#LIPS2015 @itec_es Session 1* Case study of an alliance railway renovation project Lielahti – Kokemäki (Liekki) Pekka Petäjäniemi Finnish Transport Agency

Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

#LIPS2015 @itec_es

Session 1*Case study of an alliance railway renovation project Lielahti – Kokemäki (Liekki)

Pekka Petäjäniemi Finnish Transport Agency

Page 2: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

It all started in LIPS 2009in Karlsruhe, Germany

2

LIPS 2009 Jim Ross introduced the Project Alliance

EU-legislation is challenge in the public sector

LIPS in Washington DC 2010We can challenge the EU-legislation

First Alliance pilot started 2011No problems with procurement Law

Page 3: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

Lielahti–Kokemäki rail renovation project in short● Lenght of railway renovation project 89,6 km● Project original budget 91 M€ (incl. owner’s material 20–30 M€)● Goal for the renovation is to:

•Improve safety for railway section and reduce maintenance costs by renewing and repairing constructions (railway sleepers, rails, ballast, culverts, bridges, drainage, build new and tear down old platforms)

•Reinforce surface and bench structures of the railway track so that it is possible to operate on 250 kN in 80-100 km/h.

● Besides the renovation there are improvement needs, such as:•Changes in bench width•Removal of railway grade crossings

● First Public sector Alliance Pilot in Europe

3

Page 4: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

Coaching was needed

Dialogue inside the owners side●Started in May 2010●Core team started to develop the Finnish approach for Alliancing in June 2010●Wider coaching in two workshops in November 2010●More coaching during the selection process

2.9.2011 4

Page 5: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

Changing culture is the issue – Building trust, trust, trust

Dialogue with the industry● Started in May 2010 (1-day workshop)● General information of the pilot projects in September 2010● Workshop with the industry in November 2010

Focus on commercial framework and selection criteria● More workshops during the selection process

2.9.2011 5

Page 6: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

Alliance steps and situation

6

1.6.2012 28.2.2015 20191.4.2011

STRA-TEGY

DEFECTS CORRECTION PERIOD

Liekki situation 9/2015

13.8.2011

ESTABLISH ALLIANCE

PROJECT DEVELOP-MENT PHASE

IMPLEMENTATION PHASE

PROJECT DELIVERY

Page 7: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

7

FinnTrA’s Strategic Targets for Alliancing

• To improve productivity of the entire industry

• To change the culture into a more open and trusting way of working

• To improve the customer satisfaction for end products –faster, better quality and cheaper

• To develop innovativeness and knowledge

Page 8: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

Lielahti−Kokemäki –alliance ”Value for Money”

8

ALLIANCE

Total optimization

Way of action: best for project and as the needs arise

Collaboration between owner, designers and 

contructors

Human in center:WE ‐spirit

Page 9: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

Project Key Result Areas

2.9.2011 9

KRA Alliance ObjectivesSafety Zero harm in traffic and work safety on a very good

level, open reporting culture

Schedule Meet all milestone dates and project commissioned and handed over on agreed date

Operations Zero reliability incidents, including no late return of track possessions

Usability Use of railway track on agreed speed level

Page 10: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

Outcomes of Key Result Areas

Objectives Failure Minimum Conditions ofSatisfaction

Break-through

Results KRA‐performance

Passenger Traffic Precision [%] 70 85‐90 98 99,65 26

Freight Traffic Precesion [%] 70 85‐90 98 99,93 9

Project Completion Date[dd.mm.yyyy]

31.05.2016 31.05.2015 28.02.2015 28.02.2015 20

Deviation of Rail Safety [pcs] 25 6‐10 0 2,5 5

Safety ‐measurements [%] 75 93 100 95,8 7

Frequency of Accident at Work [pcs/1 Mhours]

100 18 0 6,2 12

10

Total    79

0 +10079‐100Value for Money

Page 11: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

Usability of track under construction

● In three Years delivery period about 27 000 trains passed the site, because of construction only 42 trains has been delayed or cancelled● Accuracy of traffic during constuction:

Freight Tarffic99,93%

Personal Traffic99,65%

(Avg. In FIN ~82 %)

11

Cooordinaton between construction site and rail traffic has been excellent !

Page 12: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

Effective delivery

● Project manage and effective schedule planning with Lean -tools

12

Traditional project delivery

2011 2012 2013 2014 2015 2016 2017 2018Total Schedule of ProjectAdministrative Plans

Final DesignPoject Delivery

Initialization

2011 2012 2013 2014 2015 2016 2017 2018Total Schedule of ProjectAdministrative Plans

Final DesignPoject Delivery

Initialization

Alliance model

Project Delivery has been reduced about 2 years

Page 13: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

13

Even fast delivery the project management has been succesfull

Total management of construction works, final design and owner´s administrative procedures. All decisions are made ”best for project”Taking ”lean-principles” to practice:● Last Planner● Gemba Walk● Kaizen● LPDS

Collaboration in work coordination, management of change and innovative problem solving create efficiency.Training and guiding play a key roleNew way of collaboration requires constant learning during the project

Page 14: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

Safety as performance

● Safety level has been high level throughout the project delivery● Safety process has been created by alliance and it is part of daily action

14

Safety –measurements, about 12 000 notes have been made Work Safety Level 95,8%

Total hours of work about 640 000 hWork accidents 4 kpl, of which lost working days totally 19

Frequency of work accidents 6,2 (avg. In Finland 20 in railway projects)

Traffic Safety DeviationsCommucation between Rail Traffic Control and Site PersonalSecuring the road traffic at level crossingWorking in safety device premises without a permission

Railroad traffic Safety in good level

Page 15: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

Target Outturn Costs (TOC)

15

Service Producers Project Costs

Owner Project Costs

Fee

KRA 0”Bonuspool 1,7 M€”

Total Project Costs76,6 M€

Level at 1.6.2012 (Begin of Implementation Phase) 85,6 M€

Risks

Alliance Leadership Teamhas accepted TOC1.6.2012

Page 16: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

Outcomes of the commercial model

21.9.2015 16

Palveluntuottajankorvattavat

kustannukset

Projektikohtaiset yhteiskustannukset

Palkkio korvattavillekustannuksille

Project costs71,5 M€

Actual outturn cost prediction at the end of the constructionperiod: 80,0 M€

Owner has increased the projectscope with 4,2 M€ gained during

the alliance

Forecast:Gain +7,0  M€

Direct project costsfor non-owner

participant

Owner´s costs

Fee for projectspecific costs

Risks

Goals are achievedand the success of the project can be welldemonstrated

12%/25,6%

Project has been expanded ‐combined constructions with municipalities

”Value for Money”  

Page 17: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

17

Target Outturn Costs devided for Technical areas

1.059

6.027

2.054

1.809

7.137

6.894

13.823

27.373

4.434

1.730

3.952

4.727

1.059

6.062

1.970

1.214

5.470

8.459

11.744

22.792

4.889

1.692

3.361

7.604

0

5.000

10.000

15.000

20.000

25.000

30.000

35.000

EstimatedRealized

Railway sleepers, rails, ballastTotal new level of costs [‐20%]!k€

Excavation work

Design

Page 18: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

Public Relations during the Alliance –great part of the achievements

18

Page 19: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

Site of the Year 2012 in Finland!

19

Exceptional collaboration between owner and service providers

Page 20: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

Integrated Project Deliveries in Finland

Page 21: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

Experience of Alliance

+ Successful Alliance pilot – strong achievements+ Remarkable Start for Finnish Alliance Market+ No problems with EU Procurement Law+ Begin of Project is possible with general plans+ Project Management+ Alliance Model has been created new skills+ Good learning environment+ Risk management

∆ Commitment of all participants∆ Changes of Key Personal∆ Key Result Areas also for Warranty Period∆ Big Room –common for all participants ∆ Initiation of Alliance Model – way of working

21

Page 22: Session 1* study of an alliance railway project ... - ITeC...1.214 5.470 8.459 11.744 22.792 4.889 1.692 3.361 7.604 0 5.000 10.000 15.000 20.000 25.000 30.000 35.000 Estimated Realized

22

Owner’s Project Manager

Mikko A. Heiskanen, Liikennevirastop. 029 534 [email protected]

Alliance Project Manager

Mikko Nyhä, VR Track Oyp. 040 863 [email protected]

Thank You for listeningMore informationliikennevirasto.fi/lielahti-kokemäki