SOLAR ENERGY TRADE MISSION SOLAR ENERGY OUTLOOK AND LOCAL CONTENT

KSA26 - 27 - 28 November 2019Sheraton Olaya - Riyadh

SAKAKA ProjectCase Study

The OEM Perspective

Page 2: SAKAKA Project Case Study The OEM Perspective TRADE MISSION€¦ · SAKAKA Project Case Study The OEM Perspective. 27 November -SAKAKA -OEMPERSPECTIVE 1 -Reflections and lessons learned

27 November - SAKAKA - OEM PERSPECTIVE

1 - Reflections and lessons learned acquired from the Sakaka PV IPP, being the first grid-connected large scale Solar PV plant

1.0 REFLECTIONSAL-BABTAIN METALOGALVA SOLAR, SAUDI ARABIA WAS AWARDED BY MAHINDRA FOR SUPPLY OF STEEL COMPONENTS OF TRACKERS CONSISTING OF TORQUE TUBES AND PIERS FOR 300 MW (AC) FOR SAKAKA PROJECT FOR TRACKER TECHNOLOGY OF NEXTRACKER

*TYPE OF PIERS : C PROFILE 150X100X30X3MM *TYPE OF TORQUE TUBES :

DIA 127 MM, 8.73 AND 7.73M Length WITH DRILLING AND SWEDGING

2.0 LESSONS ACQUIRED * MAKE THE RAW MATERIAL AVAILABLE IN

ADVANCE .* LEAD TIME FOR PROCUREMENT OF MACHINERY

SHOULD BE REASONABLE. * SMOOTH RUNNING OF MACHINERY.

Page 3: SAKAKA Project Case Study The OEM Perspective TRADE MISSION€¦ · SAKAKA Project Case Study The OEM Perspective. 27 November -SAKAKA -OEMPERSPECTIVE 1 -Reflections and lessons learned

27 November - SAKAKA - OEM PERSPECTIVE

2 - The challenges encountered in executing the project: measures and best practices that has been undertaken to overcome them

CHALLENGES MEASURES AND BEST PRACTICE PROCUREMENT OF RAW MATERIALS HIGH GRADE OF STEEL AND THEIR SPECIFICATION, LOCALLY NOT AVAILABLE

NEEDS TO BE IMPORTED , REQUIRE THREE TO FOUR MONTHS FOR DELIVERY TO FACTORY

TO PROCURE ALL THE MATERIAL AT ONE TIME

PROCUREMENT OF SLITTED COILS FOR PREGALVA MATERIAL DELAYED DELIVERIES , PROCURE MOTHER COILS AND SLIT LOCALLY

HIGH TOLERANCES : IN RAW MATERIAL AND FABRICATION THIRD PARTY INSPECTION

INSPECTION AND QUALITY ALL QUANTITIES WERE INSPECTED AND TESTED FOR DIMENSIONS , MECHANICAL PROPERTIES , GALVANIZING REQUIREMNTS .

THIRD PARTY INSPECTION APPROVED BY TECHNOLOGY PROVIDER DURING IN PROCESS AND DESPATCH

AVAILABILITY OF MACHINERY AS WE ARE LOCAL SUPPLIER, THE ORDER WAS RECEIVED WHEN THE MACHINERY WAS AT PROCUREMENT STAGE.

DELAYS FROM OUR MACHINERY SUPPLIERS IN INSTALLATION. FOR PIERS USED ALTERNATIVE MACHINERY .

DESPATCH OF MATERIALS BUNDLING AND PACKING APPROVED PACKING PROCEDURE LOGISTICS AND DOCUMENTATION AS PER WEEKLY DELIVERY SCHEDULES AND DOCUMENTATIONS APPROVED BY EPC AND TECHNOLOGY PROVIDER

HIGHLIGHT IS THAT WE HAD NO REJECTION OR SHORTAGES AT SITE

Page 4: SAKAKA Project Case Study The OEM Perspective TRADE MISSION€¦ · SAKAKA Project Case Study The OEM Perspective. 27 November -SAKAKA -OEMPERSPECTIVE 1 -Reflections and lessons learned

27 November - SAKAKA - OEM PERSPECTIVE

3 - Opportunities, or low-hanging fruits for localization recognized in Sakaka for services

ALBABTAIN METALOGALVA SOLAR HAS ESTABLISHED FACTORY AT DAMMAM AT A COST OF USD 25 MILLION TO MANUFACTURER STEEL COMPONENTS FOR TRACKERS WHICH WILL SUPPORT LOCAL SAUDI PV MARKET. THE FACTORY HAS ALREADY ACHIEVED 20 % SAUDIZATION OF ITS EMPLOYEES AND AIMS AT 26% IN 2020

1.2 GWProduction Capacity

90,000 TonsGalvanizing Capacity

55,000 SqmTotal Land Area

22,000 Sq.Factory Area