Senior Design, Spring 2013 DEC13-03: ISU Substation Jane Peters Riley Groves Jared Jasper Matt Murphy Muzi Li

Senior Design, Spring 2013 Jane Peters Riley Groves Jared Jasper Matt Murphy Muzi Li

Embed Size (px)

Citation preview

Page 1: Senior Design, Spring 2013 Jane Peters Riley Groves Jared Jasper Matt Murphy Muzi Li

Senior Design, Spring 2013

DEC13-03: ISU Substation

Jane Peters

Riley Groves

Jared Jasper

Matt Murphy

Muzi Li

Page 2: Senior Design, Spring 2013 Jane Peters Riley Groves Jared Jasper Matt Murphy Muzi Li

Project Description

TASK: Design a new 115kV substation (switchyard) to service ISU

– Voltage Level Transformations– Inter-system communication with other

substations (OUTSIDE SCOPE)– Regional transmission line connection– System health monitoring capabilities– System protection

DEC13-03: ISU Substation

Page 3: Senior Design, Spring 2013 Jane Peters Riley Groves Jared Jasper Matt Murphy Muzi Li

Scope of Services/Deliverables

DEC13-03: ISU Substation

• Physical Campus Layout• Foundation Layout• One-line Diagram• Three-line Diagram• Bus and Insulator Sizing • Grounding grid design• Component Raceway

Design

• Transformer Design• 125VDC System Battery

Design• Relay Design• Control System Design• Control House Layout• Control House Service

NOT INCLUDED: System Simulation and Transformer Design

Page 4: Senior Design, Spring 2013 Jane Peters Riley Groves Jared Jasper Matt Murphy Muzi Li

Project Requirements

DEC13-03: ISU Substation

• Design services– Layout will allow for future expansion– 125 Volt Station Battery supply for station service outage– Fiber-Optics communication between substations – The substation be designed with Iowa weather in mind

• Safety– Clearance for emergency vehicles – Clearance for removal of defective parts– Ground grid capable of handling a fault

• Follow industry and company standards

Page 5: Senior Design, Spring 2013 Jane Peters Riley Groves Jared Jasper Matt Murphy Muzi Li

CONSTRAINTS

• Burns & McDonnell expectations

• Standards– Industry Specific– Component Specific– Environmental Specific

• Hierarchy of development dependency

RISKS

• Hierarchy of development dependency

• Learning curve• Design validation

DEC13-03: ISU Substation

Project Constraints & Risks

Page 6: Senior Design, Spring 2013 Jane Peters Riley Groves Jared Jasper Matt Murphy Muzi Li

Project Schedule

DEC13-03: ISU Substation

SPRING

• Design Document and Project Plan

• One-line Diagram• Three-line

Diagram• Physical Campus

Layout• Elevation

Drawings

SUMMER FALL

• System load calculation

• Grounding Grid Design

• Foundation Layout

• Bus and Insulator Sizing Design

• Service Station Transformer Design

• Raceway Design• Control House

Design• Station Battery

Design• Relay Panel

Wiring

Page 7: Senior Design, Spring 2013 Jane Peters Riley Groves Jared Jasper Matt Murphy Muzi Li

Project Resources

DEC13-03: ISU Substation

• Software Tools– AutoCAD– WinIGS

• Design Resources– Burns and McDonnell design team– Industry design standards– External Reference material

Page 8: Senior Design, Spring 2013 Jane Peters Riley Groves Jared Jasper Matt Murphy Muzi Li

Project Verification

DEC13-03: ISU Substation

• Campus Resources– Dr. Ajjarapu– Dr. Christy– Weekly progress review meetings

• Burns and McDonnell Design Team– Bi-monthly design review meetings

Page 9: Senior Design, Spring 2013 Jane Peters Riley Groves Jared Jasper Matt Murphy Muzi Li

Project Status

DEC13-03: ISU Substation

• Deliverable Requirements

• One/Three Line Diagram

• Foundation Design

• Substation Layout

• Bus and Insulator Sizing Design

• Ground Grid

• Station Service Transformer

• Raceway

• Control Building

• 125V DC Station Battery Design

• Relaying and Controls

• Design Resources

2/18/2013

4/1/2013

4/1/2013

Page 10: Senior Design, Spring 2013 Jane Peters Riley Groves Jared Jasper Matt Murphy Muzi Li

Acknowledgements

DEC13-03: ISU Substation

In conclusion, we would like to extend a, “thank you”, to the following resources for their help throughout this project:• Brad Jensen and Nathan Schares, Burns and

McDonnell• Dr. Ajjarapu, Dr. Christy and Jason Boyd, Iowa

State University• P. Meliopoulos, Georgia Institute of Technology

Page 11: Senior Design, Spring 2013 Jane Peters Riley Groves Jared Jasper Matt Murphy Muzi Li

Team Breakdown

DEC13-03: ISU Substation

• Jane Peters (Team Leader)– project documents, one-line, control building, three-line, section cuts,

relay wiring

• Jared Jasper (Team Webmaster)– website maintenance, site design, grounding layout, section cuts

• Riley Groves (Communications Coordinator)– one-line, three-line, client communications, raceway, grounding layout,

relay wiring

• Matt Murphy (Grounding Expert)– one-line, three-line, raceway, grounding, control building, bus and

insulator sizing

• Muzi Li (Layout Expert)– foundation design, grounding layout, site design, bus and insulator sizing

Page 12: Senior Design, Spring 2013 Jane Peters Riley Groves Jared Jasper Matt Murphy Muzi Li

One Line DiagramOne Line Diagram