6
1 1. Investment Cost Estimation The costs included in the investment cost estimate are grouped into three categories as follows: Inside Battery Limits (ISBL) costs Outside Battery Limits (OSBL) costs Other Project Costs The estimated cost of ISBL and OSBL facilities by major process unit is presented in Table 3.The estimated total cost of the utilities and supporting systems project is presented in Table 4.This has improved the accuracy of the capital cost estimates to ±30%. The cost estimate initially was developed in U.S. dollars based on material and labor costs thatapplied during 2013. The resulting cost estimate needs to be adjusted to reflect costs that are expected to apply during the Project’s procurement and construction period. Table 1 - Facilities Investment Cost Units Capacity Investment Cost(MMUS$) Hydrogen Manufacturing 10.3 MMSCFD Amine System 100 t/d Sour Water Stripping 35 m3/hr Sulphur Recovery Unit 100 t/d Waste Water Treatment 7000 m3/d

siraf refinery

Embed Size (px)

DESCRIPTION

some thing about siraf

Citation preview

  • 1

    1. Investment Cost Estimation

    The costs included in the investment cost estimate are grouped into three categories as

    follows:

    Inside Battery Limits (ISBL) costs

    Outside Battery Limits (OSBL) costs

    Other Project Costs

    The estimated cost of ISBL and OSBL facilities by major process unit is presented in

    Table 3.The estimated total cost of the utilities and supporting systems project is

    presented in Table 4.This has improved the accuracy of the capital cost estimates to

    30%.

    The cost estimate initially was developed in U.S. dollars based on material and labor

    costs thatapplied during 2013. The resulting cost estimate needs to be adjusted to reflect

    costs that are expected to apply during the Projects procurement and construction period.

    Table 1 - Facilities Investment Cost Units Capacity Investment Cost(MMUS$)

    Hydrogen Manufacturing 10.3 MMSCFD

    Amine System 100 t/d

    Sour Water Stripping 35 m3/hr

    Sulphur Recovery Unit 100 t/d

    Waste Water Treatment 7000 m3/d

  • 2

    Compressed Air System 13925 Nm3/hr

    Nitrogen Generation -

    Fire Fighting Water System -

    Laboratory -

    Raw Water Receiving Facilities -

    Cooling Water System -

    Steam Generation system -

    DM Water System -

    Loading Facilities -

    Buildings -

    Piping System for Feed and

    Products

    -

    Site preparation -

    Connection Piping System -

    Control Rooms -

    Analyzers -

    Total Facilities Cost - 298.11

  • 3

    Table 2 - Project Total Investment Cost Units Investment Cost(MMUS$)

    Total Facilities Cost 298.11

    Working Capital 3.39

    Total Investment Cost 301.50

    2. Economic Analysis

    2.1. Feed and Products

    2.1.1. Feed and Products Amounts

    According to section 3 the input material to Siraf Supporting Company and its products

    are as the below table.

    Table 3 - Project Feed and Products Input Material Amounts unit

    Natural Gas (As fuel) 15192 MMBTU/Day

    Natural Gas (As H2 Plant Feed) 4506 Nm3/hr

    Raw Water 5000 m3/hr

    Electricity Power 8565 kw

    Output Products(for sale)

    Hydrogen 24.68 T/d

    Compressed Air 8960 Nm3/hr

    Cooling Water 40000 m3/hr

  • 4

    2.2. Economic Evaluation Basis

    Table 4- Economic Evaluation Basis Item Basis

    Investment:

    Loan 75% of Total Investment

    Cash 25% of Total Investment

    Investment Distribution:

    1PstP year 25%

    2PndP year 50%

    3PrdP year 25%

    Repayment 6 Years (after construction period)

    On stream factor 0.96

    Discounted Rate 20%

    Interest Rate 12%

    Depreciation 15 Years

    Salvage value 20%

    Construction period 3 Years

    Production lifecycle 25 Years

  • 5

    2.3. Operating Cost

    Table 5 - Others Operating Costs Item MMUS$/Y

    Maintenance 7.45

    Insurance 0.89

    0BManpower 9.8

    Chemical and Catalyst, Feed &Energy 22.4

    2.3.1. Services Price

    Some services are provided by centralized facilities plant and for each refinery in the

    Park are summarized in Table 6.

    Table 6 - Services Costs Name of Services MMUS$/Y

    Sulphur Recovery Unit 3

    Amine Gas Treating Unit 1

    Sour Water Stripper Unit 1

    Waste Water Treatment Unit 2

    Fire Fighting Facilities 3

    Others Services 4

    Total 14

  • 6

    2.4. Economic Evaluation

    Using data in section 2.3.1 and Comfar III software, also considering 112 MMUS$ per

    year as the tariff of export services for this company, the economic evaluation results of

    the project are as below table.

    Table 7 - Economic Evaluation Results Item

    Total Investment(MMUS$) 301.50

    IRR% 42.64%

    NPV(MMUS$) 395.76

    Normal Payback Period(Years) 1

    Investment Cost EstimationManpowerEconomic AnalysisFeed and ProductsFeed and Products Amounts

    Economic Evaluation BasisOperating CostServices Price

    Economic Evaluation