Senior Design
1University of Portland School of Engineering
Team Without LimitsSelf-Ordering Bocce Balls
• Team– Michael Chhor– Sean Pfister– Allan Young– Brent Groulik
AdvisorDr. Joseph Hoffbeck
Industry RepresentativeN/A
Senior Design
2University of Portland School of Engineering
Introduction
Pallino Bocce Ball Handheld Device
Sense SenseProcess Process Actuate
Our project automatically orders Bocce balls with respect to their relative proximity to the Pallino. This will eliminate the need for the players to physically determine the order of the balls.
Senior Design
3University of Portland School of Engineering
Scorecard
• Enjoyed Christmas Break• Continued working when we returned
Senior Design
4University of Portland School of Engineering
Additional Accomplishments
• Sent and sensed a wireless RF signal• Hooked up mounted acoustic sensors• Continued to update website
– Pictures and videos
• Ordered more parts – Acoustic transmitter pair– Logic shift chips (steps down voltage PIC ->
XBee)
Senior Design
5
Recent Pictures
University of Portland School of Engineering
1 Hz Circuit
Wired RF Connection
Senior Design
6
Videos
http://teaching.up.edu/srdesign/AY12/WithoutLimits/photos.htm
University of Portland School of Engineering
Senior Design
7University of Portland School of Engineering
Plans
• Test acoustic receivers and transmitters• Interface acoustic system with RF stystem• Ordered more PICs, build more boards
Senior Design
8University of Portland School of Engineering
Milestones (Recent past and near future)
Status Description OriginalTarget
PreviousTarget
PresentTarget
Completed RF Modules Purchased 5 Nov 11 5 Nov 11 5 Nov 11
Completed Design Document 0.9v 12 Nov 11 12 Nov 11 12 Nov 11
Completed Final Budget 12 Nov 11 12 Nov 11 12 Nov 11
Completed Design Document 1.0v 19 Nov 11 19 Nov 11 19 Nov 11
Completed Selection of Acoustic Modules
14 Oct 11 14 Oct 11 5 Nov11
Completed RF to PIC Interfaced 26 Nov 26 Nov 11 6 Feb 12
Completed November Program Review 2 Dec 11 2 Dec 11 2 Dec 11
Completed Peer Evaluations/ Lab Notebooks 5 Dec 11 5 Dec 11 5 Dec 11
On Track January Program Review 27 Jan 12 27 Jan 12 27 Jan 12
Hopeful Acoustic Receiver to PIC 3 Feb 12 3 Feb 12 3 Feb 12
On Track BBR Receives Acoustic 6 Feb 12 6 Feb 12 6 Feb 12
Very Wishful BBR sends and receives 13 Feb 12 13 Feb 12 13 Feb 12
Senior Design
9University of Portland School of Engineering
Concerns/Issues
• 741 Op Amps might not have enough current to power speaker
• Interfacing acoustic receiver to PIC