12
Experience with the verification procedure Options for a future operation of JI JI roundtable and JISC 22 Bonn, 14 - 16 June 2010 Lennard de Klerk Chair JIAG JIAG

Session III 3 DeKlerkMicrosoft PowerPoint - Session III_3_DeKlerk.pptx Author: Ishmukhametov Created Date: 6/14/2010 4:35:34 PM

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Session III 3 DeKlerkMicrosoft PowerPoint - Session III_3_DeKlerk.pptx Author: Ishmukhametov Created Date: 6/14/2010 4:35:34 PM

Experience with the

verification procedure

Options for a future operation of JI

JI roundtable and JISC 22

Bonn, 14 - 16 June 2010

Lennard de Klerk

Chair JIAG

JIAG

Page 2: Session III 3 DeKlerkMicrosoft PowerPoint - Session III_3_DeKlerk.pptx Author: Ishmukhametov Created Date: 6/14/2010 4:35:34 PM

Content

1. Introduction

2. Merging Track 1 & Track 2

3. Issuance of ERUs

4. Additionality

5. Governance of JI

6. Providing certainty inside and outside the EU

2

Page 3: Session III 3 DeKlerkMicrosoft PowerPoint - Session III_3_DeKlerk.pptx Author: Ishmukhametov Created Date: 6/14/2010 4:35:34 PM

Introduction

JIAG has made several suggestion how to design JI in a post-2012 regime.

Two papers were published before CMP4 in Poznan and CMP5 in Copenhagen

JIAG welcome the mandate given by CMP5 of the JISC to propose suggestions for the future operation of JI in a post-2012 regime

3

Page 4: Session III 3 DeKlerkMicrosoft PowerPoint - Session III_3_DeKlerk.pptx Author: Ishmukhametov Created Date: 6/14/2010 4:35:34 PM

Merging Track 1 and Track 2

Some observations:

• The JISC guidance for baseline setting and monitoring has become the ‘de facto’ standard for JI, including Track 1 projects.

• Furthermore Host Country Track 1 regulations all require PDD, determination, monitoring and verification.

• Hence we believe there is no need for two separate tracks or at least should be aligned, taking the best of ‘both worlds.

Minimum requirements should be set, being:

• A baseline should be set presenting the most plausible scenario in absence of the project;

• The baseline and monitoring plan should be determined by an AIE;

• Reductions should be monitored and verified by an AIE.4

Page 5: Session III 3 DeKlerkMicrosoft PowerPoint - Session III_3_DeKlerk.pptx Author: Ishmukhametov Created Date: 6/14/2010 4:35:34 PM

Issuance of ERUs

Project Developers see a political risk in the issuance of ERUs (compared to the CDM).

JIAG proposed that, after the Host Country approved the project,the equivalent amount of AAUs is set aside in a registry of the JISC.

After verification the AAUs will be automatically converted into ERUs and transferred upon instructions of the Focal Point appointed by the Project Participants.

Should no reductions have been generated the AAUs will be returned to the Host Country.

5

Page 6: Session III 3 DeKlerkMicrosoft PowerPoint - Session III_3_DeKlerk.pptx Author: Ishmukhametov Created Date: 6/14/2010 4:35:34 PM

No additionality in JI

JIAG believes that additionality can and should be taken out as a requirement.

Environmental integrity is guaranteed as for each issued ERU an AAU is cancelled.

It is up to the Host Country to use JI as a policy instrument to reduce emissions and promote investments in energy efficiency, technology transfer and sustainable development.

(Currently JI Track 1 can be seen as policy instrument)

As a service JISC can provide guidance for those Host Countries that, on a voluntary basis, would like to have an additionality test 6

Page 7: Session III 3 DeKlerkMicrosoft PowerPoint - Session III_3_DeKlerk.pptx Author: Ishmukhametov Created Date: 6/14/2010 4:35:34 PM

Governance of JI

The continuation of the JISC is essential to:

• Accredit Independent Entities

• Set generic guidance on baseline setting and monitoring

Members of the JISC should have practitioners on board, for example:

• One third representing Parties

• One third representing AIEs

• One third representing Project Participants

7

Page 8: Session III 3 DeKlerkMicrosoft PowerPoint - Session III_3_DeKlerk.pptx Author: Ishmukhametov Created Date: 6/14/2010 4:35:34 PM

Providing certainty within the EU

The conclusion and entry into force of a new international agreement will take 3-5 years. To provide some to investors in JI projects within the EU, the Commission can do the following:

• Enact on Article 24a of the ETS directive allowing for non-ETS domestic offsets;

• Article 24a reads: ….measures for issuing allowances or credits in respect of projects administered by Member States that reduce greenhouse gas emissions not covered by the Community scheme may be adopted.”

We strongly advice the European Commission to use the JI as blueprint for the non-ETS domestic offsets!

8

Page 9: Session III 3 DeKlerkMicrosoft PowerPoint - Session III_3_DeKlerk.pptx Author: Ishmukhametov Created Date: 6/14/2010 4:35:34 PM

Providing certainty with EU neighbours

To provide some certainty to investors in JI projects outside the EU, the Commission can do the following:

• Conclude Bilateral agreements with neighbouring countries recognizing reductions from JI projects;

• The directive read that in case an int’l agreement is not concluded by 31 December 2009: …..through agreements with third countries. Such agreements could enable projects to continue to be recognised in the Community scheme that generated ERUs until 2012 but are not longer able to do so under the Kyoto framework.

This will enable strategic investments in technology transfer and energy efficiency to increase the security of energy supply by and through the direct neighbours of the EU!

9

Page 10: Session III 3 DeKlerkMicrosoft PowerPoint - Session III_3_DeKlerk.pptx Author: Ishmukhametov Created Date: 6/14/2010 4:35:34 PM

Providing certainty by the JISC

After 31 December 2012 but before the end of the ‘true-up’period, there is a possibility to continue to issue ERUs and usethem for compliance. To provide certainty to investors we ask the JISC to recommend COP/MOP the following:

1. Emission reductions generated after 31 December 2010 can be verified both under track 2 and track 1 procedures;

2. Have confirmed that, based on these verifications, AAUs from the first commitment period can be converted into ERUs;

3. That these ERUs can be used for compliance purpose of the first commitment period.

10

Page 11: Session III 3 DeKlerkMicrosoft PowerPoint - Session III_3_DeKlerk.pptx Author: Ishmukhametov Created Date: 6/14/2010 4:35:34 PM

+ 100 days after the date set by CMP

Extension of crediting period within UNFCCC framework

11

1st commitment period (CP1)

2008 2009 2010 2011 2012 2013 2014 2015

Host PartyAssigned Amount Units for CP1

Additional period for fulfillment commitments

100 000 ER

2008 2009 2010 2011 2012 2013 2014 2015

Project commissioning

50 K ER 100 000 ER 100 000 ER 50 K

ER

By 15 April: Inventory for 2012 and the entire CP1

max 1 yearReview Process

Transfer and acquisition of AAUs, ERUs, CERs and RMUs of CP1

Page 12: Session III 3 DeKlerkMicrosoft PowerPoint - Session III_3_DeKlerk.pptx Author: Ishmukhametov Created Date: 6/14/2010 4:35:34 PM

12

Contacts JIAG

Global Carbon BV (chair) Lennard de Klerk

Climate Focus (secretariat) Jelmer HoogzaadMoritz von Unger

Core Carbon Group Morten Prehn Sorensen

Vertis Environmental Finance James Atkins

Carbon Trade & Finance Ingo Ramming

Future Camp Roland Geres

Greenstream Hanna-Mari Ahonen

Web: www.jiactiongroup.com