September 23, 2013
2019 District Wide Renovations Schematic Design PresentationBeacon City School District March 19, 2018R H I N E B E C K A R C H I T E C T U R E 1
Schematic Design Presentation
Project Scope By BuildingClassroom ImprovementsSports ImprovementsSite ImprovementsAccessibility ImprovementsLife Safety ImprovementsFacilities Improvements
Project Budget
Project Schedule
Next Steps
September 23, 2013
2019 District Wide Renovations Schematic Design PresentationBeacon City School District March 19, 2018R H I N E B E C K A R C H I T E C T U R E 2
District Wide Scope of Work
September 23, 2013
2019 District Wide Renovations Schematic Design PresentationBeacon City School District March 19, 2018R H I N E B E C K A R C H I T E C T U R E 3
Beacon High School Site Plan: New Artificial Turf Field
BEACON HIGH SCHOOL
September 23, 2013
2019 District Wide Renovations Schematic Design PresentationBeacon City School District March 19, 2018R H I N E B E C K A R C H I T E C T U R E 4
Beacon High School Floor Plan
Improve Pool Locker RoomsNew Pool Score Board
Improve Areas of Refuge at 2nd Floor
Improve Areas of Refuge at 2nd Floor
Repoint Exterior Masonry
Repoint Exterior Masonry
September 23, 2013
2019 District Wide Renovations Schematic Design PresentationBeacon City School District March 19, 2018R H I N E B E C K A R C H I T E C T U R E 5
Beacon High School Roof Plan
Replace Roofing at Selected Areas
New RoofNew Roof
New Roof
September 23, 2013
2019 District Wide Renovations Schematic Design PresentationBeacon City School District March 19, 2018R H I N E B E C K A R C H I T E C T U R E 6
Rombout Middle School 1st Floor Plan
Replace Doors
`
Home & Careers Classroom
Air Conditioning at B WingStair Rails
New Classrooms
Stair RailsAnd Smoke Doors
Replace Doors
Replace Doors
Stair RailsAnd Smoke Doors
Replace Wheelchair Lift
Improve Bus Drop off Area
September 23, 2013
2019 District Wide Renovations Schematic Design PresentationBeacon City School District March 19, 2018R H I N E B E C K A R C H I T E C T U R E 7
Rombout Middle School Classroom Improvements
New Science Classroom 1,235 sf 24 Lab Stations
Res.Rm.165 sf
Maker SpaceClassroom
740 sf
Assisted Daily Living Classroom
720 sf
Partial Floor Plan B Wing: New Classrooms
Home & Careers5 Kitchen Stations
Stor.165 sf
Corridor
Partial Floor Plan AWing
Res.Rm.165 sf
September 23, 2013
2019 District Wide Renovations Schematic Design PresentationBeacon City School District March 19, 2018R H I N E B E C K A R C H I T E C T U R E 8
Rombout Middle School 2nd Floor Plan
ADA Toilet Rooms
Air Conditioning at B Wing Second Floor
Areas of RefugeSmoke Doors
Area of RefugeADA Toilet RoomsStair Rails
Air Conditioning at D WingSecond Floor
September 23, 2013
2019 District Wide Renovations Schematic Design PresentationBeacon City School District March 19, 2018R H I N E B E C K A R C H I T E C T U R E 9
Rombout Middle School Roof Plan
Replace Roofing at Selected Areas
New Roof
New Roof
New Roof
New Roof
September 23, 2013
2019 District Wide Renovations Schematic Design PresentationBeacon City School District March 19, 2018R H I N E B E C K A R C H I T E C T U R E 10
Rombout Middle School Site Plan
ROMBOUT MIDDLE SCHOOL
September 23, 2013
2019 District Wide Renovations Schematic Design PresentationBeacon City School District March 19, 2018R H I N E B E C K A R C H I T E C T U R E 11
Replace Kindergarten Toilet Partitions
Replace DoorsAnd Ceiling
Replace Rooftop HV Units
New Smoke Doors
Replace CeilingReplace VAT in 3 Rooms
Replace Doors
J. V. Forrestal Elementary School Floor Plans
First Floor Plan
Lower Level Floor Plan
Gym
Caf.
September 23, 2013
2019 District Wide Renovations Schematic Design PresentationBeacon City School District March 19, 2018R H I N E B E C K A R C H I T E C T U R E 12
Glenham Elementary School Floor Plan
New Stair and Rail
Replace Classroom Carpeting with VCT
Regrade Paving at two Catch Basins in Parking Area
Replace Exterior Doors
New 2nd Exit Door
Gym
Cafeteria
Office
September 23, 2013
2019 District Wide Renovations Schematic Design PresentationBeacon City School District March 19, 2018R H I N E B E C K A R C H I T E C T U R E 13
Sargent Elementary School
First Floor Plan
Replace Classroom Carpeting with VCT
Second Floor Plan
ADA Toilet Rooms
New Smoke Doors and Stair Rails
Masonry Repairs over Windows at 2nd Floor
New Smoke Doors and Stair Rails
ADA Toilet RoomsReplace Ext. Doors Replace Ext. Doors
All Floors: Replace Unit Ventilators
Aud.
Lower LevelFloor Plan
Replace Ceiling
ADA Toilet Rooms
Gym
All Purpose Room
Library
Replace Kitchen Make Up Air Unit
September 23, 2013
2019 District Wide Renovations Schematic Design PresentationBeacon City School District March 19, 2018R H I N E B E C K A R C H I T E C T U R E 14
South Avenue Elementary School
Lower LevelFloor Plan
Second Floor Plan
First Floor Plan
Library
Fac.Rm.
New Rails at Stair
AllPurpose Room
Repoint Exterior Brick
Repoint Exterior Brick
Area of RefugeSmoke Doors
Replace Deteriorated Concrete
Replace Exit Window
New Rails at Gym Stairs
All Floors: Replace Unit VentilatorsReplace VAT in Closets
Improve Ventilation in Kitchen and Selected Rooms
`
Kitchen`
September 23, 2013
2019 District Wide Renovations Schematic Design PresentationBeacon City School District March 19, 2018R H I N E B E C K A R C H I T E C T U R E
Project Budget
15
BuildingConstruction
Budget20% Incidental
Budget TotalBeacon High School $3,456,600 $691,320 $4,147,920Rombout Middle School $2,221,000 $444,000 $2,665,000James V. Forestall ES $128,000 $25,600 $153,600Glenham ES $99,000 $19,800 $118,800Sargent ES $996,400 $199,280 $1,195,680South Avenue ES $595,000 $119,000 $714,000Bus Maintenance Bldg. $0 $0 $0Bus Garage $0 $0 $0Rosenmeier Field House $0 $0 $0Hammond Field House $0 $0 $0Press Box $0 $0 $0
Totals $7,496,000 $1,499,000 $8,995,000
September 23, 2013
2019 District Wide Renovations Schematic Design PresentationBeacon City School District March 19, 2018R H I N E B E C K A R C H I T E C T U R E 16
Capital Project Schedule
Key:
A/E Activity Client Review Client Approval Cost Estimate$
20182017 2019
Task
Determine Scope of Project
BOE SEQRA Review
Public Information & Referendum
Public Vote: December 5
Design
Construction Documents
SED Review
Bid & Award
Construction
BOE Schedules Vote
$
$
$
$
$
$
NYSED Review
♦ Schematic Design Phase 3/14/18♦ Design Development Phase 5/16/18♦ Construction Documents July 2018♦ NYSED Review Complete by December 2018♦ Bid & Award January‐February 2019♦ Construction Starts May 2019
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
September 23, 2013
2019 District Wide Renovations Schematic Design PresentationBeacon City School District March 19, 2018R H I N E B E C K A R C H I T E C T U R E 17
Next Steps
Accept Schematic Design Documents
Authorize Start of Design Development Phase
Engage the Construction Manager for Pre‐Construction Services for Cost Estimates and Constructability Reviews
Questions or Comments?