    Information Management for Projects

    Site Document Management Activities

    Presented by: Olajide Kehinde

    Document Controller, AfamProjects

  • 8/14/2019 Site DCC Activities Presentation

    2/17

    Outline

    IMOperations Document control

    Document review process

    Revision control

    Document Retrieval Disaster recovery

    Conduct refresher training courses

    Time Management Register Management Interface management

    Escalation Management Quality Assurance Challenges/Recovery Strategies

  • 8/14/2019 Site DCC Activities Presentation

    3/17

    Background

    Site document control activitiescommences at construction phase ofprojects and terminates at projecthandover..

    DCC should be mobilized to site at least amonth to commencement of actualconstruction works..

    Early construction site would have aminimum of 2 document controllersrunning full time. Adjustments can be madeto the staff size as the volume of workincreases.

  • 8/14/2019 Site DCC Activities Presentation

    4/17

    TimeManagement

    Site DCC operate within the usual workperiod of 7am 4pm (9hrs), however at thepeak of construction activities DC are knowto work up to 9pm (14hrs).

    Site DCC also work on weekends as

    construction activities extends to thisperiod.

    Time management is key to ensuring DC isable to deliver effectively on assigned KPIs.

    . Templates for effective time managementin DCC has been developed by IM4P seesamples below

    TPI time management template.

    https://sww-knowledge-epg.shell.com/knowtepg2/livelink.exe?func=ll&objId=6967528&objAction=downloadhttps://sww-knowledge-epg.shell.com/knowtepg2/livelink.exe?func=ll&objId=6967528&objAction=download
  • 8/14/2019 Site DCC Activities Presentation

    5/17

    DCC receive document from contractor

    Quality check document

    Log document in assai/LL

    Identify appropriate department to which

    document is to be transmitted

    Contractor DCC transmits document

    to SPDC site DCC

    Transmit document via assai to responsible

    engineer determined by agreed matrix

    DCC updates document status in assai

    and transmits same to contractor DCC

    office

    Document Review Process

    Document Ok? No. Return to

    Contractor

    Engineer reviews document withinSLA and returns comments to DCC

    Document Ok? - YesYes

  • 8/14/2019 Site DCC Activities Presentation

    6/17

    Revision Control Process

    DCC receive document from contractor

    Quality check document

    Log document/drawing in assai/LL

    Identify appropriate department to

    which drawings belong

    Contractor DCC transmits

    document to SPDC site DCC

    Hard copies are printed, sorted, filed per

    discipline and finally stamped with official DCC

    control stamp.

    DCC carries out site inspections to

    ensure drawings in use on site are

    most current revisions as issued byDCC. Deviations are reported to

    construction manager for

    appropriate action

    Updated Revision? No. Return to

    Contractor

    Drawing are then transmitted to various

    departments for engineers to use on project site

    Updated Revision? Yes

  • 8/14/2019 Site DCC Activities Presentation

    7/17

    Other Processes Managed By DCC

    Correspondence Management Process. Controlled Documents Management Process.

    Site Queries, DCN, NCR and CAR Management

    .

    Facts - At peak of construction activities DCC has

    processed an average of 600 marked up

    documents and drawings/day. Processes vary from projects to project

    however there is a need to harmonize processto ensure a standard across the board.

    https://sww-knowledge-epg.shell.com/knowtepg2/livelink.exe?func=ll&objId=6998105&objAction=browsehttps://sww-knowledge-epg.shell.com/knowtepg2/livelink.exe?func=ll&objId=6998271&objAction=browsehttps://sww-knowledge-epg.shell.com/knowtepg2/livelink.exe?func=ll&objId=6999184&objAction=browsehttps://sww-knowledge-epg.shell.com/knowtepg2/livelink.exe?func=ll&objId=6999184&objAction=browsehttps://sww-knowledge-epg.shell.com/knowtepg2/livelink.exe?func=ll&objId=6998271&objAction=browsehttps://sww-knowledge-epg.shell.com/knowtepg2/livelink.exe?func=ll&objId=6998105&objAction=browse
  • 8/14/2019 Site DCC Activities Presentation

    8/17

    Registers Management

    Registers managed by DCC include butis not limited to Document Deliverables registers. Correspondence Registers.

    Technical Queries Register Design Change Notice Register Quality Audit Register Corrective Action Report Register Non Conformance Report register Interface Management registrar (QA-QC, Weekly

    Progress Meetings, Security Meetings). Project Document Activity Schedule

    https://sww-knowledge-epg.shell.com/knowtepg2/livelink.exe?func=ll&objId=7000775&objAction=browsehttps://sww-knowledge-epg.shell.com/knowtepg2/livelink.exe?func=ll&objId=7000775&objAction=browse
  • 8/14/2019 Site DCC Activities Presentation

    9/17

    IM Activites - Livelink Training

    Periodic training primarily for contractorDCC staff and subsequently for othercontractor engineers as the need arises.

    Site DCC also arranges assai/livelink

    training for SPDC engineers.

  • 8/14/2019 Site DCC Activities Presentation

    10/17

    IM Activites Document Retrieval

    Process of searching, compiling and printing of selecteddocuments and drawings for use during companyaudits, special reviews and VAR sessions

    URLs to recently compiled Audit Spreadsheet are shownbelow

    4. Afam VI PSUA Register 17-04- 08 Rev. 4

    5. PSUA Document Listing

    6. Afam Contracts Spreadsheet

    http://sww-knowledge-epe.shell.com/glasepp/livelink.exe/Afam_VI_PSUA_Register_17-04-_08_Rev._4_.xls?func=doc.Fetch&nodeId=7729424&docTitle=Afam+VI+PSUA+Register+17%2D04%2D+08+Rev%2E+4+%2Exlshttps://sww-knowledge-epg.shell.com/knowtepg2/livelink.exe?func=ll&objId=6402912&objAction=downloadhttps://sww-knowledge-epg.shell.com/knowtepg2/livelink.exe?func=ll&objId=5729252&objAction=downloadhttps://sww-knowledge-epg.shell.com/knowtepg2/livelink.exe?func=ll&objId=5729252&objAction=downloadhttps://sww-knowledge-epg.shell.com/knowtepg2/livelink.exe?func=ll&objId=6402912&objAction=downloadhttp://sww-knowledge-epe.shell.com/glasepp/livelink.exe/Afam_VI_PSUA_Register_17-04-_08_Rev._4_.xls?func=doc.Fetch&nodeId=7729424&docTitle=Afam+VI+PSUA+Register+17%2D04%2D+08+Rev%2E+4+%2Exls
  • 8/14/2019 Site DCC Activities Presentation

    11/17

    IM Activites - Disaster Recovery Process involves conversion of all hardcopy

    documents on the project into electroniccopies, for subsequent storage in theproject EDMS. This a proactive step takento reduce recovery time on the business inthe event of a disaster e.g. Fire.

    To date Afam projects has converted over11,000 documents and stored same inassai/ll.

    Documents are stored in PDF format. Hard copies of converted documents are

    filed and stored in metal cabinet files.

    NB - above mentioned process are seamlessly achieved usingvarious sophisticated business solutions i.E. HP printers,

    scanners and photocopying machines.

  • 8/14/2019 Site DCC Activities Presentation

    12/17

    IM Activites - Adhoc

    Scanning Requests

    Printing Requests

  • 8/14/2019 Site DCC Activities Presentation

    13/17

    Weekly interface meeting with contractorDCC to ensure harmonizeddocument/correspondence registers.

    Weekly exception reports are issued everyweek to project management team forpossible follow up on all overdue documentsif any.

    Weekly DCC internal meeting on site.

    Bi-weekly meeting with project IM lead. For DC running back to back activities,

    changeover date doubles as a handoverdate. Both DC work together on changeover

    date and exchange handover notes.

    Interface Management

  • 8/14/2019 Site DCC Activities Presentation

    14/17

    Escalation Management

    Issues/Challenges 1st Line of Reporting2nd Line of

    ReportingEscalation

    Overdue

    DocumentsSite QA-QC Lead

    Construction

    SuperintendentProject IM Lead

    Revision

    Control/Controlled Documentsbreakdown

    Site QA-QC Lead

    Construction

    Superintendent Project IM Lead

    HardwareAllocation

    Project IM LeadFollow-up Follow-up

    Network Outages Project IT SupportProject IM Lead

    Follow-up

    Livelink

    Permissions

    Document Control

    LeadProject IM Lead Follow-up

    Contract Renewal Project IM Lead IM4P ContractsManager

    Follow-up

  • 8/14/2019 Site DCC Activities Presentation

    15/17

    To ensure contractor compliance with approved IMplan and other DC procedures

    To ensure IM deliverables are on schedule, if any

    delays are encountered recovery plans are resolved

    during such audit programs

    Proactive monitoring of DDR to obtain documents

    for review/approval

    External QA Audits are structured andfollow approved IM assurance plan

    See URL to IM assurance plan -

    Quality Assurance

    http://sww-knowledge-epe.shell.com/glasepp/livelink.exe/Afam_Projects_IM_Assurance_Plan.xls?func=doc.Fetch&nodeId=7206174&docTitle=Afam+Projects+IM+Assurance+Planhttp://sww-knowledge-epe.shell.com/glasepp/livelink.exe/Afam_Projects_IM_Assurance_Plan.xls?func=doc.Fetch&nodeId=7206174&docTitle=Afam+Projects+IM+Assurance+Plan
  • 8/14/2019 Site DCC Activities Presentation

    16/17

    Challenges/Recovery Strategies

    Erratic network on site incurs downtime and

    reduces effective delivery of IMdeliverables.

    Procure stand alone business solutions tofacilitate business continuity.

    Duly report network outages to appropriateauthorities and ensure follow-up.

    Hard copy transmittals are generated and sent tocontractors in addition to soft copies.

    Complacent attitude of some engineers to

    the IM process. Conduct frequent awareness sessions to educate

    engineers on the values of the IM process.

    Escalate breaches in the IM process to Site

    construction lead and project IM lead .