The 60 acre San Diego City College campus is home to more than 17,000 students and offers 100 majors and 115 certificate programs. Propositions S & N-funded projects for City College include six new instructional and career training facilities, eight major renovations, parking facilities, public safety enhancements and a sweeping infrastructure upgrade. The design and construction will follow the updated master plan as adopted by City College in 2008.
Citation preview
Seven new teaching and learning facilities
Seven major renovations
Campus expansion willprovide facilities/programs toaccommodate eventual enrollment of 25,000 students
SDCCD Propositions S and N
City College Overview
Project Budget: $3.4 million
Completion Date: August 2007
Renovation to convert approximately 15,000 SF of
parking garage space into faculty offices, student
classrooms and support space. First Propositions S
and N project to obtain LEED certification.
City College Completed Projects
Learning Resource Center (LRC)
Project Budget: $10.3 million
Completion Date: April 2009
Complete, major renovation of two-story building
totaling 28,700 sq. ft. Serves as one-stop shopping
for all student services, including tutoring,
assessment, advising, and other student support
and student achievement programs.
City College Completed Projects
Academic Success Center (L Building Renovation)
Project Budget: $10.9 million
Completion Date: January 2010
Major interior and exterior renovation of two-
story concrete gymnasium building. Renovated
facility includes work-out rooms, locker rooms,
training areas, classrooms, faculty/staff areas, and
enhanced parking and ADA accessibility.
City College Completed Projects
P Building Renovation
Project Budget: $63.1 millionConstruction Start: May 2008Completion: June 2010
New five-story 88,000 sq. ft. facility to house the
Nursing, Cosmetology and Photography &
Digital Arts programs. Includes classrooms,
computer labs, medical simulation labs, a
gallery for student work, a 694-space parking
structure and new headquarters for City College
Police. It has nation’s largest vertical solar array.
City College Completed Projects
Career Technology Center (CTC)
Project Budget: $89.2 million
Expected Construction Start: Nov. 2010
Targeted Completion: October 2012
Arts & Humanities will consist of approximately
70,000 sq. ft. to include new classrooms, a lecture
hall, computer labs, studio space and a 100-seat
“black box theatre.”
Business Technology will consist of approximately
40,000 sq. ft. to include classrooms, computer labs
and areas for start-up businesses for students.
The project includes sublevel parking designated
for ADA and faculty.
Propositions S and N Projects in Progress
Humanities and Business Technology Buildings
Project Budget: $54.4 millionExpected Construction Start: March 2011Targeted Completion: Dec. 2012
Four-story, L-shaped building providing 73,000 square feet of new construction for classrooms, labs and a planetarium.
Propositions S and N Projects in Progress
Science Building
Project Budget: $80.9 million (incl. land acquisition)
Expected Construction Start: January 2011
Targeted Completion: May 2012
Project involves land acquisition and construction
of new 72,000 sq. ft. classroom and laboratory
building. It will include the District’s Corporate
Education Center, Military Education, a Family
Health Center and a six-story parking structure
with 400+ stalls.
City College Future Projects
Math and Social Sciences
Project Budget: $17.7Expected Construction Start: July 2010Targeted Completion: Nov. 2012
•Central Plant Expansion•Storm & Sewer Upgrades•IT/Data/Comm Infrastructure Upgrade
Propositions S and N Projects in Progress
Infrastructure Projects
Construction Start: Summer 2010
Estimated Construction Cost: $8 million
Project will provide:
•Installation of new electrical switchgear and distribution.
•Installation of new heating and cooling water piping and distribution to the main campus.
•Construction of a new Central Plantbuilding to the east of the L Building.
City College Current Projects
Central Plant Upgrade
Construction Start: Fall 2010
Estimated Construction Cost: $4 million
Project will provide:
•16th Street Sewer Replacement -From Russ Boulevard to Broadway
•Storm Drain Replacements-From T Building Parking Lot to B Street-From B Street to 16th Street-From 16th Street to C Street
City College Future Projects
16th Street Sewer/Storm Drain Upgrade Project
Construction Start: Fall 2010
Estimated Construction Cost: $1.2 million
Project will provide a data/IT loop around the City College campus. The construction documents have been completed and approved by the City.
City College Current Projects
Telecommunications Infrastructure
C Building RenovationProject Budget – $21.8 MillionDSA Submittal ETA – August 2011
M Building RenovationProject Budget – $9.7 MillionDSA Submittal ETA – December 2011
Child Development Center Project Budget – $11 MillionDSA Submittal ETA – September 2011
Eng. Technology / T Bldg RenovationProject Budget – $38.4 MillionDSA Submittal ETA – August 2011
A Building RenovationProject Budget – $28.9 MillionDSA Submittal ETA – August 2011
D Building RoofProject Budget – $3.1 Million DSA submittal – August 2010
SAN DIEGO COLLEGE
As the current projects in design and construction complete, these projects will need to be through the design phase
and ready to begin construction.
Propositions S and N
Projects in Planning
SAN DIEGO COLLEGE
Propositions S and N Facilities and Master Plan Update
Questions?
Dave UmstotVice Chancellor Facilities Management