea Break
11:00-11:30 The way forward to Disseminate
the Output in the Model Regions
Eng. Mkwata/ RSE Dodoma
Eng. Mwakalille /RSE Iringa 30 min
11:30-11:40 The Activities to be completed by
Tanzanian Side Eng Nanai/PO-RALG 10 min
11:40- 12:10 The Road Map to be attained the
Overall Goal Eng Kayanda/DID,PO-RALG 30 min
12:10-12:25
Summarization of the Project and
Proposal for the Future Action in
Tanzania
Dr. Tokunaga/JICA-RMSD 15 min
12:25 -13:20 Discussions All 55 min
13:20-13:25 Sign on MM PO-RALG/JICA-RMSD 5 min
13:25-13:30 Closing remarks PO-RALG 5 min
13:30-14:30 Lunch
Annex 54
JCC 5 Participants
Annex‐55
JCC-5 Meeting Minutes(tentative)
MINUTES OF THE MEETING BETWEEN
PRESIDENT’S OFFICE, REGIONAL ADMINISTRATION AND LOCAL GOVERNMENT AND
THE JAPAN INTERNATIONAL COOPERATION AGENCY FOR THE FINAL JOINT COORDINATING COMMITTEE (JCC‐FINAL)
IN THE RURAL ROAD MAINTENANCE SYSTEM DEVELOPMENT PROJECT (RMSD)
Dar es Salaam, 23 February, 2016
The Final Joint Coordinating Committee meeting (JCC‐Final) between members of
the President’s Office, Regional Administration and Local Government (hereinafter
referred to as “PO‐RALG”) and the Project Team organized by the Japan International
Cooperation Agency (hereinafter referred to as “JICA”) was convened on 23rd February,
2016 at the Protea Courtyard Hotel in Dar es Salaam for the purpose of concluding
the activities and achievements of “Rural Road Maintenance System Development
(RMSD) Project” (hereinafter referred to as “the Project”).
As a result of discussion, both sides agreed to the matters in the documents
attached hereto.
Eng. Musa Iyombe
Permanent Secretary
President’s Office
Regional Administration and Local Government,
The United Republic of Tanzania
Mr. Motoki OGAWA
Chief Adviser/ Team Leader
JICA‐Rural Road Maintenance System Development
Project
Annex‐56
Attached Document
Major Points Discussed
1. Achievements of the Project Activities PO‐RALG presented achievements based on the indicators during the Project
operation. The summary of lessons learned and the achievements in the model
districts, experience from Annual Maintenance and Training Cycle (AMTC) in the disseminated districts, and monitoring activities by Regional Secretariat
Engineers (RSEs) were presented respectively by the RMSD Project Team and
Counterparts. The Operational Guidelines for the District Roads maintenance have developed by the RMSD Project. Moreover, guidelines for LBT works in
LGAs have been drafted. Those guidelines will significantly contribute to the
improvement of rural road maintenance management in Tanzania. Regarding the dissemination of the Project output to other LGAs, RMSD has developed an
Annual Monitoring and Training Cycle (referred as AMTC) as a tool for
dissemination.
2. Activities remain after the Project period
Due to the delay of budget disbursement in FY2015/2016 which led to delayed implementation of pilot projects, some of the planned activities will not be
completed within the project period. Therefore, PO‐RALG, with the full of
ownership, shall implement the remaining activities as follows. The model and disseminated districts shall collect the data of FY2015/2016
for the indicators, and PO‐RALG shall report the summary of the
achievement based on the collected indicators to JICA around August 2016. PO‐RALG shall clarify the items in the proposed Project annual plan, which
shall be compatible to DROMAS‐2, if any.
3. Road Map to attain the Project Overall Goal
PO‐RALG expressed the appreciation to JICA for the technical assistance in the
sector of rural road in Tanzania. Majority of LGAs roads network in Tanzania are rural roads, whereby a number of issues and challenges are yet to be tackled so
as to improve rural roads condition. PO‐RALG presented the Road Map to
achieve the Overall Goal by building on the outputs from the first phase of the Project. The keywords for the Road Map are to improve “Cost‐effectiveness” in
maintenance approaches/strategies as well as to develop the “Appropriate
Annex‐57
Technology” that will improve rural road maintenance. The proposed outputs and activities under the Road Map are summarized as follows;
Project Purpose : Capacity Development for Rural Road Maintenance (Operational and Technical) in the five (5) selected regions
Outputs: Output‐1: Enhance the Institutional Capacity of PO‐RALG
Output‐2: Enhance the Operational Capacity of RSEs and Council
Engineers in five (5) regions Output‐3: Enhance the technical capacity in construction of Rural
Road, Develop Appropriate Construction technology for
Rural Road Maintenance Activities
<For Output‐1>
- Identify and prioritize capacity gaps, issues and challenges of rural road maintenance
- Convene stakeholder meetings to discuss and deliberate on the issues of
rural road maintenance - Support to modify the standards, manuals, guidelines of rural road
maintenance (e.g. Guidelines for bridge design for rural road )
<For Output‐2>
- All LGAs in Dodoma and Iringa regions to improve their
administrative/technical skills through AMTC - Five (5) regions and two (2) district councils from each region shall be
selected as the disseminated regions and councils to enhance their
administrative/technical skills through AMTC - RSEs and council engineers in those five selected regions and ten councils
shall be involved into AMTC based on Dodoma and Iringa regions for the
first two (2) years. After two (2) years, five (5) regions shall operate AMTC in their own regions while involving other neighboring regions as a national
wide dissemination mechanism.
- RSEs and council engineers in five (5) regions and ten (10) councils share the experience of the RMSD through AMTC in the Stakeholder Meeting (e.g.
LGAs’ Engineers Day)
Annex‐58
<For Output‐3> - Select the pilot site and appropriate construction technology in Dodoma
and Iringa regions
- Prepare the construction methods, design, procurement, contract - Procure set of LBT equipment for each of the five targeted regions and
introduce the LBT equipment leasing system
- Support the study in Research Centre for the appropriate surfacing method - Provide the study tour to the country which is familiar to the relevant
technology (Ghana, Kenya, Ethiopia etc.)
- Construct the demonstration rural road in Dodoma and Iringa (Implementation)
- Provide technical training during the construction including Equipment
operation and management - Provide technical Cost‐Benefit analysis of each construction technology
- Support the policy dialog and standardization/regulation of appropriate
technology to be utilized in the rural road maintenance.
4. Summary and Proposal from the JICA‐RMSD Team
The sub‐leader of RMSD summarized the current Project operation, and proposed further actions to approach the Road Map.
Utilization of the Operational Guidelines, LBT Specification Guidelines The Operational Guidelines are essential to monitor the appropriate procedures
to meet the requirement from the audit. To ensure the utilization of the
Operational Guidelines shall contribute to improve the administrative capacity of rural road works. Therefore, the Operational Guidelines is required to be
sustainably fruitful by updating or revising when it is necessary.
LBT technical specification guidelines are also expected to promote the use of LBT construction in the LGAs. Applying these technical guidelines will enable
LGAs to meet the requirement of the Annual Performance Agreement (APA)
between PO‐RALG and LGAs, which direct LGAs to deploy 20% of the maintenance activities for LBT wherever feasible. The Project recommends
PO‐RALG to encourage the utilization of the draft LBT technical specification
guidelines in the LGAs through the announcement from time to time, such as in the Engineers Day.
Standardization of AMTC AMTC has been designed in accordance with the quarterly monitoring cycle of
RSEs. It aims to monitor and instruct the administrative procedure of the each
road work stages in the model and disseminated districts. Before the
Annex‐59
production of the Operational Guidelines and the introduction of AMTC, RSEs had forced to supervise LGAs so many times to modify or correct the
documents required to submit to PO‐RALG. It is due to insufficient preparation
of the documents. It resulted in difficult to meet the requirement from the audit and inefficiency of monitoring works of RSEs. Through the utilization of
AMTC, the monitoring activities of RSEs shall be enhanced in both the
effectiveness and the quality. PO‐RALG and RSEs are required to operate AMTC continuously to achieve the overall goal even after the project completion.
To realize the sustainable operation of AMTC, PO‐RALG is required; (i) to utilize the Operational Guidelines, (ii) to produce and improve the practical materials
through the lessons learned from RSEs and the model districts, (iii) to secure
sufficient budget and assignment for RSEs to enable monitoring in quarterly basis, (iv) to ensure the fund for the model districts, i.e. allowance and the
transport cost. The Project expects PO‐RALG to encourage RFB to secure
necessary fund to operate AMTC.
LBT Equipment leasing system in Chamwino and Iringa DCs
During the project implementation leasing system in Chamwino and Iringa DCs was developed. Accordingly the APA (Annual Performance Agreement), LGAs
are supposed to implement LBT works as 20% of total rural road works. Most of
councils, however, it is difficult to implement LBT works up to 20% of total, partly because insufficient number of LBT equipment in the market. The trialed
leasing system of EBT equipment verified the model districts to accumulate the
cost for future replacement. It is supposed this leasing system contributes to increase the number of LBT works in LGAs. The project recommends PO‐RALG
and RSEs to continue the trial and to verify the benefit from it.
5. Commitment from PO‐RALG
1) Operational Guidelines and LBT Specification Guidelines
The Operational Guidelines were distributed to LGAs with the letter named by PS requested councils to activate it into rural road works. In the Stakeholder’s
Meeting, in Arusha August 2015, PO‐RALG and RMSD team shared the contents
of Operational Guidelines among the participants of 250 engineers. PO‐RALG, as a responsible organization, strongly commit LGAs to utilize the Guidelines
continuously, and monitor their utilization and feedback occasionally such as
Engineer’s Day in every year.
Regarding LBT Specification, it has drafted and ready to submit to MoW for the
approval. PO‐RALG has responsible to enable LGAs to fully utilize the Guidelines
Annex‐60
for their rural road work in order to ensure increasing number of LBT work application in LGAs.
2) AMTC
AMTC, as a monitoring and training cycle, has been applied in the model and
disseminated districts. RSEs and staffs in the Chamwino DC, Kondoa DC, Iringa DC, Mufindi DC has administratively capacitated through AMTC.
They all well understood and moreover they are able to instruct to the other
councils by the end of the Project. Currently, the challenge for AMTC is how to apply the administrative skills into the practical implementation.
PO‐RALG assumes obligation to improve AMTC for further dissemination of the contents of Operational Guidelines. (i) For future, PO‐RALG shall continuously
request RF to secure the budget for AMTC, although it would take some time to
be approved from the RF. (ii) In the short while, PO‐RALG shall commit to operate one week AMTC training in Dodoma and Iringa regions respectively,
and two or three additional days for AMTC in the Stakeholders’ Meeting or
Engineer’s Day for the model regions. (iii) Regarding the number of qualified engineers in RAS, PO‐RALG has already requested to PO‐PSM, and resulted in
increasing two or three RSEs respectively in each regions. PO‐RALG aims to
eliminate the regions with only one RSE assigned.
3) Summary of the Achievement based on the Indicators FY2015/2016 As requested by the terminal evaluation team, PO‐RALG has obligated to report
JICA Tanzania office in August.
4) LBT Equipment
PO‐RALG has strong interests in LBT equipment leasing system. It shall contribute to minimize the cost for rural road maintenance, and accelerate the
progress, i.e. improve the cost‐effectiveness of the rural road maintenance.
Thus, PO‐RALG has to commit to sustain the trial of LBT Equipment leasing system, and verify its effectiveness. To do so, PO‐RALG request Dodoma and
Iringa RSEs to report the benefit and achievement at least once a year in
Engineer’s Day.
ANNEX: Road Map
Annex‐61
ANNEX: Road Map Project
Purpose
Capacity Development for Rural Road Maintenance (Operational and technical) in
five regions
Output‐1 Enhance the Institutional capacity of PO‐RALG
Activity‐1 Identify the issues and challenges of Rural Road Maintenance
Activity‐2 Convene stakeholder meeting to discuss the issues of rural road
maintenance
Activity‐3 Support to modify the standards, manuals, guidelines of rural road
maintenance
Output‐2 Enhance the Operational Capacity of RSEs and DEs in 5 regions
Activity‐1 Provide operational Training for RSEs and DEs of 5 regions through
AMTC in Dodoma and Iringa Regions
Activity‐2 Provide operational training for councils through AMTC in the 5
regions
Activity‐3 Present the lessons learned through AMTC in the 5 regions in the
Engineers Day in the third and fourth year
Output‐3 Enhance the technical capacity in construction of Rural Road, Develop Appropriate
Construction technology for Rural Road Maintenance
Activity‐1 Decide the pilot site and appropriate construction technology in
Dodoma and Iringa
Activity‐2 Prepare the construction methods, design, procurement, contract
Procure the LBT equipment for the each target regions
Verify the LBT equipment leasing system
Activity‐3 Support the study in Research Centre for the appropriate surfacing
Provide the study tour to the country which is familiar to the relevant
technology (Ghana, Kenya, Ethiopia etc.)
Activity‐4 Construct the demonstration rural road in Dodoma and Iringa
(Implementation)
Activity‐5 Provide technical training during the construction incl. Equipment
management
Activity‐6 Provide technical Cost‐Benefit analysis of each construction
technology
Activity‐7 Support the policy dialog and standardization/regulation of
appropriate technology to be utilized in the Rural Road
Annex‐62
JCC‐5 Presentation
Annex‐63
Annex‐64
Annex‐65
Annex‐66
Annex‐67
Annex‐68
Annex‐69
Annex‐70
Annex‐71
Annex‐72
Annex‐73
Annex‐74
Annex‐75
Annex‐76
Annex‐77
Annex‐78
Annex‐79
Annex‐80
Annex‐81
Annex‐82
Annex‐8
3 Annex‐7
: Counterparts D
esignatio
n
JPY2011
3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2
Prime Minister's Office
(PMO‐RALG)/Infrastructure
Development Unit
Director
Prime Minister's Office
(PMO‐RALG)/Infrastructure
Development Unit
Exective Engineer
Dodoma Regional OfficeRegional Secretariat
Engineer (RSE)
Iringa Regional OfficeRegional Secretariat
Engineer (RSE)
Chamwino District
Office/Department of WorksDistrict Engineer
Iringa District Office/
Department of WorksDistrict Engineer
Kondoa District Office/
Department of WorksDistrict Engineer
Mufindi District Office/
Department of WorksDistrict Engineer
MonthJFY2014 JFY2015
Achievement of Input (Human Resource allocation, Tanzanian side)
JPN Year JFY2012 JFY2013
Eng. Ezron C. Kilamhama
Eng. Mkwata M. M.
Eng. David Michael Mwakalaline
Eng.Godwin S. Mpinzile
Eng. Peter Mawere Shirima
Eng. Elina Kayanda
Eng. Girbert MfinangaEng. Nanai
Eng. Leopold Runji
Eng. Richard Anyelwisye
Eng. Peter Johnson
Eng. Ayubu Myaule
Annex‐84
Annex‐8: RMSD Summary of Project Input (2012‐2016 March)
Item Unit Tanzania Japan Total
1. Human Resources MM ‐ ‐
‐Principal Counterpart MM 328.00 ‐ 328.00 ‐Assistant for the Dissemination/ Monitoring
MM 33.00 ‐
33.00
‐ATTI Consultation MM 6.00 ‐ 6.00
‐Japanese Experts MM ‐ 105.10 105.10
‐JICA JOCV MM 42.00 42.00
2. C/P training Participants ‐ ‐ 348 ‐Technical Training in Tanzania
Participants 197 ‐ 197
‐AMTC (Annual Training and Monitoring Cycle)
Participants 100 39 139
‐Training in Kenya & Uganda
Participants 11 1 12
‐Training in Japan* USD 14,608 14,608
3. Equipment USD ‐ ‐
‐JICA Procured USD ‐ 243,427 243,427
‐Project Procured USD ‐ 5,851 5,851
‐Maintenance TSH 3,845,800 0.0 3,845,800
4. Pilot Project in Model DC TSH ‐ ‐ 515,563,500
‐Chamwino DC* TSH 311,032,760 0.0 311,032,760
‐Iringa DC* TSH 285,492,500 0.0 285,492,5005. RMSD Project Operational Cost in Local USD 358,363 358,363
5‐1 Human resources USD 103,174
5‐2 Vehicle Related USD 124,635
5‐3 Commodities USD 7,767
5‐4 Transport USD 44,124
5‐5 Communication USD 4,271
5‐6 Cost for Meeting USD 136,580
5‐7 Local Consultant USD 11,260
5‐8 Others USD 4,779 * Contract Cost for the Pilot Project in Chamwino DC has revised because of the design was reviewed. * The cost for Training in Japan exclude the flights and accommodation * The exchange rate of USD = 122.74 JPN * Pilot Project in Iringa in FY 2015/2016 is not yet confirmed