Upload
wayne-kirk
View
19
Download
0
Embed Size (px)
DESCRIPTION
Single Machine Deterministic Models. Jobs: J 1 , J 2 , ..., J n Assumptions : The machine is always available throughout the scheduling period. The machine cannot process more than one job at a time. Each job must spend on the machine a prescribed length of time. S ( t ). 3. 2. 1. - PowerPoint PPT Presentation
Citation preview
1
Single Machine Deterministic Models
Jobs: J1, J2, ..., Jn
Assumptions:
• The machine is always available throughout the scheduling period.• The machine cannot process more than one job at a time.• Each job must spend on the machine a prescribed length of time.
2
t
tJktS k
at time processed is job no if0
at time processed is job if)(
1
3
2
J1J2 J3 ...
S(t)
t
3
Requirements that may restrict the feasibility of schedules:
• precedence constraints• no preemptions• release dates• deadlines
Whether some feasible schedule exist? NP hard
Objective function f is used to compare schedules.
f(S) < f(S') whenever schedule S is considered to be better than S'problem of minimising f(S) over the set of feasible schedules.
4
1. Completion Time Models
Due date related objectives:
2. Lateness Models
3. Tardiness Models
4. Sequence-Dependent Setup Problems
5
Completion Time Models
Contents
1. An algorithm which gives an optimal schedulewith the minimum total weighted completion time 1 || wjCj
2. An algorithm which gives an optimal schedule with the minimum total weighted completion time when the jobs are subject to precedence relationshipthat take the form of chains1 | chain | wjCj
6
Literature:• Scheduling, Theory, Algorithms, and Systems, Michael Pinedo,
Prentice Hall, 1995, or new: Second Addition, 2002, Chapter 3.
7
1 || wjCj
Theorem. The weighted shortest processing time first rule (WSPT) isoptimal for 1 || wjCj
WSPT: jobs are ordered in decreasing order of wj/pj
The next follows trivially:
The problem 1 || Cj is solved by a sequence S with jobs arranged innondecreasing order of processing times.
8
Proof. By contradiction.
S is a schedule, not WSPT, that is optimal.
j and k are two adjacent jobs such that
k
k
j
j
p
w
p
w which implies that wj pk < wk pj
t t + pj + pk
j kS:
t t + pj + pk
k jS’
......
... ...
S: (t+pj) wj + (t+pj+pk) wk = t wj + pj wj + t wk + pj wk + pk wk
S’: (t+pk) wk + (t+pk+pj) wj = t wk + pk wk + t wj + pk wj + pj wj
the completion time for S’ < completion time for S contradiction!
9
1 | chain | wjCj
chain 1: 1 2 ... k chain 2: k+1 k+2 ... n
Lemma. If
n
kjj
n
kjj
k
jj
k
jj
p
w
p
w
1
1
1
1
the chain of jobs 1,...,k precedes the chain of jobs k+1,...,n.
Let l* satisfy
l
jj
l
jj
kll
jj
l
jj
p
w
p
w
1
1
1*
1
*
1max
factor of chain 1,...,kl* is the job that determines the factor of the chain
10
Lemma. If job l* determines (1,...,k) , then there exists an optimalsequence that processes jobs 1,...,l* one after another withoutinterruption by jobs from other chains.
Algorithm
Whenever the machine is free, select among the remaining chainsthe one with the highest factor. Process this chain up to and includingthe job l* that determines its factor.
11
Example
chain 1: 1 2 3 4chain 2: 5 6 7
jobs 1 2 3 4 5 6 7wj 6 18 12 8 8 17 18pj 3 6 6 5 4 8 10
factor of chain 1 is determined by job 2: (6+18)/(3+6)=2.67 factor of chain 2 is determined by job 6: (8+17)/(4+8)=2.08chain 1 is selected: jobs 1, 2
factor of the remaining part of chain 1 is determined by job 3:12/6=2 factor of chain 2 is determined by job 6: 2.08chain 2 is selected: jobs 5, 6
12
factor of the remaining part of chain 1 is determined by job 3: 2 factor of the remaining part of chain 2 is determined by job 7:18/10=1.8chain 1 is selected: job 3
factor of the remaining part of chain 1 is determined by job 4: 8/5=1.6 factor of the remaining part of chain 2 is determined by job 7: 1.8chain 2 is selected: job 7
job 4 is scheduled last
the final schedule: 1, 2, 5, 6, 3, 7, 4
13
1 | prec | wjCj
Polynomial time algorithms for the more complex precedenceconstraints than the simple chains are developed.
The problems with arbitrary precedence relation are NP hard.
1 | rj, prmp | wjCj preemptive version of the WSPT ruledoes not always lead to an optimal solution,the problem is NP hard
1 | rj, prmp | Cj preemptive version of the SPT rule is optimal
1 | rj | Cj is NP hard
14
Summary
1 || wjCj WSPT rule
1 | chain | wjCj a polynomial time algorithm is given
1 | prec | wjCj with arbitrary precedence relation is NP hard
1 | rj, prmp | wjCjthe problem is NP hard
1 | rj, prmp | Cj preemptive version of the SPT rule is optimal
1 | rj | Cj is NP hard