TESTING: UNIT TESTING / USER MANUAL MODULE : PRODUCTION PLANNING
ENVIRONMENT
SYSTEM : SAP R/3
CLIENT : 200
UNIT TESTING SCENARIO
SCENARIO NUMBER : PP05
DESCRIPTION : Order Confirmation
PREPARED BY
NAME : Shrikant Ingole
TEAM : Production Planning
DATE : 17/11/2008
APPROVED & TESTED BY
NAME : Nanhe Babu (PwC)
DATE :
TEAM : Production Planning
Page 1 of 11
TESTING: UNIT TESTING / USER MANUAL MODULE : PRODUCTION PLANNING
1. Transaction Code/ Path
Enter the menu path of the transaction code, which is going to be tested by the user.
Menu Path Logistics Production Shop Floor control Confirmation Enter For Operation CO11N Time Ticket
T-Code CO11N
2. Input Data
1. Enter the Input parameters, which need to be given by the user during the testing of this scenario.
2. Input the value for the fields and then if required, copy the screen shot of the input screen after the table.
Page 2 of 11
TESTING: UNIT TESTING / USER MANUAL MODULE : PRODUCTION PLANNING
2.1 Input Screen Name – Time Ticket For Production Order: Initial Screen
Description of the Field Nature of the Field Value of the Field
Order Mandatory Enter your Order No. 85000011
Operation Mandatory Enter your Operation No. 0010
Yield Optional Enter the no. item that one want to confirm
'Posting date' will be date on which Confirmation will be posted
'Reason for Var.',the reason for deviation of Confirmed Quantity to Planned Quantity.Plant wise reason codes are provided as F4 values.
click on
Observe the following Message
Page 3 of 11
TESTING: UNIT TESTING / USER MANUAL MODULE : PRODUCTION PLANNING
Again go to the CO11N for confirmation of another operation for the same order no
If there is no further operation the system will give you the following Message
Page 4 of 11
See the Message
Click Here
TESTING: UNIT TESTING / USER MANUAL MODULE : PRODUCTION PLANNING
For order confirmation there are three transaction codesCO11N
But 'CO11N' transaction code will be used.
For the material 311323000049 (collector Ring) there are Four operation.So we need to confirm the order no 85000012 four time for the four operations for t-code CO11NGo to CO11N
2.2 Input Screen Name – Time Ticket For Production Order: Initial Screen
Description of the Field Nature of the Field Value of the Field
Order Mandatory Enter the order no 85000012
Operation Mandatory Enter the operation 0010yield Optional Enter the no. of Item
See the following screen
Page 5 of 11
TESTING: UNIT TESTING / USER MANUAL MODULE : PRODUCTION PLANNING
After hitting the enter in above screen the following screen appears
Page 6 of 11
TESTING: UNIT TESTING / USER MANUAL MODULE : PRODUCTION PLANNING
Just Save the file (ctrl+s)The following message appears on the screen
This is only confirmation for the operation oneFollow the procedure for remaining operation
Page 7 of 11
TESTING: UNIT TESTING / USER MANUAL MODULE : PRODUCTION PLANNING
Operation 0020
2.3 Input Input Screen Name – Time Ticket For Production Order: Initial Screen
Description of the Field Nature of the Field Value of the Field
Order Mandatory Enter the order no 85000012
Operation Mandatory Enter the operation 0020
yield Optional Enter the no. of Item
Follow the same Procedure for the operation 0030 & 0040 by Entering T-code CO11N
Page 8 of 11
TESTING: UNIT TESTING / USER MANUAL MODULE : PRODUCTION PLANNING
For Last operation, please select following Tab
If the confirmed order is of Finish Good then do the Goods Receipt for the same product by entering the T-code MB31 other wise just check the stock by T-code MMBE & you will observe the quantity is increase by the confirmed quantity at production storage location.
Also you can change the time & work centre that is provide in the routing while confirming the order for such process please see the following screen
After entering the order no. & operation No. We will get all the standard data as per the routing data
Here we can mention the work center that is actually used while going for the machining process
Also can be entered the original time that has been taken for the machining.
Page 9 of 11
TESTING: UNIT TESTING / USER MANUAL MODULE : PRODUCTION PLANNING
Above screen shows all the standard data, While following screen shows the changed data according to the physical process
The actual time may be vary fro time entered in the routing then we can change this time to actual time Also same for the work centre
Down Time is the time for which the Work Centre was down. Shift tab is used to mention, in which Shift the Order was confirmed. In COOIS report, Shift wise production confirmation order can be seen.SHIFT values are '1', '2', '3'.
Outcome of the Testing using the T-code CO11N
1) Order confirmation is to be done stage wise
2) Partial or Full Quantity can be confirmed.
Page 10 of 11
TESTING: UNIT TESTING / USER MANUAL MODULE : PRODUCTION PLANNING
3) Time for the machining can be maintain as per the actual tme
4) Actual work center can be maintain without hanging the routing or using the production version.
5) Confirmation No. is generate
Page 11 of 11