SCT Production Status. ‘Snap-shot’ of the status of the SCT production (May 2003) Barrel Modules Barrel Opto-harnesses Barrel support structures & cooling Endcap Modules Endcap Opto-harnesses Endcap support structures & cooling Power & Cables Off-detector readout Assembly & Integration. - PowerPoint PPT Presentation
Citation preview
M. TYNDEL 1 LHCC Interactions May 2003
ATLAS ATLAS SCTSCT
SCT Production Status
‘Snap-shot’ of the status of the SCT production (May 2003)
1. Barrel Modules
2. Barrel Opto-harnesses
3. Barrel support structures & cooling
4. Endcap Modules
5. Endcap Opto-harnesses
6. Endcap support structures & cooling
7. Power & Cables
8. Off-detector readout
9. Assembly & Integration
M. TYNDEL 2 LHCC Interactions May 2003
ATLAS ATLAS SCTSCT
Modules Barrel module PRR May 01 Detector production May 03 ( I.e. complete)
Hybrids target end date Aug 03 1214/2500 (49%) Baseboards target end date Oct 03 1481/2530 (59%)
Modules-Japan 356/ 786 (45%) Modules-UK 79/ 549 (14%) Modules-US 48/ 483 (10%) Modules-Scand (qualification soon) 16/ 404 ( Total (2112+5%) 499/ 2218 (22%)
Modules target end date Apr 04
Barrel Modules
M. TYNDEL 3 LHCC Interactions May 2003
ATLAS ATLAS SCTSCT
Barrel Optoharnesses
Opto-harnesses Production now underway after slow start-up Main problem was ESD damage to DORIC ASIC First 2 harnesses fully evaluated Schedule can be recovered
B3 Jun 03 B6 Jul 03 B5 Sep 03 B4 Oct 03
M. TYNDEL 4 LHCC Interactions May 2003
ATLAS ATLAS SCTSCT
Barrel Structure & Cooling
Support structures
All 4 CF cylinders delivered
…but there are ~40000 small parts!
Cooling
Design is finalised
Production of cooling circuits underway
On critical path
M. TYNDEL 5 LHCC Interactions May 2003
ATLAS ATLAS SCTSCT
Endcap Modules
Modules Endcap module PRR Aug 02 & Nov 02
Hybrid design was validated as suitable for production Hybrid production & assembly transferred to industry Thermal performance validated
Production Hybrids
Pre-series of 200 in production – some delivered Full order for 2500 placed
Spines 200 in production by Protvino/MPI Contract in place for 2500
Module assembly All 3 clusters have started ‘qualification’ process 1rst modules within specification Aim is to have all sites qualified in 2 months Goal is to complete module production in Sep 04
Very ambitious – will require extra resources
M. TYNDEL 6 LHCC Interactions May 2003
ATLAS ATLAS SCTSCT
Endcap Optoharnesses, Structure & Cooling
Opto-harnesses Simpler as the electronics is
incorporated in the hybrid Production can start as soon as fibre
lengths finalised Cooling
Design is finalised & prototyped Production of cooling circuits ready to
start Support structures
CF disks & support cylinders ordered First 4 delivered; complete by Dec 03
Again many small parts 4 first disks & Stub cylinder delivered Expect delivery of cylinders by Aug 03
Disk PAR MAY 19 Critical issue is to complete disc
machining by July
M. TYNDEL 7 LHCC Interactions May 2003
ATLAS ATLAS SCTSCT
SCT Power, Cables, Readout, Assembly & Integration
Power & Cables System designed & all elements prototyped FDR/PRR scheduled for May 28 Early production necessary for macro-assembly Cable tender in June
Readout System designed & all elements prototyped FDR/PRR May 13 Early production necessary for macro-assembly
Assembly & Integration B3 is at RAL to be equipped with services B3 will go to Oxford to have modules added Jul 03 – Nov 03 SR building at CERN now available
Program of work underway to commission cooling, power & readout