Upload
truongcong
View
216
Download
1
Embed Size (px)
Citation preview
SITE DESIGN ENGINEERING, LLC.
11 Cushman Street, Middleboro, MA 02346 P: 508-967-0673 F: 508-967-0674
INTRODUCTION
This drainage report was prepared for the proposed site re-development at 10 B Street in Burlington, Massachusetts.
The project site is approximately 1.05± acres consisting of approximately 70% impervious surfaces and 30% open space. The site contains an existing 9,900± sf building surrounded on all sides with paved parking. The site is accessed from B Street by three existing driveways. Abutting properties to the east, west, and south are fully developed and contain commercial buildings with associated parking. This drainage analysis was performed to determine and analyze the stormwater runoff characteristics resulting from the proposed site changes. There are no existing on-site stormwater systems to accommodate parking lot stormwater runoff. Stormwater from the paved areas of the site runs toward abutting properties to the south, east and west as well as into B Street. There is a small open wooded area on the east side of the building that collects a portion of the runoff from abutting parking areas. The proposed project will reconstruct the majority of parking areas and provide additional site parking and improved site circulation. An underground drainage system will be constructed to capture, treat and infiltrate stormwater runoff. The proposed system will improve treatment of the existing stormwater runoff where none currently exists.
DRAINAGE SYSTEM DESIGN
Drainage System Model
The proposed drainage system is designed to mitigate and treat stormwater runoff occurring from 2, 10, 25 and 100-year 24-hour storm events. The project proposes to expand and redesign the layout of the existing driveway and parking. The proposed driveway and parking redesign will not increase the amount of impervious area on the property. The drainage system is designed according to the recommendations of the Department of Environmental Protection Stormwater Management Policy. The drainage system for this project was designed using the HydroCad Stormwater Modeling System. The HydroCad model consists of subcatchments and ponds. The subcatchments are the drainage areas to each respective structure; the structures are modeled as ponds. The site’s drainage area is divided into subcatchments. In the pre-development analysis the central portion is modeled in HydroCad as subcatchment e1. Presently an isolated vegetated area surrounded by paved driveway and parking exists east of the building. Existing topography indicates a significant quantity of surface runoff generated on site as well as a portion of its easterly abutter flows toward a low point contained within the isolated wooded area modeled as HydroCad pond eL1. Pre-development subcatchment model e2 represents stormwater runoff at the rear of the site which flows from the southeasterly corner to southwesterly corner towards the abutting property. Pre-development subcatchment model e3 represents stormwater surface runoff on site which flows uniformly from south to north towards B Street contributing to the existing municipal drainage system.
SITE DESIGN ENGINEERING, LLC.
11 Cushman Street, Middleboro, MA 02346 P: 508-967-0673 F: 508-967-0674
The post-development site is divided into two subcatchments, S12 and S3. Subcatchment S12 represents a combination of pre-development subcatchment E1 and E2 which are now combined and flow into the proposed stormwater system. Post-development subcatchment S3 is the equivalent of pre-development E3 which flows towards B Street. The rate and volume of water directed to B Street is reduced in the poste-development condition due to decreases in impervious cover in this area. Stormwater Treatment & Storage System
The proposed stormwater treatment and storage system utilizes stormwater management Best Management Practices (BMP’s). The BMP’s proposed consist of a sediment forebay, oil water separator and underground storage/infiltration system. The majority of the runoff generated from the parking area is captured and treated by the proposed BMP’s. The proposed system will provide treatment and mitigation to stormwater flows where none currently exist. HydroCad was utilized to analyze and design the stormwater storage system. The HydroCad
model simulates the system’s function during a storm in order to evaluate its design. The system is modeled in series starting with the sediment forebay, oil/water separator and underground infiltration system. The sediment forebay and oil/water separator provide a minimum 44% TSS removal rate prior to water entering the underground system. The system is entirely self-contained with no outlets discharging to abutting properties or public ways. Stormwater will first enter the sediment forebay where it will be stored and infiltrated at a slow infiltration rate of 2.41 inches per hour. This slow rate is utilized to allow for sediment buildup and clogging of soil pore space. In large storm events the water level will rise sufficiently to discharge water into the oil/water separator and the underground storage/infiltration system. The oil/water separator does not provide any meaningful storage component. The underground system stores water within the plastic chambers and surrounding stone void space. The stone void ratio is accounted to be 40 percent. A Rawls infiltration rate of 8.27 in/hour class “A” sand is utilized based on available soil boring information. The underground system is constructed with heavy duty H20 plastic chambers model Stormtech SC-310 as manufactured by ADS. The system will store and infiltrate stormwater as stipulated by the stormwater management policy. In HydroCad the underground system is modeled as pond US1. The system is designed utilizing a groundwater elevation of 43.75+/- (5.75 foot depth) based on soil borings completed by GZA. Copies of the soil borings are included in this report, refer to boring GZ-1, 2 and 8. This depth to groundwater provides a minimum separation of 2.0 feet from the bottom of the proposed infiltration system.
RESULTS
Post-development HydroCad Pond P1b is the analytical comparison to pre-development subcatchment e2. In the post-development condition all of the runoff generated from E1 and E2 is infiltrated in the proposed storage system on-site therefore there is no longer a post-development discharge point on the south end of the site. Post-Development subcatchment S3 is the analytical comparison to pre-development subcatchment E3. S3 and E3 are direct runoff contributors to the existing municipal drainage network within B Street. S3 contains less
SITE DESIGN ENGINEERING, LLC.
11 Cushman Street, Middleboro, MA 02346 P: 508-967-0673 F: 508-967-0674
impervious area than E3 and therefore reduces the rate and volume of water entering B Street. Post-development peak flow rates for applicable subcatchment comparison points do not exceed peak flow rate values of the comparative pre-development HydroCad subcatchment models.
FLOW RATES & VOLUME SUMMARY
Pre-Development
Analysis Pt. e3 Post-Development
Analysis Pt. S3 Storm Event Flow Rate (cfs) Volume (cf) Flow Rate (cfs) Volume (cf)
2 - Year 0.61 2,081 0.43 1,647 10 - Year 0.65 2,580 0.65 2,580 25 - Year 1.06 3,712 0.80 3,152
100 - Year 1.31 4,621 1.04 4,051
SITE DESIGN ENGINEERING, LLC.
11 Cushman Street, Middleboro, MA 02346 P: 508-967-0673 F: 508-967-0674
ANALYSIS DATA
The following information was used in performing the calculations for the drainage system.
NRCS Soils Information The NRCS Soil Survey lists the site as Urban Land (602) with Hinckley (253B) nearby. Site soil evaluation and monitoring have indicated that the prevalent material has the characteristics of a NRCS drainage class for this soil type is “A”. Please refer to the appendices for copies of the NRCS soil survey map and soil boring logs.
1. Existing & Proposed Ground Covers:
The existing ground cover of the site is predominantly developed, consisting of landscaping and buildings. The Curve Numbers listed below, hydrologic soil type A, were used in all the calculations performed with HydroCad.
RUNOFF CURVE NUMBERS
Cover Description Cover Type Hydrologic condition Curve Number
Dense Grass, Woods Fair 43 Landscaping, Lawns Fair 49
Rooftops, Pavements - 98 Walkways, Sidewalks - 98
2. Rainfall Data (24 Hour Storm Duration*)
Storm Event Rainfall
2 - Year 3.1 inches
10 - Year 4.5 inches
25 - Year 5.3 inches
100 - Year 6.5 inches
* From U.S. Department of Commerce Weather Bureau T.P. 40, May 1961, see attached.
SITE DESIGN ENGINEERING, LLC.
11 Cushman Street, Middleboro, MA 02346 P: 508-967-0673 F: 508-967-0674
STORMWATER MANAGEMENT SYSTEM
BEST MANAGEMENT PRACTICES (BMP) RECOMMENDED MAINTENANCE
10 B STREET BURLINGTON, MA
SEDIMENT FOREBAYS Maintenance:
• Inspections shall be performed monthly. • Accumulated sediment should be removed a minimum of one time per year or
whenever the depth of accumulation exceeds 3 inches. • Grass height should be maintained between 3 to 6 inches. • All sediment, debris, floatables, contaminants shall be disposed of to a landfill or
other permitted facility. OIL/WATER & SEDIMENT SEPARATOR Maintenance:
• Inspections shall be performed two times per year. • Units shall be cleaned at least once a year or more frequently whenever the
depth of sediment is greater than or equal to half the sump depth. • The inlet grate shall not be welded to the frame so that the sump can be easily
inspected and maintained. • Maintenance of structure shall be performed by qualified personnel and in
accordance with OSHA regulations. • All sediment, debris, floatables, contaminants shall be disposed of to a landfill or
other permitted facility. SUBSURFACE INFILTRATION/STORAGE CHAMBERS Maintenance:
• Inspections shall be performed on pretreatment BMP’s per above outline to ensure proper function of chamber system.
• The infiltration system shall be inspected 24 hours after major rainfall events (4
inches or more) for retention of liquid following the first 6 months of full operation. After 6 months of operation the system should be inspected at least two time per year at upon the same schedule used for the oil/water separator. The inspection shall be by means of the inspection manhole and/or inspection ports. If liquid is found, the depth shall be recorded and a check of recent storm events and rainfall totals shall be obtained. A follow up inspection within twenty-four (24) hours shall be conducted and the depth of liquid shall be re-measured. If water is still present after the follow up inspection the owner shall notify the design engineer.
e1
Ex Cond/ Pre Dev Subcatchment - flowing
to exist. low point
e2
Ex Cond/ Pre Dev Subcatchment - flowing
to NE rear of site
e3
Ex Cond/ Pre Dev Subcatchment - flowing
south to B-Street (municipal)
S12
Post Dev Subcatchment - flowing to proposed
catch basin
S3
Post Dev Subcatchment - flowing south to
B-Street (municipal)
eL1
Exist. low point at westerly of site
P1a
Vegetated Depression - storage volume below
OW/OCB Rim
P1b
Vegetated Depression - storage volume above
OW/OCB Rim
US1
Underground Storage System - StormTech
SC310
Routing Diagram for 10 B STREET HYDROCAD MODEL 12-3-15Prepared by {enter your company name here}, Printed 12/3/2015
HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLCSubcat Reach Pond Link
10 B StreetType III 24-hr 2-year Rainfall=3.10"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 2HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Summary for Subcatchment e1: Ex Cond/ Pre Dev Subcatchment - flowing to exist. low point
Runoff = 0.35 cfs @ 12.15 hrs, Volume= 1,455 cf, Depth= 1.14"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 2-year Rainfall=3.10"
Area (sf) CN Description* 0 98 Buildings - existing* 6,040 98 Driveways, parkings, walkways - existing* 0 98 Other impervious - existing
0 49 50-75% Grass cover, Fair, HSG A9,300 43 Woods/grass comb., Fair, HSG A
15,340 65 Weighted Average9,300 43 60.63% Pervious Area6,040 98 39.37% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)
9.6 50 0.0120 0.09 Sheet Flow, SEGMENT ABGrass: Dense n= 0.240 P2= 3.50"
1.5 50 0.0120 0.55 Shallow Concentrated Flow, SEGMENT BCWoodland Kv= 5.0 fps
11.1 100 Total
Summary for Subcatchment e2: Ex Cond/ Pre Dev Subcatchment - flowing to NE rear of site
Runoff = 0.49 cfs @ 12.15 hrs, Volume= 2,025 cf, Depth= 1.91"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 2-year Rainfall=3.10"
10 B StreetType III 24-hr 2-year Rainfall=3.10"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 3HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Area (sf) CN Description* 0 98 Buildings - existing* 8,450 98 Driveways, parkings, walkways - existing* 0 98 Other impervious - existing
0 49 50-75% Grass cover, Fair, HSG A4,300 43 Woods/grass comb., Fair, HSG A
12,750 79 Weighted Average4,300 43 33.73% Pervious Area8,450 98 66.27% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)10.4 40 0.0175 0.06 Sheet Flow, SEGMENT AB
Woods: Light underbrush n= 0.400 P2= 3.50"1.0 95 0.0060 1.57 Shallow Concentrated Flow, SEGMENT BC
Paved Kv= 20.3 fps11.4 135 Total
Summary for Subcatchment e3: Ex Cond/ Pre Dev Subcatchment - flowing south to B-Street (municipal)
Runoff = 0.61 cfs @ 12.07 hrs, Volume= 2,081 cf, Depth= 2.54"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 2-year Rainfall=3.10"
Area (sf) CN Description* 0 98 Buildings - existing* 8,700 98 Driveways, parkings, walkways - existing* 0 98 Other impervious - existing
0 49 50-75% Grass cover, Fair, HSG A1,130 43 Woods/grass comb., Fair, HSG A9,830 92 Weighted Average1,130 43 11.50% Pervious Area8,700 98 88.50% Impervious Area
10 B StreetType III 24-hr 2-year Rainfall=3.10"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 4HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)
5.0 Direct Entry, SEGMENT AB
Summary for Subcatchment S12: Post Dev Subcatchment - flowing to proposed catch basin
Runoff = 1.26 cfs @ 12.09 hrs, Volume= 4,554 cf, Depth= 2.08"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 2-year Rainfall=3.10"
Area (sf) CN Description* 0 98 Buildings - existing* 18,920 98 Driveways, parking, walkways - proposed* 0 98 Other impervious - proposed* 4,300 49 Landscaping - proposed
0 49 50-75% Grass cover, Fair, HSG A3,085 43 Woods/grass comb., Fair, HSG A
26,305 84 Weighted Average7,385 46 28.07% Pervious Area
18,920 98 71.93% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)
6.7 35 0.0400 0.09 Sheet Flow, SEGMENT ABWoods: Light underbrush n= 0.400 P2= 3.50"
Summary for Subcatchment S3: Post Dev Subcatchment - flowing south to B-Street (municipal)
Runoff = 0.43 cfs @ 12.11 hrs, Volume= 1,647 cf, Depth= 1.70"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 2-year Rainfall=3.10"
10 B StreetType III 24-hr 2-year Rainfall=3.10"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 5HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Area (sf) CN Description* 0 98 Buildings - existing* 6,739 98 Driveways, parking, walkways - proposed* 0 98 Other impervious - proposed* 4,871 49 Landscaping - proposed
0 49 50-75% Grass cover, Fair, HSG A0 43 Woods/grass comb., Fair, HSG A
11,610 77 Weighted Average4,871 49 41.96% Pervious Area6,739 98 58.04% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)
7.8 35 0.0100 0.08 Sheet Flow, SEGMENT ABGrass: Dense n= 0.240 P2= 3.50"
Summary for Pond eL1: Exist. low point at westerly of site
Inflow Area = 15,340 sf, 39.37% Impervious, Inflow Depth = 1.14" for 2-year eventInflow = 0.35 cfs @ 12.15 hrs, Volume= 1,455 cfPrimary = 0.35 cfs @ 12.15 hrs, Volume= 1,455 cf, Atten= 0%, Lag= 0.0 min
Routing by Dyn-Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrs
Summary for Pond P1a: Vegetated Depression - storage volume below OW/OCB Rim
Inflow Area = 26,305 sf, 71.93% Impervious, Inflow Depth = 2.08" for 2-year eventInflow = 1.26 cfs @ 12.09 hrs, Volume= 4,554 cfOutflow = 1.22 cfs @ 12.12 hrs, Volume= 4,553 cf, Atten= 3%, Lag= 1.5 minDiscarded = 0.04 cfs @ 12.12 hrs, Volume= 2,210 cfPrimary = 1.18 cfs @ 12.12 hrs, Volume= 2,343 cf
Routing by Dyn-Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrs
10 B StreetType III 24-hr 2-year Rainfall=3.10"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 6HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Peak Elev= 48.65' @ 12.12 hrs Surf.Area= 939 sf Storage= 728 cf
Plug-Flow detention time= 126.5 min calculated for 4,549 cf (100% of inflow)Center-of-Mass det. time= 127.3 min ( 887.4 - 760.1 )
Volume Invert Avail.Storage Storage Description#1 47.00' 8,209 cf Custom Stage Data - Vegetated Depression (Prismatic) Listed below (Recalc)
Elevation Surf.Area Inc.Store Cum.Store(feet) (sq-ft) (cubic-feet) (cubic-feet)47.00 150 0 047.50 260 103 10348.00 450 178 28048.50 820 318 59848.80 1,060 282 88049.00 1,220 228 1,10749.33 1,500 449 1,55649.50 5,000 553 2,10950.00 19,400 6,100 8,209
Device Routing Invert Outlet Devices#1 Discarded 47.00' 2.410 in/hr Exfiltration over Surface area from 47.00' - 48.90' Excluded Surface area = 150 sf #2 Primary 48.50' 24.0" Horiz. Orifice/Grate C= 0.600 Limited to weir flow at low heads
Discarded OutFlow Max=0.04 cfs @ 12.12 hrs HW=48.65' (Free Discharge)1=Exfiltration (Exfiltration Controls 0.04 cfs)
Primary OutFlow Max=1.17 cfs @ 12.12 hrs HW=48.65' TW=46.23' (Dynamic Tailwater)2=Orifice/Grate (Weir Controls 1.17 cfs @ 1.26 fps)
10 B StreetType III 24-hr 2-year Rainfall=3.10"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 7HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Summary for Pond P1b: Vegetated Depression - storage volume above OW/OCB Rim
Inflow Area = 26,305 sf, 71.93% Impervious, Inflow Depth = 0.00" for 2-year eventInflow = 0.00 cfs @ 0.00 hrs, Volume= 0 cfOutflow = 0.00 cfs @ 0.00 hrs, Volume= 0 cf, Atten= 0%, Lag= 0.0 minDiscarded = 0.00 cfs @ 0.00 hrs, Volume= 0 cf
Routing by Dyn-Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrsPeak Elev= 48.80' @ 0.00 hrs Surf.Area= 1,060 sf Storage= 0 cf
Plug-Flow detention time= (not calculated: initial storage exceeds outflow)Center-of-Mass det. time= (not calculated: no inflow)
Volume Invert Avail.Storage Storage Description#1 48.80' 7,329 cf Custom Stage Data - Vegetated Depression (Prismatic) Listed below (Recalc)
Elevation Surf.Area Inc.Store Cum.Store(feet) (sq-ft) (cubic-feet) (cubic-feet)48.80 1,060 0 049.00 1,220 228 22849.33 1,500 449 67749.50 5,000 553 1,22950.00 19,400 6,100 7,329
Device Routing Invert Outlet Devices#1 Discarded 48.80' 2.410 in/hr Exfiltration over Surface area from 48.80' - 48.90' Excluded Surface area = 1,060 sf
Discarded OutFlow Max=0.00 cfs @ 0.00 hrs HW=48.80' (Free Discharge)1=Exfiltration ( Controls 0.00 cfs)
10 B StreetType III 24-hr 2-year Rainfall=3.10"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 8HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Summary for Pond US1: Underground Storage System - StormTech SC310
Inflow Area = 26,305 sf, 71.93% Impervious, Inflow Depth = 1.07" for 2-year eventInflow = 1.18 cfs @ 12.12 hrs, Volume= 2,343 cfOutflow = 0.35 cfs @ 12.44 hrs, Volume= 2,350 cf, Atten= 70%, Lag= 19.2 minDiscarded = 0.35 cfs @ 12.44 hrs, Volume= 2,350 cfPrimary = 0.00 cfs @ 0.00 hrs, Volume= 0 cf
Routing by Dyn-Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrsPeak Elev= 46.51' @ 12.44 hrs Surf.Area= 1,724 sf Storage= 699 cf
Plug-Flow detention time= (not calculated: outflow precedes inflow)Center-of-Mass det. time= 14.8 min ( 757.6 - 742.8 )
Volume Invert Avail.Storage Storage Description#1A 45.75' 1,216 cf 38.17'W x 45.16'L x 2.33'H Field A
4,022 cf Overall - 983 cf Embedded = 3,039 cf x 40.0% Voids#2 48.08' 9 cf 2.00'D x 3.00'H Vertical Cone/Cylinder - OW/OCB Riser -Impervious#3A 46.25' 983 cf ADS_StormTech SC-310 x 66 Inside #1
Effective Size= 28.9"W x 16.0"H => 2.07 sf x 7.12'L = 14.7 cfOverall Size= 34.0"W x 16.0"H x 7.56'L with 0.44' OverlapRow Length Adjustment= +0.44' x 2.07 sf x 11 rows
2,208 cf Total Available Storage
Storage Group A created with Chamber Wizard
Device Routing Invert Outlet Devices#1 Discarded 45.75' 8.270 in/hr Exfiltration over Wetted area #2 Primary 48.50' 24.0" Horiz. Orifice/Grate - OW/OCB Rim C= 0.600 Limited to weir flow at low heads
Discarded OutFlow Max=0.35 cfs @ 12.44 hrs HW=46.51' (Free Discharge)1=Exfiltration (Exfiltration Controls 0.35 cfs)
Primary OutFlow Max=0.00 cfs @ 0.00 hrs HW=45.75' TW=48.80' (Dynamic Tailwater)2=Orifice/Grate - OW/OCB Rim ( Controls 0.00 cfs)
10 B StreetType III 24-hr 10-year Rainfall=4.50"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 9HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Summary for Subcatchment e1: Ex Cond/ Pre Dev Subcatchment - flowing to exist. low point
Runoff = 0.51 cfs @ 12.15 hrs, Volume= 2,322 cf, Depth= 1.82"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 10-year Rainfall=4.50"
Area (sf) CN Description* 0 98 Buildings - existing* 6,040 98 Driveways, parkings, walkways - existing* 0 98 Other impervious - existing
0 49 50-75% Grass cover, Fair, HSG A9,300 43 Woods/grass comb., Fair, HSG A
15,340 65 Weighted Average9,300 43 60.63% Pervious Area6,040 98 39.37% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)
9.6 50 0.0120 0.09 Sheet Flow, SEGMENT ABGrass: Dense n= 0.240 P2= 3.50"
1.5 50 0.0120 0.55 Shallow Concentrated Flow, SEGMENT BCWoodland Kv= 5.0 fps
11.1 100 Total
Summary for Subcatchment e2: Ex Cond/ Pre Dev Subcatchment - flowing to NE rear of site
Runoff = 0.71 cfs @ 12.15 hrs, Volume= 3,084 cf, Depth= 2.90"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 10-year Rainfall=4.50"
10 B StreetType III 24-hr 10-year Rainfall=4.50"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 10HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Area (sf) CN Description* 0 98 Buildings - existing* 8,450 98 Driveways, parkings, walkways - existing* 0 98 Other impervious - existing
0 49 50-75% Grass cover, Fair, HSG A4,300 43 Woods/grass comb., Fair, HSG A
12,750 79 Weighted Average4,300 43 33.73% Pervious Area8,450 98 66.27% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)10.4 40 0.0175 0.06 Sheet Flow, SEGMENT AB
Woods: Light underbrush n= 0.400 P2= 3.50"1.0 95 0.0060 1.57 Shallow Concentrated Flow, SEGMENT BC
Paved Kv= 20.3 fps11.4 135 Total
Summary for Subcatchment e3: Ex Cond/ Pre Dev Subcatchment - flowing south to B-Street (municipal)
Runoff = 0.90 cfs @ 12.07 hrs, Volume= 3,113 cf, Depth= 3.80"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 10-year Rainfall=4.50"
Area (sf) CN Description* 0 98 Buildings - existing* 8,700 98 Driveways, parkings, walkways - existing* 0 98 Other impervious - existing
0 49 50-75% Grass cover, Fair, HSG A1,130 43 Woods/grass comb., Fair, HSG A9,830 92 Weighted Average1,130 43 11.50% Pervious Area8,700 98 88.50% Impervious Area
10 B StreetType III 24-hr 10-year Rainfall=4.50"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 11HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)
5.0 Direct Entry, SEGMENT AB
Summary for Subcatchment S12: Post Dev Subcatchment - flowing to proposed catch basin
Runoff = 1.85 cfs @ 12.09 hrs, Volume= 6,940 cf, Depth= 3.17"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 10-year Rainfall=4.50"
Area (sf) CN Description* 0 98 Buildings - existing* 18,920 98 Driveways, parking, walkways - proposed* 0 98 Other impervious - proposed* 4,300 49 Landscaping - proposed
0 49 50-75% Grass cover, Fair, HSG A3,085 43 Woods/grass comb., Fair, HSG A
26,305 84 Weighted Average7,385 46 28.07% Pervious Area
18,920 98 71.93% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)
6.7 35 0.0400 0.09 Sheet Flow, SEGMENT ABWoods: Light underbrush n= 0.400 P2= 3.50"
Summary for Subcatchment S3: Post Dev Subcatchment - flowing south to B-Street (municipal)
Runoff = 0.65 cfs @ 12.11 hrs, Volume= 2,580 cf, Depth= 2.67"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 10-year Rainfall=4.50"
10 B StreetType III 24-hr 10-year Rainfall=4.50"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 12HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Area (sf) CN Description* 0 98 Buildings - existing* 6,739 98 Driveways, parking, walkways - proposed* 0 98 Other impervious - proposed* 4,871 49 Landscaping - proposed
0 49 50-75% Grass cover, Fair, HSG A0 43 Woods/grass comb., Fair, HSG A
11,610 77 Weighted Average4,871 49 41.96% Pervious Area6,739 98 58.04% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)
7.8 35 0.0100 0.08 Sheet Flow, SEGMENT ABGrass: Dense n= 0.240 P2= 3.50"
Summary for Pond eL1: Exist. low point at westerly of site
Inflow Area = 15,340 sf, 39.37% Impervious, Inflow Depth = 1.82" for 10-year eventInflow = 0.51 cfs @ 12.15 hrs, Volume= 2,322 cfPrimary = 0.51 cfs @ 12.15 hrs, Volume= 2,322 cf, Atten= 0%, Lag= 0.0 min
Routing by Dyn-Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrs
Summary for Pond P1a: Vegetated Depression - storage volume below OW/OCB Rim
Inflow Area = 26,305 sf, 71.93% Impervious, Inflow Depth = 3.17" for 10-year eventInflow = 1.85 cfs @ 12.09 hrs, Volume= 6,940 cfOutflow = 1.80 cfs @ 12.12 hrs, Volume= 6,939 cf, Atten= 3%, Lag= 1.4 minDiscarded = 0.05 cfs @ 12.12 hrs, Volume= 2,678 cfPrimary = 1.76 cfs @ 12.12 hrs, Volume= 4,261 cf
Routing by Dyn-Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrs
10 B StreetType III 24-hr 10-year Rainfall=4.50"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 13HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Peak Elev= 48.69' @ 12.12 hrs Surf.Area= 975 sf Storage= 772 cf
Plug-Flow detention time= 100.8 min calculated for 6,933 cf (100% of inflow)Center-of-Mass det. time= 101.6 min ( 858.6 - 756.9 )
Volume Invert Avail.Storage Storage Description#1 47.00' 8,209 cf Custom Stage Data - Vegetated Depression (Prismatic) Listed below (Recalc)
Elevation Surf.Area Inc.Store Cum.Store(feet) (sq-ft) (cubic-feet) (cubic-feet)47.00 150 0 047.50 260 103 10348.00 450 178 28048.50 820 318 59848.80 1,060 282 88049.00 1,220 228 1,10749.33 1,500 449 1,55649.50 5,000 553 2,10950.00 19,400 6,100 8,209
Device Routing Invert Outlet Devices#1 Discarded 47.00' 2.410 in/hr Exfiltration over Surface area from 47.00' - 48.90' Excluded Surface area = 150 sf #2 Primary 48.50' 24.0" Horiz. Orifice/Grate C= 0.600 Limited to weir flow at low heads
Discarded OutFlow Max=0.05 cfs @ 12.12 hrs HW=48.69' (Free Discharge)1=Exfiltration (Exfiltration Controls 0.05 cfs)
Primary OutFlow Max=1.74 cfs @ 12.12 hrs HW=48.69' TW=46.52' (Dynamic Tailwater)2=Orifice/Grate (Weir Controls 1.74 cfs @ 1.44 fps)
10 B StreetType III 24-hr 10-year Rainfall=4.50"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 14HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Summary for Pond P1b: Vegetated Depression - storage volume above OW/OCB Rim
Inflow Area = 26,305 sf, 71.93% Impervious, Inflow Depth = 0.00" for 10-year eventInflow = 0.00 cfs @ 0.00 hrs, Volume= 0 cfOutflow = 0.00 cfs @ 0.00 hrs, Volume= 0 cf, Atten= 0%, Lag= 0.0 minDiscarded = 0.00 cfs @ 0.00 hrs, Volume= 0 cf
Routing by Dyn-Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrsPeak Elev= 48.80' @ 0.00 hrs Surf.Area= 1,060 sf Storage= 0 cf
Plug-Flow detention time= (not calculated: initial storage exceeds outflow)Center-of-Mass det. time= (not calculated: no inflow)
Volume Invert Avail.Storage Storage Description#1 48.80' 7,329 cf Custom Stage Data - Vegetated Depression (Prismatic) Listed below (Recalc)
Elevation Surf.Area Inc.Store Cum.Store(feet) (sq-ft) (cubic-feet) (cubic-feet)48.80 1,060 0 049.00 1,220 228 22849.33 1,500 449 67749.50 5,000 553 1,22950.00 19,400 6,100 7,329
Device Routing Invert Outlet Devices#1 Discarded 48.80' 2.410 in/hr Exfiltration over Surface area from 48.80' - 48.90' Excluded Surface area = 1,060 sf
Discarded OutFlow Max=0.00 cfs @ 0.00 hrs HW=48.80' (Free Discharge)1=Exfiltration ( Controls 0.00 cfs)
10 B StreetType III 24-hr 10-year Rainfall=4.50"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 15HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Summary for Pond US1: Underground Storage System - StormTech SC310
Inflow Area = 26,305 sf, 71.93% Impervious, Inflow Depth = 1.94" for 10-year eventInflow = 1.76 cfs @ 12.12 hrs, Volume= 4,261 cfOutflow = 0.37 cfs @ 12.54 hrs, Volume= 4,271 cf, Atten= 79%, Lag= 25.4 minDiscarded = 0.37 cfs @ 12.54 hrs, Volume= 4,271 cfPrimary = 0.00 cfs @ 0.00 hrs, Volume= 0 cf
Routing by Dyn-Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrsPeak Elev= 47.15' @ 12.54 hrs Surf.Area= 1,724 sf Storage= 1,481 cf
Plug-Flow detention time= (not calculated: outflow precedes inflow)Center-of-Mass det. time= 29.0 min ( 774.3 - 745.4 )
Volume Invert Avail.Storage Storage Description#1A 45.75' 1,216 cf 38.17'W x 45.16'L x 2.33'H Field A
4,022 cf Overall - 983 cf Embedded = 3,039 cf x 40.0% Voids#2 48.08' 9 cf 2.00'D x 3.00'H Vertical Cone/Cylinder - OW/OCB Riser -Impervious#3A 46.25' 983 cf ADS_StormTech SC-310 x 66 Inside #1
Effective Size= 28.9"W x 16.0"H => 2.07 sf x 7.12'L = 14.7 cfOverall Size= 34.0"W x 16.0"H x 7.56'L with 0.44' OverlapRow Length Adjustment= +0.44' x 2.07 sf x 11 rows
2,208 cf Total Available Storage
Storage Group A created with Chamber Wizard
Device Routing Invert Outlet Devices#1 Discarded 45.75' 8.270 in/hr Exfiltration over Wetted area #2 Primary 48.50' 24.0" Horiz. Orifice/Grate - OW/OCB Rim C= 0.600 Limited to weir flow at low heads
Discarded OutFlow Max=0.37 cfs @ 12.54 hrs HW=47.15' (Free Discharge)1=Exfiltration (Exfiltration Controls 0.37 cfs)
Primary OutFlow Max=0.00 cfs @ 0.00 hrs HW=45.75' TW=48.80' (Dynamic Tailwater)2=Orifice/Grate - OW/OCB Rim ( Controls 0.00 cfs)
10 B StreetType III 24-hr 25-year Rainfall=5.30"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 16HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Summary for Subcatchment e1: Ex Cond/ Pre Dev Subcatchment - flowing to exist. low point
Runoff = 0.62 cfs @ 12.15 hrs, Volume= 2,890 cf, Depth= 2.26"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 25-year Rainfall=5.30"
Area (sf) CN Description* 0 98 Buildings - existing* 6,040 98 Driveways, parkings, walkways - existing* 0 98 Other impervious - existing
0 49 50-75% Grass cover, Fair, HSG A9,300 43 Woods/grass comb., Fair, HSG A
15,340 65 Weighted Average9,300 43 60.63% Pervious Area6,040 98 39.37% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)
9.6 50 0.0120 0.09 Sheet Flow, SEGMENT ABGrass: Dense n= 0.240 P2= 3.50"
1.5 50 0.0120 0.55 Shallow Concentrated Flow, SEGMENT BCWoodland Kv= 5.0 fps
11.1 100 Total
Summary for Subcatchment e2: Ex Cond/ Pre Dev Subcatchment - flowing to NE rear of site
Runoff = 0.85 cfs @ 12.15 hrs, Volume= 3,723 cf, Depth= 3.50"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 25-year Rainfall=5.30"
10 B StreetType III 24-hr 25-year Rainfall=5.30"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 17HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Area (sf) CN Description* 0 98 Buildings - existing* 8,450 98 Driveways, parkings, walkways - existing* 0 98 Other impervious - existing
0 49 50-75% Grass cover, Fair, HSG A4,300 43 Woods/grass comb., Fair, HSG A
12,750 79 Weighted Average4,300 43 33.73% Pervious Area8,450 98 66.27% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)10.4 40 0.0175 0.06 Sheet Flow, SEGMENT AB
Woods: Light underbrush n= 0.400 P2= 3.50"1.0 95 0.0060 1.57 Shallow Concentrated Flow, SEGMENT BC
Paved Kv= 20.3 fps11.4 135 Total
Summary for Subcatchment e3: Ex Cond/ Pre Dev Subcatchment - flowing south to B-Street (municipal)
Runoff = 1.06 cfs @ 12.07 hrs, Volume= 3,712 cf, Depth= 4.53"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 25-year Rainfall=5.30"
Area (sf) CN Description* 0 98 Buildings - existing* 8,700 98 Driveways, parkings, walkways - existing* 0 98 Other impervious - existing
0 49 50-75% Grass cover, Fair, HSG A1,130 43 Woods/grass comb., Fair, HSG A9,830 92 Weighted Average1,130 43 11.50% Pervious Area8,700 98 88.50% Impervious Area
10 B StreetType III 24-hr 25-year Rainfall=5.30"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 18HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)
5.0 Direct Entry, SEGMENT AB
Summary for Subcatchment S12: Post Dev Subcatchment - flowing to proposed catch basin
Runoff = 2.22 cfs @ 12.09 hrs, Volume= 8,364 cf, Depth= 3.82"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 25-year Rainfall=5.30"
Area (sf) CN Description* 0 98 Buildings - existing* 18,920 98 Driveways, parking, walkways - proposed* 0 98 Other impervious - proposed* 4,300 49 Landscaping - proposed
0 49 50-75% Grass cover, Fair, HSG A3,085 43 Woods/grass comb., Fair, HSG A
26,305 84 Weighted Average7,385 46 28.07% Pervious Area
18,920 98 71.93% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)
6.7 35 0.0400 0.09 Sheet Flow, SEGMENT ABWoods: Light underbrush n= 0.400 P2= 3.50"
Summary for Subcatchment S3: Post Dev Subcatchment - flowing south to B-Street (municipal)
Runoff = 0.80 cfs @ 12.11 hrs, Volume= 3,152 cf, Depth= 3.26"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 25-year Rainfall=5.30"
10 B StreetType III 24-hr 25-year Rainfall=5.30"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 19HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Area (sf) CN Description* 0 98 Buildings - existing* 6,739 98 Driveways, parking, walkways - proposed* 0 98 Other impervious - proposed* 4,871 49 Landscaping - proposed
0 49 50-75% Grass cover, Fair, HSG A0 43 Woods/grass comb., Fair, HSG A
11,610 77 Weighted Average4,871 49 41.96% Pervious Area6,739 98 58.04% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)
7.8 35 0.0100 0.08 Sheet Flow, SEGMENT ABGrass: Dense n= 0.240 P2= 3.50"
Summary for Pond eL1: Exist. low point at westerly of site
Inflow Area = 15,340 sf, 39.37% Impervious, Inflow Depth = 2.26" for 25-year eventInflow = 0.62 cfs @ 12.15 hrs, Volume= 2,890 cfPrimary = 0.62 cfs @ 12.15 hrs, Volume= 2,890 cf, Atten= 0%, Lag= 0.0 min
Routing by Dyn-Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrs
Summary for Pond P1a: Vegetated Depression - storage volume below OW/OCB Rim
Inflow Area = 26,305 sf, 71.93% Impervious, Inflow Depth = 3.82" for 25-year eventInflow = 2.22 cfs @ 12.09 hrs, Volume= 8,364 cfOutflow = 2.17 cfs @ 12.12 hrs, Volume= 8,363 cf, Atten= 2%, Lag= 1.3 minDiscarded = 0.05 cfs @ 12.12 hrs, Volume= 2,886 cfPrimary = 2.12 cfs @ 12.12 hrs, Volume= 5,477 cf
Routing by Dyn-Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrs
10 B StreetType III 24-hr 25-year Rainfall=5.30"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 20HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Peak Elev= 48.72' @ 12.12 hrs Surf.Area= 996 sf Storage= 797 cf
Plug-Flow detention time= 90.3 min calculated for 8,356 cf (100% of inflow)Center-of-Mass det. time= 91.1 min ( 847.0 - 755.9 )
Volume Invert Avail.Storage Storage Description#1 47.00' 8,209 cf Custom Stage Data - Vegetated Depression (Prismatic) Listed below (Recalc)
Elevation Surf.Area Inc.Store Cum.Store(feet) (sq-ft) (cubic-feet) (cubic-feet)47.00 150 0 047.50 260 103 10348.00 450 178 28048.50 820 318 59848.80 1,060 282 88049.00 1,220 228 1,10749.33 1,500 449 1,55649.50 5,000 553 2,10950.00 19,400 6,100 8,209
Device Routing Invert Outlet Devices#1 Discarded 47.00' 2.410 in/hr Exfiltration over Surface area from 47.00' - 48.90' Excluded Surface area = 150 sf #2 Primary 48.50' 24.0" Horiz. Orifice/Grate C= 0.600 Limited to weir flow at low heads
Discarded OutFlow Max=0.05 cfs @ 12.12 hrs HW=48.72' (Free Discharge)1=Exfiltration (Exfiltration Controls 0.05 cfs)
Primary OutFlow Max=2.11 cfs @ 12.12 hrs HW=48.72' TW=46.70' (Dynamic Tailwater)2=Orifice/Grate (Weir Controls 2.11 cfs @ 1.53 fps)
10 B StreetType III 24-hr 25-year Rainfall=5.30"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 21HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Summary for Pond P1b: Vegetated Depression - storage volume above OW/OCB Rim
Inflow Area = 26,305 sf, 71.93% Impervious, Inflow Depth = 0.00" for 25-year eventInflow = 0.00 cfs @ 0.00 hrs, Volume= 0 cfOutflow = 0.00 cfs @ 0.00 hrs, Volume= 0 cf, Atten= 0%, Lag= 0.0 minDiscarded = 0.00 cfs @ 0.00 hrs, Volume= 0 cf
Routing by Dyn-Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrsPeak Elev= 48.80' @ 0.00 hrs Surf.Area= 1,060 sf Storage= 0 cf
Plug-Flow detention time= (not calculated: initial storage exceeds outflow)Center-of-Mass det. time= (not calculated: no inflow)
Volume Invert Avail.Storage Storage Description#1 48.80' 7,329 cf Custom Stage Data - Vegetated Depression (Prismatic) Listed below (Recalc)
Elevation Surf.Area Inc.Store Cum.Store(feet) (sq-ft) (cubic-feet) (cubic-feet)48.80 1,060 0 049.00 1,220 228 22849.33 1,500 449 67749.50 5,000 553 1,22950.00 19,400 6,100 7,329
Device Routing Invert Outlet Devices#1 Discarded 48.80' 2.410 in/hr Exfiltration over Surface area from 48.80' - 48.90' Excluded Surface area = 1,060 sf
Discarded OutFlow Max=0.00 cfs @ 0.00 hrs HW=48.80' (Free Discharge)1=Exfiltration ( Controls 0.00 cfs)
10 B StreetType III 24-hr 25-year Rainfall=5.30"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 22HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Summary for Pond US1: Underground Storage System - StormTech SC310
Inflow Area = 26,305 sf, 71.93% Impervious, Inflow Depth = 2.50" for 25-year eventInflow = 2.12 cfs @ 12.12 hrs, Volume= 5,477 cfOutflow = 0.39 cfs @ 12.57 hrs, Volume= 5,494 cf, Atten= 81%, Lag= 27.4 minDiscarded = 0.39 cfs @ 12.57 hrs, Volume= 5,494 cfPrimary = 0.00 cfs @ 0.00 hrs, Volume= 0 cf
Routing by Dyn-Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrsPeak Elev= 47.78' @ 12.57 hrs Surf.Area= 1,724 sf Storage= 1,991 cf
Plug-Flow detention time= (not calculated: outflow precedes inflow)Center-of-Mass det. time= 38.1 min ( 784.7 - 746.6 )
Volume Invert Avail.Storage Storage Description#1A 45.75' 1,216 cf 38.17'W x 45.16'L x 2.33'H Field A
4,022 cf Overall - 983 cf Embedded = 3,039 cf x 40.0% Voids#2 48.08' 9 cf 2.00'D x 3.00'H Vertical Cone/Cylinder - OW/OCB Riser -Impervious#3A 46.25' 983 cf ADS_StormTech SC-310 x 66 Inside #1
Effective Size= 28.9"W x 16.0"H => 2.07 sf x 7.12'L = 14.7 cfOverall Size= 34.0"W x 16.0"H x 7.56'L with 0.44' OverlapRow Length Adjustment= +0.44' x 2.07 sf x 11 rows
2,208 cf Total Available Storage
Storage Group A created with Chamber Wizard
Device Routing Invert Outlet Devices#1 Discarded 45.75' 8.270 in/hr Exfiltration over Wetted area #2 Primary 48.50' 24.0" Horiz. Orifice/Grate - OW/OCB Rim C= 0.600 Limited to weir flow at low heads
Discarded OutFlow Max=0.39 cfs @ 12.57 hrs HW=47.78' (Free Discharge)1=Exfiltration (Exfiltration Controls 0.39 cfs)
Primary OutFlow Max=0.00 cfs @ 0.00 hrs HW=45.75' TW=48.80' (Dynamic Tailwater)2=Orifice/Grate - OW/OCB Rim ( Controls 0.00 cfs)
10 B StreetType III 24-hr 100-year Rainfall=6.50"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 23HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Summary for Subcatchment e1: Ex Cond/ Pre Dev Subcatchment - flowing to exist. low point
Runoff = 0.84 cfs @ 12.16 hrs, Volume= 3,823 cf, Depth= 2.99"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 100-year Rainfall=6.50"
Area (sf) CN Description* 0 98 Buildings - existing* 6,040 98 Driveways, parkings, walkways - existing* 0 98 Other impervious - existing
0 49 50-75% Grass cover, Fair, HSG A9,300 43 Woods/grass comb., Fair, HSG A
15,340 65 Weighted Average9,300 43 60.63% Pervious Area6,040 98 39.37% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)
9.6 50 0.0120 0.09 Sheet Flow, SEGMENT ABGrass: Dense n= 0.240 P2= 3.50"
1.5 50 0.0120 0.55 Shallow Concentrated Flow, SEGMENT BCWoodland Kv= 5.0 fps
11.1 100 Total
Summary for Subcatchment e2: Ex Cond/ Pre Dev Subcatchment - flowing to NE rear of site
Runoff = 1.08 cfs @ 12.16 hrs, Volume= 4,719 cf, Depth= 4.44"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 100-year Rainfall=6.50"
10 B StreetType III 24-hr 100-year Rainfall=6.50"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 24HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Area (sf) CN Description* 0 98 Buildings - existing* 8,450 98 Driveways, parkings, walkways - existing* 0 98 Other impervious - existing
0 49 50-75% Grass cover, Fair, HSG A4,300 43 Woods/grass comb., Fair, HSG A
12,750 79 Weighted Average4,300 43 33.73% Pervious Area8,450 98 66.27% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)10.4 40 0.0175 0.06 Sheet Flow, SEGMENT AB
Woods: Light underbrush n= 0.400 P2= 3.50"1.0 95 0.0060 1.57 Shallow Concentrated Flow, SEGMENT BC
Paved Kv= 20.3 fps11.4 135 Total
Summary for Subcatchment e3: Ex Cond/ Pre Dev Subcatchment - flowing south to B-Street (municipal)
Runoff = 1.31 cfs @ 12.07 hrs, Volume= 4,621 cf, Depth= 5.64"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 100-year Rainfall=6.50"
Area (sf) CN Description* 0 98 Buildings - existing* 8,700 98 Driveways, parkings, walkways - existing* 0 98 Other impervious - existing
0 49 50-75% Grass cover, Fair, HSG A1,130 43 Woods/grass comb., Fair, HSG A9,830 92 Weighted Average1,130 43 11.50% Pervious Area8,700 98 88.50% Impervious Area
10 B StreetType III 24-hr 100-year Rainfall=6.50"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 25HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)
5.0 Direct Entry, SEGMENT AB
Summary for Subcatchment S12: Post Dev Subcatchment - flowing to proposed catch basin
Runoff = 2.82 cfs @ 12.09 hrs, Volume= 10,563 cf, Depth= 4.82"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 100-year Rainfall=6.50"
Area (sf) CN Description* 0 98 Buildings - existing* 18,920 98 Driveways, parking, walkways - proposed* 0 98 Other impervious - proposed* 4,300 49 Landscaping - proposed
0 49 50-75% Grass cover, Fair, HSG A3,085 43 Woods/grass comb., Fair, HSG A
26,305 84 Weighted Average7,385 46 28.07% Pervious Area
18,920 98 71.93% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)
6.7 35 0.0400 0.09 Sheet Flow, SEGMENT ABWoods: Light underbrush n= 0.400 P2= 3.50"
Summary for Subcatchment S3: Post Dev Subcatchment - flowing south to B-Street (municipal)
Runoff = 1.04 cfs @ 12.11 hrs, Volume= 4,051 cf, Depth= 4.19"
Runoff by SCS TR-20 method, UH=SCS, Split Pervious/Imperv., Time Span= 0.00-48.00 hrs, dt= 0.04 hrsType III 24-hr 100-year Rainfall=6.50"
10 B StreetType III 24-hr 100-year Rainfall=6.50"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 26HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Area (sf) CN Description* 0 98 Buildings - existing* 6,739 98 Driveways, parking, walkways - proposed* 0 98 Other impervious - proposed* 4,871 49 Landscaping - proposed
0 49 50-75% Grass cover, Fair, HSG A0 43 Woods/grass comb., Fair, HSG A
11,610 77 Weighted Average4,871 49 41.96% Pervious Area6,739 98 58.04% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (feet) (ft/ft) (ft/sec) (cfs)
7.8 35 0.0100 0.08 Sheet Flow, SEGMENT ABGrass: Dense n= 0.240 P2= 3.50"
Summary for Pond eL1: Exist. low point at westerly of site
Inflow Area = 15,340 sf, 39.37% Impervious, Inflow Depth = 2.99" for 100-year eventInflow = 0.84 cfs @ 12.16 hrs, Volume= 3,823 cfPrimary = 0.84 cfs @ 12.16 hrs, Volume= 3,823 cf, Atten= 0%, Lag= 0.0 min
Routing by Dyn-Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrs
Summary for Pond P1a: Vegetated Depression - storage volume below OW/OCB Rim
Inflow Area = 26,305 sf, 71.93% Impervious, Inflow Depth = 4.82" for 100-year eventInflow = 2.82 cfs @ 12.09 hrs, Volume= 10,563 cfOutflow = 2.76 cfs @ 12.12 hrs, Volume= 10,561 cf, Atten= 2%, Lag= 1.3 minDiscarded = 0.05 cfs @ 12.44 hrs, Volume= 3,115 cfPrimary = 2.71 cfs @ 12.12 hrs, Volume= 7,447 cf
Routing by Dyn-Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrs
10 B StreetType III 24-hr 100-year Rainfall=6.50"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 27HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Peak Elev= 48.82' @ 12.44 hrs Surf.Area= 1,077 sf Storage= 902 cf
Plug-Flow detention time= 77.3 min calculated for 10,553 cf (100% of inflow)Center-of-Mass det. time= 78.1 min ( 833.0 - 754.9 )
Volume Invert Avail.Storage Storage Description#1 47.00' 8,209 cf Custom Stage Data - Vegetated Depression (Prismatic) Listed below (Recalc)
Elevation Surf.Area Inc.Store Cum.Store(feet) (sq-ft) (cubic-feet) (cubic-feet)47.00 150 0 047.50 260 103 10348.00 450 178 28048.50 820 318 59848.80 1,060 282 88049.00 1,220 228 1,10749.33 1,500 449 1,55649.50 5,000 553 2,10950.00 19,400 6,100 8,209
Device Routing Invert Outlet Devices#1 Discarded 47.00' 2.410 in/hr Exfiltration over Surface area from 47.00' - 48.90' Excluded Surface area = 150 sf #2 Primary 48.50' 24.0" Horiz. Orifice/Grate C= 0.600 Limited to weir flow at low heads
Discarded OutFlow Max=0.05 cfs @ 12.44 hrs HW=48.81' (Free Discharge)1=Exfiltration (Exfiltration Controls 0.05 cfs)
Primary OutFlow Max=2.69 cfs @ 12.12 hrs HW=48.76' TW=47.03' (Dynamic Tailwater)2=Orifice/Grate (Weir Controls 2.69 cfs @ 1.66 fps)
10 B StreetType III 24-hr 100-year Rainfall=6.50"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 28HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Summary for Pond P1b: Vegetated Depression - storage volume above OW/OCB Rim
Inflow Area = 26,305 sf, 71.93% Impervious, Inflow Depth = 0.30" for 100-year eventInflow = 1.68 cfs @ 12.52 hrs, Volume= 661 cfOutflow = 0.00 cfs @ 12.32 hrs, Volume= 572 cf, Atten= 100%, Lag= 0.0 minDiscarded = 0.00 cfs @ 12.32 hrs, Volume= 572 cf
Routing by Dyn-Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrsPeak Elev= 49.32' @ 12.56 hrs Surf.Area= 1,488 sf Storage= 656 cf
Plug-Flow detention time= 1,061.3 min calculated for 572 cf (87% of inflow)Center-of-Mass det. time= 1,060.1 min ( 1,804.2 - 744.1 )
Volume Invert Avail.Storage Storage Description#1 48.80' 7,329 cf Custom Stage Data - Vegetated Depression (Prismatic) Listed below (Recalc)
Elevation Surf.Area Inc.Store Cum.Store(feet) (sq-ft) (cubic-feet) (cubic-feet)48.80 1,060 0 049.00 1,220 228 22849.33 1,500 449 67749.50 5,000 553 1,22950.00 19,400 6,100 7,329
Device Routing Invert Outlet Devices#1 Discarded 48.80' 2.410 in/hr Exfiltration over Surface area from 48.80' - 48.90' Excluded Surface area = 1,060 sf
Discarded OutFlow Max=0.00 cfs @ 12.32 hrs HW=48.98' (Free Discharge)1=Exfiltration (Exfiltration Controls 0.00 cfs)
10 B StreetType III 24-hr 100-year Rainfall=6.50"10 B STREET HYDROCAD MODEL 12-3-15
Printed 12/3/2015Prepared by {enter your company name here}Page 29HydroCAD® 10.00-11 s/n 05085 © 2014 HydroCAD Software Solutions LLC
Summary for Pond US1: Underground Storage System - StormTech SC310
Inflow Area = 26,305 sf, 71.93% Impervious, Inflow Depth = 3.40" for 100-year eventInflow = 2.71 cfs @ 12.12 hrs, Volume= 7,447 cfOutflow = 2.08 cfs @ 12.52 hrs, Volume= 7,459 cf, Atten= 23%, Lag= 24.2 minDiscarded = 0.40 cfs @ 12.28 hrs, Volume= 6,798 cfPrimary = 1.68 cfs @ 12.52 hrs, Volume= 661 cf
Routing by Dyn-Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrsPeak Elev= 49.31' @ 12.50 hrs Surf.Area= 1,724 sf Storage= 2,202 cf
Plug-Flow detention time= (not calculated: outflow precedes inflow)Center-of-Mass det. time= 37.3 min ( 788.0 - 750.7 )
Volume Invert Avail.Storage Storage Description#1A 45.75' 1,216 cf 38.17'W x 45.16'L x 2.33'H Field A
4,022 cf Overall - 983 cf Embedded = 3,039 cf x 40.0% Voids#2 48.08' 9 cf 2.00'D x 3.00'H Vertical Cone/Cylinder - OW/OCB Riser -Impervious#3A 46.25' 983 cf ADS_StormTech SC-310 x 66 Inside #1
Effective Size= 28.9"W x 16.0"H => 2.07 sf x 7.12'L = 14.7 cfOverall Size= 34.0"W x 16.0"H x 7.56'L with 0.44' OverlapRow Length Adjustment= +0.44' x 2.07 sf x 11 rows
2,208 cf Total Available Storage
Storage Group A created with Chamber Wizard
Device Routing Invert Outlet Devices#1 Discarded 45.75' 8.270 in/hr Exfiltration over Wetted area #2 Primary 48.50' 24.0" Horiz. Orifice/Grate - OW/OCB Rim C= 0.600 Limited to weir flow at low heads
Discarded OutFlow Max=0.40 cfs @ 12.28 hrs HW=48.82' (Free Discharge)1=Exfiltration (Exfiltration Controls 0.40 cfs)
Primary OutFlow Max=0.00 cfs @ 12.52 hrs HW=49.16' TW=49.23' (Dynamic Tailwater)2=Orifice/Grate - OW/OCB Rim ( Controls 0.00 cfs)
swcheck.doc • 04/01/08 Stormwater Report Checklist • Page 1 of 8
Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands Program
Checklist for Stormwater Report
A. Introduction Important: When filling out forms on the computer, use only the tab key to move your cursor - do not use the return key.
A Stormwater Report must be submitted with the Notice of Intent permit application to document compliance with the Stormwater Management Standards. The following checklist is NOT a substitute for the Stormwater Report (which should provide more substantive and detailed information) but is offered here as a tool to help the applicant organize their Stormwater Management documentation for their Report and for the reviewer to assess this information in a consistent format. As noted in the Checklist, the Stormwater Report must contain the engineering computations and supporting information set forth in Volume 3 of the Massachusetts Stormwater Handbook. The Stormwater Report must be prepared and certified by a Registered Professional Engineer (RPE) licensed in the Commonwealth. The Stormwater Report must include:
• The Stormwater Checklist completed and stamped by a Registered Professional Engineer (see page 2) that certifies that the Stormwater Report contains all required submittals.1 This Checklist is to be used as the cover for the completed Stormwater Report.
• Applicant/Project Name • Project Address • Name of Firm and Registered Professional Engineer that prepared the Report • Long-Term Pollution Prevention Plan required by Standards 4-6 • Construction Period Pollution Prevention and Erosion and Sedimentation Control Plan required
by Standard 82 • Operation and Maintenance Plan required by Standard 9
In addition to all plans and supporting information, the Stormwater Report must include a brief narrative describing stormwater management practices, including environmentally sensitive site design and LID techniques, along with a diagram depicting runoff through the proposed BMP treatment train. Plans are required to show existing and proposed conditions, identify all wetland resource areas, NRCS soil types, critical areas, Land Uses with Higher Potential Pollutant Loads (LUHPPL), and any areas on the site where infiltration rate is greater than 2.4 inches per hour. The Plans shall identify the drainage areas for both existing and proposed conditions at a scale that enables verification of supporting calculations.
As noted in the Checklist, the Stormwater Management Report shall document compliance with each of the Stormwater Management Standards as provided in the Massachusetts Stormwater Handbook. The soils evaluation and calculations shall be done using the methodologies set forth in Volume 3 of the Massachusetts Stormwater Handbook. To ensure that the Stormwater Report is complete, applicants are required to fill in the Stormwater Report Checklist by checking the box to indicate that the specified information has been included in the Stormwater Report. If any of the information specified in the checklist has not been submitted, the applicant must provide an explanation. The completed Stormwater Report Checklist and Certification must be submitted with the Stormwater Report.
1 The Stormwater Report may also include the Illicit Discharge Compliance Statement required by Standard 10. If not included in the Stormwater Report, the Illicit Discharge Compliance Statement must be submitted prior to the discharge of stormwater runoff to the post-construction best management practices. 2 For some complex projects, it may not be possible to include the Construction Period Erosion and Sedimentation Control Plan in the Stormwater Report. In that event, the issuing authority has the discretion to issue an Order of Conditions that approves the project and includes a condition requiring the proponent to submit the Construction Period Erosion and Sedimentation Control Plan before commencing any land disturbance activity on the site.
swcheck.doc • 04/01/08 Stormwater Report Checklist • Page 3 of 8
Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands Program
Checklist for Stormwater Report
Checklist (continued) LID Measures: Stormwater Standards require LID measures to be considered. Document what
environmentally sensitive design and LID Techniques were considered during the planning and design of the project:
No disturbance to any Wetland Resource Areas
Site Design Practices (e.g. clustered development, reduced frontage setbacks)
Reduced Impervious Area (Redevelopment Only)
Minimizing disturbance to existing trees and shrubs
LID Site Design Credit Requested:
Credit 1
Credit 2
Credit 3
Use of “country drainage” versus curb and gutter conveyance and pipe
Bioretention Cells (includes Rain Gardens)
Constructed Stormwater Wetlands (includes Gravel Wetlands designs)
Treebox Filter
Water Quality Swale
Grass Channel
Green Roof
Other (describe):
Standard 1: No New Untreated Discharges
No new untreated discharges Outlets have been designed so there is no erosion or scour to wetlands and waters of the
Commonwealth
Supporting calculations specified in Volume 3 of the Massachusetts Stormwater Handbook included.
swcheck.doc • 04/01/08 Stormwater Report Checklist • Page 4 of 8
Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands Program
Checklist for Stormwater Report
Checklist (continued)
Standard 2: Peak Rate Attenuation Standard 2 waiver requested because the project is located in land subject to coastal storm flowage
and stormwater discharge is to a wetland subject to coastal flooding. Evaluation provided to determine whether off-site flooding increases during the 100-year 24-hour
storm.
Calculations provided to show that post-development peak discharge rates do not exceed pre-development rates for the 2-year and 10-year 24-hour storms. If evaluation shows that off-site flooding increases during the 100-year 24-hour storm, calculations are also provided to show that post-development peak discharge rates do not exceed pre-development rates for the 100-year 24-hour storm.
Standard 3: Recharge
Soil Analysis provided.
Required Recharge Volume calculation provided.
Required Recharge volume reduced through use of the LID site Design Credits.
Sizing the infiltration, BMPs is based on the following method: Check the method used.
Static Simple Dynamic Dynamic Field1
Runoff from all impervious areas at the site discharging to the infiltration BMP.
Runoff from all impervious areas at the site is not discharging to the infiltration BMP and calculations
are provided showing that the drainage area contributing runoff to the infiltration BMPs is sufficient to generate the required recharge volume.
Recharge BMPs have been sized to infiltrate the Required Recharge Volume.
Recharge BMPs have been sized to infiltrate the Required Recharge Volume only to the maximum extent practicable for the following reason:
Site is comprised solely of C and D soils and/or bedrock at the land surface
M.G.L. c. 21E sites pursuant to 310 CMR 40.0000
Solid Waste Landfill pursuant to 310 CMR 19.000
Project is otherwise subject to Stormwater Management Standards only to the maximum extent practicable.
Calculations showing that the infiltration BMPs will drain in 72 hours are provided.
Property includes a M.G.L. c. 21E site or a solid waste landfill and a mounding analysis is included.
1 80% TSS removal is required prior to discharge to infiltration BMP if Dynamic Field method is used.
swcheck.doc • 04/01/08 Stormwater Report Checklist • Page 5 of 8
Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands Program
Checklist for Stormwater Report
Checklist (continued)
Standard 3: Recharge (continued)
The infiltration BMP is used to attenuate peak flows during storms greater than or equal to the 10-year 24-hour storm and separation to seasonal high groundwater is less than 4 feet and a mounding analysis is provided.
Documentation is provided showing that infiltration BMPs do not adversely impact nearby wetland resource areas.
Standard 4: Water Quality
The Long-Term Pollution Prevention Plan typically includes the following: • Good housekeeping practices; • Provisions for storing materials and waste products inside or under cover; • Vehicle washing controls; • Requirements for routine inspections and maintenance of stormwater BMPs; • Spill prevention and response plans; • Provisions for maintenance of lawns, gardens, and other landscaped areas; • Requirements for storage and use of fertilizers, herbicides, and pesticides; • Pet waste management provisions; • Provisions for operation and management of septic systems; • Provisions for solid waste management; • Snow disposal and plowing plans relative to Wetland Resource Areas; • Winter Road Salt and/or Sand Use and Storage restrictions; • Street sweeping schedules; • Provisions for prevention of illicit discharges to the stormwater management system; • Documentation that Stormwater BMPs are designed to provide for shutdown and containment in the
event of a spill or discharges to or near critical areas or from LUHPPL; • Training for staff or personnel involved with implementing Long-Term Pollution Prevention Plan; • List of Emergency contacts for implementing Long-Term Pollution Prevention Plan.
A Long-Term Pollution Prevention Plan is attached to Stormwater Report and is included as an attachment to the Wetlands Notice of Intent.
Treatment BMPs subject to the 44% TSS removal pretreatment requirement and the one inch rule for calculating the water quality volume are included, and discharge:
is within the Zone II or Interim Wellhead Protection Area
is near or to other critical areas
is within soils with a rapid infiltration rate (greater than 2.4 inches per hour)
involves runoff from land uses with higher potential pollutant loads.
The Required Water Quality Volume is reduced through use of the LID site Design Credits.
Calculations documenting that the treatment train meets the 80% TSS removal requirement and, if applicable, the 44% TSS removal pretreatment requirement, are provided.
swcheck.doc • 04/01/08 Stormwater Report Checklist • Page 6 of 8
Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands Program
Checklist for Stormwater Report
Checklist (continued)
Standard 4: Water Quality (continued)
The BMP is sized (and calculations provided) based on:
The ½” or 1” Water Quality Volume or The equivalent flow rate associated with the Water Quality Volume and documentation is
provided showing that the BMP treats the required water quality volume.
The applicant proposes to use proprietary BMPs, and documentation supporting use of proprietary BMP and proposed TSS removal rate is provided. This documentation may be in the form of the propriety BMP checklist found in Volume 2, Chapter 4 of the Massachusetts Stormwater Handbook and submitting copies of the TARP Report, STEP Report, and/or other third party studies verifying performance of the proprietary BMPs.
A TMDL exists that indicates a need to reduce pollutants other than TSS and documentation showing that the BMPs selected are consistent with the TMDL is provided.
Standard 5: Land Uses With Higher Potential Pollutant Loads (LUHPPLs)
The NPDES Multi-Sector General Permit covers the land use and the Stormwater Pollution
Prevention Plan (SWPPP) has been included with the Stormwater Report.
The NPDES Multi-Sector General Permit covers the land use and the SWPPP will be submitted prior to the discharge of stormwater to the post-construction stormwater BMPs.
The NPDES Multi-Sector General Permit does not cover the land use.
LUHPPLs are located at the site and industry specific source control and pollution prevention measures have been proposed to reduce or eliminate the exposure of LUHPPLs to rain, snow, snow melt and runoff, and been included in the long term Pollution Prevention Plan.
All exposure has been eliminated.
All exposure has not been eliminated and all BMPs selected are on MassDEP LUHPPL list.
The LUHPPL has the potential to generate runoff with moderate to higher concentrations of oil and grease (e.g. all parking lots with >1000 vehicle trips per day) and the treatment train includes an oil grit separator, a filtering bioretention area, a sand filter or equivalent.
Standard 6: Critical Areas
The discharge is near or to a critical area and the treatment train includes only BMPs that MassDEP has approved for stormwater discharges to or near that particular class of critical area.
Critical areas and BMPs are identified in the Stormwater Report.
swcheck.doc • 04/01/08 Stormwater Report Checklist • Page 7 of 8
Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands Program
Checklist for Stormwater Report
Checklist (continued)
Standard 7: Redevelopments and Other Projects Subject to the Standards only to the maximum extent practicable
The project is subject to the Stormwater Management Standards only to the maximum Extent Practicable as a:
Limited Project
Small Residential Projects: 5-9 single family houses or 5-9 units in a multi-family development provided there is no discharge that may potentially affect a critical area.
Small Residential Projects: 2-4 single family houses or 2-4 units in a multi-family development with a discharge to a critical area
Marina and/or boatyard provided the hull painting, service and maintenance areas are protected from exposure to rain, snow, snow melt and runoff
Bike Path and/or Foot Path
Redevelopment Project
Redevelopment portion of mix of new and redevelopment.
Certain standards are not fully met (Standard No. 1, 8, 9, and 10 must always be fully met) and an explanation of why these standards are not met is contained in the Stormwater Report.
The project involves redevelopment and a description of all measures that have been taken to improve existing conditions is provided in the Stormwater Report. The redevelopment checklist found in Volume 2 Chapter 3 of the Massachusetts Stormwater Handbook may be used to document that the proposed stormwater management system (a) complies with Standards 2, 3 and the pretreatment and structural BMP requirements of Standards 4-6 to the maximum extent practicable and (b) improves existing conditions.
Standard 8: Construction Period Pollution Prevention and Erosion and Sedimentation Control
A Construction Period Pollution Prevention and Erosion and Sedimentation Control Plan must include the following information:
• Narrative; • Construction Period Operation and Maintenance Plan; • Names of Persons or Entity Responsible for Plan Compliance; • Construction Period Pollution Prevention Measures; • Erosion and Sedimentation Control Plan Drawings; • Detail drawings and specifications for erosion control BMPs, including sizing calculations; • Vegetation Planning; • Site Development Plan; • Construction Sequencing Plan; • Sequencing of Erosion and Sedimentation Controls; • Operation and Maintenance of Erosion and Sedimentation Controls; • Inspection Schedule; • Maintenance Schedule; • Inspection and Maintenance Log Form.
A Construction Period Pollution Prevention and Erosion and Sedimentation Control Plan containing the information set forth above has been included in the Stormwater Report.
swcheck.doc • 04/01/08 Stormwater Report Checklist • Page 8 of 8
Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands Program
Checklist for Stormwater Report
Checklist (continued)
Standard 8: Construction Period Pollution Prevention and Erosion and Sedimentation Control (continued)
The project is highly complex and information is included in the Stormwater Report that explains why it is not possible to submit the Construction Period Pollution Prevention and Erosion and Sedimentation Control Plan with the application. A Construction Period Pollution Prevention and Erosion and Sedimentation Control has not been included in the Stormwater Report but will be submitted before land disturbance begins.
The project is not covered by a NPDES Construction General Permit.
The project is covered by a NPDES Construction General Permit and a copy of the SWPPP is in the Stormwater Report.
The project is covered by a NPDES Construction General Permit but no SWPPP been submitted. The SWPPP will be submitted BEFORE land disturbance begins.
Standard 9: Operation and Maintenance Plan
The Post Construction Operation and Maintenance Plan is included in the Stormwater Report and includes the following information:
Name of the stormwater management system owners;
Party responsible for operation and maintenance;
Schedule for implementation of routine and non-routine maintenance tasks;
Plan showing the location of all stormwater BMPs maintenance access areas;
Description and delineation of public safety features;
Estimated operation and maintenance budget; and
Operation and Maintenance Log Form.
The responsible party is not the owner of the parcel where the BMP is located and the Stormwater Report includes the following submissions:
A copy of the legal instrument (deed, homeowner’s association, utility trust or other legal entity) that establishes the terms of and legal responsibility for the operation and maintenance of the project site stormwater BMPs;
A plan and easement deed that allows site access for the legal entity to operate and maintain BMP functions.
Standard 10: Prohibition of Illicit Discharges
The Long-Term Pollution Prevention Plan includes measures to prevent illicit discharges;
An Illicit Discharge Compliance Statement is attached;
NO Illicit Discharge Compliance Statement is attached but will be submitted prior to the discharge of any stormwater to post-construction BMPs.
SDE Job No.: 15071 Date: 12/3/15Prepared by: RPBT Checked by: DCM
A B C D ETSS Removal Starting TSS Amount Remaining
BMP Rate Load* Removed (BxC) Load (C-D)Sediment Forebay 25.0% 1.000 0.250 0.750Oil/water separator 25.0% 0.750 0.188 0.563
0.563 0.000 0.5630.563 0.000 0.563
Total TSS Removal = 44%
* Equals remaining load from previous BMP (E) which enters the BMP
FOR REMOVAL RATE PRIOR TO ENTERING INFILTRATION SYSTEM
STORMWATER MANAGEMENTTSS REMOVAL CALCULATION WORKSHEET
10 B STREET
SDE Job No.: 15071 Date: 12/3/15Prepared by: RPBT Checked by: DCM
Area X in. of runoff1
Impervious Area sf cfTotal Impervious Area Excluding Roof 25,659 2,138
Total Volume = 2,138
Drainage Storage StructurePrimary Secondary Subtotal
Sediment Forebay 1,108 1,108Oil Water Separator 2,000 2,000
0
0
3,108 3,108
Note:
STORMWATER MANAGEMENTWATER QUALITY TREATMENT VOLUME CALCULATION WORKSHEET
10 B STREET
Treatment Storage Capacity( cf )
Total WQv Provided , (cf) =
1. Surface storage primary available water quality volume storage is based on volume below structures' lowest outlet excluding infiltration.
SDE Job No.: 15071 Date: 12/3/15Prepared by: RPBT Checked by: DCM
Hydrologic Group A B C D Total ReVTarget Runoff Depth Factor (Inches of Runoff) 0.60 0.35 0.25 0.10
Total Impervious Area, (sf) 25,659 0 0
X inches of runoff, (cf) 1,283 0 0 0 1,283
Total Recharge Volume Required, (cf) = 1,283
Soil Texture Class Loamy SandInfiltration Rate (inches / hour) 8.27
Structure AvailableStructure Recharged Volume, (cf) 6,798 Storage, (cf)
Underground Storage Chambers System 6,798
Total Recharge Volume Provided, (cf) = 0
Note:1. Infiltration rates are derived from the 1982 Rawls rates based on soil texture.2. Recharged volume are calculated utilizing Simple Dynamic Method : Automated3. Calculations are based on 2-Yr , 24-Hr storm event.
10 B STREET
STORMWATER MANAGEMENTSTORMWATER RECHARGE CALCULATION WORKSHEET
SHEET NO.
GZA GeoEnvironmental, Inc.
Engineers and Scientists
PREPARED BY:PREPARED FOR:
www.gza.com
PROJECT NO.DATE: REVISION NO.
DESIGNED BY:
PROJ MGR:
DRAWN BY:
REVIEWED BY: CHECKED BY:
SCALE:
PHASE I AND II ESA
10 B STREET, BURLINGTON, MA
SITE PLAN WITH EXPLORATION LOCATIONS
REMF CORP.
60 WELLS AVENUE, SUITE 100
NEWTON, MA
6/26/2015 18.0172305.00
FIG
2
MLS
MLS
CDC
AJK
FSV
AS SHOWN
GZ-
N
S
EW
0 25 50 100
SCALE IN FEET
APPROXIMATE
PROPERTY BOUNDARY
T
T
GZ-5
GZ-6
GZ-4
GZ-2
GZ-1
GZ-3
APPROXIMATE
LOCATION OF CUT IN
CONCRETE FLOOR
GZ-7
GZ-
APPROXIMATE
REVISED POOL
LOCATION
GZ-8
GZ-
GZ-
GZ-10
GZ-9
48
48
48
Cuttings 0-12'
1" PVC Screen0-10'
1
2
3
4
0-4
4-8
8-12
'
'
0.2'
12'
ND
ND
ND
S-1
S-2
S-3
36
48
48
S-1: S-1: Dry, brown, fine tomedium SAND, little Gravel,trace Silt, trace Asphalt.
S-2: S-2: Wet, grey, fine tomedium SAND, trace Gravel,trace Silt.
S-3: S-3: Wet, brown, fine tomedium SAND, trace Silt.
Bottom of boring at 12 feet.
ASPHALT
SAND
1. Field testing results represent total organic vapor levels, referenced to a benzene standard, measured in the headspace of sealed soilsample jars using a MiniRae 3000 organic vapor meter equipped with a photoionization detector (PID) and 10.6eV lamp. Results in partsper million by volume (ppmv). ND indicates nothing detected (<0.1 ppmv).
2. Soil sample for analysis from 3-4' bgs.3. Saturated soils +/- 5' bgs.4. Well removed, boring backfilled with cuttings to surface and patched to match surroundings.
Other:
Macrocore
Boring Location:
0935 5.75
DPTDrilling Method:
Geoprobe 6620 DT
Type of Rig: Track
Sampler Type:I.D./O.D (in.): 2"/3"Sampler Hmr Wt: 05/11/2015
Stab. TimeTime Water DepthDate+/-1.0 hr.
Groundwater Depth (ft.)
Hammer Fall (in.):
Auger/Casing Type:
Final Boring Depth (ft.):Logged By:
Taylor GrenierForeman:
Sample
Hammer Weight (lb.):
125/11/2015 - 5/11/2015
H. Datum:
I.D./O.D.:
Drilling Co.: Geologic Earth Exploration, Inc.
V. Datum:Matt Steele
Equipment Installed
Macrocore
Ground Surface Elev. (ft.):
Date Start - Finish:
Rig Model:
Sampler Hmr Fall:Other:
See Plan
TEST BORING LOG
REMF Corp.10 B Street
Burlington, MA
Boring No.:GZ-118
.017
2305
.00.
GP
J; S
TA
ND
AR
D B
OR
ING
W/E
W/S
MP
L 2P
G; 6
/5/2
015
Pen.(in)
Depth(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
CasingBlows/CoreRate
SPTValue R
emar
k
RE
MA
RK
S
Engineers and Scientists
Blows(per 6 in.)
Depth(ft.)
BORING NO.: GZ-1SHEET: 1 of 1PROJECT NO: 18.0172305.00REVIEWED BY: Frank Vetere
Ele
v.(f
t)
Dep
th(f
t)
FieldTestData
No. Rec.(in)
GZAGeoEnvironmental, Inc.
Sample DescriptionModified Burmister
StratumDescription
See log key for explanation of sample descriptions and identification procedures. Stratification lines represent approximate boundaries between soil and bedrocktypes. Actual transitions may be gradual. Water level readings have been made at the times and under the conditions stated. Fluctuations of groundwater mayoccur due to other factors than those present at the times the measurements were made.
48
48
48
Cuttings 0-10'
1" PVC Screen0-10'
1
2
3
4
5
0-4
4-8
8-12
'
'
0.2'
12'
ND
ND
ND
S-1
S-2
S-3
32
48
48
S-1: S-1: Dry, brown, fine tomedium SAND, trace Gravel,trace Silt.
S-2: S-2: Wet, light brown, fineto medium SAND, trace Silt.
S-3: S-3: Wet, grey to brown,fine to medium SAND, traceSilt.
Bottom of boring at 12 feet.
ASPHALT
SAND
1. Field testing results represent total organic vapor levels, referenced to a benzene standard, measured in the headspace of sealed soilsample jars using a MiniRae 3000 organic vapor meter equipped with a photoionization detector (PID) and 10.6eV lamp. Results in partsper million by volume (ppmv). ND indicates nothing detected (<0.1 ppmv).
2. Asphalt pavement at surface.3. Soil sample for analysis from 3-4' bgs.4. Saturated soils +/- 5' bgs.5. Well removed, boring backfilled with cuttings to surface and patched to match surroundings.
Other:
Macrocore
Boring Location:
1035 5.75
Drilling Method:
Geoprobe 6620 DT
Type of Rig: Track
Sampler Type:I.D./O.D (in.): 2"/3"Sampler Hmr Wt: 05/11/2015
Stab. TimeTime Water DepthDate+/-2.0 hr.
Groundwater Depth (ft.)
Hammer Fall (in.):
Auger/Casing Type:
Final Boring Depth (ft.):Logged By:
Taylor GrenierForeman:
Sample
Hammer Weight (lb.):
125/11/2015 - 5/11/2015
H. Datum:
I.D./O.D.:
Drilling Co.: Geologic Earth Exploration, Inc.
V. Datum:Matt Steele
Equipment Installed
Macrocore
Ground Surface Elev. (ft.):
Date Start - Finish:
Rig Model:
Sampler Hmr Fall:Other:
See Plan
TEST BORING LOG
REMF Corp.10 B Street
Burlington, MA
Boring No.:GZ-218
.017
2305
.00.
GP
J; S
TA
ND
AR
D B
OR
ING
W/E
W/S
MP
L 2P
G; 6
/5/2
015
Pen.(in)
Depth(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
CasingBlows/CoreRate
SPTValue R
emar
k
RE
MA
RK
S
Engineers and Scientists
Blows(per 6 in.)
Depth(ft.)
BORING NO.: GZ-2SHEET: 1 of 1PROJECT NO: 18.0172305.00REVIEWED BY: Frank Vetere
Ele
v.(f
t)
Dep
th(f
t)
FieldTestData
No. Rec.(in)
GZAGeoEnvironmental, Inc.
Sample DescriptionModified Burmister
StratumDescription
See log key for explanation of sample descriptions and identification procedures. Stratification lines represent approximate boundaries between soil and bedrocktypes. Actual transitions may be gradual. Water level readings have been made at the times and under the conditions stated. Fluctuations of groundwater mayoccur due to other factors than those present at the times the measurements were made.
48
48
48
Cuttings 0-12'
1" PVC Screen0-10'
1
2
3
4
0-4
4-8
8-12
'
'
0.2'
12'
ND
ND
S-1
S-2
S-3
36
48
48
S-1: S-1: Dry, light brown, fineSAND, trace Gravel, trace Silt
S-2: S-2: Wet, brown, fine tomedium SAND, trace Silt.
S-3: S-3: Wet, brown, fine tomedium SAND, trace Silt.
Bottom of boring at 12 feet.
ASPHALT
SAND
1. Field testing results represent total organic vapor levels, referenced to a benzene standard, measured in the headspace of sealed soilsample jars using a MiniRae 3000 organic vapor meter equipped with a photoionization detector (PID) and 10.6eV lamp. Results in partsper million by volume (ppmv). ND indicates nothing detected (<0.1 ppmv).
2. Asphalt at surface.3. Saturated soils +/- 5' bgs.4. Well removed, boring backfilled with cuttings to surface and patched to match surroundings.
Other:
Macrocore
Boring Location:
1148 6.36
Drilling Method:
Geoprobe 6620 DT
Type of Rig: Track
Sampler Type:I.D./O.D (in.): 2"/3"Sampler Hmr Wt: 05/11/2015
Stab. TimeTime Water DepthDate+/-1.5 hr.
Groundwater Depth (ft.)
Hammer Fall (in.):
Auger/Casing Type:
Final Boring Depth (ft.):Logged By:
Taylor GrenierForeman:
Sample
Hammer Weight (lb.):
125/11/2015 - 5/11/2015
H. Datum:
I.D./O.D.:
Drilling Co.: Geologic Earth Exploration, Inc.
V. Datum:Matt Steele
Equipment Installed
Macrocore
Ground Surface Elev. (ft.):
Date Start - Finish:
Rig Model:
Sampler Hmr Fall:Other:
See Plan
TEST BORING LOG
REMF Corp.10 B Street
Burlington, MA
Boring No.:GZ-318
.017
2305
.00.
GP
J; S
TA
ND
AR
D B
OR
ING
W/E
W/S
MP
L 2P
G; 6
/5/2
015
Pen.(in)
Depth(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
CasingBlows/CoreRate
SPTValue R
emar
k
RE
MA
RK
S
Engineers and Scientists
Blows(per 6 in.)
Depth(ft.)
BORING NO.: GZ-3SHEET: 1 of 1PROJECT NO: 18.0172305.00REVIEWED BY: Frank Vetere
Ele
v.(f
t)
Dep
th(f
t)
FieldTestData
No. Rec.(in)
GZAGeoEnvironmental, Inc.
Sample DescriptionModified Burmister
StratumDescription
See log key for explanation of sample descriptions and identification procedures. Stratification lines represent approximate boundaries between soil and bedrocktypes. Actual transitions may be gradual. Water level readings have been made at the times and under the conditions stated. Fluctuations of groundwater mayoccur due to other factors than those present at the times the measurements were made.
S-1
1. Field testing results represent total organic vapor levels, referenced to a benzene standard, measured in the headspace of sealed soil sample jars using a MiniRae3000 organic vapor meter equipped with a photoionization detector (PID) and 10.6eV lamp. Results in parts per million by volume (ppmv). ND indicates nothingdetected (<0.1 ppmv).
2. +/-6" concrete at surface.3. Soil sample for analysis from 3-4' bgs.4. Saturated soils +/- 5' bgs.5. Boring backfilled with cuttings to surface and patched to match surroundings.
2-6
'
'
0.5'
6'
6060
1
2
3
4
5
S-1: Dry, brown, fine SAND, trace Silt.
Bottom of boring at 6 feet.
CONCRETE
SAND
Drilling Method:
Taylor GrenierForeman:
Type of Rig:
Macrocore
6
Other:
Boring Location:
Logged By:
See PlanH. Datum:
V. Datum:
CasingDate
Sample
Drilling Co.:
Sampler Hmr Wt (lb):
Sampler Hmr Fall (in):
Auger/Casing Type:
I.D/O.D.(in): I.D./O.D. (in.): Stab. TimeSampler Type:
05/11/2015
Time2"/3"
Ground Surface Elev. (ft.):Final Boring Depth (ft.):Date Start - Finish: 5/11/2015 - 5/11/2015
Water Depth
Track
Geoprobe 6620 DT
Macrocore
Hammer Weight (lb.):
Hammer Fall (in.):
Other:
Rig Model:
Not Recorded
Geologic Earth Exploration, Inc.
Matt Steele
Groundwater Depth (ft.)
Depth(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
18.0
1723
05.0
0.G
PJ;
ST
RA
TU
M O
NLY
; 6/5
/201
5
Blows(per 6 in.)
Boring No.:GZ-4
No.
GZAGeoEnvironmental, Inc.
TEST BORING LOG
REMF Corp.10 B Street
Burlington, MA
Depth(ft.)
See Log Key for explanation of sample description and identification procedures. Stratification lines represent approximate boundaries between soil and bedrocktypes. Actual transitions may be gradual. Water level readings have been made at the times and under the conditions stated. Fluctuations of groundwater mayoccur due to other factors than those present at the times the measurements were made.
BORING NO.: GZ-4SHEET: 1 of 1PROJECT NO: 18.0172305.00REVIEWED BY: Frank Vetere
FieldTestData E
lev.
(ft.)
Dep
th(f
t.)
RE
MA
RK
S
Engineers and Scientists
Rec.(in)
Pen.(in) R
emar
k
Sample Description and Identification(Modified Burmister Procedure)SPT
Value
CasingBlows/CoreRate
StratumDescription
S-1
1. Field testing results represent total organic vapor levels, referenced to a benzene standard, measured in the headspace of sealed soil sample jars using a MiniRae3000 organic vapor meter equipped with a photoionization detector (PID) and 10.6eV lamp. Results in parts per million by volume (ppmv). ND indicates nothingdetected (<0.1 ppmv).
2. +/- 6" concrete at surface.3. Saturated soils +/- 5' bgs.4. Boring backfilled with cuttings to surface and patched to match surroundings.
3-6
'
'
0.5'
6'
6060
1
2
3
4
S-1A: 10" Dry, dark brown, fine SAND, trace Silt.S-1B: 50" Dry, brown, fine SAND, trace Silt.
Bottom of boring at 6 feet.
CONCRETE
SAND
Drilling Method:
Taylor GrenierForeman:
Type of Rig:
Macrocore
6
Other:
Boring Location:
Logged By:
See PlanH. Datum:
V. Datum:
CasingDate
Sample
Drilling Co.:
Sampler Hmr Wt (lb):
Sampler Hmr Fall (in):
Auger/Casing Type:
I.D/O.D.(in): I.D./O.D. (in.): Stab. TimeSampler Type:
05/11/2015
Time2"/3"
Ground Surface Elev. (ft.):Final Boring Depth (ft.):Date Start - Finish: 5/11/2015 - 5/11/2015
Water Depth
Track
Geoprobe 6620 DT
Macrocore
Hammer Weight (lb.):
Hammer Fall (in.):
Other:
Rig Model:
Not Recorded
Geologic Earth Exploration, Inc.
Matt Steele
Groundwater Depth (ft.)
Depth(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
18.0
1723
05.0
0.G
PJ;
ST
RA
TU
M O
NLY
; 6/5
/201
5
Blows(per 6 in.)
Boring No.:GZ-5
No.
GZAGeoEnvironmental, Inc.
TEST BORING LOG
REMF Corp.10 B Street
Burlington, MA
Depth(ft.)
See Log Key for explanation of sample description and identification procedures. Stratification lines represent approximate boundaries between soil and bedrocktypes. Actual transitions may be gradual. Water level readings have been made at the times and under the conditions stated. Fluctuations of groundwater mayoccur due to other factors than those present at the times the measurements were made.
BORING NO.: GZ-5SHEET: 1 of 1PROJECT NO: 18.0172305.00REVIEWED BY: Frank Vetere
FieldTestData E
lev.
(ft.)
Dep
th(f
t.)
RE
MA
RK
S
Engineers and Scientists
Rec.(in)
Pen.(in) R
emar
k
Sample Description and Identification(Modified Burmister Procedure)SPT
Value
CasingBlows/CoreRate
StratumDescription
S-1
1. Field testing results represent total organic vapor levels, referenced to a benzene standard, measured in the headspace of sealed soil sample jars using a MiniRae2000 organic vapor meter equipped with a photoionization detector (PID) and 10.6eV lamp. Results in parts per million by volume (ppmv). ND indicates nothingdetected (<0.1 ppmv).
2. +/- 6" concrete at surface.3. Soil sample for analysis from +/- 2-3' bgs.4. Saturated soils +/- 5' bgs.5. Boring backfilled with cuttings to surface and patched to match surroundings.
1-6
'
'
0.5'
6'
6060
1
2
3
4
5
S-1: Dry, brown, fine SAND, trace Silt.
Bottom of boring at 6 feet.
CONCRETE
SAND
Drilling Method:
Taylor GrenierForeman:
Type of Rig:
Macrocore
6
Other:
Boring Location:
Logged By:
See PlanH. Datum:
V. Datum:
CasingDate
Sample
Drilling Co.:
Sampler Hmr Wt (lb):
Sampler Hmr Fall (in):
Auger/Casing Type:
I.D/O.D.(in): I.D./O.D. (in.): Stab. TimeSampler Type:
05/11/2015
Time2"/3"
Ground Surface Elev. (ft.):Final Boring Depth (ft.):Date Start - Finish: 5/11/2015 - 5/11/2015
Water Depth
Track
Geoprobe 6620 DT
Macrocore
Hammer Weight (lb.):
Hammer Fall (in.):
Other:
Rig Model:
Not Recorded
Geologic Earth Exploration, Inc.
Matt Steele
Groundwater Depth (ft.)
Depth(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
18.0
1723
05.0
0.G
PJ;
ST
RA
TU
M O
NLY
; 6/5
/201
5
Blows(per 6 in.)
Boring No.:GZ-6
No.
GZAGeoEnvironmental, Inc.
TEST BORING LOG
REMF Corp.10 B Street
Burlington, MA
Depth(ft.)
See Log Key for explanation of sample description and identification procedures. Stratification lines represent approximate boundaries between soil and bedrocktypes. Actual transitions may be gradual. Water level readings have been made at the times and under the conditions stated. Fluctuations of groundwater mayoccur due to other factors than those present at the times the measurements were made.
BORING NO.: GZ-6SHEET: 1 of 1PROJECT NO: 18.0172305.00REVIEWED BY: Frank Vetere
FieldTestData E
lev.
(ft.)
Dep
th(f
t.)
RE
MA
RK
S
Engineers and Scientists
Rec.(in)
Pen.(in) R
emar
k
Sample Description and Identification(Modified Burmister Procedure)SPT
Value
CasingBlows/CoreRate
StratumDescription
S-1
S-2
S-3
1. Field testing results represent total organic vapor levels, referenced to a benzene standard, measured in the headspace of sealed soil sample jars using a MiniRae2000 organic vapor meter equipped with a photoionization detector (PID) and 10.6eV lamp. Results in parts per million by volume (ppmv). ND indicates nothingdetected (<0.1 ppmv).
2. Soil sample for analysis from +/- 2-3' bgs.3. Saturated soils +/- 5' bgs.4. Boring backfilled with cuttings to surface and patched to match surroundings.
0-4
4-8
8-12
'
'
1.2'
12'
36
48
48
48
48
48
1
2
3
4
S-1A: 14" Dry, brown, fine to coase SAND, little Gravel,little Silt, trace roots. (topsoil)S-1B: 22" Dry, grey, fine to medium SAND, trace Gravel,trace Silt.
S-2: Wet, grey, fine SAND, trace Silt.
S-3A: 36" Wet, grey, fine SAND, trace Silt.S-3B: 12" Wet, gray, fine to coarse SAND, trace Silt.
Bottom of boring at 12 feet.
TOPSOIL
SAND
Drilling Method:
Taylor GrenierForeman:
Type of Rig:
Macrocore
12
Other:
Boring Location:
Logged By:
See PlanH. Datum:
V. Datum:
CasingDate
Sample
Drilling Co.:
Sampler Hmr Wt (lb):
Sampler Hmr Fall (in):
Auger/Casing Type:
I.D/O.D.(in): I.D./O.D. (in.): Stab. TimeSampler Type:
05/11/2015
Time2"/3"
Ground Surface Elev. (ft.):Final Boring Depth (ft.):Date Start - Finish: 5/11/2015 - 5/11/2015
Water Depth
Track
Geoprobe 6620 DT
Macrocore
Hammer Weight (lb.):
Hammer Fall (in.):
Other:
Rig Model:
Not Recorded
Geologic Earth Exploration, Inc.
Matt Steele
Groundwater Depth (ft.)
Depth(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
18.0
1723
05.0
0.G
PJ;
ST
RA
TU
M O
NLY
; 6/5
/201
5
Blows(per 6 in.)
Boring No.:GZ-7
No.
GZAGeoEnvironmental, Inc.
TEST BORING LOG
REMF Corp.10 B Street
Burlington, MA
Depth(ft.)
See Log Key for explanation of sample description and identification procedures. Stratification lines represent approximate boundaries between soil and bedrocktypes. Actual transitions may be gradual. Water level readings have been made at the times and under the conditions stated. Fluctuations of groundwater mayoccur due to other factors than those present at the times the measurements were made.
BORING NO.: GZ-7SHEET: 1 of 1PROJECT NO: 18.0172305.00REVIEWED BY: Frank Vetere
FieldTestData E
lev.
(ft.)
Dep
th(f
t.)
RE
MA
RK
S
Engineers and Scientists
Rec.(in)
Pen.(in) R
emar
k
Sample Description and Identification(Modified Burmister Procedure)SPT
Value
CasingBlows/CoreRate
StratumDescription
0.2'
12'
48
48
48
S-1
S-2
S-3
36
48
48
1
2
3
4
S-1: Dry, brown, fine to medium
SAND, little Gravel, trace Silt.
S-2: Wet, brown, fine to medium
SAND, trace Silt.
S-3: Wet, brown, fine to medium
SAND, trace Silt.
Bottom of boring at 12 feet.
ND
ND
ND
ND
Cuttings 0-12'
1" PVC Screen0-10'
'
'
TOPSOIL
SAND
0-4
4-8
8-12
1. Field testing results represent total organic vapor levels, referenced to a benzene standard, measured in the headspace of sealed soil sample jars using a MiniRae 3000 organic vapor meterequipped with a photoionization detector (PID) and 10.6eV lamp. Results in parts per million by volume (ppmv). ND indicates nothing detected (<0.1 ppmv).
2. Soil sample for analysis from 2-5 feet bgs.3. Saturated soils observed approximately 5 feet bgs.4. Well material removed, boring backfilled with cuttings.
2"/3"
Hmr Fall (in.):
Macrocore
Geologic Earth Exploration, Inc.
Casing
Type of Rig:
V. Datum:
Hmr Weight (lb.):
Matt SteeleLogged By:
08/05/2015 5.6 out
Sample
Boring Location:Ground Surface Elev. (ft.):Final Boring Depth (ft.): 12Date Start - Finish: 8/5/2015 - 8/5/2015
out
Water Depth
5.6
Time
08/05/2015
Date
H. Datum:
Sampler Type:
I.D./O.D.:
Drilling Co.:
Equipment Installed
I.D./O.D (in.):Sampler Hmr Wt:
See Plan
Sampler Hmr Fall:
Other:
Groundwater Depth (ft.)
Rig Model:
Drilling Method:Damian Jacobs
Macrocore
Other:
Stab. Time
completion
Geoprobe 6620 DT
Track
Auger/Casing Type:
Foreman:
09301000 30 min.
Boring No.:GZ-8
Dep
th(f
t)
GZAGeoEnvironmental, Inc.
Pen.(in)No. Rec.
(in)
Depth(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
TEST BORING LOG
CasingBlows/CoreRate R
emar
k
Sample DescriptionModified Burmister
FieldTestData
RE
MA
RK
S
Blows(per 6 in.)
BORING NO.: GZ-8SHEET: 1 of 1PROJECT NO: 18.0172305.00REVIEWED BY: Frank Vetere
18.0
1723
05.0
0.G
PJ;
ST
AN
DA
RD
BO
RIN
G W
/E W
/O S
MP
2P
G2;
8/1
4/20
15
See log key for explanation of sample descriptions and identification procedures. Stratification lines represent approximate boundaries between soil and bedrocktypes. Actual transitions may be gradual. Water level readings have been made at the times and under the conditions stated. Fluctuations of groundwater mayoccur due to other factors than those present at the times the measurements were made.
Ele
v.(f
t)SPTValue
StratumDescription
Engineers and Scientists
Depth(ft.)
REMF Corp.10 B Street
Burlington, MA
0.5'
5'
42S-1 30
1
2
3
45
S-1: Dry, brown, fine SAND, trace Silt.
Bottom of boring at 5 feet.
ND
ND
'
'
CONCRETE
SAND
2-5
1. Field testing results represent total organic vapor levels, referenced to a benzene standard, measured in the headspace of sealed soil sample jars using a MiniRae 3000 organic vapor meterequipped with a photoionization detector (PID) and 10.6eV lamp. Results in parts per million by volume (ppmv). ND indicates nothing detected (<0.1 ppmv).
2. Approximate 6-inch concrete at surface.3. Hand hammer refusal approximate 4-feet bgs; boring advanced with hand auger.4. Hand auger refusal at 5-feet bgs.5. Boring backfilled with cuttings.
2"/3"
Hmr Fall (in.):
Macrocore
Geologic Earth Exploration, Inc.
Casing
Type of Rig:
V. Datum:
Hmr Weight (lb.):
Matt SteeleLogged By:
Sample
Boring Location:Ground Surface Elev. (ft.):Final Boring Depth (ft.): 5Date Start - Finish: 8/5/2015 - 8/5/2015
Water Depth
Encountered
Time
08/05/2015
Date
H. Datum:
Sampler Type:
I.D./O.D.:
Drilling Co.:
Equipment Installed
I.D./O.D (in.):Sampler Hmr Wt:
See Plan
Sampler Hmr Fall:
Other:
Groundwater Depth (ft.)
Rig Model:
Drilling Method:Damian Jacobs
Macrocore
Other:
Stab. Time
Geoprobe 6620 DT
Track
Auger/Casing Type:
Foreman:
Not
Boring No.:GZ-9
Dep
th(f
t)
GZAGeoEnvironmental, Inc.
Pen.(in)No. Rec.
(in)
Depth(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
TEST BORING LOG
CasingBlows/CoreRate R
emar
k
Sample DescriptionModified Burmister
No Equipment Installed
FieldTestData
RE
MA
RK
S
Blows(per 6 in.)
BORING NO.: GZ-9SHEET: 1 of 1PROJECT NO: 18.0172305.00REVIEWED BY: Frank Vetere
18.0
1723
05.0
0.G
PJ;
ST
AN
DA
RD
BO
RIN
G W
/E W
/O S
MP
2P
G2;
8/1
4/20
15
See log key for explanation of sample descriptions and identification procedures. Stratification lines represent approximate boundaries between soil and bedrocktypes. Actual transitions may be gradual. Water level readings have been made at the times and under the conditions stated. Fluctuations of groundwater mayoccur due to other factors than those present at the times the measurements were made.
Ele
v.(f
t)SPTValue
StratumDescription
Engineers and Scientists
Depth(ft.)
REMF Corp.10 B Street
Burlington, MA
0.5'
6'
42S-1 28
1
2
3
45
S-1: Dry, brown, fine SAND, trace Silt.
Bottom of boring at 6 feet.
ND
ND
'
'
CONCRETE
SAND
2-6
1. Field testing results represent total organic vapor levels, referenced to a benzene standard, measured in the headspace of sealed soil sample jars using a MiniRae 3000 organic vapor meterequipped with a photoionization detector (PID) and 10.6eV lamp. Results in parts per million by volume (ppmv). ND indicates nothing detected (<0.1 ppmv).
2. Approximate 6-inch concrete at surface.3. Hand hammer refusal approximate 4-feet bgs; boring advanced with hand auger.4. Hand auger completed at approximately 6-feet bgs.5. Boring backfilled with cuttings.
2"/3"
Hmr Fall (in.):
Macrocore
Geologic Earth Exploration, Inc.
Casing
Type of Rig:
V. Datum:
Hmr Weight (lb.):
Matt SteeleLogged By:
Sample
Boring Location:Ground Surface Elev. (ft.):Final Boring Depth (ft.): 6Date Start - Finish: 8/5/2015 - 8/5/2015
Water Depth
Encountered
Time
08/05/2015
Date
H. Datum:
Sampler Type:
I.D./O.D.:
Drilling Co.:
Equipment Installed
I.D./O.D (in.):Sampler Hmr Wt:
See Plan
Sampler Hmr Fall:
Other:
Groundwater Depth (ft.)
Rig Model:
Drilling Method:Damian Jacobs
Macrocore
Other:
Stab. Time
Geoprobe 6620 DT
Track
Auger/Casing Type:
Foreman:
Not
Boring No.:GZ-10
Dep
th(f
t)
GZAGeoEnvironmental, Inc.
Pen.(in)No. Rec.
(in)
Depth(ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
TEST BORING LOG
CasingBlows/CoreRate R
emar
k
Sample DescriptionModified Burmister
No Equipment Installed
FieldTestData
RE
MA
RK
S
Blows(per 6 in.)
BORING NO.: GZ-10SHEET: 1 of 1PROJECT NO: 18.0172305.00REVIEWED BY: Frank Vetere
18.0
1723
05.0
0.G
PJ;
ST
AN
DA
RD
BO
RIN
G W
/E W
/O S
MP
2P
G2;
8/1
4/20
15
See log key for explanation of sample descriptions and identification procedures. Stratification lines represent approximate boundaries between soil and bedrocktypes. Actual transitions may be gradual. Water level readings have been made at the times and under the conditions stated. Fluctuations of groundwater mayoccur due to other factors than those present at the times the measurements were made.
Ele
v.(f
t)SPTValue
StratumDescription
Engineers and Scientists
Depth(ft.)
REMF Corp.10 B Street
Burlington, MA