3 3 Nodal Status Report - Project UpdatesSeptember 22, 2008 NMMS Project Update
Citation preview
September 22, 2008TPTF
Nodal Status Report:Project Status Updates
Nodal Project Managers
2Nodal Status Report - Project UpdatesSeptember 22, 2008 2
Agenda
• NMMS• EMS• MMS• CRR• COMS• EIP (Integration) • INT (Testing)
3Nodal Status Report - Project UpdatesSeptember 22, 2008 3
NMMS Project Update
4Nodal Status Report - Project UpdatesSeptember 22, 2008 4
NMMS Update
• Testing on NMMS 4 FAT is on hold– 8 Outstanding Sev 1/Sev 2 defects– Fixes from Siemens ready, but patch would delay Oct. release would
slip– ERCOT and Siemens agreed to put testing on-hold and then validate
fixes during NMMS 5 pre-FAT
• Began Pre-FAT at Siemens for NMMS 5 – Scheduled Sept. 15 through Sept. 26 – Testing NMMS 5 functionality– Testing outstanding Sev 1/Sev 2 defects
• Identifying v1.21 schema changes and conducting cross-vendor discussion to ensure agreement on implementation
• Continuing validation rules implementation
5Nodal Status Report - Project UpdatesSeptember 22, 2008 5
EMS Project Update
6Nodal Status Report - Project UpdatesSeptember 22, 2008 6
EMS Update
• EMS CIM Importer– Restarted EMS CIM Importer Pre-FAT at ERCOT on Sept. 15 and
testing is in progress. Plan to complete the formal tests by Sept. 26 or earlier
– Known data issues are resolved
• EMS Software Upcoming Releases– EMS 5.1.5 for Outage Evaluation (OE), Voltage Support, etc. has
finished execution of planned FAT test scripts. Release is held up by several OE-specific defects – new target Sept. 26 FAT for sign-off
– EMS 5.1.7 Habitat 5.1.7 released to ERCOT several months ago, awaiting an opportunity to place in ERCOT FAT
– EMS 5.1.8 EMS CIM Importer – Pre-FAT is in progress
7Nodal Status Report - Project UpdatesSeptember 22, 2008 7
MMS Project Update
8Nodal Status Report - Project UpdatesSeptember 22, 2008 8
MMS Update
• MMS Processes & Procedures (DAM, RUC, Adjustment Period and Real-time)– MMS and MOS team members are leading the development of these documents – Process reviews with the for DAM & RUC are complete– Process reviews for adjustment period and real-time will be presented during
September and October TPTF meetings
• Software Releases– MMS 4
• Complete patch 2 FAT testing on Aug. 26• Started patch 3 FAT testing on Aug. 26• Patch 4 delivered to ERCOT on Aug. 27 (originally targeted for Aug. 31)
– Will use same CIM XML test data set as patch 2 and 3– Focused mainly on outstanding defects; smoke testing in progress; will be moved to MMS FAT
after the completion of MMS3 patch 3 FAT • MMS4 patch 5 is targeted for delivery on Sept. 30
– Targeted to include Settlements and Billing defects, interface updates, and additional work-flow development and testing with the most recent CIM schema and CIM XML test data set
– Will use v1.20 of the CIM schema and a corresponding CIM XML test data set
9Nodal Status Report - Project UpdatesSeptember 22, 2008 9
MMS Update – 2
• Software Releases (continued)– MMS 5
• No change to previous MMS5 update; remains the last scheduled MMS software release
• This release will be comprised of the following:– CIM XML import processing and testing end-to-end (defined in last
bullet in this section)– Bug fixes identified to ABB during testing– Remaining work on NPRRs (e.g., NPRR113)– Remaining SIG paper work (e.g., rounding)– Remaining software implementation changes based on testing (e.g.,
performance improvements, startup cost eligibility, SASM constraint modeling)
• Trigger start for MMS5 is a CIM schema and CIM XML data file validated and synchronized for consumption by downstream systems (e.g., EMS, MMS)
10Nodal Status Report - Project UpdatesSeptember 22, 2008 10
CRR Project Update
11Nodal Status Report - Project UpdatesSeptember 22, 2008 11
CRR Update
• Submitted Change Request for the CRR Network Model One Line Diagram to EMS for completion of cost and schedule information. Once completed, next step is submission to the Change Control Board
• Start of CRR Enhancement Release 1.06 is planned for Sept. 19 – SMEs will test revised propagation of CRR Account Holder name changes within the CRR application
• Obtained approval from the Change Control Board to add CRR to the MOTE environment
12Nodal Status Report - Project UpdatesSeptember 22, 2008 12
COMS Project Update
13Nodal Status Report - Project UpdatesSeptember 22, 2008 13
COMS Update
• Settlements/Data Agg/CSI – Product Testing at ERCOT – Development
• Settlements and Billing/Data Agg: Completed over 97% of nodal coding and functionally verified. Outstanding code (to date):
– Data Agg: Reworking recent memory footprint release from Oracle into core code and regression testing
– Internal/External Source Reports for Data Agg, Settlements, and CODIA• CSI: Completed over 94% of Lodestar Bill Determinants and verified
– Testing• Continue to test core system with upstream system changes • Continue to optimize batch cycles
– Major issues• Currently reworking the memory footprint functions into base code (added a
final regression to schedule) • Need synchronous dataset from market systems (NMMS/EMS/MMS/CRR)
running in an integrated environment before market level validation can begin (required for post Shadow Settlement Extracts)
14Nodal Status Report - Project UpdatesSeptember 22, 2008 14
COMS Update – 2
• Registration and Disputes – Migrating to Integration Test – Registration 4 Release integration test scheduled for completion Dec. 5– Registration 4 Release includes:
• Siebel changes for nodal (defect fixes)• Siebel to Lodestar interface (upgrade/change from zonal)• Lodestar to Siebel Dispute Date Look-Up
– Major Issue• Integration rework completed Zonal/Nodal cross impact created delay for Disputes
API. Disputes API now targeted for January 2009 production delivery
• Credit Monitoring and Management – FAT Testing – Build 3.1 (Vendor developed interfaces) in FAT 100% Complete– Build 3.2 (Settlement and Billing / Commercial System Integrated Releases) in
development targeting October 2008 delivery to FAT– Major Issues/Risks
• Finalizing detailed analysis and design of internal UI and reporting. Any changes from upstream systems, NPRRs or change controls have potential to impact schedule
15Nodal Status Report - Project UpdatesSeptember 22, 2008 15
Integration (EIP) Project Update
16Nodal Status Report - Project UpdatesSeptember 22, 2008 16
EIP Update
• External interfaces (web services)– Web Services for External Interface Specification v1.16 deployed to the
Sandbox– Developer Workshop on Sept. 3 was a success with over 60 attendees– Plan to bring v1.16 to TPTF for final review and approval; it has already
been reviewed by the API Subgroup
• Internal Interfaces– A significant release completed week of Sept. 15, with the following
deployments to Integrated Release 2 and Zonal iTest• Platts – MMS • CRR – MMS • CMM – MMS • REG – MMS • Adapters for Web services (v1.15)• REG – S&B• CRR – CMM • CMM – CRR
17Nodal Status Report - Project UpdatesSeptember 22, 2008 17
EIP Update – 2
• ERCOT is merging the Application Program Interface (API) Subgroup meetings into the Friday morning EDS 3 Market Call meetings– The last API Subgroup meeting will be held on Sept. 23; thereafter, the
topic will be covered on the EDS call– All questions or feedback to ERCOT regarding documentation should be
sent to the EDS 3 email at [email protected] – Google Group that facilitates API forum will continue as a peer-to-peer
forum for Market Participants to collaboratively share and obtain information; however ERCOT will now only use EDS activities and the Readiness Center for all communications and postings
– ERCOT is seeking a Market Participant volunteer to assume moderation of the Google Group
18Nodal Status Report - Project UpdatesSeptember 22, 2008 18
Design metric – 97%Nodal has 10 major end-point systems, 36 Interfaces, 57 major integration components and around 400 Information Flows
EMS
NMMS
MMS
REG
CMM
CRR
S&B
1 11
10
2
6
13
26
19
12
14
4
7
9
16
15
EWS
18
8
EWS
29
EWS
17
20
5
21,22
EXT
EXT 21
30
32
33
OS
23
24
CDR28
MIS & UIs forOS, MMS
27 34
EWS
25
3
35
31,36
31,36
IntegrationServices
# Interface Description1 NMMS -> EMS Network models2 NMMS -> MMS Network models and contingencies3 NMMS -> S&B Resource parameters and assignments4 NMMS -> CRR Network Model5 REG -> NMMS MP & Resource details6 REG -> MMS MP & Resource details7 REG <-> CMM Credit limits & Creditworthiness Status8 REG<-> S&B MP & Resource details, Calendar9 REG -> CRR MP & Resource details10 MMS -> EMS Base points and LMP11 EMS -> MMS Dynamic ratings, losses and constraints12 S&B -> MMS Heat rates, verifiable O&M
# Interface Description13 CMM -> MMS Credit limits14 S&B -> CMM Invoices, statements & determinants15 CRR -> MMS CRR ownership16 CMM -> CRR Credit limits, Bilateral trades17 S&B -> CRR Invoices, statements & payment18 EMS -> S&B Schedules, operations, BDs19 MMS -> S&B Trades, awards, schedules, BDs20 CRR -> S&B CRR settlements, BDs21 EXT -> MMS S&B Platts FIP, FOP22 S&B <-> EXT Banks financial wire transfers23 OS <-> NMMS Outage data and network model data24 OS <-> EMS Outage data and network model data
# Interface Description25 OS <-> EWS Outage Scheduler Web Services26 MMS <-> EWS Bids, offers, trades, schedules and LMP27 EMS -> CDR EMS data for Current Day Reports28 MMS -> CDR MMS data for Current Day Reports29 REG <-> EWS Disputes30 EMS -> NMMS Operational data for model31 EXT -> EMS WGR information32 MMS -> CMM Bid, RTM and DAM market data33 CRR -> CMM CRR inventory, bilateral trades34 CDR <-> EWS Market information services35 N ->MIS Multiple information services36 OS EMS <-> EXT AWS Truewind
19Nodal Status Report - Project UpdatesSeptember 22, 2008 19
Construction metric – 85%
EMS
NMMS
MMS
REG
CMM
CRR
S&B
1 11
10
2
6
13
26
19
12
14
4
7
9
16
15
EWS
18
8
EWS
29
EWS
17
20
5
21,22
EXT
EXT 21
30
32
33
OS
23
24
CDR28
MIS & UIs forOS, MMS
27 34
EWS
25
3
35
31,36
31,36
IntegrationServices
# Interface Description1 NMMS -> EMS Network models2 NMMS -> MMS Network models and contingencies3 NMMS -> S&B Resource parameters and assignments4 NMMS -> CRR Network Model5 REG -> NMMS MP & Resource details6 REG -> MMS MP & Resource details7 REG <-> CMM Credit limits & Creditworthiness Status8 REG<-> S&B MP & Resource details, Calendar9 REG -> CRR MP & Resource details10 MMS -> EMS Base points and LMP11 EMS -> MMS Dynamic ratings, losses and constraints12 S&B -> MMS Heat rates, verifiable O&M
# Interface Description13 CMM -> MMS Credit limits14 S&B -> CMM Invoices, statements & determinants15 CRR -> MMS CRR ownership16 CMM -> CRR Credit limits, Bilateral trades17 S&B -> CRR Invoices, statements & payment18 EMS -> S&B Schedules, operations, BDs19 MMS -> S&B Trades, awards, schedules, BDs20 CRR -> S&B CRR settlements, BDs21 EXT -> MMS S&B Platts FIP, FOP22 S&B <-> EXT Banks financial wire transfers23 OS <-> NMMS Outage data and network model data24 OS <-> EMS Outage data and network model data
# Interface Description25 OS <-> EWS Outage Scheduler Web Services26 MMS <-> EWS Bids, offers, trades, schedules and LMP27 EMS -> CDR EMS data for Current Day Reports28 MMS -> CDR MMS data for Current Day Reports29 REG <-> EWS Disputes30 EMS -> NMMS Operational data for model31 EXT -> EMS WGR information32 MMS -> CMM Bid, RTM and DAM market data33 CRR -> CMM CRR inventory, bilateral trades34 CDR <-> EWS Market information services35 N ->MIS Multiple information services36 OS EMS <-> EXT AWS Truewind
Remaining work
OS <-> EMS being constructed by EMS teamNMMS -> MMS CCT is incompleteS&B -> Reg for disputes calendarNew disputes API in construction
20Nodal Status Report - Project UpdatesSeptember 22, 2008 20
Deployed to Testing metric – 55%
EMS
NMMS
MMS
REG
CMM
CRR
S&B
1 11
10
2
6
13
26
19
12
14
4
7
9
16
15
EWS
18
8
EWS
29
EWS
17
20
5
21,22
EXT
EXT 21
30
32
33
OS
23
24
CDR28
MIS & UIs forOS, MMS
27 34
EWS
25
3
35
31,36
31,36
IntegrationServices
# Interface Description1 NMMS -> EMS Network models2 NMMS -> MMS Network models and contingencies3 NMMS -> S&B Resource parameters and assignments4 NMMS -> CRR Network Model5 REG -> NMMS MP & Resource details6 REG -> MMS MP & Resource details7 REG <-> CMM Credit limits & Creditworthiness Status8 REG<-> S&B MP & Resource details, Calendar9 REG -> CRR MP & Resource details10 MMS -> EMS Base points and LMP11 EMS -> MMS Dynamic ratings, losses and constraints12 S&B -> MMS Heat rates, verifiable O&M
# Interface Description13 CMM -> MMS Credit limits14 S&B -> CMM Invoices, statements & determinants15 CRR -> MMS CRR ownership16 CMM -> CRR Credit limits, Bilateral trades17 S&B -> CRR Invoices, statements & payment18 EMS -> S&B Schedules, operations, BDs19 MMS -> S&B Trades, awards, schedules, BDs20 CRR -> S&B CRR settlements, BDs21 EXT -> MMS S&B Platts FIP, FOP22 S&B <-> EXT Banks financial wire transfers23 OS <-> NMMS Outage data and network model data24 OS <-> EMS Outage data and network model data
# Interface Description25 OS <-> EWS Outage Scheduler Web Services26 MMS <-> EWS Bids, offers, trades, schedules and LMP27 EMS -> CDR EMS data for Current Day Reports28 MMS -> CDR MMS data for Current Day Reports29 REG <-> EWS Disputes30 EMS -> NMMS Operational data for model31 EXT -> EMS WGR information32 MMS -> CMM Bid, RTM and DAM market data33 CRR -> CMM CRR inventory, bilateral trades34 CDR <-> EWS Market information services35 N ->MIS Multiple information services36 OS EMS <-> EXT AWS Truewind
21Nodal Status Report - Project UpdatesSeptember 22, 2008 21
Integration Testing (INT) Project Update
22Nodal Status Report - Project UpdatesSeptember 22, 2008 22
INT Update
• Major milestones achieved in the past 2 weeks:– Established a process that works:
• Developed business-centric integration objectives for each release, including the accomplishment of end-to-end integrated business processes
• Prioritized all Nodal interfaces in each release, based on objectives above• Directed EIP and core project teams based on interface priorities• Deployed complete interface components (source, sink, adaptor) for integration testing
– To date:• INT leads assigned to five Priority 1 interfaces• All five Priority 1 interfaces deployed for Integration Testing (EWS-MMS, Platts-MMS, Reg-
MMS, CRR-MMS, CMM-MMS)• 1 passed smoke test; rest under-going smoke• MMS is running daily with stubbed data (FAT dataset)
– Target at the end of release 2 (Oct. 10)• All Priority 1 interfaces deployed and passed smoke test (base-lined and under-going
connectivity testing)• MMS running daily with data inputs through Integration layer for EWS, Platts, CRR, and
CMM
23Nodal Status Report - Project UpdatesSeptember 22, 2008 23
Questions?