Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Intégral Géotechnique
Barratt Homes South Wales Cold Storage Depot, Llantarnam Road, Cwmbran Site Investigation Report 10725-2/GNS/10
Integral Géotechnique
CLIENT: Barratt Homes South Wales
PROJECT: Cold Storage Depot, Llantarnam Road, Cwmbran
TITLE: Site Investigation Report
JOB NO: 10725
DOCUMENT REF: 10725-2/GNS/10
Revision Purpose Description Originated Reviewed Authorised Date
0
Interim
GNS MJE HP Dec 10
Geotechnical Engineers:
Intégral Géotechnique (Wales) Limited Integral House 7 Beddau Way
Castlegate Business Park Caerphilly CF83 2AX
Tel: 029 2080 7991 Fax: 029 2086 2176
CONTENTS 1.0 INTRODUCTION 1.1 General
1.2 Proposed Development
1.3 Scope of Works
1.4 Limitations
2.0 THE SITE 2.1 Site Location and Description
2.2 Site Operations
2.3 Surrounding Land Use
2.4 Available Site Investigation Data
3.0 SITE HISTORY 4.0 SITE ENVIRONMENTAL SETTING 4.1 Physical Setting
4.2 Geology
4.3 Hydrology and Hydrogeology
4.4 Landfill Sites
4.5 Potential Contamination
5.0 PRELIMINARY CONCEPTUAL SITE MODEL 6.0 THE SITE INVESTIGATION 6.1 Fieldworks
6.2 Field Observations
6.3 Laboratory Chemical Testing
6.4 Groundwater Monitoring
6.5 In-situ Gas Monitoring
7.0 GROUND CONDITIONS
CONTENTS (CONTINUED)
8.0 CONTAMINATION 8.1 Averaging Areas
8.2 Soil Contamination
8.3 Soil Leachate
8.4 Ground Gases
9.0 REVISED CONCEPTUAL MODEL 10.0 RISK ASSESSMENT 10.1 Methodology
10.2 Source-Pathway-Receptor-Model
10.3 Human Health Risk Assessment
10.4 Risks to Vegetation
10.5 Groundwater Risk Assessment
10.6 Ground Gas Risk Assessment
10.7 Risks to Buildings and Materials Durability
10.8 Spoil Disposal
10.9 Uncertainties
11.0 ENGINEERING CONSIDERATIONS & RECOMMENDATIONS 11.1 Details of Proposed Development
11.2 Site Preparation
11.3 Foundations and Floor Slabs
11.4 Excavations and Formations
11.5 Access Roads and Car Parking Areas
11.6 Soakaway Potential
12.0 RECOMMENDED FURTHER WORKS
APPENDICES Appendix A Contaminated Land Definitions
Appendix B Windowless Sample Logs
Appendix C Falling Head Test Results
Appendix D Laboratory Chemical Test Results (Soils)
Appendix E Laboratory Chemical Test Results (Leachate)
Appendix F Laboratory Physical Test Results
Appendix G Groundwater Monitoring Results
Appendix H In-Situ Gas Monitoring Results
Appendix I Statistical Assessment of Chemical Results
CONTENTS (CONTINUED) FIGURES Figure 1 Site Location
Figure 2 Site Plan
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 1
1.0 INTRODUCTION
1.1 GENERAL
Barratt Homes South Wales are proposing to redevelop the land at The Cold Stores off
Llantarnam Road, Cwmbran for residential end-use.
Intégral Géotechnique (Wales) Limited have been appointed as the Geotechnical
Engineers to undertake a site investigation to enable a geotechnical and
geoenvironmental appraisal of the site and provide a basis for design.
This report presents the findings of the site investigation and gives recommendations for
the design of foundations, floor slabs and other geotechnical and geo-environmental
aspects of the project.
1.2 PROPOSED DEVELOPMENT
The scheme comprises residential development the layout of which is unknown at
present.
1.3 SCOPE OF WORKS
The work instructed included a site reconnaissance visit and an intrusive site
investigation, followed by laboratory testing, and geotechnical and geoenvironmental
reporting.
A Desk Study for the site was previously undertaken and reported by Intégral
Géotechnique (Wales) Limited in October 2010. The desk study report (reference
10725/MJE/10) should be read in conjunction with this report. Reference to the desk
study has been made when compiling this report, and for ease of presentation and
understanding, sections of the desk study may be presented in this report. The desk study information was used to make an initial assessment of the site and to
design an investigation to be carried out by Intégral Géotechnique. The site investigation
was designed in accordance with BS10175, the Code of Practice for Investigation of
Potentially Contaminated Sites, and ‘Land Contamination: A Guide for Developers’
prepared by WLGA/EAW Land Contamination Working Group, July 2006.
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 2
1.3 SCOPE OF WORKS (CONTINUED)
The site investigation comprised:
• An intrusive investigation carried on 10 and 12 November 2010 comprising
windowless sampling following the coring of surface hard standing
• The installation of five combined groundwater/ground gas monitoring standpipes
at five windowless samples locations
• Sampling of soil/fill for laboratory chemical testing
• Sampling of natural soils for physical testing
• Leachate analysis on selected soil samples
• Ground gas monitoring and in situ permeability testing at the five standpipe
locations
1.4 LIMITATIONS
Access for the intrusive site investigation was limited at the time due to the existing
buildings present on site, the extensive number of underground services and dense
vegetation within the southern half of the site. The southern half of the site was not
accessible to the windowless sampling plant,, nor were intrusive investigations
undertaken within the footprint of any of the buildings.
This document is intended to be a working document for further development in
discussion with all concerned including the Local Planning Authority, the Environment
Agency Wales and the NHBC, as appropriate.
“Contamination” is taken throughout the report to mean the “presence of one or more
potentially harmful substances as a result of human activity”. The use of the term in this
way does not imply that harm is being or might be caused by the contamination. It should
be noted that “contamination” can have different meanings under different regulatory
regimes, for example, planning, building control and Part IIA of the Environmental
Protection Act 1990 (see Boxes 1 and 2 in Appendix A). Naturally elevated
concentrations of potentially harmful substances may also be of concern (see Box 1 in
Appendix A) and the significance of any that have been found is also evaluated in this
report.
It is important to recognise that there may be areas of contamination that have not been
found, or that contaminants are present at concentrations above those that have been
found. It is also important to recognise that contamination may be localised and that no
investigation, however comprehensive, is capable of finding such occurrences other than
by chance.
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 3
1.4 LIMITATIONS (CONTINUED)
The DEFRA/Environment Agency CLEA Model 2002, including the technical background,
generic conceptual models and model parameters, and the Soil Guideline Values derived
from this model, were withdrawn in August 2008. The model parameters and generic
conceptual models have been reviewed and the technical background updated to
incorporate the results of additional research, and new documents published that have
formed the basis of the new CLEA model. The new CLEA model (version 1.06) is being
adopted by regulators and consultants.
At the time of writing, there are only limited official Soil Guideline Values available for use
as Tier 1 soil screening values (arsenic, cadmium, nickel, mercury (elemental, inorganic,
and methyl), selenium, phenol and BTEX compounds). Atkins have updated their
ATRISKsoil screening values in line with the new CLEA guidance. Land Quality
Management (LQM), in conjunction with the Chartered Institute for Environmental Health
(CIEH), have revised their Generic Assessment Criteria for Human Health Risk
Assessment in line with recent changes to the CLEA methodology and have published a
new set of guideline values. Both Atkins ATRISKsoil and LQM/CIEH have derived
screening criteria in line with current UK guidance.
We have reviewed both sets of values and intend to use the most appropriate
assessment criteria as Tier 1 screening values until additional official screening criteria
are published. Where a published SGV is available, and considered appropriate, this will
be used in the first instance.
This report has been prepared for the use of Barratt Homes South Wales and their
advisors and should not be passed to others without the express consent of Intégral
Géotechnique (Wales) Limited.
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 4
2.0 THE SITE
2.1 SITE LOCATION AND DESCRIPTION
A detailed description of the site was provided in the initial Desk Study Report (reference
10725/MJE/10, dated October 2010).
A previously covered and obscured above ground storage tank (presumed DRO) was
identified within the southwest of the site (its location is detailed on Figure 2) during our
latest site reconnaissance visit. There was no significant evidence of excessive spillage
of fuel within the locality and the integrity of the tank looked maintained.
2.2 SITE OPERATIONS
The site operations have not changed since the completion of the Desk Study Report.
2.3 SURROUNDING LAND USE
The surrounding land use is the same as previously detailed in the Desk Study Report.
2.4 AVAILABLE SITE INVESTIGATION DATA The desk study report (reference 10725/MJE/10) previously provided by this practice
should be read in conjunction with this report.
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 5
3.0 SITE HISTORY
The recent history of the site was previously provided in our Desk Study Report.
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 6
4.0 SITE ENVIRONMENTAL SETTING
4.1 PHYSICAL SETTING
Details previously provided in our initial Desk Study Report Report (reference
10725/MJE/10, dated October 2010).
4.2 GEOLOGY
Details previously provided in our initial Desk Study Report Report (reference
10725/MJE/10, dated October 2010).
4.3 HYDROLOGY, HYDROGEOLOGY AND FLOOD RISK
Details previously provided in our initial Desk Study Report Report (reference
10725/MJE/10, dated October 2010).
4.4 LANDFILL SITES
Details previously provided in our initial Desk Study Report Report (reference
10725/MJE/10, dated October 2010).
4.5 POTENTIAL CONTAMINATION
Details previously provided in our initial Desk Study Report Report (reference 10725/MJE/10, dated October 2010).
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 7
5.0 PRELIMINARY CONCEPTUAL SITE MODEL The preliminary conceptual site model/conceptual exposure model was provided in the
initial Desk study Report, and this will be reviewed following completion of the intrusive
site investigation works and laboratory chemical analysis.
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 8
6.0 THE SITE INVESTIGATION
6.1 FIELDWORKS
A site investigation was designed in accordance with BS5930:1999, the Code of Practice
for Site Investigations, BS10175, the Code of Practice for Investigation of Potentially
Contaminated Sites, and ‘Land Contamination: A Guide for Developers’ prepared by
Welsh Local Government Association (WLGA)/Environment Agency Wales (EAW) Land
Contamination Working Group, July 2006.
The site investigation was also designed to provide information to support and refine the
preliminary conceptual site model/conceptual exposure model that was detailed in the
initial Desk Study Report.
An investigation comprising nine windowless sample holes was carried out on 10 and 12
November 2010. Window sampling was chosen as the most appropriate intrusive form of
investigation at this stage since the site was still occupied, and this method would cause
the least disruption. The windowless sample holes were intended to provide information
on the shallow ground conditions and to take representative soil samples for laboratory
chemical/physical testing. In-situ strength testing (SPT/CPTs) was carried out during the
windowless sampling. Surface hardstandings were cored using a specialist diamond
coring drill at each location prior to sampling.
It is important to note that no windowless sample holes were undertaken within any of the
buildings, nor were holes sunk within the southern area of the site which was densely
vegetated and inaccessible.
Representative soil samples were taken from the windowless sample holes for laboratory
chemical testing and placed in the appropriate sample containers deemed suitable for the
analysis required. Strict protocols were adopted during this process to limit the cross
contamination of samples and included the use of sterile disposable gloves and stainless
steel sampling equipment cleaned with de-ionized water prior to sampling.
Gas monitoring standpipes were also installed within five of the windowless sample holes
(WS1, WS3, WS4, WS6 and WS9) to allow a programme of gas monitoring to be carried
out.
Following the installation of the standpipes a regime of ground gas monitoring was
commenced.
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 9
6.1 FIELDWORKS (CONTINUED)
Falling head permeability tests were later carried out on 3 December 2010 within the five
windowless sample holes installed with standpipes. Water was rapidly discharged into
the windowless sample hole, and rate of fall of the generated head measured over time.
The results of the falling head tests are presented in Appendix C
A programme of gas monitoring was commenced as soon as the site works were
complete.
The fieldworks were supervised by a qualified Geotechnical Engineer from Intégral
Géotechnique (Wales) Limited who also logged the windowless sample holes and
prepared their detailed engineering logs in accordance with the requirements of BS5930:
1999.
The approximate locations of the windowless sample holes are shown on Figure 2, while
their logs are presented in Appendix B.
6.2 FIELD OBSERVATIONS No visual or olfactory evidence of any contamination was observed during the drilling of
the windowless sample holes with the exception of a slight hydrocarbon odour noted in
WS8 at between 1.0m and 1.7m depth.
6.3 LABORATORY CHEMICAL TESTING
Representative soil samples were taken from the window sample holes across the site,
stored at the appropriate temperature and dispatched to the laboratories of STL for
laboratory chemical testing within 24 hours.
The samples were tested for a range of contaminants that reflects the historical use of the
site, the findings of the desk study and the preliminary conceptual site model/conceptual
exposure model. A list of the soil testing carried out is given below:
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 10
6.3 LABORATORY CHEMICAL TESTING (CONTINUED)
Beryllium Cadmium
Total Chromium Hexavalent Chromium (VI)
Copper Lead
Mercury Nickel
Vanadium Zinc
Arsenic Boron
Selenium Elemental Sulphur
Total Cyanide Total Sulphate
Sulphide Water Soluble Sulphate
pH Monohydric Phenol
PAH (Priority 16 by GC) TPH (aliphatic and aromatic split)
In addition, selected soil samples were tested for Loss on Ignition (LOI), Total Organic
Carbon (TOC) and asbestos.
The potential for leachate generation and migration off site or to groundwater was
identified as being potentially active. Therefore, selected samples were also tested for
their leachability characteristics for the same suite of contaminants as the soils (excluding
LOI, TOC and asbestos.
The results of all the soil and leachate testing are presented in Appendices D and E
respectively.
6.4 LABORATORY PHYSICAL TESTING
Selected samples were despatched to the laboratory of Geolab in Llanelli for
determinations of atterberg limits, moisture content and some routine durability chemical
testing.
The results of all the physical testing are presented in Appendix F.
6.5 GROUNDWATER MONITORING During return visits to site, the groundwater level within the standpipes installed on site
has been measured relative to ground level, the results of which are enclosed in
Appendix G.
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 11
6.6 IN-SITU GAS MONITORING (CONTINUED)
Gas monitoring standpipes were installed in five of the windowless sample holes and
these have been monitored at fortnightly intervals following completion of the fieldworks.
The gas monitoring programme commenced on 3 December 2010.
The concentration levels of methane, carbon dioxide and oxygen were measured in the
standpipes during each visit by using a GA2000 Landfill Gas Analyser. In addition, gas
flow rate and the atmospheric pressure at the time of the field measurements were also
recorded.
Gas monitoring was carried out over a range of atmospheric pressures to include at least
one reading in low and/or falling pressure, in accordance with the recommendations
made in CIRIA Report C665.
The results of the field gas monitoring undertaken to date (single visit) are presented in
Appendix H.
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 12
7.0 GROUND CONDITIONS A summary of the ground conditions encountered across the site is presented below in
Table 1.
TABLE 1 : SUMMARY OF GROUND CONDITIONS
Depth (m) From To
Stratum
0.0 0.1/0.25 MADE GROUND: Comprising surface hard standings of either tarmac or concrete or both.
0.1/0.25 0.35/1.0 MADE GROUND: Generally compact coarse granular materials seemingly used as “hard core” and comprising brown, grey, red brown, dark grey and black, slightly silty, slightly sandy, fine, medium and coarse angular and subangular gravel of sandstone, limestone, brick, slag and ash.
0.4/1.0 0.8/1.8 MADE GROUND: A predominantly cohesive made ground was recorded beneath the granular made ground in WS4, WS6, WS7, WS8 and WS9 and generally comprised firm, brown silty, slightly gravelly clay. The gravel typically comprised fine, medium and coarse, angular brick, ash, ceramic and sandstone.
0.8/1.8 1.0/4.4 SUPERFICIAL SOILS: The made ground deposits were generally underlain by a variable thickness superficial cohesive soils comprising soft, brown, grey, yellow brown and red brown, silty, slightly sandy, slightly gravelly CLAY, the gravel of which comprised fine, medium and coarse rounded and sub-rounded sandstone.
1.0/4.4 2.5/4.5 SUPERFICIAL SOILS: The natural shallow cohesive soils were generally underlain by a medium dense and dense, brown and light brown silty, slightly sandy to sandy GRAVEL comprising rounded fine, medium and coarse sandstone.
Surface tarmac or concrete was cored using specialist coring equipment at each
windowless sample location and found to be underlain by predominantly granular made
ground deposits containing variable quantities of angular sandstone, brick, slag, concrete,
bitumen and ash to depths of between 0.35m and 1.0m below ground level.
In five locations, this granular made ground was underlain by predominantly cohesive
made ground to a maximum depth of 1.8m in WS4. Generally the cohesive made ground
was seemingly confined to the eastern and southern areas of the site.
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 13
7.0 GROUND CONDITIONS (CONTINUED)
The made ground deposits were underlain by a poorly consolidated layer of cohesive
superficial soils typically described as soft, brown, yellow brown and red brown, silty,
sandy, slightly gravelly clay to depths of between 1.0m and 4.4m below ground level.
The cohesive superficial soils were underlain by generally competent, medium dense and
dense gravels to proven depths of between 2.5m and 4.5m depth below ground level.
The windowless sampling equipment refused in these materials and thus confirmed their
general competency.
The natural solid strata were only recorded within WS1 at 3.9m depth, with the natural
solid strata being described as stiff, red brown mottled teal and grey, slightly silty clay with
frequent mudstone lithorelicts. This deposit is believed to be the Raglan Marl group.
The groundwater levels identified on site during the drilling of the windowless sampling
holes were shallow and recorded at depths of between 0.5m and 1.85m below existing
ground level, which would suggest the presence of perched water in the made ground
and that the superficial soils are saturated.
This high groundwater table has been measured during a return visit to the site, where
after a settling period, the ground water levels were recorded at depths of between 1.0m
and 1.93m below ground level, indicating that the groundwater table presides in the
superficial soils.
It is difficult to gauge the stability of the ground conditions from windowless sample holes
drilled on site, but several of the holes collapsed during drilling and had to be re-drilled in
achieve the termination depth. Considering this, and the low strength of the upper
cohesive soils and the saturated nature of the gravel materials, it is considered that
instability within trenches/excavations formed on site will be extensive.
Falling head permeability tests were undertaken in five of the windowless sample holes in
which standpipes were installed. The response zone was generally below a depth of
1.0m. The head achieved when undertaken the test was artificially increased by raising
the test pipe 1.0m above existing ground level. The permeability values recorded during
the testing ranged between 1.0x10-3m/s and 2.1x10-6m/s.
It should be noted that this initial testing should only be regarded as indicative. If it should
be proposed to use soakaways for this site, then more extensive follow-up tests will be
required and should fully comply with BRE 365, in order to confirm the suitability of the
site and to satisfy the local authority.
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 14
8.0 CONTAMINATION
8.1 AVERAGING AREAS In order to assess the laboratory test results reliably and in context, the data have been
grouped into two averaging areas. An averaging area (or area of interest) is that area of
soil to which a receptor is exposed or which otherwise contributes to the creation of
hazardous conditions. This may be an area of historical industrial usage, a soil type, e.g.
made ground, or a specific proposed end use.
In the case of this analysis, the averaging area has been determined according to soil
type, with the made ground being the selected averaging area.
8.2 SOIL CONTAMINATION
As detailed in Section 1.4, the DEFRA/Environment Agency CLEA Model 2002, including
the technical background, generic conceptual models and model parameters, and the Soil
Guideline Values derived from this model, were withdrawn in August 2008. This included
the withdrawal of R&D Publication CLR 7 which detailed the statistical approach to be
adopted at the time for assessing site wide contamination. Subsequent to the withdrawal
of this document, CL:AIRE (Contaminated Land: Applications in Real Environments) has
published a document entitled ‘Guidance on Comparing Soil Contamination Data with a
Critical Concentration’, 2008. The CL:AIRE document includes guidelines on the use of
various statistical methods to assess the soil contamination concentrations, either
conducted in the context of the land use planning system or Part 2A of the Environmental
Protection Act 1990.
To conform to this new approach, we have implemented the use of the ESI Contaminated
Land Statistics Calculator developed by Environmental Simulations International (ESI)
Limited, which fully conforms to the CL:AIRE guidance.
In accordance with the CL:AIRE guidance, the results of the laboratory testing have been
compared to a critical concentration and if required, statistical analysis undertaken to
produce an Upper Confidence Limit (UCL0.95), against which the soil contamination
concentrations can be compared. If the Upper Confidence Limit (set as a default at 95%)
is achieved then the Null Hypothesis (i.e. the level of contamination is the same as, or
greater than the critical concentration) can be rejected and no further analysis or remedial
works are likely to be required at the site. If the Upper Confidence Limit is not achieved
then either further statistical data is required (comprising further chemical laboratory
analysis) or remedial action may be required.
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 15
8.2 SOIL CONTAMINATION (CONTINUED)
The published Soil Guideline Values for arsenic, cadmium, mercury, nickel, selenium,
phenol and BTEX compounds have been adopted as critical concentrations against which
soil contaminant concentrations can be compared. In the absence of additional published
SGVs, the Soil Screening Values (SSVs) derived by Atkins ATRISKsoil for a residential
with home grown produce end use and the Generic Assessment Criteria (GAC’s) derived
by Land Quality Management (LQM)/Chartered Institute of Environmental Health (CIEH)
have been adopted. These values have been derived by using the new CLEA 1.06
Model and using the revised and updated methodology and conceptual models.
The soil test results have been summarised and are shown in Appendix I
The results of the laboratory testing indicate that most of the analysed chemical elements
or compounds are present at concentrations below the appropriate thresholds. However,
the initial screening indicates that total chromium, lead, some speciated PAHs and
selected aromatic hydrocarbon fractions are initially contaminants of concern.
With regards to metalliferous contaminants, only total chromium and a single isolated
lead value have been detected at concentrations which exceed their relevant LQM or
ATRISK guideline values.
Total chromium was recorded at an elevated concentration in all of the eight analysed soil
samples with the recorded values being 9mg/kg and 26mg/kg which exceed the
conservative published LQM soil screening value of 4.3mg/kg. However, total chromium
typically comprises the less toxic, more stable chromium (III) and the more toxic
chromium (VI). Chromium (VI) was detected in the samples at a maximum concentration
of 1.0mg/kg (detection limit). Therefore it is likely that the total chromium concentrations
identified comprise mostly chromium (III). The LQM residential end use guideline for
chromium (III) is 3000mg/kg, whilst the guideline for hexavalent chromium is 4.3mg/kg.
Total chromium is therefore not considered to be a contaminant of concern at the site.
A single elevated concentration of lead was recorded from WS6 at 0.6m depth, with the
identified value of 231mg/kg exceeding the published Atkins ATRISKsoil screening value
of 166mg/kg. The recorded value is, however, significantly below the former SGV of
450mg/kg. The single elevated concentration is deemed to be an outlier and does not
belong to the general population of lead results.
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 16
8.2 SOIL CONTAMINATION (CONTINUED)
Elevated concentrations of several individual PAHs including benzo(a)anthracene,
benzo(a)pyrene, benzo(b)fluoranthene, benzo(k)fluoranthene, chrysene,
dibenzo(ah)anthracene and indeno(123cd)pyrene were recorded from four of the
windowless sample locations (WS5, WS6, WS8 and WS9), the values of which exceeded
their relative LQM screening values. The samples displaying elevated concentrations
were derived from deposits that often contained significant quantities of ash and clinker,
and it is these anthropogenic materials that account for the elevated concentrations of
individual PAHs.
Five soil samples were screened for speciated TPH (detailed aliphatic/aromatic split), of
which only a single soil sample from WS9 at 0.5m recorded any elevations of the
individual hydrocarbon fractions.
The elevated fractions included the aromatic bands C16-C21, C21-C35 and C35-C40, the
results of which only just exceeded their respective LQM guideline concentrations. No
other hydrocarbon fractions were elevated. The elevated fractions are indicative of the
presence of the heavier end hydrocarbons potentially including diesel fuel and oils.
A sample obtained from WS9 at 1.4m below the recorded hydrocarbon contamination did
not record any elevations potentially indicating that the TPH contamination is relatively
confined to the shallow soil profile.
None of the eight soil samples screened for asbestos recorded a positive identification.
8.3 SOIL LEACHATE We are currently awaiting the results of the scheduled leachate analysis and we will
assess these results once they are received.
8.4 GROUND GASES A single ground gas has been undertaken to date using a GA 2000 Gas Analyser. The
results of the gas monitoring programme are included in Appendix H. A summary of the
first set of results is given in Table 2 below.
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 17
8.4 GROUND GASES (CONTINUED)
Table 2: Summary of Ground Gas Results
Windowless Sample
Maximum Methane Concentration
(%)
Maximum Carbon Dioxide Concentration
(%)
Minimum Oxygen Concentration
(%)
Gas Flow Rate (l/hr)
WS1 0.0 0.2 20.10 0.0
WS3 0.0 0.4 19.40 0.0
WS4 0.0 1.6 17.90 0.0
WS6 0.0 0.1 20.40 0.0
WS9 0.0 0.3 20.00 0.0
The results show a maximum methane concentration of 0.0% and a maximum carbon
dioxide concentration of 1.6% to date. A maximum gas flow rate of 0.0l/hr has been
measured during the gas monitoring programme to date.
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 18
9.0 REVISED CONCEPTUAL SITE MODEL The preliminary conceptual site model/conceptual exposure model has been reviewed
and revised to reflect the findings of the site investigation and the results of the laboratory
testing of soils, soil leachate, groundwater and gas monitoring. Any previously identified
in-active pathways have been removed. Pathways identified as still active require
appropriate risk assessment or mitigation measures (see Section 10).
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 19
Table 6: Preliminary Conceptual Site Model/Conceptual Exposure Model
Site
Area/Zone Source Contaminant Receptor Pathway
Hazard Potential Active
Pathway and
Evidence?
Potential Risk Mitigation
Human Health –
Site End Users
Dermal Contact with soil
Ingestion of soil/dust
Inhalation of vapours
Human Health
Risks
Yes
Elevated
concentrations of
benzo(a)anthracene,
benzo(a)pyrene,
benzo(b)fluoranthene,
chrysene,
dibenzo(ah)anthracene
and
indeno(123cd)pyrene,
with a single elevated
concentration of lead.
Moderate Risk Assessment
required. Capping
of impacted soils will
be required within
proposed garden
areas.
Human Health –
Site Workers
(Construction and
Maintenance)
Dermal Contact with soil
Ingestion of soil/dust
Inhalation of vapours
Human Health
Risks
Yes
Elevated
concentrations of
benzo(a)anthracene,
benzo(a)pyrene,
benzo(b)fluoranthene,
chrysene,
dibenzo(ah)anthracene
and
indeno(123cd)pyrene,
with a single elevated
concentration of lead.
Moderate Risk Assessment
required. The
adoption of
appropriate PPE will
be required
Site wide Made ground
generated from
historical activities
on site
Metals, semi-
metals, non-
metals,
polyaromatic
hydrocarbons
Controlled Waters Leaching of contaminants
from made ground,
subsequent infiltration
through the made ground
and superficial deposits into
perched water, migration to
Reduction in water
quality
Awaiting the results of
leachate analysis
To be
confirmed
following
receipt of the
results of
leachate
To be confirmed
following receipt of
the results of
leachate analysis
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 20
alluvial groundwater and
lateral transport to surface
water
analysis
Neighbouring
Land
Leachate migration via
perched water or along
permeable service trenches
off site
Human Health
Risks/Land Quality
Awaiting the results of
leachate analysis
To be
confirmed
following
receipt of the
results of
leachate
analysis
To be confirmed
following receipt of
the results of
leachate analysis
Building Materials Direct contact of concrete
with made ground
Building Materials
Durability
Yes
Potential for acidic
aggressiveness
associated with the
made ground
Moderate Risk assessment
required with
regards to proposed
foundation concrete
and building
materials in
accordance with
BRE SD1:2005
Controlled Waters Vertical migration to alluvial
groundwater
Lateral migration to surface
water
Reduction in water
quality
Perched water and a
shallow groundwater
table identified.
To be
confirmed
following
receipt of the
results of
leachate
analysis
To be confirmed
following receipt of
the results of
leachate analysis
Perched
Groundwater
Metals, semi-
metals, non-
metals,
polyaromatic
hydrocarbons
Neighbouring
Land
Lateral migration off site Human Health
Risks/Land Quality
Perched water and a
shallow groundwater
table identified.
To be
confirmed
following
receipt of the
results of
leachate
analysis
To be confirmed
following receipt of
the results of
leachate analysis
Ground Gas Methane, Human Health – Accumulation of gases in Human No Low Risk Assessment
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 21
associated with
made ground
and/or in-situ
natural gas
producing
materials
carbon dioxide Site end users,
construction and
maintenance
workers
Structures and
buildings
confined spaces, and/or
migration off site, leading to
asphyxiation, or risk of
explosion
Health/Buildings
and Structures
Maximum carbon
dioxide gas
concentration of 1.6%
recorded to date with
no flow detected
required in
accordance to
CIRIA report C665
to confirm findings.
Human Health –
Site End Users
Inhalation of vapours Human Health
Risks
Yes
Elevated
concentrations of
aromatic bands C16-
C21, C21-C35 and
C35-C40
Moderate Further risk
assessment
required.
Human Health –
Site Workers
(Construction and
Maintenance)
Inhalation of vapours Human Health
Risks
Yes
Elevated
concentrations of
aromatic bands C16-
C21, C21-C35 and
C35-C40
Moderate Further risk
assessment
required.
Appropriate PPE
should be adopted
as a precautionary
measure
Controlled Waters Migration of hydrocarbons to
perched water, migration to
alluvial groundwater and
lateral transport to surface
water
Reduction in water
quality
Awaiting the results of
leachate analysis
To be
confirmed
following
receipt of the
results of
leachate
analysis
To be confirmed
following receipt of
the results of
leachate analysis
Area within
vicinity of
WS9
Point Source –
shallow soils
impacted by
hydrocarbons
within the vicinity
of WS9
Hydrocarbons
– Fuel/oils
Neighbouring
Land
Migration of hydrocarbons to
perched water, migration to
alluvial groundwater and
lateral transport to surface
water
Human Health
Risks/Land Quality
Awaiting the results of
leachate analysis
To be
confirmed
following
receipt of the
results of
leachate
analysis
To be confirmed
following receipt of
the results of
leachate analysis
LLEWELLYN ROAD, PENLLERGAER 9867MJE/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 22
10.0 RISK ASSESSMENT
10.1 METHODOLOGY
The risk of pollution, health effects or environmental harm occurring as a result of ground
contamination is dependent upon three principal factors:
• The scale of the contamination sources;
• The presence of sensitive “receptors”, eg Humans: health of the general public,
site occupiers, redevelopment workers. Environment: flora, fauna, etc;
• The existence of migration pathways by which contaminants can reach the
sensitive receptors.
This section assesses each of these factors in order to evaluate the overall level of risk
and potential harm to receptors. The receptor may be human, a water resource, an eco-
system or construction materials. Pathways connecting a perceived hazard to a receptor
are referred to as exposure pathways.
The sources of contamination and the links connecting the hazards to the sensitive
receptors will represent the basis for the risk assessment.
10.2 SOURCE-PATHWAY-RECEPTOR MODEL
The preliminary conceptual site model was based on the findings of the desk study. This
was later reviewed and refined according to the findings of the site investigation, allowing
for the ground conditions encountered and the results of laboratory testing of soil and
groundwater. Any pathways considered to be inactive were removed from the model and
all remaining potentially active pathways require risk assessment.
The pathways shown as potentially active in the Revised Conceptual Site Model in
Section 9.0 above have been assessed below.
10.3 HUMAN HEALTH RISK ASSESSMENT 10.3.1 Site in its Present Condition The ground does not pose any risks to casual visitors or trespassers. The site is largely
covered by tarmacadam or concrete and is fenced off.
LLEWELLYN ROAD, PENLLERGAER 9867MJE/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 23
10.3 HUMAN HEALTH RISK ASSESSMENT (CONTINUED)
10.3.2 Future Site Users The contamination test results and investigation observations show elevated
concentration levels in the made ground (at shallow depth) of lead, speciated PAHs and
isolated TPH contamination within the vicinity of WS9
Since lead is a metallic element and is not volatile, and the elevated PAHs are also not
considered volatile, the only potentially active pathway by which a future site resident
could be exposed to the recorded contamination would be via dermal contact with, or
direct ingestion of, contaminated made ground.
It is therefore considered necessary to provide protective measures to remediate the site
in order to protect site end users. The proposed buildings and hardstanding areas will
sever the link between site end users and any remnant made ground sourced
contaminants.
The risks of site end users coming into direct contact with contaminated made ground are
therefore only applicable within proposed garden areas.
To sever the link between proposed site end users and the made ground deposits, it is
recommended that a clean and suitable cover system should be incorporated into the
proposed garden/landscaped areas. The proposed cover system would provide a barrier
between site end users and the remnant made ground sourced contamination, subject to
correct specification and installation.
We understand that the site may be raised by in the region of a 1.0m above existing site
level as part of either a flood protection measure or for the facilitation of drainage.
Providing the imported materials are classified as inert, and suitable for use on a
residential site, then this raising of the site will sever the link between site end users and
the made ground sourced contamination.
As a minimum requirement, we recommend that the imported soils are screened for a
suite of chemical contaminants prior to importation onto site, with the concentrations of
such determinants being below DEFRA and EA published SGVs, or other appropriate
guidance (ATRISK/LQM) based on a residential end use. Further verification of soil
quality will be required during the importation and placement of the materials.
LLEWELLYN ROAD, PENLLERGAER 9867MJE/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 24
10.3 HUMAN HEALTH RISK ASSESSMENT (CONTINUED)
If the site is not raised then ultimately, the thickness of imported cover systems within
proposed garden areas will be dependent on the requirements of the Local Environmental
Health Officer, but we envisage that a minimum thickness of 600mm should be placed.
Level requirements may then dictate that some materials will require off-site disposal to
achieve the levels necessary and provide the appropriate cover.
The investigations undertaken on site have also identified the presence of TPH
contamination within the vicinity of WS9 at shallow depth. This contamination appears to
be confined to the shallow soil profile, but will require further investigation.
The TPH contamination should be considered volatile in nature, and will present a risk to
site end users from inhalation pathways, which will not be retarded by the provision of the
proposed capping system. It is difficult at this stage to assess the actual risks, and further
works will be required to delineate the vertical and lateral extent of any hydrocarbon
contamination within the vicinity of WS9.
Dependent on the nature and extent of any hydrocarbon contamination, mitigation
measures could include localised removal and bioremediation, off site disposal, or the
use of gas vapour protective membranes within proposed plots local to the sources of
contamination.
The above ground fuel storage tank noted within the south-western area of the site will
require decommissioning in accordance with established industry practice, and visual
inspection of the soils within this area will be required, followed by appropriate validation
sampling and testing.
If soil excavation is required, the removal of hydrocarbon impacted materials should be
undertaken under the supervision of a suitably qualified professional. The excavated
materials could be stockpiled on a suitably impermeable surface (concrete hardstanding
or impermeable plastic sheeting) and over sheeted to reduce the potential for leachate
generation as a result of rainfall infiltration.
Validation sampling and analysis will be required within the areas of hydrocarbon
removal, with samples being obtained from the impacted and excavated soils, and also
from the sides and base of the resultant excavations to prove the satisfactory removal of
the impacted soils.
LLEWELLYN ROAD, PENLLERGAER 9867MJE/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 25
10.3 HUMAN HEALTH RISK ASSESSMENT (CONTINUED)
Any groundwater found to be impacted by hydrocarbons within the excavations will
require removal and processing, the method of which will be dependent on the quantities
of impacted groundwater. For small quantities it is probable that the impacted
groundwater could be removed by using a tanker and hose, and disposed of off site. If
larger quantities are encountered it will be necessary to mobilise settlement and baffled
fuel interceptors to site. It should be possible to dispose of water treated in this way to
adopted sewers under licence with the waste collected in tankers and disposed of off site
to a licensed treatment facility.
The future development of the site will involve the formation of excavations within the
made ground deposits and natural soils, and as such there is an increased risk of ground
workers/site operatives encountering contamination, including hydrocarbon impacted
soils/groundwater.
All excavations should be regularly checked for safe atmospheres.
Normal good hygiene practices should be adequate to protect the health and safety of
redevelopment workers, and should include:
• Minimum handling of materials;
• Washing of hands prior to all meal breaks, which should be taken in a designated
clean area;
• The use of standard protective clothing such as boots, overalls and gloves, where
considered relevant.
• Vapour masks should be made available when working in excavations and
workers should be made aware of the risks associated with hydrocarbon
contamination.
• Masks which protect the users face from splashes of hydrocarbon impacted
waters should also be made available
• Site designated a no smoking area.
In dry weather, inhalation of dust and gases should be avoided preferably by the use of
dust suppression techniques to minimize fugitive emissions and minimisation of exposed
materials at any particular time.
Additionally, a system should be established by which any ‘unusual’ materials that may
be encountered are reported rapidly to the site management, so that the appropriate
action may be taken, following specialist advice if necessary. An unusual material may be
identified on site by colour, odour or physical nature.
LLEWELLYN ROAD, PENLLERGAER 9867MJE/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 26
10.3 HUMAN HEALTH RISK ASSESSMENT (CONTINUED)
Reference should be made to the Health and Safety Executive document “Protection of
Workers and the General Public during the development of contaminated land” for
detailed guidance on these matters.
10.4 RISKS TO VEGETATION
No elevated concentrations of phytotoxic contaminants have been identified on site. It
should, however, be noted that the proposed capping within garden areas should
incorporate a suitable growth medium for the proposed planting.
10.5 GROUNDWATER RISK ASSESSMENT
We are currently awaiting the results of the scheduled leachate analysis, and following
receipt of this information we will provide a detailed assessment with regards to the risks
controlled waters.
Given the high groundwater table encountered, and the nature of on site contamination,
an allowance for a period of groundwater monitoring, sampling and testing should be
allowed for.
10.6 GROUND GAS RISK ASSESSMENT
The single result of the gas monitoring programme undertaken to date indicates a
maximum methane concentration of 0.0% and a maximum carbon dioxide concentration
of 1.6%. A maximum gas flow rate of 0.0l/hr was measured during the gas monitoring
programme.
As no flow was detected during the gas monitoring to date, we have conservatively
adopted a gas flow rate of 0.1l/hr in calculation of the Gas Screening Value.
In accordance with CIRIA Report C655 a Gas Screening Value (GSV) of 0.0016l/hour has
been calculated. This GSV corresponds to a Characteristic Situation 1 which does not
require any special gas protective measures. Such a scenario applies to multi-storey
buildings (in excess of two storeys).
For low rise buildings (two storeys or less) this GSV corresponds to a green classification
when utilising the NHBC traffic light system (when assuming a 150mm void and
suspended floor slabs), which again does not require any special gas protective
measures.
LLEWELLYN ROAD, PENLLERGAER 9867MJE/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 27
10.6 GROUND GAS RISK ASSESSMENT (CONTINUED)
It is important to note that this assessment is based on a single gas monitoring result and
should be considered preliminary. The risk assessment will be reviewed following
completion of the gas monitoring programme.
10.7 RISKS TO BUILDINGS AND MATERIALS DURABILITY
10.7.1 Concrete Classification A summary of the laboratory chemical test results for the chemicals monohydric phenol,
sulphur, total sulphate, water soluble sulphate, sulphide and pH, which may adversely
affect the durability of building materials is presented in Appendix I.
Evidence to date does not indicate any specifically aggressive conditions, but it would be
reasonable to expect a degree of sulphate and acidic aggressiveness from the made
ground.
In accordance with BRE Digest SD1:2005 and adopting the assessment procedure
specified therein for brownfield sites, the laboratory chemical test results indicate a
characteristic value (taking the mean of the two highest results) for water soluble sulphate
of 215mg/l.
Using Table C2 of BRE Digest SD1:2005, this characteristic value corresponds to Design
Sulphate Class DS-1.
The groundwater regime of the site has been assessed as ‘mobile’ and a characteristic
pH value of 7 has been determined (adopting the lowest test result). The Design Sulphate
Class has been modified to give a site ACEC class of AC-1.
10.7.2 Water Services Water pipes will need to be protected from contamination within the ground. In particular
the presence of PAH and TPH should be addressed when selecting pipe materials.
Measures to protect the pipes will include clean backfill to trenches and possibly
alternative material selection. Reference should be made to WRAS document 9-04-03.
The final design and selection of the pipe and associated backfill should be agreed with
the appropriate Regulator prior to installation.
LLEWELLYN ROAD, PENLLERGAER 9867MJE/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 28
10.8 SPOIL DISPOSAL
Under the Landfill Regulations (2002) all spoil materials should be classified if they
require disposal to a landfill facility. To determine the appropriate type of landfill site,
there will need to be a characterisation of the materials in relation to the Waste
regulations.
The made ground materials are tentatively classified as stable non reactive hazardous
waste but specialised testing will be required once earthworks design and volumes are
known.
Locally soils impacted by hydrocarbons may be classified as hazardous. Basic Characterisation For each waste intended to be landfilled, the following information will be required, either
separately or as part of the Duty of Care waste transfer note, or Special Waste
consignment note:
• Source and origin
• Standard Industry Code (SIC), process producing waste
• Treatment applied or reason not considered necessary
• Composition (including Waste Acceptability Criteria (WAC) leaching tests
hazardous and inert waste where necessary)
• Appearance
• European Waste Catalogue (EWC) Code
• Hazardous properties (if hazardous waste and applicable)
• Not a waste prohibited from landfill (i.e. not corrosive, flammable etc)
• The class of landfill that waste is suitable for (i.e. hazardous)
• Likely behaviour of the waste in the landfill
• Whether waste can be recycled
The basic characterisation is the responsibility of the waste producer. The waste
contractor may undertake all or part of the process of basic characterisation – including
the WAC analysis. It will still be the responsibility of the waste producer to ensure that the
information is correct.
In the absence of any detailed assessment of the likely areas and types of soils that may
be generated for disposal (based on the ground conditions, remediation proposals and
soil materials encountered at the site) the following tentative classification is proposed,
based on the made ground materials.
LLEWELLYN ROAD, PENLLERGAER 9867MJE/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 29
10.8 SPOIL DISPOSAL (CONTINUED)
Source and origin Cold Storage Depot, Llantarnam Road, Cwmbran
Standard Industry Code (SIC), process producing waste 45.11
Stratigraphic horizon Made Ground Natural Ground
Treatment applied or reason not considered necessary Segregation applied at
point of excavation
Segregation applied at
point of excavation
Composition (including WAC leaching tests for hazardous and inert waste where necessary)
Refer to Section 7.0 Refer to Section 7.0
Appearance (smell, colour, consistency and physical form)
Non odorous locally odorous (hydrocarbons)
Brown/grey brown/dark grey and black
Both heterogeneous and homogenous
Granular and cohesive
Non odorous
Brown/orange brown/yellow brown/red brown
Reasonably homogenous
Cohesive over granular
European Waste Catalogue (EWC) Code 17.05
Soil (including excavated soil from contaminated sites), stones and dredging spoil
17.05
Soil (including excavated soil from contaminated sites), stones and dredging spoil
Not a waste prohibited from landfill (i.e. corrosive, flammable etc)
No No
The class of landfill that waste is suitable for (i.e. hazardous)
Stable Non-reactive Hazardous Waste in Non-hazardous Landfill
Inert (where not impacted by hydrocarbons)
Likely behaviour of the waste in the Landfill Stable Stable
Whether waste can be recycled Yes Yes
This preliminary classification will require more definitive assessment and confirmation
when detailed designs are produced detailing the likely areas of waste disposal if
required. Alternatively, at construction stage any materials identified by the developer as
waste will require Waste Acceptance Criteria (WAC) testing and characterisation prior to
pre-approval from the landfill operator and ahead of export to tip.
It is recommended that a sustainable development strategy is adopted which reduces to a
practicable minimum the need for export of waste to a licensed tip.
LLEWELLYN ROAD, PENLLERGAER 9867MJE/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 30
10.8 SPOIL DISPOSAL (CONTINUED)
In order to minimise disposal, the materials generated should be segregated and
examined, with appropriate testing as necessary, to enable the materials to be sorted or
treated into lower classifications, with the resultant benefit of potentially generating re-use
rather than disposal.
10.9 UNCERTAINTIES It is important to recognise that there may be areas of contamination within the site that
have not been found or that contaminants may be present at concentrations above those
that have been found. It is also important to recognise that contamination may be
localised and that no investigation, however comprehensive, is capable of finding such
occurrences, other than by chance.
The existing buildings have not been inspected as part of the investigations reported here
for asbestos or other contaminants.
The near-surface drainage patterns have not been fully established.
The ground beneath the buildings has not been examined but on present evidence the
existing floor slabs are in good condition and there is no evidence of any pits, basements
or past spills of potential contaminants. Some degree of made ground material should be
expected beneath the existing floor slabs.
It should be noted that cold storage depots often have two floors (a ground bearing floor
slab and a suspended slab, with the lower floor slab providing insulation. Extensive pipe
work is often routed beneath the floor slabs, with these services often clad extensively
with asbestos.
LLEWELLYN ROAD, PENLLERGAER 9867MJE/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 31
11.0 ENGINEERING CONSIDERATIONS AND RECOMMENDATIONS
11.1 DETAILS OF PROPOSED DEVELOPMENT
The scheme comprises residential development the layout of which is unknown at
present.
11.2 SITE PREPARATION Detailed material and building inventories together with structural surveys will be required
to ensure safe and efficient demolition strategies and subsequent material management
and re-use strategy. The existing buildings will require a detailed asbestos survey and
subsequent demolition in a controlled manner. Allowances should be made for removing
buried structures associated with the past usage of the site, including foundations of the
existing buildings, inspection pits, any above and below ground tanks, underground pipe
works, interceptors and site drainage.
All redundant footings, services and surface hardstandings associated with the former
buildings will need to be broken out with the resulting debris crushed and screened to a
structural specification, typically 150mm maximum particle size. All excavated materials
should be screened for unsuitable materials such as timber, metal etc. The most reliable
way to achieve a formation cleared of underground obstructions associated with the past
site usage would be to excavate the previously developed areas to a depth of
approximately 1.5m. The resulting spoil would be screened and crushed to a 6F2
standard and re-laid in controlled and compacted layers in accordance with DTp
Specification for Highways Works.
The exposed formations should be checked and any soft spots/areas should be removed
and replaced with well compacted site won or imported granular fill material.
The reduced levels should be brought up to the required levels with well compacted
imported granular materials. Department of Transport (DTp) Type 1 sub base, or similar
approved, could be used, and should be compacted in layers, in accordance with the
current DTp Specification for Highway Works.
Excavating and processing the ground to approximately 1.5m depth, will also have the
additional benefit of exposing, and being able to appropriately deal with, any hitherto
undetected ‘hot spots/areas’ of hydrocarbon contamination. Any soft spots identified
during preparation works should be removed and backfilled with clean granular material
in accordance with the DTp Specification for Highway Works.
LLEWELLYN ROAD, PENLLERGAER 9867MJE/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 32
11.2 SITE PREPARATION (CONITNUED)
A contingency should be allowed for the possible presence of loosely backfilled former
tanks or inspection pits (associated with vehicular maintenance). These and any other
‘soft spots/areas’ should be removed and replaced with well compacted acceptable
granular materials, as described above.
The materials required to achieve finished levels, i.e. fill materials, topsoil, road
construction materials etc. should be acceptable site processed or imported materials.
Any shortfall in quantities shall be made up with clean, inert, granular imported materials
in accordance with an agreed specification. These materials will need to be placed and
compacted to achieve structural performance standards.
All the investigation, remediation and engineering works should be fully supervised by
appropriate qualified and experienced geotechnical engineers. All physical and chemical
testing will be subject to certification procedures with full documentation by appropriate
Consulting Engineers and regulators such as the Local Authority’s Environmental Health
Department, the Environment Agency and the NHBC.
Any buried services running within the site should be traced and either disconnected and
removed or diverted prior to site works commencing
The dense trees and vegetation within the southern area of the site will require
appropriate clearance subject to TPO’s etc. A detailed Japanese Knotweed survey
should be undertaken during this process, and if any is found, suitably treated,
11.3 FOUNDATIONS AND FLOOR SLABS
Both the made ground and cohesive superficial deposits, owing to their physical nature,
are not considered suitable founding horizons for the proposed structures, and as such
should be fully penetrated by the chosen foundation arrangement. It should also be
recognised that a significant amount of ground disturbance will arise when the existing
development of buildings and infrastructure are removed.
Several foundation options have been considered for the proposed structures, the details
of which are provided below.
Traditional Trench Fill Foundations The main problems with adopting such a foundation solution would be the problems
arising from the excavation of the foundation trenches and the presence of a variable and
rising water table.
LLEWELLYN ROAD, PENLLERGAER 9867MJE/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 33
11.3 FOUNDATIONS AND FLOOR SLABS (CONTINUED)
The trench sides are likely to become rapidly unstable and require shoring to maintain an
open excavation. Furthermore, it is recommended that foundations are excavated in
sections to retain some stability, meaning that foundation concrete will require pouring in
sections, making for a slow build programme.
In addition, the trenches would need to extend to depths of between 1.0m and possibly
up to 4.4m below existing ground level. This fact and the anticipated instability may mean
that significantly large volumes of mass poured concrete may be required, probably
making this foundation solution impractical and uneconomical.
Standing water observed in the trial pits excavated during the site investigation indicates
that significant dewatering of foundation trenches may also be required.
If trench fill foundations are proposed in some areas (where the made ground and
cohesive superficial soils are thinner) mass concrete strip/trench fill foundations could be
used and founded within the competent in-situ granular soils. An allowable bearing
pressure of 100kN/m2 can be used to design foundations in these materials. At this
intensity of loading, and in these competent materials the total settlements should not
exceed 25mm and any angular distortions caused by differential movements should be
less than 1:750.
Any soft spots encountered in foundation trenches should be excavated out and the
foundation over deepened until more competent soils are encountered.
To protect against the effects of frost heave and thermal shrinkage, foundation formations
should be a minimum of 900mm below finished ground level.
Owing to the presence of mature trees and vegetation located to the south of the site,
foundations may require deepening in accordance with NHBC Chapter 4.2.
Suspended floor slabs would be required with this approach.
Raft Foundation An alternative to trench fill/pier foundations could be the use of an engineered raft
foundation.
LLEWELLYN ROAD, PENLLERGAER 9867MJE/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 34
11.3 FOUNDATIONS AND FLOOR SLABS (CONTINUED)
The made ground below any proposed raft foundation should be excavated out and
screened to remove any unsuitable materials such as large, typically boulder sized
inclusions of concrete, brickwork, metal and timber etc. The processed and acceptable
made ground can then be placed back in the resultant excavation in thin well compacted
layers, in accordance with the current DTp Specification for Highways Works.
A suitable bed of Type 1 sub base or similar approved material should be laid on top of
the re-engineered made ground, and again compacted and placed in a controlled manner
compliant with the Specification for Highways Works.
The thickness of such materials should be determined by a suitable qualified structural
engineer and will depend somewhat on the chosen design of the raft foundations.
For preliminary purposes, the proposed rafts should be designed to an allowable
maximum bearing pressure of 40kN/m2, with an average pressure of less than 30kN/m2.
At this intensity of loading, the total settlements should not exceed 25/30mm and any
angular distortions caused by differential movements should be less than 1:750.
Plate load tests and/or dynamic probing of any fill materials placed and the proposed
formation will be required in order to confirm the adequacy of the earthworks prior to
floating the raft.
Pile Foundations/Vibro compaction treatment Given the economic considerations of the above foundations, and the possible difficulties
that may be encountered when constructing the above foundation types, it may be
prudent to adopt a piled foundation arrangement or ground treatment by vibro methods of
treatment supporting reinforced strip footings.
Pile Foundations
Provided that the piles are taken down into suitably competent in-situ materials then pre-
cast concrete driven or cast in-situ augered/driven piles could be used and taken down to
appropriate sets.
Shell and auger boreholes will be required to provide geotechnical information on the
shallow to medium depth soils.
The advice of a specialist piling contractor should be sought regarding the specific design
and load bearing capacity of any piles. Any load capacity contribution from the made
ground or cohesive superficial deposits should be ignored in the pile design.
LLEWELLYN ROAD, PENLLERGAER 9867MJE/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 35
11.3 FOUNDATIONS AND FLOOR SLABS (CONTINUED)
Allowances should be made for a negative skin friction within any uncompacted made
ground or soft in-situ soils.
Allowances should again be made by the piling contractor for the removal of any buried
structures and the ease of piling through the made ground, cohesive superficial soils,
granular soils and solid strata at depth that may be encountered during the piling works.
Allowance should also be made for suitable pile testing.
Vibro compaction treatment Consideration may also be given to ground improvement, which could be achieved with
vibro-compaction. This method would involve the construction of closely spaced stone
columns using bottom feed systems, beneath the load bearing areas of the buildings.
The stone columns should extend as far as possible through the made ground and soft to
firm predominantly cohesive shallow superficial soils and into the competent granular
soils at depth. The aim is to ensure 'stiffening' of the ground, thereby spreading and
dissipating the new development bearing stresses to minimise any differential settlements
within the underlying soils.
If the use of vibro-compaction is to be considered further it is strongly recommended that
a suitably experience specialist vibro-stabilisation contractor be contacted to explore this
technique further.
Removal and/or pre-loosening during site preparation may be necessary to ensure
penetration of the vibro-compaction probe through areas of more compact made ground.
Following successful ground treatment works, reinforced concrete strip foundations with
suspended floor slabs or could be utilised.
The ground treatment works, if adopted after further review, should be such that an
allowable bearing pressure in the range of 100-125kN/m2 could be achieved 600mm
below the surface of the site suitable for an appropriately designed reinforced concrete
beam or strip footing.
Within the prepared ground at the proposed foundation formations, and at this intensity of
loading, the total settlements should not exceed 20mm and any angular distortions
resulting from differential settlements should be less than 1 in 750.
LLEWELLYN ROAD, PENLLERGAER 9867MJE/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 36
11.3 FOUNDATIONS AND FLOOR SLABS (CONTINUED)
Upon completion of the vibro stabilisation works, properties may be founded using
reinforced strip or raft foundations designed in line with design requirements of the
specialist vibro piling contractor.
Ground slabs should be of suspended construction and incorporate the suitable gas
protection/vapour resistant membranes and ventilated sub floor voids. This provision will
be confirmed subject to the completion of the gas monitoring recommended in this report.
As detailed for piling, shell and auger boreholes will be required to investigate the deeper
ground conditions prior to finalising design.
11.4 EXCAVATIONS AND FORMATIONS
It is difficult to gauge trench stability and ease of excavation based on the penetration of
windowless sample equipment. However, we consider that excavation should be
possible with normal soil excavating machinery. Allowances should be made for the use
of more powerful machinery and the use of pneumatic/hydraulic breakers, where the
potential for remnant buried obstructions (buried services, old foundations, pits etc) within
the made ground exist, or where excavations into the dense natural superficial soils are
anticipated.
Excavations to depths of typically 1.0m are likely to encounter significant groundwater
inflows. Perched pockets of groundwater associated with buried foundations and other
structures should be anticipated. Some of these influxes of groundwater (if contaminated
by organic materials) should be treated/removed using appropriate tanker and hose, or a
specialised filtered free phase separator leading to the hydrocarbon product being
removed from the perched water.
If excavations are required to extend to greater depths, then variable and possibly
considerable quantities of groundwater should be anticipated, particularly within the
saturated gravel horizon at depth. Such water ingress should be adequately controlled at
all times to ensure stability and protection of the temporary and permanent works
Some pit side instability within the heterogeneous made ground deposits should be
anticipated. The stability of trenches within the made ground is likely to rapidly
deteriorate over time, and excavations may require shoring to maintain an open
excavation. Trenches extending into the natural gravels are also likely to rapidly become
unstable owing to the progressive influxes of groundwater.
LLEWELLYN ROAD, PENLLERGAER 9867MJE/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 37
11.4 EXCAVATIONS AND FORMATIONS (CONTINUED)
Any trenches to depths greater than 1.2m and required to be entered by personnel should
be made safe in line with health and safety requirements, or temporarily battered back at
gradients of typically 30 degrees.
Any ‘soft spots/areas’ encountered in the formations should be removed and replaced
with well compacted imported granular materials.
The exposed formations within the in-situ materials will be susceptible to damage,
loosening and deterioration by wet weather and site traffic. They should therefore be
protected by blinding concrete, or a 200mm thick layer of hardcore, immediately after
exposure.
11.5 ACCESS ROADS AND CAR PARKING AREAS
Following the site strip there are likely to be variations in the strength of the materials at
the formation levels. It is recommended that for design purposes, a California Bearing
ratio (CBR) value of between 1% (made ground) and 2% (natural shallow cohesive soils)
could be assumed for the in-situ soils subject to confirmation by in-situ testing. After
appropriate site preparation as outlined in Section 11.2 above a CBR of 5% should be
achievable.
Where the granular materials are re-used to reinstate and raise the site area 5% CBR
values are considered achievable. Lesser quality materials may necessitate the use of a
capping layer.
After proof rolling the formations, all the ‘soft spots/areas’ should be removed and
replaced with well compacted imported granular materials. Such materials should be to
the approval of the local highway authority and should be compacted in layers, in
accordance with the DTp Specification for Highways Works.
11.6 SOAKAWAY POTENTIAL Soakaway testing to British Standards required to show regimes was not attempted but in
situ falling head permeability tests were undertaken in the installations constructed in five
of the window sample holes.
Soakaway testing was attempted in the more permeable strata.
LLEWELLYN ROAD, PENLLERGAER 9867MJE/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 38
11.6 SOAKAWAY POTENTIAL (CONTINUED)
Location Test Section Result Comments
(m) (m/s)
WS1 1.0 – 3.36 8.2 x 10 -4
WS3 1.0 – 3.56 1.5 x 10 -4
1.8 X 10-5 Initial result more indicative of installation effects rather than ground. Adopt second result
WS4 1.0 – 4.0 4.8 x 10 -5
WS6 1.0 – 3.84 2.1 x 10 -6
WS9 1.0 – 3.2 1.4 x 10 -3
Generally the upper superficial materials are of low permeability as they are
predominantly clay based. They may possess some macro permeability due to the
nature of the backfilling but infiltration could cause further settlement and loss of material.
The gravelly strata at depth are more permeable but are often saturated possibly with a
sub artesian or even artesian head seasonly or during heavy rainfall periods.
In view of the above, the use of infiltration may not be applicable within drainage design if
levels remain at current levels as the drainage systems will essentially be flooded and
there will be insufficient head to facilitate infiltration. However, if levels are raised then
this might permit the use of trench type soakaway systems providing adequate storage is
provided. However, sustainable drainage systems including swales and attenuation
basins should be considered to attenuate surface run off, subject to appropriate design.
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 39
COLD STORAGE DEPOT, LLANTARNAM ROAD, CWMBRAN 10725-2/GNS/10
INTÉGRAL GÉOTECHNIQUE (WALES) LIMITED Page 40
12.0 RECOMMENDED FURTHER WORKS
The following further works are recommended following clearance of the site.
• Undertake investigations in the unexplored areas currently vegetated.
• Undertake research into building construction and then intrusive investigations of
floor areas and construction together with contamination surveys.
• Undertake trial pitting across the site to obtain better coverage, particularly in
those areas previously inaccessible (beneath the footprint of the former buildings
and within the densely vegetated area in the south).
• Undertaken a number of soil infiltration tests within trial pit excavations in
accordance with BRE 365.
• Drill a series of shell and auger boreholes across the site to investigate the nature
of the soils/rocks at depth and provide the necessary parameters for vibro-
treatment/pile design.
• Detailed laboratory analysis will be required in those areas previously
inaccessible.
• Further delineation of areas in which hydrocarbons were previously identified will
require investigation and laboratory analysis.
APPENDIX A
CONTAMINATED LAND DEFINITIONS
Box 1: Contamination and contaminated land in a planning context Annex 2 of Planning Policy Statement 23 (3) states that:
� To avoid confusion with the statutory term “contaminated land” and its definition [i.e. in Part IIA of
the Environmental Protection Act 1990] and to reflect the different context of planning control, this
Annex uses the wider term “land affected by contamination”. This is intended to cover all cases
where the actual or suspected presence of substances in, on or under the land may cause risks to
people, property human activities, or the environment, regardless of whether or not the land meets
the statutory definition in Part IIA.
Annex 2 also states:
� Potentially hazardous substances, such as radon, methane or elevated concentrations of metallic
elements may also be present in the ground due to the underlying geology. Since these may pose a
risk to human health or to the environment, their presence is a material consideration.
Box 2: The Building Regulations – Approved Document C(4) Contamination is dealt with in requirement C1 which concerns `Preparation of site and resistance to
moisture'.
C1(1) requires that: The ground to be covered by the building shall be reasonably free from any material that might
damage the building or affect its stability, including vegetable matter, top-soil and pre-existing
foundations.
C1(2) requires that: Reasonable precautions shall be taken to avoid danger to health and safety caused by
contaminants on or in the ground covered, or to be covered by the building and any land associated
with the building.
C1(3) requires that:
Adequate sub-soil drainage shall be provided if it is needed to avoid –
(a) the passage of ground moisture to the interior of the building;
(b) damage to be building, including damage through the transport of water-borne contamination to
the foundations of the building.
Contaminant is defined as (C1(4)):
Any substance which is or may become harmful to persons or buildings, including substances
which corrosive, explosive, flammable or radioactive or toxic.
The “building and land associated with the building” means: The building and all land forming the site subject to building operations which includes land under
the building and the land around it which may have an effect on the building or its users.
Requirement C1(2) applies to new construction and under Regulation 6, whenever there is a
“material change of use” of the whole building. “Material change of use” is defined in Regulation 5.
APPENDIX B
WINDOWLESS SAMPLE LOGS
APPENDIX C
FALLING HEAD TEST RESULTS
APPENDIX D
LABORATORY CHEMICAL TEST RESULTS (SOILS)
APPENDIX E
LABORATORY CHEMICAL TEST RESULTS (LEACHATE)
APPENDIX F
LABORATORY PHYSICAL TEST RESULTS
APPENDIX G
GROUNDWATER MONITORING RESULTS
APPENDIX H
IN-SITU GAS MONITORING RESULTS
APPENDIX I
STATISTICAL ASSESSMENT OF CHEMICAL RESULTS
FIGURES
APPENDIX A
CONTAMINATED LAND DEFINITIONS
Box 1: Contamination and contaminated land in a planning context Annex 2 of Planning Policy Statement 23 (3) states that:
� To avoid confusion with the statutory term “contaminated land” and its definition [i.e. in Part IIA of
the Environmental Protection Act 1990] and to reflect the different context of planning control, this
Annex uses the wider term “land affected by contamination”. This is intended to cover all cases
where the actual or suspected presence of substances in, on or under the land may cause risks to
people, property human activities, or the environment, regardless of whether or not the land meets
the statutory definition in Part IIA.
Annex 2 also states:
� Potentially hazardous substances, such as radon, methane or elevated concentrations of metallic
elements may also be present in the ground due to the underlying geology. Since these may pose a
risk to human health or to the environment, their presence is a material consideration.
Box 2: The Building Regulations – Approved Document C(4) Contamination is dealt with in requirement C1 which concerns `Preparation of site and resistance to
moisture'.
C1(1) requires that: The ground to be covered by the building shall be reasonably free from any material that might
damage the building or affect its stability, including vegetable matter, top-soil and pre-existing
foundations.
C1(2) requires that: Reasonable precautions shall be taken to avoid danger to health and safety caused by
contaminants on or in the ground covered, or to be covered by the building and any land associated
with the building.
C1(3) requires that:
Adequate sub-soil drainage shall be provided if it is needed to avoid –
(a) the passage of ground moisture to the interior of the building;
(b) damage to be building, including damage through the transport of water-borne contamination to
the foundations of the building.
Contaminant is defined as (C1(4)):
Any substance which is or may become harmful to persons or buildings, including substances
which corrosive, explosive, flammable or radioactive or toxic.
The “building and land associated with the building” means: The building and all land forming the site subject to building operations which includes land under
the building and the land around it which may have an effect on the building or its users.
Requirement C1(2) applies to new construction and under Regulation 6, whenever there is a
“material change of use” of the whole building. “Material change of use” is defined in Regulation 5.
APPENDIX B
WINDOWLESS SAMPLE LOGS
APPENDIX C
FALLING HEAD TEST RESULTS
PERMEABILITY TEST DATA
PROJECT JOB No.
TYPE FALLING
DATE 03.12.10 TIME 10.3 hrs
BOREHOLE NUMBER WS 1 TEST No. 1
3.36 m From top of casing
3.36 m From top of casingOK
0.076 m
0.050 m
0.00 m
L/D Ratio 31.1
2.36 m
1.00 m From top of casing
1.00 m
1.04 m
0.00 m
HG TEST 2.04 m
Depth of water below top of casing Head of Water Ratio
t t h H = (Hg - h) H/H0(mins) (s) (m) (m)
0 0 0.00 2.0 1.00
0.5 30 1 60 0.62 1.4 0.70
1.5 902 120 1.03 1.0 0.503 180 1.33 0.7 0.354 240 1.59 0.5 0.225 300 1.70 0.3 0.1710 600 1.81 0.2 0.1115 900 1.92 0.1 0.0620 1200 1.96 0.1 0.0425 1500 1.99 0.1 0.0230 1800 2.00 0.0 0.0245 270060 3600
TEST SECTIONLength L = 2.36 m Area A = 0.5680 m2
INTAKE FACTORRefer to BS 5930 Figure 7
Type Special
F =
F = 4.09
TIME LAGT = Time from start of test when h = 0.37 ho
See graph opposite
T = 750 s
PERMEABILITY
K = A / ( F * T )
K = 1.85E-04 m/s
COMMENTS
Soil in casing (m) L
Depth of casing (mBGL) hc
Height of casing above ground level huc
Ground water level (mBGL) HG
Hole in Soil below base of casing (m) L
Elapsed Time
Water level at start of test below top of casing ho
Cold Store Llantarnam 10725
Piezometer diameter (m) d
Depth of borehole at start of test (mBGL) hi
Depth of borehole at end of test (mBGL) he
Borehole diameter (m) D
D*2.32*Π*(L/D)loge[1.1(L/D)+((1+1.1(L/D)2)0.5]
Borehole WS 1
0.10
1.000 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 950 1000
Time (secs)
LOG
H/H
o 0.37 H/H0
TRENDLINE
PERMEABILITY TEST DATA
PROJECT JOB No.
TYPE FALLING
DATE 03.12.10 TIME 11 hrs
BOREHOLE NUMBER WS 3 TEST No. 1
3.56 m From top of casing
3.56 m From top of casingOK
0.076 m
0.050 m
0.00 m
L/D Ratio 33.7
2.56 m
1.00 m From top of casing
1.00 m
1.04 m
0.00 m
HG TEST 2.04 m
Depth of water below top of casing Head of Water Ratio
t t h H = (Hg - h) H/H0(mins) (s) (m) (m)
0 0 0.00 2.0 1.00
0.5 30 1 60 0.21 1.8 0.90
1.5 902 120 0.53 1.5 0.743 180 0.82 1.2 0.604 240 0.96 1.1 0.535 300 1.02 1.0 0.5010 600 1.17 0.9 0.4315 900 1.28 0.8 0.3720 1200 1.31 0.7 0.3625 1500 1.34 0.7 0.3430 1800 1.39 0.7 0.3245 2700 1.41 0.6 0.3160 3600
TEST SECTIONLength L = 2.56 m Area A = 0.6158 m2
INTAKE FACTORRefer to BS 5930 Figure 7
Type Special
F =
F = 4.36
TIME LAGT = Time from start of test when h = 0.37 ho
See graph opposite
T = 7900 s
PERMEABILITY
K = A / ( F * T )
K = 1.79E-05 m/s
COMMENTS
Soil in casing (m) L
Depth of casing (mBGL) hc
Height of casing above ground level huc
Ground water level (mBGL) HG
Hole in Soil below base of casing (m) L
Elapsed Time
Water level at start of test below top of casing ho
Cold Store Llantarnam 10725
Piezometer diameter (m) d
Depth of borehole at start of test (mBGL) hi
Depth of borehole at end of test (mBGL) he
Borehole diameter (m) D
D*2.32*Π*(L/D)loge[1.1(L/D)+((1+1.1(L/D)2)0.5]
Borehole WS 3
0.10
1.000 250 500 750 1000 1250 1500 1750 2000 2250 2500 2750 3000 3250 3500 3750 4000 4250 4500 4750 5000
Time (secs)
LOG
H/H
o 0.37 H/H0
TRENDLINE
PERMEABILITY TEST DATA
PROJECT JOB No.
TYPE FALLING
DATE 03.12.10 TIME 11.30 hrs
BOREHOLE NUMBER WS 4 TEST No. 1
4.01 m From top of casing
4.01 m From top of casingOK
0.076 m
0.050 m
0.00 m
L/D Ratio 39.6
3.01 m
1.00 m From top of casing
1.00 m
1.90 m
0.00 m
HG TEST 2.90 m
Depth of water below top of casing Head of Water Ratio
t t h H = (Hg - h) H/H0(mins) (s) (m) (m)
0 0 0.00 2.9 1.00
0.5 30 1 60 0.59 2.3 0.80
1.5 902 120 0.93 2.0 0.683 180 1.24 1.7 0.574 240 1.52 1.4 0.485 300 1.86 1.0 0.3610 600 2.03 0.9 0.3015 900 2.18 0.7 0.2520 1200 2.31 0.6 0.2025 1500 2.50 0.4 0.1430 1800 2.61 0.3 0.1045 2700 2.68 0.2 0.0860 3600 2.72 0.2 0.06
TEST SECTIONLength L = 1.60 m Area A = 0.3866 m2
INTAKE FACTORRefer to BS 5930 Figure 7
Type Special
F =
F = 4.94
TIME LAGT = Time from start of test when h = 0.37 ho
See graph opposite
T = 1650 s
PERMEABILITY
K = A / ( F * T )
K = 4.75E-05 m/s
COMMENTSInitial curve reflects made ground.
Soil in casing (m) L
Depth of casing (mBGL) hc
Height of casing above ground level huc
Ground water level (mBGL) HG
Hole in Soil below base of casing (m) L
Elapsed Time
Water level at start of test below top of casing ho
Cold Store Llantarnam 10725
Piezometer diameter (m) d
Depth of borehole at start of test (mBGL) hi
Depth of borehole at end of test (mBGL) he
Borehole diameter (m) D
D*2.32*Π*(L/D)loge[1.1(L/D)+((1+1.1(L/D)2)0.5]
Borehole WS 4
0.10
1.000 250 500 750 1000 1250 1500 1750 2000
Time (secs)
LOG
H/H
o 0.37 H/H0
TRENDLINE
PERMEABILITY TEST DATA
PROJECT JOB No.
TYPE FALLING
DATE 03.12.10 TIME 12 hrs
BOREHOLE NUMBER WS 6 TEST No. 1
3.84 m From top of casing
3.84 m From top of casingOK
0.076 m
0.050 m
0.00 m
L/D Ratio 37.4
2.84 m
1.00 m From top of casing
1.00 m
1.93 m
0.00 m
HG TEST 2.93 m
Depth of water below top of casing Head of Water Ratio
t t h H = (Hg - h) H/H0(mins) (s) (m) (m)
0 0 0.00 2.9 1.00
0.5 30 1 60 0.82 2.1 0.72
1.5 902 120 1.07 1.9 0.633 180 1.22 1.7 0.584 240 1.34 1.6 0.545 300 1.39 1.5 0.53
10 600 1.56 1.4 0.4715 900 1.72 1.2 0.4120 1200 1.84 1.1 0.3725 1500 1.90 1.0 0.3530 1800 2.03 0.9 0.3145 2700 2.03 0.9 0.3160 3600 2.09 0.8 0.29
TEST SECTIONLength L = 0.10 m Area A = 0.0284 m2
INTAKE FACTORRefer to BS 5930 Figure 7
Type Special
F =
F = 4.72
TIME LAGT = Time from start of test when h = 0.37 ho
See graph opposite
T = 2800 s
PERMEABILITY
K = A / ( F * T )
K = 2.15E-06 m/s
COMMENTS
Cold Store Llantarnam 10725
Piezometer diameter (m) d
Depth of borehole at start of test (mBGL) hi
Depth of borehole at end of test (mBGL) he
Borehole diameter (m) D
Assumes infiltration to gravel horizon only
Soil in casing (m) L
Depth of casing (mBGL) hc
Height of casing above ground level huc
Ground water level (mBGL) HG
Hole in Soil below base of casing (m) L
Elapsed Time
Water level at start of test below top of casing ho
D*2.32*Π*(L/D)loge[1.1(L/D)+((1+1.1(L/D)2)0.5]
Borehole WS 6
0.10
1.000 250 500 750 1000 1250 1500 1750 2000 2250 2500 2750 3000
Time (secs)
LOG
H/H
o 0.37 H/H0
TRENDLINE
PERMEABILITY TEST DATA
PROJECT JOB No.
TYPE FALLING
DATE 03.12.10 TIME 12 hrs
BOREHOLE NUMBER WS 9 TEST No. 1
3.24 m From top of casing
3.24 m From top of casingOK
0.076 m
0.050 m
0.00 m
L/D Ratio 29.5
2.24 m
1.00 m From top of casing
1.00 m
1.00 m
0.51 m
HG TEST 2.00 m
Depth of water below top of casing Head of Water Ratio
t t h H = (Hg - h) H/H0(mins) (s) (m) (m)
0 0 0.51 1.5 1.00
0.5 30 1 60 1.04 1.0 0.64
1.5 902 120 1.36 0.6 0.433 180 1.61 0.4 0.264 240 1.82 0.2 0.125 300 10 600 15 900 20 1200 25 1500 30 1800 45 2700 60 3600
TEST SECTIONLength L = 2.24 m Area A = 0.5394 m2
INTAKE FACTORRefer to BS 5930 Figure 7
Type Special
F =
F = 3.94
TIME LAGT = Time from start of test when h = 0.37 ho
See graph opposite
T = 130 s
PERMEABILITY
K = A / ( F * T )
K = 1.05E-03 m/s
COMMENTS
Cold Store Llantarnam 10725
Piezometer diameter (m) d
Depth of borehole at start of test (mBGL) hi
Depth of borehole at end of test (mBGL) he
Borehole diameter (m) D
Test may be more reflective of made ground rather than natural soils.
Soil in casing (m) L
Depth of casing (mBGL) hc
Height of casing above ground level huc
Ground water level (mBGL) HG
Hole in Soil below base of casing (m) L
Elapsed Time
Water level at start of test below top of casing ho
D*2.32*Π*(L/D)loge[1.1(L/D)+((1+1.1(L/D)2)0.5]
Borehole WS 9
0.10
1.000 50 100 150 200 250 300 350 400 450 500
Time (secs)
LOG
H/H
o 0.37 H/H0
TRENDLINE
APPENDIX D
LABORATORY CHEMICAL TEST RESULTS (SOILS)
APPENDIX E
LABORATORY CHEMICAL TEST RESULTS (LEACHATE)
APPENDIX F
LABORATORY PHYSICAL TEST RESULTS
APPENDIX G
GROUNDWATER MONITORING RESULTS
Field Gas Monitoring ResultsSite: Cold Store Job No: 10725
Date: 03.12.10 Weather: Cloudy/Icy
Name of Engineer: RH Barometric Pressure (Millibars): On Arrival During Monitoring End of Monitoring Ambient Temp1009 1008 1008 1ºC
Water level Well Base Level Methane (CH4) Oxygen Carbon Dioxide Carbon Monoxide Hydrogen Sulphide Peak Gas Flow VOC Vapours TimeBorehole No. (mbgl) (mbgl) LEL (%) Average (%) Peak (%) O2 (%) CO2 (%) CO (ppm) H2 S (ppm) (l/per hr) (ppm > background)
WS 1 1.04 2.36 0.00 0.00 0.00 20.10 0.20 0.00 0.00 0.00 0.00 12.15
WS 3 1.31 2.56 0.00 0.00 0.00 19.40 0.40 0.00 0.00 0.00 0.00 13.00
WS 4 1.90 3.01 0.00 0.00 0.00 17.90 1.60 1.00 0.00 0.00 0.00 13.30
WS 6 1.93 2.84 0.00 0.00 0.00 20.40 0.10 0.00 0.00 0.00 0.00 14.00
WS 9 1.00 2.24 0.00 0.00 0.00 20.00 0.30 0.00 0.00 0.00 0.00 14.45
Notes:
1. Instrument Used: GA 2000 Gas Analyser2. Typical Accuracy: Gas 0-5% Volume 5-15% Voume 15%-FS Gas 0-FS
%CH4 +/- 1% +/- 1% +/- 3% CO +/1 10%FS%CO2 +/- 2% +/- 1% +/- 3% H2S +/1 10%FS%O2 +/- 1% +/- 1% +/- 3%
3. LEL = Lower Explosive Limit4. N/R = No Reading Taken
Intégral Géotechnique
APPENDIX H
IN-SITU GAS MONITORING RESULTS
Field Gas Monitoring ResultsSite: Cold Store Job No: 10725
Date: 03.12.10 Weather: Cloudy/Icy
Name of Engineer: RH Barometric Pressure (Millibars): On Arrival During Monitoring End of Monitoring Ambient Temp1009 1008 1008 1ºC
Water level Well Base Level Methane (CH4) Oxygen Carbon Dioxide Carbon Monoxide Hydrogen Sulphide Peak Gas Flow VOC Vapours TimeBorehole No. (mbgl) (mbgl) LEL (%) Average (%) Peak (%) O2 (%) CO2 (%) CO (ppm) H2 S (ppm) (l/per hr) (ppm > background)
WS 1 1.04 2.36 0.00 0.00 0.00 20.10 0.20 0.00 0.00 0.00 0.00 12.15
WS 3 1.31 2.56 0.00 0.00 0.00 19.40 0.40 0.00 0.00 0.00 0.00 13.00
WS 4 1.90 3.01 0.00 0.00 0.00 17.90 1.60 1.00 0.00 0.00 0.00 13.30
WS 6 1.93 2.84 0.00 0.00 0.00 20.40 0.10 0.00 0.00 0.00 0.00 14.00
WS 9 1.00 2.24 0.00 0.00 0.00 20.00 0.30 0.00 0.00 0.00 0.00 14.45
Notes:
1. Instrument Used: GA 2000 Gas Analyser2. Typical Accuracy: Gas 0-5% Volume 5-15% Voume 15%-FS Gas 0-FS
%CH4 +/- 1% +/- 1% +/- 3% CO +/1 10%FS%CO2 +/- 2% +/- 1% +/- 3% H2S +/1 10%FS%O2 +/- 1% +/- 1% +/- 3%
3. LEL = Lower Explosive Limit4. N/R = No Reading Taken
Intégral Géotechnique
APPENDIX I
STATISTICAL ASSESSMENT OF CHEMICAL RESULTS
SUMMARY OF LABORATORY CHEMICAL TEST RESULTS
Job Number: 10725 Site: Cold Storage Depot, Llantarnam Client: Barratt South Wale
Number of Samples
Minimum Concentration
Maximum Concentration
Guideline Concentration Source
(mg/kg) (mg/kg) (mg/kg)Beryllium 8 0.20 1.10 51 LQMCadmium 8 0.02 4.80 10 SGVChromium 8 9.00 26.00 4.3 LQMHexavalent Chromium 8 1.00 1.00 4.3 LQMCopper 8 5.70 34.00 2330 LQMLead 8 8.20 231.00 166 ATRISKMercury 8 0.03 0.89 1 SGVNickel 8 1.90 24.00 130 SGVVanadium 8 10.00 27.00 75 LQMZinc 8 39.00 323.00 3750 LQMArsenic 8 0.40 5.20 32 SGVBoron 8 0.10 2.21 291 LQMCyanide 8 1.00 1.00 34 ATRISKSelenium 8 0.70 0.70 350 SGVElemental Sulphur 8 0.10 2.70 5000 EATotal Sulphate 0 0.00 0.00 2000 BRESulphide 8 1.00 1.00 250 EAMonohydric Phenol 8 1.00 1.00 420 SGVpH 8 7.00 12.00 5 -Acenaphthene 8 0.30 3.30 210 1%SOM LQMAcenaphthylene 8 0.10 1.50 170 1%SOM LQMAnthracene 8 0.10 10.00 2300 1%SOM LQMBenzo(a)anthracene 8 0.10 20.00 3 1%SOM LQMBenzo(a)pyrene 8 0.10 13.00 0.8 1%SOM LQMBenzo(b)fluoranthene 8 0.10 15.00 6 1%SOM LQMBenzo(ghi)perylene 8 0.10 11.00 44 1%SOM LQMBenzo(k)fluoranthene 8 0.10 14.00 9 1%SOM LQMChrysene 8 0.10 28.00 6 1%SOM LQMDibenzo(ah)anthracene 8 0.10 4.10 0.8 1%SOM LQMFluoranthene 8 0.10 21.00 260 1%SOM LQMFluorene 8 0.40 5.30 160 1%SOM LQMIndeno(123cd)pyrene 8 0.10 12.00 3.2 1%SOM LQMNaphthalene 8 0.10 1.30 1.5 1%SOM LQMPhenanthrene 8 0.50 16.00 92 1%SOM LQMPyrene 8 0.10 18.00 560 1%SOM LQMAliphatic C5-C6 5 0.10 0.20 30 1%SOM LQMAliphatic C6-C8 5 0.10 0.10 73 1%SOM LQMAliphatic C8-C10 5 10.00 10.00 19 1%SOM LQMAliphatic C10-C12 EPH 5 10.00 10.00 93 1%SOM LQMAliphatic C12-C16 EPH 5 10.00 129.00 740 1%SOM LQMAliphatic C16-C35 EPH 5 20.00 1960.00 45000 1%SOM LQMAliphatic C35-C44 EPH 5 10.00 903.00 45000 1%SOM LQMAromatic C5-C7 5 0.10 0.10 65.00 1%SOM LQMAromatic C7-C8 5 0.10 0.10 120 1%SOM LQMAromatic C8-C10 5 10.00 10.00 27 1%SOM LQMAromatic C10-C12 EPH 5 10.00 10.00 69 1%SOM LQMAromatic C12-C16 EPH 5 10.00 18.00 140 1%SOM LQMAromatic C16-C21 EPH 5 10.00 294.00 250 1%SOM LQMAromatic C21-C35 EPH 5 11.00 1025.00 890 1%SOM LQMAromatic C35-C40 EPH 5 11.00 1025.00 890 1%SOM LQMMonohydric Phenol 8 1.00 1.00 420 SGVElemental Sulphur 8 0.10 2.70 5000 EATotal Sulphate 0 0.00 0.00 2000 BREWater Soluble Sulphate (g/l) 8 0.04 0.22 0.5 BRESulphide 8 1.00 1.00 250 EApH 8 7.00 12.00 5 -
Note: All concentrations in mg/kg unless stated
Exceedence Representative US95 concentration exceeds guideline concentration
BU
ILD
ING
M
ATE
RIA
LS
DU
RA
BIL
ITY
Determinand
ME
TALS
SE
MI-M
ETA
LS
&
NO
N-
ME
TALS
PA
HTP
H
Integral Geotechnique (Wales) Limited
LABORATORY CHEMICAL TEST RESULTS SUMMARY
10725 Cold Storage Depot, Llantarnam
METALS, SEMI-METALS & NON-METALS
No. Location Depth (m) Arsenic as As, dry weight
Boron as B, hot water sol
dw
Beryllium as Be, dry weight
Cadmium as Cd, dry weight
Chromium as Cr, dry weight
Hexavalent Chromium as
DW
Copper (Total BG Spec)
Lead (Total BG Spec)
Mercury as Hg, dry weight
Nickel as Ni, dry weight
Selenium as Se, dry weight
Vanadium as V, dry weight
Zinc as Zn, dry weight
(mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg)
1 WS1 0.5 0.4 0.3 0.2 4.8 9 1 6.7 14 0.89 1.9 0.7 10 3232 WS5 0.4 3.9 0.4 0.9 0.02 15 1 33 22 0.08 24 0.7 23 573 WS6 0.3 0.4 1.8 1.1 0.09 9 1 13 231 0.07 3.3 0.7 11 864 WS6 0.6 4.7 0.5 0.8 0.02 15 1 22 37 0.1 20 0.7 26 685 WS7 0.5 5.2 0.4 0.8 0.02 16 1 20 28 0.1 22 0.7 27 826 WS8 0.5 4.7 2.21 0.8 0.02 14 1 34 67 0.1 23 0.7 26 1357 WS8 1.2 0.4 0.1 0.6 0.02 15.3 1 9.2 15 0.03 21.2 0.7 24 458 WS9 0.5 1.2 0.3 0.2 0.02 26 1 5.7 8.2 0.03 16 0.7 12 39
Soil Guidance value (SGV) 32.0 291.0 51.0 10.0 4.3 4.3 2330.0 166.0 1.0 130.0 350.0 75.0 3750.0
Source of SGV SGV LQM LQM SGV LQM LQM LQM ATRISK SGV SGV SGV LQM LQM
Integral Geotechnique (Wales) Limited
LABORATORY CHEMICAL TEST RESULTS SUMMARY
10725 Cold Storage Depot, Llantarnam
INORGANIC CHEMICALS & OTHERS
No. Location Depth (m) Cyanide (Total), dry weight
Loss on ignition, dried
solids
Monohydric phenols dw pH
Sulphate as SO4, Water
SolubleSulphide Sulphur
(Elemental)TOC (Ignition in
O2)
(mg/kg) (%) (mg/kg) (pH units) (g/l) (mg/kg) (mg/kg) (%)
1 WS1 0.5 1 6.4 1 12 0.035 1 0.1 4.32 WS5 0.4 1 3.7 1 10 0.154 1 0.2 6.23 WS6 0.3 1 5 1 8.2 0.133 1 2.7 4.54 WS6 0.6 1 5.4 1 7.2 0.039 1 0.3 1.85 WS7 0.5 1 5.5 1 7.3 0.056 1 0.4 2.36 WS8 0.5 1 7.3 1 7 0.049 1 2.7 2.27 WS8 1.2 1 1.8 1 7 0.038 1 0.2 0.48 WS9 0.5 1 2 1 9.2 0.215 1 0.1 2.5
Soil Guidance value (SGV) 34.0 10.0 420.0 5.0 0.5 250.0 5000.0 6.0
Source of SGV ATRISK WAC SGV - BRE EA EA WAC
Integral Geotechnique (Wales) Limited
LABORATORY CHEMICAL TEST RESULTS SUMMARY
10725 Cold Storage Depot, Llantarnam
POLY AROMATIC HYDROCARBONS (PAH)
No. Location Depth (m) Acenaphthene mg/kg 313
Acenaphthylene mg/kg 313
Anthracene mg/kg 313
Benzo(a)anthracene mg/kg 313
Benzo(a)pyrene mg/kg 313
Benzo(b)fluoranthene mg/kg 313
Benzo(ghi)perylene mg/kg 313
Benzo(k)fluoranthene mg/kg 313
Chrysene mg/kg 313
Dibenzo(ah)anthracene mg/kg
313
Fluoranthene mg/kg 313
Fluorene mg/kg 313
Indeno(123cd)pyrene mg/kg 313
Naphthalene mg/kg 313
Phenanthrene mg/kg 313
Pyrene mg/kg 313
(mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg)
1 WS1 0.5 0.6 0.1 1.3 1.5 0.7 1.4 0.5 0.7 1.3 0.2 3.3 0.7 0.5 1 3.8 2.42 WS5 0.4 3.3 1.5 10 20 13 15 11 14 28 4.1 21 5.3 12 1.3 16 183 WS6 0.3 1.2 0.6 3.5 7.7 6.2 9.4 2.8 3.8 8.4 1.3 16 1.7 3.1 0.3 11 114 WS6 0.6 0.4 0.1 0.2 0.5 0.5 1.2 0.4 0.5 0.8 0.2 1.2 0.4 0.4 0.3 0.8 15 WS7 0.5 0.4 0.1 0.1 0.1 0.1 0.2 0.1 0.1 0.1 0.1 0.2 0.4 0.1 0.2 0.5 0.16 WS8 0.5 0.9 0.7 1.7 6.1 6.3 9.8 3.2 4.3 8.1 1.4 8.9 1.3 3.4 0.6 6.7 5.87 WS8 1.2 0.3 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.7 0.1 0.2 1 0.18 WS9 0.5 1 0.3 3.3 7.7 5.3 8.6 2.3 4.1 7.8 1 17 1.2 2.6 0.1 12 11
Soil Guidance value (SGV) 210.0 170.0 2300.0 3.1 0.8 5.6 44.0 8.5 6.0 0.8 260.0 160.0 3.2 1.5 92.0 560.0
Source of SGV 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM
Integral Geotechnique (Wales) Limited
LABORATORY CHEMICAL TEST RESULTS SUMMARY
10725 Cold Storage Depot, Llantarnam
TOTAL PETROLEUM HYDROCARBONS (TPH)
No. Location Depth (m) Aliphatic C5-C6 Aliphatic C6-C8 Aliphatic C8-C10 Aliphatic C10-C12 EPH
Aliphatic C12-C16 EPH
Aliphatic C16-C35 EPH
Aliphatic C35-C44 EPH Aromatic C5-C7 Aromatic C7-C8 Aromatic C8-C10 Aromatic C10-
C12 EPHAromatic C12-
C16 EPHAromatic C16-
C21 EPHAromatic C21-
C35 EPHAromatic C35-
C40 EPH(mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) (mg/kg) -
9 WS7 0.5 0.2 0.1 10 10 10 22 12 0.1 0.1 10 10 10 10 14 1410 WS8 0.5 0.2 0.1 10 10 10 43 33 0.1 0.1 10 10 10 10 11 1111 WS8 1.2 0.1 0.1 10 10 129 221 56 0.1 0.1 10 10 10 10 18 1812 WS9 0.5 0.17 0.1 10 10 66 1960 903 0.1 0.1 10 10 18 294 1025 102513 WS9 1.4 0.19 0.1 10 10 10 20 10 0.1 0.1 10 10 10 10 19 19
Soil Guidance value (SGV) 30.0 73.0 19.0 93.0 740.0 45000.0 45000.0 65.0 120.0 27.0 69.0 140.0 250.0 890.0 890.0
Source of SGV 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM 1%SOM LQM
Integral Geotechnique (Wales) Limited
FIGURES
FIGURE 1 - SITE LOCATION
NORTH
Cold Storage Depot, Llantarnam, Cwmbran
1000m
SITE LOCATION
Intégral House7 Beddau WayCastlegate Business ParkCaerphillyCF83 2AXTel: 029 2080 7991Fax: 029 2086 2176
Integral Géotechnique
Window Sampling Location Crown Copyright Reserved
FIGURE 2 - SITE LAYOUT
NORTH
Cold Storage Depot, Llantarnam, Cwmbran
APPROXIMATE SITE BOUNDARY
TP1
TP4
TP5
TP3
TP2
TP6
Intégral House7 Beddau WayCastlegate Business ParkCaerphillyCF83 2AXTel: 029 2080 7991Fax: 029 2086 2176
Integral Géotechnique
WS 1
WS 6
WS 5
WS 2
WS 8
WS 9 WS 4
WS 3
WS 7
Area inaccessible due to dense vegetation