Second LHC Splices Review. Work Organisation for LS1. Outline. What has to be done ? Main splices Other activities Organization chart and roles Planning Resources Conclusions. Work reported here is the continuation of the tremendous and detailed work done by F Bertinelli. - PowerPoint PPT Presentation
Citation preview
Technology Department
Second LHC Splices Review
Outline
What has to be done ?Main splicesOther activities
Organization chart and roles Planning Resources Conclusions
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
Work reported here is the continuation of the tremendous and detailed work done by F Bertinelli
Work Organisation for LS1
1/20J.Ph. Tock
Technology Department
Second LHC Splices Review
What has to be done …?
To consolidate the superconducting circuits
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
Main splices in the arc DFBA circuits (A Perin) Replace cryomagnets Consolidate connection cryostatsNB: Other activities not linked directly to SC circuits:
PIMs, Helium level gauges, Y lines, DN200, …
2/20J.Ph. Tock
Technology Department
Second LHC Splices Review
Replace cryomagnets
28th of November 2011
Work Organisation for LS1Second LHC Splice Review Courtesy S Izquierdo
3/20J.Ph. Tock
Technology Department
Second LHC Splices Review
Replace cryomagnets
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
14 cryodipoles, 3 SSSs
[ ]
High internal splice resistance
Under assessment : Cryomagnets with wrong beam screens types
Q7R3
4/20J.Ph. Tock
Technology Department
Second LHC Splices Review
Replace cryomagnets
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
Courtesy A MussoCryomagnets coordination workspace :
https://espace.cern.ch/cryomagnet-coordination/default.aspx
5/20J.Ph. Tock
Technology Department
Second LHC Splices Review
Consolidate connection cryostats
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
The plan is :•Measure and if necessary consolidate the CC 11L8•Consolidate the CC in 11L3 & 11L1•Measure / inspect all the CCs to check no displacement
Details in ECR: LHC-LE-EC-0003
6/20J.Ph. Tock
Technology Department
Second LHC Splices Review
Installation of DN 200
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
To be installed during LS1 in 23, 45 (part), 78 & 81: About 600 units
7/20J.Ph. Tock
Technology Department
Second LHC Splices Review
Other interventions (not exhaustive)
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
• PIMs (# 45 to be replaced)
-Buckled during warm-up ≈ 18 (RF ball test) -Heavily damaged : ≤ 10-Preventive replacements :+ Arc extremities 18/32 in baseline
•Consolidation of SAM Helium level gauges and DN160It is planned to consolidate the 2 remaining ones: Q6R2&L8 Support from MME
•Repair of leaking Y-lines
It is planned to consolidate the 2 known cases (S78:17-19R7 & S81:19-22R8)
8/20J.Ph. Tock
Technology Department
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
Start at P5 / clockwise
5
1
82
3
4
7
6
High inner splice
SSS
Highest leakElectrical integrity issue
Beam opticsDS Coll.(For mem.)
Spread all around : work on leaks, PIMs,
SAM (He, DN160)
Y-lines repairCC Consolidation / InspectionDN 200 installation
Triplet braid (End of LS1 for rad prot)
Cryo-dipole
Circuit and splices issues
Goal : Special interventions completed before the train arrives : To be checked 9/20
J.Ph. Tock
Technology Department
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
Long Shutdown 1F. Bordry
Consolidation of the superconducting circuits: JPh TockMain arc splices cons.
“The train”F Savary #52
Open/Close IC [DN200]A Musso #32
-Sleeves cutting-BB surfacing-Shunt installation-Splice de-&resoldering (15%)
Special interventions “SIT”N Bourcey #15
-Cryomagnets exchange-Connect. Cryostat cons.-PIMs-Specific issues-Heavy NC
-Opening/ Closure of IC Partial and complete W bellows & ther. shields-Installation of DN200
Quality AssuranceR Ostojic #39
-Electrical QC: C Scheuerlein #17 See presentation-Welding QC: JM Dalin-Beam vacuum QC: C Garion-Open/close IC QC: D Bodart-QA manager support
ELQATE-MPE
N Catalan #23-Continuity-HV test
Leak TestTE-VSC
P Cruikshank #19-Beam lines-Cryogenics lines-Insulation vacuum
Project Office M Pojer #11
-Radiation protection-Safety-Access
-Coordination with Survey, Instrumentation, Transport, LS1 planning, QPS, cryogenics,… Test teams on a chain of IC -Reporting tools
DFBAA Perin [#12
(TBC)]-Splices and BB
Organisation Chart
10/20J.Ph. Tock
TIG weldingS Atieh #14
- Orbital & manual
Technology Department
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
Open/Close IC [DN200]A Musso #32
-Opening/ Closure of IC Partial and complete W bellows & ther. shields-Installation of DN200
Detailed roles
Open interconnections for : Consolidation of main splices Installation of DN200
Partial opening first Recovery of RP samples (LHC-LI-EC-
0001) Special interventions
Install DN200 (3,5 sectors)Reclose interconnections
11/20J.Ph. Tock
Technology Department
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
Detailed roles
Main arc splices cons. “The train”F Savary #52
-Sleeves cutting-BB surfacing-Shunt installation-Splice de-&resoldering
Was covered in details by previous presentationsEnsure coordination from opening to readiness for reclosure of M sleeves [Individual IC]
12/20J.Ph. Tock
Technology Department
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
Detailed roles
Special interventions “SIT”N Bourcey #15
-Cryomagnets exchange-Connect. Cryostat cons.-PIMs-Specific issues-Heavy NC
Was covered in previous slidesPolyvalent teamWill intervene on heavy NC to avoid slowing down the work of the main train
DFBAA Perin [#12
(TBC)]-Splices and BB
See presentation by A Perin tomorrowStill to be defined
13/20J.Ph. Tock
Technology Department
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
Detailed roles
The QA manager will:Coordinate QA activitiesEnsure that an adequate level of Quality Assurance is applied, especially in terms of traceability (MTF) and documentationEnsure a timely management of the non-conformities, minimizing the impact on the overall scheduleEnsure that production parameters are analysed in time to give an early warning in case of drift. Identify as early as possible critical issues that could jeopardize the consolidation work
Quality AssuranceR Ostojic #39
-Electrical QC: C Scheuerlein #17 See presentation-Welding QC: JM DalinOperators, tooling, procedures qualificationQC during production (Visual inspection)Off-line samples-Beam vacuum QC: C GarionProtection and inspection of Bellows, PIMsEndoscopy of beam lines-Open/close IC QC: D BodartVisual inspectionProtection of critical surfaces-QA manager supportTooling, inspection, reporting
14/20J.Ph. Tock
Technology Department
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
Planning
Rate: 4 weeks for each activity so 53 IC/weekDimensioned to 60 IC/week: 10% marginRemember : Series installation at 30 IC/week !
F Bertinelli @ 1st splices review
Courtesy P Fessia
15/20J.Ph. Tock
Technology Department
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
ID Task Name Duration
130 Point 8 90 days131 Cryo maintenance 18 wks132 Sector 81 210 days133 Preliminary powering tests - ph.2 4 edays134 ELQA before warm-up 4 days135 Preliminary PT78 4 edays136 Preliminary PT12 4 edays137 Warm-up 5 ewks138 Interconnections train 70 days139 Opening W 3 wks140 Bellows inspection & protection, cryo-thermometers3 wks141 Cutting PIMs 4 wks142 Endoscopy beam lines 4 wks143 Repair, reinstall & tack PIMs 4 wks144 Cutting M sleeves 4 wks145 Removal of IC splices insulation 4 wks146 QC, R8, busbar resistance 4 wks147 Busbar surface machining 4 wks148 Solder shunt 4 wks149 Desolder/resolder/shunt splices 4 wks150 Spools 4 wks151 QC splices/shunts 4 wks152 Mounting & QC insulation 4 wks153 ELQA 4 wks154 Welding M sleeves & PIMs 6.6 wks155 QC welding & leak testing 6.6 wks156 Closure 4 wks157 VAC sectors leak test 6 wks158 IC Non Conformities 3 wks159 Pressure test 2 edays160 DN200 6 wks161 Possible transport of magnet for sector 78 12 wks162 Cool-down 5 ewks163 ELQA 2 wks164 Powering tests - ph.2 6 wks165 PT78 6 wks
Interconnections train
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12
Courtesy K Foraz
One typical sector
16/20J.Ph. Tock
Technology Department
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
Global Planning
•Preliminary powering tests•Warm-up
•Opening•Splice consolidation(incl. internal leak tests)
•Closure•Leak tests (Ins vacuum)•Preparation for cool-down•Cool-down
•ELQA@cold
•Powering tests
Courtesy K Foraz
14 months
1st sector cold tested (2nd one), one year after the start of LS1 !
Consolidation of main splices in 4 sectors in parallel (13 km)
17/20J.Ph. Tock
Technology Department
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
Resources
LHC LS1(#195)
TE(#146)
EN(#21)
BE(#15)
PH(#7)
Not ID(#6)
New resources have been identified since the last review
Collaboration agreement under finalisation with PAEC for:-Opening/Closure of IC (#21)-Busbar machining (#11)-Welding (#6)
18/20J.Ph. Tock
Technology Department
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
Resources
> 60% have to be trained !Some rotation in staff (Collaborations) > 200 individualsChallenge to have this in parallel with work in tunnel
TrainedIdent, To trainNew FSUMssing
19/20J.Ph. Tock
Technology Department
Second LHC Splices Review
Conclusions
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
• Organisation chart defined and most of the key roles are assigned• Workplan almost defined
DFBA consolidation definition is starting nowResources to be identified
• Most of resources are identified • BUT: Commitments to be kept
To be reviewed with tooling optimization and test
with updated durations
•The production rate (53 IC/week) is ambitious• QA/QC will be implemented to ensure the required quality level• No (very little) margin for extra work, bad surprises 20/20
J.Ph. Tock
Technology Department
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
21/20J.Ph. Tock
Technology Department
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
Spare slides
22/20J.Ph. Tock
Technology Department
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
0 5 10 15 20-2
0
2
4
6
8
10
Electric resistance (n)
Fru
ptu
re (kN
)
Cable 02 oxidized RTCable 02 no oxidized 4.3KCable 01 no oxidized, pretinned 4.3KCable 01 oxidized, no pretinned 4.3KCable 01 no oxidized, no pretinned 4.3K
Courtesy S Izquierdo23/20
J.Ph. Tock
Technology Department
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
Resources status for splices train
Activity Trained Id, TBT Missing TOT Remark
Open/Close IC 8 21 22 20 PAEC, (7 DUBNA), 2 MSC
IC op/clos QC 4 4 3 BE-OP, 1 MSC-MNC
Cut M sleeves (PIMs) 2 10 12 10 PAEC
Busbars surfacing 7 7 7 MSC-MNC
Elec conn (shunt/splice) 8 9 3 20 MSC
Splice QC 4 13 17 MSC, 10 BE-OP
ELQA 13 10 23 3 MPE, 20 Krakow
Weld M sleeves (PIMs) 6 9 15 MME
Weld QC 6 6 MME
Leak test 12 7 19 VSC
TOTAL 46 96 3 145
More needs to supervise PAEC : 2 trained for open/closure to identify and 1 extra for cutting
24/20J.Ph. Tock
Technology Department
28th of November 2011
Work Organisation for LS1Second LHC Splice Review
Resources for Other activities
Activity Trained Id, TBT Missing TOT Remark
Bellows insp, prot, end 3 5 8 VSC, 6 Krakow
Repair, tack PIMs 1 1 2 VSC, 2 FSU
DN 200 7 1 8 7 DUBNA
Special Interv Team 10 5 15 Was 20
Logistics 3 3 MSC-LMF
Coordination 2 6 3 11 MSC, 2 BE-OP
QA 1 3 1 5 TE-HDO,…
TOTAL 27 18 5 50
Grand total 73 114 8 195