Bond, Facility Planning and Construction DepartmentSeptember 2019
1
Project Status Update - September 2019
2
SITE PROJECT TYPE STATUS
CONSTRUCTION
Wilson ES Campus Replacement Bond Under Construction
Crespi MS Gym Seismic Retrofit Bond Under Construction
Fairmont ES Critical Needs, Phase 1 Bond Under Construction
Pinole Valley HS Replacement Campus Bond Punchlist work
Vista HS North Campus Relocation Non-Bond Under Construction
PROCUREMENT
Riverside ES Critical Needs (Soils Stabilization) Bond Request for Proposals procurement
Fairmont ES Campus Expansion Non-Bond Bids received
Montalvin ES K-8 Expansion Non-Bond Bidding
DESIGN
Highland ES Critical Needs Bond Assessing Water & Power Upgrades
Richmond HS Critical Needs Bond Increment 2 & 3 pending DSA Approval
Pinole Valley HS Fields Restoration & Site Work Bond Design Development
Pinole Valley HS Solar Non-Bond Planning
Lake ES Campus Replacement Bond Planning
Stege ES Critical Needs Bond Hold-Pending Program Redesign
Korematsu MS Fall Protection Bond Hold
Wilson Elementary School Groundbreaking
3Student speaker
PTA President Maisha Simmons-Cole (left), Principal Claudia Velez (center) and Assistant Principal Amanda Henderson (right)
Students participating in the turning of the soil
Fifth and sixth grade intermediate band ceremony performance
Wilson Elementary Campus Replacement
4Admin footing rebar Main electrical conduits
Crespi Elementary Gym Seismic Retrofit
5
Gym footing rebar Shear wall concrete
Newsletters
6
Wilson Elementary School Richmond High School
Notes:
○ Chavez ES - Project no longer feasible. Board approved the remaining budget to return to fund balance on 06/26/19
○ Lake ES - Board approved $1M of $65.5M from existing project budget for initial planning and design on 06/26/19.
○ Wilson ES - Board approved supplemental funds of $1.75M from Developer Fee and $0.85M from MRAD due to anticipated cost of conversion Temp Campus. The total Wilson Campus Replacement project budget is $42.9M
FMP Budget - September 2019
7
8
State Funding Updates - September 2019
Note: OPSC (Office of Public School Construction) Submitted Applications amount and fund release is subject to revision.
$184.5 M School Facility Program Funding Received to Date
Expected State Funding as of September 2019
School Funding OPSC Status SAB Approval Fund Release Amount
Pinole Valley HS Modernization Under Review 08/28/19 Est: Jul-20 $23,400,090
Helms MS Modernization On Workload List Est: 01/23-06/23 Est: Jul-23 $4,133,414
Crespi Modernization On Workload List Est: 07/23-12/23 Est: Feb-24 $3,482,164
Total Expected State Funding $31,015,668