Senior Colleges Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
Baruch College
17 Lex Field Building Renovation, Phase IA Construction $109,756 $109,756 2020
Energy and Controls (Phase I Upgrades) Construction $13,805 $13,805 2018
ITB Student Computer Lab Rehab Construction $2,576 $1,792 2017
NVC Performing Arts Center (BPAC) Accessibility + Terrazzo Construction $2,466 $1,713 2018
17 Lex Ave FA Upgrade Construction $1,300 $1,300 2018
North Campus Exterior Lighting Construction $709 $709 2017
NVC FA Panel Upgrade (Admin Building FA) Construction $610 $578 2018
Admin Bldg Sidewalk Replacement Construction $300 $237 2018
Repair Damage from 26th st water main Break Construction $103 $103 2017$131,625 $129,993Sub-Total
25th Street Plaza Bid $2,700 $6,000 2019
Admin Bldg ADA Bid $2,700 $2,600 2019
ITB Skylight Panel Replacement Bid $2,350 $2,325 2018
NVC Atrium Doors Hardware Bid $226 $209 2018$7,976 $11,134Sub-Total
NVC & ITB Window Washing Equip and Flooring Design $4,150 $3,368 2018
ITB Roof Replacement Design $3,350 $3,229 2019
ITB Elevator Modernization Design $2,544 $9,778 2019
17 Lex Mason Hall Water Damage Design $1,000 $961 2018
Admin Bldg Water Tank Replacement Design $969 $969 2018
Campus Wide Door Replacement Design $832 $832 2019
Admin Bldg Window Replacment Design $510 $6,985 2018
NVC - Steam Condensate Receiver Tank Design $350 $350 2019
NVC / ITB Replace RPZ valves Design $275 $215 2018$13,980 $26,687Sub-Total
ITB Cooling Towers 4 & 5 Pre-Design $758 $758 2020$758 $758Sub-Total
23 $154,339Project Count and Funding Total $168,572
11/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Senior Colleges Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
Brooklyn College
(Tow) Performing Arts Center Construction $100,500 $100,500 2018
Ingersoll Reno Lab/Vent System Construction $42,000 $42,000 2019
Fire Alarm & Security Project Construction $16,376 $16,376 2018
ADA Upgrades (Multiple Lecture Halls) Construction $12,097 $12,097 2018
Whitman Hall - Reconstruction of Ramps and Interiors Construction $10,271 $10,271 2018
2020: Vessel Construction $3,000 $3,000 2017
Whitehead Window Replacement Construction $3,000 $3,000 2018
Whitman Hall Parapets & Roof Construction $1,216 $1,216 2018
James Hall Concrete Cornice Construction $914 $914 2018
Boylan Ansul System Construction $200 $175 2018$189,574 $189,549Sub-Total
Drain and Paving Repair Bid $883 $883 2018$883 $883Sub-Total
Roosevelt Science Building (New Building) Design $132,000 $377,000 2025
2020: AREAC labs Design $2,500 $3,400 2019
Ingersoll Hall Extension Roof Replacement Design $2,011 $3,611 2019
2020: Resiliency Center @ Jamaica Bay Design $2,000 $32,000
Meat Market (Roosevelt Science building) Design $1,200 $1,200 2018
Lab Reno - Ingersoll Hall Geology Lab Design $1,200 $1,200 2019
Aquatics Lab Renovation Design $1,100 $1,100 2018
Campus-wide Fire Protection Design $1,000 $1,200 2018
Chiller Plant Design $800 $3,100 2018
West Quad Air Distribution Design $750 $750 2018
Ingersoll Hall Pump Replacement Design $500 $500 2019
Campus-Wide Cornice Reconstruction Design $500 $500 2018
Whitehead TV Center (Production Lab) - HVAC Design $330 $330 2018$145,891 $425,891Sub-Total
Boiler Replacement Pre-Design $4,255 $22,000 2023
Fire Alarm Rehabilitation at Roosevelt Hall Pre-Design $0 $2,300 2019$4,255 $24,300Sub-Total
Steiner Studios - Equipment for Graduate Film School of Cinema Equipment Purchase
$1,000 $1,000 2018
$1,000 $1,000Sub-Total
27 $341,603Project Count and Funding Total $641,623
21/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Senior Colleges Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
City College
Marshak Science Bldg (HVAC Ph. II & IIIA-C) Construction $71,838 $71,838 2019
NAC Central Chiller Upgrade Construction $33,796 $33,796 2018
NAC Central Plant, Ph 2A and 2B Construction $25,298 $25,298 2018
Shepard Hall Ph 11 & 12 Construction $22,845 $22,845 2017
Steinman/Shepard Elevator Construction $12,100 $12,100 2019
Sophie Davis Interiors (Medical School) Construction $10,250 $10,250 2017
Daycare Center Renovation Construction $7,958 $7,958 2018
NAC Controls Replacement Construction $4,000 $12,000 2019
Shepard Hall Room 350 Renovation Construction $2,800 $2,800 2017
NAC Lib. Active Learning Center Construction $1,124 $1,124 2017
Steinman Hall First Floor Parapet Wall Construction $920 $920 2018
ASRC Interior Renovations Construction $0* $5,000 2019$192,929 $205,929Sub-Total
Library WHCR Cooling Syst Bid $9,200 $9,200 2019
Baskerville Hall Student Clubs and Lecture Hall Bid $5,300 $6,458 2019$14,500 $15,658Sub-Total
Steinman Hall HVAC Design $15,246 $24,000 2019
Marshak Pool and Locker Room Renovation Design $14,000 $14,000 2019
Marshak Plaza Replacement Design $6,137 $23,500 2020
Marshak-Hall-Steinman IT Modernization Design $6,007 $6,007 2019
Campus-Wide Accessibility Design $3,753 $7,253 2019
Firehouse -MFA Renovation Design $3,285 $6,000 2019
Marshak Emergency Generator Design $2,445 $2,445 2019
Lab Reno 2014 (Marshak 503/504, 507/511) Design $2,400 $2,400 2019
Spitzer Fabrication Lab Design $1,000 $1,000 2018
Shepard Hall Rm 15 Design $500 $500 2018
Aronow Theater Renovation Design $339 $4,000 2020
NAC Culinary Art Design $300 $1,500 2019
Wingate Locker Room Project Design $130 $1,100 2019
Shepard Music Library Roof Replacement Design $50 $500 2019$55,592 $94,205Sub-Total
Pre-Design $350 $3,000 2019
Pre-Design $350 $8,000 2020
Pre-Design $350 $350 TBD
Pre-Design $347 $347 TBD
ASRC/CDI Retrocommissioning
Aaron Davis Hall ADA Upgrade and Theater Renovation Shepard 51 Smart Classroom Project
NAC Hurricane Sandy Repairs
NAC Escalators
*Funded through another project.
Pre-Design $300 $2,000 TBD$1,697 $13,697Sub-Total
33 $264,718Project Count and Funding Total $329,489
31/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Senior Colleges Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
College of Staten Island
2M Renovation Construction $19,048 $19,048 2018
Campus Roadway Reconstruction Construction $9,047 $9,047 2018
Site Hardscape Reconstruction Phase 1 Construction $7,652 $7,652 2018
2M Renovation Phase 3 Construction $5,000 $5,000 2018
Oil Tank Replacement at Central Plant Building 1M Construction $4,400 $4,400 2018
6S Chemical Waste Construction $2,900 $2,900 2018
1R Pool Dehumidification and Water Filtration System Construction $2,818 $2,818 2019$50,865 $50,865Sub-Total
IHPCC Electrical Substation Upgrade Design $39,000 $35,000 2020
Interdisciplinary High Performance Computational Center Design $39,000 $274,000 TBD
2020: Big Data Design $7,600 $7,600 2019
1M Cental Htg & Cooling Design $2,660 $2,660 2019
Soccer field improvements Design $1,500 $1,500 2018
Campus-wide Emergency Generator/automatic transfer switch Design $1,050 $1,050 2019
New Garage for vehicle storage Design $700 $700 2019
Media Culture Screening room renovation Design $510 $550 2019$92,020 $323,060Sub-Total
15 $142,885Project Count and Funding Total $373,925
41/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Senior Colleges Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
CUNY Law
Trial Courtroom Pre-Design $1,250 $1,250 2019$1,250 $1,250Sub-Total
Omnia-Media Technology System Equipment Purchase
$0 $1,548 2019
$0 $1,548Sub-Total
2 $1,250Project Count and Funding Total $2,798
51/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Senior Colleges Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
CUNY-Wide Senior
CUNY Data Center Ph. 2 Construction $32,621 $32,621 2018
Water Treatment Pro Construction $2,900 $2,900 2025$35,521 $35,521Sub-Total
Sub-metering: EO-88 Senior Colleges Design $8,988 $8,988 2021
Boiler Reconstruction (CUNY Managed) Design $6,700 $6,700 2025
Boiler Diagnostics Program Design $4,925 $4,925 2022
Solid State Lighting Project Design $4,450 $4,450 2019
Emergency Façade Repair Queens and CCNY Design $3,980 $3,980 2020
PA CCNY, Queens Design $3,300 $3,300 2018
Energy & Greenhouse Design $3,090 $3,090 2025
LL 87/EO 88 Compliance Design $1,685 $1,685 2018
PA Permits Design $1,502 $1,502 2020
Local Law 11 Cycle 8 Design $864 $864 2020$39,484 $39,484Sub-Total
12 $75,005Project Count and Funding Total $75,005
61/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Senior Colleges Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
Graduate Center
Elevator Upgrade Project Construction $3,418 $3,418 2018
Security System Upgrade Construction $1,007 $1,007 2017$4,425 $4,425Sub-Total
Ninth Floor Renovation Design $5,530 $5,530 2019
2020: Big Data Design $4,260 $4,260 2019
VFD Cooling Tower Upgrade Design $2,000 $2,000 2018
Bathroom Upgrades Design $1,000 $1,500 2018$12,790 $13,290Sub-Total
Library Upgrades Pre-Design $500 $500 TBD$500 $500Sub-Total
7 $17,715Project Count and Funding Total $18,215
71/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Senior Colleges Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
Hunter College
North Bldg Roof Construction $8,290 $8,290 2019
North Bldg Elevator Upgrade Construction $6,050 $6,050 2019
Lab Renovations 2014 Construction $5,701 $5,701 2018
North Bldg Boiler Plant Construction $4,551 $4,551 2017
Thomas Hunter Hall 2nd floor Student Union Construction $3,289 $3,300 2019
East Bldg 8th Fl Roof Construction $1,839 $1,839 2018
East Bldg. Leak Construction $420 $420 2018
East/West Bldg. Sump Pumps Construction $350 $350 2018$30,490 $30,501Sub-Total
West Bldg. Plaza Design $2,258 $2,258 2019
Cooperman/Baker Walkway Design $1,245 $1,245 2019
Kaye Playhouse Entrance Design $1,176 $1,176 2019
North and West Bldg. Acid Neutralization Design $650 $650 2019
North Bldg. Stairwell Doors Design $537 $537 2019
West 8th floor Terrace Fence Design $400 $400 2019
West Bldg. Hot Water Heaters Replacement Design $300 $300 2019$6,566 $6,566Sub-Total
Thomas Hunter HVAC Pre-Design $8,700 $17,000 2020
MFA Visual&Perform Arts, Ph1 Pre-Design $6,000 $6,000 2020
Emergency Generator Upgrades Pre-Design $1,000 $1,000 2019
North Bldg. Facade and Window Replacement Pre-Design $1,000 $1,000 2020
Various Mechanical Work in the North Bldg. Pre-Design $750 $750 2018
Kaye Playhouse Dehumidification and HVAC Upgrades Pre-Design $400 $400 2020
THH Bathroom Upgrades Pre-Design $300 $300$18,150 $26,450Sub-Total
Roosevelt House HVAC Upgrade Equipment Purchase
$499 $499 2019
North Bldg.Gas Detection Equipment Purchase
$70 $110 2018
$569 $609Sub-Total
24 $55,775Project Count and Funding Total $64,126
81/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Senior Colleges Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
John Jay College of Criminal Justice
Haaren Hall Façade Restoration Project Construction $15,238 $15,800 2019
Haaren Hall – Swimming Pool/ Natatorium Rehabilitation Construction $8,300 $8,500 2019
ADA Upgrades Construction $850 $650 2018
New Building Vending Alcove Conversion Construction $250 $250 2018
Haaren Hall Library Rehabilitation Construction $215 $550 2018$24,853 $25,750Sub-Total
Haaren Hall Toilet Renovation Design $4,000 $4,200 2019
Haaren Athletic Facility Design $3,700 $4,800 2021
Haare Hall Lighting Upgrades Design $2,193 $0 2019
Campus Door Upgrages Design $1,000 $0 2019
PH II Retro-Commissioning Design $450 $150 2017$11,343 $9,150Sub-Total
Library Renovation Pre-Design $10,913 $50,000 2021$10,913 $50,000Sub-Total
11 $47,109Project Count and Funding Total $84,900
91/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Senior Colleges Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
Lehman College
Utilities Plant Expansion Construction $42,000 $42,000 2017
Fire Alarm/Security Construction $21,870 $21,870 2011
Concert Hall Addition and ADA Construction $15,316 $15,316 2019
APEX Bird Proofing Construction $7,742 $7,000 2018
Bookstore Relocation Construction $4,252 $4,252 2019
Gillet & Davis Halls Façade Renovation Construction $3,963 $3,500 2017
Elevator Upgrade Ph II (APEX, Old Gym, Fine Arts, Music) Construction $2,850 $2,500 2017
Old Gym Roofs Construction $1,300 $1,000 2018
Standpipe Inspection Construction $500 $500 2018$99,793 $97,938Sub-Total
College Labs Round III Bid $6,927 $6,927 2019$6,927 $6,927Sub-Total
Nursing Education, Research and Practice Center Design $53,150 $61,000 2021
Library Ventilation and Renovation Design $17,900 $17,900 2019
Oil Tank Room and Music Plaza Renovation Design $11,000 $11,000 2019
Dept. Social Work Design $4,811 $4,811 2020
Teaching and Learning Commons Design $3,670 $4,500 2020
Emergency Power Network Design $2,836 $3,000 2020
S&T Amphitheater Design $2,762 $3,000 2019
Lovinger Theater ADA Design $2,504 $2,504 2020
Music Building Chimney Design $1,500 $1,500 2019
Shuster Hall and Fine Arts Envelope Design $1,013 $6,000 2022
Science Hall Greenhouse Truss Replacement Design $928 $0 2018
Hub Rooms HVAC Design $750 $750 2019
Library Windows Replace Design $700 $550 2018
2020: New Media Job Incubator Design $30 $1,700 2019$103,554 $118,215Sub-Total
24 $210,274Project Count and Funding Total $223,080
101/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Senior Colleges Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
Macaulay Honors College
Replace HVAC Construction $4,400 $4,216 2018$4,400 $4,216Sub-Total
Server Room HVAC Upgrade Design $605 $450 2019
2020: New Media Jobs Incubator Design $30 $5,500 2020$635 $5,950Sub-Total
Fire Alarm Replacement Pre-Design $412 $412 2018$412 $412Sub-Total
4 $5,447Project Count and Funding Total $10,578
111/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Senior Colleges Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
Medgar Evers College
AB1 + Bedford Heating Cooling Cross Connection Construction $19,000 $17,305 2018
Campus Wide Security Upgrade Construction $2,496 $2,764 2018
Carroll St. Façade Repairs & Site Work, Ph II Construction $1,325 $1,035 2018$22,821 $21,104Sub-Total
Bedford Building - Lobby Reconstructions Bid $5,391 $7,400 2019$5,391 $7,400Sub-Total
Carroll St. Building Egress and ADA Design $8,000 $8,000 2019
Carroll St. Athletic Cntr Upgrades & ADA Bathrooms Design $7,435 $7,435 2019
Bedford Avenue Building- Site Reconstruction Site Work. Design $6,800 $5,200 2018
Carroll St. Fire Alarm and Egress Design $3,280 $1,369 2018
Carroll Street Building Energy Upgrade Phase 1 Design $2,750 $34,000 2018
AB1 SSB Energy Reconstruction Project Design $1,000 $700 2019
Bedford Building Roofing Reconstruction Design $300 $2,200 2019$29,565 $58,904Sub-Total
Master Plan Pre-Design $300 $300 2017$300 $300Sub-Total
12 $58,077Project Count and Funding Total $87,708
121/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Senior Colleges Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
New York City College of Technology
Academic Bldg. 1 Construction $410,000 $410,000 2018
Allied Health (Pearl St) 1st Fl Reno Construction $14,252 $15,852 2018
Voorhees Hall Interior Reno & Exterior Site Improvements Construction $3,900 $3,900 2018
Campus-wide Roof and Plaza Replacement Construction $3,856 $3,830 2018
Misc. Campus-wide MEP Upgrades Construction $780 $575 2018$432,788 $434,157Sub-Total
Installation of Permanent Piping for Temp. Boilers in Namm Hall Bid $475 $1,200 2018$475 $1,200Sub-Total
Voorhees MEP Upgrade Design $24,200 $28,900 2018
Namm Hall Vestibule Renovation Design $6,250 $6,089 2019
Campus-wide Elevator Modernization Design $4,100 $4,100 2019
Replace 5 Existing Air Units Design $3,950 $3,700 2018
Namm Hall Loading Dock Renovations Design $3,427 $2,465 2019
Lab Renovations (Namm & E Bldg) Design $475 $2,500 2018$42,402 $47,754Sub-Total
Namm Hall Replacement of Cooling Systems in Server Rooms Pre-Design $1,250 $1,250 2019
Allied Health Building Renovations Pre-Design $1,185 $1,185 2018
Allied Health Building Electrical Upgrades Pre-Design $313 $49 2019
Voorhees Hall 3rd Floor Renovation Pre-Design $275 $15,000 2018$3,023 $17,484Sub-Total
16 $478,688Project Count and Funding Total $500,595
131/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Senior Colleges Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
Queens College
Campus Chiller Plant, Phase I Construction $31,811 $29,350 2018
Louis Armstrong Education Center Construction $23,900 $25,000 2019
Kiely Hall Energy Reconstruction, Phase I Construction $15,539 $15,500 2018$71,250 $69,850Sub-Total
Gym Roof Replacement Bid $12,075 $12,000 2020
Storm Damage Restoration (Kupferberg Roof Railings) Bid $650 $650 2018$12,725 $12,650Sub-Total
Central Chiller Plant Phase 2 Design $11,780 $23,240 2019
Steamline Distribution Reconstruction Design $6,317 $5,383 2019
Boiler Plant Reconstruction Phase 1 Design $5,000 $5,000 2019
Campus Wide Fire Alarm Project Ph 2 Design $5,000 $22,000 2022
Powdermaker Hall Lighting Upgrade Design $4,450 $4,450 2021
Gertz Hall Speech Hearing Learning Design $4,390 $4,390 2019
Razran Lab Renovations (Razran 4 Labs) Design $4,265 $4,265 2019
Local Law 11: Kiely and Rosenthal Design $3,100 $3,083 2019
Sci Labs 2015 (Avella) Renovation Design $2,000 $2,000 2019
Outdoor Athletic Facility Reconstruction Design $1,500 $7,200 2019
Perimeter Sidewalk Reconstruction Design $1,000 $1,000 2019
Perimeter Fence Design $950 $950 2020
CUNY- wide Public Assembly Project Design $671 $671 2019
Gym Sills & Façade Reconstruction Design $480 $1,230 2020
Campuswide Security Camera Project Design $400 $400 2019
Behavioural Neuroscience and Molecular Cellular Design $372 $2,784 2020
IT Bldg/Dining Hall Roofing Reconstruction Design $350 $2,000 2019
Rosenthal Library Renovation, Phase II Design $266 $2,000 2019
Environmental Labs Renovation Design $242 $2,000 2019
Gym Pool Filtration System Reconstruction Design $230 $1,100 2019$52,763 $95,146Sub-Total
One Stop Student Services Center Pre-Design $12,000 $15,200 TBD
ADA Bathroom Upgrade Phase 2 Pre-Design $108 $1,200 2020$12,108 $16,400Sub-Total
27 $148,846Project Count and Funding Total $194,046
141/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Senior Colleges Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
School of Professional Studies
31 Street Lobby Expansion Construction $250 $250 2018
IT Center HVAC Modifications Construction $75 $75 2018$325 $325Sub-Total
2 $325Project Count and Funding Total $325
151/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Senior Colleges Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
York College
Computer & Multimedia (Faculty Dining Room) Construction $1,883 $1,883 2019
Sci Bldg FA Upgrade Construction $250 $250 2019
Academic Core Water Main Leak Construction $193 $193 2017$2,326 $2,326Sub-Total
Campus Wide Escalators and Elevator Upgrades Bid $14,803 $14,803 2019$14,803 $14,803Sub-Total
Academic Village & Conference Cntr Design $41,000 $287,000
Groundwater Infiltration at Academic Core Design $13,097 $13,097 2018
BMS Controls Upgrade Design $10,731 $10,731 2020
Campus Wide MEP Upgrades Design $8,820 $8,820 2019
PAC Renovations/Upgrade/Improvements Design $7,734 $7,734 2021
Track & Field Upgrade Design $7,225 $12,800 2020
PAC Roof Upgrades and Facade Repairs Design $4,049 $5,000 2020
PAC- Various Interior Upgrades (Design) Design $4,000 $4,000 2021
Chemistry and Biology Lab Renovations Design $3,046 $3,046 2019
Ac Core Lecture Hall Upgrade Design $2,765 $2,765 2020
Ac Core Building Entrance Door Restoration Design $2,000 $2,000 2019
Replacement of Pool Dehumidification Unit Pool Pak Design $1,500 $2,200 2019
Campus Wide A/C IT Closets Design $1,000 $1,000 2019$106,967 $360,193Sub-Total
Ac Core Building Roof Pre-Design $1,000 $1,000 2020
Bathroom Upgrades Pre-Design $500 $500
PAC Passenger Elevator Expansion Pre-Design $500 $1,300 2020
Fuel Oil Tank Pre-Design $400 $0 2018$2,400 $2,800Sub-Total
21 $126,496Project Count and Funding Total $380,122
161/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Senior Colleges Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
260Senior CollegeProject Count and Funding Total $2,128,552 $3,155,107
171/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Community College Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
BMCC
HVAC and Controls Upgrade Construction $22,095 $22,095 2018
ADA Bathrooms Upgrades Ph. II Construction $16,328 $16,328 2019
Roof Replacement and Photovoltaic Installation Construction $12,000 $12,000 2018
Pool Deck Restoration Construction $11,500 $11,500 2018
Emergency Generator Construction $7,400 $7,400 2018
ADA Bathrooms Upgrades Ph. I Construction $6,300 $16,328 2017
Façade Restoration & Ancillary Exterior Improvements Construction $5,687 $5,687 2018
Gym HVAC Upgrade Construction $3,000 $2,900 2018
Chamber St. Hurricane Sandy - North & South Feeders Construction $2,750 $2,750 2018
West Street Façade Windows Construction $800 $800 2018$87,860 $97,788Sub-Total
Chambers St. Ramp & Plaza Paver Replacement Bid $9,121 $11,900 2019
70 Murray Street, Seond and Third Floor Expansion Bid $0 $0 2018$9,121 $11,900Sub-Total
Student Commons Expansion Design $11,000 $11,000 TBD
Theatres 1, 2 and 3 Upgrades Design $3,042 $3,042 TBD
Battery Interconnect Design $300 $600 2018$14,342 $14,642Sub-Total
Gym LED Lighting Pre-Design $249 $249 2019
Cooling Tower Replacement Pre-Design $0 $3,600 2019$249 $3,849Sub-Total
17 $111,572Project Count and Funding Total $128,179
11/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Community College Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
Bronx Community College
Campus Utility Upgrade, Phase IV Distribution Construction $27,000 $27,000 2018
Fire Alarms - Meister GML CPH & New Halls Construction $4,995 $4,995 2018
Alumni Gym Pool Rehabilitation Construction $4,846 $4,113 2018
Havemeyer Roof Construction $2,160 $2,160 2018
New Hall Roof - Upper Roof Replacement Construction $500 $500 2018$39,501 $38,768Sub-Total
Student Center Roof Replacement & Façade Repair Bid $4,900 $5,374 2018
New Hall Data Center Air Conditioning Bid $700 $700 2019
Alumni Gym Bridge Replacement Bid $618 $618 2018
Dominican Veterans Memorial fka Monument Hill Bid $295 $295 2017$6,513 $6,987Sub-Total
Campus Utility Upgrade, Phase V Electric Design $69,632 $69,632 2021
2020: Automotive & Fuel Technology Design $9,000 $9,000 2020
Gould Memorial Library Dome Roof & Oculus Design $5,320 $11,600 2020
Gould Memorial Library Egress Stairs Design $855 $855 2019
Community Hall LL11 Design $250 $1,500 2018
Snow Hall Elevator Design $210 $1,700 2020
Ohio Field Track Restoration Design $150 $2,500 2019
Nichols Hall ADA Entrance Ramp Design $87 $512 2019
Bliss ADA Restrooms & Entrance Ramp Design $80 $680 2019
Alumni Gym Locker Room Restrooms Design $67 $567 2019$85,651 $98,546Sub-Total
New Hall Roof - Plaza & Facade Pre-Design $3,000 $3,000 2020
Loew Hall Accessibility & Elevator Pre-Design $113 $900 2019
Bronx Express, aka Student Success Center Pre-Design $100 $14,170 2021$3,213 $18,070Sub-Total
22 $134,878Project Count and Funding Total $162,371
21/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Community College Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
CUNY-Wide Community
CC Solid State Lighting Pre-Design $528 $528 2025
CUNY LL87 Compliance (Retrocommissioning) Pre-Design $300 $300 2025
Boiler Reconstruction (CUNY Managed) Pre-Design $68 $68 2025
CC Water Treatment Program Pre-Design $0 $0 2025$896 $896Sub-Total
4 $896Project Count and Funding Total $896
31/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Community College Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
Guttman Community College
North Hall Condition Assessment and Programming Study Pre-Design $1,898 $1,898 2018$1,898 $1,898Sub-Total
1 $1,898Project Count and Funding Total $1,898
41/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Community College Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
Hostos Community College
VFD Installation Construction $2,257 $2,257 2017
Savoy Manor Roof Construction $1,800 $1,800 2017
450 GC FA Upgrade Construction $650 $650 2018$4,707 $4,707Sub-Total
500 GC Window Replacement Bid $6,000 $6,000 2019
500 GC Emergency Generator and Sub-Cellar Renovation Bid $5,900 $5,900 2018$11,900 $11,900Sub-Total
New Allied Health & Science Building Complex Design $2,000 $239,000 TBD
500 GC 3rd Floor Renovation Design $850 $12,000 2019
HVAC Upgrade 475 GC and Admin Bldg Design $800 $2,800 2019
475 GC Replacement of (9) Air Handling Units Design $250 $6,450 2018
300-Ton Chiller Replacement at 475 Grand Concourse Design $245 $3,245 2018
Summer Boiler Design $237 $237 2018$4,382 $263,732Sub-Total
Retaining Wall Pre-Design $30 $2,000 TBD$30 $2,000Sub-Total
12 $21,019Project Count and Funding Total $282,339
51/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Community College Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
Hunter College Campus Schools
HVAC & Boiler Upgrade Bid $12,565 $12,565 2019$12,565 $12,565Sub-Total
Athletic Facilities Renovation Design $1,333 $1,629 2019$1,333 $1,629Sub-Total
2 $13,898Project Count and Funding Total $14,194
61/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Community College Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
Kingsborough Community College
LED Lighting Conversion Bid $3,369 $6,500 2019
Fire Alarms U & P Building Bid $2,998 $2,998 2018
Student Conference Ctr Bid $2,491 $2,900 2019$8,858 $12,398Sub-Total
T7 Ph 1 Electrical and HVAC Design $3,298 $3,298 2018
Bursar Renovation Design $1,581 $1,581 2019
T4 Roof Replacement Design $1,233 $3,000 2019
KGBCC Performing Arts Design $1,138 $14,900 2019
Storm Sandy HVAC T2,T3,T4 Buildings Design $1,068 $1,368 2019
Marina Rehabilitation Design $600 $9,800 2019
West Academic Cluster Setback Roof Replacement Design $0 $350 2019$8,918 $34,297Sub-Total
Pool Renovation Pre-Design $810 $5,000 2020
Physical Sciences Equipment Pre-Design $0 $227 2019
Library Roof Partial Replacement Pre-Design $0 $1,100 2020
Gas Booster Pump Upgrade Pre-Design $0 $252 2019$810 $6,579Sub-Total
14 $18,586Project Count and Funding Total $53,274
71/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Community College Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
LaGuardia Community College
Center 3 Façade Construction $116,000 $116,000 2018
2020: Goldman Sachs 10,000 Small Businesses Ed Cntr Construction $5,000 $5,000 2018
Building E Fire Alarm Construction $3,461 $3,414 2018$124,461 $124,414Sub-Total
Business, Entrepreneurial & Career Center Design $1,220 $15,074 2021
Library Expansion and Renovation Phase II Design $1,185 $6,000 2020
Boiler & Chiller Centralization Design $650 $8,880 2020
E Building Roof Replacement Design $483 $5,300 2019
Fire Alarm replacement in Shenker Hall Design $0 $4,500 2019$3,538 $39,754Sub-Total
Center 3 Infrastructure Pre-Design $3,172 $30,000 2022$3,172 $30,000Sub-Total
9 $131,171Project Count and Funding Total $194,168
81/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Community College Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
Queensborough Community College
Campus-Wide Electrical Reconstruction Construction $42,100 $37,733 2018
Medical Arts, Science and Admin Bldgs - Roof Replacements Construction $8,900 $7,725 2018$51,000 $45,458Sub-Total
Humanities Building - Performing Arts Center Upgrades Bid $9,500 $9,500 2019
Medical Arts Bldg Sprinkler/Standpipe Bid $2,300 $1,300 2018$11,800 $10,800Sub-Total
Central Plant Chiller Reconstruction - Phase II Design $21,164 $21,164 2018
Cafeteria and Kitchen - Phase II Design $9,500 $9,034 2019
Lab Renovations Design $316 $3,100 2019$30,980 $33,298Sub-Total
Ph II Fire Alarm Pre-Design $2,928 $2,652 2018
W Building- ASAP Expansion Pre-Design $366 $2,990 2019$3,294 $5,642Sub-Total
9 $97,074Project Count and Funding Total $95,198
91/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.
Phase
Community College Active Projects
Funded Budget
Anticipated Project Cost
Anticipated Year of Project
Completion(in thousands)
90 $530,992 $932,517Community Colleges Project Count and Funding Total
101/24/2018 Office of Facilities Planning, Construction and Management
The projects listed in this report are active FPCM projects. Projects recently completed, under consideration, without CPs,on-hold, and projects managed by the campuses are not included in this report.