AWSS: Installation of architectural roof over new Ashbury Heights Tank NFS: Exterior Envelope, Station 31 Public Safety Building Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting DESIGN BUILD ENJOY 09 - Concrete & Reinforcing Steel 10 - Earthwork/Shoring/Utilities/Demo 12 - AOA Pavement 13 - Fueling Systems 14 - Roofing & Waterproofing 15 - Stairs (Design-Build) 16 - Precast 17 - Passenger Loading Bridges 18 - Special Systems (Design-Build)

Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

AWSS: Installation of architectural roof over new Ashbury Heights Tank

NFS: Exterior Envelope, Station 31

Public Safety Building

Seattle-Tacoma International Arrivals Facility

Trade Packages 9,10,12-18 Pre-Proposal Meeting

DESIGN BUILD ENJOY

• 09 - Concrete & Reinforcing Steel • 10 - Earthwork/Shoring/Utilities/Demo • 12 - AOA Pavement • 13 - Fueling Systems • 14 - Roofing & Waterproofing • 15 - Stairs (Design-Build) • 16 - Precast • 17 - Passenger Loading Bridges • 18 - Special Systems (Design-Build)

Page 2: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 2

Project Team

• Jeffrey Brown, Director Aviation Facilities &

Capital Programs/Project Sponsor Port of Seattle • David Brush, Port Program Leader Port of Seattle • Noah Toomey, Design Manager Clark Construction • Martin McMahon, Construction Manager Clark Construction

• Lou Palandrani, Officer in Charge Clark Construction • Marshall Singh, Project Director Clark Construction • Marguerite Clark, Business Manager/ SBE

Coordinator Clark Construction • Tina Smith, Procurement Coordinator Clark Construction

• Larry Santone, Purchasing Manager Trade Package 14 & 17 • Russ Floreske, Purchasing Manager Trade Package 18

• Nelson Cook, Purchasing Manager Trade Packages 9, 15 & 16 • Jim Black, Purchasing Manager Trade Packages 10, 12 & 13

Purchasing Managers

Page 3: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 3

• Key to the growth of our Great Northwest • Growth in international traffic – 13% year-over-year • Federal Inspection Services (FIS) facility built in 1970’s • Currently built to accommodate approximately 800 passengers – current demand is as high as 2,000 passengers.

WHY?

WHAT? • New modern state-of-the-art facility for enhanced passenger experience. • Improve the airlines’ abilities to operate efficiently. • Provide for the 2025 demand of 2,600 passengers/hour. • Passenger connection times between international and domestic flights. WHEN? • Construction Start – February/March 2017 • Beneficial Occupancy – October 2019

Page 4: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 4

• Bring the project in below budget. • Open new facility on-time in the fall of 2019. • Encourage robust SCS/SBE participation • Deliver an iconic passenger bridge from SSAT to the new IAF • A modern and efficient international passenger processing facility using latest technology.

Future Goals

Page 5: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 5

Subcontractors & Suppliers & Design Team

Progressive Design Build Delivery – Partnership with Port of Seattle

Page 6: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 6

Overall Schedule • Project Award July 20th, 2015

• Design Development - Finalization 2016 / 2017

• Procurement Key Trade Packages July – December 2016

• Construction 1st Quarter 2017

• Open New Facilities Fall 2019 / Mid 2020

Page 7: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 7

Page 8: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 8

1

2

3

Page 9: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 9

Page 10: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

Page 10

International Arrivals Facility

Page 11: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

Page 11

International Arrivals Facility

Page 12: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

Page 12

International Arrivals Facility

Page 13: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

Page 13

International Arrivals Facility

Page 14: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 14

• Package 09 - Concrete & Reinforcing Steel • Package 10 - Earthwork/Shoring/Utilities/Demo • Package 12 - AOA Pavement • Package 13 - Fueling Systems • Package 14 - Roofing & Waterproofing • Package 15 - Stairs (Design-Build) • Package 16 - Precast • Package 17 - Passenger Loading Bridges • Package 18 - Special Systems (Design-Build)

Page 15: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 15

• This subcontract includes excavation & backfill for foundations.

• The underslab gravel is included with this bid package.

• Please note that the attachment hardware for connection of the precast shear walls are part of this contract.

• Multiple mobilizations are required for the concrete work at the airside (Sterile Corridor & Passenger Walkway).

Page 16: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 16

• Pricing is to be base on the Drawings and Specification issued on October 17, 2016

• Airside phasing: We are only allowed to take 2 gates (per concourse) at a time.

• Demolition and Clear and Grub is to include all Site Demo including but not limited to AC pavement, site concrete, AOA pavement, all shown utilities to be removed, removal of abandon duckbanks, bollards etc. Demolition is to include the removal of the canopy attached to concourse A at the GT Lot.

• Installation of all Wet Utilities: Water, Storm Drain, IWS, Sewer

• Design build all shoring and underpinning for the IAF and Raised Pedestrian Walkway. All shoring needs to be designed/stamped by a registered engineer in the state of Washington.

Page 17: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 17

• Pricing is to be base on the Drawings and Specification issued on October 17, 2016

• Airside phasing: We are only allowed to take 2 gates (per concourse) at a time.

•Replace AOA concrete paving.

• Includes fine grading and installation of base.

• Coordinate with the fueling system and utility contractor for all adjustments.

Page 18: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 18

• Pricing is to be base on the Drawings and Specification issued on October 17, 2016

• Airside phasing: We are only allowed to take 2 gates (per concourse) at a time.

• Installation and testing of all fueling system.

• Include all flushing of fueling system. Provide all trucking and tanks for the flushing. Include all fuel and fuel disposal and restocking.

• Coordinate with AOA concrete pavement contractor to insure hydrants are adjusted to grade.

Page 19: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 19

• Waterproofing Scope includes: - Sheet Membrane Waterproofing at Foundation Walls - Sheet Membrane Waterproofing at In Ground Elevator Pits - Drainage Board at Bus Turnaround Retaining Wall - Sheet Membrane Waterproofing at Grease Interceptor & Isolation Valve Pits - Crystalline Waterproofing at Elevator, Escalator and Moving Walkway Pits

Page 20: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 20

• Roofing Scope includes:

- PVC Membrane Roofing at Arrivals Building - One Color, 10'-0 Wide Rolls (Roof Slide #1)

- Alternate for Two Colors per Current Plan Drawing - PVC Membrane Roof at Pedestrian Bridge Roof (Roof Slide #2) - Pedestrian Roof Sloped Sections - by Metal Panel Sub - Vegetated Roof at Tug Tunnel Roof and at Level 02 Roof Garden • Flashing and Curbs - Curbs at Skylights - Roof Penetrations and Tie Downs

Page 21: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 21

Page 22: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 22

Page 23: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 23

• Interior pan filled stairs are located at the interior of the building.

• Exterior "air side" stairs are a metal plate tread with a galvanized finish.

• Egress mezzanine stairs are required.

• The subcontract includes fabrication and erection.

• Architectural stairs in IAF, SC & PW are not part of this contract.

Page 24: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 24

• Supplier is required to stage 4 shear walls on site to aid in erection.

• Please note there is a requested alternate to provide standard gray in lieu of white.

• Mock ups for finish, color and construction are going to be important factors. • An anchor bolt pattern supplied to the foundation contractor is going to be required.

Page 25: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 25

• Scope includes: Two (2) new PLBs Ten (10) new Fixed Walkways Eleven (11) Refurbished PLBs One PLB Relocated from Terminal A to SSAT **Note - No work at the existing PLBs for Gates A5 and A14 (ALT) • Bid Alternates: a. Upgrade tires at Existing PLBs b. Upgrade Finishes c. Add PC Air at Existing PLBs (currently in Mechanical scope) d. Add Refurbish 11 Existing PLBs at SSAT

Page 26: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 26

Page 27: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 27

Page 28: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 28

• Work scope is based on the Information Technology and Special Systems Visioning

Document included in the PDD and on CBP Airport Technical Design Standard requirements.

• The Special Systems Matrix was developed to assist the bidders in understanding procurement, configuration, installation, and testing responsibilities as the stakeholder IT groups will play an active role in activating new equipment.

• The Systems Manager will be a key player in coordinating and managing all division 27 and 28 Special Systems Work.

• In most instances, we are extending the existing stakeholder systems.

• There is UG communications ductbank and OSP cabling work included in the scope that will be the immediate focus.

Page 29: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 29

Page 30: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 30

Page 31: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 31

• Bidder Overview • Proposal Form • Attachments to Proposal • Appendix

• Subcontract Agreement

• Exhibit A – Contract Documents

• Exhibit B – Scope of Work – Per Package • Exhibit B1 – Package Specific

• Exhibit C – Payment &

Performance Bonds

.

RFP Package Contents • Exhibit D – Supplementary

Conditions

• Exhibit D-1 – Letter of Assent to PLA

• Exhibit E – Insurance Requirements

• Exhibit J – Owner Flow Down Provisions

• Exhibit R – Release of Lien

• Logistics Plan – Parking & Access Points

Page 32: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 32

Page 33: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 33

Page 34: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 34

Small/Diverse Business Participation – Scoring Factor • Clark Construction Group & Port of Seattle

o History of Commitment and Core Values o Community Development > Small Business Development

• Overall Project Goal -- 12% SCS Participation / SBE Participation 17.5%

o Includes SBE/MBE/WBE/DBE/DVBE or Small and Diverse firms o Small/Diverse Business Participation involves All Tiers o Participation will be part of the Best Value Evaluation in proposals

o Each package has specific goals

• Clark SeaTac IAF Website Resource

o www.clarkseataciaf.com under the small business page. o King County SCS Directory

• Small Business Meet & Greet November 7th, 2016 9:00 a.m. - 11:00 a.m.

Page 35: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 35

Subcontractor Suggested Opportunities – Scoring Factor

o Provide Innovative & Creative Ideas

o Support Performance & Quality Standards

o Result in Cost, Schedule & Operational Savings

Page 36: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

Page 36

International Arrivals Facility

Completing & Submitting Proposals Each trade package shall include the following:

• Fully completed and executed Proposal Form (Attachment 1) • Proposal value. • Letter from Surety confirming bondability • Insurance Verification Letter • PLA Letter of Assent (see subcontract Exhibit D-1) • Completed “Proposers SCS/SBE Participation Summary” (Attachment 2) • Acknowledgement of receipt of issued Addenda. • Detailed Proposal Analysis (Attachment 3) • Subcontractor Suggested Opportunities From (Attachment 4)

Page 37: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

Page 37

What’s Next for Trade Packages 9,10,12 – 18 Proposal Process

International Arrivals Facility

• Job Walk Today

• Small Business Meet & Greet November 7th, 2016 • RFP Bid Due Date November 15th, 2016

• Interviews November 22nd,2016 - Trade Package 18

Remaining Packages - As Required

• Contract Awards December 2016

www.clarkseataciaf.com

Page 38: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

International Arrivals Facility

Page 38

• Bring the project in below budget. • Open new facility on-time in the fall of 2019. • Encourage robust SCS/SBE participation • Deliver an iconic passenger bridge from SSAT to the new IAF • A modern and efficient international passenger processing facility using latest technology.

Future Goals

Page 39: Seattle-Tacoma International Arrivals Facility Trade ... · 10/1/2016  · Seattle-Tacoma International Arrivals Facility Trade Packages 9,10,12-18 Pre-Proposal Meeting ... • Roofing

Page 39

International Arrivals Facility