Upload
unknown
View
217
Download
0
Embed Size (px)
Citation preview
7/25/2019 Silver Bridge
1/58
Bridge Failures - Lessons learned
George A. Christian, P.E.Director, Office of Structures
New York State Dept. of Transportation
Bridge Engineering Course
University at Buffalo
March 29, 2010
7/25/2019 Silver Bridge
2/58
Bridge Failures Lessons Learned
Outline
Overview of Bridge Failures
Historic Failures in North America
Recent U.S. failures that impacted bridge engineering
practice
Lessons and Response
o
Recent NYSDOT BridgeFailure Investigations
oDealing with a failure
Part 1:
Part 2:
7/25/2019 Silver Bridge
3/58
My general lessons from bridge failures
Bridges can, and will fail, if not properly designed,
constructed and maintained
We may think we know everything to prevent
failures, but we do not. In hindsight, most failures could have been
prevented (but not all).
Failures generally result from a confluence ofcontributing events and/or underlying causes.
When it comes to underlying causes, history can
repeat itself.
7/25/2019 Silver Bridge
4/58
Honest human error in the face of the
unforeseenor the unforeseeableisultimately what brings bridges down.
J.Tarkov, Human Failure In, Bridge Failure Out,
Engineering Case Library report ECL 270, Carleton
University, CA
Two Historic Bridge Failures
7/25/2019 Silver Bridge
5/58
Quebec Bridge1800 ft. main span, collapsed Aug 29, 1907
Buckling Failure of compression
chord (A9L)inadequate latticing
7/25/2019 Silver Bridge
6/58
Quebec Bridge Collapse -Findings
Higher allowable stresses specified
Underestimated dead load ( 18% +/-)
Decision to lengthen span by 200 ft.
Error discovered but accepted
Financial pressures
Project Management issues
Ceding to Consulting Engineer reputation
Lack of experience on site
Communication failures
7/25/2019 Silver Bridge
7/58
Quebec Bridge Collapse -Findings
Lack of knowledge ofbehavior of large
compression members.
Lattice bracing proved to be
inadequate.
7/25/2019 Silver Bridge
8/58
Second Quebec Bridge - 1917
construction collapse Sept 1914
7/25/2019 Silver Bridge
9/58
Tacoma Narrows Bridge collapse- 1940
7/25/2019 Silver Bridge
10/58
Advancements in suspension bridge analysis (deflection theory)
Williamsburg Bridge
-1903
1600 ft. span, 40 ft.
deep stiffening truss
(Depth: span = 1:40)
Manhattan Bridge -1909
1470 ft. span, 27 ft. deep
stiffening truss (1: 54)
7/25/2019 Silver Bridge
11/58
1920s -- Highway suspension bridges become practical
Bear Mountain Bridge -1924
1632 ft. spanWurts Street Bridge,
Kingston, NY -1921
705 ft. span
7/25/2019 Silver Bridge
12/58
1930s--Landmark Bridges
Golden Gate Bridge - 19374200 ft. span, d:s = 1: 168
George Washington Bridge -1931
3500 ft. span, d:s = 1: 120
Originally opened with upper level
roadway only, no stiffening truss
d:s = 1: 350
7/25/2019 Silver Bridge
13/58
1930s: maximize structural efficiency, economy, aesthetics
Plate girder in place of truss for deck stiffening
7/25/2019 Silver Bridge
14/58
Bronx Whitestone
Bridge -1939
-- 2300 ft. span
-- 11 ft. girder
-- d:s = 1: 209
--77 ft. wide, w:s = 1:31
--BWB and other new
suspension bridges withshallow stiffening girders
exhibit wind-induced
Vertical oscillations
--Early retrofits
implemented
7/25/2019 Silver Bridge
15/58
Tacoma-Narrows Bridge--1940
--2800 ft. span--8 ft. girder
--d:s = 1: 350
--39 ft. width, w:s = 1:72
Problem with vertical
oscillations-
Retrofits:
Clamp cable to girder @midspan
Side span tiedowns
Wind tunnel studies initiated
7/25/2019 Silver Bridge
16/58
Torsional motion of Tacoma Narrows bridge prior to failure
Nov 7, 1940
7/25/2019 Silver Bridge
17/58
Lessons Learned
Lack of understanding of aerodynamics effects
Extrapolated past design successes
Economic pressures affecting design
Emphasis on structural efficiency
Lack of emphasis on designing to avoid failure
Inadequate regard to failures of 19th century flexible
suspension bridges
7/25/2019 Silver Bridge
18/58
Impacts of TNB failure
Intensive research on aerodynamic behavior Still no unanimous consensus on actual cause
Buffeting, Vortex shedding, Torsional flutter
Wind tunnel tests during design for all cablesupported structures (suspension and cable stayed)
Ended use of stiffening plate girders
Stiffening trusses continued to be used until 1970s
7/25/2019 Silver Bridge
19/58
Post-Tacoma new bridges
Tacoma-Narrows Bridge
Replacement - 1950 Mackinac Straits Bridge -1954
7/25/2019 Silver Bridge
20/58
Thousand Islands Bridge -Retrofits
7/25/2019 Silver Bridge
21/58
Deer Isle Bridge retrofits
7/25/2019 Silver Bridge
22/58
Bronx-Whitestone Bridge
retrofitsTower stays
Stiffening truss retrofit
Tuned mass Damper
at midspan
7/25/2019 Silver Bridge
23/58
Bronx-Whitestone Bridge --second retrofit 2007
Replaced Concrete
deck with Orthotropic
steel deck
Removed Stiffening
Trusses
Added lateral bracingto lower flanges
Added wind fairings
on stiffening girders
Diagonal stays and
tuned mass damper
remain
Reduce Dead load,
improve torsional stiffness,
improve aerodynamic behavior
7/25/2019 Silver Bridge
24/58
Recent U.S. bridge Failures of significance(and one less significant failure)
Last 30 years
Had Significant impact on Federal and State agencybridge management and safety practices
NTSB findings and recommendations
7/25/2019 Silver Bridge
25/58
Silver Bridge over Ohio RiverPoint Pleasant , WV Gallipolis, OH
Built 1928 , collapsed Dec. 15, 1967
7/25/2019 Silver Bridge
26/58
Silver Bridge collapse
Collapse initiated by eyebar fracture
Initiated at a crack Stress corrosion cracking
High residual stress
corrosion fatigue
At time of design these phenomena werenot known to occur with materials and
conditions present.
Higher traffic loads than when
originally designed New high strength steel had low
toughness
Flaw was inaccessible to inspection
Lack of Redundancy
7/25/2019 Silver Bridge
27/58
Silver Bridge Collapse
consequences
Burning Question : How many other bridges canhave a similar fate??
Resulted in Federal National Bridge Inspection
Standards regulations National bridge inventory
Biennial inspections
Inspector qualifications Reporting requirements
New research: fracture mechanics, materials
7/25/2019 Silver Bridge
28/58
Mianus BridgeI-95 over Mianus River, Greenwich, CT.
Built 1958 , collapsed June 1983
7/25/2019 Silver Bridge
29/58
Mianus River Bridge collapse
Failure of pin and hanger assembly supporting suspended span Hanger displaced laterally, worked off the pin
Transferred (eccentric)load to other hanger
Hanger worked outward, fractured pin
Underlying causes
Corrosion- unmaintained
drainage system
Lack of redundancy
Skew
7/25/2019 Silver Bridge
30/58
Mianus Bridge Collapse
Consequences
Fracture Critical Inspection requirements
Visual hands on every 2 years
NDT methods
Pin and Hanger inspection NDT methods
improved
7/25/2019 Silver Bridge
31/58
Mianus Bridge Collapse Consequences
New York DOT Response
Add redundancy to all 2 and 3girder Pin and Hanger bridges
(approx. 24 bridges)
Over time, these bridges (or
superstructures) have beenreplaced or made redundant /
continuous
7/25/2019 Silver Bridge
32/58
Mianus Bridge Collapse Consequences
New York DOT Response
Detailed Inspections of 3 and 3 welded girderbridges (hands-on and NDT)
Found many fatigue prone details, cracks
Removed flaws, tab plates, drilled out cracks
Some prioritized for replacement
Lesson in 1960s welding
became popular and economical,
however effects of fatigue andunintended structural participation
was not fully recognized.
7/25/2019 Silver Bridge
33/58
A near collapse
Hoan Bridge, Milwaukee, WIBuilt 1970, Failure on Dec. 13, 2000
Brittle fractures that originated
at a lateral bracing system
connection to the girder, where a
horizontal shelf plate intersects atransverse connection plate with
intersecting and overlapping
welds.
2 of 3 girders completely
fractured full depth
7/25/2019 Silver Bridge
34/58
Hoan Bridge Failure
Connection detail provided high tri-axial
constraint at the web, resulted in very highstress concentration (1.6 x Fy).
Very small initiating crack in web,
critical crack size not detectable.
Cold weather contributed to
brittle behavior of steel.
Steel toughness met spec.
requirements
Hoan Br idge Forensic I nvestigation,
Failur e Analysis F inal Report;
Federal Hwy. Admin. and Wisconson DOT,
2001
7/25/2019 Silver Bridge
35/58
(The one less significant failure)
New York County Road Bridge Failure -1986
Significant section losson trusses ( up to 50%)
Lack of redundancy
Excessive dead load:
Timber deck replaced bya steel pan deck with
asphalt
50 psf from 20 psf
Shows importance
of load ratings
Bridge should have
been closed
200 ft. deck truss span one lane bridge
Load posted for 8 tons
Failure initiated by 16 ton truck crossing
the bridge
7/25/2019 Silver Bridge
36/58
Schoharie Creek BridgeNYS Thruway over Schoharie Creek
Built 1954, Collapsed April, 1987
7/25/2019 Silver Bridge
37/58
Schoharie Creek Bridge failure(NTSB Findings)
Caused by scour undermining pier foundation
50 year flood event
Spread foundations on dense glacial till
Inadequate rip rap protection
Inadequate rip rap size
Damage from prior flood events
Rip rap not maintained
7/25/2019 Silver Bridge
38/58
Schoharie Creek Bridge failure
Contributing
causes- Lack of:
Redundancy
ductility in piers
resiliency
f
7/25/2019 Silver Bridge
39/58
Schoharie Creek Bridge failure
Follow Up Actions in NY
Improved hydraulic and scour evaluations
Post flood inspections
Flood warning action plan
Bridge Safety Legislation Uniform Code of bridge inspection
Codified inspection requirements
Structural integrity evaluations
NYSDOT oversight of Authorities, local owners NYSDOT authority to close unsafe bridges
Priority given to bridge inspection program
S h h i C k B id f il
7/25/2019 Silver Bridge
40/58
Schoharie Creek Bridge failure
Follow Up Actions in NY
Bridge Safety Assurance (BSA) Initiative
Program of assessment of bridges vulnerability
to structural failure due to their inherent
characteristics or due to extreme events Assessments are made for individual failure
modes
Identify causes of failure beyond condition
(Why do Bridges Fail?)
Bridge Failures in the US: 1966 2005
7/25/2019 Silver Bridge
41/58
Bridge Failures in the US: 1966-2005
Cause of Bridge Failures from 1966 to 2005
Figure courtesy of J-L Briaud, Texas A&M University
7/25/2019 Silver Bridge
42/58
NYSDOT Bridge Failure Database
7/25/2019 Silver Bridge
43/58
Sytematic evaluations of bridges based on individual
failure modes.
Hydraulics Steel Details
Overload Concrete Details
Collision Earthquake
Evaluate statewide bridge population:
Screen Assess Classify
Vuln. Classifications consider failure likelihood andconsequence.
Evaluation data needs collected during bridge
inspections
NYSDOT Bridge Safety Assurance Initiative
Vulnerability Assessments
7/25/2019 Silver Bridge
44/58
Scour repairs
Steel Detail Retrofits
Add Redundancy
BSA Retrofits
Vulnerability score may
influence rehab / replace
decision
7/25/2019 Silver Bridge
45/58
I-35W over Mississippi RiverBuilt 1967 , collapsed Aug 1, 2007
7/25/2019 Silver Bridge
46/58
Inadequate load capacity of gusset plates at U10 joints,
attributed to design error Substantial increases in weight of the bridge from prior
modifications
Concentrated construction loads combined with traffic
I-35W over Mississippi River
NTSB Findings
I-35W over Mississippi River
7/25/2019 Silver Bridge
47/58
I-35W over Mississippi River
Inadequate Gusset plate thicknesses at U10 and L11
(NTSB) Contributing Cause: Failure of designer Quality
Control Procedures
Deficiency seems evident in hindsight.
Lesson: Design errors can slip through.
NTSB
7/25/2019 Silver Bridge
48/58
I-35W over Mississippi River
Bowed gusset plates suggested problem for further investigation.
NTSB
(NTSB) Contributing cause: Inadequate attention to gusset plates by
transportation agencies during inspections.
7/25/2019 Silver Bridge
49/58
I-35W over Mississippi River
Response by DOTs and FHWA
Inspections of all non-redundant deck truss bridges
(How many other bridges can have a similar fate?)
Guidance on construction loads and stockpiling on bridges
Gusset plate analysis
Include gusset plate analysis in load capacity evaluations
Evaluate gusset plates on all bridges that have undergone a substantial
change in load.
Gusset Plate Analysis Research NCHRP 12-84
FHWA Advisory on non-destructive testing of gusset plates
I-35W over Mississippi River
7/25/2019 Silver Bridge
50/58
I 35W over Mississippi River
NYSDOT actions
Inspected 50 deck truss bridges in NYS
Analyzed Gusset Plates on 133 Trusses that had undergone asubstantial change in load.
Developed analytical tools for gusset plate design and load
capacity checks (LFD and LRFD)
Did not find design errors
similar to I-35W
Found problems due to
deterioration
Developed gusset repair and
replacement procedures
Closed / replaced 1 bridge
due to gusset evaluations
NYSDOT G t
7/25/2019 Silver Bridge
51/58
NYSDOT Gusset
repairs
Failures Caused by Extreme Events
7/25/2019 Silver Bridge
52/58
Failures Caused by Extreme Events Earthquakes
Collisions
Vessel Vehicle
Storm surge
Fire
7/25/2019 Silver Bridge
53/58
Failures Caused by Extreme Events
Lessons learned result in improved design
specifications, detailing practices
Seismic research,
AASHTO seismic specifications
AASHTO Guide specs. for Vessel Collision
AAHSTO Guide specs. For Bridges Vulnerable to Coastal Storms
--NCHRP 12-85:Highway Bridge Fire
Hazard Assessment
--NCHRP 12-72:
Blast Resistant Highway
Bridges- Design and
Detailing Guidelines
7/25/2019 Silver Bridge
54/58
Failures during Construction
When a bridge may be
most at risk to a
structural collapse.
Failures during Construction
7/25/2019 Silver Bridge
55/58
Failures during Construction
Rt 470 / I-70 overpass, Golden CO; May 15, 2004
Probable Cause of Failure (NTSB Report):
Failure of temporary bracing system due toinsufficient planning.
Contributing causes:
--girder installed out of plumb.
--inadequate standards for temporary bracing
--inadequate oversight
Only ifs ---Problem reported by passerby, but miscommunication occurred.
---Subsequent girder erection was delayed
(NTSB) Recommendations / Lessons:
Improve standards for temporary works and erection procedures (FHWA, State
DOT, AASHTO, OSHA)
-Prequalification
-Submit written plan, dwgs.
-Certified by a P.E
Failures during construction
7/25/2019 Silver Bridge
56/58
Failures during construction
Potential Issues
Bridges are often in their most failure vulnerable
state during construction
Considering construction states during design
Design focuses on completed structure in service
Specs may be vague in addressing construction states Division of responsibility between designer and
contractor/erector.
Designer responsibility for a constructible bridge
Contractor responsible for means and methods for
construction.
l d
7/25/2019 Silver Bridge
57/58
Failures during construction
Lessons
Must provide a constructible design Contract documents show one feasible method of
construction (plans or notes)
Design specs shall address constructability
Design loads, limit states during construction
Structural construction operations shall be designed,
certified by a P.E., submitted for approval
Temporary structures, temporary works Erection Drawings
Structural lifting
7/25/2019 Silver Bridge
58/58
Questions?