Directors: M. C. Dickens G. A. Dickens J. A. Meadows A. P. Needham Registered in England No 735448
Produced for the Whittlesey Internal Drainage Board
FMR90784 Telemetry Installations
Phase 1
Ironside PS07 Beggars Bridge PS01
Wype Dole PS14 Manor Farm PS09
Monday 10th April – Monday 24th April 2017 Please reference DRB log book for day to day record of activities A temporary Telemetry materials store was established at Wype Dole Pump station Ironside PS07 (2 pump site / weed screen / grease pumps) Midi8 RTU wall mounted. 5db cellular whip antenna extended (5m) outside for better signal quality. Marshalling enclosure wall mounted. Switched fused spur installed (fitted 3Amp fuse)
Rushton Road, Desborough, Kettering, Northants, NN14 2QW, UK Tel. +44 (0) 1536 760 156 Fax +44 (0) 1536 762 552 email: [email protected]
Web Page: http://www.lee-dickens.co.uk
LEE-DICKENS LTD. SYSTEMS DI VISION
Lee-Dickens Ltd 2 May, 2017
FMR90784_WIDB_ Phase1 Report.docx Page 2 of 20
Telemetry power taken from a new 6amp breaker installed on din rail within the pump control panel by A J Speechley.
4” tray-work routed around pump station to carry power and signal cables. Metal marshalling enclosure and tray-work connected to pump station earth system using 6mm earth cable. Upstream water level frame mounted over the drain. The frame had a 2 metre arm to span the drain so extra support was given to the assembly by bracing the existing handrail to the pump station wall.
Level Sensor Installed in stainless steel housing. Brass ODN marker bolted to floor.
Lee-Dickens Ltd 2 May, 2017
FMR90784_WIDB_ Phase1 Report.docx Page 3 of 20
Sump level cable routed into pump station sump and coiled, ready for when WIDB expand the Telemetry system in the near future. Weed screen panel drilled (22mm), lamp and warning label fitted.
Door contact installed; contact wired to small junction box. Signal cable routed around pump station, clipped to wall.
Relays, contactors and current transformers installed within pump control panels
Where drilling has taken place within control panels, all drill and cabling debris has been swept and hoovered up.
Lee-Dickens Ltd 2 May, 2017
FMR90784_WIDB_ Phase1 Report.docx Page 4 of 20
All power and signal cables have been routed around site and dressed into cabinets.
Quantity Cable Type Description Type
1 2 core SWA Telemetry Power 230VAC
1 12 core braided Weed screen DINS/DOUTS
2 12 core braided Water Pumps DINS
1 12 core braided Grease Pumps/ELL
1 4 core braided Pump Current AINS
1 2 core SWA Upstream Water Level AIN
1 2 core SWA Sump Water Level AIN
1 2 core flexible Door Contact DIN
Where cables enter/exit building, holes drilled in walls have been sleeved with 20/25mm conduit.
Outstanding Installation Activities
CW Engineering to provide the weed screen signals.
Signal cables to be numbered/ferruled and terminated within control panels
Signal cables to be numbered/ferruled and terminated within marshalling panel
Fit cable idents to all telemetry cables
Fit idents (labels) to pump status relays and CTs
Point up brickwork where antenna and level cables enter building
Lee-Dickens Ltd 2 May, 2017
FMR90784_WIDB_ Phase1 Report.docx Page 5 of 20
Beggars Bridge PS01 (1 pump site / weed screen) Midi8 RTU wall mounted. 5db cellular whip antenna extended (5m) outside for better signal quality. Marshalling enclosure wall mounted. Switched fused spur installed (fitted 3Amp fuse)
Telemetry power taken from a spare 6amp breaker from the distribution board mounted within the pump control panel. Circuit breaker marked TELEMETRY.
4” tray-work routed around pump station to carry power and signal cables. Metal marshalling enclosure and tray-work connected to pump station earth system using 6mm earth cable. Upstream water level frame mounted over the drain. The level sensors 2 core SWA cable was routed around the drain within a 20mm galvanised conduit system. Upstream water level cable enters the pump station via the pump sump. We note the poor quality condition of the pump sump cover.
Lee-Dickens Ltd 2 May, 2017
FMR90784_WIDB_ Phase1 Report.docx Page 6 of 20
Level Sensor Installed within the stainless steel housing. Brass ODN marker bolted to floor.
Sump level cable routed into pump station sump and coiled, ready for when WIDB expand the Telemetry system in the near future.
Lee-Dickens Ltd 2 May, 2017
FMR90784_WIDB_ Phase1 Report.docx Page 7 of 20
Weed screen panel drilled, lamp and warning label fitted.
Door contact installed; contact wired to small junction box. Signal cable routed around pump station, clipped to wall.
Relays, contactors and current transformers installed within pump control panels
Lee-Dickens Ltd 2 May, 2017
FMR90784_WIDB_ Phase1 Report.docx Page 8 of 20
Where drilling has taken place within control panels, all drill and cabling debris has been swept and hoovered up. All power and signal cables have been routed around site and dressed into cabinets.
Quantity Cable Type Description Type
1 2 core SWA Telemetry Power 230VAC
1 12 core braided Weed screen DINS/DOUTS
1 12 core braided Water Pump/ELL DINS
1 4 core braided Pump Current AINS
1 2 core SWA Upstream Water Level AIN
1 2 core SWA Sump Water Level AIN
1 2 core flexible Door Contact DIN
Outstanding Installation Activities
CW Engineering to provide the weed screen signals.
Signal cables to be numbered/ferruled and terminated within control panels
Signal cables to be numbered/ferruled and terminated within marshalling panel
Fit cable idents to all telemetry cables
Fit idents (labels) to pump status relays and CTs
Relocate door contact using bespoke bracket to achieve a more positive connection
Clip 12 core braided cable to wall just below pump control panel
Lee-Dickens Ltd 2 May, 2017
FMR90784_WIDB_ Phase1 Report.docx Page 9 of 20
Wype Dole PS14 (1 pump site with weed screen) Midi8 RTU wall mounted. 5db whip antenna remains box mounted as standard (no need to extend outside) Marshalling enclosure wall mounted. Switched fused spur installed (fitted 3Amp fuse)
Telemetry power taken from a new 6amp breaker fitted in a spare fuse position within the Wylex distribution board.
Existing SWA cables repositioned on the existing tray-work so these and the new Telemetry cables could be managed more neatly.
Lee-Dickens Ltd 2 May, 2017
FMR90784_WIDB_ Phase1 Report.docx Page 10 of 20
Upstream water level frame mounted over the drain. To find a suitable, safe position on a stable undamaged section of hand rail, the framework had to be mounted outside the compound.
Level Sensor Installed in stainless steel housing. Brass ODN marker bolted to floor.
Sump level cable routed into pump station sump and coiled, ready for when WIDB expand the Telemetry system in the near future.
Lee-Dickens Ltd 2 May, 2017
FMR90784_WIDB_ Phase1 Report.docx Page 11 of 20
Weed screen panel drilled, lamp and warning label fitted.
Relays, contactors and current transformers installed within pump control panels
Where drilling has taken place within control panels, all drill and cabling debris has been swept and hoovered up.
Lee-Dickens Ltd 2 May, 2017
FMR90784_WIDB_ Phase1 Report.docx Page 12 of 20
All power and signal cables have been routed around site and dressed into cabinets.
Quantity Cable Type Description Type
1 2 core SWA Telemetry Power 230VAC
1 12 core braided Weed screen DINS/DOUTS
1 12 core braided Water Pump/ELL DINS
1 4 core braided Pump Current AINS
1 2 core SWA Upstream Water Level AIN
1 2 core SWA Sump Water Level AIN
1 2 core flexible Door Contact DIN
Where cables enter/exit building, holes drilled in walls have been sleeved with 20/25mm conduit.
Outstanding Installation Activities
CW Engineering to provide the weed screen signals.
Signal cables to be numbered/ferruled and terminated within control panels
Signal cables to be numbered/ferruled and terminated within marshalling panel
Fit cable idents to all telemetry cables
Fit idents (labels) to pump status relays and CTs
Install door contact using bespoke bracket to achieve a more positive connection
Lee-Dickens Ltd 2 May, 2017
FMR90784_WIDB_ Phase1 Report.docx Page 13 of 20
Manor Farm PS09 (3 pump site / weed screen / grease pumps) Trial site for Temperature Sensor and Rain Gauge. Midi8 RTU wall mounted. 5db whip antenna remains box mounted as standard (no need to extend outside) Marshalling enclosure wall mounted. Switched fused spur installed (fitted 3Amp fuse)
RTU, marshalling enclosure and spur connected to existing metal trunking using 32mm couplings.
Lee-Dickens Ltd 2 May, 2017
FMR90784_WIDB_ Phase1 Report.docx Page 14 of 20
Telemetry power taken from an existing spare breaker (far right)
Rain Gauge installed on hand railings in front of the pump sumps. Signal cable runs within the kee-klamp frame exiting in 20mm flexible steel ring conduit before entering the 20mm fixed galvanised conduit system.
Upstream water level frame bolted to the floor using M10 raw bolts. The frame has been given additional support by strapping it back to the existing hand rail.
Lee-Dickens Ltd 2 May, 2017
FMR90784_WIDB_ Phase1 Report.docx Page 15 of 20
Level Sensor Installed in stainless steel housing. Brass ODN marker bolted to floor.
Sump level cable routed into pump station sump and coiled, ready for when WIDB expand the Telemetry system in the near future.
Lee-Dickens Ltd 2 May, 2017
FMR90784_WIDB_ Phase1 Report.docx Page 16 of 20
HP823 temperature sensor wall mounted outside the pump station. Signal cable enters the building via the air vent. Cable is clipped to the pump station wall before entering the top of the marshalling enclosure via an M20 plastic stuffing gland.
Weed screen panel drilled, lamp and warning label fitted.
Lee-Dickens Ltd 2 May, 2017
FMR90784_WIDB_ Phase1 Report.docx Page 17 of 20
Wired door contact mounted and cabled back to marshalling enclosure, via the small IP rated junction box. Need to manufacture a small bespoke bracket to mount the wireless contact to the metal door frame.
Relays, contactors and current transformers installed within pump control panels
The Hand/Auto switch arrangement differed at to previous sites. Previous sites had a 230AVC supply turned on/off in the Auto switch position. This enabled us to operate the coil of our relay to genrate a volt free contact to mimic the auto position on the Telemetry. With certain “timed”scenarios (a combination of other swicth positions), the 230VAC supply on the auto switch is not available, the switch can be operated but no mains supply is turned on or off.
Lee-Dickens Ltd 2 May, 2017
FMR90784_WIDB_ Phase1 Report.docx Page 18 of 20
Lee-Dickens returned to site on Monday 24th April to meet with Matt Cullip of A J Speechley to investigate this matter further. After some time spent trying to understand the pump logic at site, it was decided it would be a cheaper solution to replace the Hand/Auto switches, replicating the current switch operation but providing Lee-Dickens with an auxiliary set of volt free contacts to be used to mimic each pump being IN AUTO or NOT IN AUTO. Where drilling has taken place within control panels, all drill and cabling debris has been swept and hoovered up. All power and signal cables have been routed around site and dressed into cabinets.
Quantity Cable Type Description Type
1 2 core SWA Telemetry Power 230VAC
1 12 core braided Weed screen DINS/DOUTS
24 Single core cables Water/Grease Pumps DINS
2 Single core cables (ELL)Extra Low Level DINS
3 8 core screened Pump Current AINS
1 2 core SWA Upstream Water Level AIN
1 2 core SWA Sump Water Level AIN
1 2 core SWA Rain Gauge DIN
1 2 core flexible Door Contact DIN
1 8 core screened Ambient Temperature AIN
Where cables enter/exit building, holes drilled in walls have been sleeved with 20/25mm conduit.
Outstanding Installation Activities
CW Engineering to provide the weed screen signals.
Signal cables to be numbered/ferruled and terminated within control panels
Signal cables to be numbered/ferruled and terminated within marshalling panel
Fit cable idents to all telemetry cables
Fit idents (labels) to pump status relays and CTs
Lee-Dickens Ltd 2 May, 2017
FMR90784_WIDB_ Phase1 Report.docx Page 19 of 20
Install door contact using bespoke bracket to achieve a more positive connection
Wire signals to auxiliary contacts on new Hand/Auto signals
Template Wiring schedule Digital Inputs
Item Description Notes
01 PUMP1 STATUS (Run/Stop)
02 PUMP1 FAULT (Tripped/Healthy)
03 PUMP1 (Auto/Hand)
04 PUMP2 STATUS (Run/Stop)
05 PUMP2 FAULT (Tripped/Healthy)
06 PUMP2 (Auto/Hand)
07 WEED SCREEN STATUS (Run/Stop)
08 WEED SCREEN FAULT (Tripped/Healthy)
09 WEED SCREEN (Auto/Hand)
10 EXTRA LOW LEVEL
11 DOOR OPEN/CLOSE
12 GREASE1 PUMP STATUS
13 GREASE2 PUMP STATUS
14 PUMP3 STATUS (Run/Stop)
15 PUMP3 FAULT (Tripped/Healthy)
16 RTU BATTERY HEALTH (Internal point) Sub board
17 RAIN GAUGE (Pulsed Input) Sub board
18 PUMP3 (Auto/Hand) Sub board
Pump Hours Run signals derived from Pump Run signal.
Analogue Inputs
Item Description Notes
01 UPSTREAM WATER LEVEL
02 SUMP WATER LEVEL
03 PUMP 1 CURRENT
04 PUMP 2 CURRENT
05 PUMP 3 CURRENT
06 AMBIENT TEMPERATURE
Digital Outputs
Item Description Notes
01 WEED SCREEN INHIBIT Remote manual control
Lee-Dickens Ltd 2 May, 2017
FMR90784_WIDB_ Phase1 Report.docx Page 20 of 20
Midi8 RTU Activated Sim Cards