69
S.C. Srivastava, Professor Departmentof Electrical Engineering Indian Institute of Technology Kanpur Email: [email protected] SC Srivastava / IITK WAMCS QIP course 10 May 2019 1

S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

  • Upload
    others

  • View
    9

  • Download
    1

Embed Size (px)

Citation preview

Page 1: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

S.C. Srivastava, ProfessorDepartmentof Electrical Engineering

Indian Institute of Technology KanpurEmail: [email protected]

SC Srivastava / IITK WAMCS QIP course 10 May 2019 1

Page 2: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

General Introduction The size and complexity of the system has increased.

A.C. transmission systems at 1100/1200 kV.

Generating unit sizes have gone upto 800/1000 MW.

HVDC links (+/- 500/800 kV) are in operation for back to back and long distance power transfer.

Concerns to its operators: Maintaining security, reliability, quality and stability of power system

Ensuring economic operation. ( Monopoly-Market based operation)

Leading to use of large number of sensors, DSP, PE devices, communication networks and IT enabled services ( Large CPS)

Computer aided monitoring & dispatching SCADA (Supervisory Control and Data Acquisition) based Energy

Management System (EMS)and Distribution Automation System (DMS).

Wide Area Monitoring and Control Systems (WAMCS) using synchrophasors.

2SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 3: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Power System Stability

Frequency

Stability

Small-Signal

Stability

Transient

Stability

Short

Term

Long

Term

Large-

Disturbance

Voltage Stability

Small-

Disturbance

Voltage Stability

Voltage

Stability

Rotor Angle

Stability

Consideration

for

Classification

Physical

Nature/ Main

System

Parameter

Size of

Disturbance

Time

Span

Short Term

Short

Term

Long

Term

P. Kundur, J. Paserba, V. Ajjarapu, G. Andersson, A. Bose, C. Canizares, N. Hatziargyriou, D. Hill, A. Stankovic, C. Taylor, T. V. Cutsem, and V. Vittal, "Definition and classification of power system stability IEEE/CIGRE joint task force on stability terms and definitions," IEEE Transactions on Power Systems, vol. 19, no. 3, pp. 1387-1401, Aug. 2004.

3

Page 4: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

RTU RTU RTU

SUB LDC SUB LDC SUB LDC

SLDC SLDC SLDC

ERLDC WRLDC NRLDC SRLDC NERLDC

NLDC

SCADA EMS System+

(Typical Architecture in India)

+ Wide area monitoring system since 1960s

SC Srivastava / IITK WAMCS QIP course 10 May 2019 4

Page 5: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Components of SCADA EMS

• Remote Terminal Units – Intelligent units to collect data from field,convert these to suitable form ( through A/D or D/A converters,Transducers etc.), communicate the data to Control Center.

• Communication Networks or Data Transmission Networks –PLCC, Microwave Telemetry Link, Dialup Network, Fiber Optics etc.

• Computer Systems & Man Machine Interface- at Control Center

• Software:

1. Operating system software for Data base management & MMI

2. Communication Software

3. Application Software (to perform advance functions of EMS)

Problems with SCADA based WAMS:• Data time skewed. Data scan rate upto 10 sec.

• Only magnitude measurements and phasors through stateestimation-time extensive.

5SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 6: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Advance Functions of Energy Management System

• Supervisory Control & Data Acquisition (SCADA) functions

• System Monitoring and Alarm Functions

• State Estimation

• On line Load Flow

• Economic Load Dispatch

• Optimal Power Flow ( including Optimal Reactive Power Dispatch)

• Security Monitoring and Control

• Automatic Generation Control

• Unit Commitment

• Load Forecasting

• Log Report Generation ( Periodic & Event logs), etc.

A program scheduler may invoke various Application programs at fixed intervals. 6

Page 7: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

PHASOR DATA CONCENTRATOR

APPLICATIONSOFTWARE

SYSTEM CONTROL CENTER

MONITORINGCONTROLDATABASE

PMU

GPS

PMU

PMU PMU

PDC

PDC SUPER PDC

A Typical Synchrophasor based WAMCS Architecture

7

Recommended PMU reporting rates (frames/sec): as per IEEE std. 37.118

System frequency 50 Hz : 10 25 50System frequency 60 Hz : 10 12 15 20 30 60

(New standard also encourages fps of 100, 120 or less than 10, if required for a specific application)

Page 8: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Event Millions of

people

affected

Location Date

July 2012 India blackout 620 India 30–31 July 2012

2014 Bangladesh blackout 150 Bangladesh 1 Nov 2014

2005 Java-Bali blackout 100 Indonesia 18 Aug 2005

1999 Southern Brazil blackout 97 Brazil 11 March 1999

2009 Brazil and Paraguay

blackout

87 Brazil, Paraguay 10–11 Nov 2009

Northeast blackout of 2003 55 United States,

Canada

14–15 Aug 2003

2003 Italy blackout 55 Italy, Switzerland,

Austria, Slovenia,

Croatia

28 Sep 2003

Northeast blackout of 1965 30 United States,

Canada

9 Nov 1965

Few Major Black-out Events across the World(Ref. http://en.wikipedia.org/wiki/List_of_power_outages)

SC Srivastava / IITK WAMCS QIP course 10 May 2019 8

Page 9: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

SC Srivastava / IITK WAMCS QIP course 10 May 2019 9

RTO/ISO in USA

August 14, 2003 North-East Blackout in US, Canada

Page 10: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

10

Reliability Coordinators in Midwest

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 11: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

2003 US Blackout: Few Eventshttps://en.wikipedia.org/wiki/Northeast_blackout_of_2003

12:15 p.m. Incorrect telemetry data renders inoperative the state estimator, operated by the Indiana-based MISO. An operator corrects the telemetry problem but forgets to restart the monitoring tool.

2:02 p.m. The first of several 345 kV overhead transmission lines in northeast Ohio fails due to contact with a tree in Walton Hills, Ohio

2:14 p.m. An alarm system fails at FirstEnergy's control room, not repaired.

3:05 p.m. A 345 kV transmission line known as the Chamberlin-Harding line sags into a tree and trips in Parma, south of Cleveland.

3:32 p.m. Power shifted onto another 345 kV line, the Hanna-Juniper interconnection, causes it to sag into a tree, bringing it offline as well. While MISO and FirstEnergy controllers concentrate on understanding the failures, they fail to inform system controllers in nearby states.

3:39 p.m. A FirstEnergy 138 kV line trips in northern Ohio.

4:05:57 p.m. The Sammis-Star 345 kV line trips due to undervoltage and overcurrent interpreted as a short circuit. Later analysis suggests that the blackout could have been averted prior to this failure by cutting 1.5 GW of load in the Cleveland–Akron area.

SC Srivastava / IITK WAMCS QIP course 10 May 2019 11

Page 12: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

4:09:02 p.m. Voltage sags deeply as Ohio draws 2 GW of power from Michigan.

4:10:34 p.m. Many transmission lines trip out, first in Michigan and then in Ohio, blocking the eastward flow of power around the south shore through Erie, Pennsylvania and into the Buffalo, New York area.

4:10:38 p.m. Cleveland separates from the Pennsylvania grid after a series of line and generator trip.

4:10:40 p.m. Flow flips to 2 GW eastward from Michigan through Ontario (a net reversal of 5.7 GW of power), then reverses back westward again within a half second.

4:10:43 p.m. International connections between the United States and Canada start to fail.

4:10:45 p.m. Northwestern Ontario separates from the east The first Ontario power plants go offline

4:10:46 p.m. New York separates from the New England grid.

4:10:50 p.m. Ontario separates from the western New York grid, cascaded separation and tripping happens.

4:13 p.m. End of cascading failure. 256 power plants are off-line, 85% of which went offline after the grid separations occurred, most due to the action of automatic protective controls. 12

Page 13: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

13

Blackout Root Cause : FE Situational Awareness & Vegetation Management

FE did not ensure a reliable system after contingencies occurred because it did not have an effective contingency analysis capability

FE did not have effective procedures to ensure operators were aware of the status of critical monitoring tools

FE did not have effective procedures to test monitoring tools after repairs

FE did not have additional high level monitoring tools after alarm system failed

FE did not adequately manage tree growth in its transmission rights of way

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 14: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

14

Blackout Cause: Reliability Coordinator Diagnostics

MISO’s state estimator failed due to a data error.

MISO’s flowgate monitoring tool didn’t have real-time line information to detect growing overloads

MISO operators couldn’t easily link breaker status to line status to understand changing conditions.

PJM and MISO ineffective procedures and wide grid visibility to coordinate problems affecting their common boundaries

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 15: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Grid Disturbances in Indiaon 30th & 31st July 2012

Enquiry Committee report posted at

http://www.cercind.gov.in/2012/orders/

Final_Report_Grid_Disturbance.pdf

Loss of load: 36000 and 48000 MW

SC Srivastava / IITK WAMCS QIP course 10 May 2019 15

Page 16: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

NRNER

ER

SR

WR

Schd : 2220 MW

Actual : 2044 MW

Schd : 832 MW

Actual : 975 MW

Schd : 1192 MW

Actual : 3123 MW

Schd : 835 MW

Actual : 962 MW

Schd : -33 MW

Actual : 95 MW

Schd: 278 MW

Actual : 2654 MW

Antecedent Conditions on 30th July 2012

Time 02:30 Hrs

592 MW

Mh’garh

Mundra

FrequencyNEW Grid- 49.68 Hz

Over-drawal : 1755 MW

Under-drawal: 2343 MW

Over-drawal : 446 MW

SCADA

Snapshot

16

Loss of load: 36000 MW and 48000 MW

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 17: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

NR NER

ER

Inter-regional lines under outage on 30th July 2012Z

erd

aB

hin

ma

l

Ka

nkro

li

Gw

alio

r

Au

raiy

aM

ah

alg

ao

nM

ala

np

ur

Sipat Ranch

iRourkela

Sterlite

Raigarh

RaigarhBudhipadar

Korba

Sala

kat

iB

irpara

Bin

aguri

Bongoig

aonGorakhpur

BaliaFa

teh

pu

r

Gaya

Agra

Ko

taB

adod

Mo

rak

To SRHVDC

BhadrawatiHVDC

Talcher Kolar

HVDC

Gazuwaka

HV

DC

Vin

dh

.

WR

17SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 18: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Center of angular Separation on 30th July 2012

18SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 19: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

PMU plots on 30th July 2012. The trippings at ~2:33:15 due to large angular separation – correlates with DRs and WAFMS

19

Balia-Biharsharif

Balia-Patna

Grkpr-Muzzpr.

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 20: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

NRNER

ER

SR

WR

Schd : 740 MW

Actual : 1978 MW

Schd : 830 MW

Actual : 830 MW

Schd : 850 MW

Actual : 2044 MW

Schd : 894 MW

Actual : 900 MW

Schedule: -21 MW

Actual : 150 MW

Schd : 73 MW

Actual : 1822 MW

Antecedent Conditions on 31st July 2012

Frequency NEW Grid-49.84 Hz

Time 12:57 Hrs

432 MW

Mh’garh

Mundra

Over-drawal : 2432 MW

Under-drawal: 2987 MW

Over-drawal : 720 MW

SCADA

Snapshot

20SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 21: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

NR NER

ER

Inter-regional lines under outage on 31st July 2012

Ze

rda

Bh

inm

al

Ka

nkro

li

Gw

alio

r

Au

raiy

aM

ah

alg

ao

n

Ma

lan

pu

r

Sipat Ranch

iRourkela

Sterlite

Raigarh

RaigarhBudhipadar

Korba

Sala

kat

iB

irpara

Bin

aguri

Bongoig

aonGorakhpur

BaliaFa

teh

pu

r

Gaya

Agra

Ko

taB

adod

Mo

rak

To SRHVDC

Bhadrawati

HVDC

Talcher Kolar

HVDC

Gazuwaka

HV

DC

Vin

dh

.

WR

21SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 22: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Separation on 31st July 2012

22SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 23: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

PMU Plots

23

Jabalpur, Bhadrawati, Raipur

Gwal-Bina

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 24: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Important Observations

Few Major Causes of the Grid Disturbances:

• Lack of Situational Awareness and real time monitoring tools

• Early security assessment/warning system.

• Unintended operation of Protection/ Improper coordination of Control Actions

• Lack of enough reactive compensation

• Human error & Grid Indiscipline

Few Remedial Measures:

• Wide area monitoring & control. PGCIL-URTDMS Project (http://www.cea.nic.in/reports/powersystems/sppa/scm/allindia/agenda_note/1st.pdf )

• Ensuring activation of all emergency controls and protection

• Smart grid - Proper automation, information flow and data management.

• Regulatory changes to strengthen system security and operation.

24SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 25: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

➢Pilot projects in all regions already in place.

➢ Integrate the pilot project PMUs with the National plan.

➢Unified Real Time Dynamic Measurement System(URTDMS) being implemented.

➢About 1700 PMUs are planned, to be placed at all the400 kV and above voltage buses and major generatingplant buses. Analytics being developed by IIT Bombay.

➢Few analytics to be implemented in the first phase

include; Line parameter estimation, Oscillation

monitoring, Distance relays’ vulnerability analysis,

Linear/dynamic state estimation, CT/CVT calibration,

Supervision of zone-3 distance protection.

25SC Srivastava / IITK WAMCS QIP course 10 May 2019

Roadmap of WAMCPS Deployment in India

Page 26: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Some Research Work on Synchrophasor based WAMCPS carried out at IIT Kanpur

• Phasor Assisted State Estimation

• Dynamic Phasor Estimation

• Machine Rotor Angle Estimation for Transient Stability

• Critical Mode Identification for Small Signal Stability

• Synchrophasor based Voltage Stability Assessment

• Wide Area Measurement based Adaptive Distance Protection

• Network based Wide Area Damping Control

• Optimal Frequency and Voltage stability based load shedding

• Load, Transmission Line and Generator Model Parameter

Estimation.

• On Line Tuning of Power system Stabilizers

• Testing in WAMS Lab using RTDS

26SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 27: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

*P. Tripathy, S. C. Srivastava, and S. N. Singh, “A Modified TLS-ESPRIT-Based Method for Low-Frequency Mode Identification in Power Systems Utilizing

Synchrophasor Measurements", IEEE Transactions on Power Systems, vol. 26, no. 2, May 2011, pp. 719-727.

Modified TLS-ESPRIT+ based Low Frequency Mode Identification*

27SC Srivastava / IITK WAMCS QIP course 10 May 2019

+ Total Least Squares Estimation of

Signal Parameters via Rotational

Invariance Technique (TLS-ESPIRIT)

Page 28: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Test signals corresponding to inter-Area modes

The test signal, considered for simulations had a small signal

oscillation* of 0.4 Hz, having attenuation factor -0.07, amplitude

set to unity with an initial phase of 60 degree.

Two area test system assuming the availability of power signals

from PMUs (Ref: Kundur’s book)

Probing test data of the Western Electricity Coordination Council

(WECC) system (obtained from BPA site)

PMU data obtained on Northern Grid system (source: POSOCO)

Test Cases

28SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 29: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Test Signal corresponding to Inter- Area Oscillations with SNR 30 dB

29

Page 30: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Test Signal corresponding to Inter- Area Oscillations with SNR 30 dB

30SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 31: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Improved Voltage Instability Monitoring Index (IVIMI) :

VDR – Voltage Deviation from its Reference

CVD – Consecutive Voltage Deviation (Rate of

Voltage Deviation)

• is system wide voltage instability index at instant-i.

• Based on voltage deviation and rate of voltage change.

• Rate of change of voltage reflects the dynamic variation.

max

2

max

1CVD

)(VDR

)(IVIMI ii

i

CVDiw

VDRiw +=

setbusesloadtheallpIVIMIISVIMI p

ii= )max(

Improved Voltage Instability Monitoring Index*

* Sodhi, R., Srivastava, S.C., Singh, S.N., "A Simple Scheme for Wide Area Detection of Impending Voltage Instability," IEEE

Trans. on Smart Grid, vol.3, no.2, pp.818-827, June 2012.

*Ch. V. V. S. Bhaskara Reddy, S. C. Srivastava and Saikat Chakrabarti, “An improved Static Voltage Stability Index using

Synchrophasor Measurements for Early Detection of Impending Voltage Instability,” National Power Systems

Conference (NPSC), IIT (BHU), Varanasi, India, December 12‐14, 2012.

iISVIMI

Page 32: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Voltage Stability Risk Index (VSRI)#

1. Calculate the Moving Average

2. Calculate the % diversity of the ith measurement

3. Calculate the Risk Index

where, Vi= voltage measurement at ith interval

Vj=moving average of jth window,

N=length of the moving window,

dj=diversity of th ith measurement for the jth window

Zj = VSRI of the jth window.

=

=N

iij

vN

v1

1

100−

=j

ji

iv

vvd

+=

=

2

)(11

)1(

N

iii

j

tdd

Nz

# Kim, et al., “System an method for calculating real-time voltage stability risk index in power system using

time series data,” Patent No. US007236898B2, Dt. Jun. 26,2007.

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 33: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

0 50 100 150 200 250 300

0.7

0.8

0.9

1

1.1

1.2

TIME in sec.

VO

LT

AG

E in P

U

156

158

174

Fig: Critical bus voltages for load increase.

i. Slow increase of load

Simulation Results

NRPG 246 bus Indian test system

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 34: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

0 50 100 150 200 250 300-1

-0.5

0

0.5

VS

RI

Time in Sec.

156

158

174

Fig.: VSRI plot for

load increase.

0 50 100 150 200 250 300-3

-2

-1

0

1

2

3

4

TIME in sec.

VIM

I

156

158

174

Fig: IVIMI plot for

load increase.

(195 s early prediction)

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 35: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

0 50 100 150 200 250 300

0.65

0.7

0.75

0.8

0.85

0.9

0.95

1

TIME in sec.

VO

LT

AG

E in P

U

156

158

174

ii. A line outage and simultaneous load increase

Fig: Critical bus voltages

for line outage

SC Srivastava / IITK WAMCS QIP course 10 May 2019

0 50 100 150 200 250 3000

0.2

0.4

0.6

0.8

1

1.2

1.4

1.6

TIME in sec.

VIM

I

156

158

174

Fig: IVIMI plot for

load increase.

(170 s early prediction)

Page 36: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

➢ Power system events that cause the impedance

trajectories to enter into tripping zones, under no-

fault situations, cause system security concerns.

Resistance

Re

acta

nc

e

36

Distance Relay Protection

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 37: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Unintended Operation of Distance Relays➢ Due to impedance trajectory encroachment into

relay tripping zone.

➢ System events which, sometimes, lead to distance

relay operation

➢ Dynamic

• Power Swings - Blinders and Timer blocking

scheme

• Voltage Instability

➢ Static

• Load encroachment

➢ Operation under Zone-3 has been observed to result in

cascading failures of power systems.37SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 38: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

A Method* using SVM to avoid Unintended

Operation of Distance Relays

➢ Relay Ranking Index

▪Ratio of normalized apparent impedance of the relay to

branch loss sensitivity used to rank the relays in terms of its

vulnerability to Power Swings and Voltage Instability.

➢Fault and Disturbance Classifiers

▪Two support vector machines used, SVM-1 for

distinguishing between fault and no fault condition, and

SVM-2 for classifying the no fault disturbance in ‘Voltage

Instability’ or ‘Power Swing.

38

*Seethalekshmi K., S.N. Singh and S.C. Srivastava, “A Classification Approach Using Support Vector

Machines to Prevent Distance Relay Mal-operation under Power Swing and Voltage Instability”, IEEE

Transactions on Power Delivery, Vol. 27, No. 3, July 2012, pp. 1124-1133.

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 39: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Critical Relays’ Identification➢ Normalized Apparent Impedance for a relay, Rij in line i-j

where, and are the sending and receiving end voltages of the line i-j and is the impedance corresponding to third zone setting of the relay. is the impedance of the line.

➢ Branch loss sensitivity:

where,

➢ Relay Ranking Index

( )3

ij

iliner

i j

r ij

VZ Z

V V

Z

= −

3r ijZiV jV

lineZ

39

= + −loss loss

h P jQ in line i j

2 22 2

j ji iVV

ij ij ij ij ijS S S S S

= + + +

ij

ij

ij

ZrRRI

S=

,

=

iV

ij

i

hS

V,

=

i

ij

i

hS and

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 40: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Proposed Classification StrategyRelay impedance measurement unit

1= Trip

0= Block

1= Relay pick-up

0= ResetV

1= Enable SVM-2

0= Disable SVM-2

1= Power swing

-1= Voltage instability

Digital distance relay block

for sampling & DFT based

phasor calculation

Feature vectorSVM-1

(Fault

classifier)

SVM-2

(Disturbance classifier)Feature vector

Inputs , , ,s s s lossV I P Q

s sInputs , , , ,s s sV I P Q

i

➢SVM-1 classifier

Label ‘0’ for fault condition

Label ‘1’ for other situations

SC Srivastava / IITK WAMCS QIP course 10 May 2019 40

Page 41: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Bus 7Bus 2 Bus 8 Bus 9 Bus 3

Bus 5 Bus 6

Bus 4

Bus 1

Simulation StudiesWSCC 9-bus System

41SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 42: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Relay No. Normalized Apparent

Impedance

Branch Loss

Sensitivity

Relay Ranking

Index

Relay Ranking

R5-7 0.0994 2.5031 0.0339 1

R7-5 0.1025 2.4308 0.0360 2

R6-9 0.1201 1.6859 0.0608 3

R9-6 0.1226 1.6534 0.0632 4

R8-7 0.5456 2.1443 0.2171 5

R7-8 0.5513 2.1232 0.2215 6

R5-4 0.5643 1.4612 0.3294 7

R4-5 0.5804 1.4376 0.3444 8

R8-9 0.7929 0.7515 0.9001 9

R9-8 0.8056 0.7440 0.9237 10

R6-4 0.9881 0.8614 0.9786 11

R4-6 1.0000 0.8531 1.0000 12

Step-1: Identification of Critical Relays

42SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 43: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Rf=0.01

Bus 8 Bus 9Bus 7Bus 2 Bus 3

Bus 5 Bus 6

Bus 4

Bus 1

tclg=0.3 sec

Simulation of Power Swing Scenario

SC Srivastava / IITK WAMCS QIP course 10 May 2019 43

Page 44: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

5 6 7-200

-100

0

100

200

300

Time (s)

Vo

lta

ge

(p.u

.)

4.5 5 5.5 6 6.5-200

-100

0

100

200

Time (s)

Vo

lta

ge (

p.u

.)

4.5 5 5.5 6 6.5 7

0

0.2

0.4

0.6

0.8

1

Time (s)

Pred

icte

d l

ab

el

(SV

M-1

)

Classification by SVM-1

Fast Swing Slow Swing

4.5 5 5.5 6 6.5

0

0.2

0.4

0.6

0.8

1

Time (s)

Pred

icte

d l

ab

el

(SV

M-1

)

Classification label by SVM-1 Classification label by SVM-1

44SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 45: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Performance of SVM-1 (Fault Classifier)

2 4 6 8 10 12 14 16 1840

60

80

100

120

140

Time (s)

Volt

age a

t th

e r

ela

y l

ocati

on (

bus-

7)

2 4 6 8 10 12 14 16 18

0

0.2

0.4

0.6

0.8

1

Time (s)

Pre

dic

ted

lab

el

(SV

M-1

)

Voltage unstable case Classifier output

SVM-1 Comparison with ANFIS* Scheme

Scheme Classification accuracy (%) Testing accuracy (%)

ANFIS based classifier 80.02 75.83

SVM based proposed classifier 98.85 96.18

* H. K. Zadeh and Z. Li, “A novel power swing blocking scheme using adaptive neuro-fuzzy inference system, “Electric

Power Systems Research, vol. 78, pp 1138-1146, 2008.

Accuracy of SVM-2 classifier in WSCC 9-bus system

Cases Training accuracy

(%)

Testing accuracy (%)

32 100 96.71

45

Page 46: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Proposed Methodology:

• Logarithm of the singular values of the Hankel matrix formed from

the Measurement data used for model order estimation.

• Second order Taylor series extended TLS-ESPRIT used for accurate

dynamic phasor estimation*.

• Taylor’s second order approximation used to estimate first and

second derivatives of the phasor amplitude and phase derivatives.

• Deviation in the derivative values used to distinguish between fault

and no fault conditions**.

* P. Banerjee and S. C. Srivastava, “An Effective Dynamic Current Phasor Estimator for SynchrophasorMeasurements,” IEEE Transactions on Instrumentation and Measurements, vol.64, no.3, Mar. 2015, pp. 625-637.

** Paramarshi Banerjee, Improved Estimation of Dynamic Phasors, and their Applications in Distance Protection &Stability Assessment, Ph.D. Thesis, IIT Kanpur, January 2015.

Avoiding Relay Unintended Operation

Using Phasor Derivatives

46SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 47: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Proposed Approach for Relay Blocking

• The predicted and the accurate phasor at the present time

• The vector deviation of the predicted phasor as a percentage

of the amplitude at the fifth previous data window is given by

• Corresponding values for the voltage and the current phasors

are denoted as 𝐸_𝑉 and 𝐸_𝐼, respectively.

• The Relay Blocking (RB) signal is high and releases the relay

for operation when 𝐸_𝑉 and 𝐸_𝐼 are simultaneously greater

than 15% (experimentally established).

2 2

(0), 5

ˆ ˆ(Re( Re( ) (Im( Im( )%

) ) ) )100k k k k

b k

P PE

P P

X −

− + −=

(0) (0), ,

ˆ(0) (0), ,

ˆ ˆ , b k b kj jk kb k b kP X e P X e = =

SC Srivastava / IITK WAMCS QIP course 10 May 2019 47

Page 48: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

▪ The proposed algorithm for generating RB signal should remain low for power swings and voltage instability but high for faults .

▪ The test cases considered in WSCC 9 bus system are

• A:Unstable swing;

• B:Fault during unstable swing;

• C:Fault during stable swing;

• D:Voltage Instability;

• E:Fault during voltage instability;

▪ The test cases considered in NE-39 bus system are

• F:Unstable swing;

• G:2 cases of fault during unstable swing;

• H:Stable swing;

• I:Fault during stable swing;

• J:Voltage Instability;

• K:Fault during voltage instability;

Performance Evaluation

SC Srivastava / IITK WAMCS QIP course 10 May 2019 48

Page 49: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Case B: Fault during unstable swing in WSCC 9 bus system

Voltage and current at bus 8 in WSCC 9 bus system for fault during unstable power swing.

RB at bus 8 in WSCC 9 bus system for fault during unstable power swing.

SC Srivastava / IITK WAMCS QIP course 10 May 2019 49

Page 50: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Case D: Voltage Instability in WSCC 9 bus system

Voltage at bus 7 in WSCC 9 bus system for fault during voltage instability.

RB at bus 7 in WSCC 9 bus system during voltage instability

SC Srivastava / IITK WAMCS QIP course 10 May 2019 50

Page 51: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Local Stabilizing Control: Power System Stabilizers

Turbine

Vt

Gen

Governor

Exciter

Voltage

Regulator

PSS

Transmission Line

(Power System Network)

Output

KPSS 1

w

w

sT

sT+

T(s)

Input

PSS

Gain Washout Lead-Lag Compensator

Limiter

51

▪ It provides damping to the

oscillations in the range of

0.2Hz-3 Hz, by modulating

generator field excitation.

▪ The input signal can be rotor

speed or frequency or line

power flow power deviation.

Major Problems

▪ Robustness towards multiple

operating conditions and

topology-needs retuning.

▪ Lack of global observation.

▪ Coordination of multiple

controllers

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 52: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

52

➢ A two-loop framework of a wide-area stability control system.

➢ The Wide-Area Damping Controller (WADC) in the higher level receives remote

signals, from few pre-selected PMUs located in a wide-

geographical area in the network & provides additional supplementary damping

signals, to some of the pre-decided generators/FACTS devices

POWER SYSTEM

G-1

G-2

G-N

PMU-1

PMU-2

PMU-K

AVR-1

AVR-2

AVR-N

CPSS-1

CPSS-2

CPSS-N

2Δω

NΔω

+

+

+

+

+

+

delay

delay

delay

N_caτ

2_caτ

1_caτ

WADC

delay

delay

delay

1_scτ

2_scτ

K_scτ

1VS

2VS

NVS

KY

2Y

1Y

1Δω

Exciter

Exciter

Exciter

1 2 KY Y Y

1 2 NVS VS VS

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Centralized Wide Area Damping Controller

Page 53: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Some of the major issues:

❑ The choice of the control I/O signals

❑ Control law or algorithm

❑ Latency in communication network

❑ Packet Loss

❑ Packet Disorder

❑ Channel Bandwidth

❑ Communication Failure

53

Issues with Wide-Area Damping Controller

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 54: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Wide-Area TS Fuzzy Output Feedback Controller with

Input/Output Signal Selection

54

➢ Coherency based approach* for input/output signal selection

• Data transformed into orthogonal space to make correlated variables

uncorrelated by applying Principal Component Analysis (PCA).

• Self-Organizing Map (SOM) for final data clustering. For clustering data,

few critical line contingencies were considered.

➢ Producing better damping effect to the critical inter-area modes of

oscillations. TS-Fuzzy Controller (WATSF) was applied**. Results

compared with existing H2/H∞ Controller (called as WARDC)+.

* B.P. Padhy, S.C. Srivastava, and N.K. Verma, "A Coherency-Based Approach for Signal Selection for Wide Area Stabilizing

Control in Power Systems", IEEE Syst. Journal, vol.7, no.4, pp.807-816, Dec. 2013.

**B.P. Padhy, S. C. Srivastava, and N. K. Verma, “Robust Wide-Area TS Fuzzy Output Feedback Controller for Enhancement of

Stability in Multimachine Power System”, IEEE Systems Journal, vol.6, no.3, pp.426,435, Sept. 2012.

+ Y. Zhang and A. Bose, "Design of Wide-Area Damping Controllers for Inter area Oscillations," IEEE Transactions on Power

Systems, vol. 23, no. 3, pp. 1136-1143, Nov. 2008.

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 55: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Implementation of the proposed method

Line Outage Contingency

Index Value

1.2463

1.2073

1.1953

0.3666

0.1280

55

Line Outage Contingency

Index Value

0.096

0.064

0.058

0.039

0.0374

28 29L

1 39L−

1 2L−

2 25L−

16 21L

1 2L−

8 9L−

2 25L−

21 22L

16 21L

Dynamic Contingency Index (39-bus system)

Dynamic Contingency Index (68-bus system)

Dynamic contingency

index is defined

ξ -ξI Jsys sysDCI =

J ξIsys

Page 56: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

2600 2800 3000 3200

0.9985

0.999

0.9995

1

1.0005

1.001

1.0015

1.002

Samples

Gen

-Spe

ed in

P.U

.

G1

G2

G3

G4

G5

G6

G7

G8

G9

G10

G11

G12

G13

G14

G15

G16

Gen Speed of 68-bus system for line L1-2 outage –Data used

as input to the signal selection algorithm

56SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 57: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

39

-bu

s N

ew E

ngl

and

Sy

stem

Type. Pole vector approach

Geometric approach

Proposed approach

Generators G1, G5, G7, G9 G3, G7, G8, G9 G3, G5, G9, G10

Power Flow

In Lines

L(8-9), L(1-2), L(2-3), L(14-15),

L(3-18)

L(9-39), L(16-17), L(2-3), L(2-25),

L(4-5)

L(17-27), L(16-19), L(9-39),

L(2-25), L(8-9)

68

-bu

s N

ew

Engl

and

New

Yo

rk S

yste

m

Generators G11, G12, G13, G14, G15, G16

G3, G9, G10, G13, G14, G16

G1, G3, G5, G9, G13, G15

Power Flow

In Lines

L(36-37), L(50-52), L(40-41),

L(34-36), L(1-30), L(9-36)

L(1-2), L(42-52), L(1-47), L(33-38), L(26-27), L(9-30)

L(36-37), L(1-2), L(9-30),

L(50-52), L(9-36), L(4-5)

Signal Selection for 39-Bus and 68-Bus Systems

57SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 58: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

GG15

67

42

52

49

G

G14

G

G16

41

66

68

46

38

33

51

50

45

39

44

35

34

G

G12

64

36

43

37

G

G13

65

40

31

G

G10

62

48 47

1

30

32

G

G11

63

9

8

G

G2

7 5

6

54

4

3

2

G

G1

53

25

G

G8

G

G9

292826

18 17

27 24

21

16

61

G

G3

10

55

11

12

13

14

15 19

G

G5

G

G4

20

57

56

G

G6

58

G

G7

59

23

22

60

WADC

New England and New York Interconnected 68-bus system showing

selected input and output signals with the proposed method58

Page 59: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Comparative Results (68-bus system)

59

30 32 34 36 38 40 42

-2

0

2

x 10-3

Time (sec)

Sp

ee

d D

iv W

7 (

pu

)

3-phase fault

With only PSS

With poledir

With geometric

With proposed WARDC

With proposed WATSF

50 52 54 56 58 60 62 64 66 68 70-100

0

100

200

Time (sec)

P

9_39(M

W)

Load outage

With only PSS

With poledir

With geometric

With proposed WARDC

With proposed WATSF

Speed deviation of Gen 7 and power deviation in line 9-39 due to

3-Φ fault and load outage (68-bus system)

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 60: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Network Delay & Packet drop Compensation*➢ A New Time Delay Compensation (TDC) technique with packet

drop has been proposed.

➢ The network latency considered in the application of

synchrophasor assisted wide area control for the Static Var

Compensator (SVC).

➢ The power oscillation modes are estimated online by Modified

Extended Kalman Filter (MEKF) approach.

➢ Delay has been compensated by predicting the dynamics of the

delayed measurement signal.

➢ The performance of the proposed delay compensation scheme has

been tested on 39-bus and 68- bus systems.

➢An insertion sort algorithm has been used for chronological

sequence restoration of the data in case of packet disorder.

* Bibhu P. Padhy, S.C. Srivastava and Nishchal K. Verma, “A Network Delay Compensation Technique for Wide-Area SVC

Damping Controller in Power System,” IEEE PES Transmission & Distribution Conference & Exposition, Chicago, USA,

April 14-17, 2014. 60

Page 61: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Proposed Network Architecture

61

Power

System

m1(KT)

1 1m (KT - τ )

2 2m (KT - τ )

n nm (KT - τ )

2Buffer

1Sensor1

S (t)

nBuffer

1Buffer

nEKFnDelay Compensator

WADC

Satellite

GPS

Clock

rr rr

Other

PMUs

• • •

•••

•••

••

•M

U

X

BN

2EKF2Delay Compensator

1EKF1Delay Compensator

1PMU

1PDC

m2(KT)

2Sensor

2S (t)

2PMU

2PDC

mn(KT)

nSensorn

S (t)n

PMUn

PDC

rr rr• • •

rr rr• • •

Co

mm

un

ica

tio

n

Ne

two

rk•••

•••

•••

•••

Satellite

GPS Clock

nNPDC

2NPDC

1NPDC

Logic To

Calculate Time

Delay

dnΤ

d2T

d1T

Time Stamp of

Incoming Data Packets Control Center

Remote

Location

1y

2y

ny

1mode

2mode

nmode

1Sdc

2Sdc

nSdc

sV

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 62: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Time Delay Compensation (TDC) Scheme

62

Incoming

Data

GPS Clock

Buffer

TOP

MEKF

Extract the Time

Stamp Time

stampT

GPST

dT

WADC

Power

System

Network Buffer

k k k kφ ,ω ,λ ,ζk k d

dc s

(λ -ζ T )

k k d

S (kT ) =

e sin(φ -ω T )

TDC

dc sS (kT )

sV

••• •••jy ky

3y 1y

Logic to Calculate

Time Delay

The delay compensated signal can be represented as

,3,

, ,1,

1

.sin( )i k T Td s

d s d s

Nx

dc k k T T i k T T

i

S y e x+

+ +

=

= = , ,4, ,4,(ln )

,2, , ,2,

1

.sin( )i k i k d i k

NA x T x

i k i k d i k

i

e x T x− −

=

= + +

, ,( )

, ,

1

.sin( )i k d i k

NT

i k d i k

i

e T

=

= +

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 63: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

39 Bus Test System The input/output signal selection using the coherency approach.

The remote input signals to the WADC are , and

63

G

G

G

G8

G1037

30 25

18

G139

G

31 11

12

17

26

27

10

32

G

16

13

14

15

G2

G3

28

G G9

29

G G5

34

20

19

G G4

33

24

21 22

G

G G7

36

23

G6

35

38

WADC

PMU 1

PMU 2

7

8

9

6

4

3

5

2

1

1( )tt 2 ( )tt

TSC TCR

SVC

Input 1 Input 2

Input 3

Output

PMU 3

16-19P 1-39

P26-27

P

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 64: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Implementation Results

A random input delay of maximum value 1sec has been created in

the input channel-1( ) , 400 ms in the input channel-2( ),

and zero delay created in channel-3( ) as this is a local signal

Packet drop probability is considered as 4%

Test Cases:

A 3-phase fault was applied at bus-16 and bus-26 for 70ms.

A load outage at bus-16 and 28

3-phase fault at bus- 4 followed by outage

Bus connecting 21-22 line contingency

64

1-39P

16-19P

26-27P

4-14L

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 65: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Simulation Results

9 11 13 15 17 19 21 23 25 27 29 31 33 35

-4

-2

0

2

4

x 10-3

Time(Seconds) (A)

W4-W

1 (

P.U

.)

9 11 13 15 17 19 21 23 25 27 29 31 33 35-5

0

5

x 10-3

Time(Seconds) (B)

W4-W

1 (

P.U

.)

Without WADC With Phasor Approach

Without WADC With Phasor Approach

10 15 20 25 30 350

0.5

1

Time(Seconds) (A)

(1-

)

10 15 20 25 30 350.38

0.4

Time(Seconds) (B)

Pac

ket

Del

ay(S

ec)

10 15 20 25 30 35-25

-15

-5

5

15

25

Time(Seconds) (C)

P

16

_1

9(p

.u.)

Delayed Signal PMU Output Predicted Signal

1 (A) Packet drop (B)

Random time delay (C)

Tracking of PMU signal

2. (A) 3-phase fault at

bus- 26 for 70ms (B) a 3-

phase fault at bus- 16 for

70ms

65

Page 66: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

66

MATLAB as

Server

IPDC as Client

PMUs

Omicron

Amplifiers

Desktop PC

with RSCAD

NI PCI 6704

DAQ Card

SEL PMU

Arbiter PMU

Router

Satellite

GPS clock

3-phase

voltage and

current

signal

Ethernet

Based LAN

Control

signal

RTDS

Hardware Lab Setup used for Real-Time

Simulation of WADC+

+ Addressing

• Optimal input/output

selection

• Robust Control

• Time delay compensation

• Packet drop and packet

disorder compensation

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 67: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

67

29 33 37 41 45 49 530.52

0.53

0.54

0.55

0.56

0.57

Time(Seconds)

Del

ay

Delay with time for a 3 phase fault at bus-27 (39 bus NE system)

29 33 37 41 45 49 53

-1

-0.5

0

0.5

1

Time(Seconds)

W9-

W1

(P.U

.)

No WADC

Only Simulation

HIL Simulation

Oscillations in the speed deviation of the generator

WADC Simulation and Validation on RTDS

SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 68: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Conclusions Synchrophasor based WAMCP system will form an

important component of Smart Grid. It offers new paradigmof real time security monitoring and control.

Large number of PMUs are being deployed in thetransmission grid at strategic locations in various countries.

The successful implementation of WAMPC requiresdevelopment of suitable application tools.

PMUs must be embedded with proper dynamic phasorestimation algorithm, complying with the IEEE standards.

It can be effectively utilized for better situational awarenessmonitoring impending system instability, and improvinginter-area mode damping, important to avoid majordisturbances.

68SC Srivastava / IITK WAMCS QIP course 10 May 2019

Page 69: S.C. Srivastava, Professor Departmentof Electrical ...iitk.ac.in/smartcity/qip/download/ppt/Day-3/01_Wide Area Monitoring … · General Introduction The size and complexity of the

Thank

You

69SC Srivastava / IITK WAMCS QIP course 10 May 2019