Sample Programme Target vs Actual

Embed Size (px)

Citation preview

  • 8/6/2019 Sample Programme Target vs Actual

    1/7

    Activity

    ID

    Activity

    Description

    Orig

    Dur

    %

    Complet

    Planned

    Start

    Planned

    Finish

    Actual

    Start

    Actual

    Finish

    ABRA 132/11KV SUBSTATION

    KEY POINTSNSHR00 Project LOI Received 0 100 06MAR10 06MAR10A

    NSHR02 Project Commenced 0 100 06MAR10 06MAR10A

    NSHR03 Project Testing & Commissioning (Contract) 0 0 31DEC11* 31DEC11*

    NSHR04 Project Planned Completion 0 0 14DEC11 14DEC11

    NSHR06 Contract Signed date 0 100 07OCT10* 07OCT10A

    DESIGN PHASE

    Drawings (IFA + Approval + IFC)DSGN00 Preliminary Drawings from Siemens 0 100 06MAR10 28MAR10A

    DSGN02 Conceptual Drawings Submitted 7 100 06MAR10 13MAR10 09JUN10A 17JUN10A

    DSGN04 Approved Construction Drawings from Siemens 230 100 30MAR10* 26JUL10A 22DEC10A

    DSGN06 Design/Drawings Preparation & Submittal (IFA) 118 80 30MAR10 14AUG10 14AUG10A 10MAY11

    DSGN08 Drawings Approval by DEWA 118 50 24APR10 07SEP10 22SEP10A 20JUN11

    DSGN10 Shop Drawings (IFC) 105 28 26MAY10 25SEP10 23FEB11A 10JUL11

    Material SubmittalsMS210 FP - Submittals - Fire Pipes & Fittings 21 100 09OCT10 01NOV10 18SEP10A 12OCT10A

    MS212 FP - Submittals - Fire Pump & Accessories 21 100 09OCT10 01NOV10 18SEP10A 05DEC10A

    MS214 FP - Submittals - Nitrogen System 21 100 09OCT10 01NOV10 18SEP10A 07FEB11A

    MS217 FP - Submittals - Valves & Fittings 21 100 09OCT10 01NOV10 18SEP10A 12OCT10A

    MS218 FP - Submittals - Equipments & Accessories 21 100 09OCT10 01NOV10 18SEP10A 12OCT10A

    MS220 FD - Submittals - Cables & Accessories 21 100 09OCT10 01NOV10 10OCT10A 03NOV10A

    MS222 FD - Submittals - Panels 21 100 09OCT10 01NOV10 10OCT10A 03NOV10A

    MS224 FD - Submittals - All Devices 21 100 09OCT10 01NOV10 10OCT10A 03NOV10A

    Materials ApprovalMA310 FP - Approvals - Fire Pipes & Fittings 21 100 02NOV10 25NOV10 13OCT10A 13FEB11A

    MA312 FP - Approval - Fire Pumps 21 100 02NOV10 25NOV10 06DEC10A 30MAR11A

    2011 2012FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F

    Primavera Systems, Inc.

    Start Date 06MAR10

    Finish Date 31DEC11Data Date 13APR11

    Planned Bar

    Actual BarProgress Bar

    Critical Activity

    Date Revision Checked Approved

    27FEB11 Contract Programme Sha/Nel Thiru.S

    13APR11 Overall Programme Sha/Nel Thiru.S

    ABRA

    DEWA CONTRACT NO.7405/ABRA132/11 KV SUBSTATION

    Fire Systems Overall Programme

    Sheet 1 of 7

    7881/SV/PROG/FP/001

  • 8/6/2019 Sample Programme Target vs Actual

    2/7

    Sheet 2 of 7

    Activity

    ID

    Activity

    Description

    Orig

    Dur

    %

    Complet

    Planned

    Start

    Planned

    Finish

    Actual

    Start

    Actual

    Finish

    MA314 FP - Approval - Nitrogen System 21 0 02NOV10 25NOV10 07NOV10A 07MAY11

    MA318 FP - Approval - Valves & Fittings 21 88 02NOV10 25NOV10 13OCT10A 16APR11

    MA320 FP - Approvals - Equipments & Accessories 21 94 02NOV10 25NOV10 13OCT10A 13APR11

    MA322 FD - Approvals - Cables & Devices 21 100 02NOV10 25NOV10 04NOV10A 30NOV10A

    MA324 FD - Approval - Fire Alarm Panels 21 96 02NOV10 25NOV10 04NOV10A 13APR11

    Materials ProcurementMAPT00 FP Materials Procurement - Pipes 84 15 31MAR11* 22JUN11 14FEB11A 22JUN11

    MAPT02 FP Materials Procurement - Fire Pump set 160 5 31MAR11 06SEP11 08APR11A 11SEP11

    MAPT06 FP MaterialsProcurement - Nitrogen System 126 0 31MAR11 03AUG11 15MAY11 17SEP11

    MAPT08 FP Materials Procurement - Valves & Fittings 84 0 31MAR11 22JUN11 03MAY11 25JUL11

    MAPT09 FP MaterialsProcurement-Equipments&Accessories

    84 0 31MAR11 22JUN11 01MAY11 23JUL11

    MAPT10 FD Material Procurement - Fire Alarm Panels 56 0 31MAR11 25MAY11 01MAY11 25JUN11

    MAPT12 FD Material Procurement - Cables & Devices 56 0 31MAR11 25MAY11 21APR11 15JUN11

    INSTALLATION PHASE

    BASEMENT FLOOR

    132 kV Basement

    Fire Systems Access

    132KVBT Fire Protection & Detection Access 0 0 08AUG11* 08AUG11*

    Fire Protection

    132BTFP01 Installation of Wet pilot pipes 15 0 09AUG11 25AUG11 09AUG11 25AUG11

    132BTFP03Pressure test in wet pilot pipes 7 0 27AUG11 03SEP11 27AUG11 03SEP11

    132BTFP05 Install Wet pilot sprinkler heads 6 0 04SEP11 10SEP11 04SEP11 10SEP11

    132BTFP07 Installation of Deluge pipes 20 0 23AUG11 14SEP11 23AUG11 14SEP11

    132BTFP09 Installation of Deluge Nozzles 4 0 06OCT11 10OCT11 06OCT11 10OCT11

    Fire Detection

    132BTFD01Installation of Cables 18 0 09AUG11 29AUG11 09AUG11 29AUG11

    132BTFD02Cble Testing 3 0 30AUG11 01SEP11 30AUG11 01SEP11

    132BTFD03Install Devices 4 0 06SEP11 10SEP11 06SEP11 10SEP11

    11 kV Cable Floor

    Fire Systems Access11KV BT Fire Protection & Detection Access 0 0 19MAY11* 19MAY11*

    2011 2012FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F

    Provided by Siemens dated 31.03.2011

    Provided by Siemens dated 31.03.2011

    Sheet 2 of 7

  • 8/6/2019 Sample Programme Target vs Actual

    3/7

    Sheet 3 of 7

    Activity

    ID

    Activity

    Description

    Orig

    Dur

    %

    Complet

    Planned

    Start

    Planned

    Finish

    Actual

    Start

    Actual

    Finish

    Fire Protection

    11BTFP01 Installation of Wet pilot pipes 20 0 21MAY11 12JUN11 21MAY11 12JUN11

    11BTFP03 Pressure test in wet pilot pipes 7 0 13JUN11 20JUN11 13JUN11 20JUN11

    11BTFP05 Install Wet pilot sprinkler heads 7 0 21JUN11 28JUN11 21JUN11 28JUN11

    11BTFP07 Installation of Deluge pipes 20 0 28MAY11 19JUN11 28MAY11 19JUN11

    11BTFP09 Installation of Deluge Nozzles 5 0 01OCT11 05OCT11 01OCT11 05OCT11

    Fire Detection

    11BTFD01 Installation of Cables 18 0 28MAY11 16JUN11 28MAY11 16JUN11

    11BTFD03 Cble Testing 3 0 18JUN11 20JUN11 18JUN11 20JUN11

    11BTFD05 Install Devices 4 0 25JUN11 28JUN11 25JUN11 28JUN11

    GROUND FLOORET-1,2 & 3 Rooms

    Fire Systems Access

    ET-1-3 Fire Protection & Detection Access 0 0 23JUL11* 23JUL11*

    Fire Protection

    ETFP01 Installation of Wet pilot pipes 12 0 24JUL11 06AUG11 24JUL11 06AUG11

    ETFP02 Pressure test in wet pilot pipes 4 0 07AUG11 10AUG11 07AUG11 10AUG11

    ETFP03 Install Wet pilot sprinkler heads 6 0 11AUG11 17AUG11 11AUG11 17AUG11

    ETFP04 Installation of Deluge pipes 12 0 24JUL11 06AUG11 24JUL11 06AUG11

    ETFP05 Installation of Deluge Nozzles 4 0 11OCT11 15OCT11 11OCT11 15OCT11

    Fire Detection

    ETFD01 Installation of Cables 10 0 24JUL11 03AUG11 24JUL11 03AUG11

    ETFD02 Cble Testing 3 0 04AUG11 07AUG11 04AUG11 07AUG11

    ETFD03 Install Devices 3 0 08AUG11 10AUG11 08AUG11 10AUG11

    IDT-1,2 & 3 Rooms

    Fire Systems Access

    IDT -1-3 Fire Protection & Detection Access 0 0 13JUL11* 13JUL11*

    Fire Protection

    IDTFP01 Installation of Wet pilot pipes 22 0 14JUL11 08AUG11 14JUL11 08AUG11

    IDTFP02 Pressure test in wet pilot pipes 4 0 09AUG11 13AUG11 09AUG11 13AUG11

    IDTFP03 Install Wet pilot sprinkler heads 4 0 14AUG11 17AUG11 14AUG11 17AUG11

    IDTFP04 Installation of Deluge pipes 25 0 21JUL11 18AUG11 21JUL11 18AUG11

    IDTFP05 Installation of Deluge Nozzles 3 0 11OCT11 13OCT11 11OCT11 13OCT11

    2011 2012FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F

    Provided by Siemens dated 31.03.2011

    Provided by Siemens dated 31.03.2011

    Sheet 3 of 7

  • 8/6/2019 Sample Programme Target vs Actual

    4/7Sheet 4 of 7

    Activity

    ID

    Activity

    Description

    Orig

    Dur

    %

    Complet

    Planned

    Start

    Planned

    Finish

    Actual

    Start

    Actual

    Finish

    Fire Detection

    IDTFD01 Installation of Cables 16 0 14JUL11 01AUG11 14JUL11 01AUG11

    IDTFD02 Cble Testing 4 0 04AUG11 08AUG11 04AUG11 08AUG11

    IDTFD03 Install Devices 3 0 16AUG11 18AUG11 16AUG11 18AUG11

    Reactor RoomFire Systems Access

    RTR-00 Fire Protection & Detection Access 0 0 13JUL11* 13JUL11*

    Fire Protection

    RTRFP01 Installation of Wet pilot pipes 12 0 14JUL11 27JUL11 14JUL11 27JUL11

    RTRFP02 Pressure test in wet pilot pipes 4 0 28JUL11 01AUG11 28JUL11 01AUG11

    RTRFP03 Install Wet pilot sprinkler heads 12 0 02AUG11 15AUG11 02AUG11 15AUG11

    RTRFP04 Installation of Deluge pipes 12 0 21JUL11 03AUG11 21JUL11 03AUG11

    RTRFP05 Installation of Deluge Nozzles 2 0 15OCT11 16OCT11 15OCT11 16OCT11

    Fire Detection

    RTRFD01 Installation of Cables 6 0 14JUL11 20JUL11 14JUL11 20JUL11

    RTRFD02 Cble Testing 2 0 21JUL11 23JUL11 21JUL11 23JUL11

    RTRFD03 Install Devices 2 0 24JUL11 25JUL11 24JUL11 25JUL11

    132 KV GIS RoomsFire Systems Access

    132GIS Fire Detection Access 0 0 14JUL11* 14JUL11*

    Fire Detection

    132GIS01 Installation of Cables 12 0 16JUL11 28JUL11 16JUL11 28JUL11

    132GIS02 Cable Testings 4 0 30JUL11 02AUG11 30JUL11 02AUG11

    132GIS03 Installation of MIMIC Panels 8 0 16JUL11 24JUL11 16JUL11 24JUL11

    132GIS04 Installation of Repeator Panel 8 0 25JUL11 02AUG11 25JUL11 02AUG11

    132GIS05 Installation Of Devices 4 0 03AUG11 07AUG11 03AUG11 07AUG11

    132GIS06 Installation of Extinguishers 1 0 08AUG11 08AUG11 08AUG11 08AUG11

    Fire Pump Room

    Fire Systems Access

    PMP00 Fire Protection & Detection Access 0 0 22JUN11* 22JUN11*

    Fire Protection SystemPMPFP01 Install Pipes 20 0 23JUN11 16JUL11 26JUL11 17AUG11

    PMPFP02 Install Fire Pumps 2 0 07SEP11 08SEP11 12SEP11 13SEP11

    2011 2012FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F

    Provided by Siemens dated 31.03.2011

    Provided by Siemens dated 31.03.2011

    Provided by Siemens dated 31.03.2011

    Sheet 4 of 7

  • 8/6/2019 Sample Programme Target vs Actual

    5/7Sheet 5 of 7

    Activity

    ID

    Activity

    Description

    Orig

    Dur

    %

    Complet

    Planned

    Start

    Planned

    Finish

    Actual

    Start

    Actual

    Finish

    PMPFP05 Install Valves & Accessories 6 0 10SEP11 15SEP11 14SEP11 20SEP11

    Fire Detection System

    PMPFD01 Install Cables 12 0 23JUN11 06JUL11 23JUN11 06JUL11

    PMPFD03 Cable testing 3 0 07JUL11 10JUL11 07JUL11 10JUL11

    PMPFD05 Install Devices 6 0 11JUL11 17JUL11 11JUL11 17JUL11

    PMPFP07 Install Pump Controlers 3 0 07SEP11 10SEP11 12SEP11 14SEP11

    Security Room

    Fire Systems Access

    SECU00 Fire Detection Access 0 0 22JUN11* 22JUN11*

    Fire Detection

    SECU01 Install Cables 4 0 23JUN11 27JUN11 23JUN11 27JUN11

    SECU03 Cable Testing 2 0 28JUN11 29JUN11 28JUN11 29JUN11

    SECU05 Install Device 2 0 30JUN11 02JUL11 30JUN11 02JUL11

    SECU07 Install MIMIC Panels 4 0 23JUN11 27JUN11 09JUL11 12JUL11

    SECU09 Install Repeater Panels 2 0 28JUN11 29JUN11 13JUL11 14JUL11

    SECU13 Termination of Cables 2 0 03JUL11 04JUL11 03JUL11 04JUL11

    FIRST FLOOR

    Capacitor Bank Room -1-3Fire Systems Access

    CAPOR Fire Protection & Detection Access 0 0 24SEP11* 24SEP11*

    Fire Protection System

    CAPFP01 Install Supports and Pipes 9 0 25SEP11 04OCT11 25SEP11 04OCT11

    CAPFP03 Presuure test 2 0 05OCT11 06OCT11 05OCT11 06OCT11

    CAPFP05 Install Nozzles 4 0 24OCT11 27OCT11 24OCT11 27OCT11

    Fire Detection System

    CAPFD01 Install Cables 4 0 25SEP11 28SEP11 25SEP11 28SEP11

    CAPFD03 Cable Testing 2 0 29SEP11 01OCT11 29SEP11 01OCT11

    CAPFD05 Install Devices 2 0 02OCT11 03OCT11 02OCT11 03OCT11

    Nitrogen Room

    Fire Systems Access

    NTGN00 Fire Protection & Detection Access 0 0 24SEP11* 24SEP11*

    Fire Protection System

    NTGNFP01 Install Nitrogen System Cylinders 14 0 25SEP11 10OCT11 25SEP11 10OCT11

    2011 2012FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F

    Provided by Siemens dated 31.03.2011

    Provided by Siemens dated 31.03.2011

    Provided by Siemens dated 31.03.2011

    Sheet 5 of 7

  • 8/6/2019 Sample Programme Target vs Actual

    6/7Sheet 6 of 7

    Activity

    ID

    Activity

    Description

    Orig

    Dur

    %

    Complet

    Planned

    Start

    Planned

    Finish

    Actual

    Start

    Actual

    Finish

    NTGNFP03 Install Nitrogen System Pipes 7 0 11OCT11 18OCT11 11OCT11 18OCT11

    NTGNFP05 Install Valves & Accessories 4 0 19OCT11 23OCT11 19OCT11 23OCT11

    Fire Detection System

    NTGNFD01 Install Cables 17 0 25SEP11 13OCT11 25SEP11 13OCT11

    NTGNFD03 Cable Testing 4 0 15OCT11 18OCT11 15OCT11 18OCT11

    NTGNFD05 Install Gas Release panels 6 0 19OCT11 25OCT11 19OCT11 25OCT11

    NTGNFD07 Install Devices 2 0 26OCT11 27OCT11 26OCT11 27OCT11

    11 kV Switch Gear Room

    Fire Systems Access

    11SWGR Fire Detection Access 0 0 07SEP11* 07SEP11*

    Fire Detection System

    11SWR01 Installation of Cables 20 0 08SEP11 01OCT11 08SEP11 01OCT11

    11SWR03 Cable Testings 8 0 02OCT11 10OCT11 02OCT11 10OCT11

    11SWR05 Installation of MIMIC Panels 8 0 08SEP11 17SEP11 08SEP11 17SEP11

    11SWR07 Installation of Repeator Panel 8 0 08SEP11 17SEP11 08SEP11 17SEP11

    11SWR09 Installation Of Devices 4 0 11OCT11 15OCT11 11OCT11 15OCT11

    11SWR11 Installation of Extinguishers 1 0 16OCT11 16OCT11 16OCT11 16OCT11

    SECOND FLOOR

    Corridoor & Rooms

    Fire Systems Access

    FIR00 Fire Detection Floor & Celing Access 0 0 07SEP11* 07SEP11*

    Fire Detection Systems

    FIRFL01 Install Cable 12 0 08SEP11 21SEP11 08SEP11 21SEP11

    FIRFL03 Cable Testing 12 0 22SEP11 05OCT11 22SEP11 05OCT11

    FIRFL05 Install Devices 6 0 06OCT11 12OCT11 06OCT11 12OCT11

    FIRFL07 Install Extinguishers 2 0 13OCT11 15OCT11 13OCT11 15OCT11

    Control Room

    Fire Systems Access

    FCR01 Fire Detection Floor & Celing Access 0 0 29OCT11* 29OCT11*

    Fire Detection Systems

    FCR02 Install Cables 12 0 30OCT11 12NOV11 30OCT11 12NOV11

    FCR03 Cable Testing 12 0 13NOV11 26NOV11 13NOV11 26NOV11

    FCR04 Install Devices 6 0 20NOV11 26NOV11 20NOV11 26NOV11

    2011 2012FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F

    Provided by Siemens dated 31.03.2011

    Provided by Siemens dated 31.03.2011

    To be confirmed by Siemens

    Sheet 6 of 7

  • 8/6/2019 Sample Programme Target vs Actual

    7/7Sheet 7 of 7

    Activity

    ID

    Activity

    Description

    Orig

    Dur

    %

    Complet

    Planned

    Start

    Planned

    Finish

    Actual

    Start

    Actual

    Finish

    FCR05 Install FACP Panel 6 0 30OCT11 05NOV11 30OCT11 05NOV11

    FCRPANL Panel Programming 10 0 15NOV11 26NOV11 15NOV11 26NOV11

    EXTERNAL AREA

    Fire Water Tank Area

    Fire Systems Access

    WATR00 Fire Protection & Detection Access 0 0 08AUG11* 08AUG11*

    Fire Protection Systems

    ATRFA05Install Pipes & Valves 16 0 13AUG11 30AUG11 13AUG11 30AUG11

    ATRFD07Install Cables 4 0 27AUG11 30AUG11 27AUG11 30AUG11

    ATRFD09Install Devices & Cable tests 2 0 31AUG11 01SEP11 31AUG11 01SEP11

    Manifold Locations

    Fire Systems Access/ClearenceEXTMD Fire Protection & Detection Access 0 0 25AUG11* 25AUG11*

    Fire Protection & Detection works

    EXTMD01 Installation of Manifold No.1 1 0 27AUG11 27AUG11 27AUG11 27AUG11

    EXTMD03 Installation of Valves & Accessories 10 0 27AUG11 06SEP11 27AUG11 06SEP11

    EXTMD04 Install cables & Device 1 0 07SEP11 07SEP11 07SEP11 07SEP11

    EXTMD16 Installation of Manifold No.2 1 0 28AUG11 28AUG11 28AUG11 28AUG11

    EXTMD18 Installation of Valves & Accessories 16 0 07SEP11 25SEP11 07SEP11 25SEP11

    EXTMD20 Install cables & Device 1 0 26SEP11 26SEP11 26SEP11 26SEP11

    Trench Areas

    Fire Systems Access/Clearence

    TRCH Fire Protection & Detection Access 0 0 25AUG11* 25AUG11*

    Fire Protection & Detection works

    TRCH01 Install Supports & Pipes 26 0 27AUG11 25SEP11 27AUG11 25SEP11

    TRCH03 Pressure test 2 0 26SEP11 27SEP11 26SEP11 27SEP11

    TRCH05 Installs Valves & Hydrants 2 0 28SEP11 29SEP11 28SEP11 29SEP11

    TESTING & COMMISSIONING PHASE

    Fire ProtectionT&C FP Fire Protection Systems 16 0 29OCT11 15NOV11 29OCT11 15NOV11

    Fire Detection

    T&C FD Fire Detection Systems 16 0 27NOV11 14DEC11 27NOV11 14DEC11

    2011 2012FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN F

    Provided by Siemens dated 31.03.2011

    Provided by Siemens dated 31.03.2011

    Provided by Siemens dated 31.03.2011

    Sheet 7 of 7