Upload
vancong
View
214
Download
0
Embed Size (px)
Citation preview
L O C A L P O R T O F P O R T L A N D B A Y
S A F E T Y & E N V I R O N M E N T
M A N A G E M E N T P LA N
R e v i e w e d M a r c h 2 0 1 7
VERSION 6 MARCH 2017 2
Document Title:
Local Port of Portland Bay – Safety and Environment Management Plan V.6
Document Status and Reference:
Officers authorised to make changes and update the Local Port of Portland Bay Safety and Environment Management Plan are:
Chief Executive Officer, Glenelg Shire Council Director, Assets Local Port of Portland Bay Manager Local Port of Portland Bay Port Officer/s
Document Status and Record:
Date
Revised Details Revised
Amended by Verified by Version
April 2010 C. Malone, Author - New document G.Bebbington 1
February
2013
Whole of document – to comply with
Dec’12 Ministerial Guideline changes
C.Malone S.Deam 2
March
2014
SEMP reviewed to include change in
Port boundary
C.Malone S.Kerrigan 3
March
2015
Annual SEMP review P. Roberts S. Kerrigan 4
March
2016
Annual SEMP review P. Roberts S. Kerrigan 5
March
2017
Annual SEMP review G. Bebbington P Healy 6
Document Distribution List
Recipient Issue Status
Local Port of Portland Bay
Manager
V.N. 1 2 3 4 5 6
I.N. A A A A A A
Date Oct’10 Feb’13 March 14 March 15 March 16 March 17
Department of Economic
Development, Jobs, Transport &
Resources. Local Ports Division
V.N. 1 2 3 4 5 6
I.N. B B B B B B
Date Oct’10 Feb’13 March 14 March 15 March 16 March 17
Port of Portland –
Harbourmaster
V.N. 1 2 3 4 5 6
I.N. C C C C C C
Date Oct’10 Feb’13 March 14 March 15 March 16 March 17
Worksafe
V.N. 1 2 3 4 5 6
I.N. D D D D D D
Date Oct’10 Feb’13 March 14 March 15 March 16 March 17
VERSION 6 MARCH 2017 3
Contents
1. Introduction .............................................................................................................. 4
1.1 Objectives .......................................................................................................5
1.2 Scope ..............................................................................................................5
1.3 Local Port of Portland Bay Physical Boundaries .............................................5
1.4 Key Activities ...................................................................................................7
2. Local Port of Portland Bay Health Safety & Environment Policy ............................. 9
3. Roles and Responsibilities .................................................................................... 10
3.1 The Port Manager and Organisational Structure ........................................... 10
3.2 Government Agencies ................................................................................... 11
3.3 Service Providers, Permit Holders and Recreational Users .......................... 12
4. Legal and Other Requirements ............................................................................. 12
5. Health, Safety Hazards & Environment Aspects and Impacts .............................. 13
6. Health, Safety and Environment Management Program ....................................... 15
6.1 Local Port of Portland Bay Key Performance Indicators ............................... 16
6.2 Local Port of Portland Bay - OH&S Hazard and Environment Risk Register ..... 17
6.3 Risk Register – Residual High Risks ............................................................. 22
7. Emergency & Accident Preparedness and Response ........................................... 22
7.1 Emergency Planning ..................................................................................... 22
7.2 Incident Management.................................................................................... 23
8. Implementation, Review and Revision of SEMP ................................................... 24
8.1 Health, Safety and Environment Procedures, Instructions and Guidelines ... 24
8.2 Involvement of Port Users and Service Providers ......................................... 25
8.3 Monitoring and Measurement ....................................................................... 26
8.4 Communication and Reporting ...................................................................... 26
8.5 Competence Awareness and Training .......................................................... 26
8.6 Non-conformity, Corrective and Preventive Action ........................................ 26
8.7 Internal and External Auditing ....................................................................... 27
8.8 Management Review .................................................................................... 27
Appendix 1 Local Port of Portland Bay Gazetted Port Boundary Map ..................... 28
Appendix 2 Inspection Sheets ................................................................................. 29
Appendix 3 List of relevant Legislations, Policies and Guidelines ........................... 32
Appendix 4 Glenelg Shire Council Incident Reporting Form .................................... 36
VERSION 6 MARCH 2017 4
1. Introduction
As of 1 July 2009, the Glenelg Shire Council accepted appointment as Manager of the Local Port
of Portland Bay (Trawler Wharf) on behalf of the Crown (under the Crown Land Reserves Act
1978). Council adopted a management structure with Council as Local Port Manager with advice
as required from a skills-based Advisory Committee.
Glenelg Shire Council acts as Port Manager to manage and administer the Local Port of Portland
Bay striving to ensure the secure, safe, efficient and environmentally responsible operation of the
Local Port.
A significant change to the Local Port of Portland Bay occurred in 2012/13 with the Local Port
boundary extended to cover all the waters within Council’s Committee of Management area. This
included the newly opened 70 berth Portland Bay Marina, the existing old marina jetty, the swing
mooring area and the existing boat ramp. The new four-lane boat ramp commissioned in 2014.
This Safety and Environment Management Plan (SEMP) was initially developed in 2010 and was
based on the Ministerial Guidelines for Port Safety and Environment Management Plans (2005).
These Guidelines, issued under section 91G(1) of the Port Management Act1995 provide
direction and advice on the form, content, method and process for preparing plans including
stakeholder involvement, consultation with those potentially affected by the plans and the
publication and availability of management plans. These Guidelines were superseded by
Ministerial Guidelines Port SEMPs November 2012 and the SEMP has been updated
accordingly.
The SEMP is a dynamic document that will change as a consequence of regular review and
revision. The maintenance of this SEMP is an important component of the ongoing process of
continuous improvement for safety and environmental management.
The aim of this SEMP is to present an integrated system for managing and improving
environmental and safety performance at the Local Port of Portland Bay and to promote quality
safety and environment risk management across all aspects of port activities. Beneficiaries of the
plan will be the local port management, service providers, commercial users, visitors and the
community.
Through the development of the SEMP, the Glenelg Shire Council has formed a systematic
approach to the identification and management of safety and environmental hazards and risks.
The SEMP reflects the Local Port of Portland Bay’s commitment to sustainable management and embodies the key environment and safety principles relating to:
• protection and improvement of the Local Port of Portland Bay environment
• provision and maintenance of a safe working and recreational environment
• safety and environmental management of visitors to the Port
• continuous improvement to safety and environmental performance at the Port
• establishing effective safety and environmental management as a key component of the
local port’s business management plan.
The Glenelg Shire Council, as Local Port Manager is responsible for the operation and
maintenance of the trawler wharf, marina, old marina jetty, swing moorings, the old and new boat
ramps and navigational aids. Duties include planning, issuing permits, allocating moorings and
maintenance of wharves, jetties, and other facilities.
VERSION 6 MARCH 2017 5
1.1 Objectives
In compliance with the legislative requirements of the amended Port Management Act1995
(PMA), and section 91D (1) of the PMA, the Local Port of Portland Bay Safety & Environmental
Management Plan is required to:
a) identify by a description, map or plan the area or areas of the port lands and waters to
which it applies.
b) identify the nature and extent of the hazards and risks associated with the operation of the
port.
c) assess the likely impact of those hazards and risks on the port and the surrounding area.
d) specify the measures and strategies to be implemented to prevent or reduce those hazards
or risks.
e) nominate the person who is responsible for implementing those measures and strategies.
f) set out the processes to be followed to involve tenants, licensees and service providers in
the port with the implementation of the management plan.
g) set out the procedure to be followed for implementing, reviewing and revising the
management plan.
In addition to these objectives the SEMP also aims to:
• Integrate environment and safety considerations, where practical, into the development and
operation of the Port
• Further characterise safety and environmental issues associated with future development at
the Port
• Improve interaction between stakeholders on issues and safety and environmental
management
• Apply sustainable development principles at the Port
• Create opportunities for the continued improvement of safety and environmental
performance at the Port.
1.2 Scope
The SEMP addresses safety and environment hazards which apply to the activities occurring at
the Local Port of Portland Bay. The scope of the SEMP encompasses activities that are the
responsibility of the Port Manager, including commercial operators, recreational users and
general public. Their activities pose potential safety and environment risks to the surrounds
(water, beaches, etc.) and the people using them. Activities such as fishing, waste management
and vehicle access are addressed in the SEMP as are activities in the port waters e.g. boating
and fishing, recreational swimming and movement of catch between vessels and the wharf.
1.3 Local Port of Portland Bay Physical Boundaries
The Local Port of Portland Bay is bounded by a line from the eastern side of the Trawler Wharf to
a point just north of the wharf, then west to the Old Marina Jetty then north to the Lee Breakwater
wall and to the high tide mark on the foreshore. It encompasses the Trawler Wharf and
associated Pontoon, Swing Moorings the new Portland Bay Marina and all Boat Ramps. The
image below outlines the boundaries of the Local Port of Portland Bay and the Commercial Port
which is run by the Port of Portland.
VERSION 6 MARCH 2017 7
1.4 Key Activities
1.4.1 Trawler Wharf
The Trawler Wharf is home to commercial fishing trawlers and cray fishing boats which
have permanent berths on the Trawler Wharf and Floating Pontoon. There are also
designated itinerant berths allocated for visiting commercial vessels. Visiting vessels such
as Oil and Gas Rig tenders, Government boats, i.e. Customs and DPI Fisheries, Tall Ships
and Oceanographic Research vessels utilize the Local Port of Portland Bay itinerant
facilities.
Key activities undertaken on the Trawler Wharf include but are not limited to:
• Unloading of fish from trawlers into refrigerator trucks. There can be up to 5 trucks
loading at any given time
• Stevedoring
• Refueling – by mobile fuel tanker
• Netting repairs
• Wire works.
• Minor vessel maintenance
• Minor sand blasting works
• Crane works
• Crew changeovers
• Recreational fishing
From March to June the Local Port can be home to up to 6 - 8 visiting squid vessels that
use the Trawler wharf as their base for the length of the squid season. Infrequent visitors
also include tall ships, tugs, rig tenders, dredges and patrol boats.
1.4.2 Marina
The new marina changed the view of Portland Harbour with boat owners securing berths.
Yachts, charter boats, recreational cruisers and even historic ‘couta boats’ are now berthed
bringing the marina to near capacity. The new marina is taking pressure off the trawler
wharf where berthing of non-commercial visiting vessels was previously the only option in
the harbor.
1.4.3 Boat Ramps
With the commissioning of the new four lane boat ramp in July 2014, there is now be
enough ramp capacity to cater for the peak trailer boat period during the Southern Bluefin
tuna run from March to July. The old and new ramps both have parking areas that along
with the overflow car park caters for the maximum expected number of users.
1.4.4 Old Marina Jetty
The Old Marina jetty was popular as a less costly alternative for boat owners to the Portland
Bay Marina. Boats were berthed on Mediterranean moorings. The jetty was an aging
facility, and in January 2015 a Structural Integrity Report was undertaken to enable Council
to fully understand its maintenance requirements.
Consequently, action was taken to prohibit swimming and other water activities underneath
the Jetty. The entire jetty was then declared unsafe and condemned. Tenders were called
and the jetty was demolished in 2016. Plans are underway to build a replacement jetty.
VERSION 6 MARCH 2017 8
1.4.5 Swing Moorings
After a safety inspection by divers in March 2014, it was deemed that all the swing
moorings required replacement. The old ones were disconnected from their buoys and
dropped to the bottom. A program will be developed to remove the old and abandoned
tackle on the seabed. Currently only two swing moorings exist. There is now a moratorium
on further swing moorings until a review of harbor facilities is undertaken.
1.4.6 Aids to Navigation
There are three navigation aids to be maintained as part of the key activities in the Local
Port of Portland Bay. These are an essential part of navigational safety in the bay. They
consist of two East Cardinal Marker Buoys, indicating safe water to the east of the spoil
ground in the north-western corner of the bay and a Special Marker Buoy indicating the
entrance to the Swing Mooring area.
VERSION 6 MARCH 2017 9
2. Local Port of Portland Bay Health, Safety & Environment Policy
The Glenelg Shire Council is responsible for the management and administration of the Local
Port of Portland Bay. The port is a commercial and public facility designed to provide for
commercial needs of the fishing industry, and recreational opportunities for the Glenelg Shire
community and visitors to Portland.
Glenelg Shire Council makes the following commitments with respect to environmental care, and
the health and safety of all those managing, using and enjoying the Local Port and its facilities:
• Develop, implement and maintain processes for health and safety hazard, and
environmental impact, identification, assessment and control
• Maintain compliance with applicable Health, Safety and Environmental Legislation and
regulations, and other requirements to which Council subscribes
• Apply Glenelg Shire Council’s Organisational Policy (i.e. OHS Policy)
• Establish measurable objectives and targets that are designed to eliminate or minimise
safety and health hazards and prevent injuries or illness for all Port users
• Establish measurable objectives and targets that are designed to improve the health of the
local environment and prevent pollution, including oil spills, waste contamination and the
introduction of damaging exotic biodiversity
• Communicate and encourage safety and environmental awareness and responsibility for all
Port users, and
• Regularly inspect the condition of facilities and equipment to ensure they are safe, effective
and considerate of the health of the environment
To achieve these commitments, Glenelg Shire Council will prepare and maintain a Safety &
Environment Management Plan (SEMP) that is subject to independent certification against
requirements of the Port Management Act 1995.
This plan is endorsed by:
Paul Healy
Director Assets
VERSION 6 MARCH 2017 10
3. Roles and Responsibilities
The management of the Local Port of Portland Bay has been the responsibility of the Glenelg
Shire Council since 1 July 2009. The roles of management responsibility within the port structure
include liaison with Port service providers and permit holders, maintaining public amenities and
wharf structure, implementing the SEMP, associated controls and procedures.
3.1 The Port Manager and Organisational Structure
Chief Executive Officer
Director
Assets
Local Port of Portland Bay
Manager
Port Officer
Local Port of Portland Bay
Local Port of Portland
Bay
Advisory Committee
Glenelg Shire Council
Port Officer
Local Port of Portland Bay
3.2 Government Agencies
The key Government agencies and their role in administering safety and environmental
legislation of specific relevance to the Local Port of Portland Bay activities are listed below.
These agencies will be involved in the ongoing implementation of the Plan.
Department of Economic Development, Jobs, Transport and Resources (DEDJTR)
The Department of Economic Development, Jobs, Transport and Resources (DEDJTR) took
over management and administration responsibilities for Local Ports from DTPLI from 1
November 2014. Processes from Council’s point of view as Port Manager for the Local Port
of Portland Bay will remain the same as they were under DTPLI.
Environmental Protection Authority (EPA)
EPA Victoria’s purpose is to protect, care for and improve the environment. EPA work with
the community, industry and other groups to build a sustainable, healthy future. The EPA
has statutory authority and enforcement functions such as delivering pollution abatement
notices and charging persons who are responsible for environmental pollution. In addition
the EPA also undertakes research and modeling work and manages sophisticated programs
to monitor the quality of Victoria’s air, land and water.
Worksafe Victoria
Worksafe Victoria is responsible for enforcing safety legislation, such as the following within
Victoria:
• Occupational Health & Safety Act 2004
• Occupational Health & Safety Regulations 2007
• Dangerous Goods Act 1995
• Equipment (Public Safety) Act 1994
Worksafe’s role is to ensure the Local Port of Portland Bay is a safe and healthy workplace
for employees, contractors and members of the public.
Maritime Safety Victoria (MSV)
Maritime Safety Victoria is a branch of Transport Safety Victoria and is the state’s marine
safety agency which is responsible for establishing the regulatory environment under which
all port waters operate. MSV is responsible for the administration of the Marine Safety Act
2010 (Vic). The Department of Transport’s Security and Emergency Management Division is
responsible for pollution response in State waters (3 nautical mile limit).
Victoria Police
The Water Police have the primary role of coordinating all marine incidents involving
recreational vessels, yachts and commercial vessels within Victorian Coastal and inland
waters.
VERSION 6– MARCH 2017 12
3.3 Service Providers, Permit Holders and Recreational Users
The Local Port of Portland Bay accommodates eight (8) trawlers from the local trawler fleet,
four (4) cray boats on the adjoining floating pontoon, two (2) cray boats in the new marina
and around one hundred (100) permanent recreational and charter vessels on berths and
moorings. These vessels all occupy berthing areas, some of which have designated utility
access to occupants and signage. Large Itinerant fishing vessels are berthed on the north
eastern section of the Trawler Wharf, and the northern end as required. Utility access is also
available there.
Visiting vessels such as Government boats, i.e. Customs and DPI Fisheries, Oil and Gas Rig
Tenders, Barges and Tall Ships utilise the Local Port of Portland Bay Trawler Wharf and
large recreational vessels are accommodated in the Marina.
The Local Port of Portland Bay is also extremely popular with recreational fishermen, as well
as school groups who often utilise the Port for education and recreation programs.
4. Legal and Other Requirements
The development of the Local Port of Portland Bay SEMP has been undertaken in the
context of the State and Federal environmental and safety legislative framework that
governs Victorian ports. The provisions under the Port Safety Act 2010 are intended to
complement existing legislation rather than duplicate it. As such the safety and
environmental requirements do not supersede other legislative requirements.
The Local Port of Portland Bay manages access and understanding of Safety,
Environmental and Legal requirements through the maintenance of its Health and Safety
Hazards Register and Environmental Aspects Register.
These Registers include the identification of applicable health, safety and environmental
legislation and associated regulations, policies, codes of practice, guidelines and other legal
requirements under International, Federal and State laws against each identified health &
safety hazard and environmental aspect/impact. In addition, the Registers identify non-
legislative requirements (known as “Other Requirements”) to which the Local Port of
Portland Bay subscribes.
The Registers also document the requirements of each piece of legislation/regulation as they
apply to the activities associated with each health and safety hazard and environmental
impact.
The International, Federal, State and local legislation, conventions, regulations, policies,
guidelines etc. of most relevance to Safety and Environment Management for the Local Port
of Portland Bay are listed in Appendix 3.
VERSION 6– MARCH 2017 13
5. Health, Safety Hazards & Environment Aspects and Impacts
Risk Assessment Process
The risk assessment process involves comparing the level of risk found during the analysis
with previously established risk criteria. Each risk will be expressed as a value of Very High,
High, Medium or Low risk. The outputs of this process will create a prioritised list of risks (or
risk register), that require further action. Focus will be placed on Very High and High risks
that are deemed to be significant. Low and Medium risks may fall into an acceptable level of
risk category. These risks may require monitoring and periodic review to ensure they remain
acceptable. A review of all risks will be conducted annually or if there is a major change in
the nature of activity conducted at the port.
The matrix was drawn from the Ministerial Guidelines: Port Safety and Environment
Management Plans November 2012.
Likelihood Consequence
Insignificant Minor Moderate Major Catastrophic
Almost
Certain
Moderate High High Extreme Extreme
Likely Moderate Moderate High High Extreme
Possible Low Moderate High High High
Unlikely Low Low Moderate Moderate High
Rare Low Low Moderate Moderate High
The identification of hazards includes safety reviews, consultation, discussions, comment
and contribution from council employees and stakeholders (e.g. Local Port of Portland Bay
Advisory Committee, contractors and regulatory bodies and industry organisation etc.) and
consideration of the health and safety risks knowledge generated by the implementation and
maintenance of the SEMP (e.g. training, monitoring, incident reporting, audits and
management review). Health, Safety and Environment hazards and risks are documented
according to local port activities in the Risk Register. This Register is a fluid document
continually recording hazards and risks associated with Port operations as they are identified
and refined.
In accordance with section 91D (1) – a SEMP must:
(h) “set out those measures (if any) that the port manager intends to implement to
eliminate or reduce the safety and environmental risks and hazards…”
(i) “set out the key performance indicators through which the port manager can
assess the extent to which the implementation of the management plan achieves the
safety and environment management planning objectives…”
VERSION 6– MARCH 2017 14
Hazards and associated risks are assessed considering both the “likelihood” and “consequence” of occurrence as shown in Tables 1, 2 and 3.
Table 1 – Likelihood table
DESCRIPTOR LIKELIHOOD OF EVENT
Almost Certain Is expected to occur in most circumstances
Likely Will probably occur in most circumstances
Possible Might occur at some time
Unlikely Could occur at some time
Rare May occur only in exceptional circumstances
Table 2 – OHS Consequence
DESCRIPTOR EXAMPLE CONSEQUENCE
Insignificant Activities do not cause any personal risk and will not result in injury
Minor Activities may cause injuries or personal health problems requiring local first aid and no rehabilitation period
Moderate Activities may cause injuries or health problems requiring medical attention and where short rehabilitation period is required.
Major Activities may cause serious injuries or health problems requiring hospitalisation and a significant period of rehabilitation before being able undertake normal activities or return to work.
Catastrophic Activities that could cause death or permanent disability prevent any undertaking of normal activities or return to work.
Table 3 – Environmental risk consequence
DESCRIPTOR EXAMPLE CONSEQUENCE
Insignificant Activities do not adversely impact on the environment
Minor Activities may cause an environmental impact that can be immediately cleaned up with no residual impact
Moderate Activities may cause an environmental incident that can be cleaned up over a short period of time with minimal residual adverse impact.
Major Activities may cause a considerable environmental impact that is of public interest and which may only be cleaned up over a prolonged period of time and may result in considerable residual adverse impact.
Catastrophic Activities may cause a major environmental incident that is of national or international concern; requires an extensive period (years) to clean up; causes major long term adverse impact on the environment.
VERSION 6 – MARCH 2017 15
6. Health, Safety and Environment Management Program
OCCUPATIONAL HEALTH, SAFETY AND ENVIRONMENT OBJECTIVES PROGRAM
Objective Target Actions Responsibility Time frame
Develop IMS
Prepare first SEMP Publish SEMP Port Officer Complete March 2010
Certify SEMP 3rd
party Audit Port Officer March 2016
Maintain Certification Annual reviews of SEMP Port Officer March Annually
Minimise Pollution
Risks
Establish Permit System for bunkering
Develop permit system with fuel contractors Port Officer &
Fuel Contractors Complete
2010
No fugitive waste Segregated waste disposal facilities - waste oils are not stored
on the Wharf. Port Officer N/A
Reduce risk of diesel spill to Portland Bay
Undertake upgrade works on wharf edge to eliminate risk of puncturing fuel tanks during berthing
Port Officer – design & manage DTPLI - funding
Complete 2013
Minimise
Safety Risks
Establish pier capping Undertake upgrade works on wharf edge to eliminate risk of
slips & falls – DSE funded Port Officer & DSE - design &
funding Complete
2012
Eliminate slips & trips & falls As above; and work with Commercial users to develop safe
works systems, i.e. ropes, etc. Port Officer & Port Commercial
Users Complete 2011
Develop loading & unloading procedure
Establish safe work systems in conjunction with contractors for loading & unloading
Port Officer & Commercial users Ongoing
Prepare traffic management plans
Monitor movement of traffic for commercial activities & recreational users. Prepare plans
Port Officer Ongoing
Construct storage area Install storage shed to store safety equipment Port Officer Complete June 2010
Load limits Determine load limits for vehicles & ensure compliance with
appropriate signage Port Officer Complete Dec 2010
Develop procedure for electrical insp/works
Develop procedures and inspection regimes for electrical testing, monitoring & maintenance
Port Officer Ongoing
Objective 4 Consultation
Encourage Community consultation/input
Develop webpage for Local Port of Portland Bay; include feedback form for Community input. Bi-monthly newsletter
developed for users. 1/4ly meetings held with users to discuss any issues.
Port Officer & Admin Officer
Complete 2013
In accordance with section 91CA the SEMP objectives are:
(a) “promoting improvements in safety and environmental outcomes…”
(b) “promoting and facilitating the development, maintenance and implementation of systems that enable
compliance with various safety and environmental duties that apply to the operation of the port…”
(c) “promoting an integrated and systematic approach to risk management in relation to the operation of the Port”.
VERSION 6 – MARCH 2017 16
6.1 Local Port of Portland Bay Key Performance Indicators
The Ministerial Guidelines: Port Safety and Environment Management Plans were revised
late in 2012 and required the addition of Key Performance Indicators (KPIs) from the Port
Managers. The KPIs will be used by the port managers to assess the extent to which
implementation of the management plan achieves the safety and environment management
planning objectives set out in section 91CA of the Port Management Act 1995. The overall
effectiveness of this management plan in mitigating risk to safety and the environment will be
assessed annually.
The KPIs for the local Port of Portland are:
KPI Management Strategy
1
Inspections of Local Port
(including weekends and
public holidays) – daily
Daily inspection forms completed and any hazards
identified are controlled.
2 Bi-monthly Inspection of lighting, Including AtoN
Bi- monthly inspections undertaken to ensure all lights
and AtoN are operational.
3
Maintenance electrical
services inspection – Bi-
annually
Trawler wharf. Bi-annual inspection undertaken, report
received and any non-conformances identified are
repaired. Visual inspections undertaken 6-monthly on
marina.
4
Trawler wharf - Underwater
inspection of floating
pontoon and anodes –
annually
Annual diving inspection undertaken, report received and
any non-conformances programmed for repair.
5 Underwater inspection of
AtoN – annually
Annual diving inspection undertaken, report received and
any repairs undertaken.
6
Timely completion of
incident reports –within 24
hours or next working day
Incident/hazard reporting and investigation report
completed for all incidents within Local Port.
7 Allocation of berthing with
minimal delay
Inspections undertaken, any berthing issues addressed. A Port Officer on call 24 hours a day for any berthing queries to be addressed without delay. New booking software in use in 2106.
8
Conducting Performance
Appraisal for port staff to
monitor performance and
provide training and
development opportunities -
annually
Performance Appraisals completed by 30 June each
year.
Training and development to be listed as a priority, with
identified training undertaken within agreed timeframe.
VERSION 6 – MARCH 2017 17
6.2 Local Port of Portland Bay - OH&S Hazard and Environment Risk Register
Activity Related facility Hazard Likelihood Consequence Risk Level
(Score) Responsible Officer Controls Status
Residual Risk (controls in place)
PORT MANAGEMENT
Wharf structure, design and layout Trawler wharf
Slip, trip and fall hazards Possible Catastrophic Extreme Local Port Officers Modification works on wharf edge undertaken for Extreme risk being top row of h-beam.
Complete Low
Slip, trip and fall hazards Possible Catastrophic Extreme Local Port Officers
Further modification works on wharf edge level 2 & 3 of h-beams required to alleviate collision risk with vessels with bulbous bows.
Complete Low
Collision of moving plant with personnel Possible Moderate Extreme All Port Users
Unloading contractors and Local Port users to have SWMS and traffic plans in place for activities undertaken on wharf.
Complete Low
Collision of moving plant on wharf Possible Major Extreme All Port Users
Contractors and Local Port users to have SWMS in place for activities undertaken on wharf. Traffic Plans to be submitted
Complete Low
Collision of boats when berthing Unlikely Moderate High Vessel Operators
Speed restrictions, adherence to boating regulations. Licenced operators (confirmed through User Agreement requirements)
Process in Place Low
Collision of boats with wharf when berthing Possible Moderate Medium Local Port Authorised Officers &
Skippers
Modification works to be undertaken by Dec'10. DSE to provide funding. Council providing funding, preparing tender supervising works
Complete Medium
Provision of waste disposal and recycling facilities
Trawler wharf Health hazards due to disease, bacterial infections
and fumes, explosion and fire. Possible Moderate High All Port Users
No hazardous or dangerous goods stored in Local Port. Skip provided for waste disposal. Waste oil disposal is the responsibility of vessel owners & not to be put in skip
Ongoing Medium
Provision of skip bins @ fish cleaning tables
Boat ramps Health hazards due to disease, bacterial infections
and chemical fumes, explosion and fire. Unlikely Moderate High Local Port Officers
Skips provided for fish waste only. Waste and recycle bins provided for general waste. Skips regularly emptied and cleaned. Regular inspections of skip bins to monitor waste.
Ongoing Low
Vehicle access, operations, movements, egress and parking
arrangements
Local Port Collision with cyclists, pedestrians, infrastructure or
other vehicles Unlikely Catastrophic High All Port Users incl. members of public
Speed restrictions, signage, and adherence to traffic regulations, line marking, and designated car parking areas.
Complete
Medium
Parking strategy developed to provide clear and concise direction for all users including cars with boat trailers and members of public using Local Port facilities
Complete
Trawler wharf Wharf weight load limits not being recognised Rare Catastrophic Low All Port Users incl Contractors Load limit area designated, i.e. line marked & signage in place
Complete
Refueling, fuel containment and supply
Local Port Inadequate or inappropriate storage of flammable
goods Rare Major Low Vessel Operators
Flammable goods to be stored as per Regulations.
Complete Medium
Trawler wharf Inadequate or no spill containment or spill response
materials Unlikely Moderate High Vessel Operators & Contractors
Spill containment to be used when fueling, or working with oil or chemical. Contractors transferring fuel to vessels must have a refueling permit. No hazardous chemicals stored on wharf. Signage erected. Spill containment kit stored in emergency shed. Fire extinguishers in place on marina. Hose reels on trawler wharf
Complete High
Local Port Explosion or fire Possible Major Extreme Vessel Operators & Contractors Training of users. Regular supervision. Provision of fire extinguishers and hose reels.
Complete Medium
Portland Bay Marina Explosion or fire. Fuel spill. Possible Moderate High Fuel suppliers and users
Fuel supplier to comply with AS1940-2004. Supply spill containment. Tank is double bunded. Inventory taken by supplier on fuel quantities to ensure no leakage exists.
No fuel facility as yet
N/A
VERSION 6 – MARCH 2017 18
6.2 Local Port of Portland Bay - OH&S Hazard and Environment Risk Register
Activity Related facility Hazard Likelihood Consequence Risk Level
(Score) Responsible Officer Controls Status
Residual Risk (controls in place)
Pollution and spill response
Local Port
Oil, fuel or chemical spills
Possible Moderate High All Port Users
Immediately report to Port of Portland Harbour master so POLREP can be completed.
Complete
Low
Trawler wharf
Spill containment to be used when fueling, or working with oil or chemical. Contractors transferring fuel to vessels must have a refueling permit. No hazardous chemicals stored on wharf. Signage erected. Spill containment kit stored in emergency shed.
Low
Portland Bay Marina Possible Moderate High All Port Users Spill containment kit provided. Education process regarding reporting processes.
Complete
High
Local Port Spill incident at Commercial Port - impacting
operation of Local Port Possible Catastrophic High
All Port Users including Commercial Port
Adherence to Local Port EMP and Commercial Port EMP. Participation in Pollution Control Committee. Education for all Port Users of process in event of incident
Ongoing
Provision of public access and recreational facilities
Local Port Inadequate dissemination of health & safety
information, signage etc. Possible Major High All Port Users
Comprehensive signage in place. Daily inspections Ongoing
High
Local Port Inadequate provision for disabled persons
Possible Major High All Port Users
Designated car parking for disabled persons on Trawler wharf, Marina and existing boat ramp. To be included in parking strategy for new marina and new boat ramp parking. Complete Low
Local Port Inadequate provision of safeguards, bollards, sea
to wharf ladders etc.
Possible Moderate High All Port Users
Ladders in place on Trawler wharf and Marina. Designated workplaces established when works underway. Signage. Daily Inspections
Complete - ladders. Ongoing
Inspections
Trawler wharf Deficient or defective safety/emergency response
equipment Possible Catastrophic Extreme Port Officer
Emergency Plan to be developed; emergency response equipment to be stored on wharf for immediate access
Complete Low
Provision of electrical power outlets
Trawler wharf
Wiring contact with water Unlikely Catastrophic Extreme Port Officer Regular inspections to be undertaken by qualified contractor. All electrical equipment connected to shore power must be tagged by a qualified person.
Ongoing Medium Damage to power outlets due to incorrect coupling and usage
Likely Moderate Extreme All Port Users
Portland Bay Marina Damage to power outlets due to incorrect coupling
and usage Likely Moderate Extreme All Port Users
All electrical equipment connected to shore power must be tagged by a qualified person. Inspected on entry and annually by Port Officer
Ongoing High
Portland Bay Marina Trawler Wharf
Slip, trip & fall over power leads on wharf connected to vessels
Possible Moderate High Port Officer
Assess usage and connection to shore power. Regular inspections. Ensure walkways clear of electrical leads/trip hazards
Ongoing Medium
Berth maintenance
Local Port Slip, trip and fall hazards
Unlikely Major High Port Officer/ Contractor
Wharves and pontoons to be kept clear of obstacles as far as practicable. Any ropes required to be stored on the wharf to be layed as far out of walkway as possible.
Ongoing Medium
Portland Bay Marina Injury due to deficient or no maintenance regime (or
program)
Regular maintenance inspections to be carried out. Works prioritized according to risk, and budget allocation.
Ongoing Low
Trawler wharf Injury due to deficient or no maintenance regime (or
program)
Maintenance inspections to be undertaken as per construction manual. Non conformances to be addressed as a priority
Inspections undertaken
Low
Fixed and floating plant maintenance
Portland Bay Marina
Plant failure or Injury due to deficient or no maintenance regime (or program)
Unlikely Major High Port Officer
Inspected as part of monthly inspection program.
Inspections undertaken
Low Boat ramp pontoons
Transit Jetty Jetty to be added to maintenance inspections program
Complete Low
VERSION 6 – MARCH 2017 19
6.2 Local Port of Portland Bay - OH&S Hazard and Environment Risk Register
Activity Related facility Hazard Likelihood Consequence Risk Level
(Score) Responsible Officer Controls Status
Residual Risk (controls in place)
Trawler wharf Unlikely Major
Inspections to be undertaken as per construction manual; subsequent non conformances to be addressed as a priority
Inspected annually Low
Navigation Buoys Unlikely Major High Bi-monthly night-time inspection of lights, annual underwater inspection and regular cleaning.
Ongoing Low
Emergency management
Trawler wharf Deficient or defective safety/emergency response
plan
Possible Major Extreme Port Officer
Emergency Plan developed (Sub plan to be listed in Glenelg Shire Council's Emergency Management Plan)
Plan completed and in place
Low
Local Port Injury due to deficient or no emergency response
procedure Glenelg Shire Council’s emergency plan to be reviewed to include expanded Local Port facilities, i.e. Marina, Boat Ramps, Old Marina Jetty, Swing Moorings
Complete High
Portland Bay Marina Deficient or defective safety/emergency response
plan Complete High
Issue, approve and manage permits for high risk activities undertaken on
the Local Port for individuals or organisations
Local Port
Falling from heights, crane collision with vehicles, falling items
Possible Major Extreme Port Officer Develop a crane permit system for all users/crane activities in Local Port
Permit system in place
High
Falling objects, weld flash, sparks, burns, fire Possible Major Extreme Port Officer Develop a permit system for hot works being undertaken within the Local Port
Permit system in place
Medium
Information provision
Local Port
Community communication, consultation, public access to trawler wharf management information
and Council staff contact details, open and transparent sharing of trawler wharf related news
Rare Insignificant Low
Port Officer
Webpage in place. Feedback provisions to be developed; Signage on wharf advising staff contact details. Regular email contact with permanent users regarding activities and developments on the wharf. Media releases issued for significant events or closures affecting traffic flow on the wharf. Bi-monthly newsletter distributed to all Local Port users.
Complete Low
Website Rare Insignificant Low Completed. Low
Communication and Consultation Rare Insignificant Low News releases
undertaken Low
Commercial Fishing Operations Local Port Ballast water uptake and discharge – introduction of
exotic marine species Possible Major Extreme Vessel Operators
Dumping of Ballast water not permitted in Local Port Waters. Participation as requested by EPA in studies regarding Marine Pest transfer between Ports. Notify DSE if any detected
Monitored in daily inspections
Low
Vessels berthing Local Port Collisions Unlikely Moderate High Vessel Operators
Speed restrictions, adherence to boating regulations. Licenced operators (condition in User Agreement requirements)
Monitoring ongoing. User Agreements in
place
Medium
Boat maintenance
Trawler wharf Personal injury/strain Possible Moderate High Vessel Operators & Contractors
SWMS for loading & unloading developed. Conveyors to be used when reasonably practicable to do so.
Completed. Process reviewed during inspections.
Medium
Trawler Wharf Portland Bay Marina
Spills Possible Moderate High Vessel Operators & Contractors
Bunding to be used for maintenance works, SWMS to be submitted by contractors. Spill containment located on Trawler wharf and marina
In place. Medium
VERSION 6 – MARCH 2017 20
6.2 Local Port of Portland Bay - OH&S Hazard and Environment Risk Register
Activity Related facility Hazard Likelihood Consequence Risk Level
(Score) Responsible Officer Controls Status
Residual Risk (controls in place)
Commercial plant & equipment maintenance (e.g. nets, lines, pots,
buoys etc.) Trawler Wharf Slip, trip and fall hazards Possible Major Extreme Vessel Operators & Contractors
Designated work area to be utilised for netting, etc. as per User Agreement. Appropriate traffic control to be used i.e. witches hats, bunting. Work areas to be kept clean and free of debris at all times.
In place & reviewed during daily inspections
Medium
Heavy commercial vehicles on wharf loading and unloading
Trawler Wharf
Collision Possible Major Extreme Contractors
Traffic Management plan & controls to be in place. Contractors SWP to be obtained. Wharf to be closed off during times of peak operation, i.e. multiple unloading activities such as squid season
Process in place. Low
Manual Handling Possible Major Extreme Contractors
Unloading crews to be trained in manual handling procedures. Conveyors (or cranes) to be used when practical to do so. For unloading from cray vessels and loading of bait, trolleys to be used.
Process in place. Low
Slip, trip and fall hazards Possible Catastrophic Extreme Port Users & Contractors Traffic Management plan & controls to be used; SWMS to be developed for process
Process in place.
Low
Wharf weight load limits not being recognised Rare Catastrophic Low All Port Users Signage, line marking advising weight limits. Contractors aware of restrictions
Complete
Operation of Local Port work boat Local Port Incident or injury through operation of vessel Unlikely Moderate Medium Port Officers Safety Management Plan and Safe Work Procedure developed for vessel
Complete Medium
PUBLIC ACCESS & USE
Fishing from wharves
Trawler Wharf Slip, trip and fall hazards Possible Moderate High Vessel operators & Members of the
public
Wharf areas to be kept clean & free of debris, ropes, etc. as far as reasonably practicable. If ropes must be kept on wharf, to be moved out of walkway as far as reasonable practicable
Monitoring ongoing with daily
inspections
Low
Portland Bay Marina Slip, trip and fall hazards Possible Moderate High Vessel operators & Members of the
public Fishing from Marina is prohibited
Monitoring ongoing with daily
inspections
Boating, sailing canoeing etc.
Collision with submerged obstructions,
infrastructure, etc. Rare Major Low Members of the public
Recreational boating not permitted in Local Port area. Signage on wharf outlines permitted vessels. Regular inspections by authorised officers.
Ongoing Deficient, defective or no signage or navigational
aids Rare Major Low Port Officer
Collision with commercial vessels Rare Major Low Members of the public
Capsize or swamping of vessel Rare Major Low Members of the public
Diving Local Port
Diving in shallow water
Possible Major High Port Authorised Officers, All Port Users,
Vic Police
Jetty Jumping, diving, swimming, snorkeling is not permitted from Trawler wharf. Diving is not permitted from jetties. Signage review underway to determine lower risk areas for swimming within Local
Process in place. Decompression illness (bends)
Deficient, defective or no signage or navigational aids
Medium
VERSION 6 – MARCH 2017 21
6.2 Local Port of Portland Bay - OH&S Hazard and Environment Risk Register
Activity Related facility Hazard Likelihood Consequence Risk Level
(Score) Responsible Officer Controls Status
Residual Risk (controls in place)
Collision with submerged obstructions or swimmers
Port. Integrated Local Port review being undertaken in conjunction with DEDJTR re options Regular patrols by Authorized officers & Victoria Police, public awareness.
Medium
Swimming/Snorkeling/ Jetty Jumping Local Port
Drowning or injury due to strong currents, inclement weather or a lack of experience or knowledge
No swimming or diving signage... Diving permitted for authorised wharf inspections by suitably licenced operators engaged by Council's Authorised Officers - SWMS for activities to be submitted prior to these works being undertaken, and all commercial operators to be notified of works being undertaken. PPE and navigational aids to be used at all times. Authorised diving events permitted - permits issued by Port Officers.
Process in place. High
Injury from falling objects underneath jetties
Deficient, defective or no signage or navigational aids
Vessel collision with submerged obstructions or swimmers
Deficient, defective or no signage or navigational aids
Public access - walking/sightseeing Local Port
Slip, trip or fall hazards Possible Catastrophic Extreme All Port Users Signage, line marking, work areas to be designated & restrict public access with ppe, i.e. traffic cones
Complete Low
Deficient, defective or no signage or navigational aids
Possible Minor High All Port Users
Work areas to be kept clean & free of debris, regular inspections of surfaces for potholes, slippery surfaces
Process in place.
Low
Public access - via vehicles Local Port Collision, deficient signage Possible Catastrophic Extreme Port Officers Signage, line marking, designated car parking
Complete Low
VERSION 6 – MARCH 2017 22
6.3 Risk Register – Residual High Risks
The outputs of the Risk assessment process have created a prioritised list of risks that
require further action. Focus is placed on High risks that are deemed to be significant. Low
and Medium risks may fall into an acceptable level of risk category. These risks may require
monitoring and periodic review to ensure they remain acceptable. A review of all risks is to
be conducted annually or earlier if there is a major change in the nature of activity conducted
at the port.
Major risks, including actions to be followed up are:
1. Swimming/snorkeling/jetty jumping within Local Port – includes risk of drowning,
injury, collision with vessel or submerged objects, damage to moored vessels.
This matter is currently being reviewed in conjunction with several other Victorian
Local Ports. It is a state wide issue and proving almost impossible to enforce. Options
being pursued include installation of a designated floating pontoon for swimming and
jumping off – no diving will be permitted. Currently being compared to existing risk.
2. Pollution and spill response – spill incidents at Commercial Port impacting on
operation of Local Port.
Emergency Management Plan for Local Port that has been developed needs to be
expanded to include new Local Port Area. Also further education and consultation with
Commercial Port regarding incidents which occur, that impact on the day to day
operations of the Local Port.
3. Provision of electrical power outlets – including wiring contact with water; damage to
power outlets due to incorrect coupling and usage; and slips trips & falls over power
leads on wharf connected to vessels.
Ongoing education process with permanent users of the wharf in relation to power
usage and requirements for leads to be tagged. Part of new user’s induction process.
JSA’s undertaken with contractors working for Port Management.
7. Emergency & Accident Preparedness and Response
7.1 Emergency Planning
An Emergency Management Plan has been developed for the Trawler Wharf within the
Local Port of Portland Bay. That plan includes the operations and activities within the Local
Port and based upon adopted risk management principles to meet our commitment to the
safety of all persons who enter for business operations and for the welfare of the wider
community. This plan now needs to be expanded to include new the Local Port area.
Appropriate contact details and responsibilities are documented in regard to emergency
services, authority’s roles in incidents that may occur within the Local Port, e.g. Victorian
Water Police and Port of Portland in a water incident. The Local Port also works with and
liaises with the Portland Coastguard in assisting with emergency responses that may impact
on the Local Port’s operation. This can involve meeting the Coastguard boat after it has
retrieved a vessel and is towing it back into the Local Port or determining a suitable berth for
boats involved in incidents.
VERSION 6 – MARCH 2017 23
The Local Port of Portland Bay lies within the Municipal area of the Glenelg Shire Council
and their Emergency Management Plan is referenced so that the Local Port of Portland
Bay’s Emergency Management Plan is consistent in application and operation.
The Local Port of Portland Bay’s Safety and Environment Management Plan will be reviewed
annually. The Local Port of Portland Bay’s Emergency Management Plan is integrated into
the SEMP.
7.2 Incident Management
The Glenelg Shire Council maintains an Incident Management Register to track safety and
environment incidents.
The Port of Portland’s Harbour master must be notified on 5525 0900 if a fuel/oil spill or
navigational incident occurs in the waters of the Local Port and/or adjacent areas.
The Port of Portland is responsible for coordinating emergency response activities in this
instance, and determines the appropriate incident level and will be responsible for scaling an
incident up or down as may be required. The Victorian Marine Pollution Contingency Plan is
the basis for all emergency management principles.
The Local Port of Portland Bay Officer must be notified of any contamination that occurs to
the Local Port Area and/or adjacent areas, and the responsible persons must arrange clean-
up to the reasonable satisfaction of the authorised officer or alternatively the Port Officer will
arrange clean up at the cost of the User.
Port Users are required to report any notable incident involving injury to persons or damage
to property and/or near misses immediately to the Port Officer.
Refer Appendix 4 – Incident Report.
VERSION 1 – MARCH 2017 24
8. Implementation, Review and Revision of SEMP
The Glenelg Shire Council acting as Port Manager on behalf of the Crown established under
the Crown Land (Reserves) Act 1978, to manage and administer the Local Port of Portland
Bay will be responsible for the implementation of this Plan.
The Port Officer under delegation carries out the development and implementation process.
Following assessment in this Plan, associated levels of risk will identify what controls are put
in place. Extreme and high levels of risk will be addressed foremost, and referred to the
Department of Economic Development, Jobs, Transport and Resources (DEDJTR) for
further funding if required to implement control measures through the annual budget
process.
The SEMP will be audited every three years, with the document reviewed annually. A copy of the annual review will be provided to DEDJTR if required.
8.1 Health, Safety and Environment Procedures, Instructions and Guidelines
The Local Port of Portland Bay operates under procedures, instructions and guidelines that
have been prepared to ensure that activities undertaken within the Local Port are planned
and undertaken according to specified conditions. These conditions include:
• Operating instructions and safe work procedures for unloading.
• Refueling processes and permits.
• Crane permits
• Job Safety and Environment Analyses (JSEAs) with contractors Hot Work Permit
Forms.
• Incident forms.
• Berthing forms for itinerant users.
• The induction process for new users.
• Communication Strategy.
• Emergency Management Plan (EMP)
In accordance with section 91E (1) A SEMP must be audited to determine whether:
(b) “the plan has been prepared in accordance with any Ministerial guidelines”.
In accordance with section 91HB:
(1) “The port manager must make an annual report to the Minister and any bodies
that are prescribed by the regulations on the safety and environmental performance
outcomes for the port.”
VERSION 6 – MARCH 2017 25
8.2 Involvement of Port Users and Service Providers
The Ministerial Guidelines recognize the difficulty in fully incorporating operations of Local
Port users and service providers in internal management systems and the Local Port of
Portland Bay SEMP. Port Officers are also restricted in their capacity to ensure compliance
against these procedures. Given these constraints the Ministerial Guidelines stipulate that:
8.3 Monitoring and Measurement
8.4 Communication and Reporting
8.5 Competence, Awareness and Training
.6 Non-conformity, Corrective and Preventive Action
8.7 Internal and External Auditing
In order to meet the OH&S and environmental objectives, the Local Port of Portland Bay has
introduced a Local Port of Portland Bay Berthing and Mooring Authorisation. This document
defines management responsibilities for Local Port Users.
Appropriate control of significant environment and OHS risks identified by the Risk Register
is the responsibility of the relevant lessee and contractors. The Local Port facilitates the
development, implementation and maintenance of adequate operational control procedures
and instructions for identified significant risks. This relates to Local Port users and contractor
activities. The Local Port uses Advisory Committee consultation, Local Port Berthing and
Mooring Authorisations and requirements for the development of Job Safety and
Environment Analyses (JSEAs) for contractors to assist with this.
“The Port manager must demonstrate that reasonable steps have been taken to involve the
relevant port business in the development of the Management Plans”. (section 6.1.2)
The Ministerial Guidelines (2009) also requires Ports to identify those hazards associated
with tenants, and states that:
“Where part or parts of the port area are primarily managed or controlled by one or more
tenants, the Port Manager must actively encourage the tenant(s) to undertake this process
for that area and must , to the extent possible, incorporate or reference that work in the Port
Manager’s Plan.” (section 5.4)
In accordance with section 91C (2) (b) of the Port Management Act1995, A port manager
must follow the processes that are set out in the management plan to involve tenants,
licensees and service providers in the port with the implementation of the management plan.
(section 6.1)
VERSION 6 – MARCH 2017 26
8.3 Monitoring and Measurement
Daily inspections are a key tool for monitoring the state of the environment of the Local Port
of Portland Bay and its immediate surrounds. Port Officers liaise directly with users if safety
hazards are identified.
8.4 Communication and Reporting
Communication is the key to ensuring that this Local Port of Portland Bay SEMP is
successfully implemented. Good communication through consultation with all key
stakeholders will enable safety and environmental management within the Local Port. The
following communication systems are used as tools to distribute this information:
• Regular liaison between the Local Port of Portland Bay and key stakeholders such as
permanent tenants, Port of Portland and DEDJTR. Regular contact enables the
passing of important information such as legislative changes, reporting requirements
and any new developments.
• A copy of the Local Port of Portland Bay SEMP can be found on the Glenelg Shire
Council website www.glenelg.vic.gov.au
• A hard copy of the Local Port of Portland Bay SEMP can be available from the
Portland Customer Service Centre (Shire Office) if requested.
• A page is included on Council’s website which provides information on the Local Port.
The community also has an opportunity to provide comments through email to Port
Officers or the quarterly consultation meetings which are held prior to Advisory
Committee meetings.
• Local Port staff also email information to all Local Port users as well as advising of any
issues or safety information.
8.5 Competence Awareness and Training
Stakeholders and tenants using the Local Port must ensure that all personnel and
contractors have the skills required to properly manage or undertake the tasks for which they
are responsible. Stakeholders and tenants are also responsible to make sure any person
carrying out or intending to carry out works within the Local Port are familiar with Safe
Systems of Work.
8.6 Non-conformity, Corrective and Preventive Action
Identification of non-conformances and improvement opportunities are identified by:
• Result of incidents
• Stakeholder feedback
• Data collection from inspections
VERSION 6 – MARCH 2017 27
8.7 Internal and External Auditing
8.7.1 Safety and Environmental Management Plan
Local Port of Portland Bay is required to prepare a Safety & Environmental
Management Plan (SEMP) under part 6A of the Port Management Act1995 and
associated Ministerial Guidelines. A SEMP must be independently certified that they
adequately comply with the matter required by Section 91d of the Port Management
Act and have been prepared in accordance with Ministerial Guidelines. This audit is
undertaken every 4 years. An internal review is undertaken annually.
8.7.2 Environmental, Health and Safety Inspections
Inspections are undertaken by Council’s Port Officers daily to identify and control any
Environmental or OHS risks. The SEMP document is reviewed annually with the risk
register controls updated.
8.8 Management Review
Prior to the end of each financial year, the SEMP will be reviewed. The Port Officer
also commits to conducting more frequent revisions in response to any medium to
extreme incidents or ‘near miss’ incidents occurring and in response to any major
changes to related key legislation or regulations or significant changes to port
operations, activities or functions.
VERSION 6 – MARCH 2017 29
Appendix 2 Inspection Sheet
LOCAL PORT PORTLAND BAY (Trawler Wharf) DAILY INSPECTION SHEET
Date: Time: VESSELS ON WHARF
Castella Rosa ........................................ Celtic Rose .. ...
Derwent Venture ................................... Margaret Pearl .. ...
Moira Elizabeth ...................................... Rorisa C .. .. ....
Vivienne Jane ....................................... Zeehan . ..
Veteran ................................................. Pera .. . .
Eumeralla .............................................. Southern Pride ..
ITINERANTS:
Saxon Progress Game Reason Western Alliance
.......................................................................................................................................................
.......................................................................................................................................................
INSPECTION DETAILS - Any works being undertaken?
Netting .....................................................................................................................................
Wire Works ...............................................................................................................................
Loading/Unloading ....................................................................................................................
Refueling ...................................................................................................................................
Vessel Maintenance ...................................................................................................................
Other .........................................................................................................................................
STANDARD CHECKS
Conveyors in place Fire Reels Gates closed Service boxes
Wharf clear of obstacles Other
ANY ACTIONS ARISING FROM INSPECTION: Yes No
If yes details: ...................................................................................................................................
.......................................................................................................................................................
.......................................................................................................................................................
Any HAZARDS identified
RISK CONTROL MEASURES
(list measures to be taken to eliminate/ minimize risk or injury)
WHO
(Is responsible)
VERSION 6 – MARCH 2017 30
Appendix 2 Inspection Sheet (cont.)
LOCAL PORT PORTLAND BAY
DAILY INSPECTION SHEET
Date: .. Time: Name:
• PORTLAND BAY MARINA- Any boat issues:
Vessel Name or Rego Number Berth No. Issue
Standard Checks:
Yes No Notes:
Main Gate opened/closed
Pen Gates Closed
Service Boxes in order
Marina Clear of obstacles
Any Actions Arising From Inspection:
Yes No If yes, details: ..........................................................................................................
............................................................................................................................................................
• OLD MARINA JETTY
Gate in place and closed
Any Actions Arising From Inspection Yes No If yes, details: ..........................................................................................................
• SOUTH BOAT RAMP (OLD)
Ramps OK Yes No -Fish Bins OK Yes No
Any Actions Arising From Inspection:
Yes No If yes, details: ..........................................................................................................
• NORTH BOAT RAMP (NEW)
Ramps OK Yes No -Fish Bins OK Yes No AtoN OK Yes No
Any Actions Arising From Inspection:
Yes No If yes, details: ..........................................................................................................
............................................................................................................................................................
VERSION 6 – MARCH 2017 31
LOCAL PORT PORTLAND BAY
Bi- Monthly Night Inspection
Date: . Time: Name: ..
Navigational Aids Light
Frequency & Color
Working Notes:
AtoN TYPE (Location) Yes No
Special Mark- (Swing Mooring area) (4)10s Yellow
East Cardinal Mark-(Lagoon area) (3) 5s White
East Cardinal Mark- (Spoil Ground area) (3) 5s White
Portland Bay Marina Area Working Notes:
(Exact Location of faulty light) Location of Lighting Yes No
Marina Entrance Light
Service Pedestal Lights
Solar Lighting (Pen’s A7 & H9)
Marina Entrance Street Lights
Transit Jetty Bollard Lights
Transit Jetty Street Lights
NORTH Boat Ramp Working Notes:
(Exact Location of faulty light) Location of Lighting Yes No
Fish Cleaning Tables Lights
Car Park Street Lights
Solar Lighting (Pontoons x2)
SOUTH Boat Ramp Working Notes:
(Exact Location of faulty light) Location of Lighting Yes No
Fish Cleaning Tables Light
Ramp Lights
Toilet Lights (Inside & Out)
Trawler Wharf Working Notes:
(Exact Location of faulty light) Location of Lighting Yes No
Street Lights
Pontoon Pedestal Lights
Location (Blue Flashing Light)
VERSION 6 – MARCH 2017 32
Appendix 3 List of relevant Legislations, Policies and Guidelines
The International, Federal, State and local legislation, conventions, regulations, policies, guidelines etc. of most relevance to Safety and Environment Management for the Local Port of Portland Bay are listed below:
International - International Environmental Legislation/Conventions
• Guidelines for the Control and Management of Ships’ Ballast Water to minimise the Transfer of Harmful Aquatic Organisms and Pathogens (IMO) 1997
• International Convention for the Prevention of Pollution from Ships (MARPOL), 1973/78
• International Convention for the Safety of Life at Sea (SOLAS) 1974
• International Maritime Organisation Dangerous Goods Code (IMDG Code) 2004
• The Jakarta Mandate on Marine and Coastal Biological Diversity 1995
• The United Nations Convention on the Law of the Sea (UNCLOS) 1982
Federal - Environmental Legislation
• Aboriginal & Torres Strait Islander Heritage Protection Act 1984
• Australia’s Ocean Policy 1998
• Australian Ballast Water Management Requirements (AQIS) 2001
• Australian Marine Safety Authority Act 1990
• Endangered Species Protection Act 1992
• Environment Protection and Biodiversity Conservation Act 1999
• Environment Protection and Biodiversity Conservation Regulations under the EPBC Act 1999
• Environment Protection (Sea Dumping) Act 1981
• Environment Protection (Sea Dumping) Regulations 1983
• Environmental and Heritage Legislation Amendment Act (No. 1) 2003
• Fisheries Management Act 1991
• National Environmental Protection Measures
• National Environment Protection (Assessment of Site Contamination) Measure 1999
• National Environment Protection Measures (Implementation) Regulations 1999
• National Greenhouse Strategy 1998
• National Greenhouse and Energy Reporting Act 2007
• National Standards for the Control of Major Hazard Facilities 2002
• National Strategy for Ecologically Sustainable Development 1992
• National Strategy for the Conservation of Australia’s Biological Diversity 1986
• Ozone Protection and Synthetic Greenhouse Gas Management Act 1989
• Ozone Protection and Synthetic Greenhouse Gas Management Regulations 1995
• Protection of the Sea (Prevention of Pollution from Ships) Act 1983
• Protection of the Sea (Prevention of Pollution from Ships) (Orders) Regulations 1994
• Quarantine Act 1908
Federal - Health and Safety Legislation
• Australian Workplace Safety Standards Act 2005
• Australian Workplace Safety Standards Regulations 2005
• NOSHC: 2079(200) National Standard of Occupational Noise
• NOSHC: 2009(2004) Noise Management & Protection of Hearing at Work
• NOSHC: 3008 atmosphere 10039(200) National Standard of Occupational Noise
VERSION 6 – MARCH 2017 33
Appendix 3 List of relevant Legislations, Policies and Guidelines (cont.)
Victorian - Environmental Legislation
• Archaeological and Aboriginal Relics Preservation Act 1972
• Archaeological & Aboriginal Relics Preservation Regulations 2003
• Catchment and Land Protection Act 1994
• Catchment and Land Protection Regulations 2002
• Coastal Management Act 1995
• Conservation, Forests and Lands Act 1987
• Conservation, Forests and Lands (Contracts) Regulations 2000
• Conservation, Forests and Lands (Infringement Notice) Regulations 2002
• Crown Land (Reserves) Act 1978
• Dangerous Goods Act 1985
• Dangerous Goods (Storage and Handling) Regulations 2000
• Emergency Management Act 1986
• Emergency Management Regulations 2003
• Environmental Effects Act 1978
• Environment Protection Act 1970
• Environment Protection (Fees) Regulations 2001
• Environment Protection (Prescribed Waste) Regulations 1998
• Environment Protection (Residential Noise) Regulations 1997
• Environment Protection (Scheduled Premises & Exemptions) Regulations 1996
• Environment Protection (Vehicle Emissions) Regulations 2003
• Environment Protection (Environment and Resource Efficiency Plans) Regulations 2007
• Equipment (Public Safety) Act 1994
• Equipment (Public Safety) (General) Regulations 1995
• Equipment (Public Safety) (Incident Notification) Regulations 1997
• Fisheries Act 1995
• Fisheries Regulations 1998
• Flora and Fauna Guarantee Act 1988
• Flora and Fauna Guarantee Regulations 2001
• Heritage Act 1995
• Heritage (General) Regulations 1996
• Heritage (Infringement Notice) Regulations 2002
• Industrial Waste Management Policy (Prescribed Industrial Waste) 2000
• Litter Act 1987
• Marine Safety Act 2010
• Marine Regulations 1999
• National Environment Protection Council (Victoria) Act 1995
• Planning and Environment Act 1987
• Planning and Environment Regulations 1988
• Pollution of Waters by Oil and Noxious Substances Act 1986
• Pollution of Waters by Oil and Noxious Substances Regulations 2002
• Port Management Act 1995
• Port Management (Local Ports) Regulations 2015
• State Environment Protection Policies (SEPPs)
• State Environment Protection Policy (Waters of Victoria) 1988
• State Environment Protection Policy (The Air Environment) 1988
• State Environment Protection Policy (Air Quality Management) 2001
• State Environment Protection Policy (Ambient Air Quality) 1999
• State Environment Protection Policy (Control of Noise from Commerce, Industry and Trade) No N-1 1989
• State Environment Protection Policy (Prevention and Management of Contaminated Land) June 2002
• State Environment Protection Policy (Groundwater’s of Victoria) 1997
VERSION 6 – MARCH 2017 34
Appendix 3 List of relevant Legislations, Policies and Guidelines (cont.)
Victorian - Environmental Legislation
• Sustainability Act 2005
• Victoria’s Biodiversity: Directions in Management 1997
• Victoria’s Biodiversity: Our Living Wealth 1997
• Victoria’s Biodiversity: Sustaining Our Living Wealth 1997
• Victorian Coastal Strategy 2002
• Victorian Heritage Strategy 2000-2005, 2000
• Water Act 1989
• Water Industry (Waterways Land) Regulations 2002
• Waste Management Policies (WMPs)
• Waste Management Policy (Ships’ Ballast Water) 2004
• Wildlife Act 1975
• Wildlife Regulations 2002
• Wildlife (Whales) Regulations 1998
Victorian - Health and Safety Legislation
• Accident Compensation Act 1985
• Accident Compensation (Workcover Insurance) Act 1993
• Building (Legionella) Act 2000
• Dangerous Goods Act 1985
• Dangerous Goods Legislation (Amendment) Act 2004
• Dangerous Goods (Storage and Handling) Regulations 2012
• Electricity Safety Act 2002
• Electricity Safety (Network Assets) Regulations 1999
• Electricity Safety (Management) Regulations 2009
• Equipment (Public Safety) Act 1994
• Building (Legionella) Act 2000
• Emergency Management Act 2013
• Environment Protection Act 1970
• Health Act 1958
• Local Government Act 1989
• Occupational Health and Safety Act 2004 - Part 5 Incident Notification
• Occupational Health and Safety Regulations 2007 - 2.1 General Duties - 2.2 Issue Resolution Procedures - 3.1 Manual Handling - 3.2 Noise - 3.3. Prevention of Falls - 3.4 Confined Spaces - 3.5 Plant - 3.6 High Risk Work - 4.1 Hazardous Substances - 4.3 Asbestos - 4.4 Lead - 5.1 Construction
• Occupational Health and Safety (Incident Notification) Regulations 1997
• Occupational Health and Safety (Maritime Industry) Act 1993
• Occupational Health and Safety (Maritime Industry) (National Standards) Regulations 2003
• Occupational Health and Safety (Maritime Industry) Regulations 1995
VERSION 6 – MARCH 2017 35
Appendix 3 List of relevant Legislations, Policies and Guidelines (cont.)
Local Government Area – Planning and Strategy
• Glenelg Shire Planning Scheme • The Glenelg Shire Coastal Action Plan January 2004 • Glenelg – Hopkins (CMA) Regional Catchment Strategy • Port of Portland - Port Land Use Strategy (PLUS)
Other Requirements - Associated Guidelines
• A Guide to the Measurement and Analysis of Noise (EPA Victoria) 1991
• Aquatic and Recreational Signage Style Guide (Life Saving Victoria)
• AS 1657 Fixed Platforms, Walkways, Stairways and Ladders – Design, Construction and Installation 1992
• AS/NZS 4360:2004 Risk Management
• AS/NZS ISO 14001:1996 Environmental Management Systems – Specifications with guidance for use
• AS/NZS 4801:2001 Occupational Health and Safety Management Systems – Specification with guidance for use
• Australian and New Zealand Guidelines for Fresh and Marine Water Quality (Environment Australia) 2000
• Best Practice Guidelines for Waste Reception Facilities at Ports, Marina & Boat Harbours in Australia and New Zealand (ANZECC)
• Bunding Guidelines (EPA Victoria) 1992
• Cleaner Marinas: EPA guidelines for protecting Victoria marinas (EPA Victoria)
• CS FP 001: 1995 Fire Emergency Response
• Guidance on OHS Reporting in Annual Reports (NOHSC) 2004
• Guidelines for Dredging 2001 (EPA Victoria) 2001
• HB 76.2004 Dangerous Goods – Initial Emergency Response Guide
• Noise Control Guidelines (EPA Victoria) 1992
• Protocol for Environmental Management – Domestic Ballast Water Management in
• Victorian State Waters (EPA Victoria) 2004
• Protocol for Environment Management – Greenhouse Emissions and Energy
• Siting and Design Guidelines for Structures on the Victorian Cost (Victorian Coastal Council) 1998
• Standard for Aids to Navigation on Victorian State Waters (2012)
• Statements of Environmental Audit (EPA Victoria) June 2002
INCIDENT/HAZARD REPORTING
& INVESTIGATION
VERSION 6 – MARCH 2017 36
GENERAL REQUIREMENTS .
THIS IS A REPORT OF:
Employee to complete
Supervisor to complete
Group Manager to complete
Injury to an employee Sections 1,4-8 Sections 13-16 Section 17
Report of Safety Hazard Sections 1-3 Sections 13-16 Section 17
Incident – no injury or damage (egg near miss) Sections 1-3 Sections 13-16 Section 17
Injury to third party (egg member of the public) Sections 1,4-8 Sections 13-16 Section 17
Damage to motor vehicle Sections 1,9-10 Sections 13-16 Section 17
Environmental Incident Sections 1,12 Sections 13-16 Section 17
Damage to property/equipment (including theft) Sections 1,11 Sections 13-16 Section 17
1 DETAILS OF PERSON COMPLETING FORM
Name: Phone No:
Job Title
Dept:
This information is true and correct to the best of my knowledge
Signature of person completing form Date:
SAFETY HAZARD REPORT SECTION .
2 HAZARD DETAILS:
What is the nature of the report?
Safety Hazard Near Miss Incident Reportable incident
Description of Issue
NOTE: If there is an immediate risk of death or serious injury, please contact your Team
Leader/Manager immediately
3 HAZARD CONTROL:
What could be done to eliminate the hazard?
Personal and or Health Information collected by Council is used for municipal purposes as specified in the Local Government Act 1989. The Personal and or Health Information will be used solely by Council for these purposes and or directly related purposes. Council may disclose this information to other organisations if required by legislation. The employee understands that the Personal and or Health Information provided is for the above purpose and that he or she may apply to Council for access to and/or amendment of the information. Requests for access and or correction should be made to Council’s Privacy Officer.
Appendix 4 Glenelg Shire Council Incident Reporting Form
VERSION 6 – MARCH 2017 37
INJURY REPORT SECTION .
4 DETAILS OF INJURED PERSON:
Name of Injured: Date of Birth:
Employee Contractor Member of Public Other
Relationship to the injured person: Phone no:
Home Address:
Signature of injured person Date:
5 INJURY DETAILS:
Incident Date: Time: am/pm
Name of Supervisor you have reported this to
Date & time you reported this injury: Date: Time: am/pm
Lost Time Injury: (employees only)
Yes No If yes Date/Time Ceased Work:
am/pm
Name of Witnesses: Phone No:
Where was the exact location where the injury/illness occurred?
What was the injured person doing at the time leading up to the incident?
How did the incident happen?
In your opinion, what was the cause of the incident?
In your opinion, what could be done to prevent this type of incident re-occurring?
6 MEDICAL TREATMENT:
Was first aid required: No Yes If yes, Who provided first aid
Was Doctor treatment required: No Yes If yes, Dr’s Name
Was hospitalization required: No Yes If yes, Hospital name
7 INJURY LOCATION
Left Right
Head Arm Leg Internal System
Eye Shoulder Knee Psychological
Neck Elbow Ankle Other (please specify)
Torso Wrist Foot
Back Hand Toe
Groin Finger/Thumb Multiple N/A
8 TYPE OF INJURY:
Sprain/Strain
Abrasion/ Laceration
Burn/Scald Bite – from insect
Bruise/Swelling Puncture wound Electric Shock Bite – from animal
Dislocation Foreign body Crush Bite – from human
Concussion Amputation Allergic reaction Other (please specify)
Deafness Fracture Infection/Infestation
Appendix 4 Glenelg Shire Council Incident Reporting Form (Cont.)
VERSION 6 – MARCH 2017 38
PLANT DAMAGE REPORT SECTION
.
9 VEHICLE DAMAGE DETAILS:
Registration Number: Plant No:
Vehicle make / model
Date of accident: Time: am/pm
Drivers name: Signature
Licence Number: Expiry Date
Location of collision
What caused the accident?
Estimated cost of repairs: $
What were the weather conditions at the time of accident?
Give a detailed description of the damage to all vehicles:
Shade in damaged sections to vehicles:
Council Vehicle Other Vehicle
Was anyone injured? No Yes If yes complete sections 4-9
Has driver recently consumed drugs or alcohol? No Yes
10 DETAILS OF THIRD PARTY: (if Applicable)
Registration Number: Vehicle make/model
Drivers name: Licence Number:
Address: Phone No:
Appendix 4 Glenelg Shire Council Incident Reporting Form (Cont.)
VERSION 6 – MARCH 2017 39
PROPERTY DAMAGE SECTION .
11 PROPERTY DAMAGE DETAILS:
Theft Fire Vandalism Other Specify
Type of Property:
location of the damaged property
Date damage was noticed Time: am/pm
Who/what contributed to the damage (may be more than one)
Unknown
Estimated Cost of repairs: $
NOTE: For property damage incidents in excess of $5k a significant Incident analysis is required – Refer to Risk Management Officer
Description of the damage:
How did the damage occur?
Has this been reported to Police: No Yes If yes, which station
Was there a witness to the damage: No Yes If yes, who
ENVIRONMENTAL DAMAGE SECTION .
12 ENVIRONMENTAL DAMAGE DETAILS:
Date incident was noticed Time: am/pm
Exact location of incident:
Nature of incident (Spill type, chemicals involved)
Duration of incident:
Quantity of pollutants involved:
What was the cause of the incident:
Specify the effect on the environment:
Who was directly affected? (if applicable)
Was the Environmental Protection Authority notified? Yes No
Was WorkCover Notified? Yes No
Did you inform the Environmental Health Officer? Yes No
What action has been taken:
Appendix 4 Glenelg Shire Council Incident Reporting Form (Cont.)
VERSION 6 – MARCH 2017 40
INVESTIGATION SECTION
This section is to be completed by the Supervisor
NOTE: IF Risk Assessment Finding is HIGH - A formal investigation or significant incident analysis process may be required. Refer to Risk Management Officer for guidance.
14 RISK CONTROL: (To be completed by Supervisor)
The Hierarchy of Control is a list of control measures, in priority order, that can be used to eliminate or minimise exposure to hazards. Application of the Hierarchy of Control measures involves firstly assessing whether the risk/hazard can be eliminated. Where this is not practicable, substitution should be considered. If this is not practicable, consideration should be given to each of the other control measures – isolation, engineering controls, administrative control/safe work practices, and use of PPE – in turn, until a control measure or combination of control measures are identified which can achieve the required reduction in exposure.
1. Eliminate Remove risk from the process by eliminating the step in the process, or eliminating the hazard
2. Substitute/Avoid Consider whether the process or activity is required, or whether another process or activity can be substituted (egg: use a water based paint)
3. Isolation Removing or separating people from the source of the hazard. Consider physical barriers such as fencing, barricading.
4. Engineering Control Changing the physical characteristics of plant or workplace to remove or reduce the risk (e.g.: machine guarding, using mechanical aids, reversing beepers, etc.)
5. Administrative Control
Use of policies, procedures for safe work practices, signs, training, job rotation, etc. to control risk
6. Personal Protective Equipment (PPE)
Employee is required to use/wear PPE (e.g.: safety glasses, gloves, hearing protection, red safety vest, hard helmet, safety boots, etc.)
What corrective actions are required to be taken to prevent repeat occurrence:
Change Work procedures Modify equipment Improve Environment
Training / retraining Review PPE Supervision
Other: (Please Specify)
What level of the Hierarchy of Control have you chosen:
Eliminate Substitute Isolation Engineering Admin PPE
When will these actions will be completed Date: Already Completed
Who is responsible for completing corrective action:
Have all contributing factors been addressed:
______________________________________________________________________________________________________
Probability Consequence/Impact A B C D E
1 Very High/Almost Certain
A Fatality 1 H H H M M
2 High – once in 3 yrs.
B Serious injury 2 H H M M L
3 Moderate/Sometimes
C Injury 3 H M M L L
4 Low/Rarely D Minor Injury or loss 4 M M L L L 5 Very Low/
Unlikely E Negligible Impact 5 M L L L L
13 RISK ASSESSMENT: (To be completed by Supervisor)
Undertake risk assessment to determine risk level (Probability x Consequence)
Risk Level High Medium Low
Appendix 4 Glenelg Shire Council Incident Reporting Form (Cont.)
VERSION 6 – MARCH 2017 41
INVESTIGATION SECTION
This section is to be completed by the Supervisor
15 CONTRIBUTION FACTORS:
What do you consider were the main contributing factors to this incident/hazard? (More than one box may be ticked)
Procedures: Comments:
Employee not aware of correct procedure
Employee was aware but failed to follow correct procedure
Procedure followed, but was inappropriate to condition
No formal procedure in place
Work Environment:
Inappropriate workplace design
Inappropriate task location
Poor housekeeping
External:
Incident caused by another person or thing
Weather conditions
Equipment:
Appropriate equipment available but not used
Appropriate equipment not supplied
Equipment failure/malfunction
Equipment not properly repaired/maintained
Equipment not used correctly
Equipment not appropriate for the task
Training:
Employee not adequately trained
Supervisor not adequately trained
Action by Employee:
Employee performed unsafe act
Employee did not wear appropriate PPE
Other; (Please specify)
Provide details (attach separate page if insufficient room):
16 ACKNOWLEDGEMENT:
Is this injury modifiable under the Incident Notification Regulations Yes No
Signature of Supervisor: Date:
Signature of OHS Representative Date:
When completed a copy of the injury report must be provided to the employee Done
Is disciplinary action to be taken Yes No
When completed forward this report to the Risk Management Officer Done _________________________________________________________________________________________________________________________________________________________________________________________________________________________________
17 GROUP MANAGER REVIEW:
Group Manager to review incident report and confirm that any remedial actions to address systems of work are implemented as far as reasonably practicable.
Signature of Group Manager Date:
Appendix 4 Glenelg Shire Council Incident Reporting Form (Cont.)
VERSION 6 – MARCH 2017 43
Local Port of Portland Bay
Contact Details:
Glenelg Shire Council
PO Box 152 / 71 Cliff Street
Portland, Vic 3305
Phone: (03) 5522 2200
Email: [email protected]
www.glenelg.vic.gov.au