Hunnewell Elementary School

Feasibility Study

SBC MeetingJuly 11, 2019

Elementary School Projects Timeline

Hunnewell Building Solution Conceptual Project Budget Summary

Description New Construction CostsBuilding Construction $45,250,000

Site Construction Included Above

Furniture, Equip. & Technology $1,300,000

Design and Consultant Fees $4,800,000

Project Management & Onsite Rep. $1,550,000

Other Administrative Costs $700,000 Contingencies $2,700,000

Photovoltaics (on school roof only) *** $1,200,000

Conceptual Project Budget (July 2019)*,**, $57,500,000

Fall 2019 Appropriation $4.6M

* Does not include the previously approved & funded $1.0 Million for the feasibility study

** Estimates above do not include Swing Space cost

*** Photovoltaics only include arrays on building, not adjacent sites.

Escalation

• Turner and RLB Indices report changes in construction cost quarterly to track escalation of construction costs

• These are projections based on 2018 dollars and do not attempt to anticipate relative purchasing power in 2021.

• This comparison shows that the average change per year in consumer price index is forecasted to be much lower (avg. 1.48%/year) than the average change in construction cost escalation (avg. 4.8%/year)

Stay Connected!

Follow the Hunnewell project or subscribe to updates:

wellesleyma.gov/HHU

Contact us: [email protected]

Meetings available online:

wellesleymedia.org/SBC

Hunnewell Elementary School

Feasibility Study

Swing Space

SBC Meetings: Swing Space Evaluation Timeline

• June 13th : Authorized Additional Services for Swing

Space Evaluation

• July 11th : Review Traffic Data and Updated Swing

Space Options for Late Hunnewell

• July 25th : Review Swing Space Options and Feasibility

Solution to Proceed to PBC and Advisory

Next Steps to Town Meeting

•August 8th : Presentation of Feasibility Study

Finding(s) to PBC

•August TBD: Presentation of Feasibility Study

Finding to Advisory

Hunnewell Elementary School

Feasibility Study

Late HunnewellSwing Space

Redistricting Options

Non-Redistricting Options

Current Districts

Scenario 1A Redistrict

Scenario 1B Redistrict

Study Area1. Weston Road at Cleveland Road & Route 9

Westbound Ramps

2. Weston Road at Route 9 Eastbound Ramp

3. Weston Road at Hardy Road

4. Weston Road at Turner Road & Avon Road

5. Weston Road at Linden Street

6. Linden Street at Crest Road

7. Weston Road at Central Street (Route 135)

8. Central Street (Route 135) at Washington Street (Route 16) & Grove Street

9. Washington Street (Route 16) at Wellesley Avenue & Brook Street

10. Washington Street (Route 16) at State Street & Kingsbury Street

11. Route 9 at Westgate Road & Oak Street

12. Route 9 at Westbound U-Turn

13. Route 9 at Kingsbury Street

14. Route 9 at Eastbound U-Turn

15. Bristol Road at Lowell Road

16. Bristol Road at Wynnewood Road & Oakridge Road

Bold = Traffic Signal

1. Data Compilation

▪ Compile Traffic Data at 16 intersections

2. Trip Generation and Distribution for Four Scenarios

▪ How many cars are redistributed as a result of redistricting?

▪ How many cars are redistributed from Hunnewell School?

3. Qualitative Analysis

1. 2026 No-Build and Build – Late Hunnewell

The traffic evaluation consisted of three primary tasks:

Scenario 1A

212 106 106

# Students

# Vehicle Trips

Scenario 1A Redistrict

Scenario 1A

212 106 106

# Students

# Vehicle Trips

Scenario 1A - Hunnewell Travel

Example of 2026 No-Build Volume

Scenario 1B

212

106

106

# Students

# Vehicle Trips

Scenario 1B Redistrict

Scenario 1A - Hunnewell Travel

Example of 2026 No-Build Volume

Scenario 2A

# Students

# Vehicle Trips

1490

New

0 New

Current Districts Sce

Scenario 2B - Hunnewell Travel

Example of 2026 No-Build Volume

Scenario 2B

0 New

# Students

# Vehicle Trips

1490 New

Current Districts

Scenario 2A - Hunnewell Travel

Example of 2026 No-Build Volume

Conclusions

▪ Pre-existing conditions operate with significant delay

and queuing on Weston Road, Route 9, and Kingsbury

Street

▪ Changes in traffic patterns will exacerbate

conditions

▪ More intersections impacted when Hunnewell

relocates to Upham

▪ Mitigations measures such as implementing carpool or

buses

Conclusions▪ Scenario 1A – Redistricting traffic impacts will be more

concentrated in area of Upham School. Additional impact to

Washington Street, Kingsbury Street, and Route 9

▪ Scenario 1B – Redistricting traffic impacts will be more

concentrated along Weston Road. Additional impact to

Washington Street, Kingsbury Street, and Route 9

▪ Scenario 2A – Additional impact to Washington Street,

Kingsbury Street, and Route 9

▪ Scenario 2B – Weston Road at Route 9 interchange and Hardy

Driveway at Weston Road significantly impacted

Hunnewell Elementary School

Feasibility Study

Late HunnewellSwing Space Site Slides

Late Hunnewell Options:With Redistricting

•Option 1A Redistrict w/o Mods:

New Upham, Old Upham, Old Hardy

•Option 1B Redistrict w/o Mods:

New Hardy, Old Hardy, Old Upham

•Option 1C Redistrict w/ Mods: (Traffic model sim)

New Upham, Old Hardy

•Option 1D Redistrict w/ Mods: (Traffic model sim)

New Hardy, Old Upham

New Upham

Hunnewell at Hardy

365 183

Late Hunnewell Swing Space1A: Upham Elementary School: 2024 Three Schools / Two SitesNew Upham, Hunnewell at Old Hardy & Old Upham

Hunnewell at Old Upham

182

Hunnewellat Upham

New Hardy

182365

Late Hunnewell Swing Space1B Hardy Elementary School: 2024 Three Schools / Two SitesNew Hardy, Hunnewell at Old Hardy & Old Upham

Hunnewell at Old Hardy

182

New Upham

Hunnewell at Old Hardy w/

Mods

365 365

Late Hunnewell Swing Space1C Upham ES Site: 2024 New Upham Complete / Hardy Closed -Hunnewell Occupancy Old Hardy w/ Mods

Hunnewell at Upham w/

Mods

New Hardy365 365

Late Hunnewell Swing Space1D Hardy ES Site: 2024 New Hardy Complete / Upham Closed -Hunnewell Occupancy Old Upham w/ Mods

Late Hunnewell Options:Without Redistricting

•Option 2A No Redistricting w/o Mods:

New Upham (Old Hardy & Old Upham required)

•Option 2B No Redistricting w/o Mods:

New Hardy (Old Upham & Old Hardy required)

New Upham + Hunnewell

Hardy195 277

Late Hunnewell Swing Space2A Upham Elementary School: 2024 Three Schools / Three buildings (No Redistricting & no mods)

256 451

Upham 256

Late Hunnewell Swing Space2B Hardy Elementary School: 2024 Three Schools / Three Buildings(No Redistricting & no mods)

New Hardy + Hunnewell

195 277 533

Swing Space Options Under ConsiderationOngoing study through Summer 2019

• Internal Swing Space

• St. Paul’s School

Or Delay Opening until 2026

• Late Hunnewell two schools on one campus

• Late Hunnewell with Redistricting uses vacated Hardy or Upham

School w/ Modulars

• Confirm budget assumptions for Late Hunnewell options

Hunnewell Elementary School

Feasibility Study

Site DesignDrop Off / Pick up ScenariosParkingTraffic Analysis

Considerations for Hunnewell Site Parking

• Classroom Teachers 18 spaces

• Specialists (Principal, SPED, Music, Art, Library) 15 spaces

• Paraprofessionals 14 spaces

• Travelling Staff (not included above) 3 spaces

• Other (Secretary, Nurse) 2 spaces

• Custodians (non- striped space) 1 spaces

H.C. Parking 3 spaces

EV Parking 2 spaces

Visitors 8 spaces

Total Estimated Number of Striped Spaces Required 65 Spaces

Onsite Vehicular Circulation & Parking:

+/- 47 Spaces 25 252225

Parking Comparison: Scenario A

Parking Comparison: Scenario B

Onsite Vehicular Circulation & Parking:

+/- 60 Spaces

18

252220

25

Onsite Vehicular Circulation & Parking:

+/- 55 Spaces

Offsite Vehicular Circulation & Parking:

25 Spaces

Total Parking:

+/- 80 Spaces

9

22

24

Parking Scenario B Revised

Site Circulation: AM Drop-off / PM Pick-up