Upload
mohammadreza-ghezelasheghi
View
2
Download
0
Embed Size (px)
DESCRIPTION
some thing about siraf
Citation preview
1
1. Investment Cost Estimation
The costs included in the investment cost estimate are grouped into three categories as
follows:
Inside Battery Limits (ISBL) costs
Outside Battery Limits (OSBL) costs
Other Project Costs
The estimated cost of ISBL and OSBL facilities by major process unit is presented in
Table 3.The estimated total cost of the utilities and supporting systems project is
presented in Table 4.This has improved the accuracy of the capital cost estimates to
30%.
The cost estimate initially was developed in U.S. dollars based on material and labor
costs thatapplied during 2013. The resulting cost estimate needs to be adjusted to reflect
costs that are expected to apply during the Projects procurement and construction period.
Table 1 - Facilities Investment Cost Units Capacity Investment Cost(MMUS$)
Hydrogen Manufacturing 10.3 MMSCFD
Amine System 100 t/d
Sour Water Stripping 35 m3/hr
Sulphur Recovery Unit 100 t/d
Waste Water Treatment 7000 m3/d
2
Compressed Air System 13925 Nm3/hr
Nitrogen Generation -
Fire Fighting Water System -
Laboratory -
Raw Water Receiving Facilities -
Cooling Water System -
Steam Generation system -
DM Water System -
Loading Facilities -
Buildings -
Piping System for Feed and
Products
-
Site preparation -
Connection Piping System -
Control Rooms -
Analyzers -
Total Facilities Cost - 298.11
3
Table 2 - Project Total Investment Cost Units Investment Cost(MMUS$)
Total Facilities Cost 298.11
Working Capital 3.39
Total Investment Cost 301.50
2. Economic Analysis
2.1. Feed and Products
2.1.1. Feed and Products Amounts
According to section 3 the input material to Siraf Supporting Company and its products
are as the below table.
Table 3 - Project Feed and Products Input Material Amounts unit
Natural Gas (As fuel) 15192 MMBTU/Day
Natural Gas (As H2 Plant Feed) 4506 Nm3/hr
Raw Water 5000 m3/hr
Electricity Power 8565 kw
Output Products(for sale)
Hydrogen 24.68 T/d
Compressed Air 8960 Nm3/hr
Cooling Water 40000 m3/hr
4
2.2. Economic Evaluation Basis
Table 4- Economic Evaluation Basis Item Basis
Investment:
Loan 75% of Total Investment
Cash 25% of Total Investment
Investment Distribution:
1PstP year 25%
2PndP year 50%
3PrdP year 25%
Repayment 6 Years (after construction period)
On stream factor 0.96
Discounted Rate 20%
Interest Rate 12%
Depreciation 15 Years
Salvage value 20%
Construction period 3 Years
Production lifecycle 25 Years
5
2.3. Operating Cost
Table 5 - Others Operating Costs Item MMUS$/Y
Maintenance 7.45
Insurance 0.89
0BManpower 9.8
Chemical and Catalyst, Feed &Energy 22.4
2.3.1. Services Price
Some services are provided by centralized facilities plant and for each refinery in the
Park are summarized in Table 6.
Table 6 - Services Costs Name of Services MMUS$/Y
Sulphur Recovery Unit 3
Amine Gas Treating Unit 1
Sour Water Stripper Unit 1
Waste Water Treatment Unit 2
Fire Fighting Facilities 3
Others Services 4
Total 14
6
2.4. Economic Evaluation
Using data in section 2.3.1 and Comfar III software, also considering 112 MMUS$ per
year as the tariff of export services for this company, the economic evaluation results of
the project are as below table.
Table 7 - Economic Evaluation Results Item
Total Investment(MMUS$) 301.50
IRR% 42.64%
NPV(MMUS$) 395.76
Normal Payback Period(Years) 1
Investment Cost EstimationManpowerEconomic AnalysisFeed and ProductsFeed and Products Amounts
Economic Evaluation BasisOperating CostServices Price
Economic Evaluation