Upload
tty
View
1.740
Download
23
Embed Size (px)
Citation preview
SABAH ENERGY SCENARIOS
Content
• Background• Overview of SESB System
• Overall System Performance• Interruption Index (SAIDI)
• Why Major Power Plant Is Badly Needed In East Coast Of Sabah
• Energy Option In East Coast Of Sabah
ELECTRICITY COVERAGE IN SABAHELECTRICITY COVERAGE IN SABAH
3
BACKGROUND
4
SANDAKANKOTA KINABALU
LAHAD DATU7MW
TAWAU
SEMPORNA2MW
KUDAT6MW
KOTA BELUD2MW
BEAUFORT
WP LABUANKENINGAU
4MW
PANGI
PAPAR
TENOM
TENOM PANGI HYDRO 66 MW
LABUAN 28MW
SANDAKAN42 MW
TAWAU 41 MW
TG.ARU 95MW
• SMALL ISOLATED SYSTEM• MAINLY DIESEL GENSET WTH TENOM HYDRO
• LIMITED GRID IN WEST COAST ONLY• <50% COVERAGE
SABAH SYSTEM 1984
4
5
SANDAKAN
KOTA KINABALU
LAHAD DATU7MW
SEMPORNA2MW
BEAUFORT
WP LABUANKENINGAU
PANGI
PAPAR
TENOM
LLS
IPP
Mini Hydro
TENOM PANGI HYDRO66 MW
PATAU-PATAU (112 MW)
MELAWA 44 MW
ARL 50 MW
GANTISAN38 MW
SANDAKAN41 MW
LIBARAN60 MW
TAWAU50 MW
SERUDONG37.5 MWTAWAU
TG.ARU 27 MW
POWERTRON136 MW
MELANGKAP1 MW
KIAU0.4MW
CARABAU2 MW
BOMBALAI1 MW
MEROTAI1.3 MW
SAYAP1 MW
KUDAT6MW
KOTA BELUD2MW
• EXPANDED SYSTEM• GEN MIX OF GAS, HYDRO & DIESEL
• IPPs INTRODUCED -• LIMITED GRID IN WEST COAST ONLY
SABAH SYSTEM 1998
5
SANDAKAN
KOTA KINABALU
LAHAD DATU
TAWAU
SEMPORNA
KUDAT
KOTA BELUD
BEAUFORT
WP LABUANKENINGAU
PANGI
KOTA MARUDU
KUNAK
PAPAR
TENOM
KOTA KINABATANGAN
SEGALIUD
DAM RD
TNPG (44 MW)
(FIRM CAPACITY)
PTAU (99 MW)1 X 30 MW GT2 X 28 MW GT1 X 13 MW ST
MELA (31.4 MW)2 X 5 MW DG2 X 4.4 MW DG1 X 17MW GT
ARLT (50 MW)4 X 12.5 MW DG
SBPC (100 MW)2 X 33 MW GT 1 X 34 MW ST
GANT (32 MW)2 X 16 MW GT
BSPS (32.5 MW)1 X 6 MW DG1 X 5.5 MW DG1X 12 MW DG1 x 9 MW DG
LBUK (7 MW)2 X 3.5 MW DG
SPC (32 MW)4 X 8 MW DG
LBRN (60 MW)4 X 15 MW DG
TWPS (36MW)3 X 4 MW DG1 X 9 MW GT1 X 15MW GT
SERU (36 MW)3 X 12 MW DG
TSH (10 MW)1 X 10 MW ST
SESB
IPP/SREP /
Temp. Gen.
Hydro SUTERA HARBOUR (27MW)
3 X 9 MW DG
TESA (190MW)4 X 30 MW GT 2 X 35 MW ST
Seguntor
Bioenergy
(10 MW)1 X 10 MW ST
Kinabio
Power (10 MW)1 X 10 MW ST
SREP MinihydroSg. Kadamaian
(2.0MW)
Sabah’s
power shortage problems must be assessed based on
EAST
and WEST
coasts Supply and Demand situation.
SABAH GRID (Jun 2010)RPII (130 MW)2 X 65 MW ST
7
OVERVIEW OF SESB SYSTEM
Sabah Grid Interconnection & Power Station• The forecast demand growth of electricity is in a region of 7.7% per annum.• A fully integrated grid connecting the West Coast Grid to the East Coast Grid was completed on 28 July 2007, and about 80% of the customers are now connected to this integrated grid
8
KudatPitas
Mengaris
Sandakan
Lahad Datu
Tawau
Semporna
Kota Belud
Kota Kinabalu
Sipitang
Keningau
Penampang
Segaliud
Dam Road
Kalumpang
Tenom Pangi
Beaufort
Labuan
Kolopis
Papar35.5km
113km
5.3km
90km
33km 50km
255km
132 kV
275 kV
46.5km
55km
76km
31.5km
51km
35.5km 40km68.5km
WEST COASTGRID
EAST COASTGRID
Ranau
30km
40km
57km
Upper Padas
TambunanKimanis 45km
G
G
G
90km
Coal Fired IPP Ph 1 150MW (2014)Coal Fired IPP Ph 2 150MW (2015)
G
Upper Padas 150MW (2017)
G
Liwagu 150MW (2018)
Ranhill Powertron 190MW (2010)
Committed Plant
Planned Plant
Lok Kawi
STRENGTHENING OF THE GRID CONTINUES..
8
Kimanis 200MW +100MW (2013/2014)SPR 100MW (2013)
ELECTRICITY COVERAGE IN SABAHELECTRICITY COVERAGE IN SABAH
9
SYSTEM PERFORMANCE
1010
OVERVIEW
SESB STATISTICS
ANNUAL REVENUE (FY2009) RM 954m
AVERAGE SELLING PRICE (FY2009) (Cent/kwh)
25.55
COST PER UNIT (FY2010) (CENT/KWH) (including Finance Cost)
43.70 (w/o subsidy)32.30(with subsidy)
GENERATION INSTALLED CAPACITY
SESB IPP TOTAL
436.5 MW 659.3MW 1,095.8MW
MAXIMUM DEMAND 772.8 MW
Negative margin of
-6.75 cent/kwh
41093849
2717
1947
2284
700
0
500
1000
1500
2000
2500
3000
3500
4000
4500
2005 2006 2007 2008 2009 2010
min
ute
s p
er c
ust
omer
FY
11
Under Sabah
Integrated
Master Plan, and with full
completion of the proposed
initiatives, SESB is targeting
a statewide SAIDI of 700
minutes by the year 2010.
Target Performance for :
Sector 1 : 240 mins.
Sector 2 : 800 mins.
Sector 3 : 1500 mins.
Progressive Improvement for SAIDI (Statewide)
Improving trend of SAIDI
Actual Target
TNB SAIDI : 73 min
IMPROVED SYSTEM PERFORMANCE
201.41
11.46
54
265.34134.69
19.25
56
209.69
210.41
8.08
37
255.22
238.37
7.05
52
297.48
34.11
3.27
45
82.75
24.25
0.02
33
57.57
17.16
0.18
49
66.63
40.21
9.23
35
84.26
72.67
2.42
63
138.4
28.31
10.92
45
83.86
0
50
100
150
200
250
300
Sep‐09 Oct 09 Nov‐09 Dec 09 Jan‐10 Feb‐10 Mar 10 Apr‐10 May 10 Jun‐10
SAIDI SESB ( SEP 2009 ‐ JUN 2010)
Generation Transmission Distribution SESB Linear SESB
WEST COAST VS EAST COAST SAIDI for FY 2010 (Major Towns)
WEST COAST VS EAST COAST SAIDI for FY 2010 (Major Towns)
1,155 1,161
408
1,352
731
2,2102,386
2,117
2,553
1,175
0
500
1000
1500
2000
2500
3000
Tuaran KK LBN KGAU PPAR TWAU SDKN LHDU BLRN KBTG
West Coast Town East Coast Town
min
utes
per
cus
tom
er
Less reliable system in the East Coast & rural areas having higher
frequency of interruptions
SAIDI yang tinggi disebabkan kekurangan kapasiti penjanaan & kadar Unplanned Outage Rate(UOR) yang tinggi dari set penjanaan yang telah uzur
ELECTRICITY COVERAGE IN SABAHELECTRICITY COVERAGE IN SABAH
14
WHY MAJOR POWER PLANT IS BADLY NEEDED IN EAST
COAST OF SABAH
15
SBPC (IPP)
ARLT (IPP)
TENOM PANGI
Sutera
Harbour
PATAU‐PATAU P/S
POWERTRON (IPP)
MELAWA P/S
WEST COAST: AVAILABLE CAPACITY*WEST COAST: AVAILABLE CAPACITY*
T.ARU
• Definition Available Capacity (MW) = Day to day capacity after taking into account any deration
• ** Sutera Harbour (SH) - SESB is temporary buying energy from SH and since there is no PPA signed thus it is not considered as an IPP.
SESB Plants
IPP Plants
Plant Type Plant Name Available Capacity
Gas Plants 1. SESB Patau-Patau P/S 2. IPP SPBC 3. IPP Powertron I4. IPP Rahill Tuaran (GT 1 x 65MW)
57MW 100MW190MW65MW
Hydro Plants 1. SESB Tenom Pangi2. SREP Sg. Kadamaian
66MW1MW
Oil/Diesel Plants
1. SESB Melawa2. SESB Mobile Melawa (12MW) & Tg Aru (8MW))3. IPP ARLT4. Sutera Harbour** (Temporary)5. Others
19.1MW20MW22MW17MW4.8MW
Total Available Capacity as at 21 May 2010 561.9 MW
Total Maximum Demand in West 548.4 MW
Excess Available Capacity 13.5 MW
West Coast Grid Reserve Margin 2.5%
16
SBPC 100MW
ARLT 50MW
TNPG 66MW
Sutera
Harbour
38MW
PTAU 112MW
TESA 190MW
MELA 44MW
LIBARAN (IPP)
SPC (IPP)
LABUK P/S
BATU SAPI P/S
LAHAD DATU P/S
GANTISAN P/S
TWAU P/SSEMPORNA P/S
SERUDONG (IPP)
SESB Plants
IPP Plants
EAST COAST: AVAILABLE CAPACITYEAST COAST: AVAILABLE CAPACITY
Definition Available Capacity (MW) = Day to day capacity after taking into account any deration.
KINA BIO
SGTR BIO
TSH
Plant Type Plant Name Available Capacity
Gas and Hydro Nil Nil
Biomass SREP TSHSREP KINA BIO SREP SGTR
9 MW9 MW*9 MW*
Oil/Diesel Plants SESB Labuk P/SSESB Bt. Sapi P/SSESB Gantisan P/SSESB Lahad Datu P/SSESB Semporna P/SSESB Tawau P/SIPP SPCIPP LibaranIPP SerudongSim-Sim MobilePasir-Putih MobileOthers
6 MW9 MW
17 MW6.3 MW0.5 MW36.6 MW24 MW45 MW36 MW
17.2 MW17.5 MW1.8 MW
Total Available Capacity as at 21 May 2010 243.9 MW
Total Maximum Demand in East Coast 224.4 MW
Shortage in Available Capacity 19.5 MW
East Coast Reserve Margin (%) 8.69%* Not very reliable due to fuel issues.
17
WEST
COAST
GRID(WCG)
EAST
COAST
GRID
(ECG)Daily Power Transfer = 50 ‐
100 MW
Dependable Capacity : 661.8 MW Average Daily Availability : 520.5 MW
Max Demand : 548.4 MW
Dependable Capacity : 359.7 MW Average Daily Availability : 214.5 MW
Max Demand : 224.4 MW
25%-50% of East Coast demand is supported by
West Coast Grid
In the case when
EWG
interconnection is
lost OR, no excess
capacity availbale
from West Coast
Grid, East Coast will
be operated in
islanded mode with
unserved
load of 50‐
100MW (25%‐50%)
As of 21 May 2010
(Dependable Capacity are taking into account of L.D, Semporna. Sim‐
Sim, Pasir
Putih, POIC, Melawa and Tg
Aru
Mobile.)
SABAH GRID – POWER TRANSFER
17
183MW is the
maximum power
transfer to East
Coast by Year 2013.
(14.7MW
Transmission line
losses) .
How the Demand in the East of Sabah is met in 2013
Base load plant 150MW
•By
adding
additional
capacity
in
the
West
Coast,
it
will
not
address
the
shortage
of
power
in East Coast.
• What
Sabah
really
needs
is
a
major plant in
the
East
Coast
to
meet the demand.
How the Demand in the East of Sabah is met in 2015
ELECTRICITY COVERAGE IN SABAHELECTRICITY COVERAGE IN SABAH
20
ENERGY OPTIONS AVAILABLE
CCGas OCGas Hydro Biomass Coal Solar Wind Fuel Cell
Geo- Thermal
Technologically feasible
Financing viability
Insurability
Economic fuel option in East
Coast Of Sabah
Economic fuel option in West Coast Of Sabah
Environmentally compliant
Construction Duration for 1 unit (month)
24 20 18 to 60
18 to 36
30 7 to 12
6 to 12
36
Unit MW Range 150 to 750
10 to 250
0.05 to 700
5 to 50 30 to 1000
Up to 14
Up to 3.6
Up to 100
Up to 60
Energy Options In Sabah
0.0
2.0
4.0
6.0
8.0
10.0
12.0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0
EFFICIENCY (%)
GE
N C
OS
T (U
SD
Cen
t/kW
h)
Micro Hydro Hydro
Geothermal
Biomass Oil
Coal
Nuclear
Gas
Source:Paper ‘The Economics of Generation Tecnologies’ (Lockwood Greene consulting study)
Coal Price: USD1.2 / MBtuOil Price : USD 2.0 / MBtu
Wind
Solar
Renewable Technology Offers Efficiency But Not CheapRenewable Technology Offers Efficiency But Not CheapInexpensive electricity is essential to maintaining a dynamic Sabah economy and our standard of living. Gen Cost Influence ~ Tariff Price
Comparative Generation Cost Per kWh
Source:Paper ‘The Economics of Generation Technologies’ (Lockwood Greene consulting study)
Economics-Cost Of Electricity (Busbar Cost)Economics-Cost Of Electricity (Busbar Cost)
• Potential
power
from
palm
oil
mill
biomass
after
deducting
competitive
uses
of
EFB
and on‐going projects is 256MW.
• However, mesocarp
fibre
and palm kernel shell are currently being used
to
generate
steam for POM process.
• Therefore,
only
EFB
is
available
to
be
considered
as
a
fuel
source
and
taking
into
account the 50% non‐energy uses of EFB, potential power to be generated is around
70MW.
• Potential power to be generated from biogas is shown as follows:
Electricity Generation Potential From Palm Oil Wastes(Biomass and Biogas) in Sabah
FFBFFB processed
@70%Calorific value Potential Power
tonne/yr tonne/yr m3/yr m3/hr kJ/m3 MW
29,333,200 20,533,240 328,531,840 41,671 22,000 102
Biogas production
• Total
potential
power
that
can
be
harnessed
from
POM’s
biomass
(EFB)
and biogas is 70MW + 102MW = 172MW
Source: Energy CommissionBack
Opsyen Kadar Penggunaan Bahan Api
Keperluan Logistik
300 MW Loji Engin Diesel(20 x15 MW)
Purata kecekapan3.7kWj/Liter atau
1,945,946 liter sehari
Kapasiti satu bozer diesel adalah 20,000 liter
Loji Turbin Gas Kitar Padu(10x30MW)
Purata Kecekapan3.1kWj/Liter atau
1,600,000 liter sehari
Kapasiti satu bozer diesel adalah 20,000 liter
Loji Biomass(30x10MW)
Purata kecekapan400 kWj/Ton atau
18,000 Ton sehari
Kapasiti satu lori angkut adalah 20 ton
Loji Arang Batu(4x75MW)
Purata kecekapan1,859 kWj/Ton atau3,872 Ton sehari
Kapasiti satu kapal barge adalah 10,000 ton
PERBANDINGAN KEMUDAHAN LOGISTIK
X 80
X 97
X 900
X 0.3872
Geothermal Energy in TawauGeothermal Energy in Tawau
Potential of geothermal energy was discovered through a study carried out by Jabatan Mineral & Geosains via magneto telluric study in 2007 located in Appas Kiri, TawauThe initial survey identified a reservoir of 2000~3000m depth with 220~236ºC temperature, which will provide an estimated potential capacity of 67MWThis study is at its early stage, the second phase study on isotope studywill be conducted under 10th MP to achieve a more credible results.The project can be categorized as cost effective, environmental friendly and reliable, despite its initial high capital investment.
Source: Jabatan Mineral & Geosains, Malaysia
Facts:•Energy source : Geothermal•Location : Appas
Kiri,Tawau•Reservoir depth : 2000 ~ 3000m
•Temperature : 220 ~ 236ºC•Capacity : 67MW
•Life‐span : 25 years
Back
Solar EnergySolar Energy
Solar Panel Size 994 mm x 1318 mm – Mitsubishi (180 w)Size 834 mm x 1658 mm – Sharp (180 w)
1 MW required 6 acres of land equivalent to 3 football field.
300MW required 1,800 acres of land
Back
INSTALLATION DI SABAH KALABAKAN – 150KWPULAU BANGI – 150KW
•Average Sabah Wind Speed 0.3-5.4 m/s(source: http:/www.townplanning.sabah.gov.my/iczm/reports)
•Required about 14 m/s for a rated 3.6MW wind turbine. For 1.5MW require rated wind speed 8 m/s.(source: GE website)
•If smaller scale of wind turbine is feasible. It may require estimated land mass > 30km2 @ 7413 acres
Wind Energy
Wind Turbines Technical Info
• Onshore – Typically rated at 1.5 to 2.3MW per turbine
• Offshore – Currently 3 or 3.6MW rating per
turbine
• Some Offshore turbines in development up to
5MW rating
• Onshore turbines typically 60 to 80m hub
height with 70m to 90m diameter rotors
• Typically have availabilities of 97% and yields
of around 25 to 30% of rated capacity
• Turbine spacing requirements mean that each
turbine requires approx 0.1km2 clear of other
turbines
Back
Back
Gas Allocation for Sabah and WP LabuanGas Allocation for Sabah and WP Labuan
OFFSHORE SABAH PSC OFFSHORE SABAH PSC
Labuan GAST(250mmscfd)
Sabah GASTSepangar
Bay (150mmscfd)
SOGT Kimanis (1250mmscfd)
PowerPower
Non-PowerNon-Power
PowerPower
Non-PowerNon-Power
SSGP (750mmscfd)
SSGP (750mmscfd)
SESB
Ranhill Powertron II
Industrial
Sepanggar Bay Power
Industrial
Ranhill Powertron I
MLNG
Non-Power
18 mmscfd
17 mmscfd
230 mmscfd
36 mmscfd
29.5 mmscfd
31 mmscfd
500 mmscfd
100 mmscfd
Power 60 mmscfd
Back
Back
Back
Back
Long Term Generation Study by HAPUA Working Group
Long Term Generation Study by HAPUA Working Group
36
Summary Of (SREP) Project In SabahSummary Of (SREP) Project In Sabah
• SREP POWER PLANTS REQUIREMENTS ARE:•
• MAXIMUM EXPORTABLE CAPACITY SHALL NOT BE MORE THAN 10MW
• TO BE SITED WITHIN 10KM FROM THE NEAREST GRID INTERCONNECTION POINT
• TARGET 5% OF TOTAL ELECTRICITY GENERATION
• SREP PROJECT DEVELOPER TO NEGOTIATE RENEWABLE ENERGY PURCHASE AGREEMENT (REPA) WITH POWER UTILITY (EG. SESB, TNB)
• REPA IS STRUCTURED BASED ON TAKE AND PAY CONCEPT
37
Summary Of Small Renewal Energy Program (SREP)Project In Sabah
Summary Of Small Renewal Energy Program (SREP)Project In Sabah
No DescriptionExportable Capacity
Biomass (MW) Hydro (MW)
1 Completed SREP Projects 30.0 2.0
2 SREP Under Construction 5.0 7.0
3 Approved SREP Projects 40.0 18.6
Total 75.0 27.6
Potential total exportable capacity of 102.6MW for electricity generation
38
Station Type Installed Capacity (kW)
Commissioning Year
Melangkap, Kota Belud
Pelton, Jyoti 600T-500Pelton, Xian CJ-W-90/1x11
500500
19901992
Sayap, Kota Belud
Pelton, Xian CJ-W-90/1x11Pelton, Xian CJ-W-90/1x11
500500
19911991
Carabau, Ranau
Pelton BiwaterPelton Biwater
1,0001,000
19911991
Merotai, Tawau
Francis, Gilkes G-150 1,100 1992
Kiau, Kota Belud
Wassercraft TD50H 330-1 375 1994
Bombalai, Tawau
WKV Turgo Impulse TT-285-180-1 1,100 1996
Naradau,Ranau
Wassercraft Turgo SETTT-120-480Wassercraft Turgo SETTT-120-480
880880
19991999
Pulau Bangi Mitsubishi Electric (Solar Hybrid) 150 2008
Kalabakan Mitsubisihi Electric (Solar Hybrid) 150 2009
SESB Owned Minihydro with Total Installed Capacity of 8335 kW
Small Renewal Energy In Sabah(SESB Mini Hydro & Solar Hybrid Power Plant )
SESB Owned Solar Hybrid in Total Installed Capacity of 300 kW
Other SREP DeveloperOther SREP DeveloperNo. Developer Location Area Energy
ResourceInstalled Capacity
[MW]
Capacity (On-Grid)
[MW]1 TSH Bioenergy Sdn Bhd Tawau East Coast EFB 12 10
2 Seguntor Bioenergy Sdn Bhd Sandakan East Coast EFB 11.5 10
3 Kina Biopower Sdn Bhd Sandakan East Coast EFB 11.5 10
4 Esajadi Power Sdn bhd Tambunan West Coast Mini hidro 2.1 2Operational on-grid SREP projects : 32MW
5 Esajadi Power Sdn Bhd Kundasang, Kota Marudu
West Coast Mini hidro 7.5 7
6 Alaf Ekspresi Sdn Bhd Lahad Datu* East Coast EFB 12 10
7 Kalansa Energy Corp. Sdn Bhd Sandakan East Coast EFB 6.5 5
8 Warisan Harta Sdn Bhd Ranau West Coast Mini hidro 6 5
9 Cash Horse Sdn Bhd Lahad Datu East Coast EFB 12 10
10 Mistral Eng. Sdn Bhd Lahad Datu East Coast Biogas 3 2
11 K.K Powergreen Sdn Bhd Kedamaian West Coast Mini hydro 4.8 4.5
12 Afie Power Sdn Bhd Tuaran West Coast Mini hydro 9.5 9
13 Eco Biomass Power Sdn Bhd Lahad Datu East Coast EFB 23 20Potential on-grid SREP projects : 72.5MW
SREP PerformanceSREP Performance
No. Developer Area Energy Resource
Installed Capacity
[MW]
Capacity (On-Grid)
[MW]
Availability%
1 TSH Bioenergy Sdn Bhd, Tawau
East Coast
EFB 12 10 87%
2 Seguntor Bioenergy Sdn Bhd , Sandakan
East Coast
EFB 11.5 10 68%
3 Kina Biopower Sdn Bhd, Sandakan
East Coast
EFB 11.5 10 50%
4 Esajadi Power Sdn Bhd, Kota Belud
West Coast
Mini hidro 2.1 2 60%(400kW dry
spell)Operational on-grid SREP projects : 32MW
Liwagu
Upper Padas
Kalumpang
Dam Road
Segaliud
Menggaris
Tenom
Pangi
Kunak
East West
Interconnection
Southern Grid
West Coast
Grid
Northern Grid
East Coast Grid
MH1
MH2
MH3
MH4
MH5
MH6MH7
Station No.
Mini Hydro Melangkap MH1
Mini Hydro Kiau MH2
Mini Hydro Sayap MH3
Mini Hydro Carabau MH4
Mini Hydro Naradau MH5
Mini Hydro Merotai MH6
Mini Hydro Bombalai MH7
Pulau
Bangi
(Solar Hybrid) 200kW S1
Kalabakan
(Solar Hybrid) 200kW S2
S1
S2
42
SANDAKANK..KINABALU
LAHAD DATU
TAWAU
SEMPORNA
KUDAT
KOTA BELUD
BEAUFORT
WP LABUANKENINGAU
PANGI
KOTA MARUDU
KUNAK
PAPAR
TENOM
SEGALIUD
DAM RD
SIPITANG
SREP Kina Biopower, Sandakan (10MW) COD = January 2009
SREP Seguntor Bioenergy Sandakan (10MW) COD =March 2009
SREP Alaf Expresi (10MW) POIC Lahad Datu
Status : REPA Main Body submitted to developer on Feb 09.
SREP Kalansa, Beluran (5.0MW) End : 2010
Status : Under Construction
KALUMPANG
RANAU
SREP by Esajadi Power Sdn Bhd-Sg.Kaingaran, Tambunan (2.5MW )
SREP UNDER NEGOTIATION/UNDER IMPLEMENTATION & COMPLETED PROJECT
SREP by KK Powergreen Sdn BhdSg Kadamaian, Kota Belud (4.5MW)
Status : Technical Discussion ongoing
SREP Eco-Biomass (20MW) POIC Lahad Datu
Status : KTAK issued project implementation letter on 22 June 09
SREP by Afie Power Sdn BhdSg Mulau & Sg. Mantaranau, Kiulu (8.9 MW)
Status : Pending submission of Interconnection proposal by developer
SREP Warisan Harta, Sg. Mantaranau, Ranau (5.2MW)
Status : Technical discussion ongoing
SREP TSH Bioenergy, Kunak (10MW) COD = Feb 2005
SREP Cash Horse Sdn. Bhd (10MW)) KM38-40 Sandakan-Kota Kinabatangan Road
Status : REPA Negotiation Ongoing
Completed Projects
Under Construction
Approved Projects
32.0MW
12.0MW
58.6MW
Total Exportable Capacity 102 .6MW
SREP by Esajadi Power Sdn BhdSg Kadamaian, Kota Belud (2.0MW )
COD : 02 August 2009
SREP by Esajadi Power Sdn BhdSg Pangapuyan, Kota Marudu (4.5MW)
SCOD : End 2009
LEGEND :
OPERATIONAL SREP PROJECTS
Biomass PlantMini Hydro Plant
30MW2MW
Exportable Capacity
43
Summary Of Small Renewal Energy Program (SREP)Project In Sabah
Summary Of Small Renewal Energy Program (SREP)Project In Sabah
• SESB is currently the leading off-taker in the country on Renewable Energy (RE) initiatives, with contracts of more than 30MW capacity representing about 3% of Sabah Energy Generation share, against the national average of less than 0.5%.
• We will continue to play major role in encouraging such RE initiatives, in line with the national Five-Fuel Policy which also aim to minimise the impact of power generation on environment.
PROJECTED GENERATION MIX (MWh) PROJECTED GENERATION MIX (MWh)
Gas
Oil
Hydro
LEGEND :
Renewable Energy (RE)
Increasing trend of RE Contribution in
Generation Mix (MWh)
SREP – Issues & ChallengesSREP – Issues & Challenges
• Biomass PlantAvailability of Fuel Reliability & Technology ChallengesNon – regulated fuel priceTransportation Cost for Non Palm Oil Mills DeveloperShort term contract for Fuel Supply Agreement
• Interconnection PointProject economically viable (reasonable tariff) if the transmission line less than 10km from SESB existing line
• Institutional SupportGovernment Subsidies/IncentivesBank Financing SupportClean Development Mechanism (CDM)
ELECTRICITY COVERAGE IN SABAHELECTRICITY COVERAGE IN SABAH
46
WHY COAL PLANT IN EAST COAST OF SABAH
• To maintain the Voltage Regional Balance in the East Coast of Sabah.
• Crucial to provide system voltage stability support.
• Diversify Generation Fuel Mix in line with Five Fuel Policy
• Provide balanced generation between East and West Coast.
• Coal fired power plants have overcome the pollution challenges that face them and, with continued research and development (R&D) it can overcome future environment challenges.
• Coal fired power plants provide low cost base loaded power to the grid now and into the future
• Coal fired power plants have been continuously upgraded to provide more reliable power
• Coal fired plants provide a much needed base to the needs of the power grid now and into the future
Why Coal Power Plant
• New base-load electric power generating plants are needed to meet the demand for capacity growth and GDP growth - and to replace aging, inefficient plants. Clean coal technologies and more efficient energy conversion cycles are now available for use in economical and reliable coal-fired plants. This will significantly reduce overall emissions of SO2, NOx, and particulate pollution, and the emissions of CO2.
• Compared to other alternative energy sources, coal fired power plant provides the ONLY effective option.
• Renewable Energy (RE) is not a feasible option to totally solve the generation availability because;
1. RE does not produce continuously & consistent power 2. The Cost Per Unit (CPU) is on the high side.3. The size in terms of MW for a RE plant is small
•
Why Coal Power Plant
Technology Why Not?
Gas
• Gas is not available in East Coast. Very costly to lay gas pipeline all the way from west coast (300km); ‘Shipping’ gas (LNG) from West Coast requires the construction of expensive gas liquidification/expension facilities. At the rate we are using natural gas our children will see the price rise so much that it will no longer be economical as a fuel.
Hydro• No known suitable water source or river in East Coast - high gradient for required head pressure
Biomass• A large area of farmland is required for the supply of the ‘fuel’(eg. fruit bunch). This method of generation can never generate enough power to satisfy a major part of current demands.
Solar• Yes for 30kW but for 300,000kW (300MW) - still not cost effective for large scale power generation. While the technology has great promise it has not yet been proven to be cost-competitive on a large scale.
Wind• Does not produce power when the wind isn't blowing. Need consistent wind . If a large proportion of a power system's electricity is wind power then there may be a need for a large 'spinning reserve' backup power supply.
Geo Thermal
• Potential of geothermal energy was discovered through a study carried out by Jabatan Mineral & Geosains via magneto telluric study in 2007 located in Appas Kiri, Tawau. Further study on isotope study need to be conducted to achieve a more credible results.
Other Alternative Sources
50
2007
2011 2015
OVERDEPENDENT ON EXPENSIVE DIESEL
INTRO OF COAL FOR BALANCE FUEL SOURCE
INCREASED SHARE FROM RE
2009
FIVE-FUEL STRATEGY : SABAH GENERATION MIX
51
2015
WITHOUT COAL INTRO OF COAL FOR BALANCE FUEL SOURCE
INCREASED SHARE FROM RE
2015
FIVE-FUEL STRATEGY : SABAH GENERATION MIX
Over Dependency
On Gas
CONCLUSIONCONCLUSION
• East Coast of Sabah needs a base load plant for:• Grid system security and reliability.• Grid system stability. • Future power demand.
• To meet Sabah socio-economic and infrastructure development. The economic competitiveness of the nation requires low cost, reliable electric power.
•The most technically and economically feasible option is a COAL FIRED PLANT that meets the stringent DOE and World Bank requirements.
• SESB will continue to pursue Renewable Energy as an integral part of its energy option and thus meeting the government five- fuel policy.
More info and FAQs
on Coal Plant facts are available @
www.sesb.com.my
More info and FAQs
on Coal Plant facts are available @
www.sesb.com.my
SESB
Thank YouThank You
SESB