47
Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director - Construction

Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

  • Upload
    others

  • View
    9

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Second Avenue Subway

Community Board 8

Second Avenue Subway Task Force Update

November 1, 2016

Tom Peyton

Second Avenue Subway

Program Director - Construction

Page 2: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Phase 1 Overview

• The Re-routed Q

train will travel

from the new 96th

Street Station

south through

Manhattan and

into Brooklyn,

terminating at

Coney Island

Page 3: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Current Progress

• The Second Avenue Subway Project is on budget

and scheduled for revenue service in December

2016

• Overall Construction is 98% complete as of October 1, 2016

• NYC Transit revenue service training is underway

Page 4: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

96th St. Station Finishes, Systems, Ancillary Buildings and Entrances

86th St. Station Finishes, Systems, Ancillary Buildings and Entrances

72nd St. Station Finishes, Systems, Ancillary Buildings and Entrances

63rd St. Station Upgrade

All Stations Track, Power, Signals & Communications Systems

5 Active Contracts

Page 5: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Testing

Track Geometry Car – September 2016

Page 6: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Testing

Track Geometry Car – September 2016

Page 7: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Testing

Pre Revenue Service Train – October 2016

Page 8: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Station Areas

Page 9: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

63rd Street Station Rehabilitation

Station Upgrade Contract

Contract Value incl. AWOs: $190.8 M

Award Date: January 13, 2011

Forecast Completion: December 2016

Page 10: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Construction Progress

Architectural finishes are near completion and station

systems testing is underway

Sidewalk reconstruction is complete

Work zone on the NE corner of 64th Street and Third Avenue has been removed

Plaza on the NW corner of 63rd Street and Third Avenue

has been opened to the public

Page 11: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Current Progress

The Plaza at 63rd Street and Third Avenue is open to the public.

Page 12: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Current Progress

Ancillary 2 (NW corner of 63rd Street & Third Avenue)

Page 13: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Current Progress

Entrance 1 (SE corner of 63rd Street & Third Avenue)

Page 14: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Project Completion Look Ahead

STATION

Completion of ceilings and wall tiles, lighting, and column

enclosures

Testing of mechanical, electrical, and plumbing systems in

new station area

ENTRANCE 1

Installation of finishes and tiles

Testing of elevators and escalators

STREETSCAPE

Trees in the station area will be planted this fall season

Page 15: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

72nd Street Station

Finishes, MEP Systems, Ancillary Buildings and Entrances Contract

Contract Value incl. AWOs: $286.1 M

Award Date: February 14, 2013

Forecast Completion: December 2016

Page 16: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Construction Progress

The station and track has been energized

Ancillary 1 (NW corner of 69th Street and Second Avenue) and

Ancillary 2 (NW corner of 72nd Street and Second Avenue)

façade work is nearing completion

Entrance 1 and Entrance 2 escalator installation nearing

completion

Entrance 3 (SE corner of 72nd Street and Second Avenue)

façade work and elevator installation nearing completion

Tunnel Smoke Systems Management (TSSM), HVAC, Fire

Protection System (FPS), elevator and escalator testing in

progress

Page 17: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Current Progress

Ancillary 1 (NW corner of 69th Street & Second Avenue)

Page 18: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Current Progress

Ancillary 2 (NW corner of 72nd Street & Second Avenue)

Page 19: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Current Progress

Entrance 3 (SE corner of 72nd Street & Second Avenue)

Page 20: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Current Progress

Sidewalk Restoration (east side of 70th-71st Street & Second Avenue)

Page 21: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Current Progress

Sidewalk Restoration (east side of Second Avenue between 72nd and 73rd Streets)

Page 22: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Current Progress

Sidewalk Restoration (NE corner of 73rd Street and Second Avenue)

Page 23: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Project Completion Look Ahead

MAIN STATION CAVERN

Installation of:

Floor tiles, ceiling panels, conduits, mechanical, electrical

and plumbing systems at the mezzanine level

Tunnel Smoke Systems Management (TSSM), HVAC, Fire

Protection System (FPS), elevator and escalator testing in

progress

Installation of fare array gates and turnstiles

ENTRANCE 1

Architectural finishes and lighting work to continue at escalator

incline portion of Entrance 1

Installation of street and mezzanine-level escalators

Installation of wall tiles, duct work, conduit work and finishes

Page 24: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Project Completion Look Ahead

ANCILLARY 1, ANCILLARY 2, ENTRANCE 3

Construction of façades

Electrical and mechanical equipment installation and

testing for revenue service

Installation of escalators and elevators at Ancillary 2

Page 25: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

86th Street Station

Finishes, Entrances, Ancillaries, and MEP Systems Contract

Contract Value: $223,000,000

Award Date: June 12, 2013

Forecast Completion: December 2016

Page 26: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

86th Street Station Progress

Façade installation has begun on Ancillary structures

Test trains are running in the station

The structural frame for the elevator at E. 86th Street has

been installed

East side sidewalk restoration is nearing completion

Installation of artwork by MTA Arts & Design is underway

Fan testing at Ancillary structures is underway

Page 27: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Construction Progress

27

Installation of façade at Ancillary 1 (NE corner of 83rd Street)

Page 28: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Construction Progress

Sidewalk restoration at 83rd Street (SW side)

Page 29: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Construction Progress

Sidewalk restoration on the east side of Second Avenue (82nd – 83rd Streets)

Page 30: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Construction Progress

Sidewalk restoration on the east side of Second Avenue (87th – 88th Streets)

Page 31: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Project Completion Look Ahead

82nd Street to 88th Street

Completion of east side sidewalk restoration between 82nd

and 88th Streets

Installation of Ancillary 1 and 2 façade tile

West side sidewalk restoration will begin on Second Avenue

between 84th and 88th Streets

Page 32: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

83rd Street between 2nd and 3rd Avenues

Above ground work will continue including installation of building

finishes on Ancillary 1

Sidewalk reconstruction work

86th Street between 1st and 2nd Avenues

Sidewalk and elevator finishing work

86th Street between 2nd and 3rd Avenues

Above ground work including installation of building finishes on Ancillary 2

Project Completion Look Ahead

Page 33: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Underground Construction

Installation of architectural finishes; wall panels, tiles, floor

tile, acoustical panels and service carriers on the platform

and mezzanine levels

Installation of station signage and customer information

screens (CIS)

Installation of art work

Project Completion Look Ahead

Page 34: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

96th Street Station

Finishes, MEP Systems, Ancillary Buildings and Entrances Contract

Contract Value: $324,600,000

Award Date: June 22, 2012

Forecast Completion: December 2016

Page 35: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

96th Street Station Progress

• Sidewalks restored along east

and west side of Second

Avenue, side streets nearly

complete

• Tree planting scheduled for

November

• Roadway restoration on side

streets in process

• Final testing of station safety,

HVAC, elevators, and

escalators

• Station finishes, wayfinding

signs, art and floor tile nearly

completeInstallation of street level elevator cab at Entrance 3 during testing

Page 36: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

96th Street Station Progress

Façade of Ancillary 2 west side of Second Avenue

and 97th Street

Page 37: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

96th Street Station Progress

Façade of Ancillary 1 east side of Second Avenue

and 93rd Street

Page 38: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

96th Street Station Progress

Bike lane striping on the east side of Second Avenue

104th – 105th Streets 93rd – 94th Streets

Page 39: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

96th Street Station Progress

Bus lane striping west side of Second Avenue

between 98th – 99th Streets

Page 40: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

96th Street Station Progress

Sidewalk restoration south side of 97th Street

between First & Second Avenues

Page 41: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

96th Street Station Progress

Sidewalk restoration matching tint and pattern west side of

Second Avenue and 92nd Street

Page 42: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

96th Street Station Progress

Installation of entrance canopy east side of Second Avenue at 94th Street

Page 43: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

96th Street Station Progress

Installation of entrance glass west side of Second Avenue

between 95th – 96th Streets

Page 44: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Project Completion Look Ahead

• Completion of street level restoration

• Tree planting in the fall planting season

• Completion of station finishes

• Advanced testing of all systems before handover to NYCT

• Completion of Entrance 2 & Entrance 3 glass canopy and

plaza pavers

Page 45: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

45

Track, Power, Signals and Communications Systems Contract

Contract Value incl. AWOs: $292.8 M

Award Date: January 18, 2012

Forecast Completion: December 2016

Systems Installation

Page 46: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

• Signal system has been installed

• Con Edison feeders at 86th and 96th

Street stations are energized

• Geometry trains were run and

interferences with systems were

resolved

• Signal train and stress train ran in

October as scheduled

• In service testing is complete

• Inspection is ongoing

Systems Installation

Installation of wayside traction

power cables to 3rd Rail

Page 47: Second Avenue Subwayweb.mta.info/capital/sas_pdf/CB8 SAS Task Force Nov 1 2016.pdfSecond Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director

Questions