69

Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Embed Size (px)

Citation preview

Page 1: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te
Page 2: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

 

CCusto

Yokog

02_Tab

No

1. 2.

A1. A2. A3. A4. A5. A6. A7. A8. A9. A10. A11. A12.

B1. B2. B3.

C1. C1.1 C1.2 C1.3

Project : YCustomer : Pomer Ref : Egawa Ref : Q

ble Of Conte

Title

Cover LettTable of C

ICSS CCRIntroductioCentum VScope of SSystem OSystem DeSystem CoProject ImICSS UpgCVP UpgrCVP UpgrCVP UpgrTable of C

Price SumSite ServicGeneral T

Company YokogawaQuality PlaGeneral S

YADANA SUBPT JETEC INDEMAIL DATEDQYEA1W0317

ents_R0.Do

ter Contents

R Upgrade Pon

VP Supply verview escription (onfiguration

mplementatiorade Projec

rade R5 (DCrade R5 (DCrade R5 (DC

Compliance

mmary ce Rates

Terms & Con

Profile a Engineerinan

Specification

SIDENCE PRDONESIA D 05 SEP.2011

Rev.0

ocx

TABLE

Plan

DCS) n Architectuon Plan ct ScheduleCS HW Bill CS SW Bill CS spares)

nditions Of

ng Asia Pte

ns Sheets –

ROJECT

1

Page 1

E OF CO

A. Tech

ure - Centum

e of Material)of Material)

B. Comm

Sales C. Appe

e Ltd (YEA)

– DCS

ONTENTS

hnical

m VP R5.01

) )

mercial

endices

S

Re

evision S

0 0

0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0

0 0 0 0

SubmissionDate

28-Sep-1128-Sep-11

28-Sep-1128-Sep-1128-Sep-1128-Sep-1128-Sep-1128-Sep-1128-Sep-1128-Sep-1128-Sep-1128-Sep-1128-Sep-1128-Sep-1128-Sep-11

28-Sep-1128-Sep-1128-Sep-11

28-Sep-1128-Sep-1128-Sep-1128-Sep-11

n

Page 3: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

A1_A4_ ICSS CCR Upgrade Plan.Doc Page 1

Project Name : YADANA SUBSIDENCE PROJECT

Customer Name : PT JETEC INDONESIA

Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

Proposal Section : Technical Proposal

Title : ICSS CCR Upgrade Plan

Total No. of pages of this document (including this cover page) [6]

Page 4: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A1_A4_ ICSS CCR Upgrade Plan.Doc Page 2

CONTENTS

Index

1 Introduction 2 Centum-VP

3 Scope of Supply

4 System Overview

Page 5: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A1_A4_ ICSS CCR Upgrade Plan.Doc Page 3

1 Introduction The proposed CENTUM-VP migration solution is based on Yokogawa’s latest production control system. The CENTUM-VP R5, which feature an open architecture, flexibility and compatibility with existing system.

2 Centum-VP

The CENTUM-VP Production Control System for real-time control consists of components such as HIS (Human Interface Station) and FCS (Field Control Station) interconnected by Vnet/IP or Vnet token-bus. Software running on HIS and FCS stations implements operation/monitoring and control functions respectively. Ethernet may also be used to interconnect HIS station via L2SW. HIS (Human Interface Stations) HIS servers as a human interface that meant for operation, monitoring and engineering. The software packages which are installed in an IBM PC/At-compatible computer (hereafter referred to as a general purpose PC), or in a console HIS consisting of a general-purpose PC and Open Display Style Console Assembly, implement the respective functions. A user can install and run the operation and monitoring function together with the engineering functions in the same HIS or in different HISs as necessary.

3 Scope of Supply The purpose of this technical proposal is to have a basic understanding for the ICSS upgrade and the equipment require for the implementation for this project. Following list of items to be implemented as per ICSS requirement: 1) PCS Upgrades at QP/PP/MCP/WP1/WP2 include training simulator. 2) Additional of EXAOPC Server is required for Tri-Fellows system. 3) New PCS at MSF2. 4) New temporary PCS at Jack-Up modular building. 5) PCS modification for QP, PP. 6) IFAT in Yokogawa Engineering Asia Pte Ltd (Singapore)

Page 6: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A1_A4_ ICSS CCR Upgrade Plan.Doc Page 4

The following are the scope of work as per above description.

1) In QP, convert CS application to Centum-VP R5 or later version and upgrade all FCS CPU from CP334D to CP345. Upgrade existing ICS & PICS to HMI with all conversion of all mimics. (Including training simulator) Tri-Fellows server logging version shall be upgrade from V2 to V3 and Format shall revise base on V3.

In MCP, convert CS application to Centum-VP R5 or later version and upgrade existing PICS to HMI with all conversion of all mimics. To decommission FP & implement installation of FP2. • Require TOTAL to install 2pair of 4core FO cable lay from MCP to QP via L2SW.

(Out of YEA scope) • Require TOTAL to install 2pair of 4core FO cables lay from MCP to Jack-Up via

L2SW. (Out of YEA scope) In PP, convert CS application to Centum-VP R5 or later version and upgrade all FCS CPU from CP334D to CP345. In WP1, convert CS application to Centum-VP R5 or later version and upgrade all FCS CPU from CP334D to CP345. Require TOTAL to install one set of new OBR & associated equipment. (For future Jack-Up connection) In WP2, convert CS application to Centum-VP R5 or later version and upgrade all FCS CPU from CP334D to CP345.

2) To relocate QP module and reinstallation on to QP2 platform and to specify the control & safety system to be provided for the new QP2 MSF on the offshore Yadana field as part of the Yadana Subsidence Project. (YSP) new hardware and signal required for the new equipment installed in QP2. Additional signal will be connected to the ICSS extensions installed in QP2 MSF ITR. Install one set of new OBR & associated equipment. (For future QP2 MSF) Require TOTAL to install 2pair of 4core FO cable lay from MSF2 to QP2. (Out of YEA scope)

agaconnet
Highlight
Page 7: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A1_A4_ ICSS CCR Upgrade Plan.Doc Page 5

3) Application software shall be Centum-VP R5 To cover the minimum requirement for the design manufacture and testing of Jack-Up temporary ESD and F&G matrix panels applicable to YADANA SUBSIDENCE PROJECT (YSP). One HIS-ENG & Two HIS double screen shall be install in the Jack-Up & One new FCS shall be accommodate communication to WP3 2pair of 4core FO cable shall be lay from Jack-Up to WP1. 4) To decommissioning signal required for QP & PP base on the instrument list

given. 5) IFAT shall be implement base on new equipment & system configuration with targetless FCS test in Yokogawa Singapore.

4 System Overview

The existing Yokogawa Centum-CS shall be upgrade to Centum-VP R5 or latest

version with Vnet/IP & Vnet connection via a router. The Field Control Station FCS

shall be remain and only upgrade the CPU processor card from CP334 to CP345.

System Configuration when upgrade to Centum-VP system

Page 8: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A1_A4_ ICSS CCR Upgrade Plan.Doc Page 6

During Jack-Up tie-in and QP cut-over

Final System Configuration

End of This Section

Page 9: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

A5_Sys Descpt DCS CENTUM VP_R00.Doc Page 1

Project Name : YADANA SUBSIDENCE PROJECT

Customer Name : PT JETEC INDONESIA

Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

Proposal Section : Technical Proposal

Title : SYSTEM DESCRIPTION (DCS)

Total No. of pages of this document (including this cover page) [14]

Page 10: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A5_Sys Descpt DCS CENTUM VP_R00.Doc Page 2

CONTENTS

Section Page 1  Distributed Control System (DCS) Description .......................................................... 3 

1.1  CENTUM VP Benefits ............................................................................................ 3 1.2  CENTUM VP Major Components .......................................................................... 6 1.3  CENTUM VP Expandability and Sizing .............................................................. 10 1.4  CENTUM VP Total Integration ............................................................................ 11 1.5  Plant Resource Management System (PRM) .................................................... 13 

Page 11: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A5_Sys Descpt DCS CENTUM VP_R00.Doc Page 3

1 Distributed Control System (DCS) Description

Yokogawa's Distributed Control System - CENTUM - was released in 1975 as the first real Distributed Control System (DCS) in the world. Since then, it has been continuously enhanced and upgraded, incorporating state-of-the-art technology maintaining continuities and backward compatibility of the system. Based on our 30-year DCS experience, Yokogawa is proud to develop and introduce the new CENTUM VP system.

CENTUM VP is the next evolutionary step of Yokogawa control system with better information visibility, performance foresight, and operational agility.

CENTUM VP as DCS is a flagship platform to realize “VigilantPlant ®” concept. With this brief introduction of CS 3000 we hope to give you a good understanding of the basic architecture without going into too detailed information. The detailed technical information is provided in the enclosed technical literature of our proposal (Appendices section). The CENTUM VP is a truly open system. It provides, besides straightforward process control, excellent capabilities for:

• Integration over the control network (V-net/IP) for ESD & F&G (ProSafe-RS)

• Integration of sub-systems such as PLC’s, analysers, etc.

• Integrated Instrument Management with Plant Resource Manager (PRM)

• Plant Information Management System with Exaquantum/PIMS

Altogether comprising in a total integrated production and facilities control system, and operated via a single window.

Due to the modularity and system architecture these functions can all be implemented in a segregated way. By using these segregation features the process control system can be implemented in such a way that the plant segregation is fully reflected in the production control system architecture.

The VP in CENTUM VP stands for VigilantPlant. To establish a clear focus on our VigilantPlant strategy, a VigilantPlant Operational Excellence Model has been created. It is a visual representation of the focus of the VigilantPlant solution, which aim at bringing excellence in production, asset, and safety sustained over the life cycle of our customers’ plant.

1.1 CENTUM VP Benefits

1.1.1 System Architecture

The CENTUM VP System Architecture is straightforward. Highly flexible networks can be designed using of commercially available network equipment like switches (Layer2 & Layer3). Although open and control communication data can be transferred on the physically same Vnet/IP cables, these communications are logically segregated so that they do not have an effect on each other. It will enable integration of non-CENTUM components to the network.

The System Architecture allows up to 1,000,000 Tags and 256 Stations. Different Domains can be defined to segregate functional disciplines within the user's organisation.

Page 12: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A5_Sys Descpt DCS CENTUM VP_R00.Doc Page 4

1.1.2 Operation

The HIS (Human Interface Station) is a powerful and easy-to-use Operator Station with Operator Functions, Graphic Functions, Database Functions, and if required Engineering Functions. This is the world’s first Windows® Vista ready DCS HMI software.

It provides User-defined Faceplates for an optimal Man-Machine Interface. The Windowing Operation allows the operator to place frequently used displays (e.g. in a personal group) on the screen. Different Sources of Information from the DCS (Graphic Panel, Trend Panel, etc.) as well as Information from Supervisory Computers can be presented to the Operator on one Screen in a uniform manner. The Report Package provides production reports by using spreadsheet functions. Data Compression Techniques (e.g. Min., Max., Average etc.) are available.

HIS

Ethernet

Vnet-IP

CABINETS

HIS

Ethernet

Vnet-IP

CABINETS

Figure 1 - Computer application integration in Centum VP operator interface (HIS)

1.1.3 Control

The Field Control Station (FCS) is a state of the art generation model that integrates process and batch control, and computer functions. The Integrated Control Functions include:

• Regulatory and Advanced Control Functions (Control Loops)

• Sequence Control Functions (Sequence Table, Logic Charts, Sequential Function Chart)

• Subsystem Integration Functions

• Field Instrument Management Functions

These control functions are executed at high speed by the high performance RISC (Reduced Instruction Set CPU) processor. These functions can be combined to optimise continuous processes, batch processes and even discrete processes.

agaconnet
Highlight
Page 13: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A5_Sys Descpt DCS CENTUM VP_R00.Doc Page 5

1.1.4 Redundancy

The Large Field Control Station is available in a "pair and spare" dual-redundant configuration. For the first time in a DCS the Field Control Stations central processor unit uses "pair and spare". Problems, which were not detected with former “duplex” redundancy, are now easily detected.

Figure 2 – FCS Dual-Redundant Configuration

1.1.5 Field Network I/O (FIO)

The FIO range consists of Direct nodes connected by ESB (Extended Serial Backboard) bus and Remote nodes connected by ER (Enhanced Remote) bus. Both the buses may be dual redundant. ESB bus is used within the cabinets and, by using Optical Fibre Cable, the ER bus can be used for longer distances. The physical media of ER bus is compatible with 10Base2 coaxial Ethernet cable.

1.1.6 Engineering

CENTUM VP offers engineering solutions, which match the user's introduction schedule and engineering procedures. Simplification of engineering work Since CENTUM VP functions are configured using computer-aided engineering (CAE), engineering work can be simplified.

Function configuration techniques conform to Sequential Function Chart (SFC) standards. Reduction of engineering work time CENTUM VP is capable of performing concurrent engineering. Thereby, two or more engineers can share the engineering work. Also, the work time can be reduced by re-using previously developed application software that has been registered as parts of models. Moreover, debugging can be improved by using off-line testing and simulation in the test stage without having target hardware such as Field Control Stations available.

Improvement of engineering work environment In CENTUM VP, the user can perform engineering work not only from the Engineering Workstations, but also from personal computers in a network, enabling concurrent engineering. This network can even be extended to various locations all over the world by latest network technology. Integration of user's engineering tools

Page 14: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A5_Sys Descpt DCS CENTUM VP_R00.Doc Page 6

CENTUM VP is capable of connecting different engineering tools from several users to minimise the human error for engineering as well as to shorten the engineering work.

Figure 3 - Typical Centum VP Graphic Builder window

1.1.7 Maintenance

The Maintenance Functions of CENTUM VP include monitoring, extensive self- diagnostics as well as on-line Maintenance Functions. The Maintenance Functions automatically monitor the status of the system continuously. The status of each card in the stations is monitored and reported to the Operator in case of failure.

The Remote Maintenance Functions (Optional Service) link the user's Engineering Workstation to the Maintenance Computer at a Yokogawa Regional Service. The Maintenance Computer can diagnose the user's system and skilled Maintenance Engineers can carry out a comprehensive diagnosis of the system status more quickly and at lower cost compared to a site visit. Furthermore, by using Remote Maintenance Service (RMS), the Maintenance Engineer can prepare himself if a site visit would be required.

1.2 CENTUM VP Major Components

A brief description of CENTUM VP major components is stated within this section.

For more detailed technical information on the CENTUM VP components, please refer to the technical literature available upon request.

Page 15: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A5_Sys Descpt DCS CENTUM VP_R00.Doc Page 7

1.2.1 Operator Interface, Human Interface Station – HIS

The Human Interface Station is the operator interface of the system. It provides dedicated screens for operation, monitoring, reporting, trending etc. It is directly connected to V-net/IP, ensuring real-time communication between the operator interface and plant behaviour, e.g. faceplates and alarms etc.

The HIS is connected to Ethernet which interconnects all HIS allowing for client-server features on the operator interface level such as sharing of trend files, event data bases etc.

H um an In terface S tationM ain te nance

M anagem en tIn fo rm ation

P roce ssIn fo rm ation

E nginee ring

100 .000 tagnam es 2 ,500 D isp lay Pane ls Enhanced trend ing In te lligent a la rm functions R e liab le security functions W indow ing opera tion e tc ....

E asy in tegra tion w ith h igher leve l system s Advanced m anagem ent packages H is to rica l da tabase packages e tc ...

Extensive se lf d iagnostics M a in tenance & report functions O n-line m a in tenance R em ote m a in tenance e tc ....

O ff line eng ineering O n line eng ineering P ow erfu l eng ineering & testing too lsO ne g loba l da tabasee tc ....

Figure 4 - Human Interface Station features

One HIS can have up to 4,000 graphics. Each graphic can have 800 process data on it, and 1 second data refresh is available. One HIS can have up to 4 monitors, and up to 10 graphics can be displayed at the same time with regardless the number of monitors. It can also support wide monitors.

16:10 Screen 4:3 ScreenTwo monitors(16:10 & 4:3) Four Monitors

(16:10 & 4:3)

16:10 Screen 4:3 ScreenTwo monitors(16:10 & 4:3) Four Monitors

(16:10 & 4:3)

Depending on customer requirements several platforms can be used for HIS functions viz. desktop or console type. The Yokogawa Console Type with dual/quad stacked LCD or CRT is state-of-the-art, ergonomically designed for ease of use and faster response to the operator. A general purpose PC is installed inside the console to achieve maximum synergy with installed base, minimize spare parts and different maintenance contracts. Standard IBM compatible PC workstation can also be used as an operator station.

1.2.2 Engineering Work Station – ENG

An ENG is the engineering environment of the system and contains the master database of the application. This system is based on a standard IBM compatible PC. The engineering

Page 16: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A5_Sys Descpt DCS CENTUM VP_R00.Doc Page 8

environment allows engineering in a fully graphical way. By using “pick and click” and “drag and drop” standard Windows features, the entire configuration can be built in a graphical manner, including logics, sequences, control loops, graphics etc.

With the concurrent engineering possibility, multiple engineers can work on a configuration simultaneously, thereby allowing for testing, configuration etc. at the same time.

1.2.3 Field Control Station - FCS

The Field Control Station is the heart of the CENTUM VP Control System. It consists of dual power supplies, dual communication cards and single or redundant RISC processor(s) depending on the required availability of the system.

Single CPU type or Duplexed CPU type can be selected. In case of duplex type, when the abnormality of the control module is detected, switching-over to the stand-by one happened within mille-seconds not to affect the plant operation. Each CPU module has 2 CPU chips whose the calculation results are always checked. If the result of the control module unmatched, the control right is switched to stand-by one even no hardware abnormality is detected. This is called pair & spare technology to achieve high plant operation availability.

One FCS has 8 slots for I/O module, and you can install any types of I/O modules there. In addition, it is possible to connect up to 14 expansion I/O nodes on one FCS. One I/O node has 8 slots for I/O modules.

The FCS performs all process control related actions. It contains the actual PID and other controllers, switches, logics, sequences and advanced control algorithms. It communicates via the ESB/ER and RIO-bus with the Node Units and via V-net/IP (the real time process control Local Area Network (LAN)) with the operator interface and the engineering environment.

Figure 5 - Field Control Station features

1.2.4 I/O Hardware – Field Network I/O (FIO)

1.2.4.1 I/O Modules (FIO)

The Input modules convert process signals to the digital data format used in the FCS. Output modules convert the digital data format used in the FCS to analogue or contact signals. I/O

Page 17: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A5_Sys Descpt DCS CENTUM VP_R00.Doc Page 9

modules are available for all types of signals available in process industry. FIO modules offer lots of flexibility in selection of connection with field signals.

All cards are hot swappable

I/O cards available with cable or screw connection

All cards available in a redundant configuration

Nodes and cards suitable for zone 2 environment

Environment temperature range -20 degrees to 70 degrees

I/O cards with build in barrier II (1) 3G [EEx ia] II C T4

Full range: Volt/ 4-20 mA /Pulse/ TC / RTD / DI / DO

Galvanic isolation per card and per channel available

Figure 6 - Field Network I/O Configuration

1.2.4.2 Node Unit – NU

The Node Unit (NU) are signal processing units which convert and transmit analogue or digital process I/O signals received from the field devices to the FCU for FIO. The node units (NU) for FIO have ESB bus node units (local node units) installed at the FCS station and ER bus node units (remote node units) installed in remote cabinets.

1.2.4.3 Enhanced Remote Bus – ER

This communication bus connects the remote Node Units to the Field Control Station via ER bus interface modules installed in direct nodes. The ER bus can be further extended via fibre optic cable utilising standard off-the-shelf fibre optic converters, for remote node installation.

Page 18: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A5_Sys Descpt DCS CENTUM VP_R00.Doc Page 10

1.2.5 Real Time Control Bus and other Networks

1.2.5.1 V-net/IP, Real Time Process Control LAN

The network performance is secure when huge amount of alarms break out in a short time and also able to call up or refresh any display within 1 second.

Highly flexible networks can be designed using of commercially available network equipment like switches (Layer2 & Layer3). Although open and control communication data can be transferred on the physically same Vnet/IP cables, these communications are logically segregated so that they do not have an effect on each other.

It will enable integration of an open platform that facilitates an integral part of PCS as non-CENTUM components.

1.2.5.2 Ethernet TCP/IP Operator Interface File Server LAN and interface to upper level systems

Ethernet is the Operator Interface file server LAN that enables the multiple operator stations to communicate with each other. Hence, the information stored on the hard disk of one operator station is available to all other authorised operators as well. Ethernet also enables communication to plant or business software environment without the risk of interfering with control functions using OPC and many other de-facto network communication standards. Ethernet is used to connect HIS, ENG and SER Server computer. Ethernet hubs are used to provide smooth communication.

1.2.5.3 Fieldbus Networks

Fieldbus is a bi-directional digital communication protocol for field devices. Fieldbus is a big innovation in process control systems technology and is expected to replace the standard 4 to 20 mA analogue communication protocol that most current field devices employ. CENTUM VP supports Foundation Fieldbus H1 networks. The support for dual FF-H1 modules is first in the industry.

1.3 CENTUM VP Expandability and Sizing

CENTUM VP provides a hierarchical system configuration to ensure flexible system expansions. The basic concept of the hierarchical system configuration is illustrated below. For every system domain a total of 64 Field Control Stations and Human Interface Stations can be connected.

In case more stations are needed to fulfil the end user’s requirements, more domains can be specified, up to maximum of 16 domains. The total system however remains fully transparent throughout all these domains.

A Human Interface Stations located in domain 1 can provide the consolidated operation of all processes which are controlled by each control system (domain 2, 3.....n) since all HIS have a large database to accommodate the process data (1,000,000 tags).

The process data/events monitored/controlled data by each control system (domain 2, 3,.....n) are transmitted to the HIS located in domain 1 via a Layer 3 Switch (L3SW) so that an HIS can execute total plant operation located in domain 1 as consolidated Operator Stations. For future

Page 19: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A5_Sys Descpt DCS CENTUM VP_R00.Doc Page 11

expansions within the limits of one particular domain, it is possible to add Field Control Stations in that domain.

Figure 7 - CENTUM VP System Scale details

1.4 CENTUM VP Total Integration

CENTUM VP can easily realise the total integrated control and management solutions not only with subsystems such as high level computers, programmable logic controllers (PLC), machine monitoring systems etc., but also with multi-vendor software such as advanced control packages to provide single window operation.

1.4.1 Subsystem Integration

As an interface to subsystems, such as Programmable Logic Controllers (PLC), Vibration Monitoring System etc. a Communication Card located in the Field Control Station (FCS) is provided. This card has RS232C or RS485/RS422 Interface port or Ethernet, and the cable from the subsystem is plugged into the port directly. The Communication Cards contain the subsystem driver function.

An OPC client gateway, GSGW, enables multiple OPC servers from the subsystems to be connected to the Control System Data highway (V-net/IP) via OPC. Up to 4 subsystems’s OPC servers can be connected to one GSGW OPC client gateway.

Max. No. of Domains: 16

Max. System Configuration

Max. Domain Configuration

Max. No. of Tags : 100,000 per HIS Max. No. of Stations : 64

Min. Configuration System Sizing

Total number of stations (FCS + HIS) per domain : 64 stations Maximum number of domains : 16 domains Total tag capacity per system (per HIS) : 1,000,000 tags

Page 20: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A5_Sys Descpt DCS CENTUM VP_R00.Doc Page 12

The transmitted data from the subsystem is stored in subsystem data image file and stored data is transmitted to the standard CENTUM instruments and/or sequence control elements. After the transmission, the data is transferred into the database (CENTUM standard instruments/sequence control elements) of the Field Control Station (FCS). These are processed in exactly the same way as other CENTUM VP data. The HIS can represent the subsystems data in the similar fashion as other CENTUM data (faceplates, graphics, etc.), ensuring full integration of the subsystem into CENTUM VP. In case redundant communication is required, two Communication Cards are used to update the subsystem data simultaneously (depending on the card type).

Figure 8 - Sub-systems integration

1.4.2 Intelligent Integration

The CENTUM VP Human Interface Station (HIS) is designed to support very large systems (Max 1,000,000 Tags) to realise the total operation integration (consolidated Operator Station) for the whole plant with unit-based operation. The HIS is also designed to provide operation flexibility (CRT access level priority, operation groups etc.).

Especially, operation grouping is the effective function to segregate the operation functions among the HIS - on a process unit basis - as if they are dedicated Operator Stations for a certain process unit although this HIS has the total database for the overall process.

1.4.3 Geographically Distributed Systems Integration

Nowadays, more and more customers not only want to integrate systems from different sources and manufacturers, but also want to integrate geographically distributed systems.

1.4.3.1 Optical Fibre

CENTUM VP two system networks: V-net/IP and Ethernet. These networks can be extended up to 20 kilometres by using fibre optic cables.

Page 21: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A5_Sys Descpt DCS CENTUM VP_R00.Doc Page 13

1.5 Plant Resource Management System (PRM)

Yokogawa Plant Resource Manager (PRM) is an Asset Management System.

Figure 9 – Concept of Plant Resource Manager

1.5.1 Plant Resource Manager (PRM)

Today, networked production sites are becoming the norm. These networks greatly improve maintenance work. Plant Resource Manager (PRM), the software package from Yokogawa, offers a new style of maintenance tailored using the benefits of Fieldbus technology. PRM uses both Fieldbus and HART application plant to enable remote and automated maintenance functions. PRM acquires device information including the device ID, various parameters, and self-diagnostic information and other device related details, in addition to measured data. This wealth of information is used for administration and supervision of assets such as field devices, and also for remote automated inspections. PRM transforms the style of maintenance from manual work mainly done on site, into IT-based automated device management. PRM can support its users to embed the competency gap between the latest technologies and current maintenance practices.

Highlights:

• PRM evolves maintenance from preventive maintenance to predictive maintenance

• Condition based maintenance using field data via Fieldbus

• Diagnostic function in device

• PRM changes maintenance work efficient and automatic

• Tool based maintenance work

• YVP management software – ValveNav

• Lingkage with CMMS (MAXIMO)

• PRM shifts maintenance work from site to operation room

Page 22: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A5_Sys Descpt DCS CENTUM VP_R00.Doc Page 14

• Remote maintenance using PLUG-IN application

• Field data can be accessed from PC through field network

• PRM Prevents unscheduled plant shutdown

• Diagnostic function

• Device Viewer display for the conditions of devices

End of This Section

Page 23: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

A6.TOTAL EP SYS-CONF CVP R5 01 Rev4 Page 1

Project Name : YADANA SUBSIDENCE PROJECT

Customer Name : PT JETEC INDONESIA

Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

Proposal Section : Technical Proposal

Title : TOTAL EP SYS-CONF CVP R5 01 Rev.4

Total No. of pages of this document (including this cover page) [8]

Page 24: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A6.TOTAL EP SYS-CONF CVP R5 01 Rev4 Page 2

CONTENTS

Section Page TOTAL E&P SYS-CONF CVP R5 01 Rev.4……………………………………………………………………….………2

TOTAL E&P SYSTEM CONFIGURATION ARCHITECTURE - CENTUM VP R5.01 (PHASE1)…………...……….3

TOTAL E&P SYSTEM CONFIGURATION ARCHITECTURE - CENTUM VP R5.01 (PHASE2)………….……...…4

TOTAL E&P SYSTEM CONFIGURATION ARCHITECTURE - CENTUM VP R5.01 (PHASE3)…………..……….5

TOTAL E&P SYSTEM CONFIGURATION ARCHITECTURE - CENTUM VP R5.01 (PHASE4)…………..………..6

TOTAL E&P SYSTEM CONFIGURATION ARCHITECTURE - CENTUM VP R5.01 (PHASE5)…………..………..7 TOTAL E&P SYSTEM CONFIGURATION ARCHITECTURE - CENTUM VP R5.01 (PHASE6-FINAL).................8

Yokogawa Upgrade - CENTUM-VP .01 .........................................................................................................…...8

Page 25: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

TOTAL E&P SYSTEM CONFIGURATION ARCHITECTURE - CENTUM VP R5.01 (PHASE1)

ENGS

Vnet

AVR10D

L2SW

PP

Vnet

EXAOPC

TriFellow Server TriFellow Client

HUB

EthernetFirewall

QP

WP2

Vnet

OBR OBR

OBR

Laser Printer

HIS0264 HIS0263 HIS0262 HIS0261 HIS0260

HIS0259

OPC0254

Optic cables (Vnet/IP)

Optic cables (Vnet)

Optic cables (Vnet)

Optic cables (Vnet)

Optic cables (Vnet)

QP-PCS QP-G-FG QP-G-ESD

PP-G-FG PP-G-ESD PP-PCS

WP2-PSS WP2-PCS

1.9 1.10

1.4 1.5 1.6

1.1 1.2 1.3

#2

#2

MCP

Vnet OBR

Optic cables (Vnet)

MCP-PSS MCP-PCS

1.11 1.12

(BRIDGE)

WP1

Vnet

OBR

Optic cables (Vnet)

WP1-PSS WP1-PCS

1.7 1.8

(BRIDGE)

(existing BRIDGE)

HIS0258

L2SW

HIS HIS HIS HIS

OS5 OS6OSW2 OSW3

ESD PLC

F&G PLC

F&G/ESD PLC

F&G PLC

ESD PLC ESD

FGS

F&G/ESD PLC

Page 26: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

TOTAL E&P SYSTEM CONFIGURATION ARCHITECTURE - CENTUM VP R5.01 (PHASE2)

New JB for FO &

hardwired existing

ENGS

Vnet

AVR10D

L2SW

PP

Vnet

EXAOPC

TriFellow Server TriFellow Client

HUB

EthernetFirewall

MSF2

QP

WP2

Vnet

OBR OBR

OBR

OBR

Laser Printer

HIS0264 HIS0263 HIS0262 HIS0261 HIS0260

HIS0259

OPC0254

Optic cables (Vnet)

Optic cables (Vnet/IP)

Optic cables (Vnet)

Optic cables (Vnet)

Optic cables (Vnet)

Optic cables (Vnet/IP)

Optic cables (Vnet)

QP-PCS QP-G-FG QP-G-ESD

PP-G-FG PP-G-ESD PP-PCS

WP2-PSS WP2-PCS

1.9 1.10

1.4 1.5 1.6

1.1 1.2 1.3

#2

#2

(BRIDGE)

MCP

Vnet OBR

Optic cables (Vnet)

MCP-PSS MCP-PCS

1.11 1.12

(BRIDGE)

WP1

Vnet

OBR

Optic cables (Vnet)

WP1-PSS WP1-PCS

1.7 1.8#2

#2

L2SW

JACKUP

OBR

Optic cables (Vnet) #2 #2

(BRIDGE)

(existing BRIDGE)

HIS0258

L2SW

TEMPORARY USED EQUIPMENT

JB

JB

Temporary gangway for

all cables

HIS HIS HIS HIS

OS5 OS6OSW2 OSW3

ESD PLC

F&G PLC

F&G/ESD PLC

F&G PLC

ESD PLC ESD

FGS

F&G/ESD PLC

By pass hardwired for existing

cables

FOR FUTURE JACKUP

FOR FUTURE MSF2

Page 27: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

TOTAL E&P SYSTEM CONFIGURATION ARCHITECTURE - CENTUM VP R5.01 (PHASE3)

New JB for FO &

hardwired existing

ENGS

Vnet

AVR10D

L2SW

PP

Vnet

Vnet

EXAOPC

TriFellow Server TriFellow Client

HUB

EthernetFirewall

MSF2

QP

WP2

Vnet

OBR OBR

OBR

OBR

Laser Printer

HIS0264 HIS0263 HIS0262 HIS0261 HIS0260

HIS0259

OPC0254

Optic cables (Vnet)

Optic cables (Vnet/IP)

Optic cables (Vnet)

Optic cables (Vnet)

Optic cables (Vnet)

Optic cables (Vnet/IP)

Optic cables (Vnet)

QP-PCS QP-G-FG QP-G-ESD

PP-G-FG PP-G-ESD PP-PCS

WP2-PSS WP2-PCS

1.9 1.10

1.4 1.5 1.6

1.1 1.2 1.3

1.13

FCS POWER ONQP-PCS (TEMPORARY)FOR WP3 ONLY

#2

#2

(BRIDGE)

MCP

Vnet OBR

Optic cables (Vnet)

MCP-PSS MCP-PCS

1.11 1.12

(BRIDGE)

WP1

Vnet

OBR

Optic cables (Vnet)

WP1-PSS WP1-PCS

1.7 1.8#2

#2

ENGS

Vnet

AVR10D

L2SW

JACKUP

OBR

HIS0257 HIS0256 HIS0255

Optic cables (Vnet)

Laser Printer

#2 #2

(BRIDGE)

(existing BRIDGE)

HIS0258

L2SW

TEMPORARY USED EQUIPMENT

JB

JB

Temporary gangway for

all cables

HIS HIS HIS HIS

OS5 OS6OSW2 OSW3

ESD PLC

F&G PLC

F&G/ESD PLC

F&G PLC

ESD PLC ESD

FGS

F&G/ESD PLC

By pass hardwired for existing

cables

Page 28: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

TOTAL E&P SYSTEM CONFIGURATION ARCHITECTURE - CENTUM VP R5.01 (PHASE4)

For YARD FAT, commission phase MSF2 Tie-in.

New JB for FO &

hardwired existing

ENGS

Vnet

AVR10D

L2SW

PP

Vnet

Vnet

EXAOPC

TriFellow Server TriFellow Client

HUB

EthernetFirewall

MSF2

QP

WP2

Vnet

OBR OBR

OBR

OBR

Laser Printer

HIS0264 HIS0263 HIS0262 HIS0261 HIS0260

HIS0259

OPC0254

Optic cables (Vnet)

Optic cables (Vnet/IP)

Optic cables (Vnet)

Optic cables (Vnet)

Optic cables (Vnet)

Optic cables (Vnet/IP)

Optic cables (Vnet)

QP-PCS QP-G-FG QP-G-ESD

PP-G-FG PP-G-ESD PP-PCS

WP2-PSS WP2-PCS

1.9 1.10

1.4 1.5 1.6

1.1 1.2 1.3

1.13

FCS POWER ONQP-PCS (TEMPORARY)FOR WP3 ONLY

#2

#2

(BRIDGE)

MCP

Vnet OBR

Optic cables (Vnet)

MCP-PSS MCP-PCS

1.11 1.12

(BRIDGE)

WP1

Vnet

OBR

Optic cables (Vnet)

WP1-PSS WP1-PCS

1.7 1.8#2

#2

ENGS

Vnet

AVR10D

L2SW

JACKUP

OBR

HIS0257 HIS0256 HIS0255

Optic cables (Vnet)

Laser Printer

#2 #2

EXAOPC

Server Client

(BRIDGE)

(existing BRIDGE)

HIS0258

L2SW

AVR10D

L2SW

Laser Printers

TEMPORARY USED

TEMPORARY USED EQUIPMENT

HIS ENGS-HIS

JB

JB

Temporary gangway for

all cables

HIS HIS HIS HIS

OS5 OS6OSW2 OSW3

ESD PLC

F&G PLC

F&G/ESD PLC

F&G PLC

ESD PLC ESD

FGS

F&G/ESD PLC

By pass hardwired for existing

cables

Page 29: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

TOTAL E&P SYSTEM CONFIGURATION ARCHITECTURE - CENTUM VP R5.01 (PHASE5)

New JB for FO &

hardwired existing

ENGS

Vnet

AVR10D

L2SW

PP

Vnet

Vnet

EXAOPC

TriFellow Server TriFellow Client

HUB

EthernetFirewall

MSF2

QP

WP2

Vnet

OBR OBR

OBR

OBR

Laser Printer

HIS0264 HIS0263 HIS0262 HIS0261 HIS0260

HIS0259

OPC0254

Optic cables (Vnet)

Optic cables (Vnet/IP)

Optic cables (Vnet)

Optic cables (Vnet)

Optic cables (Vnet)

Optic cables (Vnet/IP)

Optic cables (Vnet)

QP-PCS QP-G-FG QP-G-ESD

PP-G-FG PP-G-ESD PP-PCS

WP2-PSS WP2-PCS

1.9 1.10

1.4 1.5 1.6

1.1 1.2 1.3

1.13

FCS POWER ONQP-PCS (TEMPORARY)FOR WP3 ONLY

#2

#2

(BRIDGE)

MCP

Vnet OBR

Optic cables (Vnet)

MCP-PSS MCP-PCS

1.11 1.12

(BRIDGE)

WP1

Vnet

OBR

Optic cables (Vnet)

WP1-PSS WP1-PCS

1.7 1.8#2

#2

ENGS

Vnet

AVR10D

L2SW

JACKUP

OBR

HIS0257 HIS0256 HIS0255

Optic cables (Vnet)

Laser Printer

#2 #2

Server Client

(BRIDGE)

(existing BRIDGE)

HIS0258

L2SW

TEMPORARY USED EQUIPMENT

JB

JB

Temporary gangway for

all cables

HIS HIS HIS HIS

OS5 OS6OSW2 OSW3

ESD PLC

F&G PLC

F&G/ESD PLC

F&G PLC

ESD PLC ESD

FGS

F&G/ESD PLC

By pass hardwired for existing

cables

Page 30: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

TOTAL E&P SYSTEM CONFIGURATION ARCHITECTURE - CENTUM VP R5.01 (PHASE6-FINAL)

New JB for FO &

hardwired existing

ENGS

Vnet

AVR10D

L2SW

PP

Vnet

Vnet

EXAOPC

TriFellow Server TriFellow Client

HUB

EthernetFirewall

MSF2

QP

WP2

Vnet

OBR OBR

OBR

OBR

Laser Printer

HIS0264 HIS0263 HIS0262 HIS0261 HIS0260

HIS0259

OPC0254

Optic cables (Vnet)

Optic cables (Vnet/IP)

Optic cables (Vnet)

Optic cables (Vnet)

Optic cables (Vnet)

Optic cables (Vnet)

QP-PCS QP-G-FG QP-G-ESD

PP-G-FG PP-G-ESD PP-PCS

WP2-PSS WP2-PCS

1.9 1.10

1.4 1.5 1.6

1.1 1.2 1.3

1.13

#2

#2

MCP

Vnet OBR

Optic cables (Vnet)

MCP-PSS MCP-PCS

1.11 1.12

(BRIDGE)

WP1

Vnet

OBR

Optic cables (Vnet)

WP1-PSS WP1-PCS

1.7 1.8#2

#2

(BRIDGE)

(existing BRIDGE)

HIS0258

L2SW

JB

JB

HIS HIS HIS HIS

OS5 OS6OSW2 OSW3

ESD PLC

F&G PLC

F&G/ESD PLC

F&G PLC

ESD PLC ESD

FGS

F&G/ESD PLC

By pass hardwired for existing

cables

Page 31: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Yokogawa Upgrade - CENTUM-VP R5.01 Brigde Brigde Brigde Sub marine FO

QP MCPDomain2 PP Domain2 WP1 WP2

MCP FO cable - 2pair of 8core lay to QP (Vnet/IP) MCP FO cable - 2pair of 8core lay to JACKUP (Vnet/IP)

(Replace PICS)

Note 1:

FO cable 2pair of 8core (Vnet/IP)

FO cable 2pair of 8core (Vnet/IP)

FO cable 2pair of 8core (Vnet/IP) AVR10D*S3

10Base5 to 10Base2 Converter Vnet Vnet Vnet

Vnet Vnet

Bus1 Bus2 Bus1 Bus 2 Bus1 Bus2 Bus1 Bus2 New OBR To Bus1 Bus2 Bus1 Bus2 Bus1 Bus2 JACKUP

2 Pairs F.O 8 Cores ( PCS)8Cores FO 6 Cores ( PSS)

FO 8 Cores ( PCS )FO 6 Cores ( PSS)

FO cable 8 cores (SSS)QP2-MSF2 FO cable

2pair of 8core (Vnet) SSS peer to peer Bus1 Bus2 JACKUP

Domain2 Jackup FO cable (For Vnet) 2pair of 8core lay to WP1Vnet

FO 8 cores MultimodePSS

Note: Peer to peerEXAOPC & Tri-Fellow Server need 1 NIC cardTri-Fellow Client need 2 NIC card All HIS in Domain2All FCS(RIO Type) in Domain1 AVR10D*S3

MCP FO Cable 10Base5 to 10Base2 ConverterMCP FO Multimode cable - 2pair of 8core lay to QP (Vnet/IP) 3000 metersMCP FO multimode cable - 2pair of 8core lay to JACKUP (Vnet/IP) 4000 meters Bus1 Bus2Jackup FO Cable FO cable 2 by 2 pair of 8core (Vnet)Jackup FO multimode cable (For Vnet) 2pair of 8core lay to WP1 (Vnet)800 Meters Vnet To WP1 (Vnet)MSF2 FO multimode cable (For Vnet) 2pair of 8core lay to QP

Note1: Fibre Optic cables between MCP and QP shall be removed when jack up shall be controled the SITE and reconnected to QP before transfer from jack up to QP2. Fibre optic coilled in PP side.

For others length cables TENDERER shall refer to feed architecture doc as MM-YAD-20-DORI-476028

Temporay equipment in JACKUP shall be issue to Pipeline center for ONSHSORE UPGRADE.

Invensys system

10Base5 to 10 / Base2 Converter

Temporay equiment in MSF2 shall be issue to Metering station for ON SHORE UPGRADE.

HIS0264ENGS

HIS0263Console

HIS0262Console

HIS0261Console

HIS0259Desktop

L2SW BUS1

OBR OBR OBR OBR

HIS0258Desktop

QP-G-ESD 1.3

QP-G-FG1.2

QP-PCS1.1

L2SW BUS1

HIS0257Desktop

HIS0256Desktop

OBR OBR

L2SW BUS2

MCP-PSS 1.11

MCP-PCS 1.12

Existing OBR from QP via PP

OBR OBR OBR OBR

PP-PCS 1.6

PP-G-FG 1.4

PP-G-ESD 1.5

WP1-PCS 1.8WP1-PSS 1.7

OBR OBR

WP2-PCS 1.10

WP2-PSS 1.9

EXAOPC2.54

HUB

Tri-FellowServer

Tri-FellowClient

FireWall

OBR OBR

QP-MSF2 1.13

OBR OBR

HIS0255ENGS

L2SW BUS2

HIS0260Console

QP-PCS 1.1

QP-PCS (TEMPORARY)FOR WP3 ONLY

L2SW BUS1L2SW BUS2

New JB for FO cables

Existing OBR from PP via MCP

L2SW BUS1 L2SW BUS2

AVR10D*S3

HIS0254DESK TOP

HIS0255DESK TOP

OBR OBR

Page 32: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

A7_ Project Implemenation Plan.Doc Page 1

Project Name : YADANA SUBSIDENCE PROJECT

Customer Name : PT JETEC INDONESIA

Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

Proposal Section : Technical Proposal

Title : PROJECT IMPLEMENTATION PLAN

Total No. of pages of this document (including this cover page) [13]

Page 33: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A7_ Project Implemenation Plan.Doc Page 2

TABLE OF CONTENTS

1 PROJECT PROCESS ...............................................................................................................4 1.1 Project Execution Plan........................................................................................................... 4

1.2 Summary Of Project Management & Engineering Functions ................................................ 4

1.2.1 Project Team Organization ................................................................................. 5

1.2.1.1 Typical Project Organization Chart .................................................................. 6 1.2.1.2 Project Manager .............................................................................................. 6 1.2.1.3 QA Manager .................................................................................................... 6 1.2.1.4 Lead (System Integration / System) Engineers............................................... 7 1.2.1.5 Project Director ................................................................................................ 7 1.2.1.6 Project Engineers / System Engineers ............................................................ 7 1.2.1.7 Procurement Manager ..................................................................................... 7 1.2.1.8 Local Project / Site Manager ........................................................................... 8 1.2.1.9 Start-up Lead Engineer................................................................................ 8

1.3 Engineering Execution Plan .................................................................................................. 8

1.3.1.1 Introduction...................................................................................................... 8 1.3.1.2 Standard Procedures...................................................................................... 8 1.3.1.3 Job Handling Manual ....................................................................................... 8 1.3.1.4 Interface with Sub-Vendors and Sub-Contractors ........................................... 9 1.3.1.5 Responsibility of Sub-Vendors and Sub Contractors...................................... 9

1.3.2 Yokogawa Project Management ......................................................................... 10

1.3.2.1 Goal Directed Project Management.............................................................. 10

1.3.3 Tests, Installation Supervision And Start-Up .................................................... 11

1.3.3.1 Factory Acceptance Test ............................................................................... 11 Internal Tests................................................................................................................. 11

Page 34: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A7_ Project Implemenation Plan.Doc Page 3

Factory Acceptance Test ............................................................................................. 11 1.3.3.2 Site Acceptance Test .................................................................................... 11 1.3.3.3 Commissioning and Start-up ......................................................................... 12

1.3.4 Progress Reports and Progress Meetings........................................................ 12

1.3.4.1 Progress Reporting ....................................................................................... 12 1.3.4.2 Project Progress report ................................................................................. 12 1.3.4.3 Internal Management Report ......................................................................... 12 1.3.4.4 Progress Meetings ........................................................................................ 12

1.3.5 Quality Assurance ............................................................................................. 13

1.3.5.1 Project Handling Procedure.......................................................................... 13 1.3.5.2 Global Organization of Yokogawa................................................................. 13

1.3.6 Drawings & Documentation .............................................................................. 13

1.3.7 Change Order Handling .................................................................................... 13

Page 35: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A7_ Project Implemenation Plan.Doc Page 4

PROJECT EXECUTION PROCESS

1.1 Project Execution Plan This Project Execution Plan is prepared to outline the project organization. This includes project planning, project management, team roles, project design, engineering, staging etc. Over the last few decades, Yokogawa has gained a vast experience in the management and control of large-scale engineering projects worldwide. The knowledge accumulated from this rich experience has resulted in Project Management being one of Yokogawa's strongest fields of expertise. Yokogawa fully understands that in the case being selected for this project, Yokogawa had taken the following required capabilities into consideration when organizing the project team:

1 Project Management and Control 2 Project Engineering 3 System Integration 4 Start-up and Installation supervision 5 Maintenance Service 1.2 Summary of Project Management & Engineering Functions

The major functions required from the Project Organization Team typically included the following:

1 Interface with Customer’s Engineering Team 2 Work with Customer’s project team to develop “General DCS Design Practices for Yokogawa CENTUM VP System” 3 Interface with Contractor(s) 4 Schedule Management Conduct walk-through meetings: internal, with sub-vendors and sub-contractors, and with contractor Generate monthly Progress Report Ensure timely delivery of sub-vendors' equipment Ensure timely completion of project 5 Cost Control Ensure cost-effective management of project without sacrificing quality 6 Co-ordination

Internal co-ordination between various departments such as Engineering, Procurement, Manufacturing, Installation and Services

Co-ordination with sub-vendors and sub-contractors on technical and commercial issues 7. Procurement

Tendering Evaluation of Bids Placement of Orders Expediting and Follow-up 8. Engineering for Yokogawa's Equipment

Hardware Design Software Design Order Entry to Manufacturing Engineering for Non-standard Equipment System Generation and Debugging

9. Engineering for Non-Yokogawa Equipment Provide accurate engineering information to sub-vendors

Page 36: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A7_ Project Implemenation Plan.Doc Page 5

Ensure sub-vendor's quality of engineering 10. Acceptance Testing

Participate in sub-vendors' equipment Acceptance Testing Factory Acceptance Testing at Yokogawa's manufacturing facility Integrated Site Acceptance Testing

11. Documentation Prepare Drawings and Documents for Approval Prepare As-Built Drawings and Documents Compile Standard and Customized Documents

12. Training Make appropriate arrangements for comprehensive training of Customer.

13. Engineering for Installation Supervision Design for installation

14. Installation Supervision Supervise Installation activities of sub-contractors Ensure quality of sub-contractor's work Co-ordinate daily activities with Customer’s site manager Ensure safety at work site

15. Start-up supervision Coordinate presence of specialists at site

Ensure smooth start-up of Yokogawa's equipment as well as non- Yokogawa equipment

16. Commissioning assistance Provide adequate assistance to Customer, for plant commissioning Activities. Carry out hardware and/or software modifications, if required at later date, the following additional functions may be included:

17. Maintenance Make appropriate arrangements for Maintenance Contract for Yokogawa’s as well as non-Yokogawa’s equipment

Page 37: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A7_ Project Implemenation Plan.Doc Page 6

1.2.1 Project Team Organization The typical project structure is shown below, while the roles, responsibilities and functional assignment of individual members of the project team are explained in the paragraphs following the chart.

1.2.1.1 Typical Project Organization Chart A typical project organization chart gives an overview of the project team is show below. The actual organization will be proposed, discussed and finalized during the KOM.

1.2.1.2 Project Manager The Project Manager will assume full responsibility for all aspects of the project, from the commencement of project activities to the successful completion of the project. The Project Manager will closely monitor the project schedule, cost and the quality of project execution. All the key positions in the Project Organization will functionally report to him for this project. The Project Manager wills co-ordinate the activities of all the functional groups to ensure that the team operates as a cohesive unit to ensure an integrated effort. The Project Manager will raise the alerts and take necessary decisions during project execution to ensure that the project is being delivered on schedule and that the system meets all the requirements and expectations of Customer as well as the high quality standards of Yokogawa. He will also pay attention to smooth involvement of and technical transfer of the systems to the Yokogawa Service Organization for the maintenance after its start-up. The selected project manager is experienced and has track record with similar projects.

1.2.1.3 QA Manager The QA Auditor will be responsible for monitoring and ensuring that Yokogawa's policies for Quality Assurance are implemented correctly in this project. The QA Auditor is common for the

Page 38: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A7_ Project Implemenation Plan.Doc Page 7

project division and has the overall idea of the job quality requirement and will ensure that the hardware, software and engineering produced by Yokogawa for this project are of consistent and good quality. The QA Manager will also report project QA activity and status to the corporate QA General Manager.

1.2.1.4 Lead (System Integration / System) Engineers The Lead (System Integration / System) Engineer is another important key to the success of the project. He will be involved from the basic design stage to the project completion stage and will take full responsibility of total system integration. He will lead a team of engineers who will undertake the complete detailed engineering of the system and the sub-systems provide the engineering data to the sub-vendors, participate in the Acceptance Tests/Inspection of third party (buy-out) items, conduct integrated system tests, FAT and prepare the documentation for approval and as-built documents. The Project Engineer will be fully responsible to ensure the quality of the system and sub-system engineering services. He will be directly reporting to Lead Engineer closely liaising with all sub-systems for smooth project implementation.

1.2.1.5 Project Director Project Director is a member of senior Management team closely watching the project and giving total support to Project Manager if required for successful implementation of the project. He will liaise will top management team so that necessary resources can be made available for the project execution and will be in close co-ordination with Project Manager.

1.2.1.6 Project Engineers / System Engineers The Project Engineer / System Engineer will be the key person responsible for the overall project / system engineering of the project. The Project Engineer leads the Quality, Cost and Delivery Control by supervising and controlling the Engineering Teams and by monitoring and controlling the compliance with internal and project quality and engineering standards. The Project Engineering Team consists of engineers from YEA, YEA’s local representative and sub-vendors and will include in a later phase engineer(s) from the site support team. As such, the technical transfer to site staff will be executed smoothly. At the same time, this ensures that a swift and adequate response to EPC requirements for after-sales service and modifications can be provided. Yokogawa considers it essential that continuity is maintained between the engineering and construction phases of the project. Yokogawa proposes to include key project engineers in the site team to assist the Start-up and Commissioning Co-coordinator. This will effectively ensure that the complete engineering back-ground of project is utilized for smooth start-up and hand-over.

1.2.1.7 Procurement Manager The Integrated Control Vendor (ICV) concept being employed demands that a variety of systems and materials must be purchased from third-party vendors, ranging from large-scale sub-systems to many small items, such as cables etc. The Procurement Manager will arrange for timely procurement of all materials. He will be responsible for all the commercial aspects of procurement including tendering, evaluation, and order placement, expediting, follow-up and arrangements for delivering to site. The Procurement Manager will closely co-operate with the sub-system engineer. The Procurement Manager will also be the focal point for order entry and processing of Yokogawa equipment orders to factory.

Page 39: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A7_ Project Implemenation Plan.Doc Page 8

1.2.1.8 Local Project / Site Manager The Local Project Manager is another important key to the success of the project. He will be stationed at the site location from the commencement of the Construction phase to the completion of commissioning. The Local Project Manager will assume full responsibility for all the Site Administration functions, as well as act as the co-coordinator between contractor and the construction team at site. He will also be the bridge for all communication to local and regional offices in Singapore. The Local Project Manager will also take care of the vital site functions such as safety in site works, quality of the site works, co-ordination and control of labor subcontractor, materials control, and minor materials procurement. The Site Manager will ensure the timely implementation of the project.

1.2.1.9 Start-up Lead Engineer The Start-up and Installation Supervisor is a key function for the success of the project. He will be station at site location from the commencement of the installation phase to the completion of commissioning and he will direct and guide the installation of the DCS and subsystems.

1.3 Engineering Execution Plan

1.3.1.1 Introduction Yokogawa considers the quality of engineering during the execution of a project of prime importance. Excellence in engineering is a major factor in Yokogawa's success. In order to achieve this objective, extensive training is provided for the engineers in Yokogawa. The training includes classroom training in which the engineers gain in-depth knowledge of Yokogawa's products, as well as on-the-job training during whereby the young engineers are guided by their senior experiences colleagues. The on-the-job training enhances the application knowledge of the engineers and widens their perspective by exposing the engineers to other varied aspects of engineering such as sub-vendor's engineering and subsystems, installation practices etc. Yokogawa's experience and knowledge acquired by the engineering and implementation of FCS systems for various similar projects will be fully utilized in this project.

1.3.1.2 Standard Procedures Yokogawa firmly believes that standardization of procedures goes a long way in ensuring smooth accomplishment of projects. For project execution, Yokogawa has developed project procedure and engineering standards.

1.3.1.3 Job Handling Manual Yokogawa's Job Handling Manual is a comprehensive and extensive document covering many aspects. We execute projects according the work Flow Path in a project and within each phase of the project. Together with the necessary Check Lists this ensures that all necessary information and actions in the relevant stages are executed. The job definition will include the responsibility of each party involved. It must be borne in mind that each job has a different character. Obviously, no standard manual can cover the Project Handling procedure for each and every job. In fact Yokogawa engineers apply the Job Handling Manual as reference and produce a detailed Job Handling Manual to achieve the optimum Project Execution Plan for

Page 40: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A7_ Project Implemenation Plan.Doc Page 9

every project.

Yokogawa's engineering activities can be sub-divided into three categories:

Project Engineering - covers the aspects of Project Management, Customer Interface, Basic hardware engineering, sub-vendor systems engineering and total systems integration

Application Engineering - deal with the detailed engineering of the Yokogawa systems

Installation Supervision, Commissioning start-up

Yokogawa will deploy specialized personnel to accomplish each area of engineering. 1.3.1.4 Interface with Sub-Vendors and Sub-Contractors Lead engineer along with Project manager and Procurement Manager’s function will be to co-ordinate the purchasing activities such as tendering, evaluation and order placement. He will also be responsible for expediting, arrangements for inspection, liaison and shipping. The technical co-ordination with sub-vendors and sub-contractors will be carried out by the Project Engineering Team headed by the Lead Engineer. These technical functions will include:-

Obtain information from contractor Basic engineering of sub-systems Provide engineering information to sub-vendors Check sub-vendor drawings Co-ordinate drawing approvals with customer Participate in sub-vendor Factory Acceptance Test Participate in integrated Site Acceptance Test

1.3.1.5 Responsibility of Sub-Vendors and Sub Contractors Yokogawa will always remain the prime party responsible for all the activities covered under the scope of the project. As such, all sub-vendors and sub-contractors for this project will operate under the umbrella of Yokogawa. Thus the division of responsibility shown here is purely an internal division within Yokogawa's project organization. The sub-vendors and sub-contractors shall carry out all the necessary detailed engineering for their systems and products. Specifically the activities of the sub-vendors and subcontractors shall include:

Hardware design and detailed engineering

Software design and detailed engineering

Internal testing

1 Factory Acceptance Test eye-witnessed by Yokogawa and/or Customer’s Representative

Assistance during System Installation

Assistance during Commissioning

Assistance during Start-up

Assistance during Integrated Site Acceptance Test

Page 41: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A7_ Project Implemenation Plan.Doc Page 10

Training

Maintenance

2 1.3.2 Yokogawa Project Management Having a wealth of project execution experience, Yokogawa is fully aware of the need for meticulous planning and scheduling for a project of a complexity as the project. The preliminary project schedule is attached at the end of this document, which will be modified as needed after the discussion with Customer. The long experience in executing large projects has given Yokogawa the in-sight to satisfactorily handle engineered projects. Yokogawa's Engineering Division includes a Project Engineering Department responsible for all project handling, for the analysis of successes and failures, and for the initiation of pre-emptive actions to meet eventualities. The department ensures that the optimum manpower is employed for the projects and monitors and controls the schedules of the projects in close co-operation with the project managers. The project manager is the key person responsible for the planning of the project during engineering phase. He will ensure that the wide array of engineering activities follows the chartered course. He is in the right position to foresee potential problems, to make adequate decisions and to take necessary actions. When his intended actions are exceeding his responsibilities he will alert and consult the line management.

1.3.2.1 Goal Directed Project Management The YOKOGAWA management of major projects is focused on the objectives of the project. In addition to the technical goals the project should develop the people, the systems and the organization to operate the new technology. Further the YOKOGAWA approach encourages creative management, to ensure optimum product quality, balanced against the constraints of time and costs. YOKOGAWA has a long-term track record in the management of major projects and many project team members; customer and user staffs have contributed to YOKOGAWA's project management expertise. As result a project management method has evolved which is explicitly suitable to manage major technical projects. The YOKOGAWA Goal Directed Project Management method aims to:

Focus on results

Layer the project plan

Plan creatively

Organize the project

Co-ordinate the project

Control the project

YOKOGAWA's Goal Directed Project Management provides the tools to submit to the Customer, the user and the team member up to date information on technical progress at any moment. It provides the tools to control project costs to prevent unexpected surprises and to balance time, cost and quality.

Page 42: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A7_ Project Implemenation Plan.Doc Page 11

1.3.3 Tests, Installation Supervision And Start-Up 1.3.3.1 Factory Acceptance Test The factory inspection for hardware and software is divided into two phases:

Internal Test Factory Acceptance Test

Internal Test The internal test of the integrated system is designed to thoroughly test all items before the Factory Acceptance Test. This test will be conducted by Yokogawa and Sub-vendor and Sub-contractor specialists, and it is performed in accordance with Yokogawa and/or Sub-vendor standard test procedures. The test is based on the following:

In the event that any defect or failure of the functions supplied by YOKOGAWA is found during the test, YOKOGAWA shall be responsible to provide work and material to recover thepromised performance. Factory Acceptance Test The Factory Acceptance Test (FAT) is eye-witnessed by Customer’s representatives and it is intended to prove that the system and components function properly and in accordance with the Customer’s order. The FAT should prove that the design, the manufacturing, the software generation and the system and application configuration have been done correctly and completely. The FAT is carried out in accordance with the FAT procedures as mutually agreed upon by Customer and Yokogawa. The FAT will include the execution of sequential steps to prove compliance of the developed software and manufactured hardware with the Customer’s order. The FAT will be executed in Yokogawa office and will be eye-witnessed by Customer’s representatives. The area in which the system is installed is accessible from Monday until Friday from 08.30 hours until 17.30 hours. Upon successful completion of the test, Customer shall furnish YOKOGAWA with a certificate in writing to that effect and in addition, furnish to YOKOGAWA a "release note for shipment".

1.3.3.2 Site Acceptance Test

Site services are typically offered based on a per diem basis. At first the Site Acceptance Test (SAT) is to verify that no visible and/or invisible damage occurred to the system during transportation and installation. Fundamentally the SAT follows the FAT and adds the plant system interfacing to the tests. When the proposed system has been installed, (but not connected to the field equipment) and certified as fully operative Yokogawa shall conduct a Site Acceptance Test. The SAT will be a condensed form of the Factory Acceptance Test plus integrated test. The Lead Commissioning and Start-up Engineer supervise the SAT under the directions of Customer’s staff. The main items of the SAT include:

Loop checking of instrument loops - checks that the overall connections to the software are correct by checking the field signal from field to system

System functional checks - confirms that no damage to the system occurred by repeating the tests (10 to 20%) as executed during the FAT

Non-system functional checks - confirms that no damage occurred by repeating the tests as

Page 43: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A7_ Project Implemenation Plan.Doc Page 12

executed during the FAT

Overall site acceptance test - confirms that the total integrated system functions correctly. Upon the successful completion of the test, Customer shall furnish YOKOGAWA with a certificate in writing to that effect and ownership of the system shall automatically be transferred to the Purchaser.

1.3.3.3 Commissioning and Start-up It is essential that commissioning and start-up activities for the system and other sub-systems are co-coordinated to achieve a timely and adequate system start-up. The Lead Commissioning and Start-up Engineer will be responsible for this co-ordination and integration function. He will play a major role in the design and execution of the commissioning and start-up schedule in consultation with Customer’s Site-team. He wills also co-ordinate with Yokogawa's project and specialist start-up engineers and the start-up engineers of other sub-systems to ensure that the job is completed within schedule and the logistics for such work are in proper order. The Lead Commissioning and Start-up Engineer in co-operation with the Installation Supervisor and Project Engineers will co-ordinate with Customer for the smooth commissioning and start-up of the systems. At the time of start-up and commissioning is heavily related to the proper working of field equipment/plant, services will be offered based on a per diem basis.

1.3.4 Progress Reports and Progress Meetings 1.3.4.1 Progress Reporting One of the important functions of the project Manager is to continuously inform the customer and Yokogawa management of the total progress of the job and other necessary management information. Project manager prepares normally two types of reports.

1.3.4.2 Project Progress report Project progress report is prepared by the Project Manager and sent to customer. The frequency is normally every month and usually during the end of the month. Before preparing the report project manager collects the detailed information from subsystem supplier also regarding the status of the items in their manufacturing and consolidates the report as the overall project status, as the prime contractor of the job. He will clearly identify in the report the current status of the job, delay if any, what actions taken by him to recover the delay, any action / help required from the customer to expedite the work etc.

1.3.4.3 Internal Management Report In this report to the top management, he will elaborate various status of the job, delay if any management’s help in solving any problem, cost control measures and management costing.

1.3.4.4 Progress Meetings During the execution of the project, Project Manager regularly conducts the project progress meeting with Customer. The main idea is to have face to face discussions on the project, apprise customer with the progress so far, hold up, if any, have a mutually beneficial discussion on how to solve the problem and in what way the total team can come in to a conclusion to proceed smoothly the job. The frequency of the meeting depends on the progress status of the job and critically of the hold up. But in general large projects have a monthly progress meeting until the start of FAT.

Page 44: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A7_ Project Implemenation Plan.Doc Page 13

1.3.5 Quality Assurance As an organization, Yokogawa is structured to provide complete engineering, integrated system solutions, products including training and service with excellent quality. Yokogawa has been ISO 9001 certified since May 1992 for Sales, Application Engineering, After Sales Service of DCS and manufacture of Panels.

1.3.5.1 Project Handling Procedure The project handling procedure includes various checks which benefit quality control:

Contract review

Kick-off meetings

Basic design reviews

Sub-system kick-off meetings

Detailed design reviews

In addition the integrated project reporting system, weekly walk through and activity reports and monthly project manager review are tools to achieve the highest quality.

1.3.5.2 Global Organization of Yokogawa Yokogawa has a global organization to assure the quality control and assurance structure. The project engineering flow is applied in the various worldwide organizations to achieve the quality assurance of the entire integrated system.

1.3.6 Drawings & Documentation

Yokogawa will submit all required documents in the application for Customer’s approval and/or review as scheduled. Drawings provided by Yokogawa are made on in-house Auto Cad or equivalent format and IBM-PC drawings. The sub-vendor drawings will be provided by Auto Cad files or equivalent and all other documents will be provided by IBM-compatible PC.

1.3.7 Change Order Handling

A change order request is raised (e.g. in a progress meeting) whenever there is a change in the scope of supply or whenever rework is required. The request will indicate the item that requires a change order and the cost. For each change or group of changes a change order form will be submitted (Yokogawa’s standard form). This form will indicate the changes, reason for change, what will be the impact of this change (in schedule and cost, etc.). All changes will be recorded in the format defined in the kick off meeting. After approval of the change, the work will be carried out. All changes require written confirmation before commencing the implementation.

End of This Section

Page 45: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

A8_ ICSS Upgrade Project Schedule Page 1

Project Name : YADANA SUBSIDENCE PROJECT

Customer Name : PT JETEC INDONESIA

Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

Proposal Section : Technical Proposal

Title : ICSS Upgrade Project Schedule

Total No. of pages of this document (including this cover page) [3]

Page 46: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A8_ ICSS Upgrade Project Schedule Page 2

CONTENTS

Section Page

ICSS Upgrade Project Schedule ………………………………..………………………..…………….…….……3

Page 47: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

ID Task Name Duration Start Finish

1 ICSS UPGRADE EPSCC1 PROJECT 570 days Mon 10/24/11 Fri 12/27/13

2 Received Letter of Intent 1 day Mon 10/24/11 Mon 10/24/11

3 IMPLEMENTATION PHASES 570 days Mon 10/24/11 Fri 12/27/13

4 Internal KOM 1 day Mon 11/7/11 Mon 11/7/11

5 Site Survey + Download Existing Centum-CS Files 5 days Tue 11/8/11 Mon 11/14/11

6 KOM @ Site 1 day Wed 11/23/11 Wed 11/23/11

7 DCS + SIS SYSTEM 315 days Mon 10/24/11 Fri 1/4/13

8 DCS + SIS Basic Design 41 days Mon 12/5/11 Mon 1/30/12

9 General Specification 10 days Mon 12/5/11 Fri 12/16/11

10 DCS + SIS Hardware Specification 10 days Mon 12/19/11 Fri 12/30/11

11 DCS + SIS Software Specification 10 days Mon 1/2/12 Fri 1/13/12

12 Issued Specification for Review 1 day Mon 1/16/12 Mon 1/16/12

13 Design Review Meeting 10 days Tue 1/17/12 Mon 1/30/12

14 Internal Specification Freeze 1 day Tue 1/24/12 Tue 1/24/12

15 DCS + SIS Detail Design 23 days Mon 12/19/11 Wed 1/18/12

16 DCS + SIS Hardware Specification 5 days Mon 12/19/11 Fri 12/23/11

17 DCS + SIS Software Specification 5 days Mon 12/26/11 Fri 12/30/11

18 Issued Documents for Approval 1 day Tue 1/3/12 Tue 1/3/12

19 Approval by client 10 days Wed 1/4/12 Tue 1/17/12

20 Design Freeze 1 day Wed 1/18/12 Wed 1/18/12

21 DCS + SIS Manufacturing & Generation 275 days Mon 10/24/11 Fri 11/9/12

22 Hardware Manufacturing 60 days Mon 1/23/12 Fri 4/13/12

23 Software Generation 150 days Mon 3/5/12 Fri 9/28/12

24 - Graphics Generation 150 days Mon 3/5/12 Fri 9/28/12

25 -Logging Reports. 0 days Mon 10/24/11 Mon 10/24/11

26 Debug 20 days Mon 10/1/12 Fri 10/26/12

27 Staging and Pre-FAT 10 days Mon 10/29/12 Fri 11/9/12

28 DCS + SIS FAT 35 days Mon 11/19/12 Fri 1/4/13

29 FAT 25 days Mon 11/19/12 Fri 12/21/12

30 DCS System Recovery and Packing (FOB) 10 days Mon 12/24/12 Fri 1/4/13

31 SHIPMENT TO SITE 255 days Mon 1/7/13 Fri 12/27/13

32 Air-Freight 5 days Mon 1/7/13 Fri 1/11/13

33 Custom Clearance 5 days Mon 1/14/13 Fri 1/18/13

34 Local Transportation to Site 5 days Mon 1/21/13 Fri 1/25/13

35 Site Installation QP SIMULATOR 7 days Mon 1/28/13 Tue 2/5/13

36 Site Installation SAT QP 15 days Mon 3/11/13 Fri 3/29/13

37 Yard Modular Building JACKUP 30 days Mon 4/15/13 Fri 5/24/13

38 SAT JACKUP OFFSHORE 30 days Mon 6/10/13 Fri 7/19/13

39 Yard Modular Building MSF2 30 days Mon 9/2/13 Fri 10/11/13

40 SAT MSF2 OFFSHORE 30 days Mon 11/18/13 Fri 12/27/13

10/2464%

63%

83%

100%

100%

88%

10/24

0%

0%

2 9 162330 6 132027 4 111825 1 8 152229 5 121926 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926 2 9 162330 7 142128 4 111825 2 9 162330 6 132027 3 101724 3 10172431 7 142128 5 121926 2 9 162330 7 142128 4 111825 1 8 152229 6 132027 3 101724 1 8 152229 5 121926October November December January February March April May June July August Septembe October November December January February March April May June July August Septembe October November December January

Task

Split

Progress

Milestone

Summary

Rolled Up Task

Rolled Up Split

Rolled Up Milestone

Rolled Up Progress

External Tasks

Project Summary

External Milestone

Deadline

ICSS UPGRADE EPSCC1 MIGRATION PROJECT SCHEDULE

Yokogawa Engineering Asia Pte Ltd

ICSS UPGRADE Project ScheduleDocument No: EPSCC1-B91-001 rev ADate: 27 Sep 2011.

Page 48: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

A9_CVP Upgrade R5 (DCS HW Bill Of Material)_R00.DocPage 1

Project Name : YADANA SUBSIDENCE PROJECT

Customer Name : PT JETEC INDONESIA

Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

Proposal Section : Technical Proposal

Title : CVP Upgrade R5 (DCS HW Bill of Material)

Total No. of pages of this document (including this cover page) [5]

Page 49: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A9_CVP Upgrade R5 (DCS HW Bill Of Material)_R00.DocPage 2

Section Page 1  CVP Upgrade R5 (DCS HW Bill of Material) ................................................................ 3 

Page 50: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

List of Equipment for upgrade Centum-CS to Centum-VP system in March 2013

QP Model : Training Simulator in ITR QTY

1 AVR10D-V22021 (AVR10D Router) 12 L2SW Hirschman (GRVSW-664FA (MACH104-20TX-FR) 23 HIS-ENG with Double Screen (Desktop) (LPCKIT-M1L41402/USB/2TP/CH/HB) 14 CP345 25 YCB311 1-Meters Vnet 10Base5 cable (YCB311-M001) 26 YCB141 1-Meters Vnet 10Base2 cable (YCB141-M001) 27 YCB146 T-Joint (YCB146) 28 YCB148 Vnet Terminator 50 Ohms (10Base2) (YCB148) 29 YCB118 Vnet Terminator 50 Ohms (10Base5) (YCB118) 210 YCB149 Vnet Converter (YCB149) 211 Ethernet cable UTP Cat5e or Cat6 (5m) 212 Ethernet cable UTP Cat5e or Cat6 (1m) 413 MCB Breaker 2A 230VAC for AVR router 214 MCB Breaker 4A 230VAC for L2SW Switch 215 Control Bus Interface Card VI702 116 Decommissioning of ACG and related VNET cable 117 Decommissioning of E-NET cable 1

Total HW : Training Simulator in ITR

QP Model : CCR + ITR QTY

1 AVR10D-V22021 (AVR10D Router) 12 L2SW Hirschman (GRVSW-664FA (MACH104-20TX-FR) 33 HIS-ENG (Engineering WorkStation, Desktop) + 1 HIS-ENG Backup (Dell T3500) 24 Control Bus Interface Card VI702 85 HIS (Operator & Monitoring Function) Enclosed Console Type Double screen

(OS3/4/7/8) (LPCKIT-M1L41402/USB/2TP/CH/HB) 4

6 LaserJet Printer For HIS-ENG (HP P4015n) 17 CP345 68 HIS Single Screen Desktop for Maintenance (Dell T3500) 19 Laser Printer Black & White For HIS (HP LaserJet P4015n Printer) 110 Color Printer For HIS (HP CP3525dn) 111 YCB311 1-Meters Vnet 10Base5 cableYCB311-M001 212 YCB141 1-Meters Vnet 10Base2 cable YCB141-M001 213 YCB146 T-Joint (YCB146) 214 YCB148 Vnet Terminator 50 Ohms (10Base2) (YCB148) 215 YCB118 Vnet Terminator 50 Ohms (10Base5) (YCB118) 216 YCB149 Vnet Converter (YCB149) 217 Ethernet cable UTP Cat5e or Cat6 (20m) 1218 Ethernet cable UTP Cat5e or Cat6 (15m) 419 Ethernet cable UTP Cat5e or Cat6 (5m) 520 Ethernet cable UTP Cat5e or Cat6 (1m) 621 TriFellows Server or (Upgrade TriFellow Server Logger V3) 122 TriFellows Client or (Remain TriFellow Client V3) 123 EXAOPC Server For TriFellow System (PowerEdge T710) 124 YNT511-V42 Optical Bus Repeater (OBR) for MSF2 125 MCB Breaker 2A 230VAC for AVR router 226 MCB Breaker 4A 230VAC for L2SW Switch 227 MCB Breaker 4A 230VAC for OBR repeater 228 Cubical Console for Telephone (OWS2 & OWS3) 229 Cubical Console for ESD(OS5) & PA/GA CCTV (OS6) 230 Operator Chair 631 Decommissioning of ACG and releated VNET cable 332 Decommissioning of E-NET HUB and related Enet cable 3

Total HW : CCR + ITR

Page 51: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

QP Model : Production Platform QTY

1 CP345 62 Decommissioning of E-NET HUB and related Enet cable 1

Total HW : Production Platform

MCP Model : Medium Compressor Platform QTY

1 L2SW Hirschman (GRVSW-664FA (MACH104-20TX-FR) 32 HIS Single Screen Desktop ( Dell T3500) 13 LaserJet Color Printer (CP3523dn) 14 Ethernet cable UTP Cat5e or Cat6 (15m) 25 Ethernet cable UTP Cat5e or Cat6 (2m) 26 MCB Breaker 4A 230VAC for L2SW Switch 27 Control Bus Interface Card VF702 18 Lay Optical cable 2pair of 4core from MCP to QP. (Vnet/IP) 49 Lay Optical cable2pair of 4core from MCP to JACKUP. (Vnet/IP) 410 Decommissioning of ACG and releated VNET cable 111 Decommissioning of E-NET HUB 112 Decommissioning of E-NET cable 1

Total HW : Medium Compressor Platform

JACK-UP Model : Jack-Up Platform QTY

1 AVR10D Router (AVR10D-V22021) 12 L2SW Hirschman (GRVSW-664FA (MACH104-20TX-FR) 33 HIS-ENG (Desktop) - Dell T3500 14 HIS console for maintenance - Dell T3500 15 Color Printer For HIS-ENG 16 HIS Double Screen (Desktop) Dell T3500 27 Laser Printer Black & White 18 YNT511-V42 Optical Bus Repeater (OBR) 29 AFS10D-H4123/Z2P (In new Cabinet with one pair CP345) 110 AND50-562 with 2xAMN33 Nest 111 AMN33 Nest 212 ACM12 card 213 AKB161 cable for ACM12 card 214 YCB311 5-Meters Vnet 10Base5 cable 215 YCB141 1-Meters Vnet 10Base2 cable 216 YCB146 T-Joint 217 YCB148 Vnet Terminator 50 Ohms (10Base2) 218 YCB118 Vnet Terminator 50 Ohms (10Base5) 219 YCB149 Vnet Converter (YCB149) 220 Ethernet cable UTP Cat5e or Cat6 (20m) 821 Ethernet cable UTP Cat5e or Cat6 (15m) 422 Ethernet cable UTP Cat5e or Cat6 (5m) 223 Ethernet cable UTP Cat5e or Cat6 (2m) 424 MCB Breaker 2A 230VAC for AVR router 225 MCB Breaker 4A 230VAC for L2SW Switch 226 MCB Breaker 4A 230VAC for OBR repeater 227 MCB Breaker 6A 230VAC for AFM10D 228 MCB Breaker 4A 230VAC for AND50 229 FCS cabinet (communication with double door) 330 Control Bus Interface Card VF702 431 Lay Optical cable 2pair of 4core from JACKUP to WP1 (VNET) 1

Total HW : Jack-Up Platform

Page 52: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

WP1 Model : Well Head 1 QTY

1 YNT511D-V42 Optical Bus Repeater (OBR) 12 YCB311 1-Meters Vnet 10Base5 cable 23 MCB Breaker 4A 230VAC for OBR repeater 24 CP345 4

Total HW : Well Head 1

WP2 Model : Well Head 2 QTY

1 CP345 4Total HW : Well Head 2

MSF2 Model : MSF2 QTY

1 AVR10D Router (AVR10D-V22021) 12 L2SW Hirschman (GRVSW-664FA (MACH104-20TX-FR) 23 HIS-ENG (Desktop) 14 Color Printer For HIS-ENG 15 HIS Double Screen (Desktop) 16 Laser Printer Black & White For HIS 17 YNT511-V42 Optical Bus Repeater (OBR) 18 AFS10D-H4123/Z2P (In new Cabinet with one pair CP345) + 19" rack cabinet 19 AND50D-562 with 2xAMN33 Nest / 2xAMN11/ZEL Nest / 1xAMN32 Nest 110 AMN33 Nest for Modbus Communication 211 AMN11 Nest for Analog input & output 212 AMN32 Nest for Digital input & output 113 ACM12 Card + AKB161-M015 (15m) 414 AAM11B Card 2015 AAM51 Card 616 ADM11C Card 217 ADM51C Card 218 ELCO Terminal Board for Analog input/output card for AMN11 Nest 219 ELCO Terminal Board for Digital input/output module AMN32 Nest 420 ELCO Cable from AMN11 nest to Terminal board for I/O 221 KS2 or KS3 cable depend on site elco board type 422 YCB311 1-Meters Vnet 10Base5 cable 223 YCB311 5-Meters Vnet 10Base5 cable 224 YCB141 1-Meters Vnet 10Base2 cable 225 YCB146 T-Joint 226 YCB148 Vnet Terminator 50 Ohms (10Base2) 227 YCB118 Vnet Terminator 50 Ohms (10Base5) 428 YCB149 Vnet Converter (YCB149) 229 Ethernet cable UTP Cat5e or Cat6 (15m) 430 Ethernet cable UTP Cat5e or Cat6 (1m) 431 Ethernet cable UTP Cat5e or Cat6 (5m) 232 MCB Breaker 2A 230VAC for AVR router 233 MCB Breaker 4A 230VAC for L2SW Switch 234 MCB Breaker 4A 230VAC for OBR repeater 235 MCB Breaker 6A 230VAC for AFM10D 236 MCB Breaker 4A 230VAC for AND50 237 Power Distribution Cabinet (PDB for PCS & SIS) 138 FCS cabinet (communication with double door) + PSS TRICONEX 239 Control Bus Interface Card VF702 2

Total HW: MSF2

Page 53: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

A10_CVP Upgrade R5 (DCS SW Bill Of Material)_R00.DocPage 1

Project Name : YADANA SUBSIDENCE PROJECT

Customer Name : PT JETEC INDONESIA

Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

Proposal Section : Technical Proposal

Title : CVP Upgrade R5 (DCS SW Bill of Material)

Total No. of pages of this document (including this cover page) [6]

Page 54: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A10_CVP Upgrade R5 (DCS SW Bill Of Material)_R00.DocPage 2

Section Page 1  CVP Upgrade R5 (DCS SW Bill of Material) ................................................................ 3 

Page 55: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Software List for upgrade Centum-CS to Centum-VP system in March 2013QP Training Simulator in ITR

M0264 Model Description QTY1 CVPS//LFS9053-V2V1 Modbus Communication Redundancy 12 CVPS//LHS5100-V11/N0099 Standard Builder Funtion 13 CVPS//LHS1100-V11/N0099 Operation & Monitoring Funtion 14 CVPS//LHS5150-V11 Graphic Builder 15 CVPS//LHS2411-V11 EXAOPC for HIS 16 CVPS//LHS4190-V11 Line Printer Support 17 CVPS//LHS4410-V11 Control Drawing Status 18 CVPS//LHS4420-V11 Logic Chart Status Dusplay 19 CVPS//LHS5420-V11 Test Function 110 CVPS//LHS5426-V11 FCS Simulator 111 CVPS//LHS5490-V11 Self-Doc 112 CVPS//LHS4600-V11 Multiple Monitor 113 CVPS//LHS6510-V11 Long term archive 114 CVPS//LHS6530-V11 Report Package 115 CVPS//LHS5495-V11 Electronic IM 1

Total for QP M0264

QP Live System in CCR & ITR + MCPM0264 Model Description QTY

1 CVPS//LFS9053-V2V1 Modbus Communication Redundancy 12 CVPS//LHS5100-V11/N0099 Standard Builder Funtion 13 CVPS//LHS1100-V11/N0099 Operation & Monitoring Funtion 14 CVPS//LHS5150-V11 Graphic Builder 15 CVPS//LHS2411-V11 EXAOPC for HIS 16 CVPS//LHS4190-V11 Line Printer Support 17 CVPS//LHS4410-V11 Control Drawing Status 18 CVPS//LHS4420-V11 Logic Chart Status Dusplay 19 CVPS//LHS5420-V11 Test Function 110 CVPS//LHS5426-V11 FCS Simulator 111 CVPS//LHS5490-V11 Self-Doc 112 CVPS//LHS4600-V11 Multiple Monitor 113 CVPS//LHS6510-V11 Long term archive 114 CVPS//LHS6530-V11 Report Package 115 CVPS//LHS5495-V11 Electronic IM 1

Total for QP M0264

QP Live System in CCR & ITR + MCPM0260 Model Description QTY

1 CVPS//LHS1100-V11/N0099 Operation & Monitoring Funtion 12 CVPS//LHS1120-V11/WP Console HIS For Enclosed Style Dual CRT 13 CVPS//LHS2411-V11 EXAOPC for HIS 14 CVPS//LHS4190-V11 Line Printer Support 15 CVPS//LHS4410-V11 Control Drawing Status 16 CVPS//LHS4420-V11 Logic Chart Status Dusplay 17 CVPS//LHS4600-V11 Multiple Monitor 18 CVPS//LHS6510-V11 Long term archive 19 CVPS//LHS6530-V11 Report Package 1

Total for QP M0260

QP Live System in CCR & ITR + MCPM0261 Model Description QTY

Page 56: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

1 CVPS//LHS1100-V11/N0099 Operation & Monitoring Funtion 12 CVPS//LHS1120-V11/WP Console HIS For Enclosed Style Dual CRT 13 CVPS//LHS2411-V11 EXAOPC for HIS 14 CVPS//LHS4190-V11 Line Printer Support 15 CVPS//LHS4410-V11 Control Drawing Status 16 CVPS//LHS4420-V11 Logic Chart Status Dusplay 17 CVPS//LHS4600-V11 Multiple Monitor 18 CVPS//LHS6510-V11 Long term archive 19 CVPS//LHS6530-V11 Report Package 1

Total for QP M0261

QP Live System in CCR & ITR + MCPM0262 Model Description QTY

1 CVPS//LHS1100-V11/N0099 Operation & Monitoring Funtion 12 CVPS//LHS1120-V11/WP Console HIS For Enclosed Style Dual CRT 13 CVPS//LHS2411-V11 EXAOPC for HIS 14 CVPS//LHS4190-V11 Line Printer Support 15 CVPS//LHS4410-V11 Control Drawing Status 16 CVPS//LHS4420-V11 Logic Chart Status Dusplay 17 CVPS//LHS4600-V11 Multiple Monitor 18 CVPS//LHS6510-V11 Long term archive 19 CVPS//LHS6530-V11 Report Package 1

Total for QP M0262

QP Live System in CCR & ITR + MCPM0263 Model Description QTY

1 CVPS//LHS1100-V11/N0099 Operation & Monitoring Funtion 12 CVPS//LHS1120-V11/WP Console HIS For Enclosed Style Dual CRT 13 CVPS//LHS2411-V11 EXAOPC for HIS 14 CVPS//LHS4190-V11 Line Printer Support 15 CVPS//LHS4410-V11 Control Drawing Status 16 CVPS//LHS4420-V11 Logic Chart Status Dusplay 17 CVPS//LHS4600-V11 Multiple Monitor 18 CVPS//LHS6510-V11 Long term archive 19 CVPS//LHS6530-V11 Report Package 1

Total for QP M0263

QP Live System in CCR & ITR + MCPM0258 Model Description QTY

1 CVPS//LHS1100-V11/N0099 Operation & Monitoring Funtion 12 CVPS//LHS2411-V11 EXAOPC for HIS 13 CVPS//LHS4190-V11 Line Printer Support 14 CVPS//LHS4410-V11 Control Drawing Status 15 CVPS//LHS4420-V11 Logic Chart Status Dusplay 16 CVPS//LHS4600-V11 Multiple Monitor 17 CVPS//LHS6510-V11 Long term archive 18 CVPS//LHS6530-V11 Report Package 1

Total for QP M0258

QP Live System in CCR & ITR + MCPM0259 Model Description QTY

1 CVPS//LHS1100-V11/N0099 Operation & Monitoring Funtion 1

Page 57: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

2 CVPS//LHS2411-V11 EXAOPC for HIS 13 CVPS//LHS4190-V11 Line Printer Support 14 CVPS//LHS4410-V11 Control Drawing Status 15 CVPS//LHS4420-V11 Logic Chart Status Dusplay 16 CVPS//LHS4600-V11 Multiple Monitor 17 CVPS//LHS6510-V11 Long term archive 18 CVPS//LHS6530-V11 Report Package 1

Total for QP M0259

Jack-Up Jack-Up PlatformM0255 Model Description QTY

1 CVPS//LFS9053-V2V1 Modbus Communication Redundancy 12 CVPS//LHS5100-V11/N0099 Standard Builder Funtion 13 CVPS//LHS1100-V11/N0099 Operation & Monitoring Funtion 14 CVPS//LHS5150-V11 Graphic Builder 15 CVPS//LHS2411-V11 EXAOPC for HIS 16 CVPS//LHS4190-V11 Line Printer Support 17 CVPS//LHS4410-V11 Control Drawing Status 18 CVPS//LHS4420-V11 Logic Chart Status Dusplay 19 CVPS//LHS5420-V11 Test Function 110 CVPS//LHS5426-V11 FCS Simulator 111 CVPS//LHS5490-V11 Self-Doc 112 CVPS//LHS4600-V11 Multiple Monitor 113 CVPS//LHS6510-V11 Long term archive 114 CVPS//LHS6530-V11 Report Package 115 CVPS//LHS5495-V11 Electronic IM 1

Total for Jack-Up Platform M0255

Jack-Up Jack-Up PlatformM0256 Model Description QTY

1 CVPS//LHS1100-V11/N0099 Operation & Monitoring Funtion 12 CVPS//LHS2411-V11 EXAOPC for HIS 13 CVPS//LHS4190-V11 Line Printer Support 14 CVPS//LHS4410-V11 Control Drawing Status 15 CVPS//LHS4420-V11 Logic Chart Status Dusplay 16 CVPS//LHS4600-V11 Multiple Monitor 17 CVPS//LHS6510-V11 Long term archive 18 CVPS//LHS6530-V11 Report Package 1

Total for Jack-Up Platform M0256

Jack-Up Jack-Up PlatformM0257 Model Description QTY

1 CVPS//LHS1100-V11/N0099 Operation & Monitoring Funtion 12 CVPS//LHS2411-V11 EXAOPC for HIS 13 CVPS//LHS4190-V11 Line Printer Support 14 CVPS//LHS4410-V11 Control Drawing Status 15 CVPS//LHS4420-V11 Logic Chart Status Dusplay 16 CVPS//LHS4600-V11 Multiple Monitor 17 CVPS//LHS6510-V11 Long term archive 18 CVPS//LHS6530-V11 Report Package 1

Total for Jack-Up Platform M0257

Page 58: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

MSF2 MSF2 YARDM0253 Model Description QTY

1 CVPS//LFS9053-V2V1 Modbus Communication Redundancy 12 CVPS//LHS5100-V11/N0099 Standard Builder Funtion 13 CVPS//LHS1100-V11/N0099 Operation & Monitoring Funtion 14 CVPS//LHS5150-V11 Graphic Builder 15 CVPS//LHS2411-V11 EXAOPC for HIS 16 CVPS//LHS4190-V11 Line Printer Support 17 CVPS//LHS4410-V11 Control Drawing Status 18 CVPS//LHS4420-V11 Logic Chart Status Dusplay 19 CVPS//LHS5420-V11 Test Function 110 CVPS//LHS5426-V11 FCS Simulator 111 CVPS//LHS5490-V11 Self-Doc 112 CVPS//LHS4600-V11 Multiple Monitor 113 CVPS//LHS6510-V11 Long term archive 114 CVPS//LHS6530-V11 Report Package 115 CVPS//LHS5495-V11 Electronic IM 1

Total for MSF2 Yard M0253

MSF2 MSF2 YARDM0254 Model Description QTY

1 CVPS//LHS1100-V11/N0099 Operation & Monitoring Funtion 12 CVPS//LHS2411-V11 EXAOPC for HIS 13 CVPS//LHS4190-V11 Line Printer Support 14 CVPS//LHS4410-V11 Control Drawing Status 15 CVPS//LHS4420-V11 Logic Chart Status Dusplay 16 CVPS//LHS4600-V11 Multiple Monitor 17 CVPS//LHS6510-V11 Long term archive 18 CVPS//LHS6530-V11 Report Package 1

Total for MSF2 Yard M0254

Page 59: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

A11_CVP Upgrade R5 (DCS Spares)_R00.Doc Page 1

Project Name : YADANA SUBSIDENCE PROJECT

Customer Name : PT JETEC INDONESIA

Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

Proposal Section : Technical Proposal

Title : CVP Upgrade R5 (DCS spares)

Total No. of pages of this document (including this cover page) [3]

Page 60: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A11_CVP Upgrade R5 (DCS Spares)_R00.Doc Page 2

Section Page 1  CVP Upgrade R5 (DCS spares) .................................................................................... 3 

Page 61: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

List of DCS Spares

Model QTY

1 AVR10D-V22021 (AVR10D Router) 22 L2SW Hirschman (GRVSW-664FA (MACH104-20TX-FR) 23 HIS-ENG (Engineering WorkStation, Desktop) + 1 HIS-ENG Backup (Dell T3500) 24 Control Bus Interface Card VI702 25 CP345 26 YCB146 T-Joint (YCB146) 27 YCB148 Vnet Terminator 50 Ohms (10Base2) (YCB148) 28 YCB118 Vnet Terminator 50 Ohms (10Base5) (YCB118) 29 AMN33 Nest for Modbus Communication 210 ACM12 Card + AKB161-M015 (15m) 211 AAM11B Card 212 AAM51 Card 213 ADM11C Card 214 ADM51C Card 2

Total HW: DCS Spares

Page 62: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

A12_Table Of Compliance_R00.Doc Page 1

Project Name : YADANA SUBSIDENCE PROJECT

Customer Name : PT JETEC INDONESIA

Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

Proposal Section : Technical Proposal

Title : Table of Compliance

Total No. of pages of this document (including this cover page) [8]

Page 63: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A12_Table Of Compliance_R00.Doc Page 2

CONTENTS

Section Page 1  Table of Compliance ..................................................................................................... 3 1.1  Document Number YSP ITT EPSCC1 EXA Att7 R1 ............................................ 3 1.2  Document Number MM-YAD-00-DO01-474032…….…..…………...…...…….……5 

Page 64: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A12_Table Of Compliance_R00.Doc Page 3

1 Table of Compliance

Please note that we, at YOKOGAWA, made our best efforts to provide a meaningful compliance list in responding to the specifications. If in your point of view, any response is not up to the expectation, we greatly appreciate your efforts to bring them to our notice in order to review and update.

We use the following definitions to denote the state of compliance to each specification clause:

Enhancement : The proposed system/solution exceeds the stated feature/ functionality.

Complies : The proposed system/solution complies with the stated feature/ functionality.

Alternatives : The proposed system/solution does not meet the specific feature/ functionality. However, an alternative or similar feature/solution is proposed.

Noted : We acknowledge the clause provides general information for the preparation of our proposal.

Exception : The specific feature/functionality is not available in the proposed system/solution, and is not included in our proposal.

Please note that the referenced documents, paragraphs or appendices will be responded separately, instead of within the current paragraph.

1.1 Document Number Document No.: YSP ITT EPSCC1 EXA Att7 R1 Rev: Dated:

Clause No.

Enh

ance

men

t C

ompl

ies

Alte

rnat

ives

N

oted

Ex

cept

ion

Comments / Clarifications

1 x 1.1 x 1.2 x 2 x 3 x 4 x 4.1 x 4.1.1 x 4.1.2 x 4.1.3 x 4.1.4 x Jetec Indonesia to respond 4.2 x Jetec Indonesia to respond 4.2.1 x Jetec Indonesia to respond

Page 65: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A12_Table Of Compliance_R00.Doc Page 4

Document No.: YSP ITT EPSCC1 EXA Att7 R1 Rev: Dated:

Clause No.

Enh

ance

men

t C

ompl

ies

Alte

rnat

ives

N

oted

E

xcep

tion

Comments / Clarifications

4.2.2 x Jetec Indonesia to respond 4.2.3 x Jetec Indonesia to respond 4.2.4 x Jetec Indonesia to respond 4.2.5 x Jetec Indonesia to respond 4.2.6 x Jetec Indonesia to respond 4.2.7 x Jetec Indonesia to respond 4.2.8 x Jetec Indonesia to respond 4.2.9 x Jetec Indonesia to respond 4.2.10 x Jetec Indonesia to respond4.2.11 x Jetec Indonesia to respond 4.3 x Jetec Indonesia to respond 4.3.1 x Jetec Indonesia to respond 4.3.2 x Jetec Indonesia to respond 4.3.3 x Jetec Indonesia to respond 5 x Jetec Indonesia to respond 5.1 x Jetec Indonesia to respond 5.2 x Jetec Indonesia to respond 5.3 x Jetec Indonesia to respond 5.3.1 x Jetec Indonesia to respond 5.3.2 x Jetec Indonesia to respond 5.3.3 x Jetec Indonesia to respond 5.3.4 x Jetec Indonesia to respond 5.4 x Jetec Indonesia to respond 5.5 x Jetec Indonesia to respond 5.6 x Jetec Indonesia to respond 6 x Jetec Indonesia to respond 6.1 x Jetec Indonesia to respond 6.2 x Jetec Indonesia to respond 6.2.1 x Jetec Indonesia to respond 6.2.2 x Jetec Indonesia to respond 6.2.2.1 x Jetec Indonesia to respond 6.2.2.1.1 x Jetec Indonesia to respond 6.2.2.1.2 x Jetec Indonesia to respond 6.2.2.2 x Jetec Indonesia to respond 6.2.2.3 x Jetec Indonesia to respond 6.2.2.4 x Jetec Indonesia to respond6.2.2.5 x Jetec Indonesia to respond 6.2.2.6 x Jetec Indonesia to respond 6.2.3 x Jetec Indonesia to respond 6.2.4 x Jetec Indonesia to respond 6.2.5 x Jetec Indonesia to respond 6.2.6 x Jetec Indonesia to respond

Page 66: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A12_Table Of Compliance_R00.Doc Page 5

Document No.: YSP ITT EPSCC1 EXA Att7 R1 Rev: Dated:

Clause No.

Enh

ance

men

t C

ompl

ies

Alte

rnat

ives

N

oted

E

xcep

tion

Comments / Clarifications

6.2.7 x Jetec Indonesia to respond 6.3 x Jetec Indonesia to respond Annex-1 x Jetec Indonesia to respond Annex-2 x Jetec Indonesia to respond Annex-3 x Jetec Indonesia to respond Annex-4 x Jetec Indonesia to respond Annex-5 x Jetec Indonesia to respond

1.2 Document Number Document No.: MM-YAD-00-DO01-474032 Rev: 01 Dated: 13-Jul-2011

Clause No.

Enh

ance

men

t C

ompl

ies

Alte

rnat

ives

N

oted

E

xcep

tion

Comments / Clarifications

Offshore ICSS Upgrade scope of work 1 x 1.1 x 1.2 x 1.3 x 1.3.1 x 1.3.2 x 1.4 x 1.5 x 1.5.1 x 1.5.2 x Overall site activities to be discussed during KOM 2 x 2.1 x 2.1.1 x 2.1.2 x 2.2 x As per Invensys proposal 2.2.1 x As per Invensys proposal 2.2.2 x As per Invensys proposal 2.3 x 2.3.1 x 2.3.2 x

2.3.3 x Form of report & possibility to print by period shall be reviewed during detail engineering

Page 67: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A12_Table Of Compliance_R00.Doc Page 6

Document No.: MM-YAD-00-DO01-474032 Rev: 01 Dated: 13-Jul-2011

Clause No.

Enh

ance

men

t C

ompl

ies

Alte

rnat

ives

N

oted

E

xcep

tion

Comments / Clarifications

2.4 x 2.4.1 x 2.4.2 x 2.5 x

2.5.1 x Dedicated PC additional for Exaopc software may be required and to be confirmed during detail engineering.

2.5.2 x 2.6 x

2.7 x Power consumption & Heat dissipation are impacted by the upgrade and will be calculated during detail engineering phase.

2.8 x 2.8.1 x 2.8.2 x As per Invensys proposal2.9 x 2.9.1 x 2.9.2 x As per Invensys proposal 3 x 3.1 x 3.1.1 x 3.1.2 x 3.2 x As per Invensys proposal 3.2.1 x As per Invensys proposal 3.2.2 x As per Invensys proposal 3.3 x 3.3.1 x 3.3.2 x 3.4 x 3.4.1 x 3.4.2 x 3.5 x

3.6 x Power consumption & Heat dissipation are impacted by the upgrade and will be calculated during detail engineering phase.

3.7 x 3.7.1 x 3.7.2 x As per Invensys proposal 3.8 x 3.8.1 x 3.8.2 x As per Invensys proposal 4 x 4.1 x 4.1.1 x 4.1.2 x 4.2 x As per Invensys proposal

Page 68: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A12_Table Of Compliance_R00.Doc Page 7

Document No.: MM-YAD-00-DO01-474032 Rev: 01 Dated: 13-Jul-2011

Clause No.

Enh

ance

men

t C

ompl

ies

Alte

rnat

ives

N

oted

E

xcep

tion

Comments / Clarifications

4.2.1 x As per Invensys proposal 4.2.2 x As per Invensys proposal 4.3 x

4.4 x Power consumption & Heat dissipation are impacted by the upgrade and will be calculated during detail engineering phase.

4.5 x 4.5.1 x 4.5.2 x As per Invensys proposal 4.6 x 4.6.1 x 4.6.2 x As per Invensys proposal 5 x 5.1 x 5.1.1 x 5.1.2 x 5.2 x As per Invensys proposal 5.2.1 x As per Invensys proposal 5.2.2 x As per Invensys proposal 5.3 x

5.4 x Power consumption & Heat dissipation are impacted by the upgrade and will be calculated during detail engineering phase.

5.5 x 5.5.1 x 5.5.2 x As per Invensys proposal 5.6 x 5.6.1 x 5.6.2 x As per Invensys proposal 6 x 6.1 x 6.1.1 x 6.1.2 x 6.2 x As per Invensys proposal 6.2.1 x As per Invensys proposal 6.2.2 x As per Invensys proposal 6.3 x

6.4 x Power consumption & Heat dissipation are impacted by the upgrade and will be calculated during detail engineering phase.

6.5 x 6.5.1 x 6.5.2 x As per Invensys proposal 6.6 x

6.6.1 x WP3 is not equipped with Yokogawa equipment hence no upgrade is required on WP3

Page 69: Section A_Technical Proposal QYEA1W0317 Rev.0 Dtd 28 Sep2011(Yadana Subsidence Project)_te

Project : YADANA SUBSIDENCE PROJECT

Customer : PT JETEC INDONESIA Customer Ref : EMAIL DATED 05 SEP.2011

Yokogawa Ref : QYEA1W0317 Rev.0

A12_Table Of Compliance_R00.Doc Page 8

Document No.: MM-YAD-00-DO01-474032 Rev: 01 Dated: 13-Jul-2011

Clause No.

Enh

ance

men

t C

ompl

ies

Alte

rnat

ives

N

oted

E

xcep

tion

Comments / Clarifications

6.6.2 x As per Invensys proposal 7 x 7.1 x 7.2 x As per Invensys proposal 7.2.1 x As per Invensys proposal 7.2.2 x As per Invensys proposal 7.3 x As per Invensys proposal 7.4 x As per Invensys proposal

End of This Section