Shepard Energy Centre

Shepard Energy Centre. Environmental Stewardship

Embed Size (px)

Citation preview

Shepard Energy Centre

Environmental Stewardship

Overview

Nominal 800 MW Natural Gas Combined CycleEarly 2011 Received Regulatory Approval (Alberta Utilities Commission and Alberta Environment and Sustainable Resource Development) Cost: Approximately 1.35 BillionJoint Venture with Capital PowerCurrently under construction COD: Early 2015

4

TechnologyVideoNatural Gas Combined Cycle2 on 1 Mitsubishi 501G gas turbine

Environmental Attributes - Low Air Emissions

GHG – Less that 0.4 tonnes/MWh (less than half of the emissions from Coal)SOx – Virtually noneNOx – Shepard will only emit between 3 ppm and 6 ppmPM – virtually noneMercury – No mercury emissionsWe did extensive air dispersion modeling and Shepard has minimal impact on air quality in the region.

Environmental Attributes - Water Consumption

Plant MW ML/y ML/MW Comment

Keephills 766 16000 20.9 Inefficient

Battle River 663 6019 9.1 More efficient

Shepard 800 3796 4.7 Very efficient due to plant design and uses reclaimed water

Shepard Site Photos – April 2013

Aerial View Looking South

Shepard Site Photos – April 2013

Fiberglass Cooling Tower Showing End Wall And Louver Installation

Shepard Site Photos – April 2013

HRSG #2 Finger Rack Area

Shepard Site Photos – April 2013

Combustion Turbine #1

Shepard Site Photos – April 2013

Low Pressure Steam Turbine Rotor Insertion