SAP Performance Testing Guidelines by Suryakanth Kelmani - Performance Testing SME - Europe
Citation preview
1. SAP Performance Testing Best Practices Guide BEST PRACTICES
FOR SAP R3 PERFORMANCE TESTING By SURYAKANTH KELMANI Performance
Engineering Practice Wipro Technologies Version No. Author Revision
Description0.1 Suryakanth Kelmani Initial draft issued for internal
review0.2 Suryakanth Kelmani Added the SAP Performance Test Lab
setup0.3 Suryakanth Kelmani Updated with the Monitoring T codes and
Batch jobs execution results0.4 Suryakanth Kelmani Updated with SAP
performance testing methodology.0.5 Suryakanth Kelmani Added SAP
WEB correlations Wipro Performance Engineering Practice
2. SAP Performance Testing Best Practices Guide TABLE OF
CONTENT1. INTRODUCTION
.........................................................................................
3 1.1 OBJECTIVE
................................................................................................
........................... 3 1.2 PERFORMANCE TESTING FRAMEWORK
.........................................................................
32. PLANNING
..................................................................................................
4 2.1 BUSINESS STREAMS: ................................
................................ ................................
.......... 5 2.2 TEST ENVIRONMENT ................................
................................ ................................
.......... 8 2.3 TEST DATA MANAGEMENT
................................
............................................................... 9
2.4 TEST TOOL & SETUP ................................
..........................................................................103.
BUILD / TEST SCRIPTS
DESIGN.............................................................
12 3.1 SERVER SIDE SETTINGS ................................
....................................................................12
3.2 CLIENT SIDE SETTINGS
.....................................................................................................124.
EXECUTION..............................................................................................
15 4.1 EXECUTION OF ONLINE USERS In SILO
.......................................................................15
4.2 EXECUTION OF BATCH JOBS & REPORTS In SILO
......................................................15 4.3
APPROACH FOR BATCH JOBS PERFORMANCE TESTING
.............................................15 4.4 EXECUTION OF
ONLINE USERS AND BATCH JOBS & REPORTS (Combined)
..............17 4.5 RUN TIME SETTINGS FOR EXECUTION:
................................ ................................
.........17 4.6 SCHEDULE BUILDER ................................
................................ ................................
.........185. MONITORS &
ANALYSIS.........................................................................
19 5.1 SAPGUI MONITOR
................................................................................................
..............196. SAP PERFORMANCE MEASUREMENT & METRICS
............................ 22 6.1 WORKLOAD ANALYSIS
.....................................................................................................22
6.2 MEMORY/BUFFER MANAGEMENT ................................
................................ ..................22 6.3 DATABASE
MANAGEMENT ................................
.............................................................. 23
6.4 UNIX SERVERS (OS Parameters, CPUs, Memory)
................................ ................................
237. SAMPLE
GRAPHS.....................................................................................
24 7.1 UNIX RESOURCE GRAPH ................................
................................ ................................
...24 7.2 EXECUTIVE SUMMARY GRAPH
................................................................
....................... 25 7.3 AVERAGE RESPONSE TIME GRAPH FOR T
CODES ................................ ........................25
7.4 BATCH JOB/INTERFACE SAMPLE REPORT
.....................................................................268.
APPENDIX
.................................................................................................
26 A. LOADRUNNER HARDWARE & SOFTWARE
.................................................................26
B. SAP T CODES & ITS FUNCTIONS
...................................................................................26
C. SAP WEB CORRELATIONS
................................................................
............................. 27 D. REFERENCES
...................................................................................................................28
Wipro Performance Engineering Practice
3. SAP Performance Testing Best Practices Guide1.
INTRODUCTION1.1 OBJECTIVE The objective of this document is to
detail the best practice, approach & planto be followed for the
Performance testing of SAP application and to make sure thatthe
team member who is going to carry out performance test activities
can quicklyrefer and implement the best practice followed across
all phases of performancetesting. This document is intended to
guide further Volume Test Planning, tool setup,Script Preparation,
Execution & Result analysis activities of Performance test
phase.1.2 PERFORMANCE TESTING FRAMEWORK The below diagram depicts
the robust & proven performance testingframework for SAP
performance testing, each phase has the detailed activities
thatneeds to be carried out and the output or deliverables at the
end of each phase asshown in the fig below. Activities of each
phase are explained in the below sections... Performance Testing
Framework Wipro Performance Engineering Practice
4. SAP Performance Testing Best Practices Guide2. PLANNING The
objective of planning phase is to identify tasks, pre-requisite
anddependencies that is required to carry out performance testing.
Planning phase shouldexplain what are the activities you are going
to do and how we are going to plan inorder to get these task done,
what ever activities we do identify in this phase shouldbe noted
down and put these tasks on priority basis.The key tasks involved
in this phase are: Prepare the performance test approach Identify
the critical transactions, volumes, user base and define their
SLAs. Identify the environment and tools required Identify test
data requirements Prepare a detailed Project plan with miles stones
and the deliverables. Performance test approach document will
specify the approach taken to carryout performance test, scope of
testing, environments and tools used, inputs,dependencies and
deliverables of the Performance testing phase. Information
regarding critical transactions for each work stream, theassociated
volumes and the concurrent user information is expected to be
madeavailable by the business team in the form of NFR (Non
Functional Requirements)document. This NFR should contain the data
like Concurrent Users, Critical T Codes,batch Jobs, Volume of
transactions, transaction response time, batch executionwindow etc.
There are two different categories of business process types we
need toidentify in order to have smooth execution of the project,
they are divided into Onlineusers and Batch
Jobs/Interfaces/Reports. You cant just neglect Batch jobs
whichplays an important factor in successful of SAP performance
testing. Like online users,critical & data intensive batch jobs
needs to be identified along with Online users, thebatch jobs time
window, the SLAs for batch jobs how many number of records
eachbatch jobs should be processed, the important success factor
for batch jobs executionis that, are the batch jobs able to execute
n number of records within the specifiedtime window, for example
Print batch jobs able to print thousands of records within 1hour.
During this planning phase please note that there will be other
parallelactivities that can be carried out, like identification of
environments as well as thetools for performance testing, test data
analysis, work load profiling etc. Performancetesting is normally
carried out on an environment that is representative of
theProduction environment in terms of hardware, software
configuration and databasesize. Performance test tools will be used
to generate scripts and simulate user load onthe system under test.
Please note that HP Load Runner will be the best tool that canbe
used for SAP performance testing as its also been widely used &
recommended bySAP. It is necessary to have Production size data in
order to get accurate test results.There is a dependency on the
other team like Data Migration to provide the requiredvolumes of
data for carrying out performance testing. During planning phase,
test data Wipro Performance Engineering Practice
5. SAP Performance Testing Best Practices Guiderequirements
like material number, customer account, GL account, Sold to
Party,WBS Cost centre, etc will be identified and communicated to
the Functional Team orData Creation Team. SAP system has several
Business Streams like Sales & Distribution,
FinancialAccounting, Supply Chain Management, SRM, Record To Report
RTR, HR, RealEstate, Material Management etc and these are called
business streams in SAPlanguage and given below are the example for
4 business streams identified for one ofthe Energy & Utilities
client for performance testing.2.1 BUSINESS STREAMS: The following
4 streams ( for example, it could be more ) were identified
forperformance testing of SAP application, each streams transaction
codes ( T codes)were identified with critical and most frequently
used on daily basis also dataintensive in nature as shown in the
below tables for each streams. Again these shouldbe put them into
Online and batch jobs category.SALES & DISTRIBUTION (SD):
Create an order with five line items. (VA01) Create a delivery for
this order. (VL01N) Display the customer order. (VA03) Change the
delivery (VL02N) and post goods issue. List 40 orders for one
sold-to party. (VA05) Create an invoice. (VF01)Note: Each benchmark
user has his or her own master data, such as material, vendor,or
customer master data to avoid data-locking situations.Dialog
Steps0. Logon 10. Choose Enter1. Main screen 11. Call /nVL02n
(Change delivery)2. Call /nVA01 (Create customer order) 12. Choose
[F20] (Posts goods issue)3. First screen 13. Call /nVA05 (List
orders)4. Second screen (with five items) 14. Choose Enter5. Choose
Save 15. Call /nVF01 (Create invoice)6. Call /nVL01N (Create a
delivery) 16. Choose Save7. First screen 17. Call /nend8. Choose
Save 18. Confirm log off9. Call /nVA03 (Display customer order)
Wipro Performance Engineering Practice
6. SAP Performance Testing Best Practices GuideUser interaction
steps 2 - 16 are repeated n times (15 user interaction steps -->
min.150 sec. duration).FINANCIAL ACCOUNTING (FI):Dialog Steps0.
Logon 11. Select first line1. Main screen 12. Call Post incoming
payments2. Call Post Document 13. Enter header data3. Create
customer item 14. Choose Process open items4. Create general ledger
account item 15. Select item 5 of the list5. Choose Post 16. Scroll
down to the end6. Call Display document 17. Select last item7.
Enter previous posted document 18. Deactivate all selected items8.
Double-click first line 19. Choose Post9. Call Customer line item
display 20. Call /n end10. Enter data and choose Execute 21.
Confirm log offUser interaction steps 2 - 19 are repeated n times
(15 user interaction steps --> min.180 sec. duration).EMPLOYEE
SELF-SERVICE PORTAL (EP-ESS):User Interaction Steps of the EP-ESS1.
Log on to the portal Welcome page 6. Choose Address(includes three
iViews)2. Choose Working Time > Record 7. Choose Bank
InformationWorking Time3. Choose Leave Request 8. Choose Benefits
and Payment > Paycheck Inquiry4. Choose Leave Request Overview
9. Log off from portal5. Choose Personal Information >Personal
Data Wipro Performance Engineering Practice
7. SAP Performance Testing Best Practices GuideSeven different
business transactions are launched per loop (steps 2 - 8). Every
loop isrepeated n times for each user. The user think time is 10
seconds; thus, one loop takesat least 70 seconds.MATERIALS
MANAGEMENT (MM)The Materials Management (MM) Benchmark takes you
through a series of steps tocreate a purchase requisition for five
materials (transaction ME51N), a purchase orderfor the five
materials (ME21N), a goods receipt (MIGO), and an invoice (MIRO)
forthe purchase orderDialog Steps0. Logon 10. Choose Execute1. Main
screen 11. Choose Post2. Call /nME51N (Create purchase 12. Call
/nMIRO (Create invoice), enterrequisition) company code3. Enter
data 13. Enter basic data4. Choose Post 14. Choose Payment5. Call
/nME21N (Create purchase order) 15. Enter data6. Enter data 16.
Choose Post7. Choose Post 17. Call /nend8. Call /nMIGO (Goods
receipt purchase 18. Confirm log offorder)9. Enter dataUser
interaction steps 2 - 16 are repeated n times (15 user interaction
steps --> min.150 sec. duration).Like online critical
transactions as depicted above, I have also mentioned some of
thebatch jobs names which we identified as critical for the
performance test executionduring one of the SAP performance testing
project. Wipro Performance Engineering Practice
8. SAP Performance Testing Best Practices Guide My suggestion
to the members of the performance testing team to go throughthe
business process involved in testing as many times as possible and
get familiarwith the business process/flow and note down the
required data that is going to beused in test scripts, this will
help them to proceed with much confidant and createmore robust
scripts with the accurate data.2.2 TEST ENVIRONMENT Ideally, the
simulated load and the hardware used for the volume test shouldbe
identical to the load and hardware of subsequent production
operation. However,for various technical, organizational or
economic reasons, it is not always feasible tosimulate the full
load expected in subsequent production operation. In addition, it
isnever really possible to execute the test on hardware exactly
identical to the hardwareplanned for production. But, as a best
practice performance testing should be carried out on anenvironment
which is mimicking close to the production environment hardware
andsoftware configuration, the next better option is to execute
performance test onproduction environment before its Go Live, i.e.
this should happen at least 6 weeksbefore the Go Live so that you
can make use of the best. Please note that dont try todo
performance testing on any other environment which is not at all
close orequivalent to production like. Important Note: Make sure
that the hardware used for the volume test isexclusively reserved
for this purpose while the volume test is run. In-parallel usage
ofthe same hardware or system(s) for other purposes (as, for
example, training system, )can have disastrous consequences for the
volume test and leads to misinterpretation ofits results. Note that
the SAP system will exchange data with a number of internal
andexternal non-SAP systems, i.e. Interfaces and Non SAP systems
like BACS, PAYMatrix, Billing System, Cyber Source etc.. In order
to carry out Performance testing,it is essential to connect to the
test environments of all the systems identified duringtesting.
Wipro Performance Engineering Practice
9. SAP Performance Testing Best Practices Guide In an SAP
Landscape a typical test environment consists of the
followingcomponents as shown in the below mentioned lines. ECC
6.0(ERP Central Component) SRM 5.5 (Supplier Relationship
Management) SCM FICO/HR/SD/MM/MDM/PM etc PI 3.0(Exchange
Infrastructure earlier Known as XI) BI Business Intelligence EP
(Enterprise Portal) And other Non SAP system integrated with SAP2.3
TEST DATA MANAGEMENT The data required for Performance testing
should be identified during thePerformance test planning phase. The
data to be set up within SAP as well as the datarequired connecting
and test with external systems will be defined. Since database
tables (especially transaction data tables) start to grow
afterstart of production, database accesses that are not fully
specified tend to get slowerand more resource-expensive. If the
volume test is performed with almost emptydatabase tables, the
response times in subsequent production operation will be
higherthan measured in the volume test. Therefore, for the volume
test to be meaningful,you need to populate the database tables with
representative data that is both masterand transactional data. We
must understand & set the expectation to the stakeholders that
which teamis going to provide all valid transactional data and who
is going to create various userids and passwords with proper roles
& authorizations for the realistic simulation ofuser load. For
example all HR user ids cant have Sales & Distribution Roles,
and allSCM user ids may not have HR roles and authorizations.Some
of the example below shows what data is required during performance
testing.. Master Data, o Customer Account Number o Sold To Party o
WBS Cost Element o Material Number o Employee Number etc.
Transactional Data o Bank A/c number o User Name o GL Account
Number etc. User Data o Delivery Date o Material Price o Customer
Name etc. Wipro Performance Engineering Practice
10. SAP Performance Testing Best Practices GuidePlease note
that the user ids and password for emulation of the load should be
createdby the Tech arch team or BASIS team (SAP back end
administrators are called asBasis), make sure that the team creates
the user ids with appropriate namingconventions so that each users
can be identified in the back end of the system duringperformance
testing as shown in the examples below.Sales & Supply Supply
Chain Enterprise Finance &Distribution SD Resource Management
Portal EP Accounting Management SCM FI SRMSD0001 SRM0001 SCM0001
EP0001 FI0001SD0002 SRM0002 SCM0001 EP0002 FI0002.. .. .. ..SD0200
SRM0400 SCM0150 EP0800 FI0300Any data (Transaction data, user data
etc) that is required during performance testingwill be provided by
each business streams.2.4 TEST TOOL & SETUP The diagram below
shows that the performance test lab setup which make useof 4 Load
injectors (Load generators) with one Loadrunner Controller, all the
m/c areconnected to each other on a business LAN which has access
to SAP system, eachsystem has the 2GB RAM with Intel CPU speed
2.8GHz. Please note that the machine running a scenario with SAPGUI
Vusers musthave a Loadrunner typical installation. Running Vusers
from machine with only thecontroller installed is NOT SUPPORTED,
and each Loadrunner systems (Injectorsand Controller m/c) should
have the SAPGUI client installed so that they can talk toback end
SAP ECC system. LoadRunner is HP (formerly Mercury Interactive)
load/performance testingtool. It operates using a record/replay
method in which the software allows a user torecord a business
process and then replay it. LoadRunner can simulate many users
onthe system at once. It accomplishes this by capturing all data
that passes from theclient machine to the SAP server and back while
recording. When replaying the script,LoadRunner sends the same data
that it captured back to the server, thus performingthe exact same
business processes that were recorded thus by emulating real users.
Wipro Performance Engineering Practice
11. SAP Performance Testing Best Practices Guide Fig.1
Performance Test Lab Setup with the Environment Terminal Services:
Machine running SAPGUI Vusers may be limited in thenumber of Vusers
that can run, due to the graphic resource available on that
machineand due to the limitations imposed by Microsoft windows on
GDI objects and userobjects.To rectify the above mentioned issue
and allow more SAP users to be run, it isrecommended that multiple
Terminal Server sessions be run on the load generatormachine
(Injector) and relate each terminal server session to the load
generator. Thismeans a Terminal Server must be running on the load
generator. Please note that you can run maximum of 30 to 50 SAPGUI
users on eachterminal session, MS Windows 2003 server Standard
edition should be installed oneach Load Generators machine in order
to run terminal sessions, by default you canhave three terminal
session run on each machine, so with this 3X50=150 total userscan
be run each m/c, if you want to run more sessions then you need to
buy thelicense from MS vendor in order to increase the session
which helps you to run morenumber of SAPGUI users.Let us recap the
following points in order to complete the Planning phase,The main
activities in test preparation phase include: Identification of
Test Scenarios for Batch job window Identification of Test
Scenarios for On-line users (SAPGUI and Portal users) Set up and
configure the Production environment with test data. Wipro
Performance Engineering Practice
12. SAP Performance Testing Best Practices Guide Test Plan
& approach document NFR (Non Functional Requirements)The
success factor: NFR document Sign-off Performance test plan &
approach document sign-off by the stake holders. Tools &
Environment Setup completion. Identification of Test Data. Test
Data Management3. BUILD / TEST SCRIPTS DESIGN Once the planning
phase is in place and signed off from the business, with theinput
from NFR and from the functional team, its time to design work load
module &develop automated scripts in order to simulate the real
users. Before we startscripting, we need to change some settings on
the SAP server which enables theautomated tool to record user
actions on SAPGUI protocol.3.1 SERVER SIDE SETTINGS Before you
start recording in the tool, you need to set certain parameters
inSAP server in order to generate the script Enabling scripting on
Server Side: By default, the scripting API is disabled in SAP R/3
system,. To enable scripting API, For all users of a given system,
the system administrator needs to set the sapgui/user_scripting
profile parameter to TRUE on all the application servers and make
sure that the above value TRUE should be in upper case, The
administrator needs to use the T code RZ11 in order to change the
above profile parameter.3.2 CLIENT SIDE SETTINGS Enabling scripting
on Client Side: You need to enable Scripting as circled in the red
colour in the screen shot below and disable all check boxes as
shown in the screen shot shown below. In order to do this, log on
to SAP server, select the Rainbow Icon and select Options. And you
must disable the remaining two check boxes 1. Notify When a Script
attaches to a Running GUI 2. Notify When a Script Opens a
Connection Wipro Performance Engineering Practice
13. SAP Performance Testing Best Practices GuideConfiguring the
Model Dialogue Boxes for F1 and F4-Client Side:a) For F1 In order
to configure this option, Log on to the SAP serverHelpSettings,
select F1Help Tab and select the in modal dialog box (R/3) option
inthe display section as shown in the screen shot below. Wipro
Performance Engineering Practice
14. SAP Performance Testing Best Practices Guideb) For F4 To
open F4 help in model dialog boxes, the following procedure must
becompleted by a SAP administrator. Choose Help>Settings. Click
the F4 Help tab. In the Display section (Bottom Left), choose
system defaults. In the display portion of the system defaults
sections (bottom right). Select theDialog. Click on the pencil icon
first before you can change the sections. Click on theicon again to
save lock the selection as shown in the screen shot below Once the
above settings are configured on the SAP App Server, please
selectSAPGUI protocol for creating SAPGUI scripts and SAPWEB
protocol for creatingEnterprise Portal scripts. The scripting for
SAPGUI users and SAPWEB users arequite simple and not to worry much
about scripting part as its 80% direct record &Replay with very
few code enhancements in SAPGUI, and few complex correlationsin SAP
web EP applications. There is not at all correlation concept in
SAPGUI exceptcapturing the o/p of one process and input the same
value for next process, for thisyou can use Loadrunner
sapgui_get_Status_bar () functions. Once the test scripts are
developed and enhanced to meet the businessrequirements,
parameterise various data, correlating the dynamic values etc,
thesescripts should be run for various iterations with different
data inputs and cross checkwith the records created in the back end
of the system. Once you have confirmed thatall scripts are doing
what its intended to do, then get these scripts run with
thebusiness team to confirm that they are in line with the NFR and
satisfies theirrequirements. At this point of time, ask the
Functional team to identify the Batch & Schedulethe batch jobs
for the batch execution window, usually these batch jobs are
scheduled Wipro Performance Engineering Practice
15. SAP Performance Testing Best Practices Guideand executed by
Functional Team either manually or by using some tool
likeController M ( is a batch job work load scheduler tool )The
success factor: Successful development & Replay of Automated
Test Scripts. Make sure that you use coding standards implemented
in all the scripts. Automated Test Scripts Sign-off by Business
Team. Production like setup batch jobs scheduled on the test
environment. Batch jobs are successfully smoke tested.4. EXECUTION
The approach for performance test execution will be carried out in
thefollowing manner, and it should look like this as shown below.
Performance Testing of Online Users (Individually for Online users)
Performance testing of Batch Jobs (Individually for Batch Jobs)
Combine Online Users and Batch Jobs together and execute
together4.1 EXECUTION OF ONLINE USERS In SILO Once the test scripts
development is completed then all the above identifiedstreams like
S&D, FI, EP(ESS) and MM should be executed in Loadrunner
controllerfor their respective concurrent loads and analyse the
result of each execution to findany bottlenecks in the stream wise.
Please note that the execution of these streamsshould be done in
isolation of each stream (i.e. stream S&D T codes should
beexecuted individually in isolation of other streams). This helps
the project team to findany performance bottleneck in the early
phase of the performance test execution. After successful execution
of individual streams, its now time to execute allstreams together
for concurrent number of users defined in the NFR and analyse
theperformance of the system overall4.2 EXECUTION OF BATCH JOBS
& REPORTS In SILO Batch performance models will be built to
represent the average and peak load ofbatch processing in SAP
systems. Batch scheduling (Functional) team will define
theproduction batch schedule and estimate average and peak load.
This helps the team to know ifany batch jobs & Reports are
taking much time and not fitting the batch window (Forexample 10PM
to 2:00AM ).Batch performance model will include the daily batch
jobs running in ECC, BI, SCM, SRM,XI, and JCAPS etc4.3 APPROACH FOR
BATCH JOBS PERFORMANCE TESTINGBelow is the detailed approach for
Batch jobs performance testing..Objective v Check batch job
performance in ECC XX environment. To ensure current level of
performance.Pre-requisite v Deployment of Control M* and related
application on the pre production environment for the identified
critical interfaces. Wipro Performance Engineering Practice
16. SAP Performance Testing Best Practices Guide v End to End
connectivity setup for flow. v Charged day identification for data
recording/ input file for the batch jobs. v Configure monitoring
tools on ECC XX to capture the performance metrics for the batch
executions.Approach v Capture batch job baseline data of selected
interface from the current ECC system. v All the critical batch
jobs which are to/from the SAP system should be considered (
including third party systems) v Trigger Job on SAP ECC system
using Control M for reference measurements v Use the input file and
process in ECC XX Environment v Trigger Job in ECC XX system using
Control M for validation v Tuning if required v generate
performance report*Please note that Control M is batch job
scheduler tool like AppWorkxA typical 24 hrs batch jobs approach is
depicted in the below diagram, whichillustrates the batch jobs
executions in SAP and Non SAP integrated environment,please note
that the batch jobs should be given much importance as process
largeamount of data to/from the SAP & third party applications
and they need to meet theperformance requirements/KPIs as per the
NFR document. Fig: Typical Batch Jobs executions in SAP performance
testing Wipro Performance Engineering Practice
17. SAP Performance Testing Best Practices Guide4.4 EXECUTION
OF ONLINE USERS AND BATCH JOBS & REPORTS (Combined) After
completion of performance test execution for online users and Batch
Jobs, weneed to combine both the scenarios Online Users & Batch
jobs to emulate the real scenarioand measure the system performance
of SAP R/3. The below screen shot shows how the scenarios with the
load generator looklike, please note that all the load generators
sessions are running on MS terminalserver sessions and each session
is mapped with their respective names like as shownin the screen
shot below.4.5 RUN TIME SETTINGS FOR EXECUTION: The below screen
shot shows the various RunTime Settings for the
scenariosexecutions, its important to apply these runtime settings
to in order to execute thescenario successfully. General: Run Logic
No Change Pacing With fixed delay of 40 seconds. (Depends) . Log
Standard Log Think Time Replay Think Time, use random percentage
with Min 100% Max 150% with Limit Think Time to 10Sec Wipro
Performance Engineering Practice
18. SAP Performance Testing Best Practices Guide Additional
attributes No Change Miscellaneous Run Vuser as Thread SAPGUI:
General Disable Show SAP client during Replay Network: Speed
Simulation Use Max Band Width.4.6 SCHEDULE BUILDER Go to Edit
Schedule and Set the following settings in the schedule builder
asshown below. RampUp: Start 5 Vusers for every 30 Seconds.
Duration: Run for 5 Hours (depends up which test you are doing, for
example duration should be 12 to 24 hours). RampDown: Stop 5 Vusers
for every 60 Seconds. Wipro Performance Engineering Practice
19. SAP Performance Testing Best Practices GuideChecklist
before execution:HP LoadRunner script testing will occur after
creation of each automated script.Scripts can be added to
performance test bed when: 1. No scripting errors occur. 2. Looping
successfully; replaces parameterization variables with various
values. 3. Activity is noted on each system tier. 4. A minimum load
of ten users is simulated. 5. Scripts are run on a subsequent day
(dates correlated correctly).5. MONITORS & ANALYSISYou need to
configure the following monitors in order to analyse the
loadrunnerresults, if you dont have SAPGUI monitor license then you
can ask the Basis team tomonitor the application through CCMS tools
(using STO3n Tcode) which will givesame data as of SAPGUI and
Database Monitors. SAP Monitor (SAPGUI Monitor) UNIX Resource
Monitor. Oracle Database Monitor Windows Monitor for WAS server5.1
SAPGUI MONITORThe following measurements will be taken for each
script as it is executed inLoadRunner:Response time: This starts
when a user request enters the dispatcher queue; ends when the next
screen is returned to the user, this will measure the end to end
response from the client to the system Wipro Performance
Engineering Practice
20. SAP Performance Testing Best Practices GuideWait time: This
is the time a user request sits in the dispatcher queue.Roll-in
time: This is the amount of time needed to roll user context into
the work process.Load time: This is the time needed to load from
the database and generate objects like ABAP code, CUA, and screen
information.Processing time: This is the time spent in the work
process executing ABAP code.Database time: Starts when a database
request is put through to the database interface; ends when the
database interface has delivered the result.CPU time: This is the
total CPU time used by the SAP R/3 work process. The SAP monitor
displays statistics about the resource usage of a SAP R/3system
during the scenario or session step run. This monitor is
appropriate for SAPR/3 server and SAPGUI (version 6.20 or later)
environments. SAP GUI transactions help the tech arch team and
performance team toquickly isolate the performance issues within
the SAP R/3 infrastructure, and toauthoritatively delegate problem
resolution to the right SAP application teams.The solution provides
a layered breakdown of performance of SAP R/3 transactionsinto
database, system, processing, and interface layers.Database layer
shows the amount of time spent by an end-user business process or
anindividual dialog step in the database tier.System layer shows a
breakdown of time the dispatcher is waiting for a free workprocess,
time taken to load or generate ABAP programs by the work process,
timetaken to associate the user context with a work process, and
time taken to save usercontext data on the outbound path.Processing
layer shows the amount of actual time taken by the work process
toprocess the ABAP programs and SAP application server.Interface
time refers to the performance characteristics of accessing
external systems -either SAP or non-SAP such as Remote Function
Call time.Below diagram shows the break down of each layer and this
should help the team tofind out the root cause of the bottleneck.
Wipro Performance Engineering Practice
21. SAP Performance Testing Best Practices Guide5.2 UNIX
RESOURCE MONITOR UNIX monitor gives the system resource parameters
of Unix server box, inorder to run UNIX monitor successfully on
Loadrunner controller, you need to runrstatd daemon service on Unix
server box, you can ask database admin team to set thisservice
running, or else you can ask him to carry out the following steps
as shownTo configure the rstatd daemon:1 Run the command: su root2
Go to /etc/inetd.conf and look for the rstatd row(it begins with
the word rstatd). If it is commented out (with a #), remove
thecomment directive, and save the file.3 From the command line,
run:Kill -1 inet_pidWhere inet_pid is the pid of the inetd process.
This instructs the inetd to rescan the/etc/inetd.conf file and
register all daemons which are uncommented, including therstatd
daemon.4 Run rup again.If the command still does not indicate that
the rstatd daemon is configured, contactyour system
administrator.PS: You can configure the remaining monitors like
Oracle Database and Windowsresource monitor just by adding their
respective IP addresses. Wipro Performance Engineering
Practice
22. SAP Performance Testing Best Practices Guide6. SAP
PERFORMANCE MEASUREMENT & METRICS The following activities
should be planned for the performance test: Use the SAP system
monitoring procedure to check the peak hours activity. Identify
long running jobs and run it to test server performance. Run
critical business transactions and measure runtime. Define peak
hours and the system to be monitored during execution in order to
identify performance problems. The monitoring should be done using
SAPs Comput ing Center Management System(CCMS) and the UNIX utility
vmstat. CCMS provides performance monitors that trackvarious
aspects of the SAP systems while the vmstat provides detailed
operating systemperformance information. SAP system performance
actually depends on many factors such as modulesimplemented,
database size, and number of users. Because of this, there are no
standardvalues that constitute good performance. However, based on
experience and SAPrecommendations, the Technical Architecture Team
has determined the following stress testperformance metrics are
indicative of satisfactory performance: 6.1 WORKLOAD ANALYSIS
Transaction ST03n records the response time of the system and of
individualtransactions. It can be used to see how fast the system
is responding. ST03n also dividesresponse times into CPU time, wait
time, load time, and database request time. These timeswill be
evaluated as a percentage of Average Response Time (ART) for each
server duringeach test so that it can be determined where increases
occur. Parameter Requireme Measuri Description nt ng Tool Average
Response