AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION 1
PRELIMINARIES AND GENERAL
BILL NO 1 PRELIMINARIES
Unless otherwise stated all the following items shall be deemed to fall into Lump Sum Preliminaries Work Group 190 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
The JBCC Principal Building Agreement (March 2014 Edition 6.1) prepared by the Joint Building Contracts Committee shall be the applicable building agreement, amended as hereinafter described
BUILDING AGREEMENT AND PRELIMINARIES
The JBCC Principal Building Agreement contract data form an integral part of this agreement
The ASAQS Preliminaries (March 2014 edition) published by the Association of South African Quantity Surveyors for use with the JBCC Principal Building Agreement shall be deemed to be incorporated in these bills of quantities
The contractor is deemed to have referred to the abovementioned documents for the full intent and meaning of each clause
The clauses in the abovementioned documents are hereinafter referred to by clause number and heading only. Where standard clauses or alternatives are not entirely applicable to this agreement such modifications, corrections or supplements as will apply are given under each relevant clause heading and such modifications, corrections or supplements shall take precedence notwithstanding anything to the contrary contained in the abovementioned documents
-1-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
Where any item is not relevant to this agreement such item is marked N/A (signifying "not applicable")
The Model Preambles for Trades (2008 edition) as published by the Association of South African Quantity Surveyors shall be deemed to be incorporated in these bills of quantities and no claims arising from brevity of description of items fully described in the said Model Preambles will be entertained
PREAMBLES FOR TRADES
Supplementary preambles are incorporated in these bills of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the Model Preambles
The contractor's prices for all items throughout these bills of quantities shall take account of and include for all of the obligations, requirements and specifications given in the Model Preambles and in any supplementary preambles
Should the contractor select Option A in terms of clause 26.9.4 of the contract data for the purpose of adjustment of these preliminaries, the amount entered into the amount column in these preliminaries is to be divided into one or more of the three categories provided namely fixed (F), value related (V) and time related (T)
PRICING OF PRELIMINARIES
SECTION A: PRINCIPAL BUILDING AGREEMENT
Clause 1.0 - Definitions and interpretation1
Interpretation (A1-A7)
Pricing of bills of quantities
-2-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
The contractor is to allow opposite each item for all costs in connection therewith. All prices to include, unless otherwise stated, for all materials, fabrication, conveyance and delivery, unloading, storing, unpacking, hoisting, labour, setting, fitting and fixing in position, cutting and waste (except where to be measured in accordance with the standard system of measurement), patterns, models and templates, plant, temporary works, returning of packaging, duties, taxes, imposts, establishment charges, overheads, profit and all other obligations arising out of the agreement
Items left unpriced will be deemed to be covered in prices against other items throughout these bills of quantities and no claim for any extras arising out of the contractor's omission to price any item will be entertained
Prices for all plant, temporary works, services and other items shall include for the supply, maintenance, operating cost and subsequent removal and making good as necessary
Legal status of contractor
If the contractor constitutes a joint venture consortium or other unincorporated grouping of two or more personsthen:
1. These persons are deemed to be jointly and severally
liable to the employer for the performance of this
agreement
ItemF:............................. V:............................ T:............................
Clause 2.0 - Law, regulations and notices2
Health and safety
-3-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
Without limiting the generality of the provisions of clause 2.0, the contractor's attention is drawn to the provisionsof Construction Regulations issued in terms of the Occupational Health and Safety Act, 1993. It is specifically stated that the employer shall prepare a documented health and safety specification for the works and that the employer shall ensure that the contractor has made provision for the cost of health and safety measures during the execution of the works. The contractor shall price opposite this item for compliance with the act and the regulations and the reasonable provisions of the aforementioned health and safety specification [2.1]
Item
Clause 3.0 - Offer and acceptance
F:............................. V:............................ T:............................
3
Item
Clause 4.0 - Assignment and cession
F:............................. V:............................ T:............................
4
Clause 5.0 - Contract documents5
Provision is made in the summary page of these bills of quantities for the inclusion of Value Added Tax (VAT)
Priced document as specification
If any ambiguity exists between the specifications in the bill of quantities and the drawings, the principal agent must be made aware of such ambigiuty prior to submission of the tender document. In any event where such ambiguity has not been highligted before submission of the tender document, the bill of quantities will take preference.
No claim wil be entertained for such event
-4-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
Electronic issue of drawings
All drawings for this project will be issued electronically and the contractor shall be deemed to have received such drawings on the date that such drawings have been dispatched electronically [5.5]
ItemF:............................. V:............................ T:............................
Clause 6.0 - Employer's agents6
Delegated authority
The authority of the principal agent to perform duties for specific aspects of the works is delegated to the agents.
ItemF:............................. V:............................ T:............................
7
Item
Clause 7.0 - Design responsibility
F:............................. V:............................ T:............................
8
Item
Clause 8.0 - Works risk
F:............................. V:............................ T:............................
9
Insurance and security (A8-A11)
Item
Clause 9.0 - Indemnities
F:............................. V:............................ T:............................
10
Item
Clause 10.0 - Insurances
F:............................. V:............................ T:............................
11
-5-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
Item
Clause 11.0 - Security
F:............................. V:............................ T:............................
12
Item
Extension of waiver of lien
The contractor shall ensure that a waiver of lien is included in all subcontracts and that the works executed on the site are kept free of all liens and other encumbrances at all times [11.10]
F:............................. V:............................ T:............................
Clause 12.0 - Duties of the parties
F:............................. V:............................ T:............................
13
Execution (A12 - A17)
Clause 12.2.15 - Enclosure of the works
The contractor shall erect, maintain and remove at completion hoardings with gantries, fans, safety screens, barriers, access gates, covered gangways and the like as necessary for the enclosure of the works and elements thereof, all for the protection of the public and others [12.2.15]
14
Clause 12.2.18 - Office accommodation
F:............................. V:............................ T:............................
15
Clause 12.2.18 - Notice boards
The contractor shall erect in a position approved by the principal agent, maintain and remove at completion a notice board as recommended by the South African Institute of Architects listing the names and logos of the employer, the contractor and the professional consultants. No subcontractor or supplier notice boards may be erected [12.2.18]
16
-6-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
Geotechnical Report
A Geotechnical report will be avilable from the principal agent if needed. Contact details are as per contract data
17
ItemF:............................. V:............................ T:............................
18
Item
Clause 13.0 - Setting out
Encroachments
The contractor shall notify the principal agent if any encroachment of adjoining foundations, buildings, structures, pavements, boundaries, services, etc exist in order that the necessary arrangements may be made forthe rectification of any such encroachments [13.2.1]
F:............................. V:............................ T:............................
19
Item
Clause 14.0 - Nominated subcontractors
F:............................. V:............................ T:............................
20
Item
Clause 15.0 - Selected subcontractors
F:............................. V:............................ T:............................
21
Clause 16.0 - Direct contractors
In respect of direct contractors the contractor shall:
22
Allow the use of personnel welfare facilities, where provided
Provide water, lighting and single phase electric power to a position within 50m of the place where the direct contract work is to be carried out, other than fuel or power for commissioning of any installation
-7-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
Permit the direct contractor to use erected scaffolding, hoisting facilities, etc provided by the contractor, in common with others having the like right while it remainserected on the site [16.1]
ItemF:............................. V:............................ T:............................
Item
Clause 17.0 - Contract instructions
Site instructions
Instructions issued on site are to be recorded in a site instruction book which is to be supplied and maintained on site by the contractor
F:............................. V:............................ T:............................
23
Item
Clause 18.0 - Interim completion
F:............................. V:............................ T:............................
24
Completion (A18 - A24)
Item
Clause 19.0 - Practical completion
F:............................. V:............................ T:............................
25
Item
Clause 20.0 - Sectional completion
F:............................. V:............................ T:............................
26
Item
Clause 21.0 - Defects liability period and final completionF:............................. V:............................ T:............................
27
Item
Clause 22.0 - Latent defects liability period
F:............................. V:............................ T:............................
28
-8-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
Item
Clause 23.0 - Revision of date for practical completion
Substitution of materials and goods
The removal or substitution of any materials and goodswhich do not conform to the specification or the contract drawings shall not constitute grounds for the extension of the construction period nor for the adjustment of the contract value [17.1.8, 23.1 & 2]
F:............................. V:............................ T:............................
29
Item
Clause 24.0 - Penalty for late or non-completion
The tenderer to refer to the contract data for penalty amounts
F:............................. V:............................ T:............................
30
Clause 25.0 - Payment31
Payment (A25 - A27)
Materials and goods stored off site
The inclusion of materials and goods stored off site in the amount authorised for payment shall be at the sole discretion of the principal agent and such inclusion shall only be considered upon the provision, by the contractor, of an approved security
Fluctuations in costs
All fluctuations in costs are for the contractor's account (fixed price contract)
-9-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
Item
Prices submitted
Where prices are submitted by the contractor or subcontractor during the progress of the works in respect of contract instructions or in regard to a claim under the terms of the agreement and notwithstanding the fact that such prices may be used in an interim payment certificate, there is to be no presumption of acceptance. Should the principal agent wish to accept any such prices prior to the issue of the certificate of final completion, it shall be in writing
F:............................. V:............................ T:............................
Clause 26.0 - Adjustment of the contract value and final account
32
Item
Cost of claims
All costs incurred by the contractor in the preparation of claims shall be borne by the contractor
The contractor shall review, assess and adjudicate any claims received by him from any subcontractor and thereafter submit same to the principal agent with a recommendation to assist the principal agent in adjudicating the claim [26.6]
F:............................. V:............................ T:............................
Item
Clause 27.0 - Recovery of expense and/or loss
F:............................. V:............................ T:............................
33
Item
Clause 28.0 - Suspension by the contractor
F:............................. V:............................ T:............................
34
Suspension and termination (A28 - A29)
-10-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
Item
Clause 29.0 - Termination
F:............................. V:............................ T:............................
35
Item
Clause 30.0 - Dispute resolution
F:............................. V:............................ T:............................
36
Dispute resolution (A30)
Item
Agreement
The required information of the parties and the amount of the contract sum shall be inserted in the agreement for signature of the agreement by the parties
F:............................. V:............................ T:............................
37
Contract data
After submission of his tender the contractor is to complete the tenderer's selection in the contract data together with the employer and principal agent.
38
ItemF:............................. V:............................ T:............................
39
SECTION B: PRELIMINARIES
Item
Clause 1.1 - Definitions
F:............................. V:............................ T:............................
40
Interpretation (B1)
Item
Clause 1.2 - Interpretation
F:............................. V:............................ T:............................
41
-11-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
Item
Clause 2.1 - Checking of documents
F:............................. V:............................ T:............................
42
Documents (B2)
Clause 2.2 - Provisional bills of quantities43
ItemF:............................. V:............................ T:............................
Item
Clause 2.3 - Availability of construction information
Provisional sums
The Provisional sums allocated for subsequent trades included in this agreement will be separately procured, based on multiple procurement of subcontractors during the construction period
F:............................. V:............................ T:............................
44
ItemF:............................. V:............................ T:............................
Item
Clause 2.4 - Ordering of materials and goods
The quantities are measured provisionally and can not be used to order materials.
F:............................. V:............................ T:............................
45
Item
Clause 3.1 - Previous work - dimensional accuracy
F:............................. V:............................ T:............................
46
Previous work and adjoining properties (B3)
Item
Clause 3.2 - Previous work - defects
F:............................. V:............................ T:............................
47
-12-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
Item
Clause 3.3 - Inspection of adjoining properties
F:............................. V:............................ T:............................
48
Item
Clause 4.1 - Defined works area
F:............................. V:............................ T:...........................
49
The site (B4)
N/A
Clause 4.2 - Handover of site in stages
F:............................. V:............................ T:............................
50
Item
Clause 4.3 - Enclosure of the works
F:............................. V:............................ T:............................
51
Item
Clause 4.4 - Geotechnical investigation
F:............................. V:............................ T:............................
52
Item
Clause 4.5 - Encroachments
F:............................. V:............................ T:............................
53
N/A
Clause 4.6 - Existing premises occupied
F:............................. V:............................ T:............................
54
Item
Clause 4.7 - Services - known
F:............................. V:............................ T:............................
55
-13-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
N/A
Clause 4.8 - Protection of trees and/or relevant natural features
F:............................. V:............................ T:...........................
56
Item
Clause 5.1 - Management of the works
F:............................. V:............................ T:............................
57
Management of contract (B5)
Item
Clause 5.2 - Progress meetings
F:............................. V:............................ T:............................
58
Item
Clause 5.3 - Technical meetings
F:............................. V:............................ T:............................
59
Item
Clause 6.1 - Samples of materials
F:............................. V:............................ T:...........................
60
Samples, shop drawings and manufacturer's instructions (B6)
Item
Clause 6.2 - Workmanship samples
F:............................. V:............................ T:............................
61
Item
Clause 6.3 - Shop drawings
F:............................. V:............................ T:............................
62
Item
Clause 6.4 - Compliance with manufacturer's instructions
F:............................. V:............................ T:............................
63
-14-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
Item
Clause 7.1 - Deposits and fees
F:............................. V:............................ T:............................
64
Deposits and fees (B7)
Item
Clause 8.1 - Water
F:............................. V:............................ T:............................
65
Temporary services (B8)
Item
Clause 8.2 - Electricity
F:............................. V:............................ T:............................
66
Item
Clause 8.3 - Ablution and welfare facilities
F:............................. V:............................ T:............................
67
Item
Clause 8.4 - Communication facilities
F:............................. V:............................ T:............................
68
Clause 9.1 - Responsibility for prime cost amounts69
Prime cost amounts (B9)
Item
Where details of materials for which prime cost amounts are to be allowed are readily available, the quantity surveyor may elect to insert the relevant prime cost amounts in measured items, which measured items shall contain sufficient detail for the contractor to price for fixing and installation, waste, etc
F:............................. V:............................ T:............................
-15-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
Item
Clause 10.1 - General attendance
General attendance is defined as being the duties of the contractor in terms of clause 12.2 of the JBCC n/s subcontract agreement
F:............................. V:............................ T:............................
70
Attendance on subcontractors (B10)
N/A
Clause 10.2 - Special attendance
F:............................. V:............................ T:............................
71
Item
Clause 11.1 - Protection of the works
F:............................. V:............................ T:............................
72
General (B11)
Item
Clause 11.2 - Protection/isolation of existing/sectionally occupied works
F:............................. V:............................ T:............................
73
Item
Clause 11.3 - Security of the works
F:............................. V:............................ T:............................
74
Item
Clause 11.4 - Notice before covering work
F:............................. V:............................ T:............................
75
Item
Clause 11.5 - Disturbance
F:............................. V:............................ T:............................
76
-16-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
Item
Clause 11.6 - Environmental disturbance
F:............................. V:............................ T:............................
Item
Clause 11.7 - Works cleaning and clearing
F:............................. V:............................ T:............................
77
Item
Clause 11.8 - Vermin
F:............................. V:............................ T:............................
78
Item
Clause 11.9 - Overhand work
F:............................. V:............................ T:............................
79
N/A
Clause 11.10 - Tenant installations by direct contractors
F:............................. V:............................ T:............................
80
Item
Clause 11.11 - Advertising
F:............................. V:............................ T:............................
81
12.1 - Provisional bills of quantities [2.2]
The quantities are provisional Yes
Preliminaries schedule (B12)
12.2 - Availability of construction information [2.3]
Construction documentation is complete No
12.3 - Previous work - dimensional accuracy [3.1]
12.4 - Previous work - defects [3.2]
-17-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
12.5 - Inspection of adjoining properties [3.3]
12.6 - Defined works area [4.1]
12.7 - Handover of site in stages [4.2]
12.8 - Enclosure of the works [4.3]
12.9 - Geotechnical investigation [4.4]
Geotechnical Report is available from the Principal Agent. Please see contract data for contact details if needed
12.10 - Existing premises occupied [4.6] - No
12.11 - Services - known [4.7] - Refer to drawings for erf connections of services
12.12 - Protection of trees and/or relevant natural features [4.8] - No
12.13 - Water [8.1]
Refer to Contract Data
12.14 - Electricity [8.2] Refer to Contract Data
12.15 - Ablution and welfare facilities [8.3]
Refer to Contract Data
12.16 - Communication facilities [8.4]
Email: YesCell Phone: Yes
12.17 - Protection of the works [11.1]
The existing works buildings must be protected and any damage that my occur to such buildings due to the contractor's default will be born by the contractor
-18-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
12.18 - Protection/isolation of existing/sectionally occupied works [11.2]
No
12.19 - Disturbance [11.5]
All work is to be carried out in such a manner as to cause no unacceptable or unreasonable dust, noise, vibrations, nuisance, inconvenience, annoyance and the like to the public, others, other properties and traffic in so far as they exceed the permissible limitations set by government legislation or by the local authority. Any delays, stoppages and the like arising from or in order to comply with the above will not constitute grounds for an adjustment to the construction period or contract value whatsoever
12.20 - Environmental disturbance [11.6]
Controlling all forms of pollution
The contractor shall be responsible for and take all precautions in controlling by whatever means necessary all forms of pollution emanating from the site during the construction period due inter alia to noise, artificial light, wind-blown sand, dust, deposits of mud, etc
The contractor is to ensure that all roads which border the site and is used by the contractor during the execution of the works are kept clean and free of any dirt or debris caused by the execution of the works
Warranties for materials and workmanship
Where warranties for materials and/or workmanship are called for, the contractor shall obtain a written warranty,addressed to the employer, from the entity supplying the materials and/or doing the work and shall deliver same to the principal agent on the final completion of the contract
82
SECTION C: SPECIFIC PRELIMINARIES
-19-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
The warranty shall state that workmanship, materials and installation are warranted for a specific period from the date of final completion and that any defects that may arise during the specified period shall be made good at the expense of the entity supplying the materialsand/or doing the work, upon written notice to do so
Item
The warranty will not be enforced if the work is damaged by defects in the execution of the works, in which case the responsibility for replacement shall rest entirely with the contractor
F:............................. V:............................ T:............................
Item
Overtime
Should overtime be required to be worked for any reason whatsoever, the costs of such overtime is to be borne by the contractor unless the principal agent has specifically authorised, in writing, prior to execution thereof, that costs for such overtime are to be borne by the employer
F:............................. V:............................ T:............................
83
Item
Co-operation of the contractor for cost management
It is specifically agreed that the contractor accepts the obligation of assisting the principal agent in implementing proper cost management. The contractor will be advised by the principal agent of all cost management procedures which will be implemented to ensure that the final building cost does not exceed the budget
F:............................. V:............................ T:............................
84
-20-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
Rev 01
National Nuclear Regulator
Item
Confidentiality
The contractor undertakes to maintain in confidence any and all information regarding this project and shall obtain appropriate similar undertakings from all subcontractors and suppliers. Such information shall not be used in any way except in connection with the execution of the works
No information regarding this project shall be published or disclosed without the prior written consent of the employer
F:............................. V:............................ T:............................
85
Item
Media releases
All rights of publication of articles in the media, together with any advertising relating thereto or in any way connected with this project, shall vest with the employer
The contractor together with his subcontractors shall not, without the prior written consent of the employer, cause any statement or advertisement to be printed, screened or aired by the media
F:............................. V:............................ T:............................
86
Category : Fixed R........................................
Category : Value R........................................
Category : Time R........................................
SUMMARY OF CATEGORIES
-21-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to to collection R
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1Total Brought Forward from Page No.
Preliminaries
Section No. 1
Bill No. 1
AmountPageNo
Preliminaries and General
COLLECTION
Rev 01
National Nuclear Regulator
-22-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried Forward R
Preliminaries
Section No. 1
Bill No. 1
AmountPageNo
Preliminaries and General
COLLECTION
Brought Forward R
Rev 01
National Nuclear Regulator
21
20
19Total Brought Forward from Page No.
-23-
PreliminariesBill No. 1Preliminaries and GeneralSection No. 1
Carried to Final Summary R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 2
BUILDERS WORK
BILL NO 1
EARTHWORKS
For Preambles see "Model Of Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemed to fall into Earthworks Work Group 104 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
Wherever a trade name for any product has been described, the tenderer's attention is drawn to the fact that any other product of equal quality may be used subject to the written approval of the principal agent being obtained prior to the closing date for submission of tenders
If prior written approval for an alternative product is not obtained, the product described shall be deemed to have been tendered for
TRADE NAMES
SUPPLEMENTARY PREAMBLES
Use "assumed to be" if no trial holes, soils investigations, etc have been carried out - discuss with engineer. Use "Trial holes indicate that" where the ground has been investigated by means of trial holes
Nature of ground
-24-
EarthworksBill No. 1Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
A soils investigation has been carried out on site by the engineer and the report is annexed to these bills of quantities. Descriptions of excavations shall be deemed to include all ground conditions classifiable as "earth" described in the above report and where conditions of a more difficult character are indicated these are separately measured
Nature of ground
Descriptions of carting away of excavated material shall be deemed to include loading excavated material onto trucks directly from the excavations or, alternatively, from stock piles situated on the building site
Carting away of excavated material
REMOVAL OF TREES ETC
8NoTree stump exceeding 200mm and not exceeding 500mm girth
1
Taking out and removing, grubbing up roots and filling in holes
EXCAVATION, FILLING, ETC
206m3Trenches2
Excavation in earth not exceeding 2m deep
456m3Holes3
80m3Soft rock4
Extra over trench and hole excavations in earth for excavation in
40m3Hard rock5
214m3Surplus material from excavations and/or stock piles on site to a dumping site to be located by the contractor
6
Extra over all excavations for carting away
-25-
EarthworksBill No. 1Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
1 349m2Sides of trench and hole excavations not exceeding 1,5m deep
7
Risk of collapse of excavations
ItemKeeping excavations free of all water other than subterranean water
8
Keeping excavations free of water
476m3Backfilling to trenches, holes, etc9
Earth filling obtained from the excavations and compacted to 95% Mod AASHTO density
261m3Under floors, steps, pavings, etc10
Earth filling supplied by the contractor compacted to 98% Mod AASHTO density
382m2Under paving11
Sand filling compacted to 100% Mod AASHTO density
SOIL POISONING
634m2Under paving etc12
Tordon or similar approved Weedkiller mixed in the proportion of 200ml weedkiller to 4000ml water and applied at a rate of 20litre/ha.
663m2
Under floors etc including forming and poisoning shallow furrows against foundation walls etc, filling in furrows and ramming
13
Soil insecticide in accordance with SANS 5859
1 926m2To bottoms and sides of trenches etc14
-26-
EarthworksBill No. 1Builders WorkSection No. 2
Carried to to collection R
Earthworks
Section No. 2
Bill No. 1
AmountPageNo
Builders Work
COLLECTION
Rev 01
National Nuclear Regulator
26
25
24Total Brought Forward from Page No.
-27-
EarthworksBill No. 1Builders WorkSection No. 2
Carried Forward to Summary of Section No. 2 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 2
BUILDERS WORK
BILL NO 2
CONCRETE, FORMWORK AND REINFORCEMENT
For Preambles see "Model Of Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemed to fall into Concrete Work Group 110 for Contract Price Adjustment Provisions.
CPAP ADJUSTMENT
SUPPLEMENTARY PREAMBLES
The costs of making, storing and testing of concrete test cubes as required under clause 7 "Tests" of SABS 1200 G shall include the cost of providing cube moulds necessary for the purpose, for testing costs and for submitting reports on the tests to the architect. The testing shall be undertaken by an independent firm or institution nominated by the contractor to the approval of the architect. (Test cubes are measured separately)
Cost of tests
Description of formwork shall be deemed to include use and waste only (except where described as "left in" or "permanent"), for fitting together in the required forms, wedging, plumbing and fixing to true angles and surfaces as necessary to ensure easy release during stripping and for reconditioning as necessary before re-use
Formwork
-28-
Concrete, Formwork and ReinforcementBill No. 2Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
The vertical strutting shall be carried down to such construction as is sufficiently strong to afford the required support without damage and shall remain in position until the newly constructed work is able to support itself.
Formworks to soffits of solid etc shall be deemed to be slabs not exceeding 250mm thick unless otherwise described
Formwork to sides of bases, pile caps, ground beams, etc will only be measured where it is prescribed by the engineer for design reasons. Formwork necessitated by irregularity or collapse of excavated faces will not be measured and the cost thereof shall be deemed to be included in the allowance for taking the risk of collapse of the sides of the excavations, provision for which is made in "Earthworks"
-29-
Concrete, Formwork and ReinforcementBill No. 2Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
Penetron admix added to concrete at time of batching, temperature of the concrete mix should be above 40 degrees celcius dosed at 0.8% by weight of all cementitious weight content in design mix.
Under certain conditions the dosage rate may be between 2-3% depending on the quantity and type of cementitious materials.
Dry Batch Operation: Add Penetron Admix in powder form to the drum of the ready-mix truck. Drive the truck under the batch plant and add 60-70% of the required water along with 300-500 lbs (136-227kg) of aggregate. Mix the materials for 2-3 minutes to ensure the Admix is distributed evenly throughout the mix water. Add the balance of materials to the ready-mix truck in accordance with standard batch practices.
Central Mix Operation: Mix Penetron Admix with water to form very thin slurry (e.g. 40lbs/18kg of powder mixed with six gallons/22.7 litres of water). Pour the required amount of material into the drum of the ready-mix truck. The aggregate, cement and water should be batched and mixed in the plant in accordance with standard practices (taking into account the quantity of water that has already been placed in the ready-mix truck). Pour the concrete into the truck and mix for at least 5 minutes to ensure even distribution of the Penetron Admix throughout the concrete.
Penetron
UNREINFORCED CONCRETE CAST AGAINST EXCAVATED SURFACES
25m3Surface blinding under footings and bases1
10MPa/19mm concrete
2m3Concrete fill in cavity wall2
15MPa/20mm concrete
REINFORCED CONCRETE CAST AGAINST EXCAVATED SURFACES
-30-
Concrete, Formwork and ReinforcementBill No. 2Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
57m3Strip footings3
25MPa/19mm concrete
92m3Bases4
40m3Surface beds on waterproofing5
30MPa/19mm concrete
"LAFARGE" OR SIMILAR APPROVED ARTIVIA CONCRETE
56m3Surface beds on waterproofing6
30MPa/19mm concrete
REINFORCED CONCRETE CAST IN FORMWORK
109m3Slabs including beams and inverted beams7
30MPa/19mm concrete
44m3Walls in foundations8
367m3Walls9
4m3Columns in foundations10
12m3Columns11
0.1m3Circular Columns in foundations12
1m3Circular Columns13
141NoMaking and testing 150 x 150 x 150mm Concrete strength test cube (set of 3)
14
TEST BLOCKS
CONCRETE SUNDRIES
-31-
Concrete, Formwork and ReinforcementBill No. 2Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
852m2Surface beds, slabs, etc15
Finishing top surfaces of concrete smooth with a steel trowel
40NoBedding approximately 15mm thick under 270 x 270mmbase plate including chamfered edges all round
16
15 MPa non-shrink grout
259m2On floors17
"Artivia" or similar apprved concrete and diamond grinding to floor, finish in dark grey
Unless otherwise stated all the following items shall be deemed to fall into Formwork work group 111 for Contract Price Adjustment Provisions.
CPAP ADJUSTMENT
FORMWORK
ROUGH FORMWORK (DEGREE OF ACCURACY ll)
2m2Beams18
Rough formwork to sides in foundations
244m2Walls19
55m2Rectangular columns20
40m2Rectangular stub columns21
OFF SHUTTER CONCRETE
6m2Square columns with total height not exceeding 3.5m above bearing level
22
Off shutter concrete with visible timber grain
2 004m2Walls23
-32-
Concrete, Formwork and ReinforcementBill No. 2Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
111m2Inner face of shaft walls24
201m2Rectangular columns25
15m2Edges exceeding 300mm high26
4No300mm Diameter column average 3.3m high27
Smooth formwork to circular columns
732m2Slabs propped up not exceeding 3.5m high28
Smooth formwork to soffits
MOVEMENT JOINTS ETC
181m15mm Joints not exceeding 300mm high29
Expansion joints with 15mm Thick softboard between vertical concrete surfaces or "similar approved"
17m25mm Saw cut joints in top of concrete30
Saw cut joints
Unless otherwise stated all the following items shall be deemed to fall into Reinforcement work group 114 for Contract Price Adjustment Provisions.
CPAP ADJUSTMENT
REINFORCEMENT
57.90tVarious Diameter bars31
Mild steel reinforcement to structural concrete work
1 347m2Type 193 fabric reinforcement in concrete surface beds, slabs, etc
32
Fabric reinforcement
-33-
Concrete, Formwork and ReinforcementBill No. 2Builders WorkSection No. 2
Carried to to collection R
Concrete, Formwork and Reinforcement
Section No. 2
Bill No. 2
AmountPageNo
Builders Work
COLLECTION
Rev 01
National Nuclear Regulator
33
32
31
30
29
28Total Brought Forward from Page No.
-34-
Concrete, Formwork and ReinforcementBill No. 2Builders WorkSection No. 2
Carried Forward to Summary of Section No. 2 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 2
BUILDERS WORK
BILL NO 3
MASONRY
For Preambles see "Model Of Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemed to fall into Masonry Work Group 118 for Contract Price Adjustment Provisions.
CPAP ADJUSTMENT
Wherever a trade name for any product has been described, the tenderer's attention is drawn to the fact that any other product of equal quality may be used subject to the written approval of the principal agent being obtained prior to the closing date for submission of tenders
If prior written approval for an alternative product is not obtained, the product described shall be deemed to have been tendered for
TRADE NAMES
BRICKWORK
Where sizes in descriptions are given in brick units, "one brick" shall represent the length and "half brick" the width of a brick
Sizes in descriptions
-35-
MasonryBill No. 3Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
Descriptions of hollow walls shall be deemed to include leaving every fifth perpend of the bottom course of the external skin open as a weep hole.
Hollow walls etc
Walls in two skins described as "bagged and sealed" shall be deemed to include having the outer face of the inner skin bagged with 1:6 cement and sand mixture and sealed with two coats "Brixeal" bitumen emulsion waterproofing coating.
FOUNDATIONS
39m2270mm Cavity wall1
Brickwork of NFX bricks (14 MPa nominal compressive strength) in class I mortar
SUPERSTRUCTURE
123m2Half brick walls2
Brickwork of NFP bricks in class II mortar
45m2One brick walls3
83m2270mm Cavity wall4
BRICKWORK SUNDRIES
622m75mm Wide reinforcement built in horizontally5
Brickwork reinforcement
1 478m150mm Wide reinforcement built in horizontally6
32m100 x 70mm Lintels in lengths not exceeding 3m7
Prestressed fabricated lintels
STONE CLADDING
-36-
MasonryBill No. 3Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
140m2
Stone cladding for (exterior) vertical surfaces fixed to and including cold-formed metal framing including galvanised shelf angles, structural supports, anchors and other built-in components for building into natural veneer stone.
8
Stone cladding as per architects specifications
-37-
MasonryBill No. 3Builders WorkSection No. 2
Carried to to collection R
Masonry
Section No. 2
Bill No. 3
AmountPageNo
Builders Work
COLLECTION
Rev 01
National Nuclear Regulator
37
36
35Total Brought Forward from Page No.
-38-
MasonryBill No. 3Builders WorkSection No. 2
Carried Forward to Summary of Section No. 2 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 2
BUILDERS WORK
BILL NO 4
WATERPROOFING
For Preambles see "Model Of Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemed to fall into Waterproofing Work Group 120 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
Wherever a trade name for any product has been described, the tenderer's attention is drawn to the fact that any other product of equal quality may be used subject to the written approval of the principal agent being obtained prior to the closing date for submission of tenders
If prior written approval for an alternative product is not obtained, the product described shall be deemed to have been tendered for
TRADE NAMES
SUPPLEMENTARY PREAMBLES
Waterproofing of roofs, basements, etc shall be laid under a ten year guarantee. Waterproofing to roofs shall be laid to even falls to outlets etc with necessary ridges, hips and valleys. Descriptions of sheet or membrane waterproofing shall be deemed to include additional labour to turn-ups and turn-downs
Waterproofing
-39-
WaterproofingBill No. 4Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
-40-
WaterproofingBill No. 4Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
DAMP-PROOFING OF WALLS AND FLOORS
21m2In walls1
One layer of 375 micron "Consol Plastics Brikgrip DPC" embossed damp proof course
4m2On shower floors2
"abe" or similar approved waterproof paint
663m2Under surface beds3
One layer of 250 micron "Consol Plastics Gunplas Black" or similar approved waterproof sheeting sealed at laps with "Gunplas Pressure Sensitive Tape"
377m2Under walkway paving and seating area4
WATERPROOFING TO ROOFS, BASEMENTS, ETC
119m2On waterproofing to roofs5
One layer "Derbigum SP4" or similar approved waterproofing membrane with 75mm side laps and 100mm end laps sealed to primed surface to falls and cross falls by torch fusion finished with two coats bituminous aluminium paint. Waterproofing to be installed by an approved Derbigum contractor under a 10 year guarentee.
12m2On balcony floors6
PROTECTIVE ROOFING PAINT
57m2On concrete roofs7
Two coats bituminous aluminium paint
SEALING STRIPS, JOINT SEALANTS, ETC
-41-
WaterproofingBill No. 4Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
181m12 x 25mm In expansion joints in floors including raking out expansion joint filler as necessary
8
"Sikaflex PRO-3" or similar approved polysulphide sealing compound, including backing cord, bond breaker, primer, etc
-42-
WaterproofingBill No. 4Builders WorkSection No. 2
Carried to to collection R
Waterproofing
Section No. 2
Bill No. 4
AmountPageNo
Builders Work
COLLECTION
Rev 01
National Nuclear Regulator
42
41
40
39Total Brought Forward from Page No.
-43-
WaterproofingBill No. 4Builders WorkSection No. 2
Carried Forward to Summary of Section No. 2 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 2
BUILDERS WORK
BILL NO 5
ROOF COVERINGS ETC
For Preambles see "Model Of Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemed to fall into Metal roofing (steel) Work Group 124 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
Wherever a trade name for any product has been described, the tenderer's attention is drawn to the fact that any other product of equal quality may be used subject to the written approval of the principal agent being obtained prior to the closing date for submission of tenders
If prior written approval for an alternative product is not obtained, the product described shall be deemed to have been tendered for
TRADE NAMES
PROFILED METAL SHEETING AND ACCESSORIES
726m2Roof covering with pitch not exceeding 25 degrees1
"Colortech Rhynsinc aluminium Saflok 410 in Hazy Grey" or equivalent roof sheets, colour light grey @ 7° deg pitch with 150x50x20x2.5 CFLC purlins (elsewhere measured)
-44-
Roof CoveringsBill No. 5Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
80mHead wall flashing 300mm girth2
"Colortech Rhynsinc aluminium Saflok 410 in Hazy Grey" or similar approved steel sheet accessories to preceding roof coverings.
50mSide wall flashing 300mm girth3
9mValley gutters (inverted rolled top ridge capping)4
58m2Satin Black Hula bond panel Side cladding5
1500 x 1100 x 4mm "Hulabond" or similar approved satin black aluminium composite panel cladding fixed to and including wrap around portal frame structure
24mHead wall flashing 300mm girth6
25mSide wall flashing 300mm girth7
ROOF AND WALL INSULATION
790m2On purlins8
100mm Thick Lambdaboard® polyisocyanurate core board, core density 34kg/m³, laminated on both sides
EAVES, VERGES, ETC
50m12 x 225mm Fascia boards including galvanised steel H-profile jointing strips
9
"Everite Nutec" or similar approved fibre-cement medium density plain flat sheets.
22m80 x 200mm Barge boards including galvanised steel H-profile jointing strips
10
-45-
Roof CoveringsBill No. 5Builders WorkSection No. 2
Carried to to collection R
Roof Coverings
Section No. 2
Bill No. 5
AmountPageNo
Builders Work
COLLECTION
Rev 01
National Nuclear Regulator
45
44Total Brought Forward from Page No.
-46-
Roof CoveringsBill No. 5Builders WorkSection No. 2
Carried Forward to Summary of Section No. 2 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 2
BUILDERS WORK
BILL NO 6
CARPENTRY AND JOINERY
For Preambles see "Model Of Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemed to fall into Carpentry and Joinery Work Group 126 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
Wherever a trade name for any product has been described, the tenderer's attention is drawn to the fact that any other product of equal quality may be used subject to the written approval of the principal agent being obtained prior to the closing date for submission of tenders
If prior written approval for an alternative product is not obtained, the product described shall be deemed to have been tendered for
TRADE NAMES
SUPPLEMENTARY PREAMBLES
Particle board shall comply with the following specifications:
a) SABS 1300 Particle board: exterior and flooring type
b) SABS 1301 Particle board: interior type
Particle board:
-47-
Carpentry and JoineryBill No. 6Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
Descriptions of frames shall be deemed to include frames, transomes, mullions, rails, etc
Joinery:
Descriptions of hardwood joinery shall be deemed to include pelleting of bolt holes
Items described as "nailed" shall be deemed to be fixed with hardened steel nails or shot pins to brickwork or concrete
Fixing
Laminate finish shall be glued under pressure. Edge strips shall be butt jointed at junctions with adjacent similar finish
Decorative laminate finish:
ROOFS ETC
758m Roof 50 x 228mm Purlins1
SA Pine softwood grade 5
1 939m
Roof 50 x 75mm battening at 400mm centres for Rheinzink roof covering
2
726m218mm Plywood board fixed to battening3
SKIRTINGS
14m19 x 120mm Skirting nailed to brickwork and concrete wall
4
Wrought meranti
DOORS ETC
2No40mm Door 600 x 2032mm High (DT09)5
Grooved semi-solid timber leaf natural oak veneer stained
-48-
Carpentry and JoineryBill No. 6Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
2No40mm Door 762 x 2032mm High (DT08)6
16No40mm Door 813 x 2032mm High (DT01,DT10)7
2No40mm Door 1100 x 2032mm High (DT03)8
2No40mm Door 1500 x 2400mm High (DT02, DT07)9
1No40mm Door 762 x 2032mm High (FD03)10
"Bitcon" or simiar approved fire door and frame with B rating
1No40mm Door 813 x 2032mm High (FD02)11
4No40mm Door 1500 x 2032mm High (FD01)12
3No40mm Door 813 x 2032mm High (FSD01)13
Calcium silica mineral core door with masonite veneer panel and hardwood edging.
1No40mm Door 1100 x 2400mm High (FSD02)14
-49-
Carpentry and JoineryBill No. 6Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
DUCT COVERS
2m3500 x 800 x 12mm Grounds nailed fixed to and including SAP Frame 38 x 38mm
15
"Everite Nutec" or similar approved fibre-cement medium density plain flat sheets with 2-hour fire rating
5m3500 x 300 x 12mm Screwed to and including SAP frame 38 x 38mm
16
-50-
Carpentry and JoineryBill No. 6Builders WorkSection No. 2
Carried to to collection R
Carpentry and Joinery
Section No. 2
Bill No. 6
AmountPageNo
Builders Work
COLLECTION
Rev 01
National Nuclear Regulator
50
49
48
47Total Brought Forward from Page No.
-51-
Carpentry and JoineryBill No. 6Builders WorkSection No. 2
Carried Forward to Summary of Section No. 2 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 2
BUILDERS WORK
BILL NO 7
CEILINGS, PARTITIONS AND ACCESS FLOORING
For Preambles see "Model Of Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemed to fall into Ceiling Work Group 129 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
Wherever a trade name for any product has been described, the tenderer's attention is drawn to the fact that any other product of equal quality may be used subject to the written approval of the principal agent being obtained prior to the closing date for submission of tenders
If prior written approval for an alternative product is not obtained, the product described shall be deemed to have been tendered for
TRADE NAMES
SUPPLEMENTARY PREAMBLES
Items described as "nailed" shall be deemed to be fixed with hardened steel nails or pins, or to be shot-pinned, to brickwork or concrete
Fixing
-52-
Ceilings, partitions and Access FlooringBill No. 7Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
Items described as "plugged" shall be deemed to include screwing to fibre, plastic or metal plugs at not exceeding 500mm centres, and where described as "bolted", the bolts have been given elsewhere
Unless otherwise described ceilings shall be deemed to be horizontal
Ceilings
Prices for openings for light fittings, ventilation grilles, air conditioning diffusers, etcin ceilings are to include for any necessary additional support, trimming around, etc
Openings
All steel components for ceilings, partitions, etc are to begalvanised in accordance with SANS 121
Steel components
CEILINGS ETC
NAILED UP CEILINGS
89mSoffit of sloping bulkheads, size 600mm , suspended not exceedign 1m deep bolow roof truss
1
Gypsum board bulkhead 12,5mm thick skimmed and painted gypsum board bulkhead complete with ceiling framing system to dry wall specialist
SUSPENDED ACCOUSTIC CEILINGS
575m2Suspended ceiling2
Pre-painted 1200 x 600 x 15mm "OWA floating" acoustic panels or simlar approved on pre-painted exposed tee suspension system including main and cross tees, necessary hangers, grids, etc
147m2
Sloping ceilings suspended with varying heights in void not exceeding 3.5m below timber/steel purlins at 1000mm centres
3
-53-
Ceilings, partitions and Access FlooringBill No. 7Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
120m2Suspended ceiling4
Pre-painted 600 x 600 x 15mm "OWA floating" acoustic panels or simlar approved on pre-painted exposed tee suspension system including main and cross tees, necessary hangers, grids, etc
116m2Suspended ceiling5
6.4mm "Rhino" gypsum plasterboard with H-type pressed steel jointing strips with tee suspension system including main and cross tees, necessary hangers, grids, etc
184m2External ceiling at the walkway overhang6
Nutec plain ceiling board 2400 x 600 x 4mm thick including H-profile steel jointing strip
650m"Shadowline Type A-SM 25" cornices plugged7
"OWA" or similar cornices to suspended ceilings
-54-
Ceilings, partitions and Access FlooringBill No. 7Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
Unless otherwise stated all the following items shall be deemed to fall into Partitioning systems Work group 138 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
PARTITIONS ETC
69mPartitioning 3.45m high with bottom track plugged and top track fixed to suspended ceiling tees
8
"Isoboard SD" or similar approved 90mm full height "EHD type EPS cored sandwich panel system" partitioning system with structure and steel subframe according to the manufacturer's specifications
8NoExtra over partition 3.45m high for corner9
6NoExtra over partition 3.45m high for T-intersection10
2No1200 x 300mm Urinal divisions in white ceramic11
"Abalona" or similar approved
TOILET PARTITIONS
13mPartitioning 2.1m high with bottom and top tracks plugged
12
"Vitraflex" toilet partitioning with 20mm thick faced particle board bonded panels and natural anodised aluminium edging and top rails including fixing components and standard ironmongery comprising indicator bolts, coat hooks with door stops, toilet roll holders and rubber buffers
5NoExtra over partition 2.1m high for T-intersection13
10NoDoors14
Extra over partition for 40mm semi-solid flush door 813 x 1900mm high with veneer on both sides and hardwood edge strips to vertical edges hung to and including standard aluminium door frame
-55-
Ceilings, partitions and Access FlooringBill No. 7Builders WorkSection No. 2
Carried to to collection R
Ceilings, partitions and Access Flooring
Section No. 2
Bill No. 7
AmountPageNo
Builders Work
COLLECTION
Rev 01
National Nuclear Regulator
55
54
53
52Total Brought Forward from Page No.
-56-
Ceilings, partitions and Access FlooringBill No. 7Builders WorkSection No. 2
Carried Forward to Summary of Section No. 2 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 2
BUILDERS WORK
BILL NO 8
FLOOR COVERINGS, PLASTIC LININGS, ETC
For preambles see "Model Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemedto fall into Resilient floor and wall covering Work Group 130 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
Wherever a trade name for any product has been described, the tenderer's attention is drawn to the fact that any other product of equal quality may be used subject to the written approval of the principal agent being obtained prior to the closing date for submission of tenders
If prior written approval for an alternative product is not obtained, the product described shall be deemed to have been tendered for
TRADE NAMES
SUPPLEMENTARY PREAMBLES
Floor coverings, wall linings, etc shall, where applicable, be fixed with adhesive as recommended by the manufacturers of the flooring, linings, etc
Fixing
FLOOR COVERINGS
-57-
Floor Coverings, Plastic Linings, etc.Bill No. 8Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
13m2On floors1
500 x 500mm "Belgotex" or similar approved commercial Crossfire antistatic carpet tiles (PC= R 400.00/m2)
34m2On floors2
2.0mm x 1.2m wide "Floorwrx or similar approved fully flexible vinyl sheeting manufactured in accordance with SANS 786:2000, laid in FloorworX welded rod, sealed on completion (PC=R 300.00/m2)
410m2On floors3
"Aspen" or similar approved vinyl click floor tiles
12m2On Balcony floor4
230 x 1830 x 10mm Timber decking with 85mm including battons @ 600cc and stucture support
POLISH, SEALERS, ETC
41m22 coats wax polish on vinyl flooring5
Wax polish to vinyl flooring
-58-
Floor Coverings, Plastic Linings, etc.Bill No. 8Builders WorkSection No. 2
Carried to to collection R
Floor Coverings, Plastic Linings, etc.
Section No. 2
Bill No. 8
AmountPageNo
Builders Work
COLLECTION
Rev 01
National Nuclear Regulator
58
57Total Brought Forward from Page No.
-59-
Floor Coverings, Plastic Linings, etc.Bill No. 8Builders WorkSection No. 2
Carried Forward to Summary of Section No. 2 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 2
BUILDERS WORKS
BILL NO 9
IRONMONGERY
For preambles see "Model Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemedto fall into Ironmongery Work Group 132 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
Wherever a trade name for any product has been described, the tenderer's attention is drawn to the fact that any other product of equal quality may be used subject to the written approval of the principal agent being obtained prior to the closing date for submission of tenders
If prior written approval for an alternative product is not obtained, the product described shall be deemed to have been tendered for
TRADE NAMES
SUPPLEMENTARY PREAMBLES
-60-
IronmongeryBill No. 9Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
Where applicable the manufacturers' names or product catalogue titles are given in sub-headings preceding the items
Prices are to be based on the specific products/articles specified. If contractors wish to offer alternative products/articles for certain items, these items are to be clearly marked and the alternative specification given with supporting brochures, etc clarifying the features of the products/articles offered
On request returnable samples are to be provided to the principal agent for consideration
Proprietary items
Where applicable finishes to ironmongery are indicated by suffixes in accordance with the following listBS Satin bronze lacqueredCH Chromium platedSC Satin chromium platedSE Silver enamelledGE Grey enamelledAS Anodised silverAB Anodised bronzeAG Anodised goldABL Anodised blackPB Polished brassPL Polished and lacqueredPT Epoxy coatedSD Sanded
Finishes to ironmongery
Items described as "plugged" shall be deemed to include screwing to fibre, plastic or metal plugs in brickwork or concrete
Fixing
The contractor is requested to price the ironmongery as on "Extra Over" cost for the installation and supply.Replace all "Geze" Ironmongery with the specification:"Lockwood Neo Collection" as supplied by ASSA ABLOY.
Extra over for Ironmongery
HINGES, BOLTS, ETC
102No200 x 44mm Aluminium sinkless hinge in black1
"Assa Abloy" or similar approved
-61-
IronmongeryBill No. 9Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
57No100mm Black anodized hinge2
40NoGrade 13 stainless steel 102 x 75 x 2mm butt hinges, incluing stainless steel ball bearing
3
1No"Solenoid" lock, fail secure including lead cover4
16NoBlack anodized flush bolt5
6m"Abloy" Cable6
1NoSingle P/bolt 1200mm in black7
4NoDouble P/bolt P/bar 1200mm, black8
2NoRebate for 52110 lock, black9
12No"Cisa" Double throw deadlock and latch, black forend striker and bolts
10
2NoBathroom deadbolt11
11NoSwingbolt deadbolt lock in black12
6No"Adams Rite" 30Kg Maglock monitored, including bracket for 261 Mag
13
1NoNarrow stile euro profile hook bolt lock, black14
The following locks are to be suitable for master and grand master key operation
CATCHES, CABIN HOOKS, ETC
25NoCISA Euro profile double cylinder 65mm long lock, black, grand master keyed
15
"Assa Abloy" or similar approved
24No"Valli & Valli" Escuthcheons 31mm x 61mm, euro profile in black
16
24No"Lockwood" Euro profile cylinder escutcheon, black17
-62-
IronmongeryBill No. 9Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
7No"Union" Bathroom lock18
58No"Lockwood" square rose trim, black19
24NoRubber buffered door stop, black20
14No"Lockwood" square privacy trim, black21
7No"Lockwood" WC turn escutcheon, black22
7No"Lockwood" WC indicator escutcheon, black23
12NoHardware mounting bracket for stop width 54mm24
-63-
IronmongeryBill No. 9Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
HANDLES
21No"Lockwood" 304 grade stainless steel pull handles with black finish, back to back fixed at 600mm ccs.
25
"Assa Abloy" or similar approved
17No"Lockwood" passage lever handle set, black26
DOOR CLOSERS
4No"Assa Abloy" CAM Motion concealed door closer with hold open function
27
"Assa Abloy" or similar approved
9NoConcealed door closer 28
4NoFire door coordinator 1321mm including filler bar in black
29
9No"Assa Abloy" Door closer including parallel arm bracket in black
30
10NoCAM Action closer EN3-6 Black31
PANIC HARDWARE
3NoExidor Panic bolt for double door 2032mm high with one keep let into concrete
32
"Geze" or similar approved
BATHROOM FITTINGS
9No
Paper towel dispenser with paper size 200mm wide and security lock, plugged and screwed to the wall with stainless steel screws
33
"Stratos" or similar approved
9NoWaste bin wall mounted34
"Rodan" or similar approved
-64-
IronmongeryBill No. 9Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
15NoLockable double toilet roll holder plugged35
13NoSoap dispenser wall mounted36
11NoHygiene bag dispenser37
11NoSanitary towel/waste disposal38
9NoHands free electrical hand dryer39
"Franke" or similar approved
2NoParaplegic cranked grab rail 40
"Franke" or similar approved
2NoParaplegic valve grab rail41
2No300mm wide x 400mm High white bathroom cabinet plugged
42
"Elvinco" or similar approved
4No
2875mm x 600mm wide Vanity slabs with 3 circular wash hand basins embedded into the slab (Basins elsewhere)
43
TOPS, SHELVES, DOORS, MIRRORS, ETC
16NoMirror 500 x 900mm high44
4mm Silvered float glass copper backed mirrors with polished edges holed for and fixed with chromium plated dome capped mirror screws with rubber buffers to plugs in brickwork or concrete
SUNDRIES
8No"Mazac" Chrome plated hat and coat hook 156/82 (code: ESD01083)
45
"Geze" or similar approved
SHELVES ETC
-65-
IronmongeryBill No. 9Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
16m3800mm Single slot wall band plugged46
"Shelvit" or simiar approved with standard epoxy powder coated finish
110m400 x 20mm wide Shelf47
40No160mm x 120mm x 25mm Chrome bracket including M6 x 40mm hex setscrew zinc plated bolts
48
STEEL LOCKERS
6No
Bank of seven double compartment single door lockable lockers each 300 x 1800mm high with one shelf, bolted together and to wall with 30 x 30mm L section frame 100mm above finished floor level.
49
"Greenfield" or similar approved steel lockers with standard baked enamel finish
KITCHEN CUPBOARDS
1NoKitchen floor unit 2500 x 600 x 900mm high (4 doors and 1 section with 5 drawers)
50
"Kitchen Trends" or similar approved kitchen cupboards plugged
1NoKitchen floor unit 1000 x 600 x 900mm high (2 doors and 1 section with 5 drawers)
51
2NoGalvanized sink unit 2500 x 600 x 900mm high52
1No
Sink cupboard 3800 x 500 x 700mm high with sides, bottom, divisions, shelf, back and single hinged doors (sink elsewhere)
53
Approved kitchen cupboards of 16mm white melawood bottoms, sides, backs, shelves, doors, etc, in carcasses with doors and drawers of 16mm white melawood with 3mm PVC flat edge strips to all exposed edges, 32mm post-formed "Formica" faced chipboard tops of approved colour, chromium plated concealed cupboard hinges and approved handles, plugged
-66-
IronmongeryBill No. 9Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
VANITY TOP
6m2
20mm thick composite quartz slabs with gloss finish with all exposed edges T30 edged, fixed to supports (elsewhere specified) using dabs of 100% clear silicone adhesive at 200 to 300mm centres along all supports with all joints mitred at 45° and filled with matching polyester resin glue
54
Technistone "Gobi Black" or similar approved
-67-
IronmongeryBill No. 9Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
PINNING BOARDS, WRITING BOARDS, PROJECTION SCREENS, ETC
1No3000mm wide ×1200mm high55
"Mirrodex" or similar approved magnetic white board
16No1200mm wide ×1200mm high56
3NoTilting spring roller wall mounted projection screen 2000 x 1000mm high including overhead brackets plugged
57
-68-
IronmongeryBill No. 9Builders WorkSection No. 2
Carried to to collection R
Ironmongery
Section No. 2
Bill No. 9
AmountPageNo
Builders Work
COLLECTION
Rev 01
National Nuclear Regulator
68
67
66
65
64
63
62
61
60Total Brought Forward from Page No.
-69-
IronmongeryBill No. 9Builders WorkSection No. 2
Carried Forward to Summary of Section No. 2 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 2
BUILDERS WORK
BILL NO 10
STRUCTURAL STEELWORK
For preambles see "Model Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemedto fall into Structural steelwork in building Work Group 134 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
Wherever a trade name for any product has been described, the tenderer's attention is drawn to the fact that any other product of equal quality may be used subject to the written approval of the principal agent being obtained prior to the closing date for submission of tenders
If prior written approval for an alternative product is not obtained, the product described shall be deemed to have been tendered for
TRADE NAMES
SUPPLEMENTARY PREAMBLES
Descriptions of bolts shall be deemed to include nuts and washers
Descriptions
Descriptions of L-shaped and U-shaped anchor bolts shall be deemed to include bending, threading, nuts and washers and embedding in concrete
-70-
Structural SteelworkBill No. 10Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
Descriptions of expansion anchors and bolts and chemical anchors and bolts shall be deemed to include nuts, washers and mortices in brickwork or concrete
Descriptions of L-shaped and U-shaped anchor bolts shall be deemed to include bending, threading, nuts and washers and embedding in concrete. Where anchor bolts are described as embedded in sides or soffits of concrete it shall be deemed to include holes through formwork.
Descriptions of expansion anchors and bolts and chemical anchors and bolts shall be deemed to include nuts, washers and mortices in brickwork or concrete.
STEEL COLUMNS AND BEAMS TO WALKWAYS INCLUDING INORGANIC ZINC ETHYL SLICATE PRIMER
7.61t152 x 152mm x 6.0 x 26.16kg/m SHS-section columns in lengths exceeding 5m and not exceeding 8m
1
Welded columns in single lengths with flat section base, top, bearer and connection plates bolted to concrete
0.46t254 x 146 x 31 x 31.3kg/m I-section columns in lengths exceeding 5m and not exceeding 8m
2
160No300mm Long, 4 No, M16, GR 8.8 treaded bar welded to end plate
3
Bolts to columns, beams, etc
101No100mm Long, M12, GR 8.8 Chemical anchors bolted to concrete wall at 500mm coc.
4
4No1106mm x 300mm custom steel bracket 3 times bent to structural steel landing and column
5
STEEL ROOF TRUSSES INCLUDING INORGANIC ZINC ETHYL SLICATE PRIMER
-71-
Structural SteelworkBill No. 10Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
0.15t50 x 50 x 3.0 x 2.33 kg/m Lipped SAG Bars 6
Welded portal frames with flat section bearer, gusset and connection plates and L-section cleats bolted to concrete
10.55t305 x 165mm x 40kg/m I-section rafter7
200NoM12 Bolt, GR 8.8 Bolted to 50 x 50 x 5 x 3.77 kg/m L Cleate
8
Bolts to trusses etc
STEEL PURLINS, GIRTS, BRACING, ETC INCLUDING INORGANIC ZINC ETHYL SLICATE PRIMER
5.00tParallel Flange 260 x 90 x 36.3kg/m9
Purlins and girts bolted to steel
0.33t20mm thick base plate10
0.33t20mm Thick end plate11
0.88t60 x 60 x 5 x4.57kg/m Lipped top cord Bracing12
0.44t40 x 40 x 3 x1.77 kg/m Lipped top cord Bracing bolted to purlin and rafter on each side.
13
GALVANISED STEEL FLOORS, STAIRS, ETC
1.02tStaircase14
7.6mm "VASTRAP" plate welded with 5mm continuous fillet weld, or bolted, stairs to concrete and brick wall
2.40tLandings to staircases15
RS40 Rectagrip 40 x 3 non-slip raised dimple floor panels MENTIS with longitudinal bearer bars welded to bearers for landings
-72-
Structural SteelworkBill No. 10Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
ItemProvision for supplying a set of shop drawings for all structural steelwork
16
SHOP DRAWINGS
-73-
Structural SteelworkBill No. 10Builders WorkSection No. 2
Carried to to collection R
Structural Steelwork
Section No. 2
Bill No. 10
AmountPageNo
Builders Work
COLLECTION
Rev 01
National Nuclear Regulator
73
72
71
70Total Brought Forward from Page No.
-74-
Structural SteelworkBill No. 10Builders WorkSection No. 2
Carried Forward to Summary of Section No. 2 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 2
BUILDERS WORK
BILL NO 11
METALWORK
For preambles refer to "Model Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemedto fall into Metalwork Work Group 136, Aluminium Work Group 140, Stainless Steel Work Group 141, Aluminium Shop Fronts and Preglazed Windows for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
Wherever a trade name for any product has been described, the tenderer's attention is drawn to the fact that any other product of equal quality may be used subject to the written approval of the principal agent being obtained prior to the closing date for submission of tenders
If prior written approval for an alternative product is not obtained, the product described shall be deemed to have been tendered for.
TRADE NAMES
Descriptions of bolts shall be deemed to include nuts and washers
Descriptions
-75-
Metal WorkBill No. 11Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
Descriptions of expansion anchors and bolts and chemical anchors and bolts shall be deemed to include nuts, washers and mortices in brickwork or concrete
Metalwork described as"holed for bolt(s)" shall be deemed to exclude the bolts unless otherwise described
Items described as "plugged" shall be deemed to include screwing to fibre, plastic or metal plugs at not exceeding 600mm centres
Doors and windows shall comply with AAAMSA design criteria
Aluminium doors and windows
Glazing shall comply with SAGGA regulations. Glass shall be laminated sagety glass as shown on the window schedules/drawings appended to these bills of quantities. Glass thickness shall comply with SAGGA regulations irrespective of thicknesses shown on the schedules/drawings
Doors and windows shall be supplied with protective tape and plastic and shall be removed only once surrounding trades have been completed
For purpose made windows and doors, refer to drawingsannexed to these bills of quantities
-76-
Metal WorkBill No. 11Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
The following certificates shall be provided prior to commencement of site work:
1 A copy of the relevant AAAMSA Performance Test Certificate from the manufacturer/contractor supplying the architectural aluminium product
2 A Certificate of Conformance confirming that anodising has been processed in accordance with SANS 999 and SANS 1796 respectively
3 A Certificate of Conformance confirming that glazing has been installed in accordance with SANS 0137, ensuring that safety glazing materials have been
installed in the mandatory areas and that each individual pane of safety glazing materials has
been permanently marked
4 A warranty from the manufacturer of the laminated safety glass and/or hermetically sealed glazing units guaranteeing the products against delamination and colour degredation for a period of not less than five years
-77-
Metal WorkBill No. 11Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
GALVANIZED PRESSED STEEL DOOR FRAMES
4NoFrame for door 813 x 2032mm high (Type FSD01) (Drawing No AC-03-01)
1
1.6mm Rebated frames suitable for one brick walls
1NoFrame for door 1100 x 2032mm high (Type FSD02) (Drawing No AC 03 02)
2
4NoFrame for door 1500 x 2032mm high (Type FD01) (Drawing No AC 02 01)
3
1NoFrame for door 813 x 2032mm high (Type FD02) (Drawing No AC-02-02)
4
1NoFrame for door 762 x 2032mm high (Type FD03) (Drawing No AC-02-03)
5
1NoSize 2100 x 2400 High in concrete wall6
Transformer double door & frame with louvres
ALUMINIUM PURPOSE MADE WINDOWS, DOORS, ETC.
1NoWindow type 4855 x 1800mm high (AC-W10) Guard house window (Drawing No AL.01.04)
7
"Wispeco" or similar approved "L shaped" Bullet proof window glazed with toughened safety bulletproof glass
1NoWindow type 600 x 2100mm high (AC-W01) (Drawing No AC 05 01)
8
"Wispeco" or similar approved natural anodised aluminium windows glazed with 6mm toughened laminated safety glass
3NoWindow 800 x 2100mm high (AC-W02) (Drawing No AC 05 02)
9
8NoWindow type 800 x 6441mm high (AC-W03) (Drawing No AC 05 03)
10
-78-
Metal WorkBill No. 11Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
2NoWindow type (AC-W04) 2090 x 1400mm High (Drawing No AC 05 04)
11
Powder coated alumium windows glazed with 7.52mm toughened laminated safety clear low E glass with a U-Value of 3.68W/m² and SHGC of 0.53, plugged to brickwork
10NoWindow 1333 x 2400mm high (AC-W05) (Drawing No AC 05 05)
12
1NoWindow 1500 x 600mm High (AC-W06) (Drawing No AC 05 06)
13
1NoWindow type (AC-W07) 1900 x 2500mm High (Drawing No AC 05 07)
14
1NoWindows type (AC-W08) 1500 x 1200mm High (DrawingNo AC 05 08)
15
3NoWindow 600 x 1500mm High (AC-W09) ((Drawing No AC 05 09)
16
1NoWindow type 1200 x 1220mm high (AC-W11) (Drawing No AC 05 11)
17
1No1784 x 2425mm high Double door (Type DT06) (Drawing No AC-01-06)
18
Anodized black alumium Doors glazed with 7.52mm toughened laminated safety clear low E glass with a U-Value of 3.68W/m² and SHGC of 0.53, plugged to brickwork
1NoDoor 1145 x 2395mm high (Type SF01) ( Drawing No AC-07-01)
19
Dark grey anodised aluminium shopfronts including doors, sidelights and fanlights glazed with clear toughened safety glass and plugged to brickwork or concrete
2NoDoor 1160 x 2175mm high (Type SF02) ( Drawing No AC-07-02)
20
-79-
Metal WorkBill No. 11Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
1NoDoor 1285 x 2701mm high (Type SF03) ( Drawing No AC-07-03)
21
1NoDoor 913 x 2175mm high ( Type SF04) ( Drawing No AC-07-04)
22
1NoShopfront 3869 x 2750mm high (Type SF01) ( Drawing No AC-07-01)
23
1NoShopfront 10200 x 2700mm high (Type SF02) ( Drawing No AC-07-02)
24
1NoShopfront 3583 x 2701mm high (Type SF03) ( Drawing No AC-07-03)
25
4NoShopfront 3187 x 2701mm high (Type SF04) ( Drawing No AC-07-04)
26
1NoShopfront 4798 x 2751mm high (Type SF05) ( Drawing No AC-07-05)
27
1NoFrosted glazed door 1200 x 2032 mm High28
Extra- Over aluminium doors
1NoFrosted glazed door 1500 x 2400 mm High29
6NoFrosted glazed door 813 x 2032 mm High30
ALUMINIUM PURPOSE MADE FRAMES
15NoFrame for door 813 x 2032mm high (Type DT01/DT10) 31
Anodized black alumium door frames plugged to brickwork
1NoFrame for double door 1500 x 2400mm high (Type DT02) (Drawing No AC-01-02)
32
2NoFrame for door 1100 x 2032mm high (Type DT03) (Drawing No AC-01-03)
33
3NoFrame for door 1550 x 2325mm high (Type DT04) (Drawing No AC-01-04)
34
-80-
Metal WorkBill No. 11Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
1NoFrame for door 1502 x 2400mm high (Type DT05) (Drawing No AC-01-05)
35
1NoFrame for door 1500 x 2400mm high (Type DT07) (Drawing No AC-01-07)
36
2NoFrame for door 762 x 2032mm high (Type DT08) (Drawing No AC 01 08)
37
1NoFrame for door 600 x 2032mm high (Type DT09) (Drawing No AC 01 09)
38
1NoFrame for door 2100 x 2320mm high (Type DT12) (Drawing No AC 01 12)
39
CURTAIN WALLS
1NoCurtain Wall 18160 x 3205mm high (Type CW-05) (Drawing No AC-06-05)
40
Dark grey anodised aluminium curtain wall flush glazed with toughened safety glass to comply with SANS1263, AAAMSA and SAGGA standards and plugged to brickwork or concrete
1NoCurtain Wall 16300 x 3030mm high (Type CW-06) (Drawing No AC-06-06)
41
3NoCurtain wall 9200 x 7000mm high (AC-06-04) (Drawing No SK.02.02.03).
42
ALUMINIUM SUN LOUVRES
14No Louvre units for 730 x 630mm high opening.43
"Weather Master System" or similar approved system with 700 x 600mm fixed Aerofoil Natural Anodised finish aluminium louvre blades including frame for fixing.
ALUMINIUM HANDRAILS, BALUSTRADES, ETC
-81-
Metal WorkBill No. 11Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
56mBalustrade44
Aluminium panels with steel supports @1000mm ht- to Architects later detail
65m
Handrail raking to stairs, 50mm dia. steel as specified and screwed to to flat bar at 500mm centres fixed to a 20mm diameter curved bracket and fixed to a 60 x 60mm stainless steel which is fixed to the wall
45
9mBalustrade46
Glazed panels with steel supports @ 100mm high to balcony to architects later detail
NATURAL ALUMINIUM SCREENS, GATES AND FRAMES
52m21400 x 3100 x 8mm Thick aluminium screens powdercoated dark grey - to architects detail.
47
Screens and gates to and including structural steel frame as per manufacturers specifications
1No
1900 x 3100 x 8mm thick Aluminium gate or similar approved to the refuse area - to architects later detail & Specialists specification
48
-82-
Metal WorkBill No. 11Builders WorkSection No. 2
Carried to to collection R
Metal Work
Section No. 2
Bill No. 11
AmountPageNo
Builders Work
COLLECTION
Rev 01
National Nuclear Regulator
82
81
80
79
78
77
76
75Total Brought Forward from Page No.
-83-
Metal WorkBill No. 11Builders WorkSection No. 2
Carried Forward to Summary of Section No. 2 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 2
BUILDERS WORK
BILL NO 12
PLASTERING
For preambles refer to "Model Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemedto fall into Resilient floor and wall coverings Work Group 130 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
Wherever a trade name for any product has been described, the tenderer's attention is drawn to the fact that any other product of equal quality may be used subject to the written approval of the principal agent being obtained prior to the closing date for submission of tenders
If prior written approval for an alternative product is not obtained, the product described shall be deemed to have been tendered for
TRADE NAMES
SCREEDS
872m2125mm Average thick on floors and landings1
1:3 Screeds with compressive strength of 5 MPa steel trowelled on concrete
GRANOLITHIC
-84-
PlasteringBill No. 12Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
28m235mm Thick on floors and landings2
Untinted granolithic, on concrete
-85-
PlasteringBill No. 12Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
INTERNAL PLASTER
691m2On internal walls3
Cement plaster on brickwork
120m2On projecting and isolated columns4
52m2Concrete soffits5
Cement plaster on concrete
EXTERNAL PLASTER
118m2On walls6
Cement plaster on brickwork
78m2On walls7
Cement plaster on concrete
60m3 x 50mm Flat section brass dividing strips between different floor finishes
8
DIVIDING STRIPS ETC
-86-
PlasteringBill No. 12Builders WorkSection No. 2
Carried to to collection R
Plastering
Section No. 2
Bill No. 12
AmountPageNo
Builders Work
COLLECTION
Rev 01
National Nuclear Regulator
86
85
84Total Brought Forward from Page No.
-87-
PlasteringBill No. 12Builders WorkSection No. 2
Carried Forward to Summary of Section No. 2 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 2
BUILDERS WORK
BILL NO 13
TILING
For preambles refer to "Model Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemedto fall into Tiling Work Group 144 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
Wherever a trade name for any product has been described, the tenderer's attention is drawn to the fact that any other product of equal quality may be used subject to the written approval of the principal agent being obtained prior to the closing date for submission of tenders
If prior written approval for an alternative product is not obtained, the product described shall be deemed to have been tendered for
TRADE NAMES
SUPPLEMENTARY PREAMBLES
-88-
TilingBill No. 13Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
Unless described as "fixed with adhesive to plaster (plaster elsewhere)" descriptions of tiling on brick or concrete walls, columns, etc shall be deemed to include 1:4 cement plaster backing and descriptions of tiling on concrete floors etc shall be deemed to include 1:3 plaster bedding
Descriptions
-89-
TilingBill No. 13Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
WALL TILING
304m2On walls1
300 x 300mm Porcelain wall tiles fixed with tile adhesive to plaster and flush pointed with tinted jointing compound (PC = R 220.00/m2)
0.4m2On narrow widths2
FLOOR TILING
108m2On floors3
300 x 300mm Porcelain tiles (PC=R200,00/m2) delivered to site and fixed with adhesive to screed (screed elsewhere) and flush pointed with Dove Grey tinted grout
10m2On narrow widths 4
123mSkirting 150mm high of cut tiles5
-90-
TilingBill No. 13Builders WorkSection No. 2
Carried to to collection R
Tiling
Section No. 2
Bill No. 13
AmountPageNo
Builders Work
COLLECTION
Rev 01
National Nuclear Regulator
90
89
88Total Brought Forward from Page No.
-91-
TilingBill No. 13Builders WorkSection No. 2
Carried Forward to Summary of Section No. 2 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 2
BUILDERS WORKS
BILL NO 14
PLUMBING AND DRAINAGE
For preambles see "Model Preambles for Trades"
PREAMBLES
Unless otherwise stated all the following items shall be deemedto fall into Plumbing Work Group 148, Drainage Work group 146 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
Wherever a trade name for any product has been described, the tenderer's attention is drawn to the fact that any other product of equal quality may be used subject to the written approval of the principal agent being obtained prior to the closing date for submission of tenders
If prior written approval for an alternative product is not obtained, the product described shall be deemed to have been tendered for
TRADE NAMES
SUPPLEMENTARY PREAMBLES
Polypropylene pipes 54mm diameter and under shall be seamless copper coloured class 16 pipes jointed with "Fast-fuse" heat welded thermoplastic or brass compression fittings as designed for use with copper pipes as stated
"Polycop" polypropylene pipes:
-92-
Plumbing and DrainageBill No. 14Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
Pipes shall be firmly fixed to walls with coloured nylon snap-in pipe clips with provision for accommodating thermal movement and jointed and fixed strictly in accordance with the manufacturer's instructions
All pipe diameters are nominal external
Polypropylene pipes 63mm diameter and over shall be class 12 pipes jointed with cast iron "Supraclamp" running joints
"Polylink" polypropylene pipes:
Fusion welded bends, once or twice mitred as necessary, and tees shall be factory manufactured
Fusion welded bends and tees shall include jointing to pipes with PVC rubber ring double Z joint couplers
Branch tees shall include flanged and bolted joints to "Polycop" branch pipes in addition and for brass compression male iron to copper straight couplers
Reducers shall include jointing to pipes with PVC rubber ring double Z joint couplers and reducers shall be of sufficient overall length to accommodate same
All pipes shall be jointed and fixed strictly in accordance with the manufacturer's instructions
All pipe diameters are nominal external
Soil, waste and vent pipes and fittings shall be solvent weld jointed
uPVC pipes and fittings:
Pipes for water supply shall be of the class stated
uPVC pressure pipes and fittings:
Pipes of 40mm diameter and smaller shall be plain ended with solvent welded uPVC loose sockets and fittings
-93-
Plumbing and DrainageBill No. 14Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
Pipes of 50mm diameter and greater shall have sockets and spigots with push in type integral rubber ring joints. Bends shall be uPVC and all other fittings shall be cast iron, all with similar push-in type joints
Pipes shall be hard drawn and half-hard pipes of the class stated. Class 0 (thin walled hard drawn) pipes shall not be bent. Class 1 (thin walled half-hard), class 2 (half-hard) and class 3 (heavy walled half-hard) pipes shall only be bent with benders with inner and outer formers. Fittings to copper waste, vent and anti-syphon pipes, capillary solder fittings and compression fittings shall be "Cobra Watertech" type. Capillary solder fittingsshall comply with ISO 2016. Only compression fittings shall be used in walls or in ground
Copper pipes:
Unless specifically otherwise stated, descriptions of pipes shall be deemed to include fixing to walls, casting in, building in or suspending not exceeding 1m below suspension level
Fixing of pipes
Where fittings have reducing ends or branches they are described as "reducing". In the case of pipes with diameters not exceeding 60mm only the largest end or branch size is given. Should the contractor wish to use other fittings and bushes or reducers he may do so on the understanding that no claim in this regard will be entertained. In the case of pipes with diameters exceeding 60mm all sizes are given and no claim for extra bushes, reducers, etc will be entertained
Reducing fittings
Descriptions of gutter outlets etc shall be deemed to include wire balloon gratings
Wire gratings
-94-
Plumbing and DrainageBill No. 14Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
Exposed surfaces of concrete stormwater channels, cover slabs, inspection eye marker slabs, gulley tops, cleaning eye tops, catchpits, inspection chambers, etc shall be finished smooth with plaster
Exposed concrete surfaces
No claim for rock excavation will be entertained unless the contractor has timeously notified the quantity surveyor thereof prior to backfilling
Excavations
"Soft rock" and "hard rock" shall be as defined in "Earthworks"
Pipes shall be laid and bedded and trenches shall be carefully backfilled in accordance with manufacturers' instructions
Laying, backfilling, bedding, etc. of pipes
Where no manufacturers' instructions exist pipes shall be laid in accordance with clauses 5.1 and 5.2 of each of the following: SANS 1200 L : Medium-pressure pipelines LD : Sewers LE : Stormwater drainage Pipe trenches etc shall be backfilled in accordance with clauses 3, 5.5, 5.6, 5.7 and 7 of SANS 1200 DB : Earthworks (Pipe trenches) Pipes shall be bedded in accordance with clauses 3.1 to 3.4.1, 5.1 to 5.3 and 7 of SANS 1200 LB : Bedding (Pipes). Unless otherwise described bedding of rigid pipes shall be class B bedding
Flush pans shall have straight or side outlets and "P" or "S" traps as necessary
Flush pans
Descriptions of waste unions shall be deemed to include rubber or vulcanite plugs and chains fixed to fittings
Waste unions
-95-
Plumbing and DrainageBill No. 14Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
RAINWATER DISPOSAL
8No100mm Diameter fullbore with vertical outlet1
Fullbore - "Saint Gobain" or similar approved pipelines south africa 80mm 180º centre bolt vertical roof outlet with dome grate (code: 03500) placed in concrete roof
71m450mm x 2.5mm Gutters bent three times in length2
Galvanised Mild Steel Gutters
32m100mm Diameter rainwater downpipe to gutters3
Galvanised mild steel downpipes
38m100mm Diameter downpipes to full-bores4
8No110mm Vertical outlet5
4No75mm Diameter HDG MS HCS drainage spout6
32NoExtra over rainwater pipe for 100mm diameter bend7
36NoExtra over rainwater pipe for shoe8
7NoExtra over gutters for ends9
32NoExtra over gutters for outlet10
SANITARY FITTINGS
1No1160 x 460mm Double sink including waste code: 1990002 NVN621
11
"Nouveau" or similar approved
15No"Smyle" basin underslung 56cm white code: 5012801112
"Geberit Smyle" or similar approved
13NoSquare rimfree WC pan code: 50020001113
-96-
Plumbing and DrainageBill No. 14Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
13NoSquare seat, standard close overlapping code: 500234011
14
4No"Preda" Urinal with inter control battery code: 1167300115
2No55cm "Abalona" wash hand basin for less abled including fixation kits
16
2No"Abalona" WC pan for less abled, rimfree code: 50262011
17
2No"Ablona" seat ring code: 53401118
1No"Rondo" Prep bowl 45 no overflow including plumbing kit19
17No"Clicker" Basin waste code: GIO-BW202S20
WASTE UNIONS ETC
TRAPS ETC.
15NoBidet bottle trap in white Alpine code: 15110811121
"Geberit" or similar approved
1No32 x 32mm Basin trap in wall, chrome22
2NoShower trap code: CAA-WJ523T23
"Atlantica" or similar approved
TAPS, VALVES, ETC
15No"Kombifix" Cistern WH 80 HOR outlet code: 11017600124
"Alpha" or similar approved
15NoDF actuator, white code: 11504511125
15No"Ergo" Basin mixer code: 65812.2126
"Geberit Ergo" or similar approved
2NoSink mixer SQ spout code: 65920.2127
-97-
Plumbing and DrainageBill No. 14Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
2NoFinish set for concealed shower mixer code: 65875E.2128
2NoUniversal 1 box for concealed shower mixer29
37No10 x 15mm Angle valve code: GIO-537930
"Benkiser & Cone" or similar approved
2No"Vario" shower rose code: 2744100031
"Chroma" or similar approved
2NoShower arm, thin 128 CP code: 2741100032
"Hangrohe" or similar approved
2No"Decor care" basin mixer33
ELECTRIC WATER HEATERS
3No"ZIP Hydroboil code 3800/5/04" 5 litre white powder coated water boiler secured to wall
34
"Kwikot" or similar approved
1No
600 Dual geysers, 250 lt IPX4 rated.To be installed horizontally with adjustable left and right-hand wall mounting brackets. Including all valves according to manufacturers specifications.
35
ItemTesting water pipe system36
Testing
-98-
Plumbing and DrainageBill No. 14Builders WorkSection No. 2
Carried to to collection R
Plumbing and Drainage
Section No. 2
Bill No. 14
AmountPageNo
Builders Work
COLLECTION
Rev 01
National Nuclear Regulator
98
97
96
95
94
93
92Total Brought Forward from Page No.
-99-
Plumbing and DrainageBill No. 14Builders WorkSection No. 2
Carried Forward to Summary of Section No. 2 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 2
BUILDERS WORK
BILL NO 15
PAINTWORK
For preambles refer to "Model Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemedto fall into Painting Work Group 152 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
Wherever a trade name for any product has been described, the tenderer's attention is drawn to the fact that any other product of equal quality may be used subject to the written approval of the principal agent being obtained prior to the closing date for submission of tenders
If prior written approval for an alternative product is not obtained, the product described shall be deemed to have been tendered for
TRADE NAMES
SUPPLEMENTARY PREAMBLES
Colours for all paintwork shall be standard colours with a value exceeding 7 on the Munsell system
Colours
-100-
PaintworkBill No. 15Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
Descriptions of paintwork shall be deemed to include for all cutting in
DESCRIPTIONS
All painting shall be done in accordance with "Plascon" or other approved specifications unless otherwise described
PAINT SPECIFICATIONS
PAINT ON FLOATED PLASTER
638m2On internal walls1
Internal quality primer with one coat of Plaster Primer (UC 56) with an overcoating time of 16 Hours and finish with two coats of Velvaglo Satin (VLO) with 16 hours drying time between coats for a maintenance cycle of 7 years in C5
PAINT ON CONCRETE WALLS
188m2On internal walls2
Internal quality primer with one coat of Plaster Primer (UC 56) with an overcoating time of 16 Hours and finish with two coats of Velvaglo Satin (VLO) with 16 hours drying time between coats for a maintenance cycle of 7 years in C5- Coastal Marine Enviroment
187m2On external walls3
External quality primer with one coat of Plaster Primer (UC 56) with an overcoating time of 16 Hours and finish with two coats of Velvaglo Satin (VLO) or siilar approved with 16 hours drying time between coats for a maintenance cycle of 7 years in C5
PAINT ON SMOOTH CONCRETE SURFACES
120m2On projecting and isolated columns4
One coat alkali resistance plaster primer and two coats PVA acrylic emulsion paint on
-101-
PaintworkBill No. 15Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
WOOD SURFACES
91m2Doors 5
"Woodock 30" or similar approved universal undercoat and two coats super universal paint on
14mSkirtings 6
ON METAL
38m2On door frames7
One coat self-etching primer, one undercoat and 2 coats alkyd enamel paint in colours which have a value of 7 or less on the Munsell system in accordance with SABS 1091 on galvanised steel
All paintwork in accordance with "SANS standards" specifications
DECORATIVE PAINT FINISH
29tSteel columns and beams8
Touch up undercoat, apply one intermediate coat of high solids surface tolerant epoxy and two coats polyurethane finishing paint on factory applied primer (primer elsewhere) on
11tSteel purlins, girts, bracing etc9
11tGalvanised steel purlins, girts, bracing etc10
Apply one coat Inorganic Zink Ethyl Silicate primer, one coat high build epoxy primer, one intermediate coat of high solids surface tolerant epoxy and two coats polyurethane finishing paint on
-102-
PaintworkBill No. 15Builders WorkSection No. 2
Carried to to collection R
Paintwork
Section No. 2
Bill No. 15
AmountPageNo
Builders Work
COLLECTION
Rev 01
National Nuclear Regulator
102
101
100Total Brought Forward from Page No.
-103-
PaintworkBill No. 15Builders WorkSection No. 2
Carried Forward to Summary of Section No. 2 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 2
BUILDERS WORK
BILL NO 17
EXTERNAL WORKS
For preambles refer to "Model Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemedto fall into Alterations Work Group 102 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
All demolished material to be removed from site and dumped at a site identified by the contractor at no extra cost to the client
SUPPLEMENTARY PREAMBLES
REMOVAL OF EXISTING WORK, ETC
1No
Single storey building with pitched roof 17 x 13m on plan and 2.52m high at eaves comprising concrete surface bed, concrete/clay roof tiles,timber roof trusses, brick walls, steel windows, ceiling, electrical and mechanical installations
1
Demolishing and removing of buildings to an avergae of 375m²
-104-
External WorksBill No. 16Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
1No
Single storey building with pitched roof 13 x 22m on plan and 2.52m high at eaves comprising concrete surfaces bed, concrete/clay roof tiles, timber roof trusses, brick walls, steel windows, ceilings, electrical and mechanical installations.
2
1.00NoExtra over for crushing of all building materials, brickwork, concrete etc. on site for re-use as filling
3
150m2
Canopy with pitched roof 10 x 15m on plan and 3.5m high overall comprising 4 (four) 2.6m high 150mm diameter hollow section round steel poles and corrugated iron sheeting roof covering on timber beams and rafters
4
Demolishing and removing of canopies and carports
253m1200m High Consisting of Diamond Mesh and the removal of all steel and concrete footings
5
Removal of existing fence
373m2Break up and remove existing concrete pavers/brick pavers
6
Removal of all concrete paving
529m2125mm Thick concrete surface beds7
Breaking up and removing
40mDetection of low tension cables including removal of water pipes below ground of sewer pipes and manholes
8
DETECTION OF SERVICES
Unless otherwise stated all the following items shall be deemedto fall into Concrete Work Group 110 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
-105-
External WorksBill No. 16Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
10NoPrecast concrete bollards with exposed aggregate 1200mm high
9
CONCRETE BOLLARDS
Unless otherwise stated all the following items shall be deemedto fall into Metalwork Work Group 136 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
FENCING AND GATES
303mFencing10
1998mm high "Betafence" or similar approved fencing with 85mm marine fusion with 3305 x 2100mm high panels, reinforced with 4 x 50mm "V" formation horizontal recessed bands, all galvanized and marine bind coated.
1NoPedestrian Gate including steel frame 2100 x 900mm wide
11
1NoMotorised access gate 7000 x 2100mm high including steel frame, motor and power supply
12
SECURITY OVERHANGS
2NoRemote controlled 3000mm long13
"Centurion" or similar approved Boom gates
Unless otherwise stated all the following items shall be deemedto fall into Metal roofing Work Group 125 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
PROFILED METAL SHEETING AND ACCESSORIES
-106-
External WorksBill No. 16Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
289m2Roof covering with pitch not exceeding 25 degrees for carports
14
"ZIP-TEK 440" or similar approved grey sheets on structural steel frames (measured elsewhere)
-107-
External WorksBill No. 16Builders WorkSection No. 2
Carried to to collection R
External Works
Section No. 2
Bill No. 16
AmountPageNo
Builders Work
COLLECTION
Rev 01
National Nuclear Regulator
107
106
105
104Total Brought Forward from Page No.
-108-
External WorksBill No. 16Builders WorkSection No. 2
Carried Forward to Summary of Section No. 2 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 2
BUILDERS WORK
BILL NO 18
PROVISIONAL SUMS
For preambles refer to "Model Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemedto fall into Lump sum Work Group 180 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
SUPPLEMENTARY PREAMBLES
Work for which budgetary allowances are provided will be measured and valued in accordance with clause 32 of the Principal Building Agreement and deducted in whole or in part if not required without any compensation for loss or profit on the said allowances
General
Prime cost amounts and provisional sums are net. Prime cost amounts include for delivery to site of all articles concerned
Provisional sums are for material and equipment supplied and installed complete by firms of specialists
Where stated, the contractor may allow for profit if required
Profit
-109-
Provisional SumsBill No. 17Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
The item "Attendance" which follows each provisional sum for nominated/selected subcontractors' work, shall be deemed to cover all the contractor's costs incurred in providing free of charge to the nominated/selected subcontractors, the following:
General attendance on nominated/selected subcontractors
1 Access to the site and places where the subcontract work is to be carried out, including the reasonable use of any temporary personnel hoists erected by the contractor
2 The provision of water and lighting and of single phase
electric power to a position within 50 metres of the
place where the subcontract work is to be carried out
but excluding water, fuel and power for commissioning of any installation
3 The provision of an area for the subcontractor toestablish temporary office accommodation andworkshops and for the storage of plant and
materials
4 The use of erected scaffolding belonging to the contractor, in common with others having the
like right,while it remains erected on site
5 The use, at reasonable times by arrangement of the
contractor's erected hoisting equipment
6 Making good in all trades and cleaning down and removal of rubbish on completion
Where stated special attendance will be described in detail in the contract documents for the services as set out in clause B8.0
Special attendance on nominated/selected subcontractors
-110-
Provisional SumsBill No. 17Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
Builder's work in connection with specialist services is given elsewhere in these bills of quantities
Builder's work
PROVISIONAL SUMS FOR NOMINATED/SELECTED SUBCONTRACT WORKS
215 000.00Item
Provide the sum of R 215,000.00 (Two hundred and fifteen thousand rand) for staircase in main foyer to feature
1
Marble staircase
ItemProfit2
ItemAttendance3
160 000.00Item
Provide the sum of R160,000.00 (One Hundred and Sixty Thousand Rand) for signage and signage structures
4
Signage
ItemProfit5
ItemAttendance6
215 000.00ItemProvide the sum of R215,000.00 (Two Hundred and Fifteen Thousand Rand) for landscaping
7
Landscaping
ItemProfit8
ItemAttendance9
110 000.00ItemAllow R110 000.00 (One hundred and ten thousand rand) for hard landscaping, concrete benches and tables
10
Hard landscaping
ItemProfit11
-111-
Provisional SumsBill No. 17Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
ItemAttendance12
215 000.00ItemProvide the sum of R215,000.00 (Two Hundred and Fifteen Thousand Rand) for grey/rainwater harvesting
13
Grey/rainwater harvesting
ItemProfit14
ItemAttendance15
340 000.00ItemProvide the sum of R340,000.00 (Three Hundred and Forty Thousand Rand) for Gas suppression
16
Gas supression
ItemProfit17
ItemAttendance18
ELECTRONIC SERVICES
86 000.00Item
Provide the sum of R86,000.00 (Eighty Six Thousand Rand) for CCTV, 2 MegaPixel day/night camera and head end monitor
19
CCTV installation
ItemProfit20
ItemAttendance21
76 000.00Item
Provide the sum of R76,000.00 (Seventy Six Thousand Rand) for Alarm, motion sensors and magnetic door contacts
22
Alarm, motion sensors etc.
ItemProfit23
ItemAttendance24
-112-
Provisional SumsBill No. 17Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
130 000.00Item
Provide the sum of R130,000.00 (One Hundred and Thirty Thousand Rand) for electric fence, extension to perimeter, 6 wire top mounted fencing
25
Electric fence
ItemProfit26
ItemAttendance27
110 000.00ItemProvide the sum of R110,000.00 (One Hundred and ten Thousand Rand) for Access control
28
Access control
ItemProfit29
ItemAttendance30
450 000.00Item
Provide the sum of R450,000.00 (Four Hundred and Fifty Thousand Rand) for Smoke detection, break glass and sirens
31
Smoke detection
ItemProfit32
ItemAttendance33
530 000.00Item
Provide the sum of R530,000.00 (Five Hundred and Thirty Thousand Rand) for LAN room fitout, network equipment, cabinet, UPS, data cabling installation and testing
34
LAN, network equipment etc.
ItemProfit35
ItemAttendance36
-113-
Provisional SumsBill No. 17Builders WorkSection No. 2
Carried to to collection R
Rev 01
National Nuclear Regulator
660 000.00Item
Provide the sum of R660,000.00 (Six Hundred and Sixty Thousand Rand) for projectors, document camera, control and sound equipment, cabling and lecturne installation
37
Projectors, control and sound equipment
ItemProfit38
ItemAttendance39
318 000.00Item
Provide the sum of R318,000.00 (Three Hundred and Eighteen Thousand Rand) for Upgrade or correction of electrical supply
40
Electrical supply
ItemProfit41
ItemAttendance42
689 000.00Item
Provide the sum of R689,000.00 (Six Hundred and Eighty Nine Thousand Rand) for Transformer/mini sub installation
43
Transformer/minisub installation
ItemProfit44
ItemAttendance45
-114-
Provisional SumsBill No. 17Builders WorkSection No. 2
Carried to to collection R
Provisional Sums
Section No. 2
Bill No. 17
AmountPageNo
Builders Work
COLLECTION
Rev 01
National Nuclear Regulator
114
113
112
111
110
109Total Brought Forward from Page No.
-115-
Provisional SumsBill No. 17Builders WorkSection No. 2
Carried Forward to Summary of Section No. 2 R
Rev 01
National Nuclear Regulator
Builders Work
SECTION SUMMARY - Builders Work
BillNo
PageNo
Amount
Section No. 2
27Earthworks1
34Concrete, Formwork and Reinforcement2
38Masonry3
43Waterproofing4
46Roof Coverings5
51Carpentry and Joinery6
56Ceilings, partitions and Access Flooring7
59Floor Coverings, Plastic Linings, etc.8
69Ironmongery9
74Structural Steelwork10
83Metal Work11
87Plastering12
91Tiling13
99Plumbing and Drainage14
103Paintwork15
108External Works16
115Provisional Sums17
-116-
Builders WorkSection No. 2
Carried to Final Summary R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION 3
ELECTRICAL WORK
BILL NO 1
PRELIMINARY AND GENERAL
For preambles refer to "Model Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemedto fall into Lump sum preliminaries Work Group 190 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
Allow for all costs necessary to complete the works in a satisfactory manner in accordance with the drwings, spesifications, SANS Code of ractice, the Local Authorities requirements and to the Engineers satisfaction including and not limited to the following:
PRELIMINARY & GENERAL
Item
Allow for site establishment and all associated services including storage of plant, materials an equipment and protection thereof.
1
SITE ESTABLISHMENT
ItemAllow for removal of site establishent2
ItemAllow for construction supervisor for duration of construction
3
SUPERVISION
-117-
Preliminary and GeneralsBill No. 1Electrical WorksSection No. 3
Carried to to collection R
Rev 01
National Nuclear Regulator
ItemProvision of a Health and Safety plan4
COMPLIANCE WITH THE HEALTH AND SAFETY ACT AND APPLICABLE REGULATIONS
ItemProvision of a Health and Safety file5
ItemProvision of a construction safety officer6
ItemProvision of safety fences, signs and barricades7
Item
Allow for preparation of workshop drawings or samples for examination for the electrical works for approval by the Engineer prior to fabrication
8
DRAWINGS AND/OR SAMPLES
Item
Allow for preperation of samples for examination and/or technical submissions including warranties, test certificates, guarentees and other submissions for the electrical works as may be required by the Engineer.
9
Item
Allow for the provision of a complete set (3 copies) of hard copies and one electronic copy of marked-up record drawings of the final layout of the electrical works on completion of the project.
10
ItemAllow for factory inspections and acceptance tests11
FACTORY INSPECTIONS
Item
Allow for inspection, testing and commissioning of the complete installation in this Bill, including provision of all test equipment. Tests shall be carried out in the presence of the Engineer who shall have been notified of the dates and approximate durations of the tests, sufficiently in advance as to allow attendance to such testing.
12
TESTING AND COMMISSIONING
-118-
Preliminary and GeneralsBill No. 1Electrical WorksSection No. 3
Carried to to collection R
Rev 01
National Nuclear Regulator
Item
Allow for the provision of a Certificate of Compliance in terms of SANS 10142-1 specifications for each completed distribution board.
13
CERTIFICATE OF COMPLIANCE
Item
Allow for the provision of a Certificate of Compliance in terms of SANS 10142-2 specifications where part of the electrical installation is above 1000V.
14
Item
Allow for preperation and supply of a complete set (4 copies) of operating and maintenance manuals for the complete electrical installation including technical literature, drawings, lists of applicable spares and all certificates as specified in the specifications.
15
OPERATING AND MAINTENANCE INSTRUCTION MANUALS
ItemAllow for a 12 month guarantee period on all plant and equipment under this contract.
16
GUARANTEE PERIOD
Item
JBCC Series 2000 Agreement - Preliminaries (Refer to Section No 1, Bill No 1 - Preliminaries included in Bills of Quantities)
17
SUBCONTRACT CONDITIONS AND PRELIMINARIES
1MonthPayment due to the Contractor if the construction period exceeds past contacted time period
18
-119-
Preliminary and GeneralsBill No. 1Electrical WorksSection No. 3
Carried to to collection R
Preliminary and Generals
Section No. 3
Bill No. 1
AmountPageNo
Electrical Works
COLLECTION
Rev 01
National Nuclear Regulator
119
118
117Total Brought Forward from Page No.
-120-
Preliminary and GeneralsBill No. 1Electrical WorksSection No. 3
Carried Forward to Summary of Section No. 3 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION 3
ELECTRICAL WORK
BILL NO 2
LIGHTING AND SMALL POWER
Supply, installation, connections, testing, commissioning and handing over in working order of the lighting and small power installation complete with conduits, conduit ends wiring ducts, unistrut channels, powerskirting, wiring, switches, socket outlets, luminaires, terminations, all fixing materials, brackets and all small materials as required.
PREAMBLES
Unless otherwise stated all the following items shall be deemedto fall into Electrical installation Work Group 160 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
Supply and install conduits built-in brick and/or fixed on any surface complete with draw wires including bending, threading, jointing, draw boxing, cover plates, couplings, bends, tees, spacer bar saddles, screws, etc. as specified.
CONDUIT AND ACCESSORIES
175m20mm PVC Conduit1
Built in brick or concrete
105m25mm PVC Conduit2
190m32mm PVC Conduit3
-121-
Lighting and Small powerBill No. 2Electrical WorksSection No. 3
Carried to to collection R
Rev 01
National Nuclear Regulator
225m20mm PVC Conduit4
Fixed on any surface or in ceiling
85m25mm PVC Conduit5
Supply and install conduit wall boxes and conduit round boxes, one, two, three or four way built-in brick and/or fixed on any surface including fixing to conduit with necessary locknuts, adaptors, bushes, cover plates, screws etc. as specified.
CONDUIT BOXES
15No20mm Galvanised Steel 60mm diameter round box6
Built in brick or concrete
210No25mm Galvanised steel 60mm diameter round box7
241No20mm PVC 60mm diameter round box8
5No25mm PVC 60mm diameter round box9
4No100mm x 100mm x 50mm Galvanised steel wall box10
Fixed on any surface or in ceiling void
7No100mm x 50mm x 50m Galvanised steel wall box11
2No20mm Galvanised steel 60mm diameter round box12
2No25mm Galvanised steel 60mm diameter round box13
DRAW BOXES
4NoPratley Ezee Fit junction box - No 014
Supply and installed junction boxes complete with lid, blanking plugs, terminal rail and 10 "Kwikblok" terminals including fixing on ay surface, all fixing material, brackets, fixing to conduit and/or cables with necessary adaptors, locknuts, cable glands, lids, etc. Kwikblok terminals and rail to be factory fitted in box.
-122-
Lighting and Small powerBill No. 2Electrical WorksSection No. 3
Carried to to collection R
Rev 01
National Nuclear Regulator
FLEXIBLE CONDUIT AND ACCESSORIES
60m20mm Kopex Flexible conduit15
Supply and install flexible conduits
15m25mm Kopex Flexible conduit16
-123-
Lighting and Small powerBill No. 2Electrical WorksSection No. 3
Carried to to collection R
Rev 01
National Nuclear Regulator
WIRING DUCTS AND UNISTRUT CHANNELS
85mP2000 Galvanised Unistrut channel17
Supply and install wiring ducts and unistrut channels complete with splices, elbows, tees, crossover, end caps, steel covers, support brackets, clamps, clips, hangers, M8 threaded rods, coupler nuts, bolts, hex nuts, washers, screws, etc. as specified
45mP8000 Galvanised wiring duct18
POWER SKIRTING AND ACCESSORIES
80mTwo compartment white metal powerskirting19
Powerskirting complete with covers, splices, elbows, tees, end caps, fixing materials, etc. as specified.
CONDUCTORS FOR LIGHTING AND POWER POINTS
3 325m2.5mm² PVC Conductor20
Supply and install PVC insulated conductors 600/1000V drawn into conduits, wiring ducts, unistrut channels or powerskirting including identification labels, terminating etc. as indicated on the single line diagrams.
13 460m4mm² PVC Conductor21
15m6mm² PVC Conductor22
16 785m2.5mm² BCEW23
15m4mm² BCEW24
LIGHT SWITCHES AND SENSORS
1No1 Lever 1 way switch 100 x 50mm25
Supply and install flush mounted light switch
-124-
Lighting and Small powerBill No. 2Electrical WorksSection No. 3
Carried to to collection R
Rev 01
National Nuclear Regulator
5No1 Lever 2 way switch 100 x 50mm26
1NoDimmer 1000W, 1 lever 1 way switch 100 x 50mm27
Supply and install light dimmer installed in flush wall box as specified in the specification. Allowance shoul be made for 250V light dimmer c/w cover plate, screws etc. Cover plate must be baked enamel finish in the colour specified in the specification or indicated on the drawing and must be fixed with two chromium plated raised head counter-sunk screws.
51NoOccupancy sensor28
Supply and install dual technology occupancy sensor as
1No1 Lever 1 way Weatherproof switch29
Supply and install weatherproof light switches installed on any surface as specified in the specification. Allowance should be made for 16 Ampere 250V light switch c/w box, cover plate, screws, etc. Box and cover plate must be weatherproof.
4No
Supply and install 250V photocells (day/night switch) c/w enclosures and accessories as secified in the specification
30
PHOTOCELLS
221No
Supply and install unswitched socket outlets on wiring ducts as specified in the specifications. Allowance should be made for 6 Amp 3 pin 250V unswithed shuttered socket outlets on 100 x 50mm yoke c/w cover plates, screws etc. installed on 100 x 50mm conduit box.
31
UNSWITCHED SOCKET OUTLETS
SWITCHED SOCKET OUTLETS
-125-
Lighting and Small powerBill No. 2Electrical WorksSection No. 3
Carried to to collection R
Rev 01
National Nuclear Regulator
30No16A 3 Pin double switched socket outlet32
Supply and install switched socket outlets in flush wall box as specified in the specifications. Allowance should be made for 16 Amp 3 pin 250V swithed socket outlets c/w yoke, cover plates, screws etc. Cover plate must be finished in white baked enamel and must be fixed with two chromium plated raised head counter-suk screws.
2No16A 3 Pin red dedicated SSO33
ISOLATORS
10No20A Double pole isolator34
Supply and install isolators and accessories as specified in the specification. Allowance should be made for the following flush mounted isolators c/w cover plates, srews etc. installed in flush wall boxes.
30No20A Double pole isolator35
Supply and install isolators and accessories as specified in the specifications. Allowances should be made for the following surface mountd isolators c/w cover plates, screws etc. installed in surface mountd wall boxes.
1No20A Three pole isolator36
FLOOR BOXES & POP UP BOXES
5No
Floor box including 2 x 16A 3 Pin Switched socket outlet, 1 x 16A 3 Pin Slimline socket outlet, 1 x 16A 3 Pin Dedicated switched socket outlet and 2 x RJ45 data outlet
37
Supply and install square floor boxes as indicated on the drawings and specified in the specification. Allowance should be made for flush mounted floor boxes in concrete floors complete with frame, lid, modular outlet plates, screws, etc. and equiped with the following outlets.
-126-
Lighting and Small powerBill No. 2Electrical WorksSection No. 3
Carried to to collection R
Rev 01
National Nuclear Regulator
47NoAluminium power pole38
Supply and install aluminium power pole as indicated on the drawings and specified in the specification. Allowance should be made for pole complete with frame, lid, modular outlet plates, screws, etc. and equipped with the following outlets:2 x 16A 3 Pin Switched Socket Outlet1 x 16A 3 Pin Slimline witched Socket Outlet1 x 16A 3 Pin Dedicated Switched Socket Outlet2 x RJ45 Data Outlet
LUMINAIRES
115NoType L139
Supply and install SANS approved luminaires
15NoType L240
1NoType L341
4NoType L4 - Exit sign42
69NoType L543
17NoType L644
20NoType L745
36NoType L8 (LED feature lighting in concrete wall on stair), complete with external floodlights.
46
20NoType SL147
1NoType SL248
-127-
Lighting and Small powerBill No. 2Electrical WorksSection No. 3
Carried to to collection R
Lighting and Small power
Section No. 3
Bill No. 2
AmountPageNo
Electrical Works
COLLECTION
Rev 01
National Nuclear Regulator
127
126
125
124
123
122
121Total Brought Forward from Page No.
-128-
Lighting and Small powerBill No. 2Electrical WorksSection No. 3
Carried Forward to Summary of Section No. 3 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION 3
ELECTRICAL WORK
BILL NO 4
LOW VOLTAGE CABLE RETICULATION
Unless otherwise stated all the following items shall be deemedto fall into Electrical reticulation Work Group 162 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
Supply, delivery, installation, connetions, testing, commissioning and handing over in working order of the low voltage cable reticulation as specified and as follows:
LOW VOLTAGE CABLE RETICULATION
LOW VOLTAGE CABLES
125m150mm² x 4 Core1
Supply, delivery, installation and testing of 600/1000V grade PVCSWAPVCPVC cables with stranded copper conductors in trenches, sleeves, direct in ground or on cae ladder and trays including fixing and strapping as specified.
30m50mm² x 4 Core2
15m16mm² x 4 Core3
190m10mm² x 4 Core4
60m6mm² x 4 Core5
330m4mm² x 3 Core (Site lighting)6
-129-
Low Voltage Cable ReticulationBill No. 3Electrical WorksSection No. 3
Carried to to collection R
Rev 01
National Nuclear Regulator
-130-
Low Voltage Cable ReticulationBill No. 3Electrical WorksSection No. 3
Carried to to collection R
Rev 01
National Nuclear Regulator
CABLE TERMINATIONS
4No150mm² x 4 Core7
Supply and installation of 600/1000V grade cable ends and connecting to switchgear terminals complete with glands, shrouds, lugs, connections, labels and testing.
2No50mm² x 4 Core8
2No16mm² x 4 Core9
12No10mm² x 4 Core10
4No6mm² x 4 Core11
22No4mm² x 3 Core (site lighting)12
EARTH CONDUCTORS
125m70mm² BCEW13
Supply and installation of standard bare copper earth wire together with cables
30m16mm² BCEW14
265m6mm² BCEW15
EARTH CONDUCTORS TERMINATIONS
4No70mm² BCEW16
Supply and installation of bare copper earth wire ends to
2No16mm² BCEW17
16No6mm² BCEW18
-131-
Low Voltage Cable ReticulationBill No. 3Electrical WorksSection No. 3
Carried to to collection R
Rev 01
National Nuclear Regulator
DISTRIBUTION BOARDS
1NoMDB19
Manufacture, delivery, off-loading and installation of flush mounted, surface mounted or floor standing metal distribution boards complete with frames, sub-frames, base frame, chassis, faceplates, doors, busbars,all switchgear, meters, wiring, connections, labels, mounting of board including testing and commissioning as specified and as indicated on the single line diagram drawings.
1NoDB-G120
1NoDB-G221
1NoDB-Server22
1NoSDB-Multifunction23
1NoSDB-F124
1NoSDB-F225
1NoDB-Gatehouse26
1NoGenerator changeover27
1NoPV Solar inverter28
1NoHVAC DB (on roof)29
CABLE WIRE MESH
6m600mm Wide30
Cable tray welded wire mesh metal galvanised, medium
12m300mm Wide31
250m200mm Wide32
130m100mm Wide33
-132-
Low Voltage Cable ReticulationBill No. 3Electrical WorksSection No. 3
Carried to to collection R
Low Voltage Cable Reticulation
Section No. 3
Bill No. 3
AmountPageNo
Electrical Works
COLLECTION
Rev 01
National Nuclear Regulator
132
131
130
129Total Brought Forward from Page No.
-133-
Low Voltage Cable ReticulationBill No. 3Electrical WorksSection No. 3
Carried Forward to Summary of Section No. 3 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION 3
ELECTRICAL WORK
BILL NO 5
EARTHING AND LIGHTING PROTECTION
Unless otherwise stated all the following items shall be deemedto fall into Electrical installation Work Group 160 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
Supply, delivery, installation, testing, commissioning and handing over in working condition and maintenance during the guarentee period of a complete earthing installation in accordance with the relevant SANS standards and as specified.
EARTHING AND LIGHTING PROTECTION
BUILDING EARTH SYSTEMS
1NoBuilding1
Allow for soil resitivity surveys for the following buildings/structures in accordance with the relevant SANS standards and as specified.
1NoBuilding2
Allow for the complete design, supply, delivery, installation, testing, commissioning and handing over in working condition and maintenance during the guarentee period of a complete earthing and lighting protection system for the following buildings/structures as per the specification and the relevant SANS standards. A specialist contractor to be appointed by the electrical contractor for the earthing and lighting protection installation.
-134-
Earthing and Lighting ProtectionBill No. 4Electrical WorksSection No. 3
Carried to to collection R
Rev 01
National Nuclear Regulator
Item
Allow for the complete earthing and bonding of roofs, gutters, downpipes, waste pipes etc. including all fixing materials, copper strap, lugs and connections.
3
EARTHING AND BONDING
Item
Allow for the complete bonding of hot and cold water systems together and to the earth continuity conductor system including all fixing materials, copper straps, lugs and connections
4
Item
Allow for the complete earting and bonding of metal parts in hazardous areas including all fixing materials, copper straps, lugs and connections.
5
ItemAllow for inspection, testing and commissioning of the complete earthing and bonding installation.
6
TESTING AND COMMISSIONING
Item
Allow for the provision of a Certificate of Compliance for each building/structure in terms of the SANS specifications for the complete earthing and lighting protection system.
7
CERTIFICATE OF COMPLIANCE
-135-
Earthing and Lighting ProtectionBill No. 4Electrical WorksSection No. 3
Carried to to collection R
Earthing and Lighting Protection
Section No. 3
Bill No. 4
AmountPageNo
Electrical Works
COLLECTION
Rev 01
National Nuclear Regulator
135
134Total Brought Forward from Page No.
-136-
Earthing and Lighting ProtectionBill No. 4Electrical WorksSection No. 3
Carried Forward to Summary of Section No. 3 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION 3
ELECTRICAL WORK
BILL NO 6
EXCAVATIONS
Unless otherwise stated all the following items shall be deemed to fall into Earthworks Work Group 104 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
Allowance should be made for excavations of trenches for cables, cable ducts, road crossings, jointing pits, manholes etc. including setting out, safeguarding, backfilling, compaction, finishing and disposing of surplus material in accordance with SANS 2001-DP3, SANS 1200 DA, SANS 1200 LC and as specified in the standard specifications.
EXCAVATIONS
EXCAVATION OF CABLE TRENCHES
100m3Soft material1
Excavation of cable trenches 800mm wide x 800mm deep
30m3Intermediate2
5m3Hard rock3
10m3Lay a minimum thickness of 75mm sifted soil bedding4
BEDDING
8m3Import of soil bedding where no suitable soil is available on site
5
-137-
ExcavationBill No. 5Electrical WorksSection No. 3
Carried to to collection R
Rev 01
National Nuclear Regulator
25m3Backfill first layer with 150mm layer of sifted bakfill or sand to cover cable
6
BACKFILLING AND COMPACTION
33m3
Backfill and compaction of cable trenches in 200mm layers and making good surface to match surrounding area
7
10m3Import soil for backfilling where no suitable soil is available on site
8
4NoProvide steel reinforced plates over trench to create temporary access
9
TRENCH COVER PLATES
ItemProvide adequate barricading at all times to safeguard all open excavations
10
SAFEGUARDING OF EXCAVATIONS
CABLE SLEEVES
420m110mm Dia HDPE Nextube conduit11
Supply and install HDPE Nextube pipes in ground as per drawings and specifications, including long radius bends, galvanised steel draw wires and sealing of ends with water tight sealing compound.
20m160mm Dia HDPE Nextube conduit12
MANHOLES
1No2000mm x 2000mm x 1000mm Manhole13
Construction of electrical manholes complete with heavy duty cast iron covers
9No1500mm x 1500mm x 1000mm Manhole14
-138-
ExcavationBill No. 5Electrical WorksSection No. 3
Carried to to collection R
Rev 01
National Nuclear Regulator
210mSupply and install danger tape 300mm above cables for the full width of the trench as specified
15
MARKING TAPE
6NoSupply and install 900 x 300 x 75mm precast concrete cable protection cover slabs as specified
16
CONCRETE CABLE COVER SLABS
5NoSupply and install concrete cable route markers as specified
17
CONCRETE CABLE MARKERS
-139-
ExcavationBill No. 5Electrical WorksSection No. 3
Carried to to collection R
Excavation
Section No. 3
Bill No. 5
AmountPageNo
Electrical Works
COLLECTION
Rev 01
National Nuclear Regulator
139
138
137Total Brought Forward from Page No.
-140-
ExcavationBill No. 5Electrical WorksSection No. 3
Carried Forward to Summary of Section No. 3 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION 3
ELECTRICAL WORK
BILL NO 7
GENERATOR AND BULK ELECTRICAL SERVICES
Unless otherwise stated all the following items shall be deemedto fall into Electrical installation Work Group 160 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
GENERATOR AND BULK ELECTRICAL
ItemCompilation of workshop drawings and submission for1
125kVA Volvo Diesel Generators complete with an 8 hour base tank and 304 stainless steel exhaust system
1NoManufacture and supply, including factory testing2
1NoDelivery, rigging, installation, commissioning and site testing
3
ItemGenerator plant room sound proofing design4
ItemGenerator plant room sound proofing, investigation, design and submission of workshop drawings
5
ItemWitnessed dbA sound pressure tests after hours on site6
ItemDesign and submission of workshop drawings for approval
7
Generator control panel complete
-141-
Generator & Bulk ElectricalBill No. 6Electrical WorksSection No. 3
Carried to to collection R
Rev 01
National Nuclear Regulator
ItemGenerator control panel supply, delivery to site and connection
8
ItemRemote bulk tank cable terminations to generator control panel (power and signal cabling)
9
ItemAllow for warning and information signage outside plant room
10
Plant room signage
ItemAllow for warning and information signage inside plant room, as per OHS Act
11
ItemFirst 10 ppm sulphur diesel fill - day tank base frame12
Diesel fuel fill on site
1NoV-belts13
Tools and spares
1NoFuel filters14
1NoManual diesel pump for fuel tank complete with 5m hose15
1NoSet of earmuffs16
ItemSoftware and interface cabling17
ItemPlant room Earth Node, complete as per specification18
PROVISIONAL SUMS
500 000.00Item
Provide a sum of R500,000.00 (Five Hundred Thousand Rand) for the design and supply of 25kW solar panel array, complete with cables, structures and DB's, mounted above parking structures
19
ItemProfit20
ItemAttendance21
-142-
Generator & Bulk ElectricalBill No. 6Electrical WorksSection No. 3
Carried to to collection R
Generator & Bulk Electrical
Section No. 3
Bill No. 6
AmountPageNo
Electrical Works
COLLECTION
Rev 01
National Nuclear Regulator
142
141Total Brought Forward from Page No.
-143-
Generator & Bulk ElectricalBill No. 6Electrical WorksSection No. 3
Carried Forward to Summary of Section No. 3 R
Rev 01
National Nuclear Regulator
Electrical Works
SECTION SUMMARY - Electrical Works
BillNo
PageNo
Amount
Section No. 3
120Preliminary and Generals1
128Lighting and Small power2
133Low Voltage Cable Reticulation3
136Earthing and Lighting Protection4
140Excavation5
143Generator & Bulk Electrical6
-144-
Electrical WorksSection No. 3
Carried to Final Summary R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 4
MECHANICAL WORK
BILL NO 1
HOT AND COLD WATER RETICULATION
For preambles refer to "Model Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemedto fall into Mechanical services Work Group 170 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
1No
500 L Hot water industrial geyser, stainless steel, vertical, complete with back flow prevention valve, expansion valve, vacuum breaker, safety valve, shut off valves,Driptray and draining piping, all as specified
1
HOT AND COLD WATER RETICULATION
1No
ABECO Galvanised sectional steel tank 1800L Cold water storage tank, complete with float valve and all fittings and qty 1 1.4 Cold water supply pump; 2 l/s @ 350 kPa; complete with non return valve and two shut-off valves
2
2NoCold water supply pump, 2 l/s @ 350kPa, complete with non return valve and two shut off valves
3
1NoHot water return circulating pump; complete with shut-off valve, all as specified
4
4NoDial type, glycerine filled, 100mm diameter pressure guages; complete with pipe tie-in and isolating valve
5
-145-
Mechanical Hot and Cold water reticulationBill No. 1Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
COLD WATER INSTALLATION
48m42mm Piping6
Copper piping and installation Class 2 copper piping with capillary couplings.
11m35mm Piping7
16m28mm Piping8
59m22mm Piping9
12m15mm Piping10
66m22mm Pipes chased into brickwork including brown paper lagging
11
51m15mm Pipes chased into brickwork including brown paper lagging
12
4NoExpansion loops 28mm13
Expansion loops and off-sets for both cold water installations
4NoOff-sets 22mmø14
34NoElbow 90 degree, 15mm15
Fittings
34NoElbow 9 degree, 22mm16
18NoElbow 90 degree, 35mm17
6NoElbow 90 degree, 42mm18
23NoT-piece 22.22.22 mm19
6NoT-piece 28.22.28 mm20
8NoT-piece 35.35.35 mm21
-146-
Mechanical Hot and Cold water reticulationBill No. 1Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
3NoT-piece 42.42.42 mm22
14NoReducer 22.15 mm23
2NoReducer 28.22 mm24
7NoReducer 35.22 mm25
1NoReducer 35.28 mm26
1NoReducer 42.35 mm27
1NoReducer 42.28 mm28
4No42 mm Isolating ball valve29
Shut-off valves (Stop cocks)
1No28 mm Isolating ball valve30
22No22 mm Isolating ball valve31
13No15 mm Isolating ball valve32
HOT WATER INSTALLATION
10m28 mm Piping33
Class 2 copper piping with capillary couplingsHot water pipe shall be insulated with 25 mm Poly Ethylene foam with Quick seal. Thermal conductivity shall be not more than 0.035 W/m.K. Plastic straps shall be installed over the insulation at not more than 500 mm intervals.
35m22 mm Piping34
12m22 mm Pipes chased into brickwork including brown paper lagging
35
4NoExpansion loops 28 mm36
Expansion loops and off-sets for both HW installations
-147-
Mechanical Hot and Cold water reticulationBill No. 1Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
4NoOff-sets 22 mm37
5NoElbow 90 degree, 28mm38
Fittings
7NoElbow 90 degree, 22mm39
1NoT-piece 22.22.22 mm40
2NoT-piece 28.28.28 mm41
2NoReducer 28.22 mm42
2No28 mm Isolating ball valve43
Shut-off valves (Stop cocks)
4No22 mm Isolating ball valve44
28m22 mm Piping45
Hot water return line
5NoElbow 90 degree, 22mm46
1NoT-piece 22.22.22 mm47
3No22 mm Isolating ball valve48
SOLAR HOT WATER INSTALLATION
2NoSolar panel 2000x1000x80, mounted on stainless steel frame, facing north, 35 degrees from horizontal
49
Equipment
1NoElectric Circulating pump 220V50
1NoControllers and Timers: A programmable geyser timer and a solar AX for Electrical Circulating pump
51
PIPING FOR INSTALLATION
-148-
Mechanical Hot and Cold water reticulationBill No. 1Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
Copper piping and installation
Class 2 copper piping with capillary couplings
50m22 mm Piping52
Hot water pipe shall be insulated with 25 mm Poly Ethylene foam with Quick seal. Thermal conductivity shall be not more than 0.035 W/m.K. Plastic straps shall be installed over the insulation at not more than 500 mm intervals.
2NoT-piece 22.22.22 mm53
20NoElbow 90 degree, 22mm54
-149-
Mechanical Hot and Cold water reticulationBill No. 1Mechanical WorksSection No. 4
Carried to to collection R
Mechanical Hot and Cold water reticulation
Section No. 4
Bill No. 1
AmountPageNo
Mechanical Works
COLLECTION
Rev 01
National Nuclear Regulator
149
148
147
146
145Total Brought Forward from Page No.
-150-
Mechanical Hot and Cold water reticulationBill No. 1Mechanical WorksSection No. 4
Carried Forward to Summary of Section No. 4 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 4
MECHANICAL WORK
BILL NO 2
MECHANICAL FIRE PROTECTION INSTALLATION
For preambles refer to "Model Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemedto fall into Mechanical services Work Group 170 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
The bill of quantities must be read together with the tender specifications and drawings forming part of this tender260-SPEC-FIRE-00-R0
SPECIFICATIONS
260-0116-F-01 Rev3 : GROUND STOREY260-0116-F-02 Rev3 : FIRST STOREY260-0116-F-03 Rev0 : FIRE PLAN SITE LAYOUT
DRAWINGS
ItemProvide all scaffolding, lifting and plant equipment needed for the durantion of the contract
1
GENERAL (REFER TO THE SPECIFICATIONS)
ItemProvide all drawings as specified2
ItemProvide operation and maintenance manuals as specified
3
-151-
Mechanical Fire protection servicesBill No. 2Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
ItemProvide maintenance and guarantee as specified4
ItemCommissioning as specified and required5
ItemTraining as specified6
FIRE WATER PIPING
12m100mm Piping7
Supply and install - Supply and install galvanised steel piping to ASTM A795, complete with clampon fittings,screw connectors, flanged connections
6m75mm Piping8
16m32mm Piping9
6m25mm Piping10
2m100mm11
PVC sleeves for piping through walls, etc. For the following pipe sizes
1m75mm12
1m25mm13
4NoElbow 90 degree, 100mm14
Supply and install item: Pipe fittings
3NoElbow 90 degree, 75mm15
2NoElbow 90 degree, 32mm16
3NoElbow 90 degree, 25mm17
1NoT-piece 32.32.32 mm18
2NoT-piece 100.100.100 mm19
1NoReducer 32.100 mm20
-152-
Mechanical Fire protection servicesBill No. 2Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
2NoReducer 75.100 mm21
2NoReducer 25.32 mm22
SUMPainting to final coulour red of all piping as per specification
23
10NoVentilation point with shutt off valve to manually release all air trapped into the system during filling.
24
SUMRadiography and testing of all welds25
Radiography of welds
5NoPipe supports, hangers and brackets for 100 mm Piping26
Pipe supports, hangers, anchors and brackets
2NoPipe supports, hangers and brackets for 75mm Piping27
6NoPipe supports, hangers and brackets for 32 mm Piping28
2NoPipe supports, hangers and brackets for 25 mm Piping29
SUMPressure testing of total piping system including all valves, fittings, etc.
30
Pressure testing
SUMSterilization of the complete fire water piping system.31
Sterilization of fire water system
FIRE HYDRANTS AND FIRE HOSE REELS
1No100mm Booster connection32
Fire hydrants and fire hose reels
SUMAllowance for additional piping and pressure guages as specified and directed by engineer
33
2No100mm Diameter fire hydrants34
-153-
Mechanical Fire protection servicesBill No. 2Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
4NoHydrant hose, complete with quick coupler connections - 30m long
35
4NoFire hose reels with 30m hose36
FIRE EXTINGUISHERS
16NoSupply of 4.5 kg DCP fire extinguisher37
Fire extinguishers
16NoSupply and mounting of 4.5 kg DCP fire extinguisher backing boards and brackets
38
4NoSupply of 9 kg DCP fire extinguisher39
4NoSupply and mounting of 9 kg DCP fire extinguisher backing boards and brackets
40
SIGNAGE
2NoWall mounted E1 type41
Supply and install photoluminated general escape signage as specified and in positions as indicated on thedrawings, all framed in aluminium, size 190x190mm:
5NoWall mounted E2 type42
3NoWall mounted E3 type43
6NoWall mounted E6 type44
Supply and install electrically iluminated general escapesignage as specified and in positions as indicated on thedrawings, all framed in aluminium, size 190x380mm:
2NoWall mounted F1, size 190x760, complete with aluminium frame
45
Supply and install photoluminated fire equipment indication signage as specified and in positions as indicated on the drawings:
-154-
Mechanical Fire protection servicesBill No. 2Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
2NoWall mounted F4, size 190x570, complete with aluminium frame
46
4NoExternall mounted sign on all fire escape doors indicating fire escape door; framed
47
1No
Free standing assembly point sign, complete with 75mm galvanised mounting pole, installed in position in concrete base 500x500x500 deep
48
SUMAdditional signage required as directed by the engineer49
10m2Supply and install fire stop "CP 678 firestop" as specified in Section 6 for cable penetrations
50
Hilti CP or similar approved fire stop; evacuation chairs; shutters
10ltrSupply and install fire stop "CP 620 firestop" foam as specified in Section 6 for small openings
51
10m
Supply and install fire stop "CP 648-E firestop" wrap strip asspecified in Section 6 for combustible pipe penetrations
52
1m3
Supply and install fire stop "CP 670 firestop' board and'CP 670 firestop' coating as specified in Section 6 for large openings
53
ItemSupply and install additional fire stop to the rates provided above
54
3NoSupply and install evacuation chairs Evac+Chair 300H type with hammock seat and additional equipment as
55
-155-
Mechanical Fire protection servicesBill No. 2Mechanical WorksSection No. 4
Carried to to collection R
Mechanical Fire protection services
Section No. 4
Bill No. 2
AmountPageNo
Mechanical Works
COLLECTION
Rev 01
National Nuclear Regulator
155
154
153
152
151Total Brought Forward from Page No.
-156-
Mechanical Fire protection servicesBill No. 2Mechanical WorksSection No. 4
Carried Forward to Summary of Section No. 4 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 4
MECHANICAL WORK
BILL NO 3
MECHANICAL HVAC INSTALLATION
For preambles refer to "Model Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemedto fall into Mechanical services Work Group 170 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
The bill of quantities must be read together with the tender specifications and drawings forming part of this tender260-SPEC-FIRE-00-R0
SPECIFICATIONS
260-0116-F-01 Rev3 : GROUND STOREY260-0116-F-02 Rev3 : FIRST STOREY260-0116-F-03 Rev0 : FIRE PLAN SITE LAYOUT
DRAWINGS
SUMProvide all scaffolding, lifting and plant equipment needed for the durantion of the contract
1
GENERAL (REFER TO THE SPECIFICATIONS)
SUMProvide all drawings as specified2
SUMProvide operation and maintenance manuals as specified
3
-157-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
SUMProvide maintenance and guarantee as specified4
SUMCommissioning as specified and required5
SUMTraining as specified6
VENTILATION EQUIPMENT
1NoTransformation piece, galvanised steel, discharge plenum box size (500 x 300mm) to attenuator size
7
EAF-01
1NoFlexible connection between attenuator and transformation piece-suction side
8
1NoSonax 2.0D Sound Attenuator,Size Ø250 x 500mm, suction side, complete with mounting brackets
9
1NoFan, EAF-01, complete with mounting brackets flanged and hard connection to attenuators
10
1NoSonax 2.0D Sound Attenuator,Size Ø250 x 500mm, discharge side, complete with mounting brackets
11
1NoTransformation piece, galvanised steel, attenuator size to ducting size ( Ø300mm )
12
2mDucting, galvanised sheet metal, Ø300mm13
4mDucting, galvanised sheet metal, Ø250mm14
8mDucting, galvanised sheet metal, Ø200mm15
3NoBend 90°, galvanised sheet metal, Ø200mm16
1NoTransformation piece, galvanised sheet metal, Ø250mm to Ø200mm
17
12mFlexible Ducting Ø200mm18
6NoEAV-0119
Extract air grilles / valves
-158-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
3No DG-0120
Door Grilles
1NoWL-01 21
Weather Louvre
1NoTransformation piece, galvanised steel, discharge plenum box size (300 x 200mm) to attenuator size
22
EAF-02
1No
Flexible connection between attenuator and transformation piecesuction side complete with mounting brackets
23
1NoSonax 2.0D Sound Attenuator,Size Ø150 x 300mm, suction side, complete with mounting brackets
24
1NoFan, EAF-02, complete with mounting brackets flanged and hard connection to attenuators
25
1NoSonax 2.0D Sound Attenuator,Size Ø150 x 300mm, discharge side, complete with mounting brackets
26
1NoTransformation piece, galvanised steel, attenuator size to ducting size ( Ø200mm )
27
4mDucting, galvanised sheet metal, Ø200mm 28
1NoBend 90°, galvanised sheet metal, Ø200mm29
3mFlexible Ducting Ø200mm30
2NoEAV-02 31
Extract air grilles / valves
1NoDG-02 32
Door Grilles
-159-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
1NoWL-02 33
Weather Louvre
1NoTransformation piece, galvanised steel, discharge plenum box size (400 x 300mm) to attenuator size
34
EAF-03
1NoFlexible connection between attenuator and transformation piecesuction side
35
1NoSonax 2.0D Sound Attenuator,Size Ø200 x 400mm, suction side, complete with mounting brackets
36
1NoFan, EAF-03, complete with mounting brackets flanged and hard connection to attenuators
37
1NoSonax 2.0D Sound Attenuator,Size Ø200 x 400mm, discharge side, complete with mounting brackets
38
1NoTransformation piece, galvanised steel, attenuator size to ducting size ( Ø250mm )
39
4mDucting, galvanised sheet metal, Ø250mm40
1NoTransformation piece, galvanised sheet metal, Ø250mm to Ø150mm
41
6mDucting, galvanised sheet metal, Ø150mm 42
2NoBend 90°, galvanised sheet metal, Ø150mm43
3mFlexible Ducting Ø150mm44
2mDucting, galvanised sheet metal, Ø125mm45
6mFlexible Ducting Ø125mm46
2NoEAV-03 47
Extract air grilles / valves
4NoEAV-04 48
-160-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
1NoDG-01 49
Door Grilles
1NoDG-03 50
1NoWL-03 51
Weather Louvre
1NoTransformation piece, galvanised steel, discharge plenum box size (500 x 300mm) to attenuator size
52
EAF-04
1NoFlexible connection between attenuator and transformation piecesuction side
53
1No
Sonax 2.0D Sound Attenuator,Size Ø350x700mm, suction side,complete with mounting brackets
54
1NoFan, EAF-04, complete with mounting brackets flanged and hard connection to attenuators
55
1NoSonax 2.0D Sound Attenuator,Size Ø350x700mm, discharge side, complete with mounting brackets
56
1NoTransformation piece, galvanised steel, attenuator size to ducting size ( Ø350mm )
57
2mDucting, galvanised sheet metal, Ø350mm58
1NoTransformation piece, galvanised sheet metal, Ø250mm to Ø200mm
59
4mDucting, galvanised sheet metal, Ø250mm60
1NoBend 90°, galvanised sheet metal, Ø200mm61
6mDucting, galvanised sheet metal, Ø200mm 62
8m Flexible Ducting Ø200mm63
-161-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
5NoEAV-0564
Extract air grilles / valves
1NoDG-01 65
Door Grilles
1NoDG-0466
1NoWL-0467
Weather Louvre
AIR-CONDITIONING EQUIPMENT
1NoAC-01, 4-Way Cassete Unit 68
AC UNITS, all as Specified
1NoAC-02, 4-Way Cassete Unit 69
1NoAC-03, 4-Way Cassete Unit70
1NoAC-04, 4-Way Cassete Unit71
1No
Hide-away unit as specified, complete with vibration isolation,mounting brackets, flexible connections as specified
72
AC-05, Hide Away Unit
1NoSupply air attenuator 900 x 400 x 800mm 73
1NoReturn air attenuator 1000 x 400 x 800mm74
1No
Transformation piece, galvanised steel, AC-05 Unit size to400x300mm
75
Supply Air Ducting for AC-05, All insulated
2mDucting, galvanised sheet metal, 400x300mm76
-162-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
1NoTransformation piece, galvanised steel, 400x300mm to Ø250mm
77
4No90 Degree bend , galvanised sheet metal, Ø250mm78
9mDucting, galvanised sheet metal, Ø250mm 79
2mFlexible Ducting Ø250mm 80
2NoTransformation piece, galvanised steel, Ø250mm to Box for SAG-01 ( 420x250mm )
81
1NoPlenum box 1000mm wide x 500mm long x 400mm high attached to AC-05 unit
82
Return Air Ducting for AC-05, All insulated
2NoSAG-0183
Supply air grilles / diffusers
1NoSAD-0284
1NoRAG-02 85
Return air grilles
1NoAC-06, 4-Way Cassete Unit86
AC UNITS, all as Specified
1NoAC-07, 4-Way Cassete Unit87
1NoAC-08, 4-Way Cassete Unit88
1NoAC-09, 4-Way Cassete Unit 89
1NoAC-12, 4-Way Cassete Unit90
1NoAC-13, 4-Way Cassete Unit 91
1NoAC-14, 4-Way Cassete Unit 92
1NoAC-15, 4-Way Cassete Unit93
-163-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
1NoAC-16, 4-Way Cassete Unit94
1NoAC-17, 4-Way Cassete Unit95
1No
Hide-away unit as specified, complete with vibration isolation,mounting brackets, flexible connections as specified
96
AC-18, Hide Away Unit
1NoSupply air attenuator 900x400x800mm97
1NoReturn air attenuator 1000x400x800mm98
1No
Transformation piece, galvanised steel, AC-18 Unit size to500x300mm
99
Supply Air Ducting for AC-18, All insulated
1mDucting, galvanised sheet metal, 500x300mm100
1NoTransformation piece, galvanised steel, 500x300mm to 350x300mm
101
3mDucting, galvanised sheet metal, 350x300mm102
1No90 Degree bend , galvanised sheet metal, 350x300mm103
1No
Transformation piece (shoe), galvanised steel, 500x300mm to200x300mm
104
2mDucting, galvanised sheet metal, 200x300mm 105
3mDucting, galvanised sheet metal, Ø300mm106
3mFlexible Ducting Ø300mm107
1NoPlenum box 1000Wx500Lx 400H attached to AC-18 unit108
Return Air Ducting for AC-18, All insulated
-164-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
3NoSAD-03 109
Supply air grilles / diffusers
1NoRAG-01110
Return air grilles
1NoAC-19, 4-Way Cassete Unit111
AC UNITS, all as Specified
1NoAC-20, 4-Way Cassete Unit 112
1NoAC-21, 4-Way Cassete Unit 113
1NoAC-22, 4-Way Cassete Unit 114
1No
Hide-away unit as specified, complete with vibration isolation,mounting brackets, flexible connections as specified
115
AC-23, Hide Away Unit
1NoSupply air attenuator 1200x400x600L 116
1NoReturn air attenuator 1200x400x600L117
1No
Transformation piece, galvanised steel, AC-23 Unit size to700x350mm
118
Supply Air Ducting for AC-23, All insulated
2mDucting, galvanised sheet metal, 700x350mm119
1NoTransformation piece(shoe), galvanised steel, 700x350mm to 500x300mm
120
2mDucting, galvanised sheet metal, 500x300mm121
1NoTransformation piece, galvanised steel, 500x300mm to 400x250mm
122
5mDucting, galvanised sheet metal, 400x250mm123
-165-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
1NoTransformation piece(shoe), galvanised steel, 700x350mm to 400x250mm
124
1No90 Degree bend , galvanised sheet metal, Ø250mm 125
5mDucting, galvanised sheet metal, Ø250mm126
5mFlexible Ducting Ø250mm 127
1NoPlenum box 1000Wx500Lx 400H attached to AC-23 unit 128
Return Air Ducting for AC-23, All insulated
5NoSAD-02129
Supply air grilles / diffusers
1NoRAG-01130
Return air grilles
Condensing Units
1No
Condensing unit complete with mounting brackets, vibrationissolation as specified
131
CU-01
SUM
Refrigeration pipes, complete with cable trays; installed asspecified
132
1No
Condensing unit complete with mounting brackets, vibrationissolation as specified
133
CU-02
SUM
Refrigeration pipes, complete with cable trays; installed asspecified
134
SUMCondensate drains to all units, complete as specified 135
-166-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
SUMCentralised controls as specified 136
-167-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
DUCTED SPLIT PACKAGE DX UNIT FOR FRESH AIR
1No
Air handling unit AHU-01 as specified, complete with mountingframe, vibration issolation pads, motorised fresh air damper and
137
AHU-01
1NoTransformation piece, galvanised steel, AHU-01 Unit size to Sound Attenuator size 1000x600
138
Supply air ducting, all insulated
1NoSound Attenuator 1000x600x1100L 139
1NoTransformation piece, galvanised steel, Sound Attenuator to dual ducts size 500x350 and 900x550
140
3No90 Degree bend , galvanised sheet metal, 900x550 141
4No90 Degree bend , galvanised sheet metal, 900x550 142
8mDucting, galvanised sheet metal, 900x550 143
11mDucting, galvanised sheet metal, 500x350 144
4mDucting, galvanised sheet metal, 550x300145
Dropper 900x550 to First Storey
1No90 Degree bend , galvanised sheet metal, 550x300 146
1No
T-Piece, galvanised sheet metal, 550x300 to 300x300 and400x300
147
3mDucting, galvanised sheet metal, 300x300 148
Branch 1 (300x300)
1No
Transformation piece (Shoe), galvanised steel, 300x300 to250x250
149
-168-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
15mDucting, galvanised sheet metal, 250x250150
1NoTransformation piece, galvanised steel, 300x300 to 250x250
151
1NoTransformation piece, galvanised steel, 250x250 t 150x150
152
10mDucting, galvanised sheet metal, 150x150153
8mDucting, galvanised sheet metal, Ø200154
8mFlexible Ducting Ø200 155
6mDucting, galvanised sheet metal, Ø150 156
3mFlexible Ducting Ø150157
12mDucting, galvanised sheet metal, 400x300158
Branch 2 (400x300)
3No90 Degree bend , galvanised sheet metal, 400x300159
1NoTransformation piece, galvanised steel, 400x300 to 250x250
160
3mDucting , galvanised sheet metal, 250x250 161
6mDucting, galvanised sheet metal, Ø200162
1mDucting, galvanised sheet metal, Ø250163
2NoTransformation piece, galvanised steel, Ø250 to Box for SAG-01 (420x250 )
164
1NoTransformation piece, galvanised steel, 250x250 to 250x200
165
4mDucting , galvanised sheet metal, 250x200 166
1NoTransformation piece, galvanised steel, 250x200 to 200x200
167
-169-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
6mDucting , galvanised sheet metal, 200x200168
1NoTransformation piece, galvanised steel, 200x200 to 150x200
169
2mDucting , galvanised sheet metal, 150x200 170
1NoTransformation piece, galvanised steel, 150x200 to 150x150
171
2mDucting , galvanised sheet metal, 150x150 172
3mDucting, galvanised sheet metal, Ø150173
5mFlexible Ducting Ø200174
3mFlexible Ducting Ø150 175
1No90 Degree bend , galvanised sheet metal, 400x400 176
Dropper 900x550 to Ground Storey
3mDucting, galvanised sheet metal, 400x400177
1No
Transformation piece (shoe), galvanised steel, 400x400 to300x300
178
21mDucting, galvanised sheet metal, 300x300179
2No90 Degree bend , galvanised sheet metal, 300x300 180
1NoTransformation piece, galvanised steel, 300x300 to 200x250
181
5mDucting, galvanised sheet metal, 200x250182
1NoTransformation piece, galvanised steel, 200x250 to Ø200
183
25mDucting, galvanised sheet metal, Ø200184
12mFlexible Ducting Ø200 185
-170-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
2mDucting, galvanised sheet metal, Ø150186
2mFlexible Ducting Ø150 187
1NoTransformation piece, galvanised steel, 400x400 to 300x300
188
1NoTransformation piece, galvanised steel, 300x300 to 300x250
189
1No
Transformation piece (shoe), galvanised steel, 300x250 to250x250
190
6mDucting, galvanised sheet metal, 300x250191
3mDucting, galvanised sheet metal, 250x250 192
1NoTransformation piece, galvanised steel, 300x250 to 150x200
193
8mDucting, galvanised sheet metal, 150x200194
1NoTransformation piece, galvanised steel, 150x200 to Ø200
195
1No90 Degree bend , galvanised sheet metal, Ø200196
1No90 Degree bend , galvanised sheet metal, 500x350 197
Dropper 550x300 to Ground Storey
4m2 Ducting, galvanised sheet metal, 500x350 198
1NoTransformation piece, galvanised steel, 500x350 to 400x350
199
17mDucting, galvanised sheet metal, 400x350 200
2No90 Degree bend , galvanised sheet metal, 400x350 201
1NoTransformation piece, galvanised steel, 400x350 to 300x300
202
-171-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
12mDucting, galvanised sheet metal, 300x300 203
2No90 Degree bend , galvanised sheet metal, 300x300 204
1NoTransformation piece(shoe), galvanised steel, 500x350 to 250x250
205
1mDucting, galvanised sheet metal, 250x250206
1NoTransformation piece(shoe), galvanised steel, 400x350 to 300x300
207
2NoSAG-01 208
Supply air grilles / diffusers
8NoSAD-01 209
5NoSAV-01210
8NoSAV-02 211
5NoØ150 212
Balancing Dampers
12NoØ200 213
1No250x250 214
2No300x300215
1No500x350216
Motorised Control Dampers
1No900x550217
1No300x300 218
Volume Control Dampers
1No400x300219
-172-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
1NoFD-01 (550x300) 220
Fire Dampers
1NoFD-02 (400x400)221
1NoFD-03 (500x350)222
14NoDG-01 223
Door Grilles
1No
CU-03, Condensing unit complete with mounting brackets,vibration issolation as specified
224
CONDENSING UNIT
SUMCU-03, Refrigeration pipes, complete with cable trays; installed as specified
225
SUMCondensate drains for ahu-01, complete as specified226
SUMCentralised control as specified 227
HIDE-AWAY SPLIT DX UNITS FOR AUDITORIUM
1No
Hide-away unit as specified, complete with vibration isolation,mounting brackets, flexible connections as specified
228
AC-24, Hide Away Unit
1NoSupply air attenuator 1200x400x600L 229
1No3 Return air attenuator 1200x400x600L 230
1No
Transformation piece, galvanised steel, AC-24 Unit size to500x400
231
Supply Air Ducting for AC-24, All insulated
6mDucting, galvanised sheet metal, 500x400232
-173-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
1No90 Degree bend , galvanised sheet metal, 500x400 233
1NoTransformation piece(shoe), galvanised steel, 500x400 to 550x350
234
1mDucting, galvanised sheet metal, 550x350235
1NoTransformation piece, galvanised steel, 550x350 to 200x350
236
3mDucting, galvanised sheet metal, 200x350237
1NoTransformation piece(shoe), galvanised steel, 500x400 to 200x350
238
1mDucting, galvanised sheet metal, Ø250239
2mFlexible Ducting Ø250 240
3mDucting, galvanised sheet metal, Ø300241
5mFlexible Ducting Ø300242
1No
Transformation piece, galvanised steel, AC-24 Unit size to700x400
243
Return Air Ducting for AC-24, All insulated
3mDucting, galvanised sheet metal, 700x400 244
1NoSAD-02245
Supply air grilles / diffusers
3NoSAD-03246
1No
Hide-away unit as specified, complete with vibration isolation,mounting brackets, flexible connections as specified
247
AC-25, Hide Away Unit
1NoSupply air attenuator 1200x400x600L 248
-174-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
1NoReturn air attenuator 1200x400x600L249
1No
Transformation piece, galvanised steel, AC-25 Unit size to500x400
250
Supply Air Ducting for AC-25, All insulated
7mDucting, galvanised sheet metal, 500x400 251
3No90 Degree bend , galvanised sheet metal, 500x400252
1NoTransformation piece(shoe), galvanised steel, 500x400 to 550x350
253
1mDucting, galvanised sheet metal, 550x350 254
1NoTransformation piece, galvanised steel, 550x350 to 400x350
255
2mDucting, galvanised sheet metal, 400x350256
1NoTransformation piece(shoe), galvanised steel, 500x400 to 300x350
257
2mDucting, galvanised sheet metal, 300x350 258
3mDucting, galvanised sheet metal, Ø300 259
5mFlexible Ducting Ø300260
2mDucting, galvanised sheet metal, Ø250261
3mFlexible Ducting Ø250 262
1No
Transformation piece, galvanised steel, AC-25 Unit size to700x400
263
Return Air Ducting for AC-25, All insulated
3mDucting, galvanised sheet metal, 700x400264
-175-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
2NoSAD-02 265
Supply air grilles / diffusers
3NoSAD-03266
1No
CU-04, Condensing unit complete with mounting brackets,vibration issolation as specified
267
CONDENSING UNIT
SUMCU-04, Refrigeration pipes, complete with cable trays; installed as specified
268
SUMCondensate drains for AC-24/25, complete as specified269
1NoAC-10, High Split Wall Unit270
HIGH WALL SPLIT DX UNITS FOR SERVER ROOM
1NoAC-11, High Split Wall Unit 271
1No
CU-05, Condensing unit complete with mounting brackets,vibration issolation as specified
272
SUMCU-05, Refrigeration pipes, complete with cable trays; installed as specified
273
1No
CU-06, Condensing unit complete with mounting brackets,vibration issolation as specified
274
SUMCU-06, Refrigeration pipes, complete with cable trays; installed as specified
275
SUMCondensate drains for AC10/11, complete as specified276
SUM
Allowance for additional sound control over and above measureditems
277
SOUND CONTROL EQUIPMENT
-176-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
SUM
Design, supply, installation of electrical power installations fromDB to all equipmentment as specified; sections 3,4,5,6
278
ELECTRICAL INSTALLATION
SUMElectrical installation from isolators to all equipment as specified; section 2
279
SUMCertificate of compliance on completion of the installation
280
-177-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried to to collection R
174
173
172
171
170
169
168
167
166
165
164
163
162
161
160
159
158
157Total Brought Forward from Page No.
Mechanical HVAC
Section No. 4
Bill No. 3
AmountPageNo
Mechanical Works
COLLECTION
Rev 01
National Nuclear Regulator
-178-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried Forward R
Mechanical HVAC
Section No. 4
Bill No. 3
AmountPageNo
Mechanical Works
COLLECTION
Brought Forward R
Rev 01
National Nuclear Regulator
177
176
175Total Brought Forward from Page No.
-179-
Mechanical HVACBill No. 3Mechanical WorksSection No. 4
Carried Forward to Summary of Section No. 4 R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 4
MECHANICAL WORK
BILL NO 4
MECHANICAL LIFT INSTALLATION
For preambles refer to "Model Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemedto fall into Mechanical services Work Group 170 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
The bill of quantities must be read together with the tender specifications and drawings forming part of this tenderMechanical Lift Specification
SPECIFICATIONS
260-0116-LIFT-01-R0
DRAWINGS
SUMProvide all scaffolding, lifting and plant equipment needed for the durantion of the contract
1
GENERAL (REFER TO THE SPECIFICATIONS)
SUMProvide all drawings as specified2
SUMProvide operation and maintenance manuals as specified
3
SUMProvide maintenance and guarantee as specified4
-180-
Mechanical Lift installationBill No. 4Mechanical WorksSection No. 4
Carried to to collection R
Rev 01
National Nuclear Regulator
SUMCommissioning as specified and required5
SUMTraining as specified6
SUMAnnexure A inspections by lift inspector and issuing of specified and required documentation per lift
7
SUMElectrical inspection, testing and issuing of certificate of compliance by electrical contractor
8
SUMSupply and installation of complete new lift as per specifications and drawings
9
LIFT INSTALLATION
SUMSupply and install battery back-up10
SUMSupply and install fire man's lift function11
SUMSupply and install lift shaft ventilation as specified12
SUMSupply and install new electrical installation inclusive ofDistribution board in machine compartment
13
Machine Room
SUMSupply and install new lighting installation in machinecompartment, all as specified
14
SUMSupply and install new electrical and lighting installation to pit, all as specified
15
Lift pit
SUMSupply and install new lighting installation to lift shaft, all as specified
16
SUM
Supply and install new sump pump and discharge piping up to drain as specified; complete with level sensor and alarm
17
Other
SUMSupply and install new galvanised ladder from GFL to Pit, all as specified
18
-181-
Mechanical Lift installationBill No. 4Mechanical WorksSection No. 4
Carried to to collection R
Mechanical Lift installation
Section No. 4
Bill No. 4
AmountPageNo
Mechanical Works
COLLECTION
Rev 01
National Nuclear Regulator
181
180Total Brought Forward from Page No.
-182-
Mechanical Lift installationBill No. 4Mechanical WorksSection No. 4
Carried Forward to Summary of Section No. 4 R
Rev 01
National Nuclear Regulator
Mechanical Works
SECTION SUMMARY - Mechanical Works
BillNo
PageNo
Amount
Section No. 4
150Mechanical Hot and Cold water reticulation1
156Mechanical Fire protection services2
179Mechanical HVAC3
182Mechanical Lift installation4
-183-
Mechanical WorksSection No. 4
Carried to Final Summary R
AmountItemNo
Quantity RateUnitSANSPay Ref
Rev 01
National Nuclear Regulator
SECTION NO 5
CIVIL WORKSSANS 1200
BILL NO 1
SANS 1200 C - SITE CLEARANCE
For Preambles see "Model Of Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemed to fall into Earthworks Work Group 104 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
4 500m2Clear and grub site to a depth of 0.15m and spoil waste off site
1
SITE CLEARANCE
1 000m3
Uncontrolled fill to be windrowed, moisten to 2% OMC and compacted in layers < 300mm to 98% over-excavate the fill material to 1.0m depth and remove any waste. Compact the transported sands in-situ using a heavy vibratory roller. Replace the screened fill, or bring in a suitable granular material, in layers compacted to 98% Mod AASHTO up to terrace/constructionlevels - Remedial work 1
2
500m3
Stockpile 0.5m depth of material and replace when insithu remedial work is complete - Compaction same as item 2
3
-184-
SANS 1200D - Site Clearance and EarthBill No. 1Civil WorksSection No. 5
Carried to to collection R
Rev 01
National Nuclear Regulator
100m3
Cement-stabilized layer 1.0 m thick is required from founding level down. Stabilization with 5% cement is required with compaction to at least 95% Mod AASHTO
4
100m3Rip up and stockpile on site road layersworks for re-use as subbase.
5
200m3Remove unsuitable fill off site to spoil offsite
6
1 000m3
Preperation of fill areas - rip and re-compact to a depth of 500mm - compaction to 93% Mod AASHTO density
7
EARTHWORKS
500m3a) Excavate in all materials and spoil off site
8
Bulk excavation
750m3
b) Excavate in all materials and fill onsite and compact to 95% Mod Aashto density.
9
50m3i) excavation in intermediate materials10
c) Extra over for item 2.9 above for:
50m3ii) excavation in hard rock.11
200m3
Importation of clean fill (CBR > 15) from commercial source placed to
levels and compacted to 95% Mod AASHTO (100% for sand) for building platforms
12
150m3Extra over Item 8.3.4 above for backfilling against retaining walls
13
-185-
SANS 1200D - Site Clearance and EarthBill No. 1Civil WorksSection No. 5
Carried to to collection R
SANS 1200D - Site Clearance and Earthworks
Section No. 5
Bill No. 1
AmountPageNo
Civil Works
COLLECTION
Rev 01
National Nuclear Regulator
185
184Total Brought Forward from Page No.
-186-
SANS 1200D - Site Clearance and EarthBill No. 1Civil WorksSection No. 5
Carried Forward to Summaryof Section No. 5
R
AmountItemNo
Quantity RateUnitSANSPay Ref
Rev 01
National Nuclear Regulator
SECTION NO 5
CIVIL WORKSSANS 1200
BILL NO 2
SANS 1200 DM - EARTHWORKS (ROADS, SUBGRADE)
For Preambles see "Model Of Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemed to fall into Roadwork Work Group 154 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
2 100m3
Selectmaterial from road box cut excavation and stockpile on site for re-use. To include maintenance (dust control) for duration of contract
1
EARTHWORKS (ROADS, SUBGRADE)
Treatment of road-bed
600m3a) Roadways / Parking area2
Road-bed preparation and compaction of material to a minimum of 95% mod AASHTO density (150 mm thick)
100m3b) Sidewalks3
100m3c) Roadways in delivery yards4
-187-
SANS 1200 DM - Roads & SubgradeBill No. 2Civil WorksSection No. 5
Carried to to collection R
Rev 01
National Nuclear Regulator
800m3Cut to fill, level and compact to 93% Mod AASHTO
5
200m3a) From stockpile to road box6
300m3Importation of fill from commercial source for road prism
7
100m3a) 150mm thick for access roadways8
Construct selected layer with G7 material from commercial source compacted to 93% Mod AASHTO density (100% for sand)
210m3b) 150mm thick for parking area9
450m2
c) 400mm thick for Permeable paving(Complete including subsurface drain)
10
60m3d) 100mm thick under walkways11
500m3a) Soft excavation for roads spoiled off site
12
Cut to spoil
100m3b) From stockpiled material on site13
50m3i) excavation in intermediate materials14
Extra over item 3.11 above for:
50m3ii) excavation in hard rock.15
SUBBASE
300m3a) 150mm thick under roadways / Parking
16
Construct subbase with gravel (G5 quality) material compacted to 95% from commercial sources
-188-
SANS 1200 DM - Roads & SubgradeBill No. 2Civil WorksSection No. 5
Carried to to collection R
Rev 01
National Nuclear Regulator
50m3b) 150 mm thick under delivery yard17
150m3c) 150 mm thick to building platform18
100m3
Construct subbase with gravel material (G5 quality) 100mm thick compacted to 95 Mod AASHTO density under walkways using stockpiled material removed under site clearance
19
2 377m2
Construct 80mm rectangular grey cement pavers (35MPa) in 90 degree herringbone pattern for walkways including 20mm bedding sand for service areas
20
SEGMENTED PAVING
500mCutting units to fit edge restraints for item 3.28 above
21
100mCutting units to fit edge restraints for item 3.29 above
22
PRECAST CONCRETE KERBING
(Refer to details -R-1a and -R-1b)
Concrete Kerbing on concrete
50mOn radius < 20 m23
a) Barrier Kerb Type BK2
50mOn radius > 20 m24
300mOn radius < 20 m25
b) E1 Edging
50mOn radius > 20 m26
Concrete kerbing & channeling combined.
-189-
SANS 1200 DM - Roads & SubgradeBill No. 2Civil WorksSection No. 5
Carried to to collection R
Rev 01
National Nuclear Regulator
300mOn radius < 20m27
a) Barrier Kerb Type BK2 + C1 channel
100mOn radius > 20m28
100mOn radius < 20m29
b) 2 x C1 channels
50mOn radius > 20m30
4mExtra over item 3.43 (BK1+C1<20m) above for dropped kerb
31
c) E3 edging + C2 channel for stormwater channel behind building
4mExtra over item 3.44 (BK1+C1>20m) above for dropped kerb
32
20NoConstruct tree surround with BK1 kerbs, full diamond tree planter complete
33
20NoConsruct tree surround with BK1 kerbs, half tree planter complete
34
20No
Inlet, outlet, tansition and similar structures with 25 Mpa concrete, steel floated
35
Ancillaries
1 000ma) 100 mm wide white line, broken or unbroken
36
Non-reflectorized paint applied at nominal rate of 0,42 l/m², including setting out and pre-marking
50mb) 150 mm wide white line, broken or unbroken
37
25mc) 300 mm wide white line, broken or unbroken
38
-190-
SANS 1200 DM - Roads & SubgradeBill No. 2Civil WorksSection No. 5
Carried to to collection R
Rev 01
National Nuclear Regulator
25md) 150 mm wide yellow line, broken or unbroken
39
20Noe) White letters 1.25m high40
20m2f) White blocks for pedstrian crossing41
1Nog) Wheelchair parking bay symbol42
50Noh) White directional arrows43
20m2i) Yellow RM5 painted traffic islands44
6Noj) White WM5 yield symbol45
20mk) GM 8 black and white kerb face marking
46
6Noa) R1 Stop sign47
Sign faces with painted background, with painted symbols, characters, legend constructed from 2mm thick aluminium sheet of area up to 2m² for the following signs
2Nob) R3 No Entry sign48
2Nod) R2.1 Yield for pedestrians sign 49
2Noe) W306 Pedestrian crossing ahead sign
50
1Nog) W413 Double Chevron sign51
12No
Galvanised round long steel pole for signs above including all bolts, brackets, excavation, and concrete filling around pole
52
12No
Galvanised round short steel pole for signs above including all bolts, brackets, excavation, and concrete filling around pole
53
-191-
SANS 1200 DM - Roads & SubgradeBill No. 2Civil WorksSection No. 5
Carried to to collection R
SANS 1200 DM - Roads & Subgrade
Section No. 5
Bill No. 2
AmountPageNo
Civil Works
COLLECTION
Rev 01
National Nuclear Regulator
191
190
189
188
187Total Brought Forward from Page No.
-192-
SANS 1200 DM - Roads & SubgradeBill No. 2Civil WorksSection No. 5
Carried Forward to Summaryof Section No. 5
R
AmountItemNo
Quantity RateUnitSANSPay Ref
Rev 01
National Nuclear Regulator
SECTION NO 5
CIVIL WORKSSANS 1200
BILL NO 3
SANS 1200 DB - EARTHWORKS (PIPE TRENCHES)
For Preambles see "Model Of Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemed to fall into Earthworks Work Group 104 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
EARTHWORKS (PIPE TRENCHES)
20mi) 0 - 1m deep1
a) Excavate in all materials for trenches, backfill, compact and dispose of surplus material for up to 525mm diam pipe off site :
100mii) 1 - 2m deep2
450miii) Subsoil drains 0-1m deep3
BEDDING (PIPES)
-193-
SANS 1200 LE - StormwaterBill No. 3Civil WorksSection No. 5
Carried to to collection R
Rev 01
National Nuclear Regulator
30m3a) Selected granular material4
Supply only bedding and compacted to 100% Mod AASHTO from commercial source
60m3b) Selected fill material5
50m3c) Extra blanket for under roads6
50m3d) Free drainage sand for use as filling on top of subsoil drains
7
450m
Supply, Lay & Bed 110mm geopipe in 300x300mm stone bedding wrapped in U14 Geofabric
8
STORMWATER DRAINAGE
70m
Supply, Lay & Bed 110mm geopipe in 1000x300mm stone bedding wrapped in U14 Geofabric (Swale)
9
50mi) 300 mm diameter10
Supply, Lay & Bed Concrete Pipe Class 100D on class B type bedding (Spigo and socket):
110mii) 375 mm diameter11
10miii) 450 mm diameter12
50mii) 250 mm diameter13
Supply, Lay & Bed uPVC Pipe Class 34 on flexible type bedding
6No250 mm diameter end caps14
Special fittings:
6No250 x 250mm Y-junction15
-194-
SANS 1200 LE - StormwaterBill No. 3Civil WorksSection No. 5
Carried to to collection R
Rev 01
National Nuclear Regulator
Supply and install Manholes, Catchpits and the like (excavation and backfilling included)
6Noii) Depth between 1m and 2m16
a) Manholes (1.0m diameter concrete ring with type 4 cast iron cover and frame (St Gobain or similar approved)
6No
Extra over items i & ii above for type 2A CI covers and frames in place of Type 4(under roadways)
17
6No
b) 450x450 medium duty cast iron grid inlet not exceeding 600mm deep as per detail(type 2946 St Gobain or similar approved)
18
8No
c) Double heavy duty cast irongrid inlet 2x450x600(type 2898 St Gobain or similar approved)
19
2No
d) Single heavy duty cast irongrid inlet 1x450x600 (type 2898 St Gobain or similar approved)
20
2No
e) Double kerb inlet to match existing municipal structure complete not exceeding 900mm deep
21
1NoConvert existing kerb inlet into underground junction box
22
20NoSubsoil drain endcap complete including bends
23
1NoBrick up pipe openings for 300mm diameter concrete pipes
24
1No
Break into existing manhole for new 450mm pipe complete with new benching
25
-195-
SANS 1200 LE - StormwaterBill No. 3Civil WorksSection No. 5
Carried to to collection R
Rev 01
National Nuclear Regulator
1NoBreak into existing stormwater inlet for new 300mm stormwater pipe
26
20m2Reinstate road layers complete to match existing
27
10m
Mentis grating inlet and structure Stormwater grating and frame - complete to suitMentis grating type RS40 : 25x45 - 325 mm width
28
-196-
SANS 1200 LE - StormwaterBill No. 3Civil WorksSection No. 5
Carried to to collection R
SANS 1200 LE - Stormwater
Section No. 5
Bill No. 3
AmountPageNo
Civil Works
COLLECTION
Rev 01
National Nuclear Regulator
196
195
194
193Total Brought Forward from Page No.
-197-
SANS 1200 LE - StormwaterBill No. 3Civil WorksSection No. 5
Carried Forward to Summaryof Section No. 5
R
AmountItemNo
Quantity RateUnitSANSPay Ref
Rev 01
National Nuclear Regulator
SECTION NO 5
CIVIL WORKSSANS 1200
BILL NO 4
SANS 1200 DB - EARTHWORKS (PIPE TRENCHES)
For Preambles see "Model Of Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemed to fall into Earthworks Work Group 104 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
EARTHWORKS (Pipe Trenches)
20mi) 0 - 1 m deep1
a) Excavate in all materials for trenches, backfill, compact and dispose of surplus material off site for up to 150mm diam pipe:
90mii) 1 - 2 m deep2
Extra over items i to iii above for
50m3i) Intermediate excavation3
Supply, Lay, Joint, Bed (on flexible pipe bedding) and test pipeline
BEDDING (PIPES)
-198-
SANS 1200 LD - Foul SewerBill No. 4Civil WorksSection No. 5
Carried to to collection R
Rev 01
National Nuclear Regulator
30m3a) Selected granular material4
a) Supply bedding and compacted to 100% Mod AASHTO from commercial source
60m3b) Selected fill material5
50m3c) Extra blanket for under road areas6
SEWERS
110m160mm diameter uPVC class 34 sewer pipe
7
Supply, Lay, Joint, Bed (on flexible pipe bedding)and test pipeline
50m110mm diameter uPVC Class 34 sewer pipe
8
2No45 degree, 160 to 110mm Y-junction9
Extra over items i & ii above the following uPVC underground specials, including cutting of pipes to lengths and all collars
2No45 degree, 110mm diameter bend10
2No110mm end cap11
7No1 - 2 m depth12
Precast 1m diameter concrete ring manholes with type 4A cast iron cover and frame (St Gobain or similar approved)
5No
Extra over items i to ii above for type 2A cast iron covers and frames in place of type 4
13
-199-
SANS 1200 LD - Foul SewerBill No. 4Civil WorksSection No. 5
Carried to to collection R
Rev 01
National Nuclear Regulator
2No1 - 2 m depth14
Built rectangular brick manhole cover (St Gobain or similar approved)
10NoMarker post15
1No
Break into existing pipe for new manhole (manhole measured elsewhere ) all included
16
-200-
SANS 1200 LD - Foul SewerBill No. 4Civil WorksSection No. 5
Carried to to collection R
SANS 1200 LD - Foul Sewer
Section No. 5
Bill No. 4
AmountPageNo
Civil Works
COLLECTION
Rev 01
National Nuclear Regulator
200
199
198Total Brought Forward from Page No.
-201-
SANS 1200 LD - Foul SewerBill No. 4Civil WorksSection No. 5
Carried Forward to Summaryof Section No. 5
R
AmountItemNo
Quantity RateUnitSANSPay Ref
Rev 01
National Nuclear Regulator
SECTION NO 5
CIVIL WORKSSANS 1200
BILL NO 5
SANS 1200 LF - WATER MAINS
For Preambles see "Model Of Preambles for Trades 2008"
PREAMBLES
Unless otherwise stated all the following items shall be deemed to fall into Earthworks Work Group 104 for Contract Price Adjustment Provisions
CPAP ADJUSTMENT
1200 DB EARTHWORKS (Pipe Trenches)
100m0 - 1m deep1
Excavate in all materials for trenches, backfill, compact and dispose of surplus material for up to 110mm diam pipe
1200 LB BEDDING (PIPES)
10m3Selected granular material 2
Supply only bedding and compacted to 100% Mod AASHTO from commercial source
30m3Selected fill material 3
50m3 Selected fill material 4
-202-
SANS 1200 LF - Water MainsBill No. 5Civil WorksSection No. 5
Carried to to collection R
Rev 01
National Nuclear Regulator
-203-
SANS 1200 LF - Water MainsBill No. 5Civil WorksSection No. 5
Carried to to collection R
Rev 01
National Nuclear Regulator
1200 L MEDIUM PRESSURE PIPELINES
100m110 mm diam uPVC Class 125
Supply, lay and bed pipes complete
20m22mm HDPE type V class 166
4No110 mm x 110 mm diam T-piece7
Extra-over 8.2.1(a) for the supplying, laying and join uPVC specials (Incl. Cutting of pipes to required lengths.)
4No110 mm diam x 90 degree bend 8
2No110 mm diam x 45 degree bend9
2No110 mm diam x 22,5 degree bend 10
3No110mmValve complete with all fittingsand collars (box measured elsewhere)
11
Extra-over 8.2.1(a) for thesupplying, laying and join HDPE Plassonspecials (Incl. Cutting of pipes torequired lengths.)
5m3Thrust blocks (20MPa)12
2No
Fire hydrant (Pillar type)incl. all fittings and extensions and bollard)with "Bayonet" connection excluding tee offmain line (measured elsewhere) but includingall steel pipes and fittings
13
1No160mm diameter - complete.14
Connect to existing pipe
2NoMarkings or marker post.15
-204-
SANS 1200 LF - Water MainsBill No. 5Civil WorksSection No. 5
Carried to to collection R
Rev 01
National Nuclear Regulator
3NoValve box complete16
-205-
SANS 1200 LF - Water MainsBill No. 5Civil WorksSection No. 5
Carried to to collection R
SANS 1200 LF - Water Mains
Section No. 5
Bill No. 5
AmountPageNo
Civil Works
COLLECTION
Rev 01
National Nuclear Regulator
205
204
203
202Total Brought Forward from Page No.
-206-
SANS 1200 LF - Water MainsBill No. 5Civil WorksSection No. 5
Carried Forward to Summaryof Section No. 5
R
Rev 01
National Nuclear Regulator
Civil Works
SECTION SUMMARY - Civil Works
BillNo
PageNo
Amount
Section No. 5
186SANS 1200D - Site Clearance and Earthworks1
192SANS 1200 DM - Roads & Subgrade2
197SANS 1200 LE - Stormwater3
201SANS 1200 LD - Foul Sewer4
206SANS 1200 LF - Water Mains5
-207-
Civil WorksSection No. 5
Carried to Final Summary R
AmountItemNo
Quantity Rate
Rev 01
National Nuclear Regulator
SECTION NO 6
OCCUPATIONAL HEALTH AND SAFETY
Item
Notify the provincial director in writing of the commencement of construction work with and including submission of a letter of receipt and acknowledgement of the aforementioned notice by the director of his/her representative
1
BILL NO 1
Item
Allow for the necessary Workman’s Compensation Fund or FEM contributions for the duration of the project with and including renewals
2
ItemAllow for the preparation and approval of project-specific H&S Plan & File [CR 7(1)(a)]
3
MonthAllow for the implementation and maintenance of project-specific H&S Plan & File. [CR 7]
4
Month
Allow for the appointment of a Full-Time Competent Construction Health & Safety Officer to assist in the control of all health and safety related aspects on site as per [CR 8(5)]
5
Month
Provide for appointment of responsible and competent person/s to manage and supervise the works and administer and enforce health and safety on site as per [CR 8(1),(2), &(7)
6
MonthAllow for provision of telecommunication facilities for the appointed Construction Health & Safety Officer
7
MonthAllow for provision of Basic Emergency Preparedness and Response equipment & at least Level 2 First Aider/s
8
-208-
Occupational health and safetyBill No. 1Occupational health and safetySection No. 6
Carried to to collection R
Rev 01
National Nuclear Regulator
NoHard Hats(High Density polyethylene, & 6-point lining)9
Provide, supply and maintenance for each worker the following SANS approved personal protective equipment & clothing as per the site-specific risk assessments:
NoOverall/work suit (100% Cotton)10
NoSafety boots/shoes (Steel-Toe)11
NoSafety gloves12
NoEar Plugs/Muffs13
NoDust Mask(at least FF2 type)14
NoRespirators15
NoSafety goggles16
NoPersonal Fall arrest and rescue equipment with and including life lines and associated equipment
17
NoHigh visibility reflective vests and/or bibs18
mTemporary handrails ,toe boards other than for access scaffolding
19
NoTemporary warning signs and symbols20
mSANS approved safety netting (orange color with minimum of 1,2 meters high)
21
N/A
Provision for the supply and maintenance of Road Traffic Signs as in terms of the South African Road Traffic Signs Manual complete
22
ItemAllow for Pre-employment medical examinations23
ItemAllow for exit medical examinations24
-209-
Occupational health and safetyBill No. 1Occupational health and safetySection No. 6
Carried to to collection R
Rev 01
National Nuclear Regulator
MonthAllow for HIV/AIDS awareness and Implementation programmes, including STI and TB
25
HEALTH AND SAFETY EDUCATION
Month
Allow for all compulsory health and safety awareness programme (e.g. Inductions, toolbox Talks, Safety Promotions, H&S related training, etc.)
26
ItemProvide for adequate handling and storage of materials so as to minimize contamination of ground, air or water.
27
ENVIRONMENTAL
Item
Provide for the adequate and safe collection and disposal of waste material from site by an approved method.
28
ItemProvide Facilities and Eating Area for workers.29
Item
Provide for rehabilitation on completion of site areas and temporary access routes not covered by construction or landscaping specifications.
30
ItemProvide for stockpiling of topsoil for re-use31
Item
Provide for a Responsible person to prepare and update Method Statements, conduct regular inspections, maintain records, and report to the Principal Agent.
32
SUMValue Related33
COMPULSORY BREAKDOWN FOR THE ADJUSTMENT OF PRELIMINARIES
SUMFixed Value Related34
SUMTime Related35
-210-
Occupational health and safetyBill No. 1Occupational health and safetySection No. 6
Carried to to collection R
Occupational health and safety
Section No. 6
Bill No. 1
AmountPageNo
Occupational health and safety
COLLECTION
Rev 01
National Nuclear Regulator
210
209
208Total Brought Forward from Page No.
-211-
Occupational health and safetyBill No. 1Occupational health and safetySection No. 6
Carried to Final Summary R
Rev 01
National Nuclear Regulator
PageNo
FINAL SUMMARY
SectionNo
Amount
23Preliminaries and General1
116Builders Work2
144Electrical Works3
183Mechanical Works4
207Civil Works5
211Occupational health and safety6
RSUB TOTAL
RAllow Value Added Tax (15%)
RTOTAL ESTIMATED VALUE
-212-
Carried to Form of Tender R