Biodiesel Plant Conroe, Texas Assets Available for Acquisition from Aequitas Capital Management

Safe Biodiesel Plant

Embed Size (px)

Citation preview

Page 1: Safe Biodiesel Plant

7/29/2019 Safe Biodiesel Plant

http://slidepdf.com/reader/full/safe-biodiesel-plant 1/18

Biodiesel PlantConroe, Texas

Assets Available for Acquisitionfrom

Aequitas Capital Management

Page 2: Safe Biodiesel Plant

7/29/2019 Safe Biodiesel Plant

http://slidepdf.com/reader/full/safe-biodiesel-plant 2/18

Table of Contents

• Opportunity Highlights

• Summary Plant Description

• Acquisition Status

• Competitive Advantages

• Summary Unit Operations

• Process Description – Lines #1, #2

• Selected Plant Pictures

Contact Information

1

Page 3: Safe Biodiesel Plant

7/29/2019 Safe Biodiesel Plant

http://slidepdf.com/reader/full/safe-biodiesel-plant 3/18

Opportunity Highlights

• Potential 38 MMgy capacity

• Three years of production experience (18 MMgy) – mid 2004 thru mid

2008

• Multi-feedstock capability

• Close proximity to major feedstock markets and fuel markets• Multiple transportation options:

 – Located adjacent to UP main line with spur available

 – HWY I-45 is approximately two miles from site

• Re-start in approximately eight weeks offering quick access to market

• US and Texas biofuels tax credits available

• Opportune time to invest:

 – Attractive asset valuations, US energy policies encouraging bio-diesel production

• Plant is of modular design and could be re-located.

2

Page 4: Safe Biodiesel Plant

7/29/2019 Safe Biodiesel Plant

http://slidepdf.com/reader/full/safe-biodiesel-plant 4/18

Summary Plant Description

The plant, located Conroe, Texas was initially constructed in 2003 to manufacture fuelproduced by a biodiesel process that converts plant oil or animal fats into methyl esters or

biodiesel. Biodiesel is the main product. The quality of the Plant’s biodiesel was in accordance

with the ASTM 6751-7b standard.

The plant process was developed around a plugged flow reactor of in-house design. The plant

was designed with two production lines, one for virgin, degummed oils and one for recycled

oils and animal fats.

Line 1

Feedstock: Virgin, Degummed Oils

Production Capacity: 24.2 million gallons per year

Maximum FFA: <1%

Line 2

Feedstock: Recycled Oils/Animal Fats

Production Capacity: 16.2 million gallons per year

Maximum FFA: 4%

3

Page 5: Safe Biodiesel Plant

7/29/2019 Safe Biodiesel Plant

http://slidepdf.com/reader/full/safe-biodiesel-plant 5/18

Acquisition Status

• The Plant began commercial operations in 2004, expanded its operating capacity in 2006 and

2007 and then in mid-2008 was shut-down because of high feedstock prices.

• The Plant assets were acquired by its Senior Lender, Aequitas Commercial Finance, through a

negotiated settlement in March, 2009

• Aequitas is offering the plant assets for sale. Aequitas will consider terms including financing,

merger or joint venture.

• Long term lease of buildings and land available at attractive terms.

• The plant is of a modular design and could be re-located.

• Aequitas commissioned E3, an engineering firm that is experienced in designing and

constructing biodiesel refineries to perform a preliminary feasibility study of the Plant

including operating in place or re-location

Interested acquirers may obtain a copy of this study. Aequitas will arrange to make E3available for diligence calls.

• Aequitas can also assist in securing operations staff and management.

4

Page 6: Safe Biodiesel Plant

7/29/2019 Safe Biodiesel Plant

http://slidepdf.com/reader/full/safe-biodiesel-plant 6/18

Competitive Advantages – Feedstock

• Flexible feedstock sourcing strategy

 – Cottonseed, canola, soy and other plant-based oils

 – Animal fats including tallow, poultry and pork

• Feedstock Availability

 – Texas is the world’s largest producer of cotton on a per acre basis and in the U.S. produces more than

any other state

 – Texas is the nation’s largest producer of beef tallow.

 – Texas is a leader in poultry production.

5

Page 7: Safe Biodiesel Plant

7/29/2019 Safe Biodiesel Plant

http://slidepdf.com/reader/full/safe-biodiesel-plant 7/18

Competitive Advantages - Transportation

• Located Adjacent to Union Pacific Main Line

 – Access to spur available with 45 car capacity

• Port of Houston

 – 40 miles from Houston Ship Channel

• HWY I-45

 – Approximately 2 miles away with direct access

to all potential customers and feedstock

producers

6

Page 8: Safe Biodiesel Plant

7/29/2019 Safe Biodiesel Plant

http://slidepdf.com/reader/full/safe-biodiesel-plant 8/18

Summary Unit Operations

Unit operations for process line 1:1. Methanol/KOH Make-down

2. Tube Reactor

3. Decanter

4. Water Wash

5. Acid Wash

6. Coalescer7. Drying

Unit operations for process line 2:1. Methanol/KOH Make-down

2. Tube Reactor

3. Decanter – Stage 1

4. Decanter – Stage 2

5. Water Wash6. Acid Wash – Stage 1

7. Acid Wash – Stage 2

8. Coalescer

9. Drying

7

Common utility systems within the plant

include:Compressed Air

Steam Boiler

Well Water System

CO2 Fire Extinguishing System (over reactor area)

Page 9: Safe Biodiesel Plant

7/29/2019 Safe Biodiesel Plant

http://slidepdf.com/reader/full/safe-biodiesel-plant 9/18

Summary Unit Operations

Tank Storage

Tank Contents

Storage Capacity

Gallons Number of Tanks

Line 1 Feedstock (Virgin Oils) 189,000 10

Line 2 Feedstock (Oils/Fats) 72,000 4

Methanol 18,5000 1

Glycerin 72,000 4

Wash Water 158,100 19

Waste Water 10,000 2

FFA 55,000 6

Biodiesel Product 49,000 4

Unallocated Storage 46,800 5

8

Page 10: Safe Biodiesel Plant

7/29/2019 Safe Biodiesel Plant

http://slidepdf.com/reader/full/safe-biodiesel-plant 10/18

Process Description – Line #1

Line 1 has a stated capacity of 24.2 million gallons per year using a virgin degummed oil feedstock.

Methanol/KOH Make-down Area

In this area the potassium hydroxide (KOH) catalyst is dissolved in methanol prior to being pumped to the Reactor area. This

is done as a batch operation, with the KOH dumped from 50 lb bags into 330 gallon stainless steel totes filled with methanol.

The methanol is recirculated through the totes until the KOH has dissolved and then transferred to storage tanks. The

methanol/KOH solution is then pumped through a circulation loop to the Reactor area, through a fine filter to remove any

undissolved particles. Unused methanol/catalyst circulates back to the storage tank.

Including the dissolving tank volume, the line 1 makedown area has a capacity of 1,520 gallons

Reactor Area

The reactor area uses an in-house design plugged flow reactor to react the oil with the methanol/KOH solution to form

biodiesel. The oil is supplied to the reactor area from a circulating loop from the oil storage tanks. A high pressure vane

pump pulls from the oil line and pumps to the reactor inlet at approximately 3,000 psig. A high pressure triplex piston pump

pulls methanol/KOH solution from the circulating line and also supplies it to the reactor inlet at 3,000 psig. The flow of methanol/KOH is regulated by a variable speed drive on the pump motor.

The oil and methanol mix at the reactor inlet and pass through the reactor tubes. The reactor is composed of 25 coils of 22

foot long ¼ inch tubing filled with 1/8 inch steel beads. This provides high shear mixing in a plugged flow environment,

which provides for a more rapid transesterification reaction. From the reactor the reacted crude biodiesel flows to the

decanter.

9v.09.04.21

Page 11: Safe Biodiesel Plant

7/29/2019 Safe Biodiesel Plant

http://slidepdf.com/reader/full/safe-biodiesel-plant 11/18

Process Description – Line #1

Decanter

The decanter is a 10,000 gallon tank (TP-1) that separates the glycerol phase from the biodiesel. The separated biodiesel is

pumped by a stinger going into the top of the tank, to the Water Wash Tank. The separated glycerol at the bottom of the

tank is pumped to the tank farm storage.

Water Wash

The biodiesel from the decanter is mixed with wash water in the transfer pump discharge line. The water/biodiesel mixture

is pumped into a 10,000 gallon tank (TP-2) where the water separates from the biodiesel. The separated biodiesel ispumped by a stinger going into the top of the tank, to the Acid Wash Tank. The separated wash water at the bottom of the

tank is combined with the water from the Acid Wash and pumped to the tank farm for treatment. The wash water is stored

in a 1,550 gallon day tank, which is manually filled as needed from the clarified wash water tanks in the tank farm.

Acid Wash

The biodiesel from the water wash stage is mixed with acidified wash water in the transfer pump discharge line. The

water/biodiesel mixture is pumped into a 10,000 gallon tank (TP-3) where the water separates from the biodiesel. The

separated biodiesel is pumped by a stinger going into the top of the tank, to a Coalescer. The separated wash water at the

bottom of the tank is combined with the water from the Water Wash stage and pumped to the tank farm for treatment. The

acid wash water is stored in a 1,550 gallon day tank, which is manually filled as needed from the acid wash tanks in the tank

farm.

10

Page 12: Safe Biodiesel Plant

7/29/2019 Safe Biodiesel Plant

http://slidepdf.com/reader/full/safe-biodiesel-plant 12/18

Process Description – Line #1

Coalescer

The coalescer separates any biodiesel-water emulsions, and returns the water to the Acid Wash Tank. The biodiesel flows to

the drying area.

Drying

Biodiesel drying is accomplished through a falling film evaporator system that was originally designed to concentrate milk

sugars. The biodiesel is dried under vacuum in the evaporator and then pumped to the tank farm for storage.

11

Page 13: Safe Biodiesel Plant

7/29/2019 Safe Biodiesel Plant

http://slidepdf.com/reader/full/safe-biodiesel-plant 13/18

Process Description – Line #2

Line 2 has a stated capacity of 16.2 million gallons per year using a waste oil or animal fat feedstock.

Methanol/KOH Make-down Area

The line 2 area operates the same as the Line 1 Methanol/KOH Make-down Area. Including the dissolving tank volume, the

line 2 makedown area has a capacity of 990 gallons.

Reactor Area

The line 2 reactor is identical to the line 1 reactor.

Decanter

The line 2 decanter is a two-stage system. The first stage is a 6,000 gallon tank (PFP-1) that separates the glycerol phase

from the biodiesel. The separated biodiesel overflows by gravity from a nozzle near the top of the tank into the 3,000 gallon

Second Stage Decanter Tank (PFP-2). The second stage decanter provides additional separation for glycerol and soaps. The

separated biodiesel is pumped by a stinger in the top of the tank to the Water Wash systems. The separated glycerol at the

bottom of both stages is pumped to the tank farm storage.

Water Wash

The biodiesel from the decanter second stage is mixed with wash water in the transfer pump discharge line. The

water/biodiesel mixture is pumped into a 6,000 gallon tank (PFP-3) where the water separates from the biodiesel. The

separated biodiesel is pumped by a stinger going into the top of the tank, to the Acid Wash Tank (PFP-4). The separated

wash water at the bottom of the tank is combined with the water from the two Acid Wash stages and pumped to the tank

farm for treatment. The wash water comes directly from the clarified wash water tanks in the tank farm area.

12v.09.04.21

Page 14: Safe Biodiesel Plant

7/29/2019 Safe Biodiesel Plant

http://slidepdf.com/reader/full/safe-biodiesel-plant 14/18

Process Description – Line #2

Acid Wash

The biodiesel from the water wash stage is mixed with acidified wash water in the transfer pump discharge line. The

water/biodiesel mixture is pumped into a two-stage wash system consisting of two 6,000 gallon tanks (PFP-4 & 5). The first

stage separates the majority of the water from the biodiesel, and the second stage allows any remaining water to settle out.

The separated biodiesel is pumped by a stinger going into the top of the tank, to a Coalescer. The separated wash water at

the bottom of the two tanks is combined with the water from the Water Wash stage and pumped to the tank farm for

treatment. The acid wash water is stored in a 1,550 gallon day tank, which is manually filled as needed from the acid wash

tanks in the tank farm.

Coalescer

The coalescer separates any biodiesel-water emulsions, and returns the water to the Acid Wash Tank. The biodiesel flows to

the drying area.

Drying

Biodiesel drying is accomplished through a falling film evaporator system that was originally designed to concentrate milk

sugars. The biodiesel is dried under vacuum in the evaporator and then pumped to the tank farm for storage.

13

Page 15: Safe Biodiesel Plant

7/29/2019 Safe Biodiesel Plant

http://slidepdf.com/reader/full/safe-biodiesel-plant 15/18

Common Systems

Compressed Air

Compressed air for plant cleaning and control use is supplied by a small air compressor mounted on a 50 gallon receiver.

Fresh Water

Fresh water is supplied by a well pump and filter system on the south end of the tank farm area.

Wash Water Clarification

Wash water is 100% recycled within the plant. This is done by acidifying the wash water to convert soaps back into fattyacids. The fatty acids then float to the surface of the water and are decanted into storage tanks. The clarified wash water is

then recycled back into the wash lines.

CO2 Fire Extinguishing System

A CO2 gas fire smothering system has been installed over the reactor area. In the event of a fire this system will be manually

activated, flooding the area with CO2 gas and smothering the fire.

Boilers

The plant has two boilers, one an 86.2 HP, 15 psig gas fired boiler, and the other a 150 HP, 150 psig oil fired boiler. The gas

fired boiler is no longer in service. The oil fired boiler is fueled by biodiesel with propane for the pilot. This boiler supplies

steam to the plant processes.

14v.09.04.21

Page 16: Safe Biodiesel Plant

7/29/2019 Safe Biodiesel Plant

http://slidepdf.com/reader/full/safe-biodiesel-plant 16/18

Select Plant Pictures

Tankage and Rolling Stock Biodiesel Drying Columns

Boiler Catalyst-Methanol Preparation

15

Page 17: Safe Biodiesel Plant

7/29/2019 Safe Biodiesel Plant

http://slidepdf.com/reader/full/safe-biodiesel-plant 17/18

Select Plant Pictures

Laboratory Line 1-2 Reactor

Line 1 Decanter-Wash Line 2 Decanter-Wash

16

Page 18: Safe Biodiesel Plant

7/29/2019 Safe Biodiesel Plant

http://slidepdf.com/reader/full/safe-biodiesel-plant 18/18

Contacts for Further Information

Andy MacRitchie

503-419-3549

e-mail: [email protected]

Thomas Sidley503-419-3514

e-mail: [email protected]

17