Upload
allan-leyte
View
33
Download
0
Embed Size (px)
Citation preview
39.37 TONS 31.34 TONS 6.29 TONS
79.60% 15.97%
SL # MARK NO.MARK
LOCATION REF. #
PRIORITY QTY WEIGHT TOTAL WEIGHT
FORECAST FINISH
ACTUAL FINISH
FORECAST DESPATCH
ACTUAL DESPATCH
FORECAST START
ACTUAL START
FORECAST FINISH
ACTUAL FINISH REMARKS
8.25
DELIVERED TO SITEPRIO
RITY
NO
. 1
OVERALL SUMMARY: DELIVERED
Percent %
ERECTED
Percent %
G 15 @ Gridline 1-2/ H-K
DATE:
30-Apr-09SPIRE TOWER: WCN 202-ROOF FRAMING w/ CLADDING [G-15]
(INTERNAL SCHEDULE)
FABRICATION DELIVERY ERECTION
1 B18 1 1 807.1 0.8071 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
M22, M25
2 B16 1 1 2117.7 2.1177 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
M93, M91, M102, M103
3 B28 2 1 161.3 0.1613 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
4 B20 2 1 113.7 0.1137 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
5 B14 1 1 3361.4 3.3614 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
M105, M104, M95, M96, M106, M107
6 B21 2 1 228.5 0.2285 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
7 B54 2 1 365.9 0.3659 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
8 A1 3 1 74.8 0.3390 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
9 A14 3 1 72.6 0.0726 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
10 A15 3 1 74.8 0.0748 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
DELIVERED TO SITEPRIO
RITY
NO
. 1
PRIO
RITY
NO
. 211 B38 4 1 270.1 0.2701 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09
12 A8 3 1 139.4 0.1394 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09
13 B4 3 1 42.0 0.0420 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09
14 B33 4 1 156.4 0.1564 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09
PLEASE SEE MARK LOCATION REFERENCE:
B18
DELIVERED TO SITE
PRIO
RITY
NO
. 2
Please See Mark Location Reference No:
(1) Main Assembly Frames.(2) Horizontal Top Member. (3) Vertical Cross Bracings.(4) Horizontal Member.
B14 B162
3
4
1 1
B18
B16B14
Page 1
39.37 TONS 31.34 TONS 6.29 TONS
79.60% 15.97%
SL # MARK NO.MARK
LOCATION REF. #
PRIORITY QTY WEIGHT TOTAL WEIGHT
FORECAST FINISH
ACTUAL FINISH
FORECAST DESPATCH
ACTUAL DESPATCH
FORECAST START
ACTUAL START
FORECAST FINISH
ACTUAL FINISH REMARKS
OVERALL SUMMARY: DELIVERED
Percent %
ERECTED
Percent %
DATE:
30-Apr-09SPIRE TOWER: WCN 202-ROOF FRAMING w/ CLADDING [G-15]
(INTERNAL SCHEDULE)
FABRICATION DELIVERY ERECTION
7.03PR
IORI
TY N
O. 2
DELIVERED TO SITE
G 15 @ Gridline 1-2/ H-K
15 B22 2 1 278.4 0.2784 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09
16 B32 2 2 191.8 0.3836 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09
17 A7 3 1 166.7 0.1667 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09
18 B32 4 2 191.8 0.3836 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09
19 A6 2 1 159.3 0.1593 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09PRIO
RITY
NO
. 2
PRIO
RITY
NO
. 3
DELIVERED TO SITE20 B55 4 1 516.0 0.5160 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09
21 B8 3 1 394.7 0.3947 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09
22 B10 3 1 394.6 0.3946 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09
23 B11 1 1 3977.5 3.9775 26-Apr-09 28-Apr-09 27-Apr-09 29-Apr-09 28-Apr-09 28-Apr-09
M177, M4, M3, M108, M94, M92
24 A12 3 1 191.8 0.1918 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09
25 A13 3 1 185.0 0.1850 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09
PLEASE SEE MARK LOCATION REFERENCE:
PRIO
RITY
NO
. 3
DELIVERED TO SITE
B11 B142
3
4
1 1
B14
B11Please See Mark Location Reference No:
(1) Main Assembly Frames.(2) Horizontal Top Member. (3) Vertical Cross Bracings.(4) Horizontal Member.
Page 2
39.37 TONS 31.34 TONS 6.29 TONS
79.60% 15.97%
SL # MARK NO.MARK
LOCATION REF. #
PRIORITY QTY WEIGHT TOTAL WEIGHT
FORECAST FINISH
ACTUAL FINISH
FORECAST DESPATCH
ACTUAL DESPATCH
FORECAST START
ACTUAL START
FORECAST FINISH
ACTUAL FINISH REMARKS
OVERALL SUMMARY: DELIVERED
Percent %
ERECTED
Percent %
DATE:
30-Apr-09SPIRE TOWER: WCN 202-ROOF FRAMING w/ CLADDING [G-15]
(INTERNAL SCHEDULE)
FABRICATION DELIVERY ERECTION
4.83
PRIO
RITY
NO
. 3
DELIVERED TO SITE
G 15 @ Gridline 1-2/ H-K
26 C2 1 1 1839.9 1.8399 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09
27 A4 3 1 122.9 0.1229 26-Apr-09 25-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09
28 B29 4 1 126.9 0.1269 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09
29 A3 3 2 130.8 0.2616 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09PRIO
RITY
NO
. 3
PRIO
RITY
NO
. 4
DELIVERED TO SITE
30 B30 4 1 131.2 0.1312 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
31 A5 3 2 134.9 0.2698 27-Apr-09 25-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
32 B31 4 1 130.1 0.1301 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
33 B19 2 1 181.3 0.1813 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
34 B57 2 1 366.7 0.3667 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
35 B36 4 1 294.8 0.2948 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
36 A16 3 1 168.7 0.1687 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
37 B24 4 1 297.3 0.2973 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
38 A17 3 1 173.1 0.1731 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
39 B34 4 1 297.3 0.2973 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
40 A18 3 1 165.5 0.1655 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
PLEASE SEE MARK LOCATION REFERENCE:
PRIO
RITY
NO
. 4
DELIVERED TO SITE
C2 B112
3
4
1 1B11
C2
Please See Mark Location Reference No:
(1) Main Assembly Frames.(2) Horizontal Top Member. (3) Vertical Cross Bracings.(4) Horizontal Member.
Page 3
DATE:
SPIRE TOWER PROJECT 9-Apr-09
WCN -203
SPIRE TOWER with CLADDING,47M LEVEL 70
SECTION 1
Fab'n: 22-Mar-09
Deliver to Site: 15-Apr-09
Erection Start: 16-Apr-09
SECTION 3
Fab'n: 23-Mar-09
Deliver to Site: 17-Apr-09
Erection Start: 19-Apr-09
Weld Splice: 20-Apr-09
SECTION 6
Fab'n: 24-Mar-09
Deliver to Site: 21-Apr-09
Erection Start: 25-Apr-09
Weld Splice: 26-Apr-09
SECTION 8
Fab'n: 25-Mar-09
Deliver to Site: 23-Apr-09
Erection Start: 29-Apr-09
Weld Splice: 30-Apr-09
SECTION 10
Fab'n: 26-Mar-09
Deliver to Site: 24-Apr-09
Erection Start: 03-May-09
Weld Splice: 04-May-09
SECTION 11
Fab'n: 27-Mar-09
Deliver to Site: 24-Apr-09
Erection Starts: 05-May-09
Weld Splice: 06-May-09
Line& Level: 07-May-09
Inspection: 08-May-09
SECTION 9
Fab'n: 26-Mar-09
Deliver to Site: 23-Apr-09
Erection Start: 01-May-09
Weld Splice: 02-May-09
SECTION 7
Fab'n: 25-Mar-09
Deliver to Site: 22-Apr-09
Erection Start: 27-Apr-09
Weld splice: 28-Apr-09
SECTION 5
Fab'n: 24-Mar-09
Deliver to Site: 20-Apr-09
Erection Start: 23-Apr-09
Weld Splice: 24-April-09
SECTION 4
Fab'n: 23-Mar-09
Deliver to Site: 19-Apr-09
Erection Start: 21-Apr-09
Weld Splice: 22-Apr-09
SECTION 2
Fab'n: 22-Mar-09
Deliver to Site: 15-Apr-09
Erection Start: 17-Apr-09
Weld Splice: 18-Apr-09