82

SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

  • Upload
    lamthu

  • View
    285

  • Download
    12

Embed Size (px)

Citation preview

Page 1: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,
Page 2: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

SCADA and Systems Monitoring

• SCADA stands for supervisory control and data

acquisition system.

• There are locations, in most of the power systems, where

operations, such as opening and closing circuit breakers,

must be done from time to time, but the cost of providing and

maintaining operator attendance cannot be justified.

• Sending an operator to such locations could results in delay in

some cases, as a result the outage may be lengthen and end up

in total failure in some cases.

Page 3: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

SCADA and Systems Monitoring

• Moreover, the cost of providing attendance at remote stations

or providing personnel to perform switching continues to rise.

• This makes operator attendance of remote stations even

more uneconomical.

• Devices to control equipment remotely have been used for

many years.

• The need for remote indication as well as control led to the

development of equipment that could perform operations,

monitor them, and report back.

Page 4: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

SCADA and Systems Monitoring

• At the same time it is often important to transmit such

information as loads and bus voltages to an operating

center, to make corrective action in case of a violation.

• Almost all modern dispatch and operating centers of power

systems are now provided with at least some SCADA

system equipment.

• These equipment have proven to be efficient and

economical for power system operations.

• It is a very effective aid for station operators, making it

possible for them to maintain relatively complete

knowledge of conditions on the portions of the system

Page 5: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

SCADA and Systems Monitoring

• The SCADA system allows a few operators to monitor the

generation and high-voltage transmission systems and to

take action to correct overloads or out-of –limits.

Page 6: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Control and Supervision

• The term supervisory control is normally applied to

remote operation of devices such as motors and circuit

breakers. • The term supervision means signaling back to indicate that

the intended operation has been carried out.

• Simple supervisory control systems have been used since

early days of utility operations.

• The supervision was provided by lights in early systems.

• Green light to indicate an open device and red to indicate

the contrary

Page 7: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Control and Supervision

• In such systems, wires between the control point and the controlled device being were required for each device

being controlled and supervised remotely. • When there are many such devices involved, the cost and

complexity of supervisory schemes increased directly with the number of devices to be controlled remotely.

• Moreover, when significant distances were involved, the associated costs were increasingly high and reliability suffered because of the induced electrical noise in the control circuit.

• The possibility of physical failure has also increased due to such long control circuit.

Page 8: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Control and Supervision

• Some of the shortcomings of direct-wire circuits between

the controlling and controlled equipment on a one-for-one

basis were minimized by use of the selective relays.

• By such means it was possible to select the device to be

controlled, operate it, and transmit a supervision signal

back to the control center over a single control circuit. • This type of systems became complex, and sometimes

difficult to maintain.

• They were also limited in speed of operation, and in

maximum data transfer when the number of controlled and

supervision devices became large.

Page 9: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Control and Supervision

• The arrival of electronic communication methods and

digital data transmission provide a means of greatly

increasing the capabilities of supervisory control. • Sequential scanning and supplied with remote supervisory

terminal units, made it possible for one master station to

control several remote stations and many devices at each

remote station.

• It was possible to telemeter the control actions taken by the

remote units as well as live analog data on current, voltage

and many other items needed for the complete supervision

of remote station.

Page 10: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Control and Supervision

• Reduction in data transferred between the remote units and

the master station was done by a procedure known as

exception reporting.

• This means certain data are transferred only when they

change or fall outside previously set limits.

• These developments made it possible for central location

equipped with a supervisory masters station to have almost

complete control, and information concerning the status of

stations under the control of a single master station.

Page 11: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Control and Supervision

• In most of the systems, the master unit sequentially scans

the remote terminal units (RTUs) by sending short

message.

• If it does, the RTU will send a message back to the master,

and the data received will be stored into the computer.

• If necessary, a control message will be sent to the RTU,

and an alarm or message will be printed on the master

typewriter and displayed on the cathode-ray-tube (CRT)

screen.

• The scan cycle of RTUs is 2s

Page 12: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Control and Supervision

• However, in the event of trouble at a remote

station, a message will be sent from remote

station to master unit .

• In some cases, the master units can

automatically perform predetermined

control action.

Page 13: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Control and Supervision

• All modern supervisory control systems are computer-

based; that is the master unit consists of a digital computer

with input and output equipment.

• The input and output equipment are used to send and

receive information from RTUs.

• The received information is displayed on CRTs and/or

printed on electric typewriters for permanent records.

• CRTs can also display graphic information, such as one-

line diagrams of the remote stations.

• In many control centers, overall system status is also

shown on wall diagrams, which are kept current with

existing conditions by data from the remote terminals.

Page 14: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Configuration of SCADA systems

• Basic elements in a SCADA system are a master

unit and RTUs.

• Links with MU and RTUs were made through

communication channels.

• A number of configurations can be used

depending on the requirement, availability of

communication channel, and cost.

Page 15: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Configuration of SCADA systems

(a) One-for-one SCADA system.

M R

Page 16: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Configuration of SCADA systems

(b) STAR or HUP SCADA system.

R R

R R

M

Page 17: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Configuration of SCADA systems

(c) Party-line SCADA system.

R

M

R R R

Page 18: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Configuration of SCADA systems

(c) Combination of STAR and Party-line SCADA system.

M

R

R

R

R

R

R

R

Page 19: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Configuration of SCADA systems

• Reliability of SCADA systems can also be

increased by providing alternative

communication channels.

– The overall reliability of a system can be no better

than that of the communications communication

channels are exposed to various hazards, they

usually the least reliable part of SCADA systems.

Page 20: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Supervisory Master Units

• Master unit of SCADA is the heart of the system

• All operator-initiated operations of an RTU are made

through the master unit and are reported back to the master

from the RTUs.

• Modern supervisory master units consist of a digital

computer and equipment to permit communications

between the master unit and RTUs.

• Such equipment includes modems to convert the digital

pulses used by computer to a form that can be transmitted

and received from and RTUs.

Page 21: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Supervisory Master Units

• In addition to the computer, peripheral necessary for the

proper operation of the system is provided. • (a) A control console

• (b) Keyboards or other means for the purpose of entering the data

• (c) CRTs or monitors

• (d) Printers

• In some cases, a simplified one-line diagram of the power

system is supplied in the form of a large wall map that

shows when stations are normal and abnormal conditions

exist.

Page 22: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Supervisory Master Units

• When an operation is performed from a

SCADA master unit, every effort is made to

ensure that the desired device is selected

and that the correct operation is chosen.

• The operator at the master station follows a

procedure called the “select before

operate” method.

Page 23: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Supervisory Master Units

• Select before operate method

o The operator selects the remote station.

o The remote station acknowledges that it has been

selected.

o The operator selects the device to be operated.

o The RTU acknowledges that the device has been

selected.

o The operator performs the operation.

o The RTU carry out the operation and signal back to

the master unit that it has been performed.

Page 24: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Supervisory Remote Units

• These are located at some selected stations.

• They are either wired to perform certain pre-selected functions, or in modern units, equipped with microcomputers which have memory and logic capabilities.

• RTUs with microcomputer called intelligent remotes

• Can perform some functions without the direction of

the master unit.

Page 25: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Supervisory Remote Units

• However, any operation performed reported back to

the master unit in the next scan.

• The RTUs can also drive a new element, the programmable controller (PC), a dedicated controller with memory and logic.

• The RTUs are also equipped with modems so that they accept messages from master and signal back to the master

• Relays located at the RTUs are used to open or close the selected control circuits to be controlled

equipment on command from master unit

Page 26: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Supervisory Remote Units

• Transducers in the remote units are used to convert

measurement such as voltage, current, watts, and

vars to direct current or voltage signals proportional

to the respective measured quantity.

• Then A/D converters are used to convert the

measured quantity into digital form.

Page 27: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Communication for SCADA Systems

• Communication is an essential part of SCADA

systems.

• The communication links can be wire circuits,

microwave channel, or power line carrier channels.

• Any communication circuit that provides an

adequate signal to noise ratio and has a bandwidth

capable of passing the data signals at the rate at

which they are transmitted can be used.

Page 28: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Communication for SCADA Systems

• Communication is an essential part of SCADA

systems.

• The communication links can be wire circuits,

microwave channel, or power line carrier channels.

• Any communication circuit that provides an

adequate signal to noise ratio and has a bandwidth

capable of passing the data signals at the rate at

which they are transmitted can be used.

Page 29: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Communication for SCADA Systems

• In most application, a normal telephone voice

channel of about 400 to 3400 Hz bandwidth is

satisfactory.

• For low speed data transmission, a narrow

bandwidth, usually located above the highest voice

frequency, can be used.

• In such cases, the voice band is restricted to about

400 to 2200 Hz, and the data are transmitted from

2200 to 3400 Hz.

Page 30: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Communication for SCADA Systems

• This type of operation is called “Speech-plus,” and it provides for both voice and data communication on a single voice channel, with a somewhat degraded voice channel.

• It should be stressed that communication is of primary importance for SCADA system.

• Poor communication results in errors or lost messages.

• A system cannot function properly without reliable

and adequate communication channels.

Page 31: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Energy Management Systems (EMS)

• For a power system to be able to supply to all its

customers within acceptable voltage and frequency

limits, it must be able to over come some

unavoidable disturbances.

• Some of these disturbances could be quite abnormal,

but nevertheless credible; such disturbances are: – Line outages following shunt faults

– Equipment failure and subsequent isolation

– Switch surges and lightning strikes

– Mechanical damages (due to wind, snow storm)

Page 32: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Energy Management Systems (EMS)

• Some of these disturbances can be dealt with the help of protective devices and the system restored back to normal stage within few cycles.

• Other disturbances may cause transient oscillations, which could last for several seconds, producing large oscillations in power flow.

• This results in abnormal voltage and frequency and subsequent tripping of plant items.

• For this purpose and other reasons an Energy Management System is vital for any power systems.

Page 33: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Energy Management Systems (EMS)

• An EMS enables engineers to operate and control the network in real time and includes facilities to capture the current state of the system and to instruct generating plants and other controllable system components such that all the customers are supplied, at least cost, with security.

• Considerable back-up facilities are necessary, including special software programs, display facilities, and support staff.

Page 34: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Energy Management Systems (EMS)

• Hierarchy of power system with EMS

Network and Substations

Level 3

Level 2

Level 1

Level 0

Central Coordinating Control

Area Control

Local Control

Page 35: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Energy Management Systems (EMS)

• At level 0 is the power system with isolators, switch-

gears, interconnections, transmission lines, cables,

transformers, etc are located;

• At level 1 substation (local) controls are located.

• The local controls at level 1 may include protection

relays, tap-change controllers, and compensator

controls, with operating channels to the level 0 units.

Page 36: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Energy Management Systems (EMS)

• Level 1 controls often comprise digital/electronic

devices for voltage and current measurement, inter

locking and facilities for receiving and sending data

to the next level up (area concentrators).

• In many cases, level 1 consists of racks of

electronics within RTUs.

• At level 2, man-machine interfacing and data

concentrators enable control and maintenance to be

exercised so that the whole system can be kept in

reliable and efficient condition.

Page 37: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Energy Management Systems (EMS)

• At the top level (3), the SCADA system resides,

usually in a single control center (variously called

Pool, National, or System control).

Page 38: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Energy Management Systems (EMS)

• The SCADA system accepts data from the various

level 1 collectors and displays it in a meaningful

way to the control engineers or operators, usually by

one-line mimic diagram on a Colour video screen as

seen in the previous section.

• The EMS processes SCADA data in various ways,

including topology identification by using the

dynamic data from switch-gear, isolators and other

system connectors.

Page 39: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Energy Management Systems (EMS)

• Some EMS functions are:

– State estimation

– Security analysis

– Voltage reduction

– Load shedding

– Load forecasting

Page 40: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Energy Management Systems (EMS)

• State estimation (Power System State Estimation -

PSSE)

• PSSE is a process in which data telemetered from

network measuring points to a central computer,

can be formed into a set of reliable data (the “data

base”) for control and recording purpose.

Page 41: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Flexible AC Transmission System

Alternating current

transmission systems

incorporating power

electronics-based and

other static controllers to

enhance controllability

and increase power

transfer capability

Page 42: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Simple illustration of the power transmission system Power system structure

Large Electric Power Systems

= PGenerator + PLoad + PCompensation = QGenerator + QLoad + QCompensation

Pi

Qi

S = P + jQ

Page 43: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Apparent Complex Power: S = P + jQ Real Power: Reactive Power:

sin

2

X

VP

22

* * sin( / 2) * (1 cos )V

Q V IX

V voltage X reactance phase angle I current

Page 44: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

FACTS devices = Flexible Alternating Current Transmission System devices

• Direct control of power flow over designated transmission routes

• Fast Control Technology to overcome limitations to Power Transfer Capability through rapid response

2

* sinV

PX

Page 45: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

What is FACTS? The FACTS technology is a collection of controllers, which

can be applied individually or in coordination with others to control one or more of the interrelated system parameters, such as series impedance, shunt impedance, current, voltage, and damping of oscillations.

Page 46: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

What limits the Loading Capability?

• Thermal For overhead line, thermal capability is a function of ambient temperature, wind conditions,

conditions of conductor, and ground clearance. The FACTS technology can help in making an effective used of newfound line capability.

• Dielectric Being designed very conservatively, most lines can increase operation voltage by 10% or even higher. FACTS technology could be used to ensure acceptable over-voltage and power flow conditions.

• Stability

The stability issues that limit the transmission capability include: transient stability, dynamic

stability, steady-state stability, frequency collapse. Voltage collapse, and sub-synchronous

resonance.

• The FACTS technology can certainly be used to overcome any of the stability limits.

Page 47: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

A Simple Example of FACTS

Page 48: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Basic types of FACTS Controllers

• Series controllers: The series controller could be a variable impedance or a variable source both are power electronics based. In principle, all series controllers inject voltage in series with the line.

• Shunt controllers: The shunt controllers may be variable impedance connected to the line voltage causes a variable current flow hence represents injection of current into the line.

• Combined series-series controllers: The combination could be separate series controllers or unified series-series controller--- Interline Power Flow Controller.

• Combined series-shunt controllers: The combination could be separated series and shunt controllers or a unified power flow controller

Page 49: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Relative Importance of Different Types of Controllers

• For a given MVA size, the series controller is several times more powerful than the shunt controller in application of controlling the power/current flow.

• Drawing from or injecting current into the line, the shunt controller is a good way to control voltage at and around the point of connection.

• The shunt controller serves the bus node independently of the individual lines connected to the bus.

• Series connected controllers have to be designed to ride through contingency and dynamic overloads, and ride through or bypass short circuit currents.

• A combination of series and shunt controllers can provide the best of effective power/current flow and line voltage.

• FACTS controllers may be based on thyristor devices with no gate turn-off or with power devices with gate turn-off capability.

• The principle controllers are based on the dc to ac converters with bidirectional power flow capability.

Page 50: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Relative Importance of Different Types of Controllers

• Energy storage systems are needed when active power is involved in the power flow.

• Battery, capacitor, superconducting magnet, or any other source of energy can be added in parallel through an electronic interface to replenish the converter’s dc storage.

• A controller with storage is more effective for controlling the system dynamics.

• A converter-based controller can be designed with high pulse order or pulse width modulation to reduce the low order harmonic generation to a very low level.

• A converter can be designed to generate the correct waveform in order to act as an active filter.

• A converter can also be controlled and operated in a way that it balances the unbalanced voltages, involving transfer of energy between phases.

• A converter can do all of these beneficial things simultaneously I the converter is so designed.

Page 51: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Brief Description and Definitions of FACTS controllers

• Shunt connected controllers

• Series connected controllers

• Combined shunt and series connected controllers

Page 52: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Shunt connected controllers

Page 53: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Series connected controllers

Page 54: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Combined shunt and series connected controllers

Page 55: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Other controllers

Page 56: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

SVC, Static VAR Compensator (shunt connected controller)

Note: The control strategy usually aims to maintain the transmission line voltage at a fixed level.

Page 57: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

STATCOM, Static Compensator---Advanced Static VAR Compensator (shunt connected controller)

The main features:

1. Wide operating range

2. Lower rating than SVC

3. Increased transient rating and superior capability to handle dynamic system disturbances

Page 58: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

TCSC, thyristor-controlled series capacitor (series-connected controller)

Note: The TCSC behaves as a tunable parallel LC-circuit to the line current. As the impedance of XL is varied from its maximum (infinity) toward its minimum wL, the TCSC increases its capacitive impedance.

Page 59: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

UPFC, unified power flow controller (combined shunt and series connected controllers)

1. The UPFC consists of an a series STATCOM and a shunt SATACOM with a common DC link. 2. Power control is achieved by adding series voltage Vinj to Vs, thus giving the line voltage VL. 3. With two converters, the UPFC can supply active power in addition to reactive power.

Page 60: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

UPFC Capabilities

• Increase transmission line capacity

• Direct power flow along selected lines

• Powerful system oscillation damping

• Voltage support and regulation

• Control of active and reactive power flow at both sending- and receiving-end

Page 61: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Operation

• Reactive power is generated or absorbed by the shunt inverter to control bus voltage

• Reactive power is generated or absorbed by the series inverter to control the real and/or reactive power flow on the transmission line.

• A portion of the real power flow on the transmission line is drawn from the bus by the shunt inverter to charge the DC capacitor.

• Real power is inserted into the line through the series inverter.

Page 62: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

jXSV

RV

SRP

sinS R

SR

V VP

X

Power flow in a transmission line

To increase PSR, increase

and R S

V V jXI

jXI

SV

RV

Page 63: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

AV

BV

in jV- +

AV

in jV

BV

jXSV

RV

SRP

RV in j

V- + sinS R

SR

V VP

X

jXI

in jV

SV

RV

Page 64: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

How is Vinj created?

V

+ b1

a2

a1

b2

c1

c2

Page 65: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

V

+ b1

a2

a1

b2

c1

c2

a1 on, b1 on, c1 off

Vab=0, Vbc=V, Vca = -V

a1 on, b1 off, c1 off

Vab=V, Vbc=0, Vca = -V

V

+ a1 b1 c1

c2 b2 a2

V

+ a1 b1 c1

c2 b2 a2

a1 on, b1 off, c1 on

Vab=V, Vbc=-V, Vca = 0

Page 66: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Introduction • Electric power transmission was originally

developed with direct current.

• The first commercial HVDC line built in 1954, a 98 km submarine cable with ground return between the island of Gotland and the Swedish mainland. Thyristors were applied to D C transmission in the late 1960’s and solid state valves became a reality.

• D.C. transmission is now an integral part of the delivery of electricity in many countries throughout the world.

Page 67: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Introduction • A high-voltage, direct current (HVDC) electric

power transmission system uses direct current for the bulk transmission of electrical power.

• For long-distance transmission, HVDC systems may be less expensive and suffer lower electrical losses.

• For underwater power cables, HVDC avoids the heavy currents required by the cable capacitance.

• HVDC allows power transmission between unsynchronized AC distribution systems, and can increase system stability by preventing cascading failures from propagating from one part of a wider power transmission grid to another.

Page 68: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Why HVDC systems ?

Page 69: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Why HVDC • An overhead d.c. transmission line with its towers can be designed to be less costly per

unit of length than an equivalent a.c. line designed to transmit the same level of electric power.

• However the d.c. converter stations at each end are more costly than the terminating stations of an a.c. line and so there is a breakeven distance above which the total cost of d.c. transmission is less than its a.c. transmission alternative.

• The d.c. transmission line can have a lower visual profile than an equivalent a.c. line and so contributes to a lower environmental impact. There are other environmental advantages to a d.c. transmission line through the electric and magnetic fields being d.c. instead of ac.

• If transmission is by submarine or underground cable, the breakeven distance is much less than overhead transmission.

• It is not practical to consider a.c. cable systems exceeding 50 km but d.c. cable transmission systems are in service whose length is in hundreds of kilometers and even distances of 600 km or greater have been considered feasible.

• Some a.c. electric power systems are not synchronized to neighboring networks even though their physical distances between them are quite small.

• It is physically impossible to connect the two together by direct A.C methods in order to exchange electric power between them.

• However, if a d.c. converter station is located in each system with an interconnecting d.c. link between them, it is possible to transfer the required power flow even though the a.c. systems so connected remain asynchronous.

Page 70: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

HVDC Advantages 1. Interconnections between asynchronous systems. 2. Deliver energy from remote energy sources. Where generation has been developed

at remote sites of available energy, HVDC transmission has been an economical means to bring the electricity to load centers. Gas fired thermal generation can Import electric energy into congested load areas.

3. Increasing the capacity of existing a.c. transmission by conversion to d.c. transmission.

4. New transmission rights-of-way may be impossible to obtain. Existing overhead a.c. transmission lines if upgraded to or overbuilt with d.c. transmission can substantially increase the power transfer capability on the existing right-of-way.

5. Power flow control. A.c. networks do not easily accommodate desired power flow control. Power marketers and system operators may require the power flow control capability provided by HVDC transmission.

6. Stabilization of electric power networks. Some wide spread a.c. power system networks operate at stability limits well below the thermal capacity of their transmission conductors. HVDC transmission is an option to consider to increase utilization of network conductors along with the various power electronic controllers which can be applied on a.c. transmission.

Page 71: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Advantages over HVAC • Bulk Power transfer with lower capital costs and with lower losses than

AC. • In many applications HVDC is more effective than AC transmission.

– Undersea cables, where high capacitance causes additional AC losses. – Endpoint-to-endpoint long-haul bulk power transmission without

intermediate 'taps'. – Increasing the capacity of an existing power grid in situations where additional

wires are difficult or expensive to install – Power transmission and stabilization between unsynchronized AC distribution

systems – Connecting a remote generating plant to the distribution grid. – Stabilizing a predominantly AC power-grid, without increasing prospective

short circuit current – Reducing line cost. HVDC needs fewer conductors as there is no need to

support multiple phases. – Thinner conductors can be used since HVDC does not suffer from the skin

effect – Facilitate power transmission between different countries that use AC at

differing voltages and/or frequencies – Synchronize AC produced by renewable energy sources

Page 72: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

BASIC HVDC Topology

Page 73: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

HVDC is an “intelligent link”. The power flow can be controlled and changed very quickly practically independently from frequency at the terminal busses, voltage or power angle at the terminal busses like in HVAC transmission. Due to the inherent properties of the electronic equipment which forms the converter bridges, the direction of the transmitted power may be also changed very quickly.

The HVDC transmission has the

major advantage of flexibility in

power exchange in comparison

with HVAC. Moreover, in case of

transmission of bulk electrical

energy over long distances (more

than 50 km) by submarine cable,

the only applicable technology is

the HVDC transmission.

HVDC transmission

Page 74: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

In a HVDC system, the electricity is: - Taken from a 3-phase AC network - Converted to DC in a converter station - Transmitted by DC OHL or cable (underground or sub sea) - Converted back to AC in another converter station - Injected into AC network

HVDC transmission – principles and characteristics

Controllable – power injected where needed,supplemental control, frequency control - Bypass congested circuits – no inadvertent flow - Higher power, fewer lines,no intermediate S/S needed - Lower losses - Facilitates integration of remote diverse resources with less impact on existing grid - Low expensive transmission line - Reactive power demand limited to terminals independent of distances - Narrower ROW, no EMF constraints - No limit to underground or submarine cable length

Page 75: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

HVDC CONFIGURATION

Page 76: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

1. One of the terminals of the rectifier is connected to earth ground. The other terminal, at a potential high above or below ground, is connected to a transmission line.

2. The earthed terminal may be connected to the corresponding connection at the inverting station by means of a second conductor.

3. If no metallic conductor is installed, current flows in the earth between the earth electrodes at the two stations.

4. Therefore it is a type of single wire earth return. The issues surrounding earth-return current include: • Electrochemical corrosion of long buried metal objects such as pipelines • Underwater earth-return electrodes in seawater may produce chlorine or otherwise affect

water chemistry. • An unbalanced current path may result in a net magnetic field, which can affect magnetic

navigational compasses for ships passing over an underwater cable. 5. These effects can be eliminated with installation of a metallic return conductor between the two

ends of the monopolar transmission line. 6. Since one terminal of the converters is connected to earth, the return conductor need not be

insulated for the full transmission voltage which makes it less costly than the high-voltage conductor.

7. Use of a metallic return conductor is decided based on economic, technical and environmental factors.

8. Modern monopolar systems for pure overhead lines carry typically 1,500 MW. If underground or underwater cables are used, the typical value is 600 MW.

9. Most monopolar systems are designed for future bipolar expansion. 10. Transmission line towers may be designed to carry two conductors, even if only one is used

initially for the monopole transmission system.

MONOPOLAR AND EARTH RETURN

Page 77: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

BIPOLAR

1. In bipolar transmission a pair of conductors is used, each at a high potential with respect to ground, in opposite polarity.

2. Since these conductors must be insulated for the full voltage, transmission line cost is higher than a monopole with a return conductor.

3. Advantages to bipolar transmission . • Under normal load, negligible earth-current flows, as in the case of monopolar transmission with a

metallic earth-return. This reduces earth return loss and environmental effects. • When a fault develops in a line, with earth return electrodes installed at each end of the line,

approximately half the rated power can continue to flow using the earth as a return path, operating in monopolar mode.

• Since for a given total power rating each conductor of a bipolar line carries only half the current of monopolar lines, the cost of the second conductor is reduced compared to a monopolar line of the same rating.

• In very adverse terrain, the second conductor may be carried on an independent set of transmission towers, so that some power may continue to be transmitted even if one line is damaged.

4. A bipolar scheme can be implemented so that the polarity of one or both poles can be changed.

5. This allows the operation as two parallel monopoles. 6. If one conductor fails, transmission can still continue at reduced capacity. 7. Losses may increase if ground electrodes and lines are not designed for the extra

current in this mode. To reduce losses in this case, intermediate switching stations may be installed, at which line segments can be switched off or parallelized.

Page 78: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

• A back-to-back station (or B2B for short) is a plant in which both static inverters and rectifiers are in the same area, usually in the same building.

• The length of the direct current line is kept as short as possible. HVDC back-to-back stations are used for • Coupling of electricity mains of different frequency (as in

Japan; and the GCC interconnection between UAE [50 Hz] and Saudi Arabia [60 Hz] under construction in ±2009–2011)

• Coupling two networks of the same nominal frequency but no fixed phase relationship

• Different frequency and phase number. • The DC voltage in the intermediate circuit can be selected

freely at HVDC back-to-back stations because of the short conductor length.

BACK to BACK

Page 79: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

OTHER HVDC CONFIGURATIONS

Page 80: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

Components of HVDC System

Page 81: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

• Rectification and inversion use essentially the same machinery.

• Many substations (Converter Stations) are set up in such a way that they can act as both rectifiers and inverters.

• At the AC end a set of transformers, often three physically separated single-phase transformers, isolate the station from the AC supply, to provide a local earth, and to ensure the correct eventual DC voltage.

• The output of these transformers is then connected to a bridge rectifier formed by a number of valves.

• The basic configuration uses six valves, connecting each of the three phases to each of the two DC rails.

• However, with a phase change only every sixty degrees, considerable harmonics remain on the DC rails.

• In addition to the conversion transformers and valve-sets, various passive resistive and reactive components help filter harmonics out of the DC rails.

Page 82: SCADA and Systems Monitoring - sudhinpk | Arise and … · SCADA and Systems Monitoring •SCADA stands for supervisory control and data acquisition system. • There are locations,

HVDC Disadvantages • The disadvantages of HVDC are in conversion, switching, control, availability

and maintenance. • HVDC is less reliable and has lower availability than alternating current (AC)

systems, mainly due to the extra conversion equipment. • The required static inverters are expensive and have limited overload

capacity • In contrast to AC systems, realizing multiterminal systems is complex, as is

expanding existing schemes to multiterminal systems. Controlling power flow in a multiterminal DC system requires good communication between all the terminals

• HVDC circuit breakers are difficult to build because some mechanism must be included in the circuit breaker to force current to zero, otherwise arcing and contact wear would be too great to allow reliable switching.

• Operating a HVDC scheme requires many spare parts to be kept, often exclusively for one system, as HVDC systems are less standardized than AC systems and technology changes faster.