Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
March 2015
1
Screening of drafts of the second River Basin Management Plans for evidence of action on Commission's recommendations for improvements in Member States’ implementation of the WFD
Member State: France (FR)
Disclaimer The views expressed are purely those of the assessors and may not in any circumstances be
regarded as stating an official position of the European Commission
March 2015
2
1. River Basin District: Artois Picardie
1.1 Headlines
The following passage summarises the main changes made in the draft second RBMP compared to the first RBMPs, for example, as
required in annex VII B.
There is no summary list given. In terms of the general approach of the River Basin Management Plan (RBMP), 3 stages are
explained in the development of the 2nd
RBMP:
1. Identification of the important questions to which the RBMP will need to respond
2. Overview of the status and where we are in the Programme of Measures (PoM) implementation (based on the earlier mid-term
review)
3. Elaboration of the RBMP and the PoMs
This resulted in a list of fundamental orientations and their dispositions (provisions), where more detail is given on the issue and scale
of the problem, how this relates to the assessment and significance of the pressure and the established measures.
Regarding classification issues, France will use other indicators to show progress and will take into account uncertainties in biological
assessment methods.
In the 2nd
RBMP, for rivers and lakes, France is considering using new assessment methods for benthic fauna, fish fauna and
macrophytes in order to better capture various pressures like morphology degradation.
For coastal waters: methods are developed but they have to be completed and intercalibrated.
March 2015
3
Waters in overseas areas are more difficult to assess. Having re-analysed the ecological status of the water bodies, it will be possible
to estimate the number that will achieve „good‟ status in 2015, 2021 and 2027, after validation from the Schema Directeur
d‟Aménagement et de Gestion des Eaux (SDAGE) Project River Basin Committees, which was scheduled for September 2014.
Revision of the surface freshwater monitoring network is under way to integrate the networks of the Nitrates Directive and the WFD (in
France, the Surveillance Control Network or the Operational Control Network), in order to optimise monitoring over time (at the
frequency defined in the WFD, rather than once every four years, as recommended by the Nitrates Directive), which will allow for
better assessment of trends in the level of nitrates.
River Basin Specific Pollutants (RBSP) were selected at basin scale and nine RBSP at national scale (continental France). The list of
RBSP will be revised for the 2nd
cycle.
Heavily Modified Water Bodies (HMWB) and Artificial Water Bodies (AWB) will be reviewed: their designation as modified / artificial
bodies will be reassessed and the 1st cycle non-designated HMWB will be compared to neighbouring Member States (MS). As new
analysis will be performed on small Water Bodies (WB), new HMWB are expected. Besides, changes in Biological Quality Elements
(BQEs) parameters will imply some changes in designation of AWB and HMWB.
For the 2nd
cycle, the methodology for justification of exemptions will be consolidated. Therefore, a guide for the 2nd
cycle is being
finalised. France is expecting more deadline extensions (more measures needed, natural conditions-).
Regarding the article 9 of the Directive (recovery of costs for water services), a harmonised analysis will be set up as a national study.
For ground water status assessment, a new method will be used to assess the balance between groundwater abstraction and
recharge. Furthermore, there will be a national methodology for trend assessment and reversal established and applied in the 2nd
cycle. Eventually, a National guidance document about groundwater threshold values (TVs) was finalised in October 2012. There will
be more TVs established in the 2nd
cycle than in the first: not only TVs based on risks will be considered.
Regarding the PoM, a new national Methodological Guide on these is being finalised.
March 2015
4
For measures related to hydromorphology, there will be new legislation to give new legal competence on river management at a local
level (if voted for by parliament), for better implementation of measures. Mandatory works for river continuity restoration will also be
imposed. The mandatory minimum ecological flow will be increased by 2014.
For industries, results of extensive discharge monitoring of substances allowing better pressure identification and measures will be
used.
For Agriculture, new mandatory measures will concern abstraction measures (modification in water abstraction authorisation, set up
of collective management of water abstraction for irrigation (Organisme unique de gestion collective des prélèvements d'eau pour
l'irrigation: OUGC)) and taxation (gradual increasing of fees related to pesticides, new tax on nitrates). Regarding voluntary measures,
articles 29 and 38 of the RDP will be used. The agro-industry will be involved.
In cases where the expectations of the first plan have not been achieved or are not expected to be achieved, there is a description of what
expectations have not been achieved and an explanation of why not.
For groundwater, 2011 quantitative status is in line with expectations (2015 objectives) of the RBMP 2010-2015. The chemical status
changed little.
The objectives for surface water bodies have not been achieved yet. Given the gap between the current state (2011-2012) and 2015 targets,
objectives may not be attained. The media reacts slower than expected to measures implemented. In addition, changes in the monitoring
program has led to additional difficulties to achieve good status (for example the assessment of fish index downgraded water bodies status).
Some measures were not implemented as far as expected. Different causes have been highlighted in the background document.
Due to the economic crisis, resources for the implementation of measures were more limited than expected in the first RBMP.
Regarding the hydromorphological restoration of watercourses, two difficulties have been under estimated in the first cycle. First, the
technical complexity of works, secondly, the legal difficulties to intervene on a private property. Furthermore, there was a lack of
acceptability of these actions.
March 2015
5
Measures addressing agricultural diffuse pollution were not fully implemented. One cause is the uncertainty related to the agri-
environmental measures (MAE). Farmers sign a 5 years contract without knowing if the aid will be renewed afterwards. Furthermore,
financial compensations are considered insufficient and do not cover all the investment and loss of productivity induced by the MAE.
Besides, these compensations are not modulated according to the variation of agricultural prices.
The MAE are not flexible enough to allow a sector based approach. For example, the organic farming sector is not well organised
(procurement and retail).
There is a fear that the administrative requirements related to MAE are burdensome
It is not always proven or clear that MAE are leading to a better environmental efficiency. Furthermore, due to the necessary delay in
response in the environment, especially for groundwater, actions are not leading to rapid tangible results.
1.2 Screening of progress on recommendations made in the Commission Staff Working Document (2015)
For each of the recommendations made in the Commission Staff Working Document (CSWD), which was published in March 2015, Table 2
shows:
A baseline against which to assess progress, and the actions required to solve the issue and fully address the recommendation;
An evaluation (key provided in Table 1); and
Justification for the evaluation of progress.
Table 1 Description of the evaluation criteria used in the screening of progress
Evaluation Description
Strong evidence that actions taken are likely to address the COM recommendation.
All the actions relating to the recommendation have clearly been taken in the second plans. The
March 2015
6
actions are defined in relation to the “baseline” situation in the first RBMPs.
Evidence found that good progress has/is being made
There has been good progress on the actions associated with the recommendation but not all
actions have been taken, some may be on-going with a clear timetable which will solve issues in a
reasonable timeframe (1 year for simple things, 2-3 years for more complex issues).
Some evidence of progress.
Some (but not all) of the actions proposed in the recommendations are mentioned and described
but not in enough detail to be certain that they have been fully taken. Some of the actions required
by the recommendation may not have been taken or mentioned at all.
?
No information could be found on the actions associated with the recommendation.
There is no information in the plan that any of the actions associated with the recommendation have
been considered or taken. The justification must describe the documents that have been screened.
No progress, or implementation of the WFD has worsened
The same inadequate processes, approaches and/or methods used in the first plan have been
reported in the second plan, and/or implementation has worsened in relation to the subject of the
recommendation.
Table 2 Assessment of progress on recommendations made in the CSWD (2015)
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
Improve knowledge about the link
between pressures and impacts in
designing and making operational the
measures for the second cycle, in order
to:
1. Refine the significance of the
pressures by quantifying those
which are likely to prevent the
For the first cycle, the link between the status
and the measures was generally unclear.
The measures were planned but there was no
assessment or judgment as to how much the
measures would contribute to the
achievement of WFD objectives.
The main sectors responsible for the different
type of pressures have been identified in all
For item (1):
A new assessment method has been used to
evaluate the risk of not achieving the WFD
objectives. For each water body, the causes
of risk of failure were identified (e.g. risk of
failing good ecological status due to
hydromorphological pressures / water
treatment / industrial pressures / agricultural
March 2015
7
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
achievement of environmental
objectives
2. Assess the reduction in pressures
required to achieve the
environmental objectives
3. Apportion pressures by their
sources and identify the
responsible sectors/areas.
RBMPs. However, for most of the RBDs, there
is no clear explanation or definition on point
sources, diffuse sources and other pressures.
Fully meeting this recommendation would
mean that the gap that needs be filled for the
achievement of WFD objectives is quantified
in terms of the reductions needed in the
pressures causing water bodies to be failing,
or being at risk of failing, objectives.
Quantification of reductions in pressure
may be in terms of:
• loads of pollutants/contaminants to be
reduced;
• number of barriers to continuity to be
removed or adapted;
• length/area of water bodies to be remediated
or restored;
• volume of abstracted water to be reduced.
It should be clearly described how a source
apportionment has been undertaken that
gives a clear picture of the most important
sources for all identified significant
pressures or impacts. In this context a
source might be considered as a combination
of a pressure type (e.g. diffuse or point source
pressures).
For item (2):
There is no information on whether the
reduction in pressures required to achieve the
environmental objectives has been quantified
or not.
For item (3):
From the summary of the characterisation
document reported in the background
document, one can say that a quantitative
apportionment of each pressure by its source
has been carried out in the form of flow
diagrams for :
Macro-pollutants: loads of organic matter,
nitrogen, phosphorus in kT/year from each
contributory source are given (e.g. for
industry – discharge from connected
industries or industry – discharge from non-
connected industries);
Volume of water being abstracted and
consumed by each sector (industrial,
domestic, agricultural).
For chemical substances, the methodology
March 2015
8
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
pollution) with the responsible sector or driver
(e.g. diffuse – agriculture, diffuse – forestry).
used to assess the pressure is explained but
there is no result available. It seems that the
flow of pesticides and other micro-pollutants
have been quantified.
However, the sources generating
hydromorphological alterations have been
identified (qualitative) but not apportioned in a
quantitative way.
Different models have been used for the
source apportionment:
NOPOLU for calculating nutrient surpluses
from agricultural origin.
SYRAH for hydromorphological
assessment.
A model from INRA for agricultural
phosphorus.
Mercat‟eau and ARPEGES for agricultural
pesticides.
Enhance measures to tackle pollution
by nutrients (nitrogen and phosphorus),
considering their impact on ecological
status. Full consideration of the basin-
wide impact is needed in this respect
No clear baseline was found in the bilateral
meeting or in the 2012 MS Summary.
One orientation of the RBMP, named “A-3
Reduce pressure from agricultural nitrogen on
the whole territory”, contributes to the
achievement of objectives for groundwater
and transitional water.
March 2015
9
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
(local and downstream up to transitional
and coastal waters).
In addition, it is stated that a full consideration
of the basin wide impact has been taken into
account in the definition of vulnerable zones.
The following measures are addressing
pollution by nutrients:
ND national action programme (came into
force in 2013) completed by regional action
programme in mid-2014;
Fertilisation management outside of Nitrate
Vulnerable Zones (NVZ) areas;
Use of alternative practices to plant
protection products;
Promoting sustainable practices (organic
farming, grassland);
Action plan for priority catchments;
Erosion control measures.
Check that their nutrient standards are
consistent with biological requirements
for the achievement of good status and
provide a more coherent strategy
encompassing WFD with:
In the first RBMPs, it was unclear what the full
range of measures were and more importantly
how far these measures would go in
addressing agriculture's impact on water. For
the Commission, France should make this
In the RBMP, there is a reference to the
national nitrates action programme and to the
regional nitrates action programmes both
implemented under the ND. Regional action
programmes include reinforced or additional
March 2015
10
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
The Nitrates Directive (ND) and
Common Agricultural Policy (CAP) in
agriculture
much more transparent in the preparation of
the second RBMP. A coherent strategy for
agricultural action is needed encompassing
ND, WFD and CAP measures.
measures to control nitrate pollution in critical
zones (reinforced actions areas).
In the RBMP, under the orientation “Reduce
pressure from agricultural nitrogen on the
whole territory”, the disposition A-3.2 is called
“make consistent the vulnerable areas with
the RBMP‟s objectives”.
The ND and the CAP are both mentioned as
part of the basic measures (defined at
national level), and specific measures are
listed.
One of those is the conditionality of “support
by the Politique Agricole Commune” based
amongst others on the respect of the action
programme under the ND.
Check that their nutrient standards are
consistent with biological requirements
for the achievement of good status and
provide a more coherent strategy
encompassing WFD with:
The Urban Waste Water Treatment
Directive (UWWTD) in urban areas
No clear baseline was found in the bilateral
meeting or in the 2012 MS Summary.
For the 1st cycle, basic measures under
UWWTD were reported to be not enough for 8
RBDs due to point source pressure.
The UWWTD is mentioned as part of the
basic measures.
The UWWTD in urban areas was transposed
into French law. For sensitive areas,
requirements are defined on a best effort
basis and not on results. There is no evidence
that basic measures taken under the UWWT
Directive are sufficient to achieve good
ecological status.
In the Scheldt and Somme RBMP, the
Orientation A-1 “Continue to reduce point
source discharge of classic pollutants” makes
March 2015
11
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
reference to the UWWTD. The disposition A-
1.1 foresees that any project leader has to
adjust the waste water discharge of his
installation/activities subject to authorisation to
meeting the objective of good status (non-
deterioration of water quality and physico-
chemicals objectives).
There is no specific information on standards.
In particular, it is expected that RBMPs,
based on the necessary reduction in
nutrient load, clearly identify the extent
to which the measures already taken
under the implementation of ND and
UWWTD contribute to the achievement
of WFD objectives and which additional
measures should be taken to actually
achieve these objectives. A clear
identification of basic (mandatory)
measures is expected to be made
transparent both to the sectors and the
general public.
The ND and the UWWTD were implemented
in the national legislation across all 13 RBDs,
including overseas territories.
In the first RBMP‟s, there is no indication (as
there is no specific information available) on
the effectiveness of the measures included in
the ND, and of any of the additional measures
implemented.
It must be clear that the effectiveness of
measures taken under the ND or UWWTD
have been reviewed since the first plan. It
must be explicitly described how the
measures taken under the ND are expected to
contribute to the achievement of WFD
objectives (i.e. how much of the gap they will
fill) and also those relating to the UWWTD.
See above, this is included in the overall table
of basic measures.
There is no explanation on the effectiveness
of measures taken under the ND and
UWWTD.
Regarding the ND, the following
supplementary measure is defined:
Limit agricultural inputs, transfers and
erosion beyond the requirements of the ND
(implementation of measures preventing
erosion and pollutants transfers: hedges,
land cover in winter outside vulnerable
zones, etc.)
Review the regulation of the use of
pesticides in order to effectively reduce
current levels of contamination of rivers
For the first cycle, basic measure in the PoM
referred to the regulation on pesticides put on
the market (Decree of the 12 September
?
The RBMP, the PoM and the background
document were consulted.
There is no reference to the Directive itself but
March 2015
12
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
and groundwater, making clear linkages
with the implementation of the Directive
on the Sustainable Use of Pesticides.
2006). However, some more measures are
implemented within the context of the
Ecophyto plan which started in 2009.
to the regulation on the use of pesticides
(Decree of the 12 September 2006).
In the RBMP, Ecophyto plan (“Disposition A-
11.5”) is indicated as one of the main plans
that will help to reduce diffuse pollution.
Other supplementary measures defined at
RBD or sub-basin level are addressing the
use of pesticides:
Reduce agricultural pesticides and / or use
alternative practices than phytosanitary
treatment.
Implement sustainable practices
(grasslands, organic, etc.).
However, these measures do not concern the
regulation of the use of pesticides.
The conditionality of the assistance by the
CAP is also mentioned.
Define measures targeted to agriculture
at an appropriate level of detail to
ensure their uptake by farmers and
their inspection by relevant agencies.
In the 1st plans, there was no detailed
information on the different stakeholders
involved in the preparation of the measures
for agriculture and the extent of their
contributions (even if the farming sector were
consulted). Regarding the control of
implementation of the agricultural measures,
in most RBMP‟s it was mentioned that a
A specific program was put in place in the
basin Artois-Picardie: “Programme Water and
Agriculture”. The goal is to protect water
resources by encouraging farmers to
consume less pesticides and nitrogenous
fertilisers. For the period 2010-2011, 12 M€
were allocated to 605 farms.
In addition, technical support and additional
March 2015
13
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
control mechanism was in place or would be
further developed, but no further details were
provided.
communication tools are being developed.
Conditionality of the assistance by the CAP is
also mentioned.
The RBMPs are expected to make a
clear distinction between mandatory
measures and voluntary ones that will
be funded under the European
Agricultural Fund for Rural
Development (EAFRD).
For the first cycle, some voluntary measures
were based on actions under the EAFRD.
In the RBMP, the only reference to voluntary
measures is related to the voluntary schemes
implemented in Areas with Environmental
Restrictions (AER). Even if it concerns a
voluntary action programme, this programme
can become compulsory if the expected
results are not reached.
Reference to the EARDF is made in the
impact assessment study.
There is no distinction in the PoM between
mandatory measures and voluntary ones.
Ensure that ecological flow is
considered wherever existing and
planned abstractions may jeopardise
the achievement of environmental
objectives. This is particularly crucial
when considering the review of water
allocations and permits and the
construction of new dams and
reservoirs.
An important issue that was not clearly
defined in the first plan was the ecologically
based flow regime. The flow regime and
authorisation was considered as a measure to
tackle the overexploitation of groundwater but
not to ensure a sufficient ecological flow.
As part of the basic measures, the
Environmental code Article L.214-18
addresses this issue. When the administrative
authority shall issue an authorisation or
concession (even for existing construction
from 01/01/14), it is required to set a minimum
flow downstream of the works that must
contribute to the environmental objectives of
the rivers and take into account the ecological
characteristics and the biological quality of
rivers.
Ensure that the RBMPs clearly identify
the gap to good status, and that the
There was no information in the 1st plans on
how the gap required to meet WFD objectives ?
The RBMP, the PoM and the background
March 2015
14
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
PoMs are designed and implemented to
close that gap.
had been quantified in terms of the required
reduction of pressures and the respective
contribution to the pressures from the
responsible sectors/activities. There was also
no information on how much of the gaps were
expected to be filled by the different
measures.
document were consulted.
There is no information on whether the
reduction in pressures required to achieve the
environmental objectives has been quantified
or not. There is no information on how much
of the gaps are expected to be filled by the
different measures.
The plan is developed in the form of a series
of orientations with different specific
objectives for each orientation, from which
measures are set out.
France is expected to provide a more
consolidated methodology for
justification of exemptions to the
achievement of environmental
objectives (in particular as regards the
assessment of affordability and
disproportionate costs).
In the 1st RBMP‟s, there were a relatively high
number of exemptions under Article 4(4) and
4(5) based on disproportionate costs, for
which there was no clear justification (even if
the national guidelines on exemptions
mentioned that alternative financing has to be
sought).
It has to be clear in the 2nd
plan that a
consolidated methodology has been set for
justification of exemptions (which included
harmonised analysis from a national study).
The methodology to assess the costs and
search for funding should be detailed.
?
The RBMP, the PoM and the background
document were consulted.
There is no clear mention to the methodology
used for justification of exemptions to the
achievement of environmental objectives.
The disposition E-5.1 “develop economic
decision aid tools” foresees the development
of an economic analysis and environmental
benefit assessment to help defining works
programmes and contractual funding.
There is one specific paragraph on projects
for which an Art 4.7 exemption needs to be
requested.
An exemption under the article 4.7 is required
for 2 projects (Canal Seine-Nord Europe and
Harbour of Calais 2015).
March 2015
15
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
Provide a more complete definition of
water services and a proper recovery of
cost to contribute to the objectives,
especially when fully accounting for
environmental and resource costs for
services creating a pressure on water
bodies.
For the 1st cycle, water services have been
interpreted differently across the French
RBDs. Some RBDs had a broad approach,
which took into account all possible
abstraction, storage, treatment, impoundment,
etc. In other RBDs, the approach had been
narrower, taking into account public and
private water abstraction and wastewater
treatment for all sectors, as well as irrigation.
Finally, in some RBDs, the approach had
been even more limited, taking into account
only abstraction and wastewater treatment for
households, industry and abstraction for
agriculture.
There is a specific chapter on water pricing
and cost recovery in the background
document.
A distinction is made between water use and
water services:
Water use includes water intakes,
discharges and all activities which have an
impact on water.
Water services include infrastructures for
water storage, surface or groundwater
abstraction, treatment and distribution,
sewage collection and wastewater
treatment.
The way that the recovery of costs is
established is defined on a case by case
basis.
The recovery of cost is calculated but it is not
clear to what extent environmental costs are
included.
A brief case study is presented, as an
example: pricing system in progressive bands
based on water consumption in Dunkerque.
Consider restoration measures as well Those measures were not explicitly described Five main focuses have been defined in the
March 2015
16
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
as the use of green infrastructure
and/or natural water retention
measures that provide a range of
environmental (improvements in water
quality, flood protection, habitat
conservation etc.), social and economic
benefits which can be in many cases
more cost-effective than grey
infrastructure.
in the first plan. The development of the
second RBMPs should be coordinated with
the development of flood risk management
plans and the use of this type of measure is
seen as a win-win situation in achieving the
objectives of both plans.
Scheldt and Somme RBMP. One of them is
defined as the following “rely on the natural
functioning of the environment to prevent and
limit the negative effects of floods”.
Several “key directives” are then defined. Two
of them are:
Orientation C-3: Give priority to a natural
functioning of the watersheds.
Orientation C-4: Preserve and restore the
natural dynamic of watercourses
In addition, one of the two measures against
the flood focus considers the development of
expanding flood areas.
However, there is no mention of a specific
process leading to alternative solution to a
grey infrastructure.
March 2015
17
1.3 Water services excluded from the requirement of WFD Article 9 “Recovery of costs for water services”
Table 3 Water services explicitly included in/excluded from cost recovery and Article 9.4 exemptions applied
Water service
Explicitly included in cost recovery
(yes/no/no information/not
clear)
Explicitly excluded from cost recovery
(yes/no/no information/not
clear)
Article 9.4 exemptions
applied (yes/no/no
information/not clear)
Drinking water abstraction (surface and/or groundwater), treatment and distribution
Yes No information
Sewage collection and wastewater treatment Yes No information
Drinking water abstraction (surface and/or groundwater), treatment and distribution AND sewage collection and wastewater treatment (when considered together)
Yes No information
Irrigation water abstraction, treatment and distribution Yes No information
Self-abstraction Yes No information
Impoundment and storage of water Yes No information
Impoundment for flood protection No No information
Impoundment for navigation No No information
Other (please describe in text box below) Yes No information
March 2015
18
2. River Basin District: Loire
2.1 Headlines
The following passage summarises the main changes made in the draft second RBMP compared to the first RBMPs, for example, as
required in annex VII B.
There is no summary list given.
There are three stages that are explained in the development of the 2nd
River Basin Management Plan (RBMP),:
1. identification of the important questions to which the RBMP will need to respond
2. overview of the status and where we are in the Programme of Measures (PoM) implementation (based on the earlier mid-term
review)
3. elaboration of the RBMP and the PoMs
This resulted in a list of fundamental orientations and their dispositions (provisions), where more detail is given on the issue and scale
of the problem, how this relates to the assessment and significance of the pressure and the established measures.
Further on, climate change adaptation is taken into account.
Regarding classification issues, France will use other indicators to show progress and will take into account uncertainties in biological
assessment methods.
In the 2nd
RBMP, for rivers and lakes, France is considering using new assessment methods for benthic fauna, fish fauna and
macrophytes in order to better capture various pressures like morphology degradation.
March 2015
19
For coastal waters: methods are developed but they have to be completed and intercalibrated.
Revision of the surface freshwater monitoring network is under way to integrate the networks of the Nitrates Directive (ND) and the
WFD (in France, the Surveillance Control Network or the Operational Control Network), in order to optimise monitoring over time (at
the frequency defined in the WFD rather than once every four years, as recommended by the Nitrates Directive), which will allow for
better assessment of trends in the level of nitrates.
River Basin Specific Pollutants (RBSP) were selected at basin scale and 9 RBSP at national scale (continental France). The list of
RBSP will be revised for the 2nd
cycle.
Heavily Modified Water Bodies (HMWB) and Artificial Water Bodies (AWB) will be reviewed: their designation as modified / artificial
bodies will be reassessed and the 1st cycle non-designated HMWB will be compared to neighbouring Member States (MS). As new
analysis will be performed on small Water Bodies (WB), new HMWB are expected. Besides, changes in Biological Quality Elements
(BQEs) parameters will imply some changes in designation of AWB and HMWB.
For the 2nd
cycle, the methodology for justification of exemptions will be consolidated. Therefore, a guide for the 2nd
cycle is being
finalised. France is expecting more deadline extensions (more measures needed, natural conditions).
Regarding the article 9 of the Directive (recovery of costs for water services), a harmonised analysis will be set up as a national
study.
For ground water status assessment, a new method will be used to assess the balance between groundwater abstraction and
recharge. Furthermore, there will be a national methodology for trend assessment and reversal established and applied in the 2nd
cycle. Eventually, a National guidance document about groundwater threshold values (TVs) was finalised in October 2012. There will
be more TVs established in the 2nd
cycle than in the first: not only TVs based on risks will be considered
Regarding the PoM, a new national Methodological Guide on these is being finalised.
March 2015
20
In cases where the expectations of the first plan have not been achieved or are not expected to be achieved, there is a description of what
expectations have not been achieved and an explanation of why not.
In 2011, 31% of surface WB (rivers, lakes, estuaries and coastal waters) are in good ecological status. Over the last five years (2007
to 2011), the ecological status remained broadly stable for two main reasons:
1. Ecological status summarises a set of quality elements (invertebrates, fish, physical chemistry, etc.) and parameters
(phosphorus, organic matter, nitrates, etc). If even one of these quality constituent elements is measured in a state of "less than
good" then the whole ecological status is classified as "less than good". Thus, good ecological status can only improve when
actions are carried out and have effect on all elements/parameters.
2. The implementation of the actions in the PoM 2010-2015 have been delayed, including operations associated with the two
major issues of the basin that are: improving morphology of rivers and reducing agricultural pollution. Barriers to
implementation may have been undervalued: stakeholders, technical difficulties in the design and implementation of the work,
lack of visibility in terms of sustainability and the efficiency of the agri-environmental measures on the levels of quality
parameters measured in WB.
Therefore, the achievement of the objective in 2015 to reach good ecological status for 39% of the water bodies, as was set in the
2010-2015 Sdage (RBMP) seems difficult.
The following interpretation is given in the RBMP: This negative finding, however, needs a careful interpretation and it actually hides
the progress made since the validation of Sdage 2010- 2015: the ecological status changes little because all the component
indicators do not all move simultaneously.
However, significant progress can be demonstrated when the analysis on the elements of quality or settings are examined
individually.
For example, in river quality, improvements are noted on the parameters "Total phosphorus" and "organic matter". They are
linked to the continuation of efforts undertaken on treatment and collection of urban and industrial wastewater. In the interim
March 2015
21
PoMs 2010-2015 established in late 2013, the large majority of actions planned in relation to sanitation were already scheduled
or implemented.
The evolution of the chemical status of groundwater is another interesting figure: 10% of ground water bodies (GWB) are
classified as good status due to the reduction in nitrates and pesticides loadings. This improvement is to the credit of the
application of regulatory measures.
On the difficulties of implementing actions to improve the morphology and reduce diffuse pollution, the 10th action
programme of the water agency Loire-Bretagne (2013-2018) includes a number of actions that raise some difficulties observed in the
balance sheet through the 2010-2015 PoM, such as, for example: increased resources for aquatic environments, support for project
leaders of local operations, strengthening project management, individual support for farmers, etc. Nevertheless, it should be stressed
that the interventions of the water agency alone cannot solve all the difficulties of implementing the actions. Improving the status of
water bodies depends also on the orientation of other sectoral policies, which sometimes prioritise mobilising resources to serve
different purposes and even those that are contradictory with the WFD objectives.
In the section on Rethinking the management of watercourses, it is indicated that physical alterations are the main cause of
difficulties for reaching good ecological status for watercourses in 2015. They refer to (1) physical modifications and (2)
modifications to water flow/flow regime. These modifications are related to several activities such as hydro-electricity, agriculture,
navigation, water tourism, gravel extraction, transport infrastructure development, and climate change. Further on, reference is made
to erosion problems.
For that reason, the management plan has four principal orientations:
1. Preventing degradation;
2. Restoration of degrading watercourses;
3. Awareness raising for inhabitants and developers; and,
4. Ensuring better knowledge on the effects of certain actions.
March 2015
22
2.2 Screening of progress on recommendations made in the Commission Staff Working Document (2015)
For each of the recommendations made in the Commission Staff Working Document (CSWD), which was published in March 2015, Table 5
shows:
A baseline against which to assess progress, and the actions required to solve the issue and fully address the recommendation;
An evaluation (key provided in Table 4); and
Justification for the evaluation of progress.
Table 4 Description of the evaluation criteria used in the screening of progress
Evaluation Description
Strong evidence that actions taken are likely to address the COM recommendation.
All the actions relating to the recommendation have clearly been taken in the second plans. The
actions are defined in relation to the “baseline” situation in the first RBMPs.
Evidence found that good progress has/is being made
There has been good progress on the actions associated with the recommendation but not all
actions have been taken, some may be on-going with a clear timetable which will solve issues in a
reasonable timeframe (1 year for simple things, 2-3 years for more complex issues).
Some evidence of progress.
Some (but not all) of the actions proposed in the recommendations are mentioned and described
but not in enough detail to be certain that they have been fully taken. Some of the actions required
by the recommendation may not have been taken or mentioned at all.
?
No information could be found on the actions associated with the recommendation.
There is no information in the plan that any of the actions associated with the recommendation have
been considered or taken. The justification must describe the documents that have been screened.
No progress, or implementation of the WFD has worsened
The same inadequate processes, approaches and/or methods used in the first plan have been
reported in the second plan, and/or implementation has worsened in relation to the subject of the
March 2015
23
recommendation.
Table 5 Assessment of progress on recommendations made in the CSWD (2015)
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
Improve knowledge about the link
between pressures and impacts in
designing and making operational the
measures for the second cycle, in order
to:
1. Refine the significance of the
pressures by quantifying those
which are likely to prevent the
achievement of environmental
objectives.
2. Assess the reduction in
pressures required to achieve
the environmental objectives.
3. Apportion pressures by their
sources and identify the
responsible sectors/areas.
For the first cycle, the link between the status
and the measures was generally unclear.
The measures were planned but there was no
assessment or judgment as to how much the
measures would contribute to the
achievement of WFD objectives.
The main sectors responsible for the different
type of pressures have been identified in all
RBMPs. However, for most of the RBDs, there
is no clear explanation or definition on point
sources, diffuse sources and other pressures.
Fully meeting this recommendation would
mean that the gap that needs be filled for the
achievement of WFD objectives is quantified
in terms of the reductions needed in the
pressures causing water bodies to be failing,
or being at risk of failing, objectives.
Quantification of reductions in pressure
may be in terms of:
loads of pollutants/contaminants to be
reduced;
In the background documentation to the
RBMP (Presentation Synthetique relative a la
gestion de l‟eau du basin), It is indicated that
the analysis of risk is based on improved
methods and elements than the earlier one in
2004.
For item (1):
In 2004, little data were available. Numerous
meetings have been organised with technical
and local partners. With that information, it
could be seen that (1) diffuse pollution of
nitrates, phosphorous and pesticides still
remain a problem and the PoMs need to
prioritise actions in vulnerable zones, such as
drinking water zones where algae blooms still
occur, and combating erosion (phosphorus
fertilisers). Nitrate and phosphorus data are
used. Further on, it is indicated that
morphology still remains an issue (no data are
given). Water abstraction data are used to
identify pressures due to irrigation. For each
GWB, it is identified if it is at risk as a
March 2015
24
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
number of barriers to continuity to be
removed or adapted;
length/area of water bodies to be
remediated or restored;
volume of abstracted water to be
reduced.
It should be clearly described how a source
apportionment has been undertaken that
gives a clear picture of the most important
sources for all identified significant
pressures or impacts. In this context a
source might be considered as a combination
of a pressure type (e.g. diffuse or point source
pollution) with the responsible sector or driver
(e.g. diffuse – agriculture, diffuse – forestry).
qualitative or quantitative assessment and the
specific cause is noted. Similarly for protected
areas the pressures are detailed.
For item (2):
For specific pollutants (chapter 45 of the
RBMP) objectives for reductions of
emissions are given (as % reduction) for
each individual pollutant on the list of specific
pollutants. Similarly, in chapter 2, a reduction
objective has been formulated for nitrate, (with
one value per sub-basin).
For item (3):
Apportion pressures by their sources: have
been carried out per orientation in a
qualitative way but not in a quantitative way,
except for dangerous substances, but there is
still a lot of uncertainty involved.
Enhance measures to tackle pollution
by nutrients (nitrogen and phosphorus),
considering their impact on ecological
status. Full consideration of the basin-
wide impact is needed in this respect
(local and downstream up to transitional
and coastal waters).
No clear baseline was found in the bilateral
meeting or in the 2012 MS Summary.
For the Loire river basin, the domain
“agriculture” comprises actions against
pollution from diffuse origin. This is around
23% of the amount (in euros) of the total PoM
2016-2021. This part of the plan focuses on
measures to reduce diffuse pollution from
nitrogen, phosphorus and pesticides. The link
is made to the water bodies at risk from each
of these pressures. 615 M Euro will be spent.
March 2015
25
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
It is indicated that there is a significant change
in relation to the 2010-2015 programme.
There has been a request from the Ministry of
Ecology for an evaluation of two particular
actions under the establishment of Nitrate
Vulnerable Zones (NVZ), (1) the
establishment of cultivation for trapping
nitrates and (2) grass strips along
watercourses. If these are carried out across
the basin it would correspond to
approximately € 110 million per year. The
other change is that the PoM 2016-2021 are
defined for priority target areas which are the
catchment areas of WB subject to
eutrophication
It is mentioned in the RBMP 2016-2021 that
the framing of the PoM
2010-2015 was more general and applied
certain actions indiscriminately across the
whole territory. For the 2016-2021 plan the
actions appear to be set out in more detail
and are more focused.
It is indicated that a threshold of 11.5 mg/l of
nitrates (annual mean) is needed in order to
have an acceptable level for the coastal
environment. This will need to be taken into
account by all actors and based on that, a
reduction of effluent nitrate load of between
March 2015
26
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
10% and 40% is planned for the Lore sub-
basins.
There is a specific orientation included
which is preserve the coastal area and
reduce significantly the eutrophication in
coastal and transitional waters.
As a summary, one can conclude actions are
more focused towards the area where they
need to be applied, and that it is taken into
account that stricter nutrient standards need
to be applied in order to ensure good status in
the coastal zone.
Check that their nutrient standards are
consistent with biological requirements
for the achievement of good status and
provide a more coherent strategy
encompassing WFD with:
The Nitrates Directive (ND) and
Common Agricultural Policy (CAP) in
agriculture
In the first RBMPs, it was unclear what the full
range of measures were and more importantly
how far these measures would go in
addressing agriculture's impact on water. For
the Commission, France should make this
much more transparent in the preparation of
the second RBMP. A coherent strategy for
agricultural action is needed encompassing
ND, WFD and CAP measures.
No information given. Reference is made to
the national and regional nitrate action
programme.
The RBMP is structured alongside the
pressures, the objectives to be reached and
the need to take action. On the standards etc.,
no specific information is included. The
background documentation gives a synthesis
of the assessment results and the monitoring
programme for the Loire basin. It cannot be
seen that the nutrient standards for the 2nd
RBMP are now more aligned to biological
requirements. A link with the rural
development programme is given when the
financing of the measures is discussed.
March 2015
27
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
In the RBMP, under the orientation “Reduce
pressure from agricultural nitrates on the
whole territory”, the disposition A-3.2 is called
“make consistent the vulnerable areas with
the RBMP‟s objectives.
CAP is also part of the basic measure table.
Check that their nutrient standards are
consistent with biological requirements
for the achievement of good status and
provide a more coherent strategy
encompassing WFD with:
The Urban Waste Water Treatment
Directive (UWWTD) in urban areas
No clear baseline was found in the bilateral
meeting or in the 2012 MS Summary.
For the 1st cycle, basic measures under
UWWTD were reported to be not enough for 8
RBDs due to point source pressure.
No information is given.
On the standards etc., no specific information
is included.
It cannot be seen that nutrient standards for
the 2nd
RBMP are now more aligned to
biological requirements or not.
On the UWWTD measures, no specific
information was found except in the table on
basic measures.
In particular, it is expected that RBMPs,
based on the necessary reduction in
nutrient load, clearly identify the extent
to which the measures already taken
under the implementation of ND and
UWWTD contribute to the achievement
of WFD objectives and which additional
measures should be taken to actually
achieve these objectives. A clear
identification of basic (mandatory)
measures is expected to be made
transparent both to the sectors and the
The ND and the UWWTD were implemented
in the national legislation across all 13 RBDs,
including overseas territories.
In the first RBMP‟s, there is no indication (as
there is no specific information available) on
the effectiveness of the measures included in
the ND, and of any of the additional measures
implemented.
It must be clear that the effectiveness of
measures taken under the ND or UWWTD
have been reviewed since the first plan. It
In relation to the ND and the UWWTD, basic
measures are related to each directive. See
PoMs ANNEXE. Liste des mesures de base
(Guide DCE Programme de mesures – Guide
pour l‟élaboration, la mise en oeuvre et le
suivi du programme de mesures en
application de la directive cadre sur l‟eau) .
No clear distinction between those for the ND
and UWWTD, as for example measures from
ND are also included in the Table with
measures on specific disposition. The
assessment on how the ND and the UWWTD
March 2015
28
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
general public. must be explicitly described how the
measures taken under the ND are expected to
contribute to the achievement of WFD
objectives (i.e. how much of the gap they will
fill) and also those relating to the UWWTD.
contribute to achieving the objectives is not
been made. Furthermore, in the PoM,
measures to reduce nitrate pollution all refer
to the Nitrate Directive (basic measures).
Review the regulation of the use of
pesticides in order to effectively reduce
current levels of contamination of rivers
and groundwater, making clear linkages
with the implementation of the Directive
on the Sustainable Use of Pesticides.
For the first cycle, basic measure in the PoM
referred to the regulation on pesticides put on
the market (Decree of the 12 September
2006). However, some more measures are
implemented within the context of the
Ecophyto plan which started in 2009.
?
The RBMP, the PoM and its accompanying
documents were consulted.
No reference is made to the Directive on the
Sustainable Use of Pesticides.
The only measure related to the regulation of
the use of pesticides (national basic measure)
is the same as in the first cycle (Decree of the
12 September 2006). Reductions on
emissions are detailed for the pesticides
included in the list of specific pollutants.
Define measures targeted to agriculture
at an appropriate level of detail to
ensure their uptake by farmers and
their inspection by relevant agencies.
In the 1st plans, there was no detailed
information on the different stakeholders
involved in the preparation of the measures
for agriculture and the extent of their
contributions (even if the farming sector were
consulted). Regarding the control of
implementation of the agricultural measures,
in most RBMP‟s it was mentioned that a
control mechanism was in place or would be
further developed, but no further details were
provided.
It is indicated in the RBMP that all actions on
nitrate reduction (Nitrate Action Programme)
are reinforced following stipulations in the
code de l‟environnement. It is indicated that
regulatory approaches are mainly possible in
the NVZ that are delineated. It is indicated
that a threshold of 11.5 mg/l of nitrates
(annual mean) is needed in order to have an
acceptable level for the littoral (coastal)
environment. This will need to be taken into
account by all actors and based on that, a
reduction in nitrate load from effluents of
March 2015
29
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
between 10% and 40% is planned for the
Lore sub-basins. Therefore, a link is made
with coastal quality. Further on, there is a
specific chapter on “preserver le littoral” where
the objective is to significantly reduce
eutrophication in coastal and transitional
waters.
Further on, one of the chapters within the
RBMP is on facilitating local governance and
reinforcing the consistency of territories and
public policy. There is also a specific chapter
on mobilising all sectors and making them
aware of the RBMP.
The RBMPs are expected to make a
clear distinction between mandatory
measures and voluntary ones that will
be funded under the European
Agricultural Fund for Rural
Development (EAFRD).
For the first cycle, some voluntary measures
were based on actions under the EAFRD.
In the RBMP, the only reference to voluntary
measures is related to the voluntary schemes
implemented in Areas with Environmental
Restrictions (AER). Even if it concerns a
voluntary action programme, this programme
can become compulsory if the expected
results are not reached.
There is no distinction in the PoM between
mandatory measures and voluntary ones.
Ensure that ecological flow is
considered wherever existing and
planned abstractions may jeopardise
the achievement of environmental
objectives. This is particularly crucial
An important issue that was not clearly
defined in the first plan was the ecologically
based flow regime. The flow regime and
authorisation was considered as a measure to
tackle the overexploitation of groundwater but
In the RBMP there are two actions set out:
(1) To maintain a minimum flow in the river the
administrative authority shall issue an
authorisation or concession and it is required
to set a minimum flow downstream of the
March 2015
30
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
when considering the review of water
allocations and permits and the
construction of new dams and
reservoirs.
not to ensure a sufficient ecological flow. works by taking into account the objective of
achieving good status of rivers, in accordance
with Article L.214- 18 of the Environmental
Code. The aim is to integrate the local and
cumulative impacts of works by ensuring that
there is a consistency of instream flow. In
order to verify the effectiveness of the value
adopted, the administrative authority may
determine, in accordance with Article R.214-
16 of the Environmental Code, the effects of
monitoring on aquatic environments to
monitor the ecological quality of the rivers
concerned. This monitoring can lead to a
readjustment of the minimum flow set to
achieve the objectives of good state;
(2) Reducing the effects of non-natural
variations in aquatic environments. Based on
research/experiments, the administrative
authority may prescribe the requirements
needed to reduce non-natural fluctuations in
flow.
Ensure that the RBMPs clearly identify
the gap to good status, and that the
PoMs are designed and implemented to
close that gap.
There was no information in the 1st plans on
how the gap required to meet WFD objectives
had been quantified in terms of the required
reduction of pressures and the respective
contribution to the pressures from the
responsible sectors/activities. There was also
?
The RBMP, the PoM and its accompanying
documents were consulted.
There is no information on whether the
reduction in pressures required to achieve the
environmental objectives has been quantified
or not (except for specific pollutants where %
March 2015
31
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
no information on how much of the gaps were
expected to be filled by the different
measures.
reduction is specified in order to assess
progress against the objective).
There is no information on how much of the
gaps are expected to be filled by the different
measures.
France is expected to provide a more
consolidated methodology for
justification of exemptions to the
achievement of environmental
objectives (in particular as regards the
assessment of affordability and
disproportionate costs).
In the 1st RBMP‟s, there were a relatively high
number of exemptions under Article 4(4) and
4(5) based on disproportionate costs, for
which there was no clear justification (even if
the national guidelines on exemptions
mentioned that alternative financing has to be
sought).
It has to be clear in the 2nd
plan that a
consolidated methodology has been set for
justification of exemptions (which included
harmonised analysis from a national study).
The methodology to assess the costs and
search for funding should be detailed.
The RBMP, the PoM and its accompanying
documents were consulted.
There is no clear mention of the methodology
used for justification of exemptions to the
achievement of environmental objectives.
In the glossary, two guidance documents
developed in 2013 on methodologies in
relation to justifications of exemptions are
mentioned: Le guide national de décembre
2013 (ministère de l'Ecologie, du
Développement durable et de l‟Énergie
(2013), Guide méthodologique de justification
des dérogations prévues par la directive cadre
sur l'eau, décembre 2013, 40 p.).
On disproportionate costs, there is a specific
section as part of the cost recovery chapter.
There is one specific chapter on projects for
which an Art 4.7 exemption needs to be
requested. There are no projects that fulfil the
criteria in order to require exemption.
Provide a more complete definition of For the 1st cycle, water services have been There is a specific chapter on water pricing
March 2015
32
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
water services and a proper recovery of
cost to contribute to the objectives,
especially when fully accounting for
environmental and resource costs for
services creating a pressure on water
bodies.
interpreted differently across the French RBD.
Some RBDs had a broad approach, which
took into account all possible abstraction,
storage, treatment, impoundment etc. In other
RBDs, the approach had been narrower,
taking into account public and private water
abstraction and wastewater treatment for all
sectors, as well as irrigation. Finally, in some
RBDs, the approach had been even more
limited, taking into account only abstraction
and wastewater treatment for households,
industry and abstraction for agriculture.
and cost recovery in the background
document.
Users and services are defined. It is then (for
each user) defined how much the
recuperation of the costs are established. In
the next period, it is explained that it will be
necessary to develop methods and data for
better determining the environmental cost.
This is not included yet. The analysis will also
look into the aspect of disproportionate cost
when looking into environmental cost.
A brief case study is included on the coastal
environmental and resource cost, but this is
given as an example and is not included as an
actual cost-recovery methodogy.
Consider restoration measures as well
as the use of green infrastructure
and/or natural water retention
measures that provide a range of
environmental (improvements in water
quality, flood protection, habitat
conservation etc.), social and economic
benefits which can be in many cases
more cost-effective than grey
infrastructure.
Those measures were not explicitly described
in the first plan. The development of the
second RBMPs should be coordinated with
the development of flood risk management
plans and the use of this type of measure is
seen as a win-win situation in achieving the
objectives of both plans.
When looking into the measures and the
green infrastructure measures proposed, it
was found that measures are focused on
restoring natural flow and hydromorphological
restoration, restoring ecological connectivity,
management of humid zones, etc. No details
are given, except for the measures regards
riparian forest plantation.
There is no specific information included on
the enhanced use of green infrastructure
instead of the grey infrastructure.
March 2015
33
2.3 Water services excluded from the requirement of WFD Article 9 “Recovery of costs for water services”
Table 6 Water services explicitly included in/excluded from cost recovery and Article 9.4 exemptions applied
Water service
Explicitly included in cost recovery
(yes/no/no information/not
clear)
Explicitly excluded from cost recovery
(yes/no/no information/not
clear)
Article 9.4 exemptions
applied (yes/no/no
information/not clear)
Drinking water abstraction (surface and/or groundwater), treatment and distribution
Yes No information
Sewage collection and wastewater treatment Yes No information
Drinking water abstraction (surface and/or groundwater), treatment and distribution AND sewage collection and wastewater treatment (when considered together)
Yes No information
Irrigation water abstraction, treatment and distribution Yes No information
Self-abstraction Yes No information
Impoundment and storage of water No No information
Impoundment for flood protection No No information
Impoundment for navigation No No information
Other (please describe in text box below) No information
March 2015
34
3. River Basin District: Rhone
3.1 Headlines
The following passage summarises the main changes made in the draft second RBMP compared to the first RBMPs, for example, as
required in annex VII B.
There is no summary list given regarding changes of methodology between the 1s River Basin Management Plan (RBMP), and the
draft 2nd
one.
In the background document, it is stated that the water bodies have been re-defined. The number of groundwater bodies has then
changed from 180 in 2009 to 240 in 2013.
In terms of the general approach of the RBMP, Three stages are explained in the development of the 2nd
RBMP:
1. Identification of the important questions to which the RBMP will need to respond.
2. Overview of the status and where we are in the Programme of Measures (PoM) implementation (based on the earlier mid-term
review).
3. Elaboration of the RBMP and the PoMs.
This resulted in a list of fundamental orientations and their dispositions (provisions), where more detail is given on the issue and scale
of the problem, how this relates to the assessment and significance of the pressure and the established measures.
Regarding classification issues, France will use other indicators to show progress and will take into account uncertainties in biological
assessment methods.
March 2015
35
In the 2nd
RBMP, for rivers and lakes, France is considering using new assessment methods for benthic fauna, fish fauna and
macrophytes in order to better capture various pressures like morphology degradation.
For coastal waters: methods are developed but they have to be completed and intercalibrated.
Waters in overseas areas are more difficult to assess. Having re-analysed the ecological status of the water bodies, it will be possible
to estimate the number that will achieve „good‟ status in 2015, 2021 and 2027, after validation from the SDAGE Project River Basin
Committees, which is scheduled for September 2014.
Revision of the surface freshwater monitoring network is under way to integrate the networks of the Nitrates Directive (ND) and the
WFD (in France, the Surveillance Control Network or the Operational Control Network), in order to optimise monitoring over time (at
the frequency defined in the WFD rather than once every four years, as recommended by the ND), which will allow for better
assessment of trends in the level of nitrates.
River Basin Specific Pollutants (RBSP) were selected at basin scale and 9 RBSP at national scale (continental France). The list of
RBSP will be revised for the 2nd
cycle.
Heavily Modified Water Bodies (HMWB) and Artificial Water Bodies (AWB) will be reviewed: their designation as modified / artificial
bodies will be reassessed and the 1st cycle non-designated HMWB will be compared to neighbouring Member States (MS). As new
analysis will be performed on small Water Bodies (WB),new HMWB are expected. Besides, changes in Biological Quality Elements
(BQEs) parameters will imply some changes in designation of AWB and HMWB.
For the 2nd
cycle, the methodology for justification of exemptions will be consolidated. Therefore, a guide for the 2nd
cycle is being
finalised. France is expecting more deadline extensions (more measures needed, natural conditions).
Regarding the article 9 of the Directive (recovery of costs for water services), a harmonised analysis will be set up as a national study.
For ground water status assessment, a new method will be used to assess the balance between groundwater abstraction and
recharge. Furthermore, there will be a national methodology for trend assessment and reversal established and applied in the 2nd
March 2015
36
cycle. Eventually, a National guidance document about groundwater threshold values (TVs) was finalised in October 2012. There will
be more TVs established in the 2nd
cycle than in the first: not only TVs based on risks will be considered.
Regarding the PoM, a new national Methodological Guide on these is being finalised.
For measures related to hydromorphology, there will be new legislation to give new legal competence on river management at a local
level (if voted for by parliament), for a better implementation of measures. Mandatory works for river continuity restoration will also be
imposed. The mandatory minimum ecological flow will be increased by 2014.
For industries, results of extensive monitoring of substances in discharge effluents will be used, allowing better pressure and measure
identification.
For Agriculture, new mandatory measures concerning abstraction measures (modification in water abstraction authorisation, set up of
collective management of water abstraction for irrigation (Organisme unique de gestion collective des prélèvements d'eau pour
l'irrigation: OUGC)) and taxation (gradual increasing of fees related to pesticides, new tax on nitrates) will be used. Regarding
voluntary measures, articles 29 and 38 of the Rural Development Programme (RDP) will be used. In addition, the agro-industry will be
involved.
In cases where the expectations of the first plan have not been achieved or are not expected to be achieved, there is a description of what
expectations have not been achieved and an explanation of why not.
For groundwater, the objective of reaching 100% of groundwater bodies (GWB) at good quantity status as planned in the first plan will
not be attained. Otherwise, the chemical status of GWB evolved as expected.
For surface water, the ecological status of WB has not changed significantly from 2009 (for transitional waters, the acquisition of new
monitoring data is leading to a higher number of WB at risk). Surface WB at good ecological status are not necessarily those
predicted to be in the 1st plan. For example, only 65% of water bodies for which the RBMP 2010-2015 set a target of good ecological
status by 2015 reached this status. In contrast, about 20% of water bodies for which the RBMP 2010-2015 set a target of good
ecological status by 2021 or 2027 are already at good status.
March 2015
37
The chemical status of WB remains stable compare to 2009.
The main causes of deterioration of water status are: ecological morphology and continuity, pesticide pollution, abstractions and
pollution from oxidisable and organic matter.
Some measures were not implemented as far as expected. Different causes have been highlighted in the background document:
Due to the economic crisis, resources for the implementation of measures were more limited than expected in the first RBMP.
This is especially the case for territorial authorities which are the main project leaders for actions related to drinking water,
waste water treatment and hydromorphological restoration of watercourses.
There is a lack of interest for hydromorphological restoration. Others measures are then considered to be in competition, for
example those addressing floods or enhancing the landscape.
There are technical and legal complexities (property law) to implement measures related to hydromorphological restoration.
It was difficult to mobilise the agricultural sector against nitrates and phosphorus pollution, mainly because actions are not
leading to rapid tangible results and it was complicated to implement new actions in times of economic crisis.
3.2 Screening of progress on recommendations made in the Commission Staff Working Document (2015)
For each of the recommendations made in the Commission Staff Working Document (CSWD), which was published in March 2015, Table 5
shows:
A baseline against which to assess progress, and the actions required to solve the issue and fully address the recommendation;
An evaluation (key provided in Table 4); and
Justification for the evaluation of progress.
March 2015
38
Table 7 Description of the evaluation criteria used in the screening of progress
Evaluation Description
Strong evidence that actions taken are likely to address the COM recommendation.
All the actions relating to the recommendation have clearly been taken in the second plans. The
actions are defined in relation to the “baseline” situation in the first RBMPs.
Evidence found that good progress has/is being made
There has been good progress on the actions associated with the recommendation but not all
actions have been taken, some may be on-going with a clear timetable which will solve issues in a
reasonable timeframe (1 year for simple things, 2-3 years for more complex issues).
Some evidence of progress.
Some (but not all) of the actions proposed in the recommendations are mentioned and described
but not in enough detail to be certain that they have been fully taken. Some of the actions required
by the recommendation may not have been taken or mentioned at all.
?
No information could be found on the actions associated with the recommendation.
There is no information in the plan that any of the actions associated with the recommendation have
been considered or taken. The justification must describe the documents that have been screened.
No progress, or implementation of the WFD has worsened
The same inadequate processes, approaches and/or methods used in the first plan have been
reported in the second plan, and/or implementation has worsened in relation to the subject of the
recommendation.
Table 8 Assessment of progress on recommendations made in the CSWD (2015)
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
Improve knowledge about the link
between pressures and impacts in
designing and making operational the
measures for the second cycle, in order
For the first cycle, the link between the status
and the measures was generally unclear.
The measures were planned but there was no
The RBMP, the PoM and the background
documentation were consulted.
In the background document, the dangerous
March 2015
39
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
to:
1. Refine the significance of the
pressures by quantifying those
which are likely to prevent the
achievement of environmental
objectives
2. Assess the reduction in pressures
required to achieve the
environmental objectives
3. Apportion pressures by their
sources and identify the
responsible sectors/areas.
assessment or judgment as to how much the
measures would contribute to the
achievement of WFD objectives.
The main sectors responsible for the different
type of pressures have been identified in all
RBMPs. However, for most of the RBDs, there
is no clear explanation or definition on point
sources, diffuse sources and other pressures.
Fully meeting this recommendation would
mean that the gap that needs be filled for the
achievement of WFD objectives is quantified
in terms of the reductions needed in the
pressures causing water bodies to be failing,
or being at risk of failing, objectives.
Quantification of reductions in pressure
may be in terms of:
loads of pollutants/contaminants to be
reduced;
number of barriers to continuity to be
removed or adapted;
length/area of water bodies to be
remediated or restored; and,
volume of abstracted water to be reduced.
substances leading to a risk of failure were
identified for each WB. This is not the case for
other pressures.
There is no information on whether the
reduction in pressures required to achieve the
environmental objectives has been quantified
or not.
The annual flow of each specific dangerous
substance (41) has been quantified in terms
of g/year.
There is no source apportionment.
In the documents consulted, there is no
evidence that pressures were apportioned by
their sources. There is no identification of the
responsible sectors/areas.
March 2015
40
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
It should be clearly described how a source
apportionment has been undertaken that
gives a clear picture of the most important
sources for all identified significant
pressures or impacts. In this context a
source might be considered as a combination
of a pressure type (e.g. diffuse or point source
pollution) with the responsible sector or driver
(e.g. diffuse – agriculture, diffuse – forestry).
Enhance measures to tackle pollution
by nutrients (nitrogen and phosphorus),
considering their impact on ecological
status. Full consideration of the basin-
wide impact is needed in this respect
(local and downstream up to transitional
and coastal waters).
No clear baseline was found in the bilateral
meeting or in the 2012 MS Summary.
The orientation 5B “address eutrophication in
aquatic environments” focuses on nutrients
reduction. It is clearly stated that
eutrophication has to be tackled by acting in a
coordinated manner at watersheds level.
Furthermore, actions should not be limited to
areas where eutrophication occurs but should
address all inputs of pollutant in the
watershed.
Check that their nutrient standards are
consistent with biological requirements
for the achievement of good status and
provide a more coherent strategy
encompassing WFD with:
the Nitrates Directive (ND) and Common Agricultural Policy (CAP)
In the first RBMPs, it was unclear what the full
range of measures were and more importantly
how far these measures would go in
addressing agriculture's impact on water. For
the Commission, France should make this
much more transparent in the preparation of
the second RBMP. A coherent strategy for
agricultural action is needed encompassing
ND, WFD and CAP measures.
The ND and the CAP are both mentioned as
part of the basic measures (defined at
national level), and specific measures are
listed.
One of those is the conditionality of “support
by the Politique Agricole Commune” based
amongst others in respect to the action
programme under the ND.
In the RBMP for Rhone, the orientation 5B
March 2015
41
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
makes a specific reference to the ND.
There is a specific disposition to reduce inputs
of phosphorus and nitrogen in aquatic
environments.
For phosphates, guide values that go beyond
the requirements of the national regulation are
defined: 0.2 mg/l for watercourses; 0.15 mg/l
for lagoons and 0.07 mg/l for sensitive areas
(legal standard is set between 0.1 mg/l and
0.5 mg/l for good status).
There is no information available on how
these standards have been set.
These values should serve to identify effective
measures to reduce phosphorus inputs:
source reduction, tertiary treatment, reduce
diffuse pollution (reducing emissions from
fertilising crops, farms and greenhouses,
reducing runoff and erosion, etc.).
Check that their nutrient standards are
consistent with biological requirements
for the achievement of good status and
provide a more coherent strategy
encompassing WFD with:
the Urban Waste Water
Treatment Directive (UWWTD) in
urban areas.
No clear baseline was found in the bilateral
meeting or in the 2012 MS Summary.
For the 1st cycle, basic measures under
UWWTD were reported to be not enough for 8
RBDs due to point source pressure.
The UWWTD is mentioned as part of the
basic measures.
There is no evidence that basic measures
taken under the UWWT Directive are sufficient
to achieve good ecological status.
In the RBMP for Rhone, the orientation 5A
“continue to address domestic and industrial
pollution” makes a specific reference to the
UWWTD.
March 2015
42
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
The implementation of the Urban Wastewater
Directive (ERU) has reduced organic pollution
throughout the Rhone-Mediterranean Basin
by increasing the levels of water treatment
from 67% to 93% over the last twenty years.
The RBMP intends to clarify the conditions
under which it is necessary to strengthen the
measures provided in the regulations
(Directive ERU legislation on classified
installations) where it is locally needed (for
example in sensitive areas).
The disposition 5A-02 plans to adapt
discharge conditions based on the notion of
allowable flows for particularly sensitive
environments (to address eutrophication for
example).
It is stated that progress has to be made in
the identification and quantification of
pollutants flows taking into account the
different sources of pollution.
In particular, it is expected that RBMPs,
based on the necessary reduction in
nutrient load, clearly identify the extent
to which the measures already taken
under the implementation of ND and
UWWTD contribute to the achievement
of WFD objectives and which additional
The ND and the UWWTD were implemented
in the national legislation across all 13 RBDs,
including overseas territories.
In the first RBMP‟s, there is no indication (as
there is no specific information available) on
the effectiveness of the measures included in
the ND, and of any of the additional measures
See above, this is included in the list of basic
measures and under orientations 5A and 5B.
It is stated that further measures than those
under the UWWTD could be needed when
this is required by local conditions (for
example in sensitive receptors like lagoons).
March 2015
43
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
measures should be taken to actually
achieve these objectives. A clear
identification of basic (mandatory)
measures is expected to be made
transparent both to the sectors and the
general public.
implemented.
It must be clear that the effectiveness of
measures taken under the ND or UWWTD
have been reviewed since the first plan. It
must be explicitly described how the
measures taken under the ND are expected to
contribute to the achievement of WFD
objectives (i.e. how much of the gap they will
fill) and also those relating to the UWWTD.
There is no quantification of the effectiveness
of measures taken under the ND and
UWWTD.
Review the regulation of the use of
pesticides in order to effectively reduce
current levels of contamination of rivers
and groundwater, making clear linkages
with the implementation of the Directive
on the Sustainable Use of Pesticides.
For the first cycle, basic measure in the PoM
referred to the regulation on pesticides put on
the market (Decree of the 12 September
2006). However, some more measures are
implemented within the context of the
Ecophyto plan which started in 2009.
The RBMP, the PoM and the background
document were consulted. There is no
reference to the Directive on the Sustainable
Use of Pesticides (2009/128/EC).
A set of dispositions is defined under the
orientation 5D “Address pollution from
pesticides by substantial changes in current
practices”. One of them is named “Establish
local regulations regarding the use of
pesticides in sensitive areas”. It refers to the
national regulation on the use of pesticides
(Decree of the 12 September 2006) which
allow the “préfet” to limit or even forbid the
use of specific pesticides.
The conditionality of the assistance by the
CAP is also mentioned.
Define measures targeted to agriculture
at an appropriate level of detail to
In the 1st plans, there was no detailed
information on the different stakeholders
The disposition 5D-02 “Encourage more
environmentally friendly farming practices by
March 2015
44
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
ensure their uptake by farmers and
their inspection by relevant agencies.
involved in the preparation of the measures
for agriculture and the extent of their
contributions (even if the farming sector were
consulted). Regarding the control of
implementation of the agricultural measures,
in most RBMP‟s it was mentioned that a
control mechanism was in place or would be
further developed, but no further details were
provided.
mobilising actors and financial tools” aims to
involve the farmers more by implementing
technical support through different plans /
organisations (regional plans, environmental
and economic interest groups, Water
Development and Management Scheme
(SAGE)).
No more information was found.
The RBMPs are expected to make a
clear distinction between mandatory
measures and voluntary ones that will
be funded under the European
Agricultural Fund for Rural
Development (EAFRD).
For the first cycle, some voluntary measures
were based on actions under the EAFRD.
There is no distinction in the PoM or in the
RBMP between mandatory measures and
voluntary ones.
Ensure that ecological flow is
considered wherever existing and
planned abstractions may jeopardise
the achievement of environmental
objectives. This is particularly crucial
when considering the review of water
allocations and permits and the
construction of new dams and
reservoirs.
An important issue that was not clearly
defined in the first plan was the ecologically
based flow regime. The flow regime and
authorisation was considered as a measure to
tackle the overexploitation of groundwater but
not to ensure a sufficient ecological flow.
One measure is to implement a strategy to
ensure a minimum water flow or to increase
the “minimum flow downstream” beyond legal
requirements. It refers to hydroelectric
schemes and to Article L.214-18 of the
Environmental Code. When the administrative
authority shall issue an authorisation or
concession (even for existing construction
sites from 01/01/14), it is required to set a
minimum flow downstream of the works that
must contribute to the environmental
objectives of the river and take into account
March 2015
45
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
the ecological characteristics and the
biological quality of rivers.
Ensure that the RBMPs clearly identify
the gap to good status, and that the
PoMs are designed and implemented to
close that gap.
There was no information in the 1st plans on
how the gap required to meet WFD objectives
had been quantified in terms of the required
reduction of pressures and the respective
contribution to the pressures from the
responsible sectors/activities. There was also
no information on how much of the gaps were
expected to be filled by the different
measures.
?
The RBMP, the PoM and the background
document were consulted.
There is no information on whether the
reduction in pressures required to achieve the
environmental objectives has been quantified
or not. There is no information on how much
of the gaps are expected to be filled by the
different measures.
The plan is developed in orientations with
different specific objectives per orientation,
from which measures occur.
France is expected to provide a more
consolidated methodology for
justification of exemptions to the
achievement of environmental
objectives (in particular as regards the
assessment of affordability and
disproportionate costs).
In the 1st RBMP‟s, there were a relatively high
number of exemptions under Article 4(4) and
4(5) based on disproportionate costs, for
which there was no clear justification (even if
the national guidelines on exemptions
mentioned that alternative financing has to be
sought).
It has to be clear in the 2nd
plan that a
consolidated methodology has been set for
justification of exemptions (which included
harmonised analysis from a national study).
The methodology to assess the costs and
search for funding should be detailed.
?
The RBMP, the PoM and the background
document were consulted.
There is no clear mention of the methodology
used for justification of exemptions to the
achievement of environmental objectives.
In the glossary, there are some more
clarifications on disproportionate costs and
economic analysis.
There is one specific chapter on projects for
which an Art 4.7 exemption needs to be
requested. There are no projects that require
exemption under this article.
Provide a more complete definition of For the 1st cycle, water services have been There is a specific chapter on water pricing
March 2015
46
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
water services and a proper recovery of
cost to contribute to the objectives,
especially when fully accounting for
environmental and resource costs for
services creating a pressure on water
bodies.
interpreted differently across the French RBD.
Some RBDs had a broad approach, which
took into account all possible abstraction,
storage, treatment, impoundment etc. In other
RBDs, the approach had been narrower,
taking into account public and private water
abstraction and wastewater treatment for all
sectors, as well as irrigation. Finally, in some
RBDs, the approach had been even more
limited, taking into account only abstraction
and wastewater treatment for households,
industry and abstraction for agriculture.
and cost recovery in the background
document.
Both water use and water services are
considered in the water recovery calculation.
Water services include infrastructures for
water storage, surface or groundwater
abstraction, treatment and distribution,
sewage collection and wastewater treatment.
Rhone has carried out an elaborate
calculation integrating environmental costs.
The disposition A “know and understand
better the economic and social impacts” sets
out the adjustment of tariffs on basis of the
cost recovery level (disposition 3-05).
Consider restoration measures as well
as the use of green infrastructure
and/or natural water retention
measures that provide a range of
environmental (improvements in water
quality, flood protection, habitat
conservation etc.), social and economic
benefits which can be in many cases
more cost-effective than grey
infrastructure.
Those measures were not explicitly described
in the first plan. The development of the
second RBMPs should be coordinated with
the development of flood risk management
plans and the use of this type of measure is
seen as a win-win situation in achieving the
objectives of both plans
In the RBMP from Rhone, there is a specific
orientation (n°8) related to flood protection. It
is clearly stated that natural water retention
measures should be preferred. Prior to any
retention work, an analysis of alternative
solutions has to be carried out. This refers to
a specific process: “PAPI-PSR”.
Two dispositions aim to preserve and
implement expanding flood areas.
March 2015
47
3.3 Water services excluded from the requirement of WFD Article 9 “Recovery of costs for water services”
Table 9 Water services explicitly included in/excluded from cost recovery and Article 9.4 exemptions applied
Water service
Explicitly included in cost recovery
(yes/no/no information/not
clear)
Explicitly excluded from cost recovery
(yes/no/no information/not
clear)
Article 9.4 exemptions
applied (yes/no/no
information/not clear)
Drinking water abstraction (surface and/or groundwater), treatment and distribution
Yes No information
Sewage collection and wastewater treatment Yes No information
Drinking water abstraction (surface and/or groundwater), treatment and distribution AND sewage collection and wastewater treatment (when considered together)
Yes No information
Irrigation water abstraction, treatment and distribution Yes No information
Self-abstraction Yes No information
Impoundment and storage of water Not clear No information
Impoundment for flood protection No No information
Impoundment for navigation No No information
Other (please describe in text box below)
The calculation of recovery of costs for water services takes into account:
The funding and pricing in the water sector.
Contributions of key economic sectors (households, industry and agriculture) to finance water services (public water distribution and
water treatment, self-abstraction, irrigation, etc.).
March 2015
48
The concept of environmental costs.
March 2015
49
4. River Basin District: Adour Garonne
4.1 Headlines
The following passage summarises the main changes made in the draft second RBMP compared to the first RBMPs, for example, as
required in annex VII B.
Lessons learned from the first cycle management helped to set more realistic goals for the River Basin Management Plan
(RBMP) 2016-2021.
For some water bodies (WB), the RBMP 2010-2015 aimed to achieve good status in 2015, but in view of current knowledge, a later
deadline seems more feasible and an extension of the deadline has been requested.
For 127 WB a postponement had been included in the RBMP 2010-2015 although good ecological status could be achieved by 2015.
Similarly, for 191 WB a postponement was listed as good chemical status could be reached in 2015. For groundwater bodies (GWB),
a postponement was listed as good quantitative status could be reached as early as 2015. And for four GWB, a delay was listed as
the good chemical status could be achieved by 2015.
Better knowledge on the status of the WB and difficulties experienced in mobilising multiple stakeholders for measures in
relation to the field of agricultural pollution, quantitative management or hydromorphological restoration.
This RBMP integrates this knowledge to update good objectives for each WB in 2021 and in 2027.
There was also a lack of ownership for certain measures. They are also based on the assumption of effective basic measures and
the benefit of two PoMs successively by 2021.These goals are no less ambitious if we take into account uncertainties related to
general economic conditions and the likely institutional slowdowns related to the implementation of local government
reform.
March 2015
50
In terms of the general approach of the RBMP three stages are explained in the development of the 2nd
RBMP:
1. Identification of the important questions to which the RBMP will need to respond.
2. Overview of the status and where we are in the PoM implementation (based on the earlier mid-term review).
3. Elaboration of the RBMP and the PoMs.
This resulted in a list of fundamental orientations and their dispositions (provisions), where more detail is given on the issue and
scale of the problem, how this relates to the assessment and significance of the pressure and the established measures.
Furthermore, climate change adaptation is taken into account.
Regarding classification issues, France will use other indicators to show progress and will take into account uncertainties in biological
assessment methods.
In the 2nd
RBMP, for rivers and lakes, France is considering using new assessment methods for benthic fauna, fish fauna and
macrophytes in order to better capture various pressures like morphology degradation.
For coastal waters: methods are developed but they have to be completed and intercalibrated.
Revision of the surface freshwater monitoring network is under way to integrate the networks of the Nitrates Directive (ND) and the
WFD (in France, the Surveillance Control Network or the Operational Control Network), in order to optimise monitoring over time (at
the frequency defined in the WFD rather than once every four years, as recommended by the Nitrates Directive), which will allow for
better assessment of trends in the level of nitrates.
River Basin Specific Pollutants (RBSP) were selected at basin scale and 9 RBSP at national scale (continental France). The list of
RBSP will be revised for the 2nd
cycle.
March 2015
51
Heavily Modified Water Bodies (HMWB) and Artificial Water Bodies (AWB) will be reviewed: their designation as modified / artificial
bodies will be reassessed and the 1st cycle non-designated HMWB will be compared to neighbouring Member States (MS). As new
analysis will be performed on small WB, new HMWB are expected. Besides, changes in Biological Quality Elements (BQEs)
parameters will imply some changes in designation of AWB and HMWB.
For the 2nd
cycle, the methodology for justification of exemptions will be consolidated. Therefore, a guide for the 2nd
cycle is being
finalised. France is expecting more deadline extensions (more measures needed, natural conditions).
Regarding the article 9 of the Directive (recovery of costs for water services), a harmonised analysis will be set up as a national study.
For ground water status assessment, a new method will be used to assess the balance between groundwater abstraction and
recharge. Furthermore, there will be a national methodology for trend assessment and reversal established and applied in the 2nd
cycle. Eventually, a National guidance document about groundwater threshold values (TVs) was finalised in October 2012. There will
be more TVs established in the 2nd
cycle than in the first: not only TVs based on risks will be considered.
Regarding the PoM, a new national Methodological Guide on these is being finalised.
In cases where the expectations of the first plan have not been achieved or are not expected to be achieved, there is a description of what
expectations have not been achieved and an explanation of why not.
For all the riverine WB (measured and modelled), the percent at good ecological status decreases slightly (42% against 48% in 2009).
The difference is explained by the use of a new national model that seems more conservative (status downgraded more often) than
the method used in 2009. However the indicators that assess the content of material organic (Biological Oxygen Demand (BOD5),
Chemical Oxygen Demand (COD) and nutrients) have improved. The reference years of data used are from 2009 to 2010.
The chemical status of the rivers remains generally good (94% of WB in good condition). Cadmium, mercury and hydrocarbons
(PAHs) are the most responsible parameters for downgrading. Pesticides are responsible for the downgrading of only two WB (it
should be remembered that almost all phytosanitary products as part of the chemical status are banned from sale and of use). For
mercury, it should be noted that the majority (68%) of WB downgraded by this metal are located on the upstream basin of the
Garonne (15 WB out of 22).
March 2015
52
The percentage of WB in good condition is almost identical to that in 2009, that is 61%. Three WB had a reduction in quality and four
have better quality than in 2009). The presence of pesticides and nitrates is the main cause of the downgrading of chemical status for
these WB.
Regarding the quantitative status of groundwater, the percentage of GWB in good status increased compared to 2009, but this
increase is mainly due to the decision to classify as good condition all GWB for which no evidence (lacking data) of degradation
exists.
Other reasons given for the reported delays:
Reaction time of the environment.
Delay in the design and implementation of the river restoration actions.
Restoration cannot ensure good functioning of ecosystems in only one planing cycle.
Delay in the implementation of actions in order to reduce diffuse pollution.
4.2 Screening of progress on recommendations made in the Commission Staff Working Document (2015)
For each of the recommendations made in the Commission Staff Working Document (CSWD), which was published in March 2015, Table 5
shows:
A baseline against which to assess progress, and the actions required to solve the issue and fully address the recommendation;
An evaluation (key provided in Table 4); and
Justification for the evaluation of progress.
March 2015
53
Table 10 Description of the evaluation criteria used in the screening of progress
Evaluation Description
Strong evidence that actions taken are likely to address the COM recommendation.
All the actions relating to the recommendation have clearly been taken in the second plans. The
actions are defined in relation to the “baseline” situation in the first RBMPs.
Evidence found that good progress has/is being made
There has been good progress on the actions associated with the recommendation but not all
actions have been taken, some may be on-going with a clear timetable which will solve issues in a
reasonable timeframe (1 year for simple things, 2-3 years for more complex issues).
Some evidence of progress.
Some (but not all) of the actions proposed in the recommendations are mentioned and described
but not in enough detail to be certain that they have been fully taken. Some of the actions required
by the recommendation may not have been taken or mentioned at all.
?
No information could be found on the actions associated with the recommendation.
There is no information in the plan that any of the actions associated with the recommendation have
been considered or taken. The justification must describe the documents that have been screened.
No progress, or implementation of the WFD has worsened
The same inadequate processes, approaches and/or methods used in the first plan have been
reported in the second plan, and/or implementation has worsened in relation to the subject of the
recommendation.
Table 11 Assessment of progress on recommendations made in the CSWD (2015)
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
Improve knowledge about the link
between pressures and impacts in
designing and making operational the
measures for the second cycle, in order
For the first cycle, the link between the status
and the measures was generally unclear.
The measures were planned but there was no
In the background documentation, there is a
presentation given on the plan for water
management.
March 2015
54
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
to:
1. Refine the significance of the
pressures by quantifying those
which are likely to prevent the
achievement of environmental
objectives
2. Assess the reduction in
pressures required to achieve
the environmental objectives
3. Apportion pressures by their
sources and identify the
responsible sectors/areas.
assessment or judgment as to how much the
measures would contribute to the
achievement of WFD objectives.
The main sectors responsible for the different
type of pressures have been identified in all
RBMPs. However, for most of the RBDs, there
is no clear explanation or definition on point
sources, diffuse sources and other pressures.
Fully meeting this recommendation would
mean that the gap that needs be filled for the
achievement of WFD objectives is quantified
in terms of the reductions needed in the
pressures causing water bodies to be failing,
or being at risk of failing, objectives.
Quantification of reductions in pressure
may be in terms of:
loads of pollutants/contaminants to be
reduced;
number of barriers to continuity to be
removed or adapted;
length/area of water bodies to be
remediated or restored;
volume of abstracted water to be
This chapter provides further details regarding
the inventory of dangerous substances, which
leads to a refinement of pressures.
Further on, the measures are included in a
table, and the implementation of the
measures to reach the objectives is followed
by a set of indicators. This receives specific
attention in the chapter in the background
document “Dispositif de suivi destine µa
évaluer la mise en oeuvre du SDAGE 2016-
2012 (RBMP).
The RBMP is structured according to four
orientations that are seen as important for the
2nd
cycle in terms of the management of
water:
Orientation A: create the conditions of
favourable governance in order to reach the
objectives.
Orientation B: reduce pollution.
Orientation C: improve the quantitative
management.
Orientation D: preserve and restore the
functionalities of the aquatic environment.
For each of these orientations, in the
chapters, there is a part on “better knowledge
on the environment to manage the issue” and
“sustainable management” and “manage the
March 2015
55
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
reduced.
It should be clearly described how a source
apportionment has been undertaken that
gives a clear picture of the most important
sources for all identified significant
pressures or impacts. In this context a
source might be considered as a combination
of a pressure type (e.g. diffuse or point source
pollution) with the responsible sector or driver
(e.g. diffuse – agriculture, diffuse – forestry).
crisis”
The detail is not extensive, but the part on
dangerous substances includes a more
detailed assessment on the significance of the
pressure.
There is a list of dangerous and priority
substances established at the national level
which gives emission reduction targets for
each of the substances. This is neither a list
for the specific pollutants nor source
apportionment.
In the background document there is a table
included that evaluates the fluxes of each
substance for each type of emission (kg/year).
Summary: refinement by quantitative
analysis is done in a limited way; source
apportionment is not carried out for any
pressures/parameters, and reduction of
pressures required to achieve objectives
has not been carried out.
Enhance measures to tackle pollution
by nutrients (nitrogen and phosphorus),
considering their impact on ecological
status. Full consideration of the basin-
wide impact is needed in this respect
(local and downstream up to transitional
and coastal waters).
No clear baseline was found in the bilateral
meeting or in the 2012 MS Summary.
Orientation B “reduce pollution” specifically
focuses on the reduction of nutrients through
agriculture. There is also an orientation that
contains several measures. It is called “Better
know and make known to better manage”.
This orientation focuses on basin-wide
approaches. There is also one specific set of
March 2015
56
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
measures that focuses on small water bodies
that have to be protected. Further on, there is
a measure on the protection of fish with a link
to estuarine and marine zone management.
Check that their nutrient standards are
consistent with biological requirements
for the achievement of good status and
provide a more coherent strategy
encompassing WFD with:
the Nitrates Directive (ND) and
Common Agricultural Policy
(CAP) in agriculture
In the first RBMP‟s, it was unclear what the full
range of measures were and more importantly
how far these measures would go in
addressing agriculture's impact on water. For
the Commission, France should make this
much more transparent in the preparation of
the second RBMP. A coherent strategy for
agricultural action is needed encompassing
both ND, WFD and CAP measures.
Orientation B “reduce pollution” specifically
focuses on the reduction of nutrients through
agriculture and it is noted that better
understanding of the key parameters is
needed. In the PoMs document, it is noted
that the measure on reduction of nitrogen is
included as part of ND implementation for all
sub-basins as well as in the Rural
Development programme with the agri-
environmental measures. The ND is also
mentioned as part of the basic measures, and
supplementary measures for specific WB are
listed.
In addition, the conditionality of “support by
the Politique Agricole Commune [CAP]” is
included in the chapter on diffuse pollution
specific to pesticide usage. CAP is also
included in the basic measure table.
Check that their nutrient standards are
consistent with biological requirements
for the achievement of good status and
provide a more coherent strategy
encompassing WFD with:
No clear baseline was found in the bilateral
meeting or in the 2012 MS Summary.
For the 1st cycle, basic measures under
UWWTD were reported to be not enough for 8
RBDs due to point source pressure.
The UWWTD is included as part of the basic
measures, and supplementary measures for
specific WB are listed. In addition, in order to
reduce pollution (one of the thematic
orientations) the UWWTD is referenced.
March 2015
57
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
the Urban Waste Water
Treatment Directive (UWWTD) in
urban areas
In particular, it is expected that RBMPs,
based on the necessary reduction in
nutrient load, clearly identify the extent
to which the measures already taken
under the implementation of ND and
UWWTD contribute to the achievement
of WFD objectives and which additional
measures should be taken to actually
achieve these objectives. A clear
identification of basic (mandatory)
measures is expected to be made
transparent both to the sectors and the
general public.
The ND and the UWWTD were implemented
in the national legislation across all 13 RBDs,
including overseas territories.
In the first RBMP‟s, there is no indication (as
there is no specific information available) on
the effectiveness of the measures included in
the ND, and of any of the additional measures
implemented.
It must be clear that the effectiveness of
measures taken under the ND or UWWTD
have been reviewed since the first plan. It
must be explicitly described how the
measures taken under the ND are expected to
contribute to the achievement of WFD
objectives (i.e. how much of the gap they will
fill) and also those relating to the UWWTD.
See above, this is included in the overall
tables of measures and is clearly described.
The assessment on how the ND and the
UWWTD contribute to achieving the
objectives is not been made. Furthermore, in
the PoM, measures to reduce nitrate pollution
all refer to the Nitrate Directive (basic
measures).
Review the regulation of the use of
pesticides in order to effectively reduce
current levels of contamination of rivers
and groundwater, making clear linkages
with the implementation of the Directive
on the Sustainable Use of Pesticides.
For the first cycle, basic measure in the PoM
referred to the regulation on pesticides put on
the market (Decree of the 12 September
2006). However, some more measures are
implemented within the context of the
Ecophyto plan which started in 2009.
?
The Ecophyto plan is noted as one of the
main plans that will help to reduce diffuse
pollution. In addition, it is indicated that there
will be regulations for the use of pesticides.
The Directive on the Sustainable Use of
Pesticides. itself is included under the PoMs
Basic Measures table.
March 2015
58
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
Furthermore, the conditionality of the
assistance by the CAP.
Define measures targeted to agriculture
at an appropriate level of detail to
ensure their uptake by farmers and
their inspection by relevant agencies.
In the 1st plans, there was no detailed
information on the different stakeholders
involved in the preparation of the measures
for agriculture and the extent of their
contributions (even if the farming sector were
consulted). Regarding the control of
implementation of the agricultural measures,
in most RBMP‟s it was mentioned that a
control mechanism was in place or would be
further developed, but no further details were
provided.
The conditionality of the assistance by the
CAP is referenced. There is an orientation in
the plan which is called “creation of better
conditions for the governance in order to
reach the objectives”; but no specific details
are given on agriculture, farmers or farm
inspections.
The RBMPs are expected to make a
clear distinction between mandatory
measures and voluntary ones that will
be funded under the European
Agricultural Fund for Rural
Development (EAFRD).
For the first cycle, some voluntary measures
were based on actions under the EAFRD.
In the RBMP, the only reference to voluntary
measures is related to the voluntary schemes
implemented in Areas with Environmental
Restrictions (AER).
A voluntary action programme can become
compulsory if the expected results are not
reached.
There is no distinction in the PoM between
mandatory measures and voluntary ones.
Ensure that ecological flow is
considered wherever existing and
planned abstractions may jeopardise
the achievement of environmental
objectives. This is particularly crucial
An important issue that was not clearly
defined in the first plan was the ecologically
based flow regime. The flow regime and
authorisation was considered as a measure to
tackle the overexploitation of groundwater but
Article L.214- 18 of the Environmental Code of
the basic measures.
Specific attention is paid to the effects of
hydropower (hydropeaking and downstream
March 2015
59
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
when considering the review of water
allocations and permits and the
construction of new dams and
reservoirs.
not to ensure a sufficient ecological flow. low flows).
The adaptation of the minimum flow values
maintained downstream of works,
including those intended for the production of
hydroelectricity (Article L. 214-18 of the
Environment Code), must contribute to the
environmental objectives of the rivers and
take into account the ecological
characteristics and the biological quality of
rivers
Ensure that the RBMPs clearly identify
the gap to good status, and that the
PoMs are designed and implemented to
close that gap.
There was no information in the 1st plans on
how the gap required to meet WFD objectives
had been quantified in terms of the required
reduction of pressures and the respective
contribution to the pressures from the
responsible sectors/activities. There was also
no information on how much of the gaps were
expected to be filled by the different
measures.
The gap to good status is more or less clear
but the projected objectives that should be
reached have been changed for the WB in the
Garonne river basin. The plan is set out as a
series of orientations with different specific
objectives, from which measures are
produced. This is all included in a Table
alongside the implementation of the measures
and the indicators.
France is expected to provide a more
consolidated methodology for
justification of exemptions to the
achievement of environmental
objectives (in particular as regards the
assessment of affordability and
disproportionate costs).
In the 1st RBMP‟s, there were a relatively high
number of exemptions under Article 4(4) and
4(5) based on disproportionate costs, for
which there was no clear justification (even if
the national guidelines on exemptions
mentioned that alternative financing has to be
sought).
It has to be clear in the 2nd
plan that a
There is not a specific chapter on the
methodology. France reports that for three
more water bodies derogations have been
requested - to a lower objective. In the
chapter on objectives, there is a box with
information on the derogation for extending
the time to reach the objective, but this is
lacking in details. Although there is new
March 2015
60
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
consolidated methodology has been set for
justification of exemptions (which included
harmonised analysis from a national study).
The methodology to assess the costs and
search for funding should be detailed.
national guidance there is no specific
reference to it within the RBMP.
Provide a more complete definition of
water services and a proper recovery of
cost to contribute to the objectives,
especially when fully accounting for
environmental and resource costs for
services creating a pressure on water
bodies.
For the 1st cycle, water services have been
interpreted differently across the French RBD.
Some RBDs had a broad approach, which
took into account all possible abstraction,
storage, treatment, impoundment etc. In other
RBDs, the approach had been narrower,
taking into account public and private water
abstraction and wastewater treatment for all
sectors, as well as irrigation. Finally, in some
RBDs, the approach had been even more
limited, taking into account only abstraction
and wastewater treatment for households,
industry and abstraction for agriculture.
The treatment, distribution, abstraction and
stocking of water, as well as collection and
treatment of used water as water services is
well defined. The water users are categorised
as households, public services, industries,
and agriculture. Furthermore, a distinction is
made between collective and individual
services (e.g. industry treating their own
wastewater is an individual service). There
was a specific study carried out by Ernst &
Young on cost recovery estimating that there
is 1395 million on costs on top of the budget
for the basin Adour Garonne. The
environmental costs are reported to be more
difficult to estimate.
Consider restoration measures as well
as the use of green infrastructure
and/or natural water retention
measures that provide a range of
environmental (improvements in water
quality, flood protection, habitat
conservation etc.), social and economic
Those measures were not explicitly described
in the first plan. The development of the
second RBMPs should be coordinated with
the development of flood risk management
plans and the use of this type of measure is
seen as a win-win situation in achieving the
objectives of both plans.
No specific green infrastructure measures are
referred to but they are included in the several
orientations. For example, erosion reduction
measures such as planting herbs that retain
the soil.
March 2015
61
Recommendation made in CSWD (March 2015)
Baseline for assessment of progress and actions required to solve the issue and fully
address the recommendation
Evaluation Justification for evaluation of progress
benefits which can be in many cases
more cost-effective than grey
infrastructure.
4.3 Water services excluded from the requirement of WFD Article 9 “Recovery of costs for water services”
Table 12 Water services explicitly included in/excluded from cost recovery and Article 9.4 exemptions applied
Water service
Explicitly included in cost recovery
(yes/no/no information/not
clear)
Explicitly excluded from cost recovery
(yes/no/no information/not
clear)
Article 9.4 exemptions
applied (yes/no/no
information/not clear)
Drinking water abstraction (surface and/or groundwater), treatment and distribution
Yes No information
Sewage collection and wastewater treatment Yes No information
Drinking water abstraction (surface and/or groundwater), treatment and distribution AND sewage collection and wastewater treatment (when considered together)
Yes No information
Irrigation water abstraction, treatment and distribution Yes No information
Self-abstraction Yes No information
Impoundment and storage of water No information
Impoundment for flood protection No No information
Impoundment for navigation No No information
Other (please describe in text box below) No No information