  • 8/3/2019 Session 4 Ecuador Final 231111

    1/24

    IMPACT OF THE IMPLEMENTATION

    OF A NEW E-PROCUREMENT SYSTEM

    IN ECUADOR

  • 8/3/2019 Session 4 Ecuador Final 231111

    2/24

    Area: 272,046 Km2

    Population: 14,306,876 (2010 census)

    Density: 53.8/ Km2

    Official language: Spanish

  • 8/3/2019 Session 4 Ecuador Final 231111

    3/24

    WHAT IS THE E-GP

    SYSTEM IN ECUADOR?

  • 8/3/2019 Session 4 Ecuador Final 231111

    4/24

    OBJECTIVES

    Quality of public spendingTransparencyDynamics of national productionParticipation of SMEsModern, quick and simple procurement processCitizen oversightReliable and competitive suppliersCoordination of public procurement with thegovernment's planning & budgeting systems

  • 8/3/2019 Session 4 Ecuador Final 231111

    5/24

    QUALITY OF PUBLIC SPENDING

  • 8/3/2019 Session 4 Ecuador Final 231111

    6/24

  • 8/3/2019 Session 4 Ecuador Final 231111

    7/24

  • 8/3/2019 Session 4 Ecuador Final 231111

    8/24

    Do you think that the

    existence and use of the

    public procurement

    portal has generated

    resource savings in your

    organization?

    Amount per year$82,690 each entity$29,677 eachsupplierSource: Survey HexagonTools, Hexagon Group (2011)

    90%

    61%

    10%

    39%

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    SI

    NOYesNo

    ENTITIES SUPPLIERS

    RESOURCE SAVINGS

  • 8/3/2019 Session 4 Ecuador Final 231111

    9/24

    TRANSPARENCY

  • 8/3/2019 Session 4 Ecuador Final 231111

    10/24

    CHANGES

    CAUSED BY

    REFORM

    56.7%

    YEAR

    2010

    70.0%

    YEAR

    2002

    13.3%

    SOURCE: First National Validated self-assessment,

    OECD-DAC methodology

  • 8/3/2019 Session 4 Ecuador Final 231111

    11/24

    DYNAMICS OF NATIONALPRODUCTION

    &PARTICIPATION OF SMEs

  • 8/3/2019 Session 4 Ecuador Final 231111

    12/24

    Source: INCOP* The information is current as of September 2011

    High participation of

    small & mediumenterprises in Public

    Procurement

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    2008 2009 2010 2011*

    38%

    52%

    73%

    61%

    Percentage awarded to SMEs inPublic Procurement

  • 8/3/2019 Session 4 Ecuador Final 231111

    13/24

    MODERN, QUICK AND SIMPLEPROCUREMENT PROCESS

  • 8/3/2019 Session 4 Ecuador Final 231111

    14/24

    SINGLE POINT

    CONNECTION

    Before the law With the law

    Public Institutions Suppliers

    y

    Public Institutions Suppliers

  • 8/3/2019 Session 4 Ecuador Final 231111

    15/24

    Open source software was used to develop the

    informational portal and the Official Procurement

    System(transactional) of Ecuador

  • 8/3/2019 Session 4 Ecuador Final 231111

    16/24

    Publication

    1 day

    Question andAnswers

    10 days

    bidsubmission

    15 days

    Analysis ofproposals

    10 days

    Awards

    1 day

    Signing ofContract

    5 days

    Publications

    1 day

    Questions andAnswers

    2 days

    Technical bidsubmission

    2 days

    Qualification

    1 day

    Bid

    1 day

    Award

    Signing ofcontract

    2 days

    TIME TO CARRY OUT A

    PROCUREMENT PROCESS

    Publication

    3 days

    Delivery ofproposals

    48 days

    Analysis ofproposals

    10 days

    Clarifications

    5 days

    Award

    10 days

    Notificationof results

    3 days

    PreviousReports

    15 days

    Signing ofContract

    20 days

    114 days

    42 days

    Develop specifications and Resolution

    1 day

    Contract

    1 day

    9 days

    Bidding before 2008

    Current bidding

    Electronic Inverse auction

    Electronic Catalog (Shopping Cart)2 days

  • 8/3/2019 Session 4 Ecuador Final 231111

    17/24

    CITIZEN OVERSIGHT

  • 8/3/2019 Session 4 Ecuador Final 231111

    18/24

    SOURCE: INCOP

    26 citizen oversightagreements

    313 procurementprocesses have beenmonitored by overseers.

  • 8/3/2019 Session 4 Ecuador Final 231111

    19/24

    SOURCE: INCOP

  • 8/3/2019 Session 4 Ecuador Final 231111

    20/24

    RELIABLE ANDCOMPETITIVE SUPPLIERS

  • 8/3/2019 Session 4 Ecuador Final 231111

    21/24

    Source: CONTRATANET INCOP* The information is current as of September 2011

    SUBSTANTIAL INCREASE IN

    SUPPLIERS AND ENTITIES

    6,000

    486

    SUPPLIERS

    47,209

    5,254

    ENTITIES

    BEFORE 2008 NOW

  • 8/3/2019 Session 4 Ecuador Final 231111

    22/24

    COORDINATION OF PUBLICPROCUREMENT WITH

    GOVERNMENTs PLANNING &

    BUDGETING SYSTEMS

  • 8/3/2019 Session 4 Ecuador Final 231111

    23/24

    SOURCE: INCOP

    INCOP

    SRI-tax

    IESS-social

    security

    ESIGEF-budget

    system

    linking with other Public

    Entities networks for the

    mutual exchange of

    information.

  • 8/3/2019 Session 4 Ecuador Final 231111

    24/24

    THANK YOUwww.compraspublicas.gob.ec