    Sheet Pile Installation Methodology

    IVCC ENGINEERING (PVT) LIMITED

    BALLOKI REHABILITATION WORKS

    METHOD STATEMENT FOR INSTALLATION OF SHEET

    PILES

    The following major items of Plant and Equipment are required for the installation of

    sheet piles.

    i. 65 Ton Crawler mounted crane

    ii. 50 90 Ton Vibratory Hammer w/power pack.

    iii. BSP Type Pneumatic Pile driving hammer

    w/compressor and suitable lead.

    iv. Total Station for surveying.

    v. Suitable pitching frame / leader.

    The first step in the construction of a sheet pile wall is the installation of the pitching

    frame. This is required to ensure the verticality and alignment of the piles during their

    driving. The pitching frame is installed with accuracy using appropriate surveying tools.

    The installation of the pitching frame is done in the same alignment as the sheet pile wall

    to be installed.

    Once the pitching frame is in place 10-12 sheet piles are pitched in it. The crawler

    crane is used for handling and pitching of the sheet piles. The piles are joined together

    by placing the thumb of one pile into the fingers of the previously placed piles. After a set

    of piles has been joined the driving hammer is used to drive the pitched piles to approx.

    1/3 of their length. Then the next set of piles are pitched/joined and driven to a depth at

  • 7/31/2019 Sheet Pile Methodology

    2/2

    IVCC Engineering (PVT) Limited

    Sheet Pile Installation Methodology

    which resistance is encountered. In this way the last (and partly driven) pile of the

    previous set serves as the guide pile for the next panel. Thus enabling us to pitch the

    rest of the piles without the use of the pitching frame. However if it is necessary the

    pitching frame can be extended for each subsequent set of piles. We then go back

    to the initial set of piles and drive them further. This procedure is repeated till all the

    piles are driven to the required depth. Throughout this whole operation the

    verticality and alignment of the piles will be checked periodically with the use of a plumb

    line and surveying instruments.