Upload
mohamedibrahim
View
219
Download
36
Tags:
Embed Size (px)
DESCRIPTION
Method Statement for cable Laying as per ADDC requirement
Citation preview
Method Statement UG Cable Installation
Underground LV up to 33KV Cable Installation
Document Ref. : SAF-EL-001
Revision : 01
Date : 20/10/2013
Summary : This is an Engineering instruction manual detailing the adopted standards and specifications used in the Emirate of Abu Dhabi and are accepted as the absolute minimum requirement to properly install LV, MV and fiber optic cables to a satisfactory, safe and efficient manor.
Prepared by : Eng. Mohamed Ibrahim Abdel-Fattah Technical Manager Eng. Abdel-Fattah Ibrahim Abdel-Fattah Planning & Safety Manager
1 Of 17All Rights Reserved Safari General Contracting Company LLC 2013
Method Statement UG Cable Installation
Table of Contents1 Scope.................................................................................................................................................32 References.........................................................................................................................................33 Document Goals................................................................................................................................34 On Site requirements.........................................................................................................................44.1 Direct buried cables........................................................................................................................4
4.1.1 LV Cables...........................................................................................................................44.1.2 11KV Cables......................................................................................................................54.1.3 22KV Cables......................................................................................................................54.1.4 33KV Cables......................................................................................................................54.1.5 FOC Cables........................................................................................................................5
4.2 Cables in Ducts & PVC Conduits..............................................................................................64.2.1 Ducts..................................................................................................................................64.2.2 PVC Conduits.....................................................................................................................6
5 Trench Details....................................................................................................................................75.1 LV Cables...................................................................................................................................75.2 11kV Cables...............................................................................................................................85.3 22kV Cables...............................................................................................................................95.4 33kV Cables.............................................................................................................................10
6 Cable Installation.............................................................................................................................116.1 Trench Bedding........................................................................................................................116.2 Cable Covering Tiles................................................................................................................116.3 Warning Tape...........................................................................................................................116.4 Cable Route markers................................................................................................................11
7 Installation Procedure......................................................................................................................127.1 Excavation & Cable laying......................................................................................................127.2 Jointing works to existing cables.............................................................................................13
8 Annexures........................................................................................................................................148.1 Cable Covering Tiles...............................................................................................................148.2 Cable Route Markers...............................................................................................................158.3 Typical Cross Section of 4C XLPE LV Cable-grip.................................................................168.4 Risk Assessment......................................................................................................................17
2 Of 17All Rights Reserved Safari General Contracting Company LLC 2013
Method Statement UG Cable Installation
1 Scope
This is an Engineering instruction manual detailing the adopted specification and standards used in the Emirate of Abu Dhabi and are accepted as the absolute minimum requirement to properly install LV, MVand fiber optic cables to a satisfactory, safe and efficient manor.
2 References
The following resources are referenced and sited for the preparation of this instruction:
Reference Description
S-AAA-CAB-INST-LV (Rev.0-2011) Installation Requirements for LV Cables & Wires in SS Buildings
S-AAA-CAB-INST-MV (Rev.0-2011) Installation Requirements for MV UndergroundCables
S-AAA-CAB-INST-CONT-FOC (REV.0-2011) Installation Requirements for Control & Fibre Optic Cables
DWG AAA CAB 01 00 07 (LV CAB Trench) Typical LV Cable Trench Section
DWG AAA CAB 01 00 08 (11kV CAB Trench) Typical Section Of 11kv Cable Trench
DWG AAA CAB 01 00 09 (22kV CAB trench) Typical Section Of 22kv Cable Trench
DWG AAA CAB 01 00 10 (33kV CAB Trench) Typical Section Of 33kv Cable Trench
DWG AAA CAB 01 00 11 (11-22-33 CAB Trench) Trench Details of 11kV, 22kV & 33kV, & FOC
DWG AAA CAB 01 00 12 (Manhole Details) 11kV, 22kV & 33kV, & FOC Manhole Details
S-AAA-CAB-GEN (Rev.0-2011) General Requirements
31.12.97 ADM Standard Specifications for Road and Bridge construction
3 Document Goals
The goal of the document is to provide a complete and up to date instruction for the installation of different types of cables directly & indirectly buried in ground this can be achieved by showing the following:
Types & Sizes of the cables to be used and installed directly & indirectly in the ground
Trench details including its depth, layout, material to be used, etc...
Proper procedure for the pulling of the cables
Site tests & inspections to insure the health of the installed cables
3 Of 17All Rights Reserved Safari General Contracting Company LLC 2013
Method Statement UG Cable Installation
4 On Site requirements
4.1 Direct buried cables
Direct burial of new cables is the preferred installation state in the Emirate of Abu Dhabi except where on site condition dictate otherwise.
All Cables to be PVC sheathed to give it protection against the harsh conditions of underground installation whether that be salts, insects, etc.. to give it a long service life.
4.1.1 LV Cables
The following table shows the most widely used LV Cables for power distribution:
No. of Cores + Core Size Core Material + Armoring + Insulation
ADWEA/ADDC/AADC Data sheet
4Cx4mm Cu/XLPE/SWA/PVC D-AAA-CAB-LV-DB-4C-4upto300 (Rev.1-2011)
4Cx6mm Cu/XLPE/SWA/PVC D-AAA-CAB-LV-DB-4C-4upto300 (Rev.1-2011)
4Cx10mm Cu/XLPE/SWA/PVC D-AAA-CAB-LV-DB-4C-4upto300 (Rev.1-2011)
4Cx16mm Cu/XLPE/SWA/PVC D-AAA-CAB-LV-DB-4C-4upto300 (Rev.1-2011)
4Cx25mm Cu/XLPE/SWA/PVC D-AAA-CAB-LV-DB-4C-4upto300 (Rev.1-2011)
4Cx35mm Cu/XLPE/SWA/PVC D-AAA-CAB-LV-DB-4C-4upto300 (Rev.1-2011)
4Cx50mm Cu/XLPE/SWA/PVC D-AAA-CAB-LV-DB-4C-4upto300 (Rev.1-2011)
4Cx70mm Cu/XLPE/SWA/PVC D-AAA-CAB-LV-DB-4C-4upto300 (Rev.1-2011)
4Cx95mm Cu/XLPE/SWA/PVC D-AAA-CAB-LV-DB-4C-4upto300 (Rev.1-2011)
4Cx120mm Cu/XLPE/SWA/PVC D-AAA-CAB-LV-DB-4C-4upto300 (Rev.1-2011)
4Cx150mm Cu/XLPE/SWA/PVC D-AAA-CAB-LV-DB-4C-4upto300 (Rev.1-2011)
4Cx185mm Cu/XLPE/SWA/PVC D-AAA-CAB-LV-DB-4C-4upto300 (Rev.1-2011)
4Cx240mm Cu/XLPE/SWA/PVC D-AAA-CAB-LV-DB-4C-4upto300 (Rev.1-2011)
4Cx300mm Cu/XLPE/SWA/PVC D-AAA-CAB-LV-DB-4C-4upto300 (Rev.1-2011)
4 Of 17All Rights Reserved Safari General Contracting Company LLC 2013
Method Statement UG Cable Installation
4.1.2 11KV Cables
The following table shows the most widely used 11KV Cables for power distribution:
No. of Cores + Core Size Core Material + Armoring + Insulation
ADWEA/ADDC/AADC Data sheet
3Cx95mm Cu/XLPE/STA/PVC D-AAA-CAB-11-3C (Rev.0-2011)
3Cx120mm Cu/XLPE/STA/PVC D-AAA-CAB-11-3C (Rev.0-2011)
3Cx185mm Cu/XLPE/STA/PVC D-AAA-CAB-11-3C (Rev.0-2011)
3Cx240mm Cu/XLPE/STA/PVC D-AAA-CAB-11-3C (Rev.0-2011)
3Cx300mm Cu/XLPE/STA/PVC D-AAA-CAB-11-3C (Rev.0-2011)
4.1.3 22KV Cables
The following table shows the most widely used 22KV Cables for power distribution:
No. of Cores + Core Size Core Material + Armoring + Insulation
ADWEA/ADDC/AADC Data sheet
3Cx95mm Cu/XLPE/STA/PVC D-AAA-CAB-22-3C (Rev.0-2011)
3Cx120mm Cu/XLPE/STA/PVC D-AAA-CAB-22-3C (Rev.0-2011)
3Cx185mm Cu/XLPE/STA/PVC D-AAA-CAB-22-3C (Rev.0-2011)
3Cx240mm Cu/XLPE/STA/PVC D-AAA-CAB-22-3C (Rev.0-2011)
3Cx300mm Cu/XLPE/STA/PVC D-AAA-CAB-22-3C (Rev.0-2011)
4.1.4 33KV Cables
The following table shows the most widely used 33KV Cables for power distribution:
No. of Cores + Core Size Core Material + Armoring + Insulation
ADWEA/ADDC/AADC Data sheet
3Cx240mm Cu/XLPE/STA/PVC D-AAA-CAB-33-3C (Rev.0-2011)
3Cx300mm Cu/XLPE/STA/PVC D-AAA-CAB-33-3C (Rev.0-2011)
4.1.5 FOC Cables
The following table shows the most widely used FOC Cables for power distribution:
No. of Cores ADWEA/ADDC/AADC Data sheet
32 Fiber D-AAA-CAB-FOC-DB-32 (Rev 0-2011)
64 Fiber D-AAA-CAB-FOC-DB-64 (Rev.0-2011)
144 Fiber D-AAA-CAB-FOC-DB-144 (Rev 0-2011)
5 Of 17All Rights Reserved Safari General Contracting Company LLC 2013
Method Statement UG Cable Installation
4.2 Cables in Ducts & PVC Conduits
4.2.1 Ducts
Generally cables pass through ducts when the cable run is needed to pass under a Road or Street to feed a point on the other side of the road or under pavements & side walks where excavation works are not desired. These ducts shall be concrete encased to provide safety against load pressure applied on the conduits due to the passing of cars, trucks, buses, etc.. on the roads above the installation.
4.2.2 PVC Conduits
The main types of cables that pass in PVC Conduits are FOC cables used for control purposes & LV power cables used in street lighting systems, this type of arrangement is beneficial for the ease and quickness of maintenance of such networks where the need to repair any faults in the systems are critical. The outside diameter and minimum wall thickness of PVC electrical conduit shall be as follows:
Nominal Size (cm) Minimum Wall Thickness (mm)
2.0 1.8
2.5 1.9
3.2 2.5
3.8 2.5
5.0 3.2
6.0 4.7
10.0 6.0
15.0 7.1
20.0 8.2
6 Of 17All Rights Reserved Safari General Contracting Company LLC 2013
Method Statement UG Cable Installation
5 Trench Details
5.1 LV Cables
7 Of 17All Rights Reserved Safari General Contracting Company LLC 2013
Method Statement UG Cable Installation
5.2 11kV Cables
8 Of 17All Rights Reserved Safari General Contracting Company LLC 2013
Method Statement UG Cable Installation
5.3 22kV Cables
9 Of 17All Rights Reserved Safari General Contracting Company LLC 2013
Method Statement UG Cable Installation
5.4 33kV Cables
10 Of 17All Rights Reserved Safari General Contracting Company LLC 2013
Method Statement UG Cable Installation
6 Cable Installation
6.1 Trench Bedding
All Cables shall only be laid directly onto the bottom of the trench at a depth as shown in the trench details above or as directed by the Engineer.
A sand bedding shall be constructed as shown in the trench details or as directed by the Engineer to insure that the cables will not be damaged due to any protruding elements from the ground such as stones, rocks, etc..
6.2 Cable Covering Tiles
Cable Covering Tiles shall be installed over all newly directly buried cables as a means of protection of the cables as shown in the drawings or as directed by the Engineer. There is no requirement to install such tiles above approved ducts but it may be installed if it is deemed that additional protection is required.
6.3 Warning Tape
Warning Tape shall be installed over all newly directly buried cables as a means of protection of the cables asshown in the drawings or as directed by the Engineer. There is no requirement to install such tapes above approved ducts but it may be installed if it is deemed that additional protection is required.
6.4 Cable Route markers
In installations of 11kV, 22kV, 33kV it is necessary to show the route of the cable run for future purposes of quick identification in case the necessity of excavating the cables is required.
11 Of 17All Rights Reserved Safari General Contracting Company LLC 2013
Method Statement UG Cable Installation
7 Installation Procedure
7.1 Excavation & Cable laying
1. Cable Route approval to be acquired from Town Planning department
2. NOC to be obtained from different authorities such as TRANSCO, PRFD, ADM, etc..
3. Cable sizing and routes to be approved by the Engineer/DOT/ADDC
4. Trench route to be indicated by the use of steel rods directly installed in the ground
5. A survey has to be carried out on the proposed cable route to finalize the cable length and the cableroute itself and to confirm no obstacles will be meet during the work
6. If any obstacles are found, they will be promptly relayed to the Client/Consultant for their review and recommendation
7. Excavation to commence adhering to the route detailed by the steel rods and to a depth as shown on the drawings or as detailed by the Engineer
8. Excavate to Locate will be done at site at intervals of 50m from pit to pit to identify any and all services in the excavation area
9. If services are found manual excavation will be used otherwise the use of machinery will be utilized such as Backhoes, Excavators, etc..
10. Warning fences, Warning ropes, danger notices, etc.. will be used to insure public safety around the working area
11. When Excavation is to be done in sidewalk area, the removal of existing tiles will be done with care not to damage the tiles. The same will be reinstalled after back filling has been completed.
12. Making sure the trench bottom is clean from any sharp objects that would other wise damage the cable outer sheath
13. Constructing Sand bedding at the bottom of the cables as detailed in the drawings
14. Trench inspection to be conducted and approval to be acquired from the Engineer
15. Termination point inside the panels / equipment shall be considered for suitable spare length to be left available during pulling of cable termination. The maximum length shall be equal to depth + height + width of panels.
16. Cable rollers to be installed at a distance of 2m center to center to allow unhindered movement of the cable above the roller to insure cables are not damaged
17. Check adequate place for Unloading the cable drums.
18. Check suitable position for placing the Cable pulling winch depending on the length of the cable and the site condition.
19. Cable winch to be firmly fixed as to not move/slide from its position due to the tension exerted to pull the cable
20. The cable drum intended for cable pulling shall be identified as per that indicated in the drum schedule
21. The cable shall be fixed to the winch, if used, by means of a cable sock or gripper
22. Special care will be taken when pulling the cable through cable ducts as to not damage the cable ends or outer sheath
23. Cable Ducts/Pipes shall be cleaned using proper equipment to insure the smooth and safe passage of the cables with out damage or obstruction.
24. Lubricant to be applied around the cables to facilitate the easy movement of the cable in the duct
12 Of 17All Rights Reserved Safari General Contracting Company LLC 2013
Method Statement UG Cable Installation
25. Cable laying will generally start from one end of the route length or at any suitable point if required
26. In case of cable lengths which are more than one drum length, all cables which can be laid from original position will be completed. And then the cable pulling set-up will be re-positioned to the nextlocation, from where the next length will be pulled
27. Cables will be laid / pulled by hand and / or winch.
28. During pulling with winch, if required, the tension on the cable will not exceed that given by the manufacturer and this will be monitored by means of Dynamo-meter.
29. Unless the lengths exceed the maximum drum lengths joints shall be avoided
30. Before cutting the cable, both ends must be inspected to ensure sufficient length is for proper dressing and end termination
31. Soon after completion of every cable the cables will be tested for insulation resistance and witnessedby the Engineer
32. Daily progress report will be submitted for the activity as well as summary of used cable for each drum
33. Approval of laid cables to be acquired from the Engineer
34. Final Sand bedding level to be constructed and inspected by the Engineer
35. Cable Covering tiles to be installed as detailed and or required, to be inspected by the Engineer, Tilesorientation to be as show in Annexure 8.1
36. Layer of natural back fill material in the area of work to be used as detailed in the drawings
37. Warning Tape to be installed as detailed to be inspected by the Engineer
38. Warning Tape to have the following arrangement, notice to be made that depending on Voltage of cable warning tape will be modified
- DANGER - BURIED ELECTRICAL L.V. CABLE BELOW ADDC
39. Back filling to final ground level with natural material at the area of work
40. Cable route markers to be installed in case it is required
7.2 Jointing works to existing cables
1. Location of Joint connection to be agreed upon with AADC
2. After approval is acquired Excavate to Locate the cables to be jointed
3. Permit to work to be issued by AADC
4. Lock Out Tag Out system of Electrical Switch gear to be put into effect during the shut down period to allow us to perform our works
5. Before work to proceed on any cables, AADC to perform spike test on cabling to insure the correct cables have been de-energized
6. Work to proceed with jointing works by approved Cable Jointer
7. SAT to be performed on the joint in presence of AADC before energization
8. Clearance from our side that all works have been completed and it is safe to energize the cables
13 Of 17All Rights Reserved Safari General Contracting Company LLC 2013
Method Statement UG Cable Installation
8 Annexures
8.1 Cable Covering Tiles
14 Of 17All Rights Reserved Safari General Contracting Company LLC 2013
Method Statement UG Cable Installation
8.2 Cable Route Markers
15 Of 17All Rights Reserved Safari General Contracting Company LLC 2013
8.3 Typical Cross Section of 4C XLPE LV Cable-grip
16 Of 17All Rights Reserved Safari General Contracting Company LLC 2013
DWG AAA CAB 01 13 03-D
Abu Dhabi Water & Electricity Authority
123
567
4
Typical Cross Section of Low VoltageXLPE-Insulated Four-Core
Underground Cable (Conductor Shaped)
8.4 Risk Assessment
Hazard Who Mightbe Harmed
Controls in Place Risk Rating
Risk of Slips, Trips and falls:
Waste around the site
Changes in level
Workers inthe area
All workers trained in good housekeeping techniques.
Good housekeeping to be maintained at all times.
Work are to be cleaned before leaving.
Moderate.
Manual Handling: Injury from poor
manual handling procedure.
Workersconducting
manualhandling
Pulling the cable as a team. Good communications within the team must
be maintained when cable is pulled over a long distance.
A brakeman is required on the drum to ensure that the drum doesnt over run
Close supervision is required to ensure no over stressing of cable occurs.
Cable pulls must be smooth and maintainedat a reasonable rate to ensure control and tension requirements are met.
Moderate.
Falling objects: Cables slipping
when manual handling.
Loose cable gripperon winch.
Workerspulling thecables or
supervisingwinch
pulling.
Training on good handling and steady rate pulling
Checking cable gripper periodically for looseconnection.
Providing high grip gloves and safety boots to reduce risk of slipping.
Low.
Falling from height: People. Vehicles. Equipment/Material Workers in
the area.Generalpublic.
Barrier off the area to reduce risk of public accidental approach.
Display suitable signage to indicate excavation is present.
Provide access points into excavation wherenecessary.
Banks-man available to guide vehicles dropping off material nearby.
Providing chocks to nearby parked vehicles/equipment.
Moderate.
Electricity: Working near live
services.Workers inthe area.
All services must be made dead before work if possible.
Barricading of the live services to keep workers away.
Moderate.
17 Of 17All Rights Reserved Safari General Contracting Company LLC 2013
1 Scope2 References3 Document Goals4 On Site requirements4.1 Direct buried cables4.1.1 LV Cables4.1.2 11KV Cables4.1.3 22KV Cables4.1.4 33KV Cables4.1.5 FOC Cables4.2 Cables in Ducts & PVC Conduits4.2.1 Ducts4.2.2 PVC Conduits
5 Trench Details5.1 LV Cables5.2 11kV Cables5.3 22kV Cables5.4 33kV Cables
6 Cable Installation6.1 Trench Bedding6.2 Cable Covering Tiles6.3 Warning Tape6.4 Cable Route markers
7 Installation Procedure7.1 Excavation & Cable laying7.2 Jointing works to existing cables
8 Annexures8.1 Cable Covering Tiles8.2 Cable Route Markers8.3 Typical Cross Section of 4C XLPE LV Cable-grip8.4 Risk Assessment