52
Safeguards Monitoring Report Project No. 45084-002 Semiannual Report July 2015 2913-BAN(SF): Coastal Climate-Resilient Infrastructure Project Prepared by Local Government Engineering Department for the Asian Development Bank.

Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

Safeguards Monitoring Report Project No. 45084-002 Semiannual Report July 2015

2913-BAN(SF): Coastal Climate-Resilient

Infrastructure Project

Prepared by Local Government Engineering Department for the Asian Development Bank.

Page 2: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 3: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

GOVERNMENT OF THE PEOPLE’S REPUBLIC OF BANGLADESH

LOCAL GOVERNMENT ENGINEERING DEPARTMENT

RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207

Semi-Annual

Social Safeguard Monitoring Report (Cumulative)

Reporting Period (From Project Inception to June 2015)

 

July 2015 

COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP)

Page 4: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

TableofContents 

Executive Summary .............................................................................................................. 2 

1  Purpose of the Report and Land Acquisition & Resettlement Framework ....................... 5 

2  Introduction - Background and Rationale ........................................................................ 6 

Output 1 - Improved Road Connectivity .......................................................................... 7 

Output 2 - Improved Market Services .............................................................................. 7 

Output 3 - Enhanced climate change adaptation capacity ............................................... 8 

3  Institutional Arrangements ............................................................................................... 9 

4  Project Implementation .................................................................................................. 10 

5 Proposed Major Resettlement Activities in 2015 ………………………………………… 20

ANNEXURES 

Annex - 1 : List of the Sub-projects which Due Diligence Report has already been prepared

by the CCDB ......................................................................................................................... 21 

Annex - 2: Official Notification .............................................................................................. 29 

Annex - 3: Rehabilitation Guidelines in Bangla ..................................................................... 31 

 

 

Page 5: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

Coastal

Bank (A

Developm

January

economic

infrastruc

promote

rehabilita

growth ce

The key

Market S

CCRIP is

roads, br

contribut

member.

activities

Climate Re

ADB),Kredita

ment under

2013 to in

c growth,

cture in the

overall dev

ating Upazila

entres and C

component

Services and

s specially d

ridges and c

ing significa

CCRIP ha

of the proje

Ex

silient Infras

anstaltfürWie

Local Gove

ncrease rura

rural deve

project are

velopment of

a & Union r

Cyclone She

ts of the pr

(c) Enhanc

designed for

culverts, cyc

antly in emp

as made su

ect are expec

xecutiv

structure Pr

ederaufbau

ernment Eng

al incomes

lopment, s

ea to be co

f the transp

roads and ro

elter.

rojects are:

ed climate c

r the develop

clone shelte

ployment cre

ubstantial p

cted to be co

ve Summ

roject (CCR

(KfW) and

gineering De

and reduce

ocial & ge

ompleted by

portation sys

oad structur

(a) Improve

change adap

pment of clim

rs and killas

eation and p

progress tow

ompleted wit

mary

IP) financed

Internation

epartment (L

e rural pove

ender deve

y December

stem by con

res (brides/c

ed Road Co

ptation capac

mate resilien

s, ghats and

poverty allev

wards achie

thin the stipu

d by Asian

nal Fund fo

LGED) forma

erty through

elopment an

r 2018. Thi

nstructing, im

culverts), de

onnectivity;

city.

nt infrastruc

d markets. T

viation spec

eving its tar

ulated time.

Developme

or Agricultur

ally started

h sustainab

nd improve

s project w

mproving an

evelopment

(b) Improve

ture includin

The project

cially for LC

rgets. All th

nt

re

in

le

ed

will

nd

of

ed

ng

is

CS

he

Page 6: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

Land Acquisition and Resettlement Issues

So far, six sub-projects have been identified where land acquisition is required. The

CCDB is already in the process of making the Resettlement Plan based on the

detailed designs.

Also, 4 Sub-projects have been identified for Markets where some compensation for

relocation of business and loss of income is required to be paid to few affected persons. The

CCDB is preparing the estimation of such compensation through JVC and PVAT. The

recommended compensation will be paid by the LGED to the affected persons soon after the

completion of the prescribed processes.

Overview CCRIP Major achievements up to June 2015

The major achievements during this period were: (further details will be given under each

Consultant’s report):

i. Organization of Inception Workshop and Finalization of Inception Report

ii. Completion of 1st and 2nd phase Sub-Project Reports (SARs) comprising 96

packages for 12 districts under ADB funding in two subsequent phases.

iii. Completion of quarterly reports for donors on Gender and Environment as per

Gender Action Plan.

iv. Submission of IEE and EMP framework to Directorate of Environment (DOE) and

received temporary Environmental Clearance for the Project from the GoB.

v. Implementation of Upazila, Union and village level so many workshops and

training specially on climate change hazards

vi. Completion of training on Gender, Safeguard and Environment to the

stakeholders.

Page 7: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

Page 8: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

1 Purpose of the Report and Land Acquisition & Resettlement Framework

The ADB Public Communications Policy (PCP 2011) refers the Safeguard Policy Statement

(SPS 2009) with respect to information disclosure related to project safeguard

documentation states that ADB shall post on its website the safeguard documents submitted

by the borrower and/or client. These safeguard documents include Resettlement &

Indigenous Peoples Plan (RP & IPP), and the social safeguard and environmental

monitoring reports.

To comply with ADB, the CCRIP, LGED shall submit Semi-Annual monitoring report

periodically over the total implementation period of the project, covering Land Acquisition &

Resettlement issues. The CCRIP commenced on 01 January 2013, but starting of actual

works was delayed due to hiring of consultants in 27 January 2014.

The current report is the Semi-Annual Social Safeguard Monitoring Report prepared to

comply with the loan covenants covering the period from project commencement to June

2015 in a cumulative process. This report covers resettlement and social safeguard

monitoring results to comply with the spirit of ADB policy to “enhance stakeholders trust” in

and ability to engage with ADB, and thereby increase the development impact [of projects]”

in which disclosure of safeguard monitoring is a prominent aspect.

The Land Acquisition & Resettlement Framework (LARF) expresses the Government’s

commitment to avoid any negative impacts due to the project interventions or to mitigate them

ensuring that the DPs are able to maintain or improve their livelihood at the end of the project.

The document incorporates a Land Acquisition and Resettlement Entitlement Matrix consistent

with this project. The basic objectives of the LARF are to: (i) guide the EA for compensating

project Affected People properly, (ii) to serve as a binding document to ensure DPs will be

assisted and paid compensation, and (iii) to provide direction preparing, implementing and

monitoring sub-project RPs.

The Executing Agency (EA) is responsible for ensuring the preparation and implementation of

Resettlement Plans (RPs) consistent with this LARF. The LARF is a formally agreed document

between the Government and ADB. Gaps between national law and ADB policy are identified

and bridging measures are included in the Entitlement Matrix along with major types of losses

and the corresponding nature and scope of entitlements in accordance with GoB’s LAR and

ADB’s SPS 2009 relating to safeguard requirements for the project. Where the entitlement

matrix does not cover a particular impact, it can be enhanced in the resettlement plans based

on the findings of the socio-economic assessment and detailed census survey. Standards

described will not be lowered but can be enhanced in the subproject RPs as required.

The improvement works for the subprojects to be selected under different components of the

project are expected to have a limited impact as they will be carried out mostly on existing

road alignments or market footprints. The main impacts is expected to arise under the road

component in the form of land acquisition, some relocation of houses/shops/businesses, and

removal of trees with some related income loss. Other components such as improvements to

markets, and improvement of cyclone shelters will either not require any additional land or

will rely on unallocated largely unoccupied Government-owned (khas) land.

Precise identification of impacts of proposed improvements to all road subprojects is being

done during the detail design and implementation stage of the project. During project

formulation it was presumed that there will be only a small number of land acquisition and

resettlement impacts on each subproject.

Page 9: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

Social Safeguard / Resettlement Categorization

ADB's classification system

Prior to civil works implementation, all the subprojects selected for construction or development are to be Screened and Classified using ADB's classification system as follows:

• Category-A: Subprojects proposed for construction or development, will fall under this category, if, it caused a significant involuntary resettlement impacts with a physical displacement of 200 or more persons from their residences, or 200 or more persons lose 10% or more of their productive or income generating assets, or more persons or 200 or more persons experience a combination of both.

• Category-B: Any proposed subproject that includes involuntary resettlement impacts but are not deemed significant considering loss of shelter/houses or productive or income generating assets will be considered for category B.

• Category-C: A proposed subproject that has no involuntary resettlement impact.

Subprojects Categorization under CCRIP

Although there will be only a small number of land acquisition and resettlement impacts on

each subproject, it is expected that the roads component as a whole, comprising up to 100

individual subprojects, will have more than 200 people suffering significant involuntary

resettlement. It is also noted that ADB SPS 2009, SR2 Para 5 states :

“Resettlement is considered involuntary when displaced individuals or communities do not

have the right to refuse land acquisition that results in displacement”.

Accordingly the project is deemed to be in Category A for resettlement.

2 Introduction - Background and Rationale

The CCRIP aims to provide climate resilience measures that deliver a degree of climate

proofing commensurate with both the task that structures have to perform and the level of

acceptable risk as well as being sensibly within available budgets. Each of the project

components, roads; growth centers, markets; and cyclone shelters have their specific tasks

and levels of acceptable risk to the impacts of SLR, high wind, increasing temperature and

increasing likelihood of severe cyclone events. The underpinning thrust is ensuring that all

structures are constructed within a strong framework of enforced appropriate specifications

and an as-built quality audit. “Climate-proofing” measures include enhanced resilience to

present climate effects plus forecast future climate change impacts.

The impact of the project will be reduced poverty in the rural coastal districts vulnerable to

climate change and increased safety of the population during extreme climatic events. The

outcome will be enhanced climate resilience of coastal infrastructure in 12 rural coastal

districts benefiting the poor and women. This will be achieved through the following project

outputs:

• improved road connectivity;

• improved market services; and

• improved climate capacity and protection including increased availability of climate

disaster shelters, improved access to shelters and improved facilities of existing

climate disaster shelters.

Page 10: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

Output 1 - Improved Road Connectivity

The project will upgrade 130 km of upazila roads, 174 km of union roads, and 233 km of

village roads, providing year-round connectivity between agricultural production areas and

markets and to the other parts of the country. 3,050 meters of bridges/culverts will

constructed or upgraded. The road upgrading works will involve widening and raising of

embankments, with suitable slope protection against erosion and wave action; and

reconstruction or improvement of existing earthen, Herring Bone Brick, and bituminous and

concrete surfaced road sections to appropriate “climate-resilient” standards. Specific

adaptation measures to increase climate resilience have been considered for: earthworks;

pavement; and drainage. These measures include constructing the road crest levels to

600mm above the maximum normal monsoon flood level, taking account of effective Sea

Level Rise (SLR) during the next 20 years; widening the road carriageways to accommodate

forecast traffic volumes over the next 20 years; embankment protection primarily by means

of a combination of turf and shrubs, with additional geotechnical measures where there is

high risk of active erosion; and special measures adjacent to structures together with

increased cross drainage.

The road output will consist of over 100 sub-projects undertaken throughout the project area.

Alignment and cross-section design will be optimized to minimize impacts on existing

structures and land acquisition.

Output 2 - Improved Market Services

Upgraded growth centers and large markets: 88 markets (ranging from growth centre

markets to large rural markets) will be improved under the project. The market improvements

will include (where relevant) paved trading areas, sheds, water supply system, drainage

facilities, sanitation facilities, and market offices. Generally it is expected that resettlement

impacts will be negligible and land acquisition will not be necessary. In some cases, where

additional land is required it is intended that it would be unencumbered government (khas)

land.

Upgraded village markets and collection points: The project will also improve 186 community

markets and 11 women’s markets sections will be established in existing community

markets. This subcomponent will build/improve physical markets (common shed, fish shed,

open paved/raised area, women section, toilet block, internal drainage etc), build ‘commodity

collection points, and build 37 boat landing platforms (ghats). Generally it is expected that

resettlement impacts for the improved market services output will be negligible and land

acquisition will not be necessary. In some cases, where additional land is required it is

intended that it would be unencumbered government (khas) land.

Page 11: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

Output 3 - Enhanced climate change adaptation capacity

The project will strengthen the capability of LGED staff and local government units through

training and initiation of a knowledge management system, with particular emphasis on

incorporating climate resilience and adaptation measures during the design, implementation

and maintenance of rural infrastructure assets. The project will also enhance knowledge

management for climate change

The project will construct or extend around 15 multipurpose cyclone shelters; improve about

10 existing cyclone shelters and upgrade around 15 km of cyclone shelter access tracks.

Designs will take account of future sea level rise and other adjusted design requirements

due to climate change effects. A provisional sum is allocated to provide for construction of

killas in selected locations where there is a demonstrated long-term need, and sufficient land

is readily available adjacent to a new or existing cyclone shelter. Generally for existing

cyclone shelters it is expected that resettlement impacts will be negligible and land

acquisition will not be necessary. For new cyclone shelters, where land is required it is

intended that it will be unencumbered government (khas) land. Access tracks are intended to

be improved without need for land acquisition.

Page 12: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

3 Institutional Arrangements

The LGED under the Ministry of LGRD & C, Rural Development Division is the Executing

Agency (EA) responsible for implementing the RPs. LGED has established a Project

Management Unit (PMU) for the Project, headed by a Project Director (PD) who is

responsible for the overall execution of the Project. The EA also has set up a Sub-projects

Management Office (SMOs) headed by the Executive Engineer of the concerned district under

the PMU. The SMOs will prepare land acquisition (LA) plan for the land to be acquired with

the assistance from consultants for each subproject found with land acquisition &

resettlement impacts and shall submit to concern DC. M/S Christian Commission for

Development in Bangladesh (CCDP), an experienced implementing NGO (INGO) has been

hired by LGED to assist EA in implementation of resettlement program. To expedite the

process, the RP implementing NGO will assist the DC office and EA in the process of land

acquisition. A Management Support Consultant (MSC) engaged by project are assisting to

carry out a range of activities including implementing and monitoring the safeguards aspects

of the project. The Resettlement Specialist (RS) of the MSC is responsible for arranging or

carrying out the activities of preparation/updating/finalizing the RPs for the subprojects with

IR impacts based on information from the detailed engineering design documentation

prepared by the Design & Supervision Consultant (DSC).

The CCRIP project organisation is shown below:

Under the project LGED has set up a Project Management Office, (PMO) based in Dhaka. In

the project area are three Regional Project Offices (RPO) at Barisal, Madaripur and Khulna

who will coordinate the physical works at the districts (Upazilas/Thanas) in their regions.

Beside that there will be 12 PIU’s at district level by the respective Executive Engineer and

supported by the Upazila Engineers.

Page 13: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

10 

Affected Communities/ Project Affected Persons/Women’s Group/Entitled Person Representatives 

To assist LGED in achieving these objectives and physical targets there are four consultancy

services:

• Design and Supervision Consultants (DSC). HIFAB International (Sweden) has Lead

Firm of a Joint Venture.

• Management Support Consultants (MSC). HP Gauff (Germany) as the Lead Firm of

a Joint Venture.

• IFAD Individual Consultants

• Implementing NGO (M/S CCDB) for planning and implementation

4 Project Implementation

For the purposes of ensuring Safeguards, the EA has established the following institutional

arrangement:

Resettlement Plan Implementation Organogram

   

Project Director

Executive Engineer, PMU, for 

Resettlement 

Executive Engineer, SMO, LGED 

ADC (Revenue), Concerned

District 

Team Leader, RP Implementing NGO/Agency 

Resettlement Specialist (MSC) 

UZ Enggr, SMO, LGED 

SAE, SMO, LGED 

Land Acquisition Officer (Concerned

DC Office) 

MIS Specialist Area Manager, RP

Implementing Agency 

RAC GRC JVT

PVAT

Page 14: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

11 

The Ministry of LGRD through Gazette Notification has constituted required committees i.e.

Joint Verification Team (JVT), Property Valuation Advisory Team (PVAT), Grievance

Redress Committee (GRC) etc. with involvement of representatives from LGED. INGO, DC,

LGI and DPs. To ensure effective execution of all IR related tasks, capacity development

trainings both at the PMU and SMO level is needed. Table below depicts the current status

regarding some of the important actions required for the safeguard related issues.

Required Actions by EA

Current Status

Deployment & Orientation of INGO M/S Christian Commission for Development in Bangladesh deployed on 17.02.2014

Issue of Official Notification by the MLGD regarding establishement of required Committees

Already issued

Establishment of Joint Verification Committee (JVC), Property Valuation Advisory Team (PVAT), Grievance Redress Committee (GRC)

As a follow up to the Gazette Notification, JVC, PVAT and GRC are being established at the field level

Appointment of Implementing NGO for Safeguards

The Local Government Engineering Department (LGED) appointed Christian Commission

for Development in Bangladesh (CCDB) for preparation and implementation of Resettlement

Plans (RP) of Coastal Climate Resilient Infrastructure Project (CCRIP). An agreement was

signed between the Local Government Engineering Department (LGED) and the Christian

Commission for Development in Bangladesh (CCDB) on January 19, 2014. A Letter was

issued by the Project Director, CCRIP indicating Notice to proceed vide Memo No.

LGED/PD/CCRIP/INGO/2013/62/1265 dated 17-02-2014 in connection with the

commencement of the NGO services. Based on the NTP, CCDB activated the Field and

Central offices for NGO services since February 20, 2014 and informed the project authority

vide Ref. No. CCDB / CCRIP/2014/358 dated February 25, 2014.

Initial Screening of Involuntary Resettlement (IR) Impact of Subprojects

The initial step of the resettlement planning is to carry out an inception and screening survey

to identify the intensity of land acquisition and resettlement impacts of an individual

subproject (or group of subprojects) as per ADB’s SPS-2009 by using a standard IR impact

checklist form. The preliminary impact checklist form is included in Annex-. The level of

detail and comprehensiveness of the resettlement plan are commensurate with the

significance of the potential impacts and risks.

Sub-projects will most likely be combined for assessment purposes, so that a multitude of

RPs are not prepared. This will be determined as the project is implemented. Sub-projects

may be grouped by District, phasing or some other rational means, with associated RPs

developed for that group as a whole.

Page 15: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

12 

Preparation of Resettlement Plans (RP)

RPs in the prescribed ADB format are to be prepared by the Project Management Unit

(PMU) of LGED with assistance from the Management Support Consultant (MSC) supported

by the CCDB and Design & Supervision Consultant (DSC) for any subprojects which will

have land acquisition & resettlement impacts. Preparation of RPs will primarily be

undertaken by the Resettlement Specialist of the MSC. Each RP will be brought to the notice

of the relevant APs/DPs and host communities and any comments will be addressed in

subsequent revisions of the RP. The RP will be prepared in English language, with main

content to be translated in Bangla language and notified to the public (through posters

and/or resettlement booklets). The completed RP will include the census of APs/DPs, and

their entitlements to restore losses, institutional mechanisms and schedules, budgets,

assessment of feasible income restoration mechanisms, avenues for grievance redress, and

the monitoring mechanism. Each RP will be submitted to ADB for clearance prior to award of

any contract relating to the subproject.

Avoidance and Mitigation of Resettlement Impacts

LGED, through the Design & Supervision Consultant (DSC) will optimize the detailed designs

for all road subprojects (without compromising climate resilience or minimum traffic design

standards) to avoid and minimize impacts on existing buildings and land as far as practicable.

Where resettlement impacts are unavoidable, LGED will implement a process of negotiated

settlement (which may include voluntary land donation) with land/property owners following

ADB’s SPS 2009. As refusal to donate land or to enter into a negotiated financial settlement

would necessarily lead to expropriation (in order to retain climate resilience design integrity),

any subproject that entails land acquisition (either through voluntary or involuntary means) or

physical displacement will be subject to a resettlement plan (RP).

Any negotiated settlement will require adequate and meaningful consultation with affected

persons, including those without legal title to assets, with such consultation fully documented.

A negotiated settlement should ensure an adequate and fair price for affected land and/or

other assets i.e replacement cost of the affected properties. The LGED will ensure that these

negotiations with affected persons openly address the risks of asymmetry of information and

bargaining power of the parties involved in such transactions. For this purpose, the LGED will

be required to engaged an independent external party M/S CCDB to document the negotiation

and settlement processes.

In cases requiring negotiation and donation of land, the LGED will ensure that the following

aspects are addressed :

a. Verification and documentation that land required for the project is sold without

coercion;

b. Verification that nobody will be impoverished by the land donation (more than 5% of

total land holding donated will trigger livelihood restitution measures to be specified in

a resettlement plan);

c. Verification that land donation will not displace tenants, if any, from the land;

d. Meaningful consultation has been conducted with all affected persons. Documented

verification of the agreement of affected persons under any sub-project.

e. Separate discussions to be held with women and minority groups as required to

facilitate meaningful participation in the process of obtaining their consent.

Page 16: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

13 

Overview of Major Safeguard Related Activities - Inception to June, 2015

The project has allotted 311 subprojects of different categories (small, medium and large)

under 12 costal districts of three regions (Barisal, Khulna and Madaripur). 84 subprojects of

IFAD have already been visited again by the field of CCDB in the respective regions. As the

prescribed requirements of LGED, CCDB is in the process of preparing the next DDRs as

well as RAPs. It is hoped that within very short time, CCDB will accomplish the projected

tasks.

Table-1: Category-wise progress in respect of DDR for the Sub-projects

Sl No Category of Funding Agencies

Target of subproject

Cumulative achievement

Progress in percentage

01 Cyclone Shelter-KfW 20 20 100%

02 Growth Center- ADB 66 49 72.06%

03 Road- ADB 46 35 85.37%

Total 132 104 85.81%

The Table - 1 above reflects that out of 20 cyclone shelters of KfW, CCDB prepared DDRs

for all the sites (100%). On the other hand, progress of growth centers and roads is 72.06%

and 85.37% respectively.

Table-2: Region-wise progress of Sub-project activities

Sl No Region Target of sub-project

No of DDR prepared

No of RAP prepared

Remarks

01 Barisal 162 59 N/A RAP is to be

prepared soon.

02 Khulna 91 30 N/A

03 Madaripur 58 15 N/A

Total 311 104

The Table depicts that CCDB prepared DDRs of 59 subprojects from Barisal region, 30 from

Khulna and 15 from Madaripur region. List of the subprojects which have already been

submitted is annexed under Annexure-1.

Table-3: Progress of Sub-project activities on the basis of donors / agencies:

Sl No Financial agencies

No of Planned Sub-project

No. of DDR prepared

No of Sub-project activities completed

01 ADB 112 Roads & GC 84

02 IFAD 179 Markets - Reconnaissance visit continues

03 KfW 20 Cyclone Shelters 20 Completed

Total 311 104

Page 17: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

14 

The Table-3 reflects three financial agencies: ADB, IFAD and KfW are supporting to CCRIP.

The major supports are provided by the ADB (110 Subprojects). Meanwhile, CCDB

completed 84 subprojects of ADB, 20 cyclone shelters from KfW and paid reconnaissance

visits to 84 sites of IFAD.

Acquisition and Resettlement Issues

So far, acquisition of land and resettlement issues are faced for 10 Sub-projects in

three regions. The Indicative Milestones for various activities / processes are listed

in the Table below. The CCDB staff in the respective regions are working to identify

and screening losses and impacts, preparation of RP and Grievance Redressal in

respect of the identified sub-projects.

Six Sub-projects have been identified where land acquisition is required. The CCDB

is already in the process of making the Resettlement Plan based on the detailed

designs. Also, 4 Sub-projects have been identified for Markets where some compensation

for relocation of business and loss of income is required to be paid to few affected persons.

The CCDB is preparing the estimation of such compensation through JVC and PVAT. The

recommended compensation will be paid by the LGED to the affected persons soon after the

completion of the prescribed processes. However, the indicative milestones for key activities

in respect of the assessment, implementation of RPs are mentioned in the Table.

Due Diligence Report

Following on from the initial checklist, Due Diligence Reports have been prepared by the

Implementing NGO (CCDB) to the PMO.

Way Forward – Proposed Activities

• Preparation of questionnaire for Socio-Economic Survey of the Affected People

• Pre testing of questionnaire for affected People

• Preparation of Resettlement Plan

• Formation of Different Committees for resettlement activity in the field

• Monitor the Function of Different Committees for Resettlement

• Preparation of Identity Cards for the affected people

• Monitor the opening of Bank Account for the EPs

• Monitor the deposition of compensation to the Bank Account of EPs

• Conduct field visit as and when required.

Page 18: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

15 

CCRIP - INDICATIVE MILESTONES FOR SUBPROJECTS

List of Sub-Projects Requiring Land Acquisition / Resettlement ( Roads & Bridges)

Sl. No.

District Upazila Proposed Sub-project

Requirement of RP/DDR

Primary Milestones

Assessment Detailed Design

Updating RP

Submission of LA Proposal to DC

Implement RP

Beginning Construction

Monthly status of LA and compensation / other comments

1. Jahlakati Jhalakati Sadar

Jhalakati RHD-Bermahal via Himanandakati Road

Required Included in SAR Phase1

14.07.201509.08.2015

20.09.2015 01.09.2015 15.08.2016 01.09.2016 LA for 4.267 acres for 2.30 km road length is with the Ministry for Approval.

2. Gopalganj Kotalipara 39 meter Girder Bridge, UZ 35

Required Included in SAR

11.08.2015 20.09.2015 Not Required

15.01.2016 01.03.2016 Negotiated land settlement for small portion of land required

3. Gopalganj Kotalipara 90 m Girder Bridge UZ36

Required Included in SAR

09.08.2015 20.09.2015 01.09.2015 15.01.2016 01.03.2016 Section 6 served to EP by Deputy Commissioner Office

4. Gopalganj Kotalipara Approx. 450m of road UZ36

RP Required Included in SAR

15.06.2015 30.10.2015 15.11.2015 30.04.2016 01.09.2016 Partly new alignment partly very narrow existing road

5. Bhola

Borhanuddin Joyardhon Khal (90m bridge) – UZ 12b

RP Required 30.09.2015 20.08.2015 31.10.2015 15.11.2015 29.02.2016 01.04.2016 Initial assessment done by CCDB,

6. Barisal Banaripara Banaripara – Harta Road UZ 02

RP Required 30.09.2015 Additional survey and designs are required 31.10.2015

RP may be Required

01.10.2015 15.01.2016 01.03.2016 LA not required for new proposed road length of about 5.9 km. Compensation for trees etc may be required

Page 19: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

16 

List of Sub-Projects Requiring Land Acquisition / Resettlement ( Markets)

Proposed Sub-project

Primary Milestones

Sl no

District Upazila Requirement of RP/DDR

Assessment Detailed Design

Updating RP

Submission of LA Proposal to DC

Implement RP

Beginning Construction

Monthly status of LA and compensation / other comments

7 Satkhira Kaliganj

Nalta Growth Centre, Pkg.No.

CCRIP/ADB/SAT/GC/2014/W-08

RP Required 30.09.2015 28.10.2014

PBC to recommend compensation to the PMO

15.11.2015

Not required

PMO to pay compensation

by 15.01.2016

02.02.2015

Compensation for relocation of business and loss of income

8

Satkhira

Debahata

Subarnabad Growth Centre, Pkg. No. CRIP/ADB/SAT/GC/ 2014/ W-09

RP Required 30.09.2015 03.11.2014

PBC to recommend compensation to the PMO

15.11.2015

Not required PMO to pay compensation by 15.01.2016

02.02.2015

Compensation for relocation of business and loss of income

9 Khulna Rupsha Alaipur Growth Centre, Pkg. No.CCRIP/ADB/SAT/GC/ 2014/W-05

RP Required 30.09.2015 28.10.2014

PBC to recommend compensation to the PMO

15.11.2015

Not required PMO to pay compensation by 15.01.2016

05.02.2015

Compensation for relocation of business and loss of income

10 Bagerhat Chatterhat Chatterhat Growth Centre, Pkg. o.CCRIP/ADB/SAT/GC/ 2014/W-06

RP Required 30.09.2015 07.07.2014

PBC to recommend compensation to the PMO

15.11.2015

Not required PMO to pay compensation by 15.01.2016

19.02.2015

Compensation for relocation of business and loss of income

Page 20: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

17 

AggrievedPersons 

Application submitted to GRC through

INGO

Scrutinization  of Complaints by GRC

GRC members: LGED Representative • INGO Representative • LGI Representative

Referred to

DC

Complaints under Arbitration or Existing LA Law

Not under Arbitration or Law

to be settled as per RP policy

Not Redressed

GRC Hearing within 21days of Lodging the claim Redressed

Recommendation for

Compensation Claim PD for

Approval

INGO for

Payment

Seeking Legal

Settlement Decision Accepted

District

Judge

Grievance Redressal Mechanism

The project established grievance redress mechanism to receive and facilitate resolution of

AP’s concern, complaints and grievance about the project safeguards performance of the

subproject. If anybody losses assets, livelihoods or any things else due to subproject but it

does not properly address who can claim to Grievance Redress Committee for proper

compensation. The CCDB will play the vital role in the grievance redress process shown in

Flow Chart below.

Figure : Grievance Redress Flow Chart

Page 21: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

18 

Development of CMIS

CCDB developed MIS for determining the losses, disbursing the compensation

payment and affected households. The data generated by the field offices are used

as technical inputs of the MIS. The MIS Specialist and the Database Manager have

been developing the MIS at the central office of Dhaka.

Formation of Focus Group

The Focus Groups are formed with the affected persons who received notices under

different sections. These notices were served to them for collecting compensation

from DC offices. Focus Group consists of about 20 members headed by a Chairman

and assisted by a Secretary nominated by the members themselves. The Chairman

conducts the meetings. The Secretary convenes the meetings preferably once in

two months. Records the minutes of the meetings are maintained by the Secretary.

The Resettlement Workers of CCDB facilitate the meetings by providing necessary

information and technical assistance. In addition, CCDB is starting the formation of

focus group in different subproject sites.

Stakeholders’ Meetings

Since inception CCDB started establishing and closer face to face contact with the

PAPs/ beneficiaries. The Stakeholders / Focus Group meetings is an entry point

where APs / EPs discussed the issues related resettlement, relocation,

compensation, gender, project assistances and grievances. These are APs social

institutions for ventilating resettlement issues services need from time to time.

Table-04: Region-wise no of project beneficiaries attended in the stakeholders’

meetings

Sl No

Region No of stakeholders’ meetings

No of participants Remarks

Male Female Total

01 Barisal 03 55 - 55 Females are not interested to participate to the public meetings on Sariah grounds

02 Khulna - - - -

03 Madaripur - - - -

Total 03 55 - 55

At the stakeholders’ meetings, different issues are discussed and beneficiaries are also

interested to assist from any corner to implement CCRIP project. The table shows that

maximum male participants (55) are attended to the meetings.

Page 22: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

19 

Pictures: Stakeholder Meetings – Project Areas

 

Distribution of Booklets/Brochures

The Information Booklets (Annex- 3 ) developed by the project in Bangla and other

brochures are being distributed among stakeholders / beneficiaries/ UP Chairman / UP

members of subproject sites at the Focus Group / stakeholders’ meetings. The entitled

persons are addressed with this instrument. Through the booklets / brochures, entitlements

of the EPs are disclosed. The EPs are concerned about their Payment of Compensation

both from the Deputy Commissioner and CCDB / LGED office. The above booklet reflects

detail guidelines how to address their concern. It was common practice that their

entitlements against AG are to be delivered to them immediately after receiving the CCL

from DC office. CCDB will be extended support to them for getting CCL from DC offices.

Gender Development

The gender development is a priority concern in CCRIP because the women EPs or

beneficiaries of 12 coastal districts enjoy low social status in decision-making process and

household financial management. In most cases, they are unable to set agenda for their day

to day lives. They are often denied the right to share their assets and properties. They even

lack of basic IGP skills. In the socio-political affairs and participation in development

activities, they are mostly ignored and sidelined. As a result, they are deprived from getting

equal access to available opportunities and assets. In view of their vulnerability, CCDB has

considered gender equity as a priority area of action.

CCDB made all out efforts to make the women more participative in development action.

Women have been encouraging to sit in the Stakeholders / Focus Group meetings so that

they could articulate their voices alongside with man. The oppression of male over female

and female over male are also discussed in the stakeholder’s meetings upfront. The

attendance in the meetings and their active participation are duly encouraged. However, the

women participation is rather low and needs to be further increased to create awareness

about the project activities.

Page 23: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

20 

5. Proposed Major Resettlement Activities in 2015

• Preparation of Questioner for Socio-Economic Survey of the Affected People

• Pre testing of Questioners for affected People

• Preparation of tables for Resettlement Plan

• Preparation of Resettlement Plan

• Formation of Different Committees for resettlement activity in the field

• Monitor the Function of Different Committees for Resettlement

• Preparation on Identity Card for affected people

• Monitor the opening of Bank Account for the EPs

• Monitor the deposition of compensation to the Bank Account o EPs

• Conduct field visit as and when required.  

Page 24: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

21 

Annex - 1 : List of the Sub-projects which Due Diligence Report has already

been prepared by the CCDB

Sl No

Subproject Name Location Type Category Submitted

01 Syed Jafor GPS Patuakhali/ Dashmina DDR Small August 03, 2014

02 Soladana Bazar Khulna/Paickgacha DDR Small August 03, 2014

03 Rahuthor Bazar Gopalgonj/Kasiani DDR Small August 03, 2014

04 Sutabaria Circle GPS Patuakhali/Galachipa DDR Medium August 03, 2014

05 Uttar-Pachim Banshbaria GPS

Do DDR Small August 03, 2014

06 Nizamul Chatra GPS Do DDR Medium August 03, 2014

07 Maidhya Banshbaria GPS Patuakhali/

Dashmina

DDR Small August 03, 2014

08 Takerhat-Uttarpara Hat Gopalgonj/Muksudpur DDR Small August 03, 2014

09 Baishtabok GPS Barguna/B. Sadar DDR Medium August 26, 2014

10 Uttar-Chotto Labongola RPS

Do DDR Medium August 26, 2014

11 Adompur GPS Patuakhali/Dashmina DDR Small August 26, 2014

12 Sabupura Bazar Adarsho Biddaloy

Patuakhali/Bauphal DDR Medium August 26, 2014

13 Sarikal GC to Mahilara RHD Road

Barisal/Gournadi DDR Medium September 28, 2014

14 Kakchira Majher Char PS Barguna/Patharghata DDR Medium August 26, 2014

15 Amragachiya Salehiya Complex cum Cyclone Shelter

Barguna/Amtoli DDR Medium August 26, 2014

16 Kazikanda GPS cum Cyclone Shelter

Patuakhali/Rangabali DDR Small September 9, 2014

17 Joyalbhanga RPS cum Cyclone Shelter

Barguna/Taltoli DDR Medium September 9, 2014

18 Chor Chapli GPS cum Cyclone Shelter

Patuakhali/Kalapara DDR Medium September 9, 2014

19 Kaialghata GPS cum Cyclone Shelter

Barguna/Betagi DDR Medium September 9, 2014

20 Fultala Madrasha cum Cyclone Shelter

Barguna/Betagi DDR Medium September 9, 2014

21 Dhandi High School cum Cyclone Shelter

Patuakhali/Bauphal DDR Small September 9, 2014

Page 25: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

22 

Sl No

Subproject Name Location Type Category Submitted

22 Char-Unda GPS cum Cyclone Shelter

Patuakhali/Rangabali DDR Small September 9, 2014

23 Chinabunia GPS cum Cyclone Shelter

Patuakhali/Rangabali DDR small September 9, 2014

24 Gahinkhali Bazar cum cyclone shelter

Do DDR Medium September 9, 2014

25 Paisar Hat Barisal/Agoiljhara DDR Small September 28, 2014

26 Abdoler more-Majhirgati Access Road

Khulna/Terokhada DDR Large September 28, 2014

27 Panchpara GC Pirojpur/Sadar DDR Small September 28, 2014

28 Jagannathkati Growth Center

Pirojpur/Nesarabad DDR Small September 28, 2014

29 Chaterhat GC-Banshbaria GC to Baddir Bazar Road

Bagerhat/Mongla DDR Large September 28, 2014

30 Tala UZ HQ-Kolaroa UZ via Dalua GC-Patkhalghata Road

Khulna/Terokhada DDR Medium September 28, 2014

31 Gaila RHD-Dhamura GC via Mistripara Hat & Shaheber Hat GC Road

Barisal/Agailjhara DDR Small November 11, 2014

32 Gulsakhali GC to Dauatala GC via Trearkahli Bazar Road

Pirojpur/Mathbaria DDR Medium November 11, 2014

33 Moukoron GC-Khataltali GC via Hazirhat Road

Patuakhali/Dumki DDR Small November 11, 2014

34 Langutia GC – Bankerhat GC via Sreepur Bazar –Adarsha Gram Bazar Road

Barisal/Mehendiganj DDR Small November 11, 2014

35 Kapalir Hat Growth Center Pirojpur/Bhandaria DDR Small November 11, 2014

36 Baddamary Rural Market Bagerhat/Mongla DDR Small November 11, 2014

37 Patkakhali RHD-Nali GCC Road

Barguna/Sadar DDR Medium December 24, 2014

38 Dapdapiya Ferry Ghat - Ranir Hat Road

Jhalokati/Nalchity DDR Small December 10, 2014

39 R&H Bypass road to Kahtalbari Ferryghat road via Kutubpur Growth Centre and Bangla Bazar Road

Madaripur/Shibchar DDR Medium December 10, 2014

40 Radhagonj UPC-Doglas High School - Bhangerhat GC Road

Gopalgonj/Kotalipara DDR Medium December 10, 2014

41 Kamarkhali GC-Baherchar GC via Sarsi Police Farry

Barisal/Bakerganj DDR Medium December 10, 2014

Page 26: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

23 

Sl No

Subproject Name Location Type Category Submitted

road

42 Chatterhat Rural Market Bagerhat/Mongla DDR Small December 10, 2014

43 Depara Bazar Growth Center

Bagerhat/Sadar DDR Small December 10, 2014

44 Sreenadi GC Madaripur/Sadar DDR Small December 10, 2014

45 Batbunia Growth Center Khulna/Dacope DDR Small December 10, 2014

46 Purbo Damuddya Bazar Shariatpur/

Damuddaya

DDR Small December 24, 2014

47 Chandrapur GC Shariatpur/Sadar DDR Small December 24, 2014

48 Nalta GC Satkhira/Kaliganj DDR Small December 24, 2014

49 Damuddaya GC to Dasherjungle GC Road

Shariatpur/

Damuddaya

DDR Medium January 27, 2015

50 Fasiatala Hat Madaripur/Kalkini DDR Small January 27, 2015

51 Dasherjungle GC Shariatpur/Gosairhat DDR Small January 27, 2015

52 Perikhali Bagerhat/ Rampal DDR Small January 27, 2015

53 Balarjore GC Jhalokati/Rajapur DDR Small January 27, 2015

54 Bukhainagar Rural Market Barisal /Sadar DDR Small January 27, 2015

55 Takerhat Shankardipar Bazar

Madaripur/Rajoir DDR Small February 02, 2015

56 Subarnabad Satkhira/ Debhata DDR Small February 05, 2015

57 Alipur Khulna/Rupsha DDR Small February 16, 2015

58 Bangdah Rural Market Satkhira/Bangdah DDR Small February 16, 2015

59 Chandpura Sluice Bazar Patuakhali/ Dashmina DDR Small February 16, 2015

60 Shasigonj Rural Market Bhola/ Tazumuddin DDR Small February 16, 2015

61 Bangla Bazar Bhola/ Daulatkhan DDR Small March 02, 2015

62 Naikati Hat Jhalokati/Sadar DDR Small March 02, 2015

63 Illisha Hat Bhola/ Bhola Sadar DDR Small March 02, 2015

64 Mollar Hat Rural Market Jhalokati/Nalchity DDR Small March 15, 2015

65 Boalia Bazar Barisal /Bakergonj DDR Small March 15, 2015

66 Kholpotua Barguna/ Bamna DDR Small March 15, 2015

67 Amtali Hat Rural Market Barguna/ Sadar DDR Small March 19, 2015

68 Bogir Hat Barguna/ Taltali DDR Small March 19, 2015

69 Hazir Hat Rural Market Patuakhali/ Bauphal DDR Small March 19, 2015

70 Pingolkathi Bazar Barisal/Gournadi DDR Small March 19, 2015

71 Baherchar Bazar Patuakhali/ Rangabali DDR Small April 02, 2015

72 Ulania Growth Center Patuakhali/Galachipa DDR Small April 02, 2015

Page 27: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

24 

Sl No

Subproject Name Location Type Category Submitted

73 Kakchira Hat Barguna/Pathorghata DDR Small April 02, 2015

74 Banaripara - Harta Road Barisal/ Banaripara DDR Medium April 09, 2015

75 Gabkhan Gouaton Shekherhat Amrajhuri Road

Jhalokati/ Jhalokati Sadar

DDR Small April 09, 2015

76 Bhola-Tulatalihat Road Bhola/ Sadar DDR Small April 09, 2015

77 Bangla Bazar – Bagmara- Sharif K- Banker hat Road

Bhola/Bhola Sadar DDR Small May 12, 2015

78 Parulia GC to Subornabad GC Road

Satkhira/Debhata DDR Large May 12, 2015

79 Gazaria RM Bhola/Bhola Sadar DDR Small May 12, 2015

80 Fakirhat Bazar Bhola/Charfasson DDR Small May 12, 2015

81 Sarafpur Bazar Khulna/Dumuria DDR Small June 01, 2015

82 Khalil Nagar Satkhira/Tala DDR Small June 01, 2015

83 Shekpura RM Kulna/Terokhada DDR Small June 11, 2015

84 Soroshkathi RM Satkhira/Kalaroa DDR Small June 17, 2015

85 Gazalia Bazar Bagerhat/Kachua DDR Small May 21, 2015

86 Majhirgati-Bamondanga-Katega GC Road

Khulna/Digholia DDR Small June 17, 2015

87 Khanpur Baliadanga GCCR-Uzirpur GC via Gobindokati Hat Road

Satkhira/Kaliganj DDR Medium June 11, 2015

88 Noabenki – Munshiganj – Harinagar – Bhetkhali – Zada Hat - Nurnagar Hat - ZR at Khanpur Road

Satkhira/Shymnagar DDR Small June 01, 2015

89 Mongla Thana HQ- Chaterhat CARE Bazar Road

Bagerhat/Mongla DDR Small June 17, 2015

90 Reyenda GC – Upazila HQ- Jibondari-Rajapur GC Road

Bagerhat/ Sarankhola DDR Medium May 21, 2015

91 Takerhat GC- Sreenodi GC –Charmuguria-Khagdi R&H Road

Madaripur/Rajoir DDR Large May 21, 2015

92 Naria to Battalarhat Road Shariatpur/Naria DDR Medium May 17, 2015

93 Muksudpur R&H to GC Kisnadia Bahirbag Road

Gopalgonj/Muksudpur DDR Medium May 17, 2015

94 Angaria - Chandgapur GC Road

Shariatpur/Sadar DDR Medium May 21, 2015

95 Mohongonj Hat – Babugonj Girls School

Barisal/Babugonj DDR Medium June 17, 2015

Page 28: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

25 

Sl No

Subproject Name Location Type Category Submitted

Road

96 Borhangong GC – Moazzem Hat GC Via Talukderhat Road

Bhola/Borhanuddin DDR Medium May 21, 2015

97 Morichbunia UP to Bottolbunia GC via Hazi Khali Bazar

Patuakhali/Sadar DDR Medium June 11, 2015

98 Gachani GC – Hazirhat GC Road

Patuakhali/

Dashmina

DDR Medium June 01, 2015

99 Bogir Hat GC – Taltali GC via Taltali College

Barguna/Taltali DDR Large June 11, 2015

100 Jagannath Kathi Bazar – Sreeramkathi via Alkirhat Ganakpara Dhaihari Road

Pirojpur/Nesarabad DDR Large June 17, 2015

101 Telikhali GC – Safa Bazar RHD Road

Pirojpur/Bhandaria DDR Large June 01, 2015

102 Balarampur Natun Bazar LRM

Muladi/Barisal DDR Small July 13, 2015

103 Kamarkhali Hat LRM Bakerganj/Barisal DDR Small July 13, 2015

104 Dauri Bazar LRM Lalmohon/Bhola DDR Small July 13, 2015

   

Page 29: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

26 

Prescribed Formats for Monitoring for Resettlement Activity

Monitoring Format for Resettlement activity for the Sub project

Name of Sub Project

Amount of Land Required

Number of people affected

Status of Land Acquisition

Progress of Census

Preparation of Resettlement Plan

Formation of Different Committees

No of Grievance Received

No of Grievance resolved

Amount of Compensation Paid (%)

Continuation

Name of Sub Project

Type of Compensation

Preparation of ID card

Opening of Bank Account

Status of Compensation

payment

Clearance of site on the field

Remarks

 

 

 

 

 

Page 30: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

27 

Potential Monitoring Indicators

Type of Monitoring Basis for Indicators Remarks

Budget and Time Frame

• Have all land acquisition and resettlement staff been appointed and mobilized for the field and office work on schedule?

• Have capacity building and training activities been completed on schedule?

• Are resettlement implementation activities being achieved against agreed implementation plan?

• Are funds for resettlement being allocated to resettlement agencies on time?

• Have resettlement offices received the scheduled funds?

• Have funds been disbursed according to RP?

• Has the social preparation phase taken place as scheduled?

• Has all land been acquired and occupied in time for project implementation?

Implementing NGO Mobilized on field

No

Not Applicable (NA)

NA

NA

NA

NA

NA

Delivery of AP Entitlements

• Have all APs received entitlements according to numbers and categories of loss set out in the entitlement matrix?

• Have APs received payments on time?

• Have APs losing from temporary land borrow been compensated?

• Have all APs received the agreed transport costs, relocation costs, income substitution support and any resettlement allowances, according to schedule?

• Have all replacement land plots or contracts been provided? Was the land developed as specified? Are measures in train to provide land titles to APs?

• How many APs households have received land titles?

• How many APs have received housing as per relocation options in the RP?

• Does house quality meet the standards agreed?

• Have relocation sites been selected and developed as per agreed standards?

• Are the APs occupying the new houses?

• Are assistance measures being implemented as planned for host communities?

• Is restoration proceeding for social infrastructure and services?

• Are APs able to access schools, health services, cultural sites and activities?

• Are income and livelihood restoration activities being implemented as set out in the income restoration plan, for example utilizing replacement land, commencement of production, numbers of APs trained and provided with jobs, micro-credit disbursed, number of income generating activities assisted?

NA

NA

NA

NA

NA

NA

NA

NA

NA

NA

NA

NA

NA

NA

Page 31: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

28 

Type of Monitoring Basis for Indicators Remarks

• Have affected businesses received entitlements including transfer and payments for net losses resulting from lost business and stoppage of production?

NA

Consultation, Grievance and Special Issues

• How consultations taken place as scheduled including meetings, groups, community activities? Have resettlement leaflets been prepared and distributed?

• How many APs known their entitlements? How many know if they have been received?

• Have any APs used the grievance redress procedures? What were the outcomes?

• Have conflicts been resolved?

• Was the social preparation phase implemented?

• Were special measures for indigenous peoples implemented?

NA

NA

On processes

NA

NA

NA

Benefit Monitoring • What changes have occurred in pasterns of occupation, production and resource use compared to the pre-project situation?

• What changes have occurred in income and expenditure patterns compared to pre-project situation? What have been the changes in cost of living compared to pre-project situation? Have APs incomes kept pace with these changes?

• What changes have taken place in key social and cultural parameters relating to living standards?

• What changes have occurred for vulnerable groups?

Not Applicable

NA

NA

NA

Page 32: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

29 

Annex - 2: Official Notification

 

Page 33: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

30 

Page 34: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

31 

Annex - 3: Resettlement Guidelines in Bangla

Page 35: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

32 

Page 36: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

33 

Page 37: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

34 

Page 38: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

35 

Page 39: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

36 

Page 40: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

37 

Page 41: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

38 

Page 42: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

39 

Page 43: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

40 

Page 44: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

41 

Page 45: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

42 

Page 46: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

43 

Page 47: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

44 

Page 48: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

45 

Page 49: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

46 

Page 50: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

47 

Page 51: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

48 

Page 52: Safeguards Monitoring Report · LOCAL GOVERNMENT ENGINEERING DEPARTMENT RDEC BUILDING, LEVEL-3, AGARGAON, DHAKA-1207 Semi-Annual Social Safeguard Monitoring Report (Cumulative) Reporting

49