Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Draft Environmental Management Programme the Proposed Installation of Metals’ High Chrome Ball Plant
A Report For: Scaw South Africa Pty Ltd
GDARD Reference No: Gaut 002/13
Date: January 2014
Draft Environmental Management Programme (EMPr) the Proposed Installation of a Gas Fired Furnace at Scaw Metals’ High Chrome Ball Plant in Germiston
South Africa Pty Ltd
Gaut 002/13-14/E0162
(EMPr) for Gas Fired Furnace at Scaw
© Royal HaskoningDHV All rights reserved No part of this publication may be reproduced or transmitted in any form or by any means, electronic or mechanical, without tpermission from Royal Haskoning.DHV
DOCUMENT DESCRIPTION
Client:
Scaw South Africa Pty Ltd
Report Name:
Draft Environmental Management Programme (EMPr) for the Proposed Installation of a Gas Fired Furnace at Scaw Metal's High Chrome Ball Plant i
Royal HaskoningDHV Reference Number
T01.JNB.000531
GDARD Reference No:
Gaut 002/13-14/E0162
Compiled by:
Sibongile Gumbi
Reviewer and Approver:
Mark Freeman
No part of this publication may be reproduced or transmitted in any form or by any means, electronic or mechanical, without t
DOCUMENT DESCRIPTION
Draft Environmental Management Programme (EMPr) for the Proposed Installation of a Gas Fired Furnace at Scaw Metal's High Chrome Ball Plant in Germiston.
ference Number:
No part of this publication may be reproduced or transmitted in any form or by any means, electronic or mechanical, without the written
1 PROJECT DESCRIPTION
1.1 Context and Background
2 LEGAL REQUIREMENTS
3 MANAGEMENT AND MONITORING PROCEDURES
3.1. Roles and Responsibilities
3.2. Training and Environmental Awareness
3.3. Monitoring
3.4. Checking and Corrective Action
4 ENVIRONMENTAL MANAGEMENT PROGRAMME
4.1. Purpose and Objectives of the EMPr
5 CONSTRUCTION PHASE
6 POST CONSTRUCTION PHASE
7 OPERATIONAL PHASE
TABLE 1: APPLICABLE LEGISLATION
TABLE 2:ROLES AND RESPONSIBILITIES
TABLE 3:ENVIRONMENTAL EDUCATION AND TRAINING
TABLE 4:SITE CAMP ESTABLISHMENT
TABLE 5:CONSTRUCTION TRAFFIC AN
TABLE 6:AIR QUALITY MANAGEMENT
TABLE 7:GROUND AND SURFACE WATER MANAGEMENT
TABLE 8:WASTE MANAGEMENT
TABLE 9:REHABILITATION
TABLE 10:OPERATIONAL
FIGURE 1: LOCATION OF THE STUDY AREA WITHIN JOHANNESBURG
FIGURE 2: SCAW METAL GROUP PROPERTY BOUNDARY
FIGURE 3: LOCATION OF SCAW METAL HIGH CHROME BALL PLANT
TABLE OF CONTENTS
MANAGEMENT AND MONITORING PROCEDURES
Training and Environmental Awareness
Checking and Corrective Action
ENVIRONMENTAL MANAGEMENT PROGRAMME
Purpose and Objectives of the EMPr
CONSTRUCTION PHASE
LIST OF TABLES
TABLE 1: APPLICABLE LEGISLATION
TABLE 2:ROLES AND RESPONSIBILITIES
TABLE 3:ENVIRONMENTAL EDUCATION AND TRAINING
TABLE 4:SITE CAMP ESTABLISHMENT
TABLE 5:CONSTRUCTION TRAFFIC AND SITE ACCESS
TABLE 6:AIR QUALITY MANAGEMENT
D SURFACE WATER MANAGEMENT
LIST OF FIGURES
FIGURE 1: LOCATION OF THE STUDY AREA WITHIN JOHANNESBURG
FIGURE 2: SCAW METAL GROUP PROPERTY BOUNDARY
FIGURE 3: LOCATION OF SCAW METAL HIGH CHROME BALL PLANT
1
1
5
6
6
7
7
8
8
8
10
15
16
5
6
10
11
12
13
13
14
15
16
2
3
4
DEFINITIONS
Environment In terms of the National Environmental Management Act (NEMA) (No 107 of
1998), “environment” means the surroundings within which humans exist and that
are made up of:
(i) The land, water and atmosphere of the earth;
(ii) Micro
Any part or combination of (i) of (ii) and the interrelationships among and between
them; and the physical, chemical, aesthetic and cultural properties and conditions
of the foregoing that influence human health and wellbeing.
Environmental Management Programme
A detailed plan of action prepared to ensure that recommendations for enhancing
or ensuring positive impacts and limiting or preventing negative environmental
impacts are implemented during the life
Management Programme
Environmental Management System and ISO 14001 standard compliance
system.
Scaw Project Manager The person appointed by
notified, by name and in writing by
the Contract.
Environmental Site Agent An individual appointed by the Contractor to be present on site to act on behalf of
the Contractor in matters concerning the implementation and day to day
monitoring of the EMPr.
Environmental Control Officer
An individual nominated through the Project Manager to be present periodically
on site to act on behalf of the Project Manager in matters concerning the
implementation and monitoring of the EMPr.
Contractor A person or company appointed by Scaw to carry ou
Incident An undesired event which may result in significant environmental impacts but can
be managed through internal response
Environmental Impact A change to the environment, whether adverse or beneficial, wholly or partially
resulting from an organisation’s activities, products or services.
Mitigation Measure Measures designed to avoid, reduce or remedy adverse impacts.
Rehabilitation Rehabilitation is the return of a disturbed area to a state which approximates the
state (where possible) which it was in before construction.
In terms of the National Environmental Management Act (NEMA) (No 107 of
1998), “environment” means the surroundings within which humans exist and that
are made up of:
The land, water and atmosphere of the earth;
Micro-organisms, plant and animal life, and
Any part or combination of (i) of (ii) and the interrelationships among and between
them; and the physical, chemical, aesthetic and cultural properties and conditions
of the foregoing that influence human health and wellbeing.
A detailed plan of action prepared to ensure that recommendations for enhancing
or ensuring positive impacts and limiting or preventing negative environmental
impacts are implemented during the life-cycle of a project. T
Management Programme (EMPr) should preferably form part of S
Environmental Management System and ISO 14001 standard compliance
system.
The person appointed by Scaw from time to time to act in the capacity and
notified, by name and in writing by Scaw to the Contractor, to act as required in
ontract.
An individual appointed by the Contractor to be present on site to act on behalf of
ontractor in matters concerning the implementation and day to day
monitoring of the EMPr.
individual nominated through the Project Manager to be present periodically
on site to act on behalf of the Project Manager in matters concerning the
implementation and monitoring of the EMPr.
A person or company appointed by Scaw to carry out stipulated activities.
An undesired event which may result in significant environmental impacts but can
be managed through internal response.
A change to the environment, whether adverse or beneficial, wholly or partially
resulting from an organisation’s activities, products or services.
Measures designed to avoid, reduce or remedy adverse impacts.
Rehabilitation is the return of a disturbed area to a state which approximates the
state (where possible) which it was in before construction.
In terms of the National Environmental Management Act (NEMA) (No 107 of
1998), “environment” means the surroundings within which humans exist and that
Any part or combination of (i) of (ii) and the interrelationships among and between
them; and the physical, chemical, aesthetic and cultural properties and conditions
of the foregoing that influence human health and wellbeing.
A detailed plan of action prepared to ensure that recommendations for enhancing
or ensuring positive impacts and limiting or preventing negative environmental
cycle of a project. This Environmental
form part of Scaw’s
Environmental Management System and ISO 14001 standard compliance
from time to time to act in the capacity and
to the Contractor, to act as required in
An individual appointed by the Contractor to be present on site to act on behalf of
ontractor in matters concerning the implementation and day to day
individual nominated through the Project Manager to be present periodically
on site to act on behalf of the Project Manager in matters concerning the
t stipulated activities.
An undesired event which may result in significant environmental impacts but can
A change to the environment, whether adverse or beneficial, wholly or partially
resulting from an organisation’s activities, products or services.
Measures designed to avoid, reduce or remedy adverse impacts.
Rehabilitation is the return of a disturbed area to a state which approximates the
Page | 1
1 PROJECT DESCRIPTION
1.1 Context and Background
Scaw South Africa Pty Ltd (“Scaw Metals”) is proposing to install a gas fired heat treatment furnace at their
High Chrome Ball Plant (HCBP) in their Union Junction facility located in Germiston, Gauteng Province. The
heat treatment furnace will be a gas-fired furnace as opposed to the electric furnace currently installed. The
new furnace will be installed within the current heat treatment section of the HCBP adjacent to the existing heat
treatment furnace. Heat treatment of chrome balls is undertaken after casting in order to alter the internal
structure and make it more suitable for its further purpose as a grinding agent.
Scaw Metals manufactures a diverse range of steel products. The Grinding Media Division at Union Junction is
the largest producer of cast high chrome grinding media in the southern hemisphere and has an opportunity to
increase its production volume as a result of an increased market demand. Therefore, an additional heat
treatment furnace will be required to meet this demand.
Electrical supply is a limited resource both at Scaw Metals and in the entire country. From a strategic point of
view, installing a gas-fired furnace utilising natural gas will reduce Scaw’s demand on the electrical grid. In
addition, the utilisation of natural gas as a fuel source will realise a reduction in energy costs when compared to
electricity as a fuel source.
The proposed project is located in the HCBP plant at Union Junction along Dekema and Centime Roads in the
Wadeville industrial area, Germiston South, which falls within the jurisdiction of Ekurhuleni Metropolitan
Municipality (refer to Figures 1 to 3). The study area is surrounded by industries, commercial businesses,
residential houses (Dinwiddie) and Provincial Roads (M37, R103 and R554), as well as National Roads (N3
and N17).
Page | 2
Extent of the Study Area in
Johannesburg East Rand
FIGURE 1: LOCATION OF THE STUDY AREA WITHIN JOHANNESBURG
Page | 3
FIGURE 2: SCAW METAL GROUP PROPERTY BOUNDARY
Page | 4
FIGURE 3: LOCATION OF SCAW METAL HIGH CHROME BALL PLANT
Page | 5
2 LEGAL REQUIREMENTS
Table 1 below lists the relevant policies and legislation which are applicable to the proposed project.
TABLE 1: APPLICABLE LEGISLATION
LEGISLATION INTERPRETATION
The Constitution ( Act No 108 of 1996) This relates to the environmental rights to a pollution
free environment for the surrounding community,
industries and commercial businesses.
National Environmental Management Act ( Act No 107
of 1998)
The developer has a general duty to care for the
environment and to establish measures as may be
needed to demonstrate such care.
National Environmental Management: Air Quality Act
(Act No 39 of 2004).
This relates to the control of dust, emissions, odour
and noise.
National Water Act (Act 36 of 1998). This relates to the use and management of water
resources, including pollution prevention and remedy
of incidents.
National Environmental Management: Waste Act (No
59 of 2008)
It is the responsibility of the developer, and its
contractors generating waste, to ensure that any
waste (solid or liquid) is stored appropriately
(containers) and safely, treated where required and
then disposed of in an environmentally sound manner.
Ekurhuleni Metropolitan Municipality By Laws
Page | 6
3 MANAGEMENT AND MONITORING PROCEDURES
3.1. Roles and Responsibilities
It is anticipated that several key professionals will need to form part of the project execution team and their
responsibilities in respect of the environment are outlined in Table 2 below.
TABLE 2: ROLES AND RESPONSIBILITIES
ROLES RESPONSIBILITIES
Project Manager The Project Manager is responsible for overall management of the project, including the
EMPr implementation. The following tasks will fall within his / her responsibilities:
� Be familiar with the recommendations and mitigation measures of this EMPr, and
ensure implementation of these measures on site;
� Monitor site activities on a regular basis for compliance;
� Conduct internal audits of the construction site against the EMPr;
� Confine the construction site and construction activities to the demarcated area; and
� Rectify transgressions through the implementation of corrective action.
Environmental
Control Officer
The responsibilities of the Environmental Control Officer are to:
� Monitor the implementation of the EMPr during the construction phase;
� Be familiar with the recommendations and mitigation measures of the site-specific
EMPr for the project;
� Ensure protection measures are implemented on site;
� Monitor all site activities on a monthly basis for compliance;
� Conduct monthly audits of the site according to the EMPr, and report findings to the
Project Manager/Contractor;
� Recommend corrective action for any environmental non-compliance noted on site;
� Compile a monthly report highlighting any non-compliance issues as well as progress
and compliance with the EMPr prescriptions; and
� Conduct once-off training with the Contractor on the EMPr and general environmental
awareness.
It must be noted that the responsibility of the ECO is to monitor compliance and give
advice on the implementation of the EMPr, and not to enforce compliance. Ensuring
compliance is the responsibility the Site Agent appointed by the Contractor.
Contractor The Contractor and its sub-constructors are responsible for overall execution of the
activities envisioned in the construction phase, including implementation and compliance
with the recommendations and conditions of the EMPr. The Contractor shall therefore
ensure compliance with the EMPr at all times during construction activities and maintain
an environmental register which keeps a record of all environmental incidents which occur
on site during construction. The incidents may include:
� Public involvement /complaints;
� Health and Safety incidents
� Incidents involving hazardous materials stored on site; and
� Non-compliances with the EMPr
� The Contractor is responsible for the implementation of corrective actions issued by
the ECO and Project Manager within a reasonable or agreed period time.
Environmental
Site Agent
The Environmental Site Agent (ESA) should:
� Be fully conversant with the content of the EMPr;
� Be fully conversant with all relevant environmental legislation applicable to the project,
and ensure compliance with any legal obligations;
� Compile the construction Method Statements together with the Contractor that will
Page | 7
ROLES RESPONSIBILITIES
specify how potential environmental impacts in line with the requirements of the EMPr
will be managed and how they will practically ensure that the objectives of the EMPr
are achieved;
� Convey the contents of this EMPr to the construction site staff and discuss the
contents in detail with the Contractor;
� Undertake regular and comprehensive daily inspections of the site and surrounding
areas in order to monitor compliance with the EMPr;
� Take appropriate action if the specifications contained in the EMPr are not followed;
� Monitor and verify that environmental impacts are kept to a minimum, as far as
practically possible;
� Order the removal from the construction site of any person(s) and/or equipment in
contravention of the specifications of the EMPr;
� Maintain the following documents on site:
o EMPr;
o Construction layout plan (showing storage areas etc)
o Construction method statements;
o A site diary;
o Environmental incidents register; and
o Update Material Safety Data Sheets (MSDS) when necessary.
3.2. Training and Environmental Awareness
It is important to ensure that the Contractor and their sub-contractors have the appropriate level of
environmental awareness and competence to ensure continued environmental due diligence and ongoing
minimisation of environmental harm during construction. Training needs should be identified based on the
available and existing capacity of site personnel (including for all Contractors and sub-contractors) to undertake
the required EMPr management actions and monitoring activities. It is vital that all personnel are adequately
trained to perform their designated tasks to an acceptable standard.
The environmental training is aimed at:
� Promoting environmental awareness;
� Informing the Contractor of all environmental procedures, policies and programmes applicable;
� Providing generic training on the implementation of environmental management specifications; and
� Providing job-specific environmental training in order to understand the key environmental features of the
construction site and the surrounding environment.
In addition to training, general environmental awareness must be fostered among the project’s workforce to
encourage the implementation of environmentally sound practices throughout the duration of the construction
phase through regular toolbox information talks.
3.3. Monitoring
A monitoring programme should be in place to ensure compliance with the EMPr and to monitor any
environmental issues and impacts which could result in significant environmental impacts for which corrective
action is required. A monitoring programme should be implemented for the duration of the construction phase
of the project. This programme must include:
Page | 8
� Monthly site audits that will be conducted by the independent Environmental Control Officer
� Compilation of a monthly audit report which will document findings and recommend corrective action to be
taken where required. Subsequent reports will provide feedback on whether previous non conformances
raised have been resolved, thereby ensuring continual improvement of the site’s environmental
performance; and
� Daily site inspections will be conducted by the Environmental Site Agent to ensure daily implementation of
the EMPr conditions and provide corrective actions.
3.4. Checking and Corrective Action Checking and corrective action forms part of the environmental management function and is aimed at ensuring
that the necessary environmental management activities are being implemented according to the EMPr and
that the desired outcomes are achieved.
4 ENVIRONMENTAL MANAGEMENT PROGRAMME
4.1. Purpose and Objectives of the EMPr
The Environmental Management Programme (EMPr) has been compiled to provide recommendations and
guidelines according to which construction activities at HCBP must be undertaken, as well as to ensure that all
relevant factors are considered for implementing an environmentally responsible development.
This EMPr informs all relevant parties, including the Project Manager, Contractor and all other staff employed
by the Scaw Metals Group on site, as to their duties in the fulfilment of the environmental legal requirements for
the construction of the gas fired heat treatment plant and its associated infrastructure, and with particular
reference to the prevention and mitigation of anticipated potential environmental impacts.
The objectives of the EMPr are to:
� Identify a range of mitigation measures which could reduce and mitigate the potential environmental
impacts to minimal or insignificant levels;
� Detail specific actions deemed necessary to assist in mitigating the environmental impact of the project;
� Identify measures that could optimize beneficial impacts;
� To create management structures that address the concerns and complaints of the public with regards to
the development;
� To establish a method of monitoring and auditing environmental management practices during all
implementation phases of the project;
� Ensure that the final design, construction and operational phases of the project follow the principles of
Integrated Environmental Management (IEM);
� Specify time periods within which the measures contemplated in the EMPr shall be implemented where
appropriate.
The emphasis of the EMPr is to:
� Avoid impacts by not performing certain actions;
� Minimise impacts by limiting aspects of an action;
Page | 9
� Rectify impacts through consideration of the affected environment;
� Compensate for impacts by providing substitute resources or environments;
� Minimise impacts by optimising processes, structural elements and other design features;
� Maximise benefits accruing from the project and
� Provide ongoing monitoring and management of the environmental impacts of the development by
documenting any EMPr digressions / good performances.
Page | 10
5 CONSTRUCTION PHASE
TABLE 3: ENVIRONMENTAL EDUCATION AND TRAINING
PHASE CONSTRUCTION CONTRACTOR & ESA WEEKLY
ENVIRONMENTAL EDUCATION AND TRAINING
(This section deals with the environmental training of employees)
RESPONSIBILITY FREQUENCY / MONITORING
REQUIREMENTS
Environmental Training
1. The Environmental Site Agent (ESA) must ensure that all site
personnel have a basic level of environmental awareness training.
Topics covered should include;
• What is meant by “Environment”;
• Why the environment needs to be protected and conserved;
• How construction activities can impact on the environment;
• What can be done to mitigate against such impacts;
• Awareness of emergency and spills response provisions; and
2. Environmental Training should be provided to the employees
through toolbox information talks. These should be relevant to
specific construction work or activities.
3. Staff operating equipment (such as excavators, loaders, etc.) shall
be adequately trained and sensitised to any potential hazards
associated with their tasks. Proof of training to be kept in an
environmental file.
4. The ESA must be conversant with all legislation pertaining to the
environment applicable to this contract and must be appropriately
trained in environmental management and must possess the skills
necessary to impart environmental management skills to all
personnel involved in the contract.
Page | 11
TABLE 4: SITE CAMP ESTABLISHMENT
PHASE CONSTRUCTION DAILY CONTRACTOR & ESA
IMPACT SOURCE MITIGATION MEASURE MONITORING ACTIONS & FREQUENCY
RESPONSIBILITY FOR IMPLEMENTATION
Disturbance to neighbouring landowners.
Location of construction camp close to neighbouring land owners.
1. Site construction camp location and the layout
plans must be approved by the Project
Manager.
2. The location must take into account the
proximity to neighbouring landowners.
3. The Contractor must obtain consent from the
Project Manager and the landowners prior to
erecting any construction camp infrastructure.
Stormwater discharge to neighbouring properties.
Poor management of stormwater and drainage at the construction site.
1. The Contractor must attend to stormwater
drainage of the site to avoid standing water and
/ or sheet erosion by installing diversion berms
where needed.
Unauthorised access and theft at the site camp.
Unauthorised access of the public to the site.
1. The site camp must be secure at all times to
prevent unauthorised access at the construction
site.
Site contamination/ pollution.
Improper storage and use of equipment and hazardous substances (chemicals, paint and cement).
1. Hazardous substances need to be kept in a
secured storage area which is bunded and/or
has an impermeable floor layer that is able to
contain spillages.
2. The hazardous substance storage area needs
to be locked at all times.
3. Spill kits must be kept at the hazardous
substance storage facility to treat and manage
any spills immediately. All contaminated
soil/clothing/material must be disposed of at a
licensed hazardous landfill site.
4. The hazardous material storage facility should
be sited away from stormwater drainage lines.
5. Clear warning signage must be placed at all
storage areas containing hazardous substances
/ materials.
6. Staff dealing with these materials / substances
must be aware of their potential hazard and
Page | 12
PHASE CONSTRUCTION DAILY CONTRACTOR & ESA
IMPACT SOURCE MITIGATION MEASURE MONITORING ACTIONS & FREQUENCY
RESPONSIBILITY FOR IMPLEMENTATION
follow the appropriate safety measures.
Air and soil pollution and site contamination.
Improper handling of cement, fuel, paint and other chemicals on site.
1. Used paint tins/brushes must be disposed of at
hazardous landfill sites.
Use of Scaw Metals equipment and services.
Misuse of Scaw Metals equipment and services.
1. The Contractor must engage with the Project
Manager regarding the temporary access to and
usage of services located within the Scaw
Metals premises e.g. electricity and water.
TABLE 5: CONSTRUCTION TRAFFIC AND SITE ACCESS
PHASE CONSTRUCTION DAILY CONTRACTOR & ESA
IMPACT SOURCE MITIGATION MEASURE MONITORING ACTIONS & FREQUENCY
RESPONSIBILITY FOR IMPLEMENTATION
Disturbance to the
neighbouring
landowners.
Construction vehicles 1. Appropriate traffic signage must be erected on
site by the Contractor to alert other road users
to construction activities.
2. The Contractor should strategically position the
site entry and exit points to ensure that there is
minimum impact to the traffic flow on
neighbouring streets.
3. The Contractor must ensure that local access
roads are not damaged by construction
vehicles. If damage does occur, it needs to be
attended to immediately to avoid long term
problems.
Page | 13
TABLE 6: AIR QUALITY MANAGEMENT
PHASE CONSTRUCTION DAILY CONTRACTOR & ESA
IMPACT SOURCE MITIGATION MEASURE MONITORING ACTIONS & FREQUENCY
RESPONSIBILITY FOR IMPLEMENTATION
Generation of dust. Vehicles driving at a high speed and construction activities which result in dust generation.
1. The Contractor shall be responsible for dust
control (water spraying) on site to ensure no
nuisance is caused to the neighbouring
landowners.
Air emissions. Un-serviced construction vehicles and the servicing of vehicles on site.
1. The Contractor must regularly service the
construction vehicles and machinery used on site
at an approved off site service station.
TABLE 7: GROUND AND SURFACE WATER MANAGEMENT
PHASE CONSTRUCTION DAILY CONTRACTOR & ESA
IMPACT SOURCE MITIGATION MEASURE MONITORING ACTIONS & FREQUENCY
RESPONSIBILITY FOR IMPLEMENTATION
Water contamination. Improper storage and use of hazardous substances including cement, paints and other chemicals.
1. The Contractor must remove contaminated
wastewater resulting from construction activities
and dispose of it at a licensed commercial
wastewater treatment facility.
2. Used oil on site must be managed accordingly.
3. Accidental spillages of hazardous substances
(i.e. cement, paints and other chemicals) that
occur on site must be contained and remediated
as soon as possible.
4. On site ablution facilities need to be placed in a
bunded area and serviced regularly.
Water wastage. Misuse of water. 1. The Contractor and workers need to use water
responsibly and avoid unnecessary wastage.
Taps should not be left open and leaking taps
should be repaired immediately.
Disruption of Scaw Metals operational
The Contractor and its workers accessing water
1. The Contractor must liaise with the Project
Page | 14
PHASE CONSTRUCTION DAILY CONTRACTOR & ESA
IMPACT SOURCE MITIGATION MEASURE MONITORING ACTIONS & FREQUENCY
RESPONSIBILITY FOR IMPLEMENTATION
activities and services. and other services from Scaw Metals’ municipal supply.
Manager with regards to accessing potable water
and other services from the Scaw Metals’ supply,
monitor the amounts utilised and pay Scaw
Metals accordingly.
TABLE 8: WASTE MANAGEMENT
PHASE CONSTRUCTION DAILY CONTRACTOR & ESA
IMPACT SOURCE MITIGATION MEASURE MONITORING ACTIONS & FREQUENCY
RESPONSIBILITY FOR IMPLEMENTATION
Ground and water pollution and aesthetic impact.
Insufficient waste bins, incorrect labelling of waste bins, mixing of general, construction rubble and hazardous waste and storage of waste on site.
1. Sufficient waste bins shall be provided on site to
encourage waste separation and for recycling
purposes.
2. Refuse bins shall be placed at strategic
positions to ensure that litter does not
accumulate on site.
3. Construction workers need to be encouraged to
use the waste bins provided at all times, and
littering should be prohibited.
4. Skip waste containers should be kept on site to
dispose of construction rubble. Containers must
be removed when they fill up to maintain a clean
site.
5. Waste disposal certificates need to be obtained
by the Contractor from the waste disposal
facility.
6. Hazardous waste may not be stored on site in
excess of a 90 calendar day period.
Page | 15
6 POST CONSTRUCTION PHASE
TABLE 9: REHABILITATION
PHASE POST CONSTRUCTION CONTRACTOR & ESA DAILY
IMPACT REHABILITATION
(This section deals with the rehabilitation of construction sites)
RESPONSIBILITY FREQUENCY / MONITORING
REQUIREMENTS
MITIGATION STATEMENT
1. The construction site and camp is to be checked for spills of
substances such as oil, paint, etc, and these shall be cleaned up.
2. Surfaces are to be checked for waste products from activities such
as concreting and cleared accordingly.
3. All construction waste and rubble is to be removed from the site
and disposed of to the landfill site.
4. The site is to be cleared of all litter.
5. Fences, barriers and demarcations associated with the
construction footprint are to be removed from the site.
Page | 16
7 OPERATIONAL PHASE TABLE 10: OPERATIONAL
PHASE OPERATIONAL PHASE PLANT MANAGER ANNUALLY /CONTINUOUSLY
IMPACT AIR QUALITY EMISSIONS , ENERGY CONSUMPTION AND
SAVINGS
(This section deals with the air quality impacts, energy consumption
and savings at the HCBP)
RESPONSIBILITY FREQUENCY / MONITORING
REQUIREMENTS
MITIGATION
STATEMENT
1. HCBP will need to comply with the conditions that will be set by the
Municipal Council for Air Emissions and conditions of the
AEL/APPA certificate applicable at the time.