57
0 © 2006 Weatherford. All rights reserved. Tuesday April 21 st , 2009 Drilling-with-Casing (DwC™) Overcoming Wellbore Stability Issues Steve Rosenberg U.S. Region Product Line Manager

SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

0© 2006 Weatherford. All rights reserved.

Tuesday April 21st, 2009

Drilling-with-Casing (DwC™)Overcoming Wellbore Stability Issues

Steve Rosenberg – U.S. Region Product Line Manager

Page 2: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

1© 2006 Weatherford. All rights reserved.

Presentation Outline

• Definition and Benefits of DwC

• Drilling Hazard Mitigation Value

• DwC Hydraulics.

• DwC Systems

• Drillable DrillShoes

• Casing Drive Systems

• Liner Drilling

• Applications Engineering

• Case Histories

• Future DwC Technology

Page 3: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

2© 2006 Weatherford. All rights reserved.

Drilling-with-Casing/Liner technology uses the casing string as the ‘drill string’ instead of drill pipe.

DwC reduces well construction costs and improves drilling efficiency.

What is DwC™ Technology?

Page 4: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

3© 2006 Weatherford. All rights reserved.

Key Value Drivers for DwC™

Cost/Time Reduction

Safety

Problem Resolution

Page 5: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

4© 2006 Weatherford. All rights reserved.

DwC™ / DwL™ Benefits

• Increased safety. Reduced trips and less handling of heavy BHA’s

• Improve efficiency by eliminating flat spots in the drilling curve = Reduced Well Construction Costs

• Improved wellbore quality (less wellbore tortuosity)

• Improved hole cleaning

• Risk reduction and problem mitigation (lost circulation, unstable formations, depleted reservoir sections)

• Trip margin requirement eliminated

• Getting casing to bottom

Page 6: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

5© 2006 Weatherford. All rights reserved.

Wellbores Drilled 1993 – 2002; Water Depth = <600 feet

Directional Completion5%

Chem. Prob.3%

Stuck Pipe11%

Sloughing Shale3%

Wellbore Instability1%

Cement squeeze9%

Twist Off3%

Wait Weather13%

Casing or Wellhead Failure

5%

Rig Failure21%

Other1% Kick

9% Gas Flow0%

Shallow Water Flow3%

Lost Circulation13%

Impact of Trouble TimeDrill Days Lost to Trouble Time

• 24% of 25,321 total drill days from spud date to date TD was reached

Trouble Time Cost Impact –GoM Shelf Gas Wellbores

• Deep wells average dry-hole cost per foot = $444. Average impact = $98

• ‘Shallow well average dry-hole cost per foot = $291. Average Impact = $71

James K. Dodson [email protected]

Drilling Hazard MitigationProblem Incidents – GOM Shelf Gas Wells

Page 7: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

6© 2006 Weatherford. All rights reserved.

Hole Stability18%

Low Pressure Event22%

High Pressure Event12%

Client Value

The Issue

• Drilling hazards add 12% to drilling time

• 50% of hazards relate to pressures and wellbore instability (pie chart to right shows a breakdown of these drilling hazards)

• As fields mature, depletion issues increase

• Conventional methods are time consuming, costly and largely ineffective

The Answer

• Apply proper technology to address issue

• Drilling with casing, expandable tubulars and managed pressure drilling

• Combine complementing technologies to deliver integrated engineered systems and techniques

Drilling Hazard MitigationDrilling Hazard Mitigation

Page 8: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

7© 2006 Weatherford. All rights reserved.

Drilling Hazard Mitigation

A suite of technologies that individually, or in

combination, radically reduce non-productive time

due to drilling hazards.

Controlled Pressure Drilling® Solid Expandable Systems

Drilling with Casing DwC™

A better way to drill

Page 9: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

8© 2006 Weatherford. All rights reserved.

Hidden NPT - Time reduction

Time

Dep

th

0

4,000 ft.

5,000 ft.

ReducedROP

Event 2a

T1 T2

T1 = 4 daysT2 = 3 days

Total “Flat” Time = 7 days

T1 = Time Fighting Loss Circulation Zone

Time Curing Loss Circulation Zone

T2 =

Drilling curvetypically reported

Time

Dep

th

0

4,000 ft.

5,000 ft.

ReducedROP

Event 2a

T1 T2

T1 = 4 daysT2 = 3 days

Total “Flat” Time = 7 days

T1 = Time Fighting Loss Circulation Zone

Time Curing Loss Circulation Zone

T2 =

Drilling curvetypically reported

Page 10: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

9© 2006 Weatherford. All rights reserved.

Non-Productive Time (NPT)

Lost Circulation: Time spent curing losses

Time

Dep

th

0

4,000 ft.

5,000 ft.

ReducedROP

Event 2a

T1 T2

T 2 = 3 days

Total “Flat” Time = 7 days

Time Curing Lost Circulation Zone

T2 =

Drilling curvetypically reported

Time

Dep

th

0

4,000 ft.

5,000 ft.

T1

T 1 = 3 days

Total “Flat” Time = 3 days???

Time Curing Lost Circulation Zone

T1 =

Drilling curvetypically reported

Page 11: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

10© 2006 Weatherford. All rights reserved.

Non-Productive Time (NPT)

Lost Circulation: Time spent fighting and curing losses

Time

Dep

th

0

4,000 ft.

5,000 ft.

ReducedROP

Event 2a

T1 T2

T 1 = 4 daysT 2 = 3 days

Total “Flat” Time = 7 days

T1 = Time Fighting Lost Circulation Zone

Time Curing Lost Circulation Zone

T2 =

Drilling curvetypically reported

Time

Dep

th

0

4,000 ft.

5,000 ft.

ReducedROP

Event 2a

T2 T1

T 2 = 4 daysT 1 = 3 days

Total “Flat” Time = 7 days

T2 = Time Fighting Lost Circulation Zone

Time Curing Lost Circulation Zone

T1 =

Drilling curvetypically reported

Page 12: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

11© 2006 Weatherford. All rights reserved.

What is the “Smear” or “Plaster” Effect?

Conventional DwC

7.25” TJ OD5.5” FH DP

21.9ppf

Industry belief the ‘Smear’ effect cures or reduces lost circulation

13.375” casing14.38” casing coupling OD

Page 13: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

12© 2006 Weatherford. All rights reserved.

Smear effect

• Finer ground cuttings• 10% to 20% less cuttings circulated to the surface

Page 14: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

13© 2006 Weatherford. All rights reserved.

DwC Hydraulics

Page 15: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

14© 2006 Weatherford. All rights reserved.

DwC™ vs Conventional Annular Flow

Hole OD OD Flow DwC Vann

Size DP Csg Rate, gpm Conv DwC Conv DwC vs Conv8 1/2 5 1/2 7 500 33 18 292 527 1.8 X

12 1/4 5 1/2 9 5/8 800 94 45 164 341 2.1 X17 1/2 5 1/2 13 3/8 1000 217 100 89 192 2.2 X26 5 1/2 20 1100 507 217 42 98 2.3 X

Annulus Area, in^2 Vann, ft/min

292

527

164

341

89

192

42

98

-

100

200

300

400

500

600

V ann

, ft/m

in500 800 1000 1100

7 9 5/8 13 3/8 20

5 1/2 5 1/2 5 1/2 5 1/2

8 1/2 12 1/4 17 1/2 26 Flow, Csg , DP , Hole

ConvDwC

Page 16: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

15© 2006 Weatherford. All rights reserved.

DwC™ ECD with 13-3/8” Casing

13-3/8" DwC ECD Comparison1500ft, 900gpm, 8.6ppg SW

8.63 8.74 8.77 8.819.18

9.7310.25

12.95

211 13 16

45

88

129

339

0.0

5.0

10.0

15.0

5 1/2 13 3/8 13 3/8 13 3/8 13 3/8 13 3/8 13 3/8 13 3/8

17 1/2 17 1/2 17 1/4 17 16 15 1/2 15 1/4 14 3/4

Drillpipe/Casing vs Hole Size

ECD

, ppg

0

150

300

450

Ann

ular

Pre

ssur

e D

rop,

psi

ECD, ppg

Ann. dP, psi

Conventional drilling

Page 17: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

16© 2006 Weatherford. All rights reserved.

DwC™ ECD with 9-5/8” Casing

9-5/8" DwC ECD Comparison1500ft, 600gpm, 9.6ppg 13.0YP mud

9.710.3 10.4 10.5

11.212.1

12.8

15.3

21.0

7

56 65 71

125

196

252

444

886

0.0

5.0

10.0

15.0

20.0

25.0

5 1/2 9 5/8 9 5/8 9 5/8 9 5/8 9 5/8 9 5/8 9 5/8 9 5/8

12 1/4 12 1/4 12 11 7/8 11 1/2 11 1/4 11 1/8 10 7/8 10 5/8

Drillpipe/Casing vs Hole Size

ECD

, ppg

0

200

400

600

800

1000

Ann

ular

Pre

ssur

e D

rop,

psi

ECD, ppg

Ann. dP, psi

Conventional drilling

Page 18: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

17© 2006 Weatherford. All rights reserved.

Today’s DwC™ Technology

BHA latched into The Lower Casing JointRetrievable Bits & BHA’s

Cement-in-Place Non-Retrievable DwC SystemDrillable Drill Shoes

4-1/2” , 5”, 7” x 8-1/2”, 7-5/8” x 8-1/2”, 9-5/8” x 12”, 9-5/8” x 10 5/8”, 11-3/4 x 12-1/4, 11-7/8” x 12-1/4”, 13-3/8” x 14-3/4”, 13-3/8” x 17”, 18-5/8” x 24”, 20” x 24”, 24” x 27”

Page 19: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

18© 2006 Weatherford. All rights reserved.

DrillShoe™ and Latch Systems Compared

Advantages Disadvantages

Low Cost Limited directional control

Simple to operate Cased hole logs only

No rig modifications required

Limited DrillShoe selection

Zero risk of irretrievable tools in

the hole

Cementing can commence

immediately TD is reached

Drillable DrillShoe System

Ability to steer High Cost

MwD/LwDcapability

More complicated to set up and

operate

Wide range of bit selections to suit

formation and distance

Rig modification required

Risk of irretrievable tools in the hole

Unable to cement immediately upon

reaching TD

Latch System

Advantages Disadvantages

Page 20: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

19© 2006 Weatherford. All rights reserved.

DrillShoe™ 2

The DrillShoe™ is made in 2 parts:

1. The “body” is machined from a piece of 4145 ASI Steel bar.

2. The “nose” is machined from Aircraft Grade Aluminium. 6mm round pieces of TSP (Thermally Stable Polycrystalline Diamond) are then pressed into pre-drilled holes on the front of the blades. The blades are then hardfaced with HVOF Tungsten Carbide.

3. Available in 3, 4 and 5 blade designs

7,000 psi CCS Formations

Excellent Reaming Tool

Page 21: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

20© 2006 Weatherford. All rights reserved.

DwC DrillShoe™ 2 Construction

6mm round TSP pressed into the Aluminum

Copper or Ceramic Nozzles – PDC Drillable

Aircraft grade Aluminum nose (fully PDC drillable)

4145ASI Steel Body

Tungsten Carbide Hardfacing on Aluminum surface

Premium PDC Cutters

Threaded connection between the Aluminum Nose and Steel body/shoulder

Page 22: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

21© 2006 Weatherford. All rights reserved.

EZCase Bit

• Steel alloy PDC design for robust reaming / drilling

• PDC drillable only with Genesis PDC bits

• EZ Case nozzles not field interchangeable

• Secondary flow path for cement reliability

PDC cutting structure

Nozzle placement optimized using Computational Fluid Dynamics (CFD)

Casing bit crown welded to custom pups

Engineered internal profile for efficient drill-out

Secondary bypass port

Page 23: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

22© 2006 Weatherford. All rights reserved.

DrillShoe™ 3

• 5 or 6 Bladed PDC Bit

• 13 to 19 mm PDC Cutters

• Up to 20,000 psi CCS

• Converts to drillable cement shoe

• Simple pressure cycle

• Drillout with tri-cone or PDC Bit

Page 24: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

23© 2006 Weatherford. All rights reserved.

DrillShoe™ 3

• Drills like a PDC bit

• After simple pressure cycle, DrillShoe 3 becomes drillable

• Cement as normal

• Drill-thru with a normal PDC bit

• 15,000 to 20,000 psi CCS

Premium PDC cutters

Drillable core

Shear Pin

Steel blade

Cement port

Steel body

Page 25: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

24© 2006 Weatherford. All rights reserved.

Contributions to NPT Running Casing and Liner

Tight hole, stuck pipe; 49.9 %

Pressure test failed; 9.4 %

Set hanger; 4.8 %

Threads; 4.0 %

Mud loss; 3.5 %

Tong; 3.3 %

Seal Assembly; 3.2 %

Waiting time; 2.6 %

Others; 17.6 %

Fishing operation; 1.7 %

Casing Running NPT Analysis by North Sea OperatorNon productive days due to tight hole/stuck pipe: 57 days over 27 months.

Excluding cost impact of setting casing high.

Page 26: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

25© 2006 Weatherford. All rights reserved.

Reaming Shoes

Weatherford DrillShoe 2

Weatherford CleanReam Baker EZReam Davis Lynch

PenetratorTesco

Warthog

Page 27: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

26© 2006 Weatherford. All rights reserved.

Centralizers for DwC Applications

Non-RotatingRubber Lined In-Line HydroForm Spray Metal Process

Page 28: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

27© 2006 Weatherford. All rights reserved.

Surface Drive Systems

Page 29: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

28© 2006 Weatherford. All rights reserved.

Surface Drive Systems

Casing Drive System(CDS) OverDrive™Internal Casing

Drive Tool (ICDT)

Page 30: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

29© 2006 Weatherford. All rights reserved.

• Applications (rigs with top drives)

• Casing Running

• Drilling & Reaming w/ Casing

• Extended Reach and Deviated Wells

• Troublesome Well Bores

• Safety Driven Operations

OverDrive™ Casing Running and Drilling System

Page 31: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

30© 2006 Weatherford. All rights reserved.

OverDrive System Features

• Removes personnel and equipment from derrick and rig floor

• Eliminates need for conventional tongs, elevators, and related personnel.

• Fill-up tool design allows switching between fill-up and circulation modes without repositioning tool.

• Multiple safety interlocks enhance efficiency and safety by preventing unplanned events such as dropped objects.

• Used for pushing down, reciprocating, circulating, and rotating casing if required.

• Torque sub measures the true torque applied to the connection without erroneous torque readings from mechanical losses and friction in the top drive and hydraulic swivel.

Page 32: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

31© 2006 Weatherford. All rights reserved.

Liner Drilling Applications

• Depleted Formations

• Loss Zones

• Pressure Transition Zones

• Managed Pressure Drilling

• Unstable Formations

• Reaming liner through problem zones

• Just getting the Liner to bottom

Time

Dep

th

0

4,000 ft.

5,000 ft.

ReducedROP

Event 2a

T1 T2

T1 = 4 daysT2 = 3 days

Total “Flat” Time = 7 days

T1 = Time Fighting Loss Circulation Zone

Time Curing Loss Circulation Zone

T2 =

Drilling curvetypically reported

Time

Dep

th

0

4,000 ft.

5,000 ft.

ReducedROP

Event 2a

T1 T2

T1 = 4 daysT2 = 3 days

Total “Flat” Time = 7 days

T1 = Time Fighting Loss Circulation Zone

Time Curing Loss Circulation Zone

T2 =

Drilling curvetypically reported

Page 33: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

32© 2006 Weatherford. All rights reserved.

Nodeco Liner Drilling/Reaming Systems

• Drillable casing bit or conventional bit

• Float Collar (auto-fill or conventional)

• Centralizers (in-line or solid slip-on)

• Hydraulic rotating or rotatable hanger

• Liner Top Packer (integral or second trip)

• Retrievable seal mandrel

• High torque running tool

• Effective junk screening

• Diverter tool (optional)

• Drill Pipe to surface

Page 34: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

33© 2006 Weatherford. All rights reserved.

Mechanically Expanded Ball Seat

• Ball released with mechanical expansion

• No pressure surge to formation

• Can not prematurely shear out before hanger set and running tool released

• Enables higher shear pin setting pressures for hanger and running tool

Pick-Up Sub Expander Mandrel

Expandable Ball Seat

Expander Mandrel

Page 35: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

34© 2006 Weatherford. All rights reserved.

BLTT Liner Drilling System

• Drillable Casing DrillShoe™ (or conventional bit)

• 5”, 5-1/2”,7”, 7-5/8”,13-5/8” Liner Sizes

• 2nd Trip Packer Capability

• No Liner Hanger – Set Liner on Bottom

• Transmit torque to liner outer sleeve through spline.

(torque > most DP connections)

• 5” Tool Torque = 35K ft-lbs.

• 7-5/8” Tool Torque = 53,000 ft-lbs.

• 13-5/8” Tool Torque = 80,000 ft-lbs.

• Δ P will not release running tool - A drop ball pumped down to setting sleeve with hydraulic pressure is required to release running tool.

• Drill Pipe to surface

Page 36: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

35© 2006 Weatherford. All rights reserved.

Benefits of Reaming with Liners

• Maximum Insurance to get the Liner to bottom

• Minimum impact to normal running operations

• No need for extra wiper trips

– Eliminate Trip Margin Required.

• Minimize mud losses

• Minimum open hole time / formation damage

• Reduces equipment handling (better HSE)

Page 37: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

36© 2006 Weatherford. All rights reserved.

Gulf of Mexico Shelf DwC Opportunities

Page 38: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

37© 2006 Weatherford. All rights reserved.

Projected SavingsUsing DwC Given Daily Rig Spread Rates

Eliminate 16" Conductor / Drill in 9-5/8" Surface Casing

$0

$50,000

$100,000

$150,000

$200,000

$250,000

$300,000

$350,000

$400,000Rig Spread Rate

($/day)

Am

ount

Sav

ed

$120K

$130K

$140K

$150K

$160K

GoM Shelf

Page 39: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

38© 2006 Weatherford. All rights reserved.

Projected Savings Using DwC Given Daily Rig Spread Rates

Drill in 9-5/8" Surface Casing

$0

$10,000

$20,000

$30,000

$40,000

$50,000

$60,000Rig Spread Rate

($/day)

Am

ount

Sav

ed

$120K

$130K

$140K

$150K

$160K

GoM Shelf

Page 40: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

39© 2006 Weatherford. All rights reserved.

GoM Conductor and Surface Casings DwC

• Economic savings can be achieved using DwC techniques

• Average around 26% drilling cost savings based upon flat time reduction

• Savings as much as $350K without additional individual savings if 16” and 10-3/4” casing are replaced with 9-5/8” DwC

• Savings still realized if only 10-3/4” section utilizes DwC technology

Page 41: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

40© 2006 Weatherford. All rights reserved.

Financial Analysis Study – Drill in 20-in Conductor Casing with HP Housing

• Spread Rate $550k

– Projected Time Savings = 24.5% or 24 hours

– Projected Financial Savings = $380k

DwC vs Conventional Time Depth Curve

1,200

1,300

1,400

1,500

1,600

1,700

1,800

1,9000.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5

Days

Dep

th, m

CONVENTIONAL

DRILLING WITH CASING

Page 42: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

41© 2006 Weatherford. All rights reserved.

Applications Engineering

PLANNING IS KEY TO SUCCESSFUL DwC OPERATIONS!!

Page 43: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

42© 2006 Weatherford. All rights reserved.

DwC Planning Tools

• Analyze electric logs to determine compressive strength

• D-Exponent

• Mud Logs

• Drill Bit Records

• Connection Design

• Torque Drag Model

• Stress Cycles Model

Page 44: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

43© 2006 Weatherford. All rights reserved.

DwC Connection Design

Proven Connections

• Standard Buttress

• Modified Buttress - GB CDE, DWC/C

• Hydril Wedge Threads – 513, 521, 523, 563

• Vam SLIJ II, Vam Top

• Hunting SLSF

Design Factors

• MU Torque

• DLS – critical when rotating off whipstocks

• Fatigue (Stress-Cycles Plot)

• Torque Drag Modeling

Page 45: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

44© 2006 Weatherford. All rights reserved.

46,000

Page 46: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

45© 2006 Weatherford. All rights reserved.

Page 47: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

46© 2006 Weatherford. All rights reserved.

Page 48: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

47© 2006 Weatherford. All rights reserved.

Case Histories

Page 49: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

48© 2006 Weatherford. All rights reserved.

Client Value

Client Mariner Energy

Location MC 674 – Gulf of Mexico

Results 7-5/8” DwL through thief zone @ 20,400’where 2 wellbores were lost due to severe losses

Value Enabled Operator to strategically set 7-5/8”liner in competent interval to < MW and drill depleted production zone with no reported OBM fluid losses.

Client El Paso (OTC 17687)

Location EI 364 – Gulf of Mexico

Results DwL 269 ft, with 9-5/8” liner through catastrophic thief zone without losses. Previous wellbore lost over 3,000 bbls.

Value Saved 96 hours of rig time and approximately US$ 750K

Client Pemex (SPE/IADC 105403)

Location Veracruz, Mexico – Gulf of Mexico

Results Drilled with liner in high angle hole to reach fractured formation susceptible to extreme losses

Value Saved 39.5 days, representing a cost reduction of US$ 4.5 million

Page 50: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

49© 2006 Weatherford. All rights reserved.

Client ValueClient Spinnaker Exploration

Location High Island – Gulf of Mexico

Results DwL system reams and drills through unstable shale and 2 ppge depleted sand in 38º hole without fluid losses.

Reamed and drilled 5-1/2” liner with DrillShoe 2 from 13,685-ft to 13798 -ft MD to reach planned liner TD obtaining 18.3 ppge FIT

Value Successfully installed liner by reaming and drilling through drilling hazards enabling client to subsequently drill required 4-1/2”hole for completion..

Client CNOOC (SPE/IADC 118806)

Location Banuwati Field, Offshore Indonesia

Results DwL system drills through wellbore instability and severe loss interval to reach liner objective.

Drilled 7” liner with DrillShoe 3 from 9,968-ft to 10,317-ft MD in 68º hole successfully isolating drilling hazards

Value DwL technology was successful getting liner to planned TD, where conventional methods were unsuccessful. Estimated $1MM USD savings realized.

. Client Anadarko (OTC 18245)

Location Salt Creek CO2 Injection Field, Wyoming

Results 5” casing was drilled to 2,300-ft using DwC and UB technology due to high shallow overpressures (est @ 18 ppge).

Value ROP was doubled and cementing was completed within 3 hrs. of reaching TD.The well did not have to be killed to run casing.

Page 51: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

50© 2006 Weatherford. All rights reserved.

Deepwater DwC….. The Future

Page 52: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

51© 2006 Weatherford. All rights reserved.

Based on the above cost/ft, this relates to $ 128/ft for Wellbore Instability. Based on a hypothetical 20,000’ MD well: $ 2,500,000/Well

GoM Non Sub-Salt Wellbores NPT (OTC 20220)

Page 53: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

52© 2006 Weatherford. All rights reserved.

Based on the above cost/ft, this relates to $ 380/ft for Wellbore Instability. Based on a hypothetical 20,000’ MD well: $ 7,600,000/Well

GoM Sub-Salt Wellbores NPT (OTC 20220)

Page 54: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

53© 2006 Weatherford. All rights reserved.

Why Deepwater DwC??

•Deepwater operations are notoriously expensive

•Daily rig spread rates frequently exceeding $750,000/day

•Ability to apply innovative technology to reduce time/cost spent in challenging sub-sea environments is a hurdle many operators face.

•The development of a system based on proven DwC technology that enhances drilling efficiency and mitigates many drilling hazards, can be applied in a Sub-Sea Environment.•Conservative time savings estimates show Deepwater DwC to be 25% more efficient

Page 55: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

54© 2006 Weatherford. All rights reserved. 54

DwC Applications – 6 Continents

Page 56: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

55© 2006 Weatherford. All rights reserved.

Weatherford DwC Market

• Focus on cement in place system

– Time saving

– Problem resolution

• Drilled > 800 wells to date

• > 750,000 feet drilled

• Manufactured and shipped 1,000 DwC systems to date

• Over 60 Clients

Max Distance Drilled (m)

0

200

400

600

800

1000

1200

7.625 9.625 10.75 13.375 16 20

Dis

tan

ce (

m)

Page 57: SIPES DwC 4-21-09Tong; 3.3 % Seal Assembly; 3.2 % Waiting time; 2.6 % Others; 17.6 % Fishing operation; 1.7 % Casing Running NPT Analysis by North Sea Operator Non productive days

56© 2006 Weatherford. All rights reserved.

Tuesday April 21st, 2009

Drilling-with-Casing (DwC™)Overcoming Wellbore Stability Issues

Steve Rosenberg – U.S. Region Product Line Manager