Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Sh'ma L'kehila: Listen to the Community Feasibility Study Snapshot
1
Congregation Snapshot: Membership, Programs, Financials
Membership and Programs
B’nai Havurah is a congregation experiencing strong growth. Over
the last three years, membership has increased by 20% and
collected dues have increased by 8%. This demonstrates the
growth potential and future demand for space within the
congregation. The table to the right illustrates this growth.
B’nai Havurah’s programs are at the heart of the community. The
following chart shows three years of religious school attendance
by age. Class sizes are under 15, however at each grade level, classes are showing upward trends. It should be noted that B’nai
Havurah’s religious school has 12 students (pre-K to 5th grade) from Rodef Shalom congregation in 2015. However, these students will not
be returning for the 2016-2017 school year.
B’nai Havurah Religious School Attendance
Pre-K K 1st 2nd 3rd 4th 5th 6th 7th 8th 9th 10th
2013/2014 9 1 9 5 4 11 9 8 10 9 0 0
2014/2015 6 9 3 9 9 6 11 9 9 4 9 0
2015/2016 8 5 14 11 8 13 10 12 7 3 3 7
Relatively few life-cycle event ceremonies are currently held on site.
Based on comments heard during the listening phase, this is largely due
to concerns about the aesthetics and functionality of the current facility,
suggesting that an improved facility may attract more events.
Since Bat and Bar Mitzvah’s are such important life cycle events, we
examined them specifically. The table to the right illustrates B’nai Mitzvah
totals for the past three years. Over the past three years, B’nai Havurah has
had 32 Bat and Bar Mitzvahs. The average on-site Bat and Bar Mitzvah has been smaller than those held off-site. See the table to the right for
average invitation and attendance for 2013-2015. It is also relevant to point out that none of the Bat/Bar Mitzvahs have held a post-party on-site
in the last three years.
1 Program Income- Membership Dues, and Program Service Fees 2 Rental revenues were identified as a line item to be eliminated in each option evaluated
B’nai Membership and Dues
2013 2014 2015
Dues $249,118 $258,627 $273,900
Collected $240,383 $256,018 262,840
# Members (Households) 216 234 259
2013 2014 2015
B’nai Mitzvah Total 8 9 15
B’nai Mitzvah On-site 5 2 6
Oneg Shabbat On-site 5 2 6
B’nai Mitzvah Post-party On-site 0 0 0
B'nai Havurah Financial Summary
2013 2014 2015
Income
Actual Actual Actual
Program Income1 $272,567 $292,629 $345,614
Contributed Support $133,540 $143,723 $118,012
Special Events Income $25,661 $35,968 $46,000
Rentals2 $25,022 $27,532 $20,794
Investments
$0 $0
Other $45,472 $14,504 $10,181
Total: $502,262 $514,356 $540,601
Sh'ma L'kehila: Listen to the Community Feasibility Study Snapshot
2
Financial Position
In order to better understand B’nai
Havurah’s capacity for a facility
project, we completed a review of
B’nai Havurah’s financial statements
for the last three years. See chart to
the right for summary.
Facility Feasibility Snapshot
Four options were considered in the
feasibility study:
Option 1 – Renovate 6445 E. Ohio
Ave. This option preserves the
existing footprint of the current
facility, but reconfigures the floorplan
to make it more functional and to use
space more efficiently.
Option 2 – New Build at 6445 E. Ohio Ave. This option assumes the current facility is demolished and in its place a new 13,783 square
foot building with two floors is constructed. This option provides B’nai Havurah with a completely new facility, oriented to Ohio Avenue to
better utilize the site area
Option 3 – Sale of Ohio Ave and Acquisition of New Property. This option assumes the sale of the East Ohio Avenue property and
acquisition of a new building. A proxy property was identified during this engagement at 2015 S. Pontiac Way with an asking price of
$1,575,000 for a two story 19,373 square foot building. Whether B’nai Havurah purchases the building at Pontiac Way or another of
similar size, this option would afford the congregation a significantly larger sanctuary, larger social hall, more classrooms and still have
additional space for flexible use or income-generation from tenants.
Option 4 – Share Space at Central Christian Church. B’nai Havurah has a strong relationship with Central Christian Church due to the
history of using this facility for High Holy Days. There is an option to share under-utilized space at the church on a year-round basis. This
option could also provide a temporary location during any disruption to use of the existing building during renovation or new build. Note:
Due to the fact that B’nai Havurah would utilize the building on Sundays for Religious School and adult programming, the FTF and NCN
determined that this was not a feasible option, other than to consider this a temporary solution while waiting for a new or renovated space
to be completed.
New Option 4 – Land Acquisition and New Build This option assumes the purchase of a parcel of 1 – 2 acres of land on property within
Denver. We have had discussions with Denver Jewish Day School at 2450 S. Wabash Street. They have land available for sale at $13 per
acre and we are researching the buildability of the land. The purchase of 1 acre (43,560 sf) of land would cost $566,290. An advantage of
the this option is that we would be the use their classrooms for our Religious School programs on Sunday In addition and have access to
their gymnasium, playground and soccer fields. In turn, DJDS would like to use sanctuary for school-related programming during the
weekday. Finally, joint-programming may enrich both groups’ programing. Based on our work on Option 2 (level and build a new building
on our existing site), a new building without classrooms and hallway space would be about $7,500 square feet. At a cost of $277 psf (see
Option 1). The cost would be $2.1M.
3 In 2013, payroll was combined with contract services
Expense
2013 2014 2015
Payroll $320,268 $305,688 $311,634
Contract Services $03 $39,340 $41,840
Operations $54,538 $63,294 $72,165
Awards & Grants $0 $0 $7,896
Facilities & Equipment $65,182 $66,557 $68,623
Business Expenses $28,777 $31,195 $20,762
Travel & Meetings $0 $0 $2,288
Total: $468,765 $506,074 $525,208
Surplus/Deficit: $33,497 $8,282 $15,393
Sh'ma L'kehila: Listen to the Community Feasibility Study Snapshot
3
The following chart summarizes each option among twelve criteria (Option 4 hereafter represents land acquisition and new build, hereafter):
Square Footage – Option 1 has the smallest square footage and Option 3 or 4 (purchase land and build) has the most
Timing – The time to complete each option varies from Option 1 which would require the least, to Option 4, which would require the most.
Estimates on timing are included in the cost estimates in the Appendix.
Sanctuary Plus Overflow Seating – Option 4 has the most seating, Option 1 has the least.
Event Seating – is similar across all four options.
Classroom/Flexible Space – Ranges from a low of 7 to a high of 14+ across options including the library and social hall areas. As of this
writing, Option 4 classroom space has not been specified.
Parking – Option 3 or 4 has the most and Option 1 has the least.
Price – Option 1 involves the lowest cost and Option 3 and 4 has the highest (although in Options 3 and 4, the proceeds from the sale of
Ohio Avenue would offset the cost considerably).
Cost Per Square Foot – Option 1 has the lowest cost per square foot.
Funds to be Raised – Option 1 would likely require the least amount of fundraising since it is a rental option and Option 4 has the most
funds to be raised.
Note: Additional costs including closing costs, architectural fees, interest are included in costs. We selected a very conservation loan amount of $400,000 for Options 1 and 2 and $300,000 for Options 3 and 4. The scenarios presented are one of many financial approaches and strategies.
Detailed budgets include expenses for building operations.
Option 1 – Renovate
(Ohio Ave)
Option 2 – New Build
(Ohio Ave)
Option 3 – Building
Acquisition
Option 4 – Land
Acquisition +
build w/o
classrooms
Option 4 A – Land
Acquisition and
build w/
classrooms
Square Footage 10,508 13,783 19,373 7,500 13,783
Timing
Sanctuary + Overflow 300 330 350-400*
(250 chapel+library)
330 330
Event Seating @ Round
Tables
240 260 250-300 (210 in
chapel+library)
260 260
Class/Flex Spaces 7 (10 max) 10 (14 max) 9 (14 max) 0 10 (14 max)
Parking 20 23 66 150 150
Price $$ $$$ $$$ $$$$ $$$$
Project Cost $ $1.9M $3.8M $4.0M $566K Land+
$2.1M Bldg.=
$2.7M
$566K Land +$3.8M
Bldg.+ = $4.4M
Cost PSF $179 $277 $206 290 (with land) $290 (with land)
Funds to be Raised after
Financing & Sale of Ohio
Bldg.
$1.5M
(assumes $400K loan)
$3.4M
(assumes $400K loan)
$2.7M
(assumes $1M Ohio
Bldg. and $300K loan)
$1.4M
(assumes $1M
from Ohio Bldg.
and $300K loan)
$3.1 M
(assumes $1M from
Ohio Bldg. and $300
loan)
Per Year if 3YR Campaign $500K $1.07M $833K $467K $1.03M
Per Year if 5 YR Campaign $300K $640K $500K $280,000 $620K
Sh'ma L'kehila: Listen to the Community Feasibility Study Snapshot
4
East Ohio Background:
The one-story building that B’nai Havurah calls home was
constructed in 1980 as a multi-tenant office building. The
congregation has owned and occupied the building for 20 years, and
has remodeled the interior at various times to accommodate
evolving needs and growth. A portion of the building’s 10,508
square feet has been continually leased since B’nai purchased the
building in 1995. The property is approximately .48 acres.
The building is assumed to be constructed of concrete block exterior
walls with a low-sloped, trussed roof structure and a non-structural
overhanging fascia. Numerous roof-top units provide heating and
cooling to the building.
Renovations/Changes: Option 1 evaluates the existing building’s physical capacity to meet the congregation’s needs within its current one-story, 10,508 square foot
East Ohio location. The concept plan reconfigures all interior spaces to optimize adjacencies, flow and flexibility while retaining all exterior roof
and wall locations. A second floor or “pop-top” was not explored in this option. Since the exterior still reflects its 1980’s medical office
beginnings, Option 1 would also include enhancements to the building’s exterior to better reflect the character and spirit of the congregation
within.
The plan organization carefully considers the congregation’s current and future programmatic needs and desires including a more visible and
accessible entrance, enhanced flexibility of interior spaces, a dedicated catering kitchen and additional classrooms to accommodate
educational programming for children and adults.
The following are the primary assumptions of this plan:
1. Plan assumes full removal of existing interior improvements and full reconfiguration of interior spaces.
2. Main entrance is relocated to the east to allow for a new covered entry, easier access from the parking lot.
3. New covered entry at the revised main entry location for increased safety and shelter from the elements.
4. Increased size of sanctuary to comfortably seat 150.
5. Contiguous overflow spaces that double as additional sanctuary seating, classrooms, meeting and event spaces. Expands sanctuary.
6. Provide a lobby space where people can gather, wait for a meeting or a ride with visibility to the parking lot.
7. Provide a dedicated catering kitchen adjacent to event space for easy access.
8. Provide a centrally located library with additional shelving for collections which also serves as larger meeting space for movies, education,
board meetings.
9. Administrative offices are located together near the front entry for visibility and security.
10. Recaptures leased space to provide seven uniformly- sized classrooms to accommodate 20-25 children.
11. Provide ADA accessible restrooms in a central location along with a family restroom in the classroom wing.
12. All spaces to be designed to ADA standards.
13. Utilize 3-4 parking spaces for small green space, garden/ play space at new front entry.
14. Provide new energy efficient windows and doors throughout.
15. Provide sound attenuating, operable partitions between sanctuary and overflow spaces.
16. Update HVAC configuration for revised plan configuration.
17. Enhance lighting and sound system.
18. Install a sprinkler system for fire suppression.
19. Reduces parking spaces to 20. A shared parking agreement with the adjacent bank or other businesses could provide additional spaces
when the demand is great.
Timing: The project timeline shows a 20 month total project period. The first 13 months would be used for fundraising, as well as building the project
team including owner’s representative, design team, construction documents, general contractor, bids, and utility services. Construction is
estimated to take six months including installation of furniture, fixtures and equipment.
Sh'ma L'kehila: Listen to the Community Feasibility Study Snapshot
5
Option 1 - Summary
Pros Cons
High value because it accomplishes most of the design
objectives for the lowest cost.
Parking meets code but could be insufficient if congregation
grows.
Maintains current location and is the most modest in scope
(haimish).
Outdoor space is limited.
Easier to renovate a building you know than one you haven’t
occupied.
Large events will require reconfiguration of social hall
(moving tables and chairs).
Option 1 – Renovation of 6445 East Ohio Avenue, Sample Layout
Sh'ma L'kehila: Listen to the Community Feasibility Study Snapshot
6
Project Budget- Option 1
USES OF FUNDS Cost Estimate Cost Per
Square Foot % of Total
Sitework & Demolition $69,304 $6.60 4%
Concrete $23,750 $2.26 1%
Masonry $0 $0.00 0%
Metals $38,585 $3.67 2%
Wood & Plastics $129,958 $12.37 7%
Thermal & Moisture Protection $106,313 $10.12 6%
Doors & Windows $159,500 $15.18 9%
Finishes $213,554 $20.32 12%
Specialties $20,850 $1.98 1%
Equipment $12,000 $1.14 1%
Furnishings $28,300 $2.69 2%
Special Construction $0 $0.00 0%
Conveying Systems $0 $0.00 0%
Mechanical $194,398 $18.50 10%
Electrical $157,620 $15.00 9%
General Conditions $92,331 $8.79 5%
Contractor’s Fee (6%) $74,788 $7.12 4%
Construction Total: $1,321,251 $125.74 71%
Soft & Miscellaneous Costs $230,202 $21.91 12%
Furniture, Fixtures & Equipment $103,750 $9.87 6%
Subtotal: $1,655,203 $157.52 89%
Project Contingency (10%) $165,520 $15.75 9%
Moving (2x) $20,000 $1.90 1%
Temporary Location (6 months) $12,000 $1.14 1%
$1,852,723 $176.32 100%
Total Gross Square Footage:
10,508
SOURCES OF FUNDS
Per Square Foot
% of Total
Contributed Capital
Equity from Ohio Avenue $0 $0.00 0%
Capital Campaign $1,552,723 $147.77 84%
Debt
Conventional Financing $300,000 $28.55 16%
$1,852,723 $176.32 100%
Sh'ma L'kehila: Listen to the Community Feasibility Study Snapshot
7
Cash Flow – Option 1
2% = inflation factor for Income 2% = inflation factor for Expenses
2013 2014 2015 2016 2017 2018 2019 2020 2021
Income Actual Actual Internal Projected Projected Projected Projected Projected Projected
Program Income $272,567 $292,629 $345,614 $352,526 $359,577 $366,768 $374,104 $381,586 $389,217
Contributed Support $133,540 $143,723 $118,012 $120,372 $122,780 $125,235 $127,740 $130,295 $132,901
Special Events Income $25,661 $35,968 $46,000 $46,920 $47,858 $48,816 $49,792 $50,788 $51,803
Capital Campaign $0 $0 $0 $517,574 $517,574 $517,574 $0 $0 $0
Rentals $25,022 $27,532 $20,794 $20,794 $0 $0 $0 $0 $0
Additional Income/Fundraising $0 $0 $0 $0 $40,000 $40,000 $40,000 $40,000 $40,000
Investments $0 $0 $0 $0 $0 $0 $0 $0 $0
Other $45,472 $14,504 $10,181 $10,385 $10,592 $10,804 $11,020 $11,241 $11,465
Total: $502,262 $514,356 $540,601 $1,068,572 $1,098,382 $1,109,198 $602,656 $613,909 $625,387
Expense
Payroll $320,268 $305,688 $311,634 $317,867 $324,224 $330,708 $337,323 $344,069 $350,950
Contract Services $0 $39,340 $41,840 $42,677 $43,530 $44,401 $45,289 $46,195 $47,119
Operations/Awards/Grants $54,538 $63,294 $72,165 $73,608 $75,080 $76,582 $78,114 $79,676 $81,270
Awards & Grants $0 $0 $7,896 $8,054 $8,215 $8,379 $8,547 $8,718 $8,892
Facilities & Equipment $65,182 $66,557 $68,623 $69,995 $71,395 $72,823 $74,280 $75,765 $77,281
Facility Project-Renovation - - - - $1,552,722 - - - -
Debt Service - - - $24,079 $24,079 $24,079 $24,079 $24,079 $24,079
Capital Reserve ($.75 PSF)
$7,881 $7,881 $7,881 $7,881 $7,881
Business Expenses $28,777 $31,195 $20,762 $21,177 $21,601 $22,033 $22,473 $22,923 $23,381
Travel & Meetings $0 $0 $2,288 $2,334 $2,380 $2,428 $2,477 $2,526 $2,577
Total: $468,765 $506,074 $525,208 $559,791 $2,131,108 $589,315 $600,462 $611,832 $623,429
Surplus: $33,497 $8,282 $15,393 $508,781 -$1,032,726 $519,883 $2,194 $2,077 $1,958
Cumulative Surplus/Deficit: $41,779 $57,172 $565,953 -$466,774 $53,110 $55,304 $57,381 $59,339
Surplus: $33,497 $8,282 $15,393
Average Monthly Available: $2,007 Add Back Depreciation & Amortization: $9,837 $9,837 $9,837 Assumed Interest Rate: 5.5%
Available for Debt Service: $43,334 $18,119 $25,230 Assumed Term (# months): 240 Available with 1.2 DSC: $36,112 $15,099 $21,025 Assumed Square Footage: 10,508 Average Annual Available: $24,079
Sh'ma L'kehila: Listen to the Community Feasibility Study Snapshot
8
Option 2 – New Build
Summary
Option 2 explores the impact of demolishing the
existing B’nai Havurah building and constructing a
new building for the congregation on the existing .48
acre East Ohio site. This concept orients a 13,761
square-foot building to the south to maximize solar
exposure and to establish usable green space for a
garden or play area adjacent to the front entry. The
new-build concept includes an efficient and
functional 23-space parking lot with direct access to
a highly visible, covered main entry.
Once inside, the sanctuary and overflow areas are
configured within a one-story portion of the building (with higher ceilings) to emphasize the sacred nature of the space while
optimizing adjacencies, flow and flexibility throughout. High quality operable partitions would allow the sanctuary seating to
expand from 172 to 332 for large services or events. A large lobby (that could double as a gallery), centrally located library,
and dedicated catering kitchen are all organized around the primary sacred spaces for ease of access and use.
An adjacent two-story wing could accommodate the congregation’s stated educational and social programming for children
and adults with 10 uniformly-sized classrooms plus a teen lounge, a collaborative office arrangement, and enhanced
resource access and storage. All new construction would be designed and built to a high level of energy efficiency and per
ADA standards throughout.
Timing: The project timeline provided by Cliff Shumway shows a 25 month total project period. The first fourteen months would
be used for fundraising, as well as building the project team including owner’s representative, design team,
construction documents, general contractor, bids, and utility services. Construction is estimated to take ten months
including installation of furniture, fixtures, and equipment.
Option 2 - Summary
Pros Cons
Allows for additional space for growth and greater flexibility. Cannot utilize the equity in the building to fund this project.
Maintains current location. Parking meets code but could be insufficient if congregation
grows.
Enables complete re-imagining of the site and building
configuration
Highest per square foot cost.
Sh'ma L'kehila: Listen to the Community Feasibility Study Snapshot
9
Option 2 – New Build
Sh'ma L'kehila: Listen to the Community Feasibility Study Snapshot
10
Option 2 Project Budget
USES OF FUNDS Cost Estimate Cost Per
Square Foot % of Total
Sitework & Demolition $277,864 $20.16 7%
Concrete $221,454 $16.07 6%
Masonry $167,350 $12.14 4%
Metals $390,967 $28.37 10%
Wood & Plastics $158,577 $11.51 4%
Thermal & Moisture Protection $117,746 $8.54 3%
Doors & Windows $203,700 $14.78 5%
Finishes $360,510 $26.16 9%
Specialties $34,300 $2.49 1%
Equipment $12,000 $0.87 0%
Furnishings $47,350 $3.44 1%
Special Construction $0 $0.00 0%
Conveying Systems $45,000 $3.26 1%
Mechanical $318,387 $23.10 8%
Electrical $220,528 $16.00 6%
General Conditions $206,059 $14.95 5%
Contractor’s Fee (6%) $166,907 $12.11 4%
Construction Total: $2,948,699 $213.94 78%
Soft & Miscellaneous Costs $444,448 $32.25 12%
Furniture, Fixtures & Equipment $121,500 $8.82 3%
Subtotal: $3,514,647 $255.00 92%
Project Contingency (7%) $246,025 $17.85 6%
Moving (2x) $20,000 $1.45 1%
Temporary Location (10 months) $20,000 $1.45 1%
$3,800,672 $275.75 100%
Total Gross Square Footage:
13,783
SOURCES OF FUNDS
Per Square Foot
% of Total
Contributed Capital
Equity from Ohio Avenue $0 $0.00 0%
Capital Campaign $3,500,672 $253.98 92%
Debt
Conventional Financing 300,000 $21.77 8%
$3,800,672 $275.75 100%
Sh'ma L'kehila: Listen to the Community Feasibility Study Snapshot
11
Cash Flow – Option 2
2% = inflation factor for Income 2% = inflation factor for Expenses
2013 2014 2015 2016 2017 2018 2019 2020 2021
Income Actual Actual Internal Budget Projected Projected Projected Projected Projected
Program Income $272,567 $292,629 $345,614 $352,526 $359,577 $366,768 $374,104 $381,586 $389,217
Contributed Support $133,540 $143,723 $118,012 $120,372 $122,780 $125,235 $127,740 $130,295 $132,901
Special Events Income $25,661 $35,968 $46,000 $46,920 $47,858 $48,816 $49,792 $50,788 $51,803
Capital Campaign $0 $0 $0 $1,166,891 $1,166,891 $1,166,891 $0 $0 $0
Rentals $25,022 $27,532 $20,794 $20,794 $0 $0 $0 $0 $0
Additional Income/Fundraising $0 $0 $0 $0 $57,000 $57,000 $57,000 $57,000 $57,000
Investments $0 $0 $0 $0 $0 $0 $0 $0 $0
Other $45,472 $14,504 $10,181 $10,385 $10,592 $10,804 $11,020 $11,241 $11,465
Total: $502,262 $514,356 $540,601 $1,717,888 $1,764,698 $1,775,514 $619,656 $630,909 $642,387
Expense
Payroll $320,268 $305,688 $311,634 $317,867 $324,224 $330,708 $337,323 $344,069 $350,950
Contract Services $0 $39,340 $41,840 $42,677 $43,530 $44,401 $45,289 $46,195 $47,119
Operations and Awards & Grants $54,538 $63,294 $72,165 $73,608 $75,080 $76,582 $78,114 $79,676 $81,270
Awards & Grants $0 $0 $7,896 $8,054 $8,215 $8,379 $8,547 $8,718 $8,892
Facilities & Equipment ($6.91PSF) $65,182 $66,557 $68,623 $69,995 $88,349 $90,116 $91,918 $93,757 $95,632
Facility Project Renovation -less loan amt - - - - $3,500,672 - - - -
Debt Service - - - $24,079 $24,079 $24,079 $24,079 $24,079 $24,079
Capital Reserve ($.50 PSF)
$6,892 $6,892 $6,892 $6,892 $6,892
Business Expenses and Travel & Mtgs. $28,777 $31,195 $20,762 $21,177 $21,601 $22,033 $22,473 $22,923 $23,381
Travel & Meetings $0 $0 $2,288 $2,334 $2,380 $2,428 $2,477 $2,526 $2,577
Total: $468,765 $506,074 $525,208 $559,791 $4,095,022 $605,618 $617,111 $628,834 $640,791
Surplus: $33,497 $8,282 $15,393 $1,158,097 -$2,330,324 $1,169,896 $2,545 $2,075 $1,596
Cumulative Surplus/Deficit: $41,779 $57,172 $1,215,269 -$1,115,055 $54,841 $57,386 $59,461 $61,058
Surplus: $33,497 $8,282 $15,393 Average Monthly Available: $2,000
Add Back Depreciation & Amortization: $9,837 $9,837 $9,837 Assumed Interest Rate:
5.5%
Available for Debt Service: $43,334 $18,119 $25,230 Assumed Term (# months):
240
Available with 1.2 DSC: $36,112 $15,099 $21,025 Assumed Square Footage:
13,783
Average Annual Available: $24,079
Sh'ma L'kehila: Listen to the Community Feasibility Study Snapshot
12
Option 3 - Acquisition
Summary:
Option 3 explores the impact of renovating an
existing building to meet the congregation’s
programmatic and spiritual needs. For this
study, the Facilities Task Force identified a
two-story 19,373 square-foot vacant office
building on a one acre property in southeast
Denver.
By utilizing the bulk of the existing room
configurations, the proposed layout of B’nai’s
concept program yielded a plan with sufficient
space for nearly all desired synagogue functions, including an area large enough to hold larger life cycle events and High
Holy Day services along with larger annual events and celebrations. The building interior could be configured to achieve the
stated ideal program configuration where 225-250 people could be seated for a service in the “chapel” while the “social hall”
could accommodate an equal number for a seated meal without having to turn over the space.
The first floor could take advantage of an existing kitchen space adjacent to the sanctuary/ social hall and also
accommodate a large library for study, meetings, and movies. An elevator would be needed to provide full access to the
second floor.
The second floor could be configured to accommodate the entire religious school needs with 9+ classrooms along with
space for adult programming and a teen lounge. Sufficient storage areas could be located throughout the building to
accommodate book collections and resources. All restrooms would be updated to be ADA compliant. With existing 9’-0”
ceilings throughout the building, this plan proposes to raise the ceiling height in the chapel and in a selected area of the
sanctuary to enhance the sacred quality of these spaces. These modifications would require structural alterations to the
second floor and reduce the occupiable square footage on the second floor.
It’s assumed that green space around the building could accommodate garden and play space. No enhancements to the
building’s exterior, aside from additional exit doors as required by code, would be made.
Since this property was selected as a proxy for the acquisition of any larger building, the following information is meant to
provide guidance around design, fit and cost. If the Pontiac property is not available in the future, the concepts identified
here could be applied to another location.
Timing: The project timeline provided by Cliff Shumway shows a 20 month total project period. The first thirteen months would be
used for fundraising, as well as building the project team including owner’s representative, design team, construction
documents, general contractor, bids and utility services. Construction is estimated to take six months including installation
of furniture, fixtures, and equipment.
Option 3 - Summary
Pros Cons
Twice as much square footage would give a wide range of
options in terms of layout and accommodating larger
numbers in the sanctuary and social hall.
Ongoing operating costs double.
Additional parking. Much of the space may be idle much of the time.
Room for considerable growth. If Pontiac Way property becomes unavailable, then B’nai
Havurah will need to identify and compete in a real estate
market with escalating prices.
Current structural column locations may limit flexibility of use
in some spaces.
Sh'ma L'kehila: Listen to the Community Feasibility Study Snapshot
13
Option 3 - Acquisition
Sh'ma L'kehila: Listen to the Community Feasibility Study Snapshot
14
Budget – Option 3
USES OF FUNDS Cost Estimate Cost Per Square
Foot % of Total
Acquisition $1,575,000 $81.30 39%
Acquisition-Related Costs $50,000 $2.58 1%
Acquisition Total: $1,625,000 $83.88 41%
Sitework & Demolition $149,517 $7.72 4%
Concrete $13,250 $0.68 0%
Masonry $0 $0.00 0%
Metals $94,890 $4.90 2%
Wood & Plastics $77,857 $4.02 2%
Thermal & Moisture Protection $97,834 $5.05 2%
Doors & Windows $81,800 $4.22 2%
Finishes $343,077 $17.71 9%
Specialties $27,150 $1.40 1%
Equipment $12,000 $0.62 0%
Furnishings $48,500 $2.50 1%
Special Construction $0 $0.00 0%
Conveying Systems $45,000 $2.32 1%
Mechanical $271,222 $14.00 7%
Electrical $279,940 $14.45 7%
General Conditions $123,363 $6.37 3%
Contractor’s Fee (6%) $99,924 $5.16 2%
Construction Total: $1,765,324 $91.12 44%
Soft & Miscellaneous Costs $289,356 $14.94 7%
Furniture, Fixtures & Equipment $98,750 $5.10 2%
Subtotal: $3,778,430 $195.04 94%
Project Contingency (10%) $215,343 $11.12 5%
Moving (1X) $10,000 $0.52 0%
Temporary Location $0 $0.00 0%
$4,003,773 $206.67 100%
Total Gross Square Footage:
19,373
SOURCES OF FUNDS
Per Square Foot % of Total
Contributed Capital
Proceeds from Sale of Ohio Ave $1,000,000 $51.62 25%
Capital Campaign $2,703,773 $139.56 68%
Debt
Conventional Financing 300,000 $15.49 7%
$4,003,773 $206.67 100%
Sh'ma L'kehila: Listen to the Community Feasibility Study Snapshot
15
Cash Flow – Option 3
2% = inflation factor for Income 2% = inflation factor for Expenses
2013 2014 2015 2016 2017 2018 2019 2020 2021
Income Actual Actual Internal Budget Projected Projected Projected Projected Projected
Program Income $272,567 $292,629 $345,614 $352,526 $359,577 $366,768 $374,104 $381,586 $389,217
Contributed Support $133,540 $143,723 $118,012 $120,372 $122,780 $125,235 $127,740 $130,295 $132,901
Special Events Income $25,661 $35,968 $46,000 $46,920 $47,858 $48,816 $49,792 $50,788 $51,803
Capital Campaign $0 $0 $0 $901,258 $901,258 $901,258 $0 $0 $0
Rentals $25,022 $27,532 $20,794 $20,794 $0 $0 $0 $0 $0
Additional Income/Fundraising $0 $0 $0 $0 $100,000 $100,000 $100,000 $100,000 $100,000
Investments $0 $0 $0 $0 $0 $0 $0 $0 $0
Other $45,472 $14,504 $10,181 $10,385 $10,592 $10,804 $11,020 $11,241 $11,465
Total: $502,262 $514,356 $540,601 $1,452,255 $1,542,065 $1,552,881 $662,656 $673,909 $685,387
Expense
Payroll $320,268 $305,688 $311,634 $317,867 $324,224 $330,708 $337,323 $344,069 $350,950
Contract Services $0 $39,340 $41,840 $42,677 $43,530 $44,401 $45,289 $46,195 $47,119
Operations and Awards & Grants $54,538 $63,294 $72,165 $73,608 $75,080 $76,582 $78,114 $79,676 $81,270
Awards & Grants $0 $0 $7,896 $8,054 $8,215 $8,379 $8,547 $8,718 $8,892
Facilities & Equipment $65,182 $66,557 $68,623 $69,995 $117,804 $120,160 $122,564 $125,015 $127,515
Facility Project - Renovation (less loan amt) - - - - $2,703,773 - - - -
Debt Service - - - $24,079 $24,079 $24,079 $24,079 $24,079 $24,079
Capital Reserve ($.75 PSF)
$14,530 $14,530 $14,530 $14,530 $14,530
Business Expenses and Travel & Mtgs. $28,777 $31,195 $20,762 $21,177 $21,601 $22,033 $22,473 $22,923 $23,381
Travel & Meetings $0 $0 $2,288 $2,334 $2,380 $2,428 $2,477 $2,526 $2,577
Total: $468,765 $506,074 $525,208 $559,791 $3,335,217 $643,300 $655,394 $667,730 $680,312
Surplus: $33,497 $8,282 $15,393 $892,464 $1,793,152 $909,581 $7,262 $6,179 $5,075
Cumulative Surplus/Deficit: $41,779 $57,172 $949,636 -$843,516 $66,065 $73,327 $79,506 $84,580
Surplus: $33,497 $8,282 $15,393 Average Monthly Available: $2,000
Add Back Depreciation & Amortization: $9,837 $9,837 $9,837 Assumed Interest Rate:
5.5%
Available for Debt Service: $43,334 $18,119 $25,230 Assumed Term (# months):
240
Available with 1.2 DSC: $36,112 $15,099 $21,025 Assumed Square Footage:
19,373
Average Annual Available: $24,079
Sh'ma L'kehila: Listen to the Community Feasibility Study Snapshot
16
Option 4 – Land Acquisition with New Build on Denver Jewish Day School (DJDS) Property
Because this opportunity was recently discovered, B’nai Havurah has not developed a detailed plan.
More than one option as to where we might build
Use of DJDS’s classrooms would save us building expense
B’nai Havurah and DJDS operate during different times
About 20% of DJDS families with children in lower grades are not affiliated with a synagogue
DJDS families are in need on a sanctuary and social hall for B’nai Mitzvah
Cost per square foot to build is estimated at $277 per square foot (we used Option 2 as model)
Cost of land is $13/sf
Pros Cons
High value because we can design the space to our needs Working with another organization in regard to shared space
requires planning and careful consideration
Opportunity to share space, thus saving money Some may perceive location as too far from our demographic
core
Opportunity to partner with DJDS on programming Concern that we’d lose our identity
Parking is plentiful
Outdoor space is plentiful
Possible growth of membership Other?
Sh'ma L'kehila: Listen to the Community Feasibility Study Snapshot
17
Fundraising Feasibility Study Summary:
• Fundraising potential for renovation or construction has never truly been measured.
• Communal, modest and egalitarian nature of membership does not match the traditional “giving pyramid” for capital
campaigns but does not mean goal is out of reach.
• Possibilities of other revenue streams limited to borrowing and potential value from sale of current property.
• Contributions to campaign would be separate from dues and “other half/above and beyond” campaign.
• Strong willingness to donate – even from those already giving in multiple ways.
• Emphasis on only doing what is truly feasible not over-reaching or over-committing.
• A percentage of any campaign should support operational reserve for new building/growth.
• Preferred structure of 3-year pledges.
• Acceptable range of gifts from $1,500-$50,000 ($500/year - $16,666/year).
• At least half the membership need to commit to gifts at this level for the campaign to be successful.
• Involvement from the rest of membership to give to each one’s capacity.
• Any recognition must be consistent with policies of B’nai Havurah. For a campaign like this, many people expressed
desire to be recognized but willing to do it collectively and not by size of gift.
• No actual solicitations were completed.
• Interviews of 27 members suggest a minimum pledge amount of $225,000
• A stretch commitment from those interviews suggest a possible $450,000-$500,000
• Membership Interviews + Giving History Data + Membership Size = Potential Raise of $1,000,000 - $1,500,000
• Interviews do not support a higher goal.
Pledge Scenario to Reach $1.5 Million
Number of Pledges Pledge Amount Total for this level Cumulative Total
8 $50,000 $400,000 $400,000
5 $25,000 $125,000 $525,000
25 $15,000 $375,000 $900,000
20 $10,000 $200,000 $1,100,000
30 $5,000 $150,000 $1,250,000
50 $1,500 $75,000 $1,325,000
Remaining $25,000 from gifts
<$1,000
$25,000 $1,350,000
Additional Loan $150,000 $150,000 $1,500,000
Sh'ma L'kehila: Listen to the Community Feasibility Study Snapshot
18
Other Considerations:
As B’nai Havurah moves forward with its facility project, there are several considerations that should be part of the
ongoing process:
Competing capital campaigns – NCN and DSS are completing a nonprofit space survey that shows an upturn in capital
campaigns as nonprofits face an increasingly expensive rental real estate market. During the recession, many capital
campaigns were deferred and now many are being re-activated. The Jewish Community Center - Denver recently
announced a $50 million capital campaign. Various campaigns may or may not impact a B’nai Havurah campaign, but
a scan of competing demands on financial resources is important.
Alternate sites – this analysis makes assumptions about certain locations that may or may not be available when B’nai
Havurah is ready to proceed. Consideration of alternative sites may be necessary, and this may involve re-assessing
the timeline for various options. It is our goal that this analysis will provide a framework for evaluating other options not
considered here.
Shared space – if B’nai Havurah chooses an option that contains space that can be leased to others on a regular
basis, we have additional resources we can provide to support this arrangement if desired. Any facility should be
considered for its flexible use of space. As B’nai Havurah has generated rental income in the past, this is an approach
that can be beneficial on many levels. We recommend first satisfying B’nai Havurah’s needs in selecting a facility, but
are happy to provide assistance at a later date if shared space is something B’nai Havurah decides to pursue.
Conclusion
NCN believes that B’nai Havurah is poised for the next stage of its history. It is a growing congregation with increasing financial
sustainability. There is a consistent desire to develop a facility that better represents the community in terms of its aesthetics
and functionality. We have presented the opportunities and challenges for four different options, including design concepts, cost
estimates, and financial models. With the additional fundraising feasibility analysis provided by RDM Communications, B’nai
Havurah now has the information to collectively discern which option best meets all of its needs and to move forward and create
a new physical space that best reflects the community.