3/5/2015 Integrity ∙ Excellence ∙ Respect 2
SKAGWAY: DYEA ROAD SAFETY
IMPROVEMENTS
REGIONAL & VICINITY MAPS
Integrity ∙ Excellence ∙ Respect
Integrity ∙ Excellence ∙ Respect
DYEA ROAD HISTORY & LAND USE
DYEA ROAD WAS ORIGINALLY CONSTRUCTED BY THE ALASKA ROAD COMMISSION IN THE 1940’S. TOTAL LENGTH OF 8.4 MILES (2 MILES PAVED).
PROVIDES ACCESS TO:
• HISTORIC DYEA TOWNSITE
• CHILKOOT TRAIL
• DYEA CAMPGROUND
• LODGING
• RESIDENCES
• TOUR OPERATIONS
• OTHER RECREATIONAL OPPORTUNITIES
SCOPE OF WORK & FUNDING
SCOPE: IMPROVE SAFETY AT THREE LOCATIONS ALONG DYEA ROAD IN SKAGWAY, ALASKA. THESE LOCATIONS HAVE HISTORICALLY BEEN REFERRED AS THE DROP OFF, THE NARROWS, AND HACKETT HILL. SAFETY IMPROVEMENTS INCLUDED ROADWAY WIDENING, REDUCING VERTICAL AND HORIZONTAL CURVATURE, REALIGNMENT, AND GUARDRAIL INSTALLATION.
PROJECT CONSTRUCTION WAS FUNDED IN FEDERAL FISCAL YEAR 2012 THROUGH THE HIGHWAY SAFETY IMPROVEMENT PROGRAM (HSIP). CONSTRUCTION BEGAN IN 2013 AND WAS COMPLETED IN 2014.
TOTAL PHASE 4 COST - ~$3.7M (CONTRACT ITEMS, CE, & ICAP)
Integrity ∙ Excellence ∙ Respect
Integrity ∙ Excellence ∙ Respect
THE DROP OFF
SCOPE: THIS SECTION OF ROAD (APPROX. 600 LF) WAS WIDENED TO 24 FEET AWAY FROM NAHKU BAY. THIS REQUIRED CONTROLLED BLASTING WITH 4,800 CUBIC YARDS OF ROCK EXCAVATION. 570 LINEAR FEET OF GUARDRAIL WAS ALSO INSTALLED.
Integrity ∙ Excellence ∙ Respect
THE NARROWS
SCOPE: THIS SECTION OF ROAD (APPROX. 700 LF) WAS WIDENED TO
24 FEET TOWARDS TAIYA INLET DUE TO GEOTECHNICAL CONCERNS
RELATED TO THE STABILITY OF THE EXISTING SLOPE. THIS REQUIRED
25,000 CUBIC YARDS OF FILL AND RIPRAP PLACEMENT. 11,000 CUBIC
YARDS WERE PLACED BELOW HIGH TIDE LINE (HTL). 680 LINEAR FEET
OF GUARDRAIL WAS ALSO INSTALLED.
SCOPE:
THIS SECTION OF ROAD INCLUDED THE REALIGNMENT OF APPROXIMATELY 0.5 MILES OF DYEA ROAD. THIS REQUIRED CONTROLLED BLASTING WITH 49,000 CUBIC YARDS OF ROCK EXCAVATION. THIS ALSO REQUIRED 39,000 CUBIC YARDS OF EMBANKMENT CONSTRUCTION AND RIPRAP PLACEMENT. 33,000 CUBIC YARDS WERE PLACED BELOW HIGH TIDE LINE (HTL). 2,400 LINEAR FEET OF GUARDRAIL WAS ALSO NSTALLED.
HACKETT HILL
PRECONSTRUCTION PHOTOS
NARROW WINDING ROAD THAT IS CHALLENGING FOR LARGE VEHICLES
PRECONSTRUCTION PHOTOS
ROCK OUTCROPPINGS THAT LIMIT HORIZONTAL SIGHT DISTANCE
PRECONSTRUCTION PHOTOS
STEEP AND NEAR VERTICAL UNPROTECTED SLOPES
PRECONSTRUCTION PHOTOS
SHARP VERTICAL CURVES THAT LIMIT VERTICAL SIGHT DISTANCE
PRECONSTRUCTION PHOTOS
NEAR RUN-OFF-ROAD ACCIDENT & EMERGENCY WIDENING
LOCATED WITHIN DYEA SITE NATIONAL HISTORIC LANDMARK AND WITHIN VIEWSHED OF KLONDIKE GOLD RUSH NATIONAL HISTORIC PARK (PROTECTED 4(F) RESOURCES)
REQUIRED FILL PLACEMENT WITHIN INTERTIDAL, ESTUARINE, AND MARINE WATERS OF THE U.S.
REQUIRED FILL PLACEMENT IN EFH DESIGNATED WATERS FOR KING, COHO, CHUM AND PINK SALMON, AS WELL AS EULACHON
MOUNTAIN GOATS FREQUENT THE AREA IN WINTER MONTHS, WHICH REQUIRED MONITORING DURING BLASTING OPERATIONS
HUMPBACK WHALES, STELLER SEA LIONS, AND OTHER MARINE MAMMALS PRESENT IN THE AREA
ENVIRONMENTAL CHALLENGES
INCONSISTENT ROCK
FORMATIONS ALONG ENTIRE
ALIGNMENT
RUBBLIZED BEDROCK WAS
FOUND ALONG THE PROPOSED
ALIGNMENT THAT
COMPLICATED BLASTING
OPERATIONS
REMNANT GAPS WERE FOUND
WITHIN ROCK FORMATIONS
THAT LIMITED THE BLASTING
EFFICIENCY
GEOTECHNICAL CHALLENGES
PLAN VIEW - SOUTH
PLAN VIEW - NORTH
TYPICAL SECTION
FEBRUARY-APRIL 2013 – POOR
BLASTING METHODS AND
ENVIRONMENTAL OVERSIGHT
RESULTED IN THE UNAUTHORIZED
DISCHARGE OF 6,000 CY INTO
WATERS OF U.S. COVERING 0.55
ACRES
NOTE: CONSTRUCTION
ENGINEERING WAS PROVIDED BY
CONSULTANT
CONSTRUCTION CHALLENGES -
BLASTING
SEPTEMBER 2013 - DOT&PF
DESIGN BECAME AWARE OF THE
ISSUE UPON REVIEW OF
CONTRACTOR SUPPLIED CROSS
SECTIONS – APPROX. 5 MONTHS
AFTER VIOLATION OCCURRED
DOT&PF ENVIRONMENTAL STAFF
IMMEDIATELY REQUIRED
CONTRACTOR TO STOP WORK IN
THE AREA AND NOTIFIED ALL
AFFECTED AGENCIES OF
VIOLATION (USACE, ADF&G, NMFS,
USFWS, NPS, SHPO AND FHWA)
CONSTRUCTION CHALLENGES -
BLASTING
NOVEMBER 2013 - USACE ISSUED
NOTICE OF VIOLATION
REQUESTING ADDITIONAL
INFORMATION (TIMELINE OF
EVENTS)
NOTE: VIOLATION COULD INCLUDE
FINES OF UP TO $50,000 PER DAY
OR IMPRISONMENT FOR UP TO 3
YEARS FOR KNOWINGLY
VIOLATING THE CLEAN WATER ACT
CONSTRUCTION CHALLENGES -
BLASTING
MARCH 2014 - USACE ISSUED
COMPLIANCE ORDER REQUIRING:
COMPLETE REMOVAL OF ALL
MATERIAL OUTSIDE OF
PERMITTED AREAS WITHIN
APPROX. 4 WEEKS OF ORDER
NOTIFICATION
PERMITTEE RESPONSIBLE
MITIGATION PLAN BY MAY 2014
NOTE: INFORMAL DISCUSSIONS
TOOK PLACE WITH USFWS AND
USACE PRIOR TO ORDER TO
IDENTIFY LOCATIONS FOR
MITIGATION PROJECTS
CONSTRUCTION CHALLENGES -
BLASTING
MAY 2014 – DOT&PF SUBMITTED MITIGATION PLAN TO USACE FOR REVIEW AND ACCEPTANCE
NOTE: NON-PARTICIPATING FUNDS WERE REQUIRED TO DEVELOP MITIGATION PLAN, INCLUDING DESIGN AND ENVIRONMENTAL PERMITTING
PROPOSED MITIGATION PLAN INCLUDED THE REPLACEMENT OF (2) 54-INCH CULVERTS WITH A 117-INCH x 79-INCH STEEL PIPE ARCH TO IMPROVE FISH PASSAGE ON THE WEST CREEK TRIBUTARY (NEAR END OF DYEA ROAD)
TOTAL ESTIMATED COST FOR PRELIMINARY DESIGN AND CONSTRUCTION - $250,000
CONSTRUCTION CHALLENGES -
BLASTING
JANUARY 2015 – INSTALLATION OF STEEL PIPE ARCH WAS COMPLETED
FEBRUARY 5, 2015 – USACE ISSUED LETTER CONSIDERING VIOLATION RESOLVED
NOTE: IF USACE IMPLEMENTED FINES TO THE FULL EXTENT OF THE LAW THEY WOULD HAVE AMOUNTED TO APPROX. $10,000,000 (2.5 TIMES THE PHASE 4 FUNDING OF $4M)
CONSTRUCTION CHALLENGES -
BLASTING
PRE-BLAST CONSULTANT -
BLASTING METHODS IN
2013
BLASTING VIDEOS
POST-BLAST CONSULTANT -
BLASTING METHODS IN
2014
BLASTING VIDEOS
POST CONSTRUCTION PHOTOS
POST CONSTRUCTION PHOTOS
POST CONSTRUCTION PHOTOS
CONSIDER USE OF BLASTING CONSULTANT DURING DESIGN TO VERIFY CONSTRUCTABILITY AND POTENTIAL PERMIT CONCERNS.
CONSIDER THE REQUIREMENT THAT CONTRACTOR HIRE QUALIFIED BLASTING CONSULTANT TO PREPARE BLASTING PLANS TO ENSURE COMPLIANCE WITH ALL ENVIRONMENTAL COMMITMENTS AND PERMITS. THIS TECHNIQUE WAS USED FOR THE SITKA: SAWMILL CREEK PHASE III PROJECT.
CONSIDER USE OF BLASTING CONSULTANT DURING CONSTRUCTION TO REVIEW CONTRACTOR BLASTING PLAN SUBMITTALS.
PROVIDE A DOT&PF EMPLOYEE FOR ENVIRONMENTAL COMPLIANCE OVERSIGHT DURING CONSTRUCTION WHEN CONSULTANTS ARE PROVIDING THE CONSTRUCTION ENGINEERING.
IT IS IMPORTANT TO ESTABLISH AND MAINTAIN OPEN AND TRUSTWORTHY RELATIONSHIPS WITH ALL AGENCIES.
LESSONS LEARNED